Professional Documents
Culture Documents
Main Group 3 Equipment For Cargo
Main Group 3 Equipment For Cargo
33 DECK CRANES............................................................................................................... 5
331 Cargo crane:.................................................................................................................... 5
30 HATCHES
All exits shall be fitted with opening mechanisms that are easily handled from the inside and
outside. Exit hatches shall have contra-weight for easy opening.
304 Manholes
Manholes shall be arranged in all tanks, cofferdams, chain lockers etc.
Two (2) manholes shall be installed in each of the cargo and fuel oil tanks at opposite ends
of each tank.
Stainless steel bolts shall be installed in all manholes.
Coaming around flush manholes shall be installed on tank top and decks.
Flush manholes shall be arranged with screwed (removable) handles for easy removal of
the covers.
Screw stud shall be used only for flush manholes.
Twelve (12) off (six(6) each side) portable vertical steel tubular piperail stanchions, each
with a 10 tonnes eyeplate on top and twistlock fitting at the bottom shall be supplied for
fitting into suitable sockets on the 1st deck from the aft ship to frame 55.
Arrangements shall be made for satisfactory stowage of the portable piperail stanchions by
agreement with the Buyer.
The loading and discharge stations for bulk cargo shall be arranged as
follows:
- Loading amidships with one (1) port and one (1) starboard filling
line to each tank.
- Discharge SB and PS from forward two (2) tanks, and SB and PS
from aft tanks.
- The bulk system shall be installed in such manner that the Vessel
is capable of loading and discharging the two (2) segregated systems
simultaneously.
Bends for discharge pipes shall have a bending radius of min. 650 mm.
Bends for filling and ventilation pipes shall have a bending radius of approx. 600 mm.
All welding in pipes shall be flush inside pipes.
Minimum 1500 mm straight pipe between bends on discharge lines.
The discharge pipes shall not run through tanks. Pipes in each discharge, not longer than 4
meters, which shall be connected, with "Straub" type coupling.
Remote control
'The plant, valves and compressors shall be controlled from the common automatic
equipment system Spec 792, the ECR console page 3.6 last para, and by means of local
controls'.
Mucking ejector
Mucking ejector for tank cleaning shall be installed.
Two (2) air receivers, each 2 cum.
Tank air vent system shall be provided with two (2) completely independent dust cyclone
and collection systems. Each system shall be locally and remotely operated, drawing dust
from the air pipes and discharging back into the supply line and a connection on open deck.
33 DECK CRANES
Main data:
Lifting capacity: 5,0 tonnes (SWL) fix hook at max 15 m
Working radius, max: 15 metres (5,0 tonnes) including jib of 4 metres
Working radius, min: 3 metres (5 tonnes)
Safety working load : SWL 2.0 tonnes at 40 m/min, boom mounted winch
Hoisting speed, single line: 0-40 m/min stepless variable
Slewing time: 460 0 sec
Slew sector: 360 degrees unlimited
Main data :
Lifting capacity: 1.0 ton (SWL) at max 12 m, fix hook
Working radius: 12 metres
Slewing time: 30 sec
Slew sector: 270 degrees
350 General
In addition to meeting Regulatory Body requirements, the Builder shall work closely with the
Buyer and equipment manufacturers to provide functional, maintainable, and easily
accessible systems.
The fuel oil and the fresh water systems shall be arranged for complete inter transferring of
each system in addition to connection to filling/discharge stations at deck.
The piping systems shall be based on max. 3,0 m/sec flow.
All cargo systems loading and discharge arrangements shall be completely remote
controlled in addition to local manual control.
If valves are designed to remain “as is” during black-outs, UPS back-up is not required.
All valves shall be arranged for local control and remote control by pneumatically operated
double acting actuators, each actuator shall be fitted with a coalescer filter and isolating
valve.
Separate ring mains shall be installed forward and aft with port and starboard isolating
valves.
Connections shall be approx. 1.3 m above main deck facing downwards, approx. 45o.
All 40 mm drain cocks to deck, fitted adjacent to each deck discharge connection shall be
provided with a tail pipe, pipes to terminate 500 mm above deck level.
Hose connection stations shall be fitted with deep savealls at deck level, each saveall shall
be fitted with two (2) drains, one (1) to overboard the other to the slops tanks each drain to
be fitted an isolating valve.
All cargo pumps and compressors shall have remote operated 220V electric 0 to 100 %
throttle discharge valves with local and remote controls. Additional throttle discharge valves
shall be provided for each dry bulk dust collector.
A separate panel above the MCR console VDU workstations shall be fitted with
independent manual remote operated controls for each cargo pump and compressor motor:
- start, stop, running indicator, load indication and throttle discharge valve control.
Hose connection cargo isolating valves on weather deck shall be manual control only. All
valves on weather deck shall be ball type with single lever 90 deg. operation.
Bulk compressors and liquid cargo pumps with segregated systems shall have system
inter-connections for standby purposes by manually operated valves.
All cargo systems shall have pump bypass to tanks for loading via deck connections.
Maximum velocity of liquids in cargo pipes shall be 3.2 metres per sec.
Emergency stop of the cargo pumps and emergency closing system for valves on cement
tanks shall be arranged in aft bridge console.
Filling/discharge pipes shall have 4" couplings, type WECO.
Fuel Avery Hardoll.
Spare couplings
Spare reducing connection male / female shall be Builder’s supply as follows:
Pumping system shall be capable of totally segregation and concurrently handling two (2)
products during loading, carriage, re-circulation and discharge to deck connections and
slope tanks.
In order to make the two (2) forward liquid mud tanks dual purpose, separate Ring and
Blind flanges with connections P&S shall be provided from the Brine System.
Provision shall be made for continuous circulation in liquid mud tanks using the discharge
pumps at low speed through suitable pipework and nozzles.
Separate high and low suctions valves shall be fitted on each tank with independent blow
clearing connections into low suction sump.
Liquid mud pump shall be arranged as back-up for the brine pump.
The combined mud and brine tanks shall have two (2) separate filling and two (2) separate
discharge lines, one (1) for brine and one (1) for liquid mud.
Arrangement for emptying the liquid mud pump and piping by use of compressed air and
seawater to storage tank onshore shall be installed and to slope tank onboard.
Two (2) of the liquid mud tanks shall be combined with brine. Separate piping system for
brine. Blind flanges on both piping systems on the liquid mud tanks.
40 mm test cocks on 1st deck and adjacent on each pump discharge line.
A 300 mm high saveall shall be arranged on deck below each bunker station to collect
leakage which may occur with drain to slop tank and overboard, each with a shut-of valve.
Brine tanks shall be fitted with high level alarm independent of the remote sounding system
initialised at 90 % level.
Brine pump shall be arranged as back-up for the liquid mud pump.
The combined mud and brine tanks shall have two (2) separate filling and two (2) separate
discharge lines, one(1) for brine and one (1) for liquid mud. WB, DW.
A 300 mm high save all shall be arranged on deck below each bunker station to collect
leakage which may occur with drain to slop tank and overboard, each with a shut-of valve.
The fresh water cargo pumps shall be installed with suction from all fresh water tanks and
with discharge connection to deck and 100 % transfer possibilities between all tanks.
Filing through deck line.
Flowmeter shall be installed to allow for reading both during filling and discharge operation.
A 300 mm high save all shall be arranged on deck below each bunker station to collect
leakage which may occur with drain to slop tank and overboard, each with a shut-of valve.
MATERIALS
Item DESCRIPTION QTY CAPACITY HEAD TYPE PUMP CASING LINER SPINDLES PRIME MOVER
(M3/H) M.L.C.
FRESH WATER 1 1x150 90 CENTRIFUGAL CAST IRON BRONZE STAINLESS ELECTRIC MOTOR
PUMP PUMP COATED STEEL Two speed
VERTICAL
BALLAST-/ 1 1X150 90 CENTRIFUGAL CAST STEEL BRONZE STAINLESS ELECTRIC MOTOR
DRILLWATER AND PUMP OR BRONZE STEEL Two speed
FIREWASH PUMP VERTICAL W/DIMET
1) COATING
FUEL OIL / ORO 2 2x250 at 90 TWO (2) SPINDLE NODULAR BRONZE STAINLESS ELECTRIC MOTOR
PUMPS 2) 1500 cst NPSH SCREW PUMPS CAST IRON STEEL Two speed
min. 5 mwc VERTICAL EX PROOF
1) The fresh water pump and the ballast pump shall be assigned as stand-by pumps for the other system.
2) Remote controlled throttle valves shall be electrical controlled on pressure side on each pump and on dry bulk pure air. (Four (4) purge lines).
A stripping / washing pump, capacity 10 cum/h - 12 bar shall be connected to the suction
lines.
The pump shall be arranged to deliver to any liquid mud tank and to slop tank.