Motor Grader.................................................................................................................. 9
Asphalt Plant.................................................................................................................. 9
Asphalt Paver............................................................................................................... 10
Excavator...................................................................................................................... 11
Wheel Loader...............................................................................................................11
Truck Crane..................................................................................................................11
Forklift........................................................................................................................... 12
2
PROBLEM-SOLVING:...................................................................................................12
Except for those items that are specified to stay in situ or that are to be removed in
accordance with other provisions of this Specification, this item should consist of clearing,
grubbing, removing, and disposing of all vegetation and debris as specified in the Contract. All
identified remaining artifacts must be protected from harm and vandalism as part of the work.
Except for obstructions that are required to be removed and disposed of under
other items in the contract, this item entails the removal, in whole or in part, and proper disposal
of all buildings, fences, structures, old pavements, abandoned pipelines, and any other
obstructions that are not designated or permitted to remain. The salvage of specific items and
This Item consists of excavation for borrows and roadway drainage, as well as the
disposal of waste in accordance with this Specification and the lines, grades, and dimensions
The required excavation for the foundation of bridges, culverts, underdrains, and other
structures not otherwise provided for in the Specifications shall be included in this item. The
backfilling of finished structures and the disposal of all dug surplus materials must be done in
accordance with these Specifications and relatively close conformity with the Plans, unless
as well as the lines, grades, and dimensions specified by the Engineer or depicted on the Plans.
This item will involve preparing the subgrade to support the upper structural
layers. The entire width of the road must be covered by it. Subgrade preparation must wait until
the Contractor is able to begin construction of the pavement structure before being done without
This process will be used to establish the necessary densities for particular
embankments, subgrades, bases, and bituminous concrete as specified. Control strip construction
will be used to set goal densities for the designated course, and equipment using the sand-cone
method of density measurement will be used to determine in-place densities attained during
construction.
Any transporting that is approved and exceeds the free-haul distance is considered
an overhaul. The designated free-haul distance is the distance over which excavated material
must be transported without receiving any further payment. The free-haul distance shall be 600
course on a prepared subgrade in accordance with this Specification and the lines, grades, and
This Item entails providing, installing, and compacting an aggregate base course
on a prepared subgrade/subbase in accordance with this Specification, and the lines, grades,
thickness, and typical cross-sections shown on the Plans or s determined by the Engineer.
This Item entails providing, positioning, and compacting crushed gravel, crushed stone,
or crushed rock in one or more layers on a prepared subgrade or subbase in accordance with this
Specification and the lines, grades, thickness, and typical cross-sections shown on the Plans or as
accordance with this Specification and in conformity with the lines, grades, and typical cross-
sections shown on the Plans. The wearing or top course must be made of gravel or crushed
aggregate and binder material, depending on what is specified in the Bill of Quantities.
This Item shall consist of pavement of Portland Cement Concrete, with or without
reinforcement, constructed on the prepared base in accordance with this Specification and in
conformity with lines, grades, thickness and typical cross-section shown on the Plans.
8
The construction of roads is a highly technical operation that needs both thorough
In accordance to Thuita (2022), here are the seven (7) kinds of road construction
equipments:
Motor Grader
equipment used to make flat surfaces so that asphalt may be spread out over them.
Asphalt Plant
A important equipment component for making asphalt concrete and other types of
coated roadstone for use in road construction projects is the asphalt plant.
9
Asphalt Paver
lot, bridge, or other similar structures and to do some light compaction before a roller takes over
components of equipment used in road construction. As a result, road rollers are a typical sight at
construction sites for new roads. The main purpose of a roller, which is essentially a compactor-
type engineering vehicle, is to push down earth, gravel, concrete, or asphalt during the building
Excavator
to remove rocks and dirt from the ground and put them onto dump trucks.
Wheel Loader
A wheel loader, often referred to as a front loader, skip loader, or bucket loader, is
a type of tractor used to lift a pile of materials from the ground and load them onto a truck or into
a pit.
Truck Crane
Truck cranes are essential tools in the construction of roads. Typically, these
cranes are mounted on the back of a truck to help with lifting needs at a road construction site.
11
Forklift
A forklift, often called a fork truck, is a type of industrial vehicle that has a connected
platform that can be lowered to pick up objects on the ground or below it and raised to transfer
them. Originally employed to transport goods in industries, forklifts have had their design altered
throughout time to expand their applications as vital tools for road construction.
PROBLEM-SOLVING:
Compute the volume (m³) needed for Subbase, Base, and Surface Course.
12
REFERENCES
DPWH Standard Specifications for Public Works and Highways, 2012 Edition Volume II,
Thuita, P. (2022, June 1). The 7 Most Powerful Road Construction Equipment. Retrieved from
https://www.constructionkenya.com/2408/road-construction-equipment/