PT SUPRACO INDONESIA
DOCUMENT TITLE:
RECORD OF REVISIONS
THE REVISIONS LISTED BELOW HAVE BEEN INCORPORATED IN THIS COPY OF THE DOCUMENT
RECORD OF REVISIONS
Contents
1 Introduction ..............................................................................................................................................6
1.1 Purpose ................................................................................................................................................6
1.2 Project Overview ..................................................................................................................................6
1.2.1 Project Description ...............................................................................................................................8
1.2.2 Project Components .............................................................................................................................8
1.3 Construction Method Statement .........................................................................................................10
1.3.1 Scope of Work....................................................................................................................................10
1.3.2 Materials and Tools ............................................................................................................................11
1.3.3 Sequence of Work..............................................................................................................................11
1.3.4 Inspection and Testing Requirements ................................................................................................12
1.4 Quality, Health, Safety and Environment Protection Policy ................................................................12
1.5 Roles and Responsibilities .................................................................................................................14
2 Environmental Legislation, Regulations and Guidelines.........................................................................16
2.1 Indonesian Environmental Regulations ..............................................................................................16
2.2 International Standards ......................................................................................................................17
2.3 Environmental and Social Safeguard Documents ..............................................................................17
3 Work Site Hazard and Risk Assesment ..................................................................................................17
4 Environmental Mitigation Measures .......................................................................................................19
5 Environmental Monitoring and Compliance............................................................................................40
5.1 Monitoring ..........................................................................................................................................40
5.2 Audit ...................................................................................................................................................41
5.3 Inspection ...........................................................................................................................................41
6 Incident and Non-Compliance Management ..........................................................................................41
7 Health and Safety and Emergency Response Procedures ....................................................................42
7.1 Emergency Response Plan ................................................................................................................42
7.2 Covid 19 Management Plan ...............................................................................................................44
7.3 COVID-19 Emergency Response ......................................................................................................45
8 Grievance Redress Mechanism .............................................................................................................46
8.1 Current Complaint Handling Process .................................................................................................47
8.2 Project GRM Flow ..............................................................................................................................48
8.3 Filing/Submission of Complaint ..........................................................................................................49
8.4 Record Keeping..................................................................................................................................49
9 Training ..................................................................................................................................................50
10 Reporting, Communication, and Record-Keeping ..................................................................................50
10.1 Reporting............................................................................................................................................50
10.2 HSE Communication ..........................................................................................................................51
10.3 Record keeping ..................................................................................................................................51
11 Key Performance Indicators ...................................................................................................................51
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 4 of 78
12 Management of Change.........................................................................................................................52
13 CEMP Implementation Budget ...............................................................................................................53
List of Table
List of Figure
Figure 1. Project Location of Patuha 2 and Dieng 2 .............................................................................. 7
Figure 2. Location of Civil Work Patuha 2 ............................................................................................. 8
Figure 3. Project Component Stage Patuha Unit 2 ............................................................................. 12
Figure 4. SPC QHSE Policy ................................................................................................................ 13
Figure 5. Organization Structure for Environmental Management of Civil Works ................................ 14
Figure 6. Emergency Response Communication Flow ....................................................................... 39
Figure 7. Flow Response Covid-19 Outbreak ..................................................................................... 42
Figure 8. Villages affected by mob demob activity .............................................................................. 43
Figure 9. Project GRM Flow ................................................................................................................ 45
Figure 10. Example of GRM Form ...................................................................................................... 46
List of Appendix
Appendix 1: Hazard Identification and Risk Assessment
Appendix 2: Journey Management Plan
Appendix 3: Noise and Vibration Management Sub-Plan
Appendix 4: Waste Management Sub-Plan
Appendix 5: Erosion, Sedimentation, and Water Resources Control Management Sub-Plan
Appendix 6: Land Clearing Management Sub-Plan
Appendix 7: Chance Find Procedure
Appendix 8: Ambient Air Quality Management Sub-Plan
Appendix 9: Biodiversity Action Plan
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 5 of 78
1 Introduction
This Construction Environmental Management Plan (CEMP) is prepared following contract award as
an obligations of contractor for environmental management at the location where they are working.
CEMP applies to all construction activities associated with the project. It provides a management
framework for the planning and implementation of construction activities following environmental
commitments. Significant impacts are identified and evaluated, so some problems of the environment
can be recognized and mitigated accordingly. PT Supraco Indonesia (“SPC”) commits to avoid any
adverse effects that may harm to the environment and community.
This CEMP provides guidance on the environmental and social management system approach to be
adopted by SPC and sub-contractors during the construction phase of the Project. It is supplemented
by various sub-plans and procedures which have been developed to address key environmental and
social aspects identified during the IEE process for which detailed control procedures and associated
responsibilities are defined for implementation by SPC and sub-contractors. These environmental and
social sub-plans have been prepared as separate stand alone documents.
The CEMP is a living document and will be updated as necessary based on the actual condition on
site and/or CEMP implementation evaluation results.
1.1 Purpose
The purpose of a construction environmental management plan is to outline how a construction project
will avoid, minimise or mitigate negative impacts on the environment, personnel working in the project,
and community living in the surrounding area.
SPC, as a civil works contractor, will contribute in implementing environmental friendly activity to avoid
adverse impact to the environment and community at pre-construction, construction, and post-
construction stages by implementing mitigation measures through design, equipment, suitable
engineering construction methods, effective stakeholder engagement (as and when needed),
compliance to EMP and environmental monitoring, and compliance to applicable both national
environmental, health, and safety regulations and international standards on geothermal power plant
construction.
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 7 of 78
This civil works activity will support the expansion of GDE target to produce 1x55 MW of electricity at
Patuha Unit 2 and produce 1 x 55 MW at Dieng Unit 2. All activities conducted by SPC will be to support
the drilling contractor in the drilling stage preparation.
During mobilization, the contractor will pass through a residential area in Panundaan and Alamendah
Village. While in Sugihmukti Village, the contractor will pass through some farming areas and forests.
The road is segmented into cemented and graveled roads.
B Equipment
1 Excavator 3 2 owned, 1 rental
2 Bulldozer 1 Rental
3 Dump truck 1 Owned
The role and responsibility of all personnel identified on the above chart are as below:
No Position Responsibility
Communicate CEMP goals to employees
Demonstrate visible safety leadership and behavior of CEMP goals
Resolve conflicting policies and promote ownership of CEMP
Provide required resources and training to implement CEMP
Support Supervisor on environment-related issues and initiatives
1 Project Manager
Ensure all subcontractor activity comply with rules and regulation
Provide overall support and necessary resources to maintain the high
integrity of CEMP and HSE aspects by providing competent personnel
and required equipment, material
Ensure CEMP and HSE resources for the project are adequate and
meet the requirement
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 15 of 78
No Position Responsibility
Provide necessary support to handle emergency
Liaise with GDE team in responding in the emergency
Review, endorse and implement CEMP and HSE Plan
Resolve conflicting policies with sub-contractor management
Coordinate with all onsite project PIC's in ensuring project scope (based
on contract) are performed in a safe manner
Ensure all equipment and material by vendors are requested and have
2 Site Manager passed QAQC before delivery onsite
Monitor and advice site operations and inspections as per plan
Support implementation of CEMP, ERP, and HSE Plan
Assist supervisor to perform notification during an emergency, also
organize additional support as necessary
Notify and coordinate with the project manager and Site client's PIC to
respond to an emergency
Communicate CEMP goals to all personnel
Ensure CEMP, HSE Plan are implemented and use effectively
Coordinate with client coordinator regarding CEMP Implementation
Ensure the correct use of safety forms and tools to implement the CEMP
3 Supervisor and HSE Plan
Implement the corrective actions identified during the project
Lead the evacuation when an emergency happens and activate ERT
onsite to respond to the emergency
Implement the available ERP
Ensure CEMP implemented, including filled form and documentation
Facilitate Project Risk Assessment and communicate the action item
Liaise with Client's Environmental PIC on required Environmental
Requirements based on approved CEMP
Assist Site Manager and Supervisor on CEMP related tasks during
project activity
4 HSE Officer Conduct monitoring Leading and Lagging indicators related to
Environmental and Safety Performance, such as Waste Management,
Waste manifest, Hazardous material handling, Work Permit, etc.
Provide any required assistance to the site ERT respond to the
emergency environment situation
Coordinate with Client's Environment PIC if any environmental issues, a
chance find, etc.
Public Relation / Act as a positive representation of SPC to all stakeholders
5 GRM Focal Develop, maintain, and intensify contacts with stakeholders;
Person? Monitor, coordinate, and communicate strategic objectives of SPC
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 16 of 78
No Position Responsibility
Collect, analyze, and utilize data and feedback to identify opportunities
to improve the relationship between SPC and stakeholder
Complete CEMP and HSE Induction upon the first arrival to the location
Take ownership in executing the CEMP and HSE program
Stop work immediately if safety and environment issue is detected,
discuss corrective action with supervisor, HSE
Actively participate in Permit to work, Observation and Intervention
6 All Personnel
program
Comply and obey with CEMP, HSE Plan
Wear appropriate PPE, and follow hazardous material handling
procedures or pollution mitigation
Ensure work areas are kept clean
SPC will make a HIRA that will be used for all projects involving SPC At least 2 days must be completed.
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 18 of 78
• HIRA-1 is completed before mobilization for the project. All mobilization personnel must attend the
HIRA meeting, which will be coordinated by the QSHE Coordinator.
• HIRA-2 must be completed on site, before starting work. HIRA-2 will involve review of HIRA-1, and
the addition of new or unexpected activities or hazards.
HIRA is installed in a prominent location in the workplace, to be seen by all employees. All employees
are required to read the HIRA, and understand the control steps needed for each activity. Hazard
identification assessment refers to the Risk Management Procedure and Danger List.
Possibilities/possibilities occur
1. Rare = practically impossible
2. It is impossible = can happen at a time
3. Maybe = can happen or "I've heard that happened."
4. Very likely = known to have happened or "has happened."
5. Almost certain = occurs in most recurring situations or events
The severity of the Risk Matrix can be seen in the Table below.
Processes will be maintained to evaluate (assess) risks and effects of identified hazards against
screening criteria, taking into account the probabilities of occurrence and severity of consequences for:
• People
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 19 of 78
• Environment
• Assets
• Community
It should be noted that any evaluation technique provides results that may be subject to a range of
uncertainties—consequently, formal risk evaluations of the methods of inexperienced judgment
personnel, regulators, and the community. Risk evaluation will:
• Include effects of activities, products, and services
• Address effects and risks arising from both human and hardware factors
• Solicit input from personnel directly involved with the risk area
• Be conducted by qualified and competent personnel
• Be conducted according to appropriate and documented methods
• Be updated at specific intervals
Evaluation of health safety and environment risks and effects will include, where appropriate,
considerations of:
• Personnel Injuries
• Occupational Hazard
• Erosion, Landslide, and Water contamination
• Fire
• Biodiversity loss
communities affected
- Emergency system
and equipment such
as fire-fighting,
ambulance, etc., will
be made available
during mobilization
along Kampung Alam
Endah and
Panundaan including
the provincial road in
Bandung that will be
used during
mobilization in case of
accident
- Contractor will be
required to prepare
traffic management
plan in consultation
with local authorities
in Panundaan, Sugih Kampung
Mukti, and Alam Alam
Endah and the Monitoring and
Disruption to During the Endah, SPV and HSE
provincial agency in Communication GDE
local traffic mobilization Sugih Mukti, SPC
Bandung with stakeholder
and
- Conduct public
Panundaan)
consultations on the
route that will be
taken for mobilization
- Conduct pre-
mobilization survey of
the route to be taken
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 22 of 78
to assess if adequate
space or corridor is
available, load
capacity of bridges,
the condition of public
roads including
buildings/houses
close to the roads
(~100 m) the
condition of public
roads and dwellings
along the routes as
baseline for road
rehabilitation or
damage claims
- A staff will be
designated to manage
traffic along the route
for mobilization
- Trucks that will deliver
dust generating
construction materials
will be covered with a Daily and at all
tarp or other suitable times during
material to minimize mobilization
Inspection gas
dispersion Gas emission SPV and HSE GDE
Ambient air emission
- Watering the road to test at least one SPC
quality certificate
minimize dust spread (1) time during
deterioration - Regular maintenance the project
and inspection of duration
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 23 of 78
equipment/ vehicle
(emission testing
certificate)
- Avoid engine idle for
more than 30 minutes
- Detailed mitigation
measures refers to
Journey Management
Plan or JMP
(Appendix 2) and
Ambient Air Quality
Management Sub-
Plan (Appendix 8)
- Inspection exhaust
vehicle and conduct
maintenance
necessary
incremental Vehicle Initial prior
Noise generation - Workers who will be inspection mobilization and SPV and HSESPC
Checklist and as per complaint
assigned to high GDE
GRM Report event
level noise-
generating works
e.g. 100 dB(A) will
be rotated every two
hours aside from
wearing of PPEs
- For any complaints
received related to noise
refer to Grievance
Redress Mechanism
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 24 of 78
- Detailed mitigation
measures refer to Noise
and Vibration
Management Sub-Plan
- (Appendix 3)
- Socialization to the
stakeholder (Desa Letter to relevant
Traffic incident Alamendah, Pokja, stake holders, Pre- mobilization
related to Ormas, etc.) before Complaint and as per event SPV and HSESPC GDE
adjacent received from the
Mob/Demob
community community
- Conduct road survey
- from driver prior
mobilization
- Detailed mitigation
measures refer to
JMP(Appendix 2)
- Provide proper PPE for
all workers
- Provide first aid kit, Inspection and
chemical, spill kit, fire Documentation,
Occupational extinguisher, flashlight, GRM received During the SPV and HSESPC GDE
health risk related to traffic mobilization
and tool kit (Refer to JMP
occupational
in Appendix 2) incident
- Refer to Grievance
- Redress Mechanism
(Section 8)
- Conduct trainings on
safety and health
hazards at least
monthly
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 25 of 78
- Provide sanitary
facilities and safe
drinking water at the
construction site
and at the workers’
camp
- Provide workers with
PPEs such as
googles, safety
shoes, etc. and its
use will be mandatory
- Conduct daily
toolbox meetings to
emphasize safety
and health
procedures
- Site Engineers to
encourage brief
exercise routine to
highlight the value
of health in the
workplace
- Employees of
contractor(s) will be
ensure and test
health driver before
driving
- Install clear and visible
warning signs as well
as sufficient lighting
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 26 of 78
- Install portable
secondary containment
- All fuel vehicle will carry
container bags,spill kit
Fuel spill and soil materials, and tools for Inspection and Petrol Vehicle Operator
Petrol refueling contamination theclean up and Daily Checklist Daily refueling andHSE SPC GDE
grounding system area
- Containers will be
enclosed and covered by
tarpaulin
Chemical spill kit will
ready within the working
location
Drilling with Auger
Cementing / Grouting
- MSDS of hazardous
Chemical spill substances will be made
and available at the working Inspection and
During the Cementing
Cementing wastewater location documentation, SPV SPC
discharge the activity area
- Chemical handling and JSA GDE
environment storage refers to MSDS.
MSDS of chemicals to be
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 30 of 78
In addition, management Sub-plans outline a monitoring, inspection, and audit programs for specific
potential hazards. These programs will involve PMU and PMC.
a. Noise and vibration Management Sub-Plan (Appendix 3)
b. Waste Management Sub-Plan (Appendix 4)
c. Erosion, Sedimentation, and Water Resources Control Management Sub-Plan (Appendix 5)
d. Land Clearing Management Sub-Plan (Appendix 6)
e. Ambient Air Quality Management Sub-Plan (Appendix 8)
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 41 of 78
5.2 Audit
SPC will agree on commitments and implementation with the HSE Management System will discuss
during project implementation to ensure that the process is carried out appropriately. HSE performance
indicators are defined, communicated and understood at all levels of the organization. Performance
indicators are assessed, evaluated and reviewed and the results communicated to the organization's
top management and all employees. Corrective and corrective action is an important component in the
improvement of the management system that is carried out and corrections found for irregularities are
made. HSE plans to schedule formal audits, routine monitoring and measurement, and structured
management completion to complete management system suitability, adequacy, and management.
Internal audit is invaluable in providing input into key areas for better management improvement. Audit
results and corrective action plans will be documented. SPC has established an Internal Audit
Procedure and Form which are presented in Appendix 10 and Appendix 11, respectively.
5.3 Inspection
HSE inspection is a formal verification to measure compliance with CEMP. Generally inspection will be
done using a checklist, carried out by the management team and the HSE when conducting field visits
or work facilities. The inspection will be carried out by the crew working in the field. All inspection reports
will be recorded. Inspection Work Instruction is included in Appendix 12.
Incidents include accidents, work diseases, near misses; the environmental impact should be reported,
evaluated, and action taken. Correction is the action to miss the direct cause of identification of the
nonconformity. In other words, corrections should be taken just to cut the direct cause, not the primary
root cause. Corrective action is action to miss the nonconformity which is identified or other situation
which is not expected. In other words, corrective action is the action to ignore the root cause which
causes the nonconformity. Preventive action is the action taken based on the result of the corrective
action to prevent the same dissent happen again.
All Incident, Near Miss, and Non-Conformity will be reported by SPC to GDE. Nearmiss and Incident in
the form of First-Aid Cases, Medical Treatment Cases, Restricted Work Cases and Lost- Time Incidents
will be carried out by SPC. Resource persons are required to provide correct information during
investigative activities. The results of the incident investigation will be informed to all personnel by SPC
through a safety stand down (SSD) mechanism, email notifications (broadcast email) notifications on
bulletin boards and monthly HSE communications.
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 42 of 78
Every incident that has been investigated will find the root cause of the incident using the SCAT method.
SPC has established an Accident/Incident Investigation Report Procedure as described in Appendix
13.
No matter how small, an accident / incident concerning a work or work relationship will be reported to
each supervisor/supervisor and PMU (refer to Figure 6 for communication flowchart). Each accident
must be reported 1x24 hours to the SHE Coordinator Site, Branch, and Center. (Person in charge:
Supervisor).
In addition, each potential hazard generates from project activity have a response which may refer to:
a. Noise and vibration Management Sub-Plan (Appendix 3)
b. Waste Management Sub-Plan (Appendix 4)
c. Erosion, Sedimentation, and Water Resources Control Management Sub-Plan (Appendix 5)
d. Land Clearing Management Sub-Plan (Appendix 6)
e. Ambient Air Quality Management Sub-Plan (Appendix 8)
SPC has developed an emergency response flowchart (as shown in Figure 6) emergency COVID-19
procedure and will be applied if there are workers who are suspected of having contracted COVID-19.
SPC will be responsible for further handling, bringing personnel to hospitals that have collaborated to
handle COVID-19, reporting to GDE and conduct investigations and carry out recommendations from
the results of these investigations. SPC will conduct exercises related to handling and COVID-19
prevention in the workplace.
Elimination
At the elimination level, measures are taken to eliminate the potential for transmission of COVID-19.
The potential for this transmission is through direct contact with a person exposed to COVID-19. Actions
that can be taken to eliminate this transmission are as follows:
• Do not travel to areas affected by COVID-19.
• Avoid activities that involve many people (social/physical distancing).
• Doing independent isolation or not leaving the house is not very necessary
Substitution
The action that can be taken at the substitution level is to change the method of work that is usually
done in places where there are many people in the following ways:
• Working in the office has been transferred to the concept of working from home or Work From
Home (WFH).
• SPC uses communication media for coordination and meetings by replacing face-to-face/face-to-
face methods with virtual methods such as Email, Telephone, SMS, Whatsapp, Zoom, M-Team,
and others.
• Replace the handshake with the name greetings without touch to avoid direct contact with other
people
Technical Control
• Spraying disinfectant fluid around the building/building work area and work tools regularly.
Schedule and monitoring in this program need to be done
• Provide a thermometer or thermal scanner used to check body temperature in offices or other
facilities.
• Provide washing facilities (washing sinks) and hand sanitizers in several places in the office and
work activity areas.
• Enforce temperature checks for every employee or guest who enters the work area.
• Every employee is required to maintain body condition, implement Clean and Healthy Behavior
(PHBS), not touch the face before washing hands with soap and running water
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 45 of 78
GDE has established a guidance on Covid-19 management at the workplace, therefore SPC will also
comply to GDE guidance. GDE Covid-19 Guidance is outlined in Appendix 15.
1st level Complainant Informs local village head (kepala desa) about the
concern
2nd level Village Head Sends a formal letter to GDE about the issue that was
generated on behalf of the complainant.
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 48 of 78
The goal of GRM is to resolve complaints due to projects in a time-bound and transparent manner.
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 49 of 78
9 Training
SPC will ensure that all personnel related to this job have competencies appropriate to their job. The
competence of personnel is proven by a competency certificate which is still valid during the
implementation of the work. Competent personnel must obtain approval from GDE can conduct tests
to ensure the competency of the proposed personnel if deemed necessary. If there is a change of
personnel during work, the new personnel must have the required competencies.
SPC will carry out training that has been planned and approved by PMU according to the competency
matrix and training schedule. Training and Competency Procedure is presented in Appendix 17.
Project Training matrix plan is summarized in Appendix 18.
SPC will record and document minutes of meeting to monitor action plan resulted from the meeting and
communicate them to all relevant personnel.
Compliance of CEMP KPIs is the responsibility of SM where the measurement and collection of data is
the responsibility of HSE. KPIs will also be used for tracking the progress and status on CEMP
implementation and include in the monthly progress report. Progress of CEMP programs
implementation will be reviewed for room of improvements and corrective actions.
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 52 of 78
Lagging Indicator
Description PREV. TODAY CUMM.
1 Fatality 0 0 0
2 LTI 0 0 0
3 MTI 0 0 0
4 First Aid 0 0 0
5 MVA 0 0 0
6 Property Damage 0 0 0
7 Oil / Chem Spill 0 0 0
8 Fire 0 0 0
9 Theft and Public Unrest 0 0 0
10 Near Miss 1 0 1
11 Biodiversity Damage 0 0 0
12 Dust, Noise and Emission 0 0 0
13 Unreported Chance Find 0 0 0
14 Erosion & Flood 0 0 0
15 Forest Fire 0 0 0
12 Management of Change
During project implementation, changes may be required to address foreseen or unforeseen conditions
or situations. CEMP incorporates a Management of Change (MOC) procedure to ensure that during the
construction phase, planned or unplanned project design and/or method changes that have the potential
to result in negative impacts to environment and social are managed or otherwise mitigated in
compliance with the Sub-plans. SPC Management of Change Procedure is presented in Appendix 19.
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 53 of 78
PT Supraco Responsible
Indonesia Scope Unit
of Work / Estimate Cost
Mitigation / Control Measure Implem Monit
Potential (IDR)
enting oring
Environmental
Unit Unit
Impact
Mobilization and Demobilization
- Trucks that will deliver dust
generating construction materials
will be covered with tarpaulin or
other suitable material to minimize
Noise and dust 60,000,000 SPC GDE
dispersion
- Socialization to stakeholder (Desa
Alamendah, Pokja, Ormas, etc.)
prior Mob/Demob
- Regular maintenance and
inspection of equipment / vehicle
Emission 120,000,000 SPC GDE
- Avoid engine idle for more than 30
minutes
- Socialization and coordination to
stakeholder (Desa Alamendah,
Public Unrest Pokja, Ormas, etc.) prior 20,000,000 SPC GDE
Mob/Demob
- Road survey from driver prior mob
Drilling with Auger
- Utilize drilled soil as back fill for fill
area
Drilled Soil 51,000,000 SPC GDE
- Make bundwall to the soil waste
area
Install Pipe Conductor
- Using respiratory mask for
36,000,000 SPC GDE
personnel involved
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 54 of 78
PT Supraco Responsible
Indonesia Scope Unit
of Work / Estimate Cost
Mitigation / Control Measure Implem Monit
Potential (IDR)
enting oring
Environmental
Unit Unit
Impact
Smoke generating
- Waste segregation of hazardous
from welding and
waste
welding rod waste
- Trucks that will deliver dust
generating construction materials
will be covered with tarpaulin or
other suitable material to minimize
Noise and dust dispersion 36,000,000 SPC GDE
- Regular monitoring and inspection
of sound level at nearest village
every 1 weeks (Alamendah, sugih
mukti, rancabali)
- Pre mobilization inspection of
SPC
equipment / vehicle by Client
Emission 120,000,000 and GDE
- Avoid engine idle for more than 30
GDE
minutes
Cementing / Grouting
- Install tarpaulin and bundwall as
groundmat
Chemical Spill,
- Install whipcheck on hose 28,800,000 SPC GDE
soil contamination
conncection
- MSDS socialization
Waste generating - Re-Use bucket
from cement
package or - Segregate waste of cement 9,600,000 SPC GDE
grouting additive package
bucket
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 55 of 78
PT Supraco Responsible
Indonesia Scope Unit
of Work / Estimate Cost
Mitigation / Control Measure Implem Monit
Potential (IDR)
enting oring
Environmental
Unit Unit
Impact
Access Road Work & Preparation Wellpad (Cut and Fill Activity)
- Trucks that will deliver dust
generating construction materials
will be covered with tarpaulin or
other suitable material to minimize
Noise and dust dispersion 60,000,000 SPC GDE
- Regular monitoring and inspection
of sound level at nearest village
every 1 weeks (Alamendah, sugih
mukti, rancabali)
- Pre mobilization inspection of
SPC
equipment / vehicle by Client
Emission 120,000,000 and GDE
- Avoid engine idle for more than 30
GDE
minutes
- Mapping area for land clearing
plan, Socialization to personnel
involve and monitoring
- Make bundwall on slope
- Make run off water parimeter
- Design change (resize ROW) to SPC
Erosion/Landslide
maximize slope percentage 1,501,000,000* and GDE
- In case limited space/area on GDE
boundary access road, PT Supraco
Indonesia propose to construct
additional retainning wall
- Request additional IPPKH land
area (If possible) (By GDE)
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 56 of 78
T Supraco Responsible
Indonesia Scope Unit
of Work / Estimate Cost
Mitigation / Control Measure Implem Monit
Potential (IDR)
enting oring
Environmental
Unit Unit
Impact
- Propose Silt Fence installation
(Polypropylene Geotextile, 30cm
above ground, 15cm inside ground,
steel wire strap) on run off track
downstream SPC
Water
- Propose to construct control Box 185,000,000* and GDE
contamination
for monitoring sedimentation GDE
(Permit to local government by
GDE)
- Install bundwall filter on run off track
downstream
- Sign installation (No burning of
solid or liquid wastes and other
combustible materials will be
allowed within the construction
sites and portacamp)
- Propose additional free space from SPC
Forest
boundary area to end of slope (kaki and GDE
Fire/Damage 368,000,000*
slope) normaly 20m space GDE
- Propose construct temporary
Fence Using zink & wood frame
along boundary IPPKH to protect
working area from unauthorized
people
- Sign Installation : SPC
Biodiversity
- Do not tresspass IPPKH area by 384,000,000* and GDE
damage
boundary barricade line and sign GDE
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 57 of 78
PT Supraco Responsible
Indonesia Scope Unit
of Work / Estimate Cost
Mitigation / Control Measure Implem Monit
Potential (IDR)
enting oring
Environmental
Unit Unit
Impact
- Coordination and communication
with personnel involve (Contractor,
LH, GDE)
- Hunting is prohibited
- Propose additional free space from
boundary area to end of slope (kaki
slope) normaly 20m space
- Propose construct temporary
Fence Using zink & wood frame
along boundary IPPKH to protect
working area from unauthorized
people
- Isolated bone exposed in an
excavation or spoil heap must be
retrieved before it is covered by
further spoil from the excavation
SPC
and set aside;
Chance Find 12,000,000* and GDE
- Notify client GDE
- Boundary/Marking area using
safety line
Note:
*: Subject to discuss with GDE
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 58 of 78
APPENDIX 1:
Hazard Identification and Risk Assessment
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 59 of 78
APPENDIX 2:
Journey Management Plan
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 60 of 78
APPENDIX 3:
Noise and Vibration Management Sub-Plan
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 61 of 78
APPENDIX 4:
Waste Management Sub-Plan
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 62 of 78
APPENDIX 5:
Erosion, Sedimentation, and Water Resources Control
Management Sub-Plan
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 63 of 78
APPENDIX 6:
Land Clearing Management Sub-Plan
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 64 of 78
APPENDIX 7:
Chance Find Procedure
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 65 of 78
APPENDIX 8:
Ambient Air Quality Management Sub-Plan
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 66 of 78
APPENDIX 9:
Biodiversity Action Plan
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 67 of 78
APPENDIX 10:
Internal Audit Procedure
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 68 of 78
APPENDIX 11:
Internal Audit Report Template
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 69 of 78
APPENDIX 12:
Inspection Work Instruction
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 70 of 78
APPENDIX 13:
Accident/Incident Investigation Report Procedure
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 71 of 78
APPENDIX 14:
Emergency Response Procedure
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 72 of 78
APPENDIX 15:
GDE Covid-19 Procedure
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 73 of 78
APPENDIX 16:
Penanganan Pengaduan dan Keluhan Tingkat Proyek
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 74 of 78
APPENDIX 17:
Training and Competency Procedure
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 75 of 78
APPENDIX 18:
Project Training Matrix
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 76 of 78
APPENDIX 19:
Management of Change Procedure
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 77 of 78
APPENDIX 20:
MSDS of Strong Grout
Contract No. CW-GDE-D2P2-002 COMPANY Doc No.
Construction Environmental Management Plan PTH2-HS-000-PLN-SPC-40004
(CEMP) Revision: C Status: IFA
Doc Type: PLN KKS Code: 000 Discipline: HS Revision Date: 03-OCT-21
Contractor Doc No. 04/HSE/PTH2-SPC/VIII/2021 Page: 78 of 78
APPENDIX 21:
MSDS of Tiga Roda Cement