Performance Report:

sr No Date Seed Oil in Oil in Machine Motor


Crushed Seed % cake % Run load
hours amps
1 6-08-2022 3 22-24 8 2 230 to
250
2 11- 15 22-24 8.2 3 230 to
082022 250
3 12- 19 22-24 8.2 4 230 to
082022 250
4 13- 21 22-24 8.2 4 230 to
082022 250
Observations at Faiyum site:
The following observations are listed below at the Faiyum site,

• Expeller-250 and Cooker installation completed as per drawing.


• Piping is being done.
• Power is not available yet and it is expected to be available in 2-3
months.

Recommendations:
KMIPL recommends to UOC & RI the followings,
• Genuine spare parts to be maintained for the proper running of machine
at desired output and parameter.
• Proper maintenance to be done to avoid the undue breakdown of the
machine.
• Vibro-separator and pumps along with Piping is required to install
additionally.

• KMIPL recommend to install oil and foots conveyor with screen to reduce
the foots manual handling.
KMIPL representative is highly satisfied with the hospitality and cooperation
extended during his stay at site and thankful for the United oil and crops for making
the project successful and wishes them success ror their future ventures.

Mr. Muhammad hemmer Mr. Sanjay Kumar

Mr EZZAT
Mr. Ramadan
Mr. Sobhi
MOM between United Oil Crops and Related Industries, Ramadan, Egypt
and Handover Letter
Date: 16/08/2022
Place: 10Tb Ramadan, Egypt.

Members Present:
United Oil Corps & RI, Ramadan, Egypt KMIPL, Mumbai
Mr. Muhammad Hammer (Manager- Production) Mr. SanjayKumar(Site
Engineer)
Mr EZZAT — (Engineer operation & Electrical)
Mr. RAMADAN (Engineer operation and maintenance)
Mr. Sobhi (site manager)
Observation at Zagazig Location:
KMIPL Representative Mr. Sanjay Kumar visited the site from 30.08.2022 to
1708-2022, and after the initial feedback from United oils and crops, KMIPL
engineer taken the round of the plant and observed the followings,

• Machine Ex-250 with Cooker installation completed as per drawing and found
satisfactory.
• No load trial of main Ex-250 Motor taken and found load 95-100 amps. No
load trial of Main expeller-250 taken and load found to 100 to 110 Amps.
• Dry run test for expeller -250 and cooker carried out and found satisfactory.
• Expller-250 trial taken on dehulled cotton seed from dated 6 Aug to 13th Aug
2022 and total 56 tons of seed crushed and analysis for the same given as
below., During the trail it was found that expeller-250 is running on rated
capacity.
• As the cake was buming, 2 reverse worms, from feed and discharge chamber
removed and collar fitted. Spacers in the feed chamber of one compartment
replaced with 2 mm between alternate cage bars.
• Machine could not run for longer hours due to nonavailability Of seeds
Related equipment installation found to be satisfactory.

• Training to the Production engineers and production technician given


to operate and maintain the machine along with the required
parameters to be maintain to get the desired results and output.
KMIPL representative is highly satisfied with the hospitality and cooperation
extended during his stay at site and thankful for the United oil and crops for making
the project successful and wishes them success ror their future ventures.

Mr. Muhammad hemmer Mr. Sanjay Kumar

Mr EZZAT
Mr. Ramadan
Mr. Sobhi
Performance Report:
sr No Date Seed Oil in Oil in Machine Motor
Crushed Seed % cake % Run load
hours amps
1 6-08-2022 3 22-24 8 2 230 to
250
2 11- 15 22-24 8.2 3 230 to
082022 250
3 12- 19 22-24 8.2 4 230 to
082022 250
4 13- 21 22-24 8.2 4 230 to
082022 250
Observations at Faiyum site:
The following observations are listed below at the Faiyum site,

• Expeller-250 and Cooker installation completed as per drawing.


• Piping is being done.
• Power is not available yet and it is expected to be available in 2-3
months.

Recommendations:
KMIPL recommends to UOC & RI the followings,
• Genuine spare parts to be maintained for the proper running of machine
at desired output and parameter.
• Proper maintenance to be done to avoid the undue breakdown of the
machine.
• Vibro-separator and pumps along with Piping is required to install
additionally.

• KMIPL recommend to install oil and foots conveyor with screen to


reduce the foots manual handling.
MOM between United Oil Crops and Related Industries, Ramadan, Egypt
and Handover Letter
Date: 16/08/2022
Place: 10Tb Ramadan, Egypt.

Members Present:
United Oil Corps & RI, Ramadan, Egypt KMIPL, Mumbai
Mr. Muhammad Hammer (Manager- Production) Mr. SanjayKumar(Site
Engineer)
Mr EZZAT — (Engineer operation & Electrical)
Mr. RAMADAN (Engineer operation and maintenance)
Mr. Sobhi (site manager)
Observation at Zagazig Location:
KMIPL Representative Mr. Sanjay Kumar visited the site from 30.08.2022 to
1708-2022, and after the initial feedback from United oils and crops, KMIPL
engineer taken the round of the plant and observed the followings,

• Machine Ex-250 with Cooker installation completed as per drawing and


found satisfactory.
• No load trial of main Ex-250 Motor taken and found load 95-100 amps.
No load trial of Main expeller-250 taken and load found to 100 to 110
Amps.
• Dry run test for expeller -250 and cooker carried out and found
satisfactory.
• Expller-250 trial taken on dehulled cotton seed from dated 6 Aug to 13th
Aug 2022 and total 56 tons of seed crushed and analysis for the same given
as below., During the trail it was found that expeller-250 is running on
rated capacity.
• As the cake was buming, 2 reverse worms, from feed and discharge
chamber removed and collar fitted. Spacers in the feed chamber of one
compartment replaced with 2 mm between alternate cage bars.
• Machine could not run for longer hours due to nonavailability Of seeds
Related equipment installation found to be satisfactory.

• Training to the Production engineers and production technician given


to operate and maintain the machine along with the required
parameters to be maintain to get the desired results and output.