Professional Documents
Culture Documents
EDP & LRP - Modeling
EDP & LRP - Modeling
Abstract
perform
assembly,
workover
functional test
operations
1 7 rig
retrieve coil
run
tubing and
EDP/LRP TF
wireline BOP
2 wireline
unhook coil coil tubing BOP
run risers tubing and
wireline BOP SFT WOCS
3 8
hook up SFT ROV assisted vessel or
LRP
draft
retrieve
open creation process. This document is published as intermediate or nearly mature version and connection
seal test
EDP/LRP
12
XT
well
head
run coil tubing
to get feedback. Further distribution is allowed as long as the document remains complete 7
and wireline
disassembly
well
a
Aker Solutions
f
FMC Technologies
On September 4, Captain Frode Johansen was discussing the plans for the
upcoming workover of South Gulfaks (see http://www.npd.no/en/Publications/
Facts/Facts-2011/Chapter-10/Gullfaks-Sor-/) with his crew. Their vessel had been
well 1 out of operation for recertification of the equipment much longer than anticipated,
so there was a lot of pressure from Statoil on their schedule. Statoil sees
harbor diminishing production in several of the wells, so workover operations are urgent.
With the upcoming fall and winter storms, Frode hopes to finish the next three
workover operations in a new record time. The equipment supplier had not only
recertified all equipment, but also renovated parts of the riser system allowing for
faster deployment and retrieval. The supplier tested and installed equipment in
Horten. Tomorrow they will arrive in Sotra, their company support station. Here
they will stock their fuel, food, coiled tubing, and other material.
The weather forecast shows a depression close to Iceland that moves slowly in
Norway’s direction. If they can start deployment of the riser on September 7, then
they probably finish the workover before the storm associated with the depression
is too severe.
Since the schedule is so tight, the captain proposes to preassemble the riser
system as far as possible while traveling. In addition, the accumulators can already
be charged. The captain asks the foreman to make a schedule and to allocate
tasks to the crew. Safety will be a key attention point, since working with such
equipment with sea state 3 provides risks.
riser
conduit for running
tools to well
well
perform
assembly,
workover
functional test
operations
1 7 rig
retrieve coil
run
tubing and
EDP/LRP TF
wireline BOP
2 wireline
unhook coil coil tubing BOP
run risers tubing and
wireline BOP SFT WOCS
3 8
hook up SFT ROV assisted vessel or
and TF disconnect platform
4
move away from
move above well
well
riser
5 9
ROV assisted retrieve SFT and
connect TF
10
hook up coil
tubing and retrieve risers EDP
wireline BOP
6 11 LRP
system function
retrieve
and connection XT
EDP/LRP
seal test well
12
head
run coil tubing
disassembly
and wireline
7 well
EDP EDP
LRP LRP EDP ROV EDP
LRP LRP
ROV
XT XT XT XT XT XT
well well well well well well
head head head head head head
7 rig
8 rig 9 rig
10 rig
TF 11 rig
TF 12 rig
TF
TF TF TF
SFT SFT EDP SFT
SFT WOCS SFT WOCS SFT WOCS WOCS WOCS LRP WOCS
vessel or vessel or vessel or vessel or vessel or vessel or
platform platform platform platform platform platform
EDP
LRP
riser riser
EDP EDP
EDP EDP LRP LRP
LRP LRP ROV
XT XT XT XT XT XT
well well well well well well
head head head head head head
assumptions:
running and retrieving risers: 50m/hr
running and retrieving coiled tubing/wireline: 100m/hr
depth: 300m
retrieve EDP/LRP
move above well
retrieve risers
run EDP/LRP
disassembly
run risers
24 48 72 96
hours
finishing 24 hrs
finishing 24 hrs
transportation
transportation
preparation
preparation
actual
reconnect
continued
workover
workover
24 hrs
32 hrs
24 hrs
32 hrs
storm
workover
operation
48 hrs
disruption
5 10
days
workover cost per day assumed cost (MNoK) workover duration estimated duration (hours)
platform, rig 2 transportation 24 production loss
equipment 0.2 preparation 36 6
crew 0.1 workover 48 48
total 2.3 MNoK/day finishing 27 8
total 135 (5.6 days) 62 (2.6 days)
deferred operation per day assumed cost (MNoK)
production delay 0.1
ongoing cost operation 0.2
total 0.3 MNoK/day
operations
continue workover
move above well
move away
workover
reconnect
control t&p well
open valves
7c
run wireline
24 48
hours
workover cost per day assumed cost (MNoK) workover duration estimated duration (hours)
platform, rig 2 production loss
workover 0-order 135 (5.6 days) 62 (2.6 days)
equipment 0.2
average disruption
crew 0.1 duration 72
total 2.3 MNoK/day overhead 11
disruption frequency 0.3
deferred operation per day assumed cost (MNoK) 1st order disruption 83*0.3=
production delay 0.1 correction 27 27
ongoing cost operation 0.2
total 162 (6.7 days) 89 (3.7 days)
total 0.3 MNoK/day
3 well well well well well well well well well well well well
resolution of
7
move above
disruption
disruption
ROV
move away
workover
remotely operated vehicle
wait for
workover
continue
reconnect EDP
reconnect
perform workover
well
operations
one for observation
emergency disconnect package one for operation
control t&p well ROV
7 provides disconnect function EDP
retrieve coil tubing lower riser package
and wireline BOP open valves LRP provides well control function
7c Xmas tree
run wireline provides well control XT
unhook coil tubing
and wireline BOP 24 48 well
hours structural and pressure-
8 head containing interface
ROV assisted
workover timeline
hook up coiled tubing/wireline
retrieve EDP/LRP
move above well
9
depth: 300m workover cost per day assumed cost (MNoK) workover duration estimated duration (hours)
retrieve risers
run EDP/LRP
disassembly
platform, rig 2 transportation 24 production loss
TF
run risers
contextual workover
A3AO operations
workover workover
workover A3AO topic
duration health safety
robustness of interest
and cost environment
navigation
A3AOs aspect ROV connect and barrier and
and
elaboration handling disconnect containment
positioning