Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

DELAY CLAIMS IN U.K.

CONTRACTS

By Stephen Scote

ABSTRACT: Contract conditions in both the United Kingdom and the United States are sufficiently similar to
allow common generic delay claim scenarios to be recognized, but there are important differences in the extent
of legal precedent for assessing such claims. In the United States recognized procedures have been developed
to allow critical path method (CPM) to be adopted in this area, while in the United Kingdom the situation is
much less clear. It is true that U.K. professionals will generally recognize that CPM will be useful in dealing
with delay claims, but there is little evidence that a standard approach has been accepted. A survey was conducted
by the writer to discover how U.K. claims for delay were being prepared (by the contractors) and how they
were being assessed (by the supervisors). Because of the complexity of this area, the study was approached in
a number of ways. This paper presents conclusions concerning attitudes towards such claims and information
about the mechanisms that are being adopted to prepare and evaluate them.

INTRODUCTION occur and consideration must also be given to delays for which
the employer/owner is not responsible. The aim of the survey
Claims are an inevitable feature of major projects that will presently described was to attempt to understand how U.K.
have to be dealt with on the majority of contracts let. The professionals actually deal with such situations.
project designer's accepted inability to fully provide for all
eventualities means that changes will be made to the contract
BACKGROUND
as it proceeds, and, where these involve additional work, ad-
justed payments will be necessary. Disagreements on the level Delays to parts of the contractor's program, which may not
of these payments will be a typical source of claims. Along necessarily cause delays in the project as a whole, are-mosC
with changes to the payments made, these variations may also helpfully categorized as follows:
result in delays to the works. Where these delays have a
knock-on effect on the project as a whole, they may give rise 1. Those for which the employer/owner or supervisor is re-
to extra costs. These result from the contractor's prolonged sponsible (E);
presence on site, generating additional overhead costs for the 2. Those for which the contractor is responsible (C); and
extended period. There are, of course, factors other than varied 3. Those for which neither party to the contract is respon-
work that may delay the project, an4 it is also generally rec- sible (N)
ognized that delays may be attributed to the employer/owner,
to the contractor, or to neither party. American texts usually refer to these delays as: (1) compen-
The contract will normally have a predetermined time in sable; (2) nonexcusable; and (3) excusable, and some of the
which it must be substantially completed and available for use. main reasons for delay encountered under these subdivisions
In the absence of delays, failure to substantially complete are, respect!vely:
within this time frame will often mean that liquidated damages
will be deducted from the contractor. These will be at the level 1. Changes to the contract documents, failure to provide
defined in the contract and will be payable for the period by land or information within a reasonable time, and failure
which the whole project is delayed. Such damages should aim to approve the contractor's method of working expedi-
to compensate the employer/owner for any lost profits or lost tiously;
benefits stemming from the inability to make use of the project 2. Inadequate supervision and technical support, late agree-
at the agreed date. Clearly, where delays have occurred during ments with subcontractors/suppliers, and insufficient la-
the project, which can be attributed to the employer/owner and bour/plant; and
have delayed the contractor, these should be taken into account 3. Strikes, riots, and exceptional adverse weather.
before the damages are deducted. The opportunities available
in many contract conditions to recognize a contractor's right
There appears to be a general consensus as to the rights to
to have the time for completion of the contract extended reflect
additional time and payment for such delays (where war-
this acceptance of the more likely state of affairs.
ranted) in all contract forms encountered by the writer. The
By no means will all changes to a contract delay the project.
rights are as follows:
Some will involve changes in detail that merely affect the na-
ture of the work to be done without increasing its difficulty,
requirement for resources, or duration. Other changes will ac- • For a delay of type E: extension of time and extended
tually reduce the work to be carried out. There will, however, overhead costs
typically be changes that do delay, increase the duration of, or • For a delay of type C: no compensation
force a change in sequence in the activities making up the • For a delay of type N: extension of time without extended
contractor's program. The impact of such amendments on total overhead costs
project time cannot be easily predicted at the time the events
Of course, type Edelays may als?.lead. to other costs re-
'Lect., Dept. of Civ. Engrg.. Univ. of Newcastle upon Tyne, NE1 7RU, sulting from disruption and Ineffi'Ciency ana'type'c'a:erays-may
England. " "involve deductiimOfliqUidateaoaillages from the contractor.
Note. Discussion open until February 1, 1998. To extend the closing It should also be noted that in the United States, contracts with
date one month, a written request must be filed with the ASCE Manager a "no damage for delay" clause effectively convert the cate-
of Journals. The manuscript for this paper was submitted for review and gory E delay to the same as the category N delay.
possible publication on September 27, 1996. This paper is part of the
]our1Ul1 of Constructiion Engineering and Ma1Ulgement. Vol. 123, No. A realistic delay claim Scenario on a complex project may
3, September, 1997. ©ASCE, ISSN 0733-9364/97/0003-0238-0244/ well contain a number of delays of each of these three main
$4.00 + $.50 per page. Paper No. 12997. types, affecting different activities in the program at different
238/ JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT / SEPTEMBER 1997
times. It is also quite likely that a request for an extension of number 'of nonresponses, those who did take part did so en-
the contract time for completion may be made part way thusiastically. The interviews typically took 2 hours each to
through the contract. Where the contractor has already been complete and were conducted in the offices and site huts of
denied an extension of this type, he or she may accelerate the respondents.
certain activities in order to complete the project on time. The The findings from these interviews clearly relate most di-
supervisor must consider the contractor's claim in all its com- rectly to the U.K. construction industry but, because of the
plexity, and, depending on the type of claim, make a decision similarities in this area found between contract conditions used
as to whether an extension of the contract time should be given there and in other countries, it is believed that they will have
or whether the contractor should have to accelerate and should a wider relevance.
be recompensed for any additional costs. These are particularl~
difficult situations tocom1?rehend and to assess. MAIN FINDINGS
.'f.: 'revIewofthe'iherature-' oTthfs'areaShows that, in the
United States, an understanding has developed of a generalized General Principles
approach to dealing with such problems, as reported by Wick-
wire and Smith (1974) and Wickwire et al. (1989), but there As a first and rather crude attempt to determine attitudes,
appears to be no comparable approach detailed in U.K. texts. ~ four statements were presented to the interviewees. They were
asked to say whether they agreed or disagreed with the state-
This American approach involves the preparation of full "as-
built" records of exactly when. the various activities in the
project took place and when delays were effective. From this.
I ments, and were invited to comment as they wished. The state-
ments were selected, in part, to check whether certain princi-
information, a judgement is made on the right to extensions I ples discussed in the literature were generally accepted by the
profession, and also to test out attitudes on matters that have
of time with costs by pulling out the delays for which the I
employer was responsible and assessing how long the con- i not been so widely considered. The aim here, as in other parts
tractor would have taken to complete the job in the absence I of this section, was not only to record and analyze decisions,
of these delays. It is generally recognized that this may not be ! but also to try to ascertain how such decisions were made. The
a simple process, and that it is not likely to ever be mecha- ! results and comments made on each statement will now be
nized, as it requires judgement and common sense. ,j considered in tum. To assist this process, the statements and
One of the main sets of contract conditions used in the i results have been tabulated in Table 1.
United Kingdom for civil engineering construction, which The first 9.!!estion suggests that a claim for extended over-
adopts a traditional arrangement of the parties and a bill of head costs shouict-not succeeduni'essthe-iTi.ile-forcom.pletion'
quantities, is the Institution of Civil Engineers "Conditions of Jilnc~!y t9~~=e~~~e4icf-dp-posriiji'vIewpointsliavebeenfound
Contract," 6th edition (ICE 1991). In this document, the prin- il}. th~,Y :~: Jit.e!..!l:t~~{l.~i!h.!~g~~LtQ .!h.Ls.,.s.!.~:!:t~IJ:l~!}!.. Support
cipal clause relating to extensions of time says that the super- for the view is recorded by Powell-Smith and Stephenson
visor must consider whether, " ... the delay suffered fairly en- (1989) although it is rejected by Abrahamson (1979). The in-
titles the Contractor to an extension of time for the substantial tervi~'Y~.~~~2.~~.~.P~!~t~_<?!~ ..~E1.~~~~~£!2.~?,_~ere _~uivo­
completion of the WorkS~~~-:'-'-Exactly'how thIs"Isto bedone;' C:o~Jj~UE~iE .. ~i~_a.~t::~.I}1~n! with this statement. Only two 'COlU:-
however, is left to the'supervisor to decide, and although texts ments were made: (1)8. supervisor stated ihat a contractor may
relating to the U.K. experience suggest that the application of be due an extension of time even if he or she can still finish
the critical path method will make for a more just solution, on time; and (2) a contractor stated that the time for comple-
they only given very simplistic examples. tion affects only liquidated damages. Whatever the views of
The U.K. supervisor thus has little supporting material to writers and commentators on this issue, the industry appears
provide guidance in deliberating on these problems and no to be quite clear as to its opinion.
substantive legal precedent. In the absence of such precedent
or recognized procedures, it is suggested that the views of TABI,.E 1. Assessment of Claims: General Principles
other professionals working in this field may be the most use- Decision Supervisor Contractor
ful guide that can be provided. If general areas of common (1) (2) (3)
agreement between the two main parties on site can be rec-
(a) There is no point in making a claim for extended overhead costs
ognized and accepted, this may help to simplify the delibera- unless the time for completion is likely to be exceeded.
tions on some of these complicated claims situations that have
been found to 'occur so frequently.

MAIN SURVEY
E" I 1! I ,!
(b) If the contract program shows completion in 18 months, and the
The survey was carried out on organizations operating as contractor actually completes in 18 months, no extended overhead
supervisors and contractors on major construction projects in _ _ _ _ _ _ _--=costs can ever be justified.

g_~_sa_:~_e_e
the United Kingdom. Because of the complexity of the area o
being studied it was not considered feasible to use a mail-shot 11
approach. Instead, interviews were held based on question- ___ 1 : I o
naires. The questionnaires were piloted by carrying out inter- (c) If the supervisor awards an extension of time without costs for a
views prior to the main survey, and were edited to take account delay attributed to exceptional adverse weather, this prevents the
contractor from justifying an extension of time with recovery
of the findings from these interviews. Two questionnaires were
used: one for the supervisors and one for the contractors.
The response rate for the main survey was 45%, and it gen-
~ of Old ro," f~ m, .. m'rriOd !
erated a total of 22 interviews. Of these, 11 were conducted
with organizations fulfilling the supervisor's role and 11 with
contractors. Some of the companies did not respond at all, (d) Providing the supervisor never actually instructs the contractor to
accelerate, no acceleration claim can be justified.
even after a reminder was sent out, and one firm replied that
it would not become involved as it was, " ... policy not to
discuss commercial matters outside our own organization."
Despite this viewpoint, which may have been the basis for a
g[;" I ! I !
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT / SEPTEMBER 1997/239
In the second statement, if a contractor's program shows Specific Cases
completion in 18 months and the contract is actually com-
As an alternative means of shedding light on the way in
pleted in that time, the statement says that n~ .extend~d ove~­ which professionals in the industry consider delay claims, it
head costs can ever be justified. The SupposItion behmd thIS
was decided to try to describe fully some particular outcomes
statement is that having anticipated paying overheads for the
to contracts and to ask the respondents to recommend solu-
18-month period, even if the contractor could have completed
tions. This was the approach adopted in both questions in this
it in 16 months and was delayed 2 months by the employer,
section, although different methods were used. In the first
no loss was actually suffered. Overheads havf; only been paid
question, the whole scenario was described in words, while'
for the time they were expected to be paid. All the contractor
for the second question four diagrams were drawn to chronicle
responses disagreed with this view. This might have been ex-
the outcomes to four contracts.
pected, but the majority of supervisor responses were against
The interviewee in the first question was asked to make a
it too. Some of the comments made show that some respon-
decision on extension of time matters part way through a con-
dents would have been considering, not extended overhead
tract On the basis of the following statement:
costs but additional overhead costs for the 18-month period
occa1ioned by any additional work instructed by the supervi-
"Six months into the contract, it is clear that the employer
sor. There still, however, seems to be a general distrust of the has delayed a part of the works in such a way that the whole
logic supporting this statement. It should of course be recog- of the contract will be delayed by two months. The time
nized that the first and second statements are very similar and for completion is 24 months and the contractor's original
relate generally to the "right to finish early" issue. program showed completion in 20 months. What should the
The suggestion contamed m the thIrd statement resulted contractor doT'
from a discussion with a supervisor during a visit to one of
the sites on which the preparatory work for the questionnaires Seventy-eight percent of the supervisors said that the con-
was being conducted. He related that in the past he had been tractor should request an extension of time; the rest that a
involved in a contract on which the supervisor had taken the claim for a delay with costs should be made. Of the contractor
initiative to award an extension of time without costs as a responses, 60% said that the contractor should claim for an
result of exceptionally adverse weather. This had been done extension of time; 40% that a claim should be made for delay,
specifically to prevent the contractor from claiming an exten- not for an extension of time.
sion oftime with costs for some cause that was the employer's It is clear from the figures that at the point of consideration,
JesQonsibility. Irrespective ofthe rights or wrongs ~f suc? .ac:' no extension of time will be needed. Yet, if the contractor was
tion, this situation raises the general issue of alternatIve cntIcal to allow the program to slip, or further delays occurred, the
paths and parallel delays, and for this reason was felt to be situation would change. An extension of time might then be
worthy of inclusion. Among the supervisors, 60% disagreed necessary to defray the deduction of liquidated damages. This
and made comments suggesting that this would be somehow fact was clearly understood by the respondents.
underhand; and 40% agreed, some of these believing that the In assessing the effects of a delay partway through a con-
contractor would find another way to recover these costs. The tract, the supervisor must attempt to predict how the contract
contractors were much more strongly opposed to this state- will proceed in the future. For some delays, where the whole
ment, with 82% disagreeing and only 18% agreeing. The com- site was brought to a standstill as a result of the employer's
ments made, however, did not particularly attempt to disprove actions, the effect on the completion of the whole project is
the statement, but were general accounts of their views on undeniable. However, if the delay was not so wide-ranging
dealing with weather in claims situations. Although the ques- and yet at the time it appeared that it would necessarily delay
tion is a rather complex one, it was surprising that none of the the whole project, a later assessment might prove that another
comments anticipated the possibility that a further extension path through the network had become critical. This second
of time beyond the first might be awarded, this time with costs. path might then control the completion of the project and
Also, the chance that another parallel path through the net- might only contain within it delays for which the contractor
work, much delayed by the employer, might supersede the was responsible. In such a situation, awarding an extension of
impact of the path on which the weather delay occurred was time, rather than simply recognizing a delay for which the
not considered. It is possible that delays to the contract are not employer is responsible and that could lead to an extension of
seen or perhaps not considered in this way? time, might lose the employer the right to deduct liquidated
The final question concerns acceleration claims and states damages. Recognition of a fundamental delay to the project
that, providing the supervisor never actually instructs the con- rather than awarding an extension of time, however, was not
tractor to accelerate, no acceleration claim can be justified. The favoured by most supervisors. It appears that such delays tend
responses from both contractors and supervisors were identi- to be closely linked to ideas of extensions of time.
cal, with 64% of responses disagreeing with the statement and In the second question, the intention was to illustrate a few
27% agreeing. The comments showed a recognition by the simple yet interesting scenarios that might have to be dealt
majority of the possibility of what is sometimes known as with in claims situations. Time-scaled CPM diagrams were
"constructive acceleration." That is, if the supervisor fails to used for this purpose and although the simplest cases were
award a properly deserved extension of time during the period chosen, it was still found necessary to clarify a number of
of the works, the contractor speeds up to complete within the points. For this reason, a checklist was developed to help ex-
original time for completion and the supervisor later decides plain the diagrams before they were shown to the interviewee.
that the extension should actually be awarded. In such a case, The points on the checklist were as follows:
the contractor has no need for the late extension but may have
suffered additional costs as a result of having to complete work 1. For each case, two diagrams are shown: one showing the
at a faster rate than was reasonable., Such costs should be re- contractor's original program (planned); one showing the
coverable by the contractor for having to accelerate, even actual "as-built" record of work (Actual).
Jh9JJ~nQ.Ji~ifu:_ order ...to acc~lerat~ ..~_~s_given. This is a 2. The diagrams use a time-scaled, activity-on-arrow format
generally recognized scenario and perhaps the reason for a in which a number of symbols are used. A rectangle with
number or the respondents not identifying it results from the rounded ends or a circle represents an event. A thick
fact that so few acceleration claims are made. arrow indicates a critical activity, a thin arrow an activity,
240/ JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT / SEPTEMBER 1997
and a dotted line float. A rectangle with a C over it means I, Time for completion .1
a delay that is the contractor's responsibility, an E one Weeks
that is the employer's responsibility, and an N one that
is the responsibility of neither party.
o 1 2 3 4 5 6
3. It is assumed throughout that the existence of one delay
has not affected the duration or timing of subsequent
delays. For instance, if the construction site is not avail- a
able at the start of the works, any contractor delay might
be a result of holding back preparations. Such effects are
assumed not to have occurred.
4. It is to be assumed that no acceleration has taken place.
5. In each case, the interviewee's views are sought on the
contractor's rights to an extension of time, the recovery (a)
of overhead costs, and the employer's right to deduct
liquidated damages. Time for completion
Weeks
The actual diagrams used during the interviews were A3 size 3 456
and these are reproduced at a much smaller scale together with
the accompanying description and a summary of the results
obtained as Figs. 1-4.
In Fig. 1, the time for completion is four weeks, the con- a
tractor's program shows the job finishing in four weeks, and

I, Time for completion


Weeks
o 1 2 3 4 5 6 (b)
I
Number of
Supervisors Contractors
weeks
a liqUidated 0 10 10
damages 1 1 1
2 0 0

Extension of 0 0 0
time 1 4 2
2 7 9
(a)
Recovery of 0 0 0
overheads 1 8 5
\. Time for completion 2 3 6
Weeks
o 1 2 3 4 5 6 (c)
FIG. 2. Scenario 2 in Which Whole Project Consists of One
Activity-a; Work Cannot Start until End of Second Week When
Site Becomes Available-Contractor is Not Ready to Start until
a E a End of First Week, and Project Is Completed Two Weeks Late: (a)
Planned; (b) Actual

it does actually finish in four weeks. This is true, even though


the employer has delayed the contract for a week. There is
(b) clearly no need for any liquidated damages to be deducted and
all respondents agreed on this. Although no extension of time -1
Number of is required to defray deduction of damages, almost a half of
Supervisors Contractors
weeks the s~rvisors and 36% of the'contractors felt that one should
Liquidated 0 11 11 ~~~.i'Y.~(f~d.Conceriilng··wfi"etfier·overlieadcosts should be
damages 1 0 0 paid to the contractor, there was a majority of both supervisors
2 0 0
and contractors who favored paying overhead costs for one
Extension of 0 6 7 week.
time 1 5. 4
)
,1._ This case has parallels with both the second statement in
~--.-_.

2 0 0 the General Principles section and with the first question in


Recovery of 0 3 2
this section. In the second statement, even though the con-
overheads 1 8 9 tractor had allowed for the amount of overheads eventually_
2 0
. 0 paid, the consensus seemed to be that overheads should be
!~irnb~u~s~4fo~...ally'i~JE~jE~_~.~Rl..~~iJiad-Clefa.~dtlie·whore_
(c) contract. This result is repeated here. In the first question in
FIG. 1. Scenario 1 in Which Whole Project Consists of One this sectIon, most 'respondents felt that an extension of time
ActiVity-a; at End of Two Weeks, Work Is Suspended for One should be awarded rather than simply a recognition of a delay
Week (E-Type Delay), but Contractor Still Completes on Time: for which the employer was responsible. In somewhat similar
(a) Planned; (b) Actual circumstances, but in an instance where there is obviously no
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT / SEPTEMBER 1997/241
Time for completion _I Time for completion
Weeks Weeks
o 1 234 5 6 o 1 2
a
3 4 5 6
a

b b

(a) (a)
Time for completion Time for completion -I
Weeks Weeks
o 2 3 4 5 6 o 234
a
5 6
I I a 1 I

C b N b
~ .............. ~ ..............
rI ~
(b) (b)
Number of Number of
SupelVisors Contractors Su pervlsors Contractors
weeks weeks
.liquidated 0 11 11 Liquidated 0 0 1
damages 1 0 0 damages 1 8 8
2 0 0 2 3 2

Extension of 0 0 0 Extension of 0 2 3
time 1 1 1 time 1 9 8
2 10 10 2 0 0

Recovery of 0 0 0 Recbveryof 0 9 11
overheads 1 3 1 overheads 1 2 0
2 8 10 2 0 0

(c) (c)
FIG. 3. Scenario 3 in Which Whole Project Consists of Two FIG. 4. Scenario 4 in Which Whole Project Consists of Two
Activities-a and b, Which Can Proceed Simultaneously; De- Activities-a and b; Delays due to Contractor and to Neither
lays due to Employer and Contractor Result in Project Being Party Result in Project Being Completed Two Weeks Late: (a)
Completed Two Weeks Late: (a) Planned; (b) Actual Planned; (b) Actual

need for an extension of time, a number of interviewees still The delays are, in fact, on parallel paths. The response was
wanted one to be awarded. There appears to be a linkage in unanimous that no liquidated damages should be deducted,
many of the respondent's minds between such delays and ex- and nearly so on the belief that a two-weeks extension of time
tensions of time. This ignores any possibility that overheads should be awarded. It was less conclusive concerning the
might be recovered.without such an extension. amount of overheads that should be recovered, but most su-
The remaining diagrams show a variety of ways in which pervisors and contractors still thought that these should be paid
overlapping delays might affect a project's outcome. The first for two weeks. This is a marked difference in view to the view
of these, Fig. 2, contains two delays type E and C both af- with regard to recovery of overheads in scenario 2, which may
fecting a single activity a. Almost all of those interviewed be seen as a very similar situation to this one.
replied that no liquidated damages should be deducted, with a If an adjusted schedule was to be constructed for this situ-
majority of both supervisors and contractors recommending a ation, in line with the Wickwire and Smith (1974) approach,
two-week extension of time. The position on the recovery of and the Wickwire et al. (1989) approach, removing the em-
overheads, however, was not so clear cut. Most supervisors ployer-responsible delays would show that the contractor
felt that overhead costs should be paid for one week only, would not have been able to complete the project on time. The
while 55% of contractors felt that two weeks overhead costs contract would be one week beyond the time for completion
should be payable. The supervisor's view in this case is iden- and thus the contractor should, on this basis, have one week
tical to the solution that would pertain to adopting legal rem- of liquidated damages deducted. The other week should be
edies for concurrent delays in the United States, as reported covered by an extension of time for which overhead costs
by Kraiem and Diekmann (1987). That is, that a two-week should be paid. Both supervisors and contractors disagreed
extension of time should be awarded, but with overhead costs strongly with this view and seemed to simply identify the crit-
payable for only one of those weeks. ical path and make their decisions based on the delays on that
Fig. 3 is similar to Fig. 2, involving two delays of type E path alone.
and C, although this time they are affecting different activities. The last diagram, Fig. 4, also has parallel delays but this
242/ JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT / SEPTEMBER 1997
time they are of types C and N. Again a majority view can be see if path on which delay occurred is actually critical; (3)
defined for both supervisors and contractors alike. That is that CPM program appear when such claims are being made; (4)
there should be an extension of time for one week, liquidated program should be used as a basis, but then monitor actual
damages deducted for one week and no recovery of overheads activities and only agree payment if real delay occurs; (5) crit-
at all. An alternative view would be that it was the contractor's icality is judged from understanding the sequence of activities;
own actions that delayed the contract by two weeks, causing and (6) contractor typically identifies critical path-you check
it to finish two weeks late, and the contractor should be totally it.
responsible for this delay. By this argument, two weeks liq- The importance of critical paths and the shunting effect of
uidated damages should be deducted. The respondents were, particular delays on activities on such a path were also rec-
however, more generous than this. They clearly felt that the ognized by the contractors who answered this question. There
contractor should benefit from the fact that an "act of God" was, however, another important element reported by 36% of
type of delay would have prevented the contract being com- the contractors that was not mentioned by any of the super-
pleted on time, had he or she not been responsible for a delay. visors. This was the concept of "plugging" delays into the
Depending on how the concurrent delays were dealt with, the contract program to see their effect on completiontime. Some
U.S. response on such an outcome would be either that rec- said that they would use a software package for this. This is
ommended by the majority of respondents here, or the alter- particularly interesting as it begins to appear that the produc-
native view expressed. It should, of course, be noted that the tion of an "as-built" program is being described. However,
delay type N is not on a critical path and in some circum- on further examination, this was seen not to be the case. The
stances may not be considered a concurrent delay. contractors who used this approach admitted that they would
use the activity durations from the original program for this
Claims Procedure purpose, and made no attempt to record actual durations of
the activities. In fact, it was mentioned by one contractor that
Under this heading are collected the responses to questions he would extend actual delay durations used in this exercise
that aimed to identify particular procedures adopted by both to those that would have occurred had he not increased re-
contractors and supervisors in preparing and assessing delay sources to improve the situation. The contractors explained
claims. For this, three basic questions were adopted. The first that their aim in using this approach was to demonstrate their
of these was addressed to the supervisors only, the second to "entitlement" to the employer. Having plugged in the delays
both contractors and supervisors, and the third solely to con- to the initial contract program in this way, they would expect
tractors. The first question goes straight to the point: to show a completion time beyond what they actually needed.
The fact that they had managed to complete before this time,
"What procedure do you adopt for assessing the validity they would argue, was because they had been particularly ex-
of a claim for an extension of time on a complex project?" peditious in carrying out the contract. This would then be fol-
lowed with an expectation that the employer would pay them
The responses received were varied, ranging from: "Ana- their costs, possibly with an element of profit.
lyze evidence, compare with our records, and make a decision In some circumstances, a large number of site instructions
based on those facts," to "Require demonstration that delay might cause considerable disruption to a contractor's perfor-
has occurred, secondly that delay was critical to completion mance. This might happen in such a way that it would be
date; gets very complicated-anything but straightforward." difficult to isolate and deal with each delay individually. A
There was a general recognition of a need to check facts as question was posed to contractors that described this scenario
proposed by the contractor with the supervisor's records, but as follows:
other suggested actions were: (1) justify that the delays could
not have been expected; (2) look at the claim as though you "How do you formulate claims when the disruption to pro-
were making it; (3) try to establish another one or two ways gress is due to the effects of a large number of site instruc-
of evaluating the cost of the claim to get a feel for where the tions and it is not possible to separate individual causes of
settlement figure should lie-then negotiate with the contrac- delay?"
tor; (4) look at how the individual claim is presented (as it is
difficult to specify a general procedure); (5) use program, as- Forty percent of the responses said that this .would be dealt
sess links between activities, and take account of float; and (6) with as a combination of individual causes of delay, effectively
try to accept contractor's approach-if not, use own methods. saying that they would be able to isolate individual delay ef-
In this belief that this first question might not elicit re- fects. The others recommended amassing information on the
sponses that directly addressed the actual mechanism used to value of the instructions together with information on total
affirm or assess the impact of individual delays, a second more costs. By showing the monies spent compared with the antic-
specific question was included: ipated spending profile, these contractors aimed to show that
the increased expenditure was due to the disruptive effect of
"How do you show that/decide whether a delay to a par- the instructions.
ticular activity has actually contributed towards delaying
the whole project.1" CONCLUSIONS
The material will be considered under two main themes: (1)
The responses of the supervisors will 'be dealt with first, the attitudes to particular claims situations; and (2) the mech-
followed by those of the contractors. Sixty-four percent of the anisms that are adopted in preparing and assessing those
supervisors interviewed mentioned the critical path or critical claims. In terms of the first theme, the principal conclusions
activities in their replies, some of them recognizing that it may that can be drawn from the study are as follows:
not always be easy to identify this path. Two respondents used
the word "shunting," referring to subsequent activities in the 1. There appears to be good agreement between both su-
project being moved along by the effect of the delay in ques- pervisors and contractors that a claim for extended over-
tion. There was certainly a general belief that where this shunt- head costs should be able to succeed despite the fact that
ing occurred on the critical path, an extension of time might the time for completion has not been exceeded. In this
well be justified. Other comments made were: (1) need to situation, however, a number of those interviewed would
check for float on path affected; (2) possibility of stalling to award an extension of time.
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT / SEPTEMBER 1997/243
2. A strong link seems to exist in the minds of many who the entitlement method, the interviewees tended to deal with
deal with delay claims between awarding an extension these problems on the basis of the critical path alone. Other
of time and accepting a claim for extended overhead paths through the network were not likely to be considered.
costs. As has already been reported, the legal basis for dealing
3. In the claims situations involving· concurrent delays, the with delay claims in the United Kingdom and the United
approach adopted by the supervisors was generally very States is quite different. It is clear, however, that in the United
fair to the contractor. No attempt seemed to have been Kingdom most claims will be dealt with at site level. This
made by either party to remove delays for which the study was intentionally aimed at those professionals who made
contractor was not responsible and then identify how the claims and those who assess them on site. In making in-
well the contractor could have proceeded in the absence formation available about how some of these matters are being
of those delays. handled by others, it is hoped that some benefit can be derived.
When little legal precedent exists, the procedures adopted by
In terms of the second theme, the basic approach adopted other professionals may be a valuable guide.
by most supervisors in assessing the claims was as follows: APPENDIX. REFERENCES
Abrahamson, M.W. (1979). "Engineering law and the I.C.E." Contracts,
1. Check the facts of the contractor's submission. 4th Ed., Applied Science Publishers Ltd., London, England.
2. Identify or verify the critical path. Institution of Civil Engineers (ICE). (1991). Conditions of contract. 6th
3. Check whether the delays on that path have had a shunt- Ed., Thomas Telford, London, England.
ing effect on the activities. Kraiem, Z. M., and Diekmann, J. E. (1987). "Concurrent delays in con-
4. If some of the delays on the critical path would cause struction projects." J. Constr. Engrg. and Mgmt., ASCE, 113(4),
591-602.
an extension of time, then an extension of time may well Powell-Smith, V., and Stephenson, D. (1989). Civil engineering claims.
be justified. BSP Professional Books, London, England.
Wickwire, J. M., and Smith, R. F. (1974). "The use of critical path
Similar views were expressed by contractors concerning the method techniques in contract claims." Public Contract Law J., 7(1),
1-45.
ways in which they would try to prove their rights to an ex- Wickwire, J. M., Hurlbut, S. B., and Lerman, L. J. (1989). "The use of
tension of time. A few of them sought to demonstrate entitle- critical path method techniques in contract claims: issues and devel-
ment, as previously described. It seems clear that, apart from opments 1974 to 1988." Public Contract Law J., 18(2), 338-391.

244 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT / SEPTEMBER 1997

You might also like