PROJECT: DP/BLD/012 - REMOTE LOUNGES IN CONCOURSES A, B & C Rev: 01

SAS Engineer Comments on MS No.: AFO-CFC316-MS-0223 - R01


(Code-2)
Subcontracted: M/s. Honeywell Intl Middle East Ltd – Storage Unit
Sl. No. HONEYWELL
ENGINEER RESPONSE HONEYWELL RESPONSE
CUSTOMERS’S COMMENTS RESPONSE REMARKS
CODE 2 REV1 Code 2 Rev1
Code 2 Rev0

Why the document referring to the DP-


MISC-020 project at Al-Maktoum It’s already revised in
1 Comply Reply isn't clear to be accepted
airport in the section#1 of the section 1 code 2 Rev 0.
document
Many items /materials are missing
form Manufacturer lectures section,
contractor shall provide complete data
sheet for all items under the project Comply
All the material items data
scope including EMC2 Equipment Not complete, contractor to add
2 sheet already added in
archive node and accessories, all used all products
section 14 of Code 2 Rev0.
mounting Kits and supports, Node
Filler, Licenses, and contractor shall
update the Equipment Schedules
Section accordingly.
Operation Sections shall include EMC2
storage node/unit’s operation /user
It’s provided in section 7
3 guide (In addition to the Submitted Comply Comment is still valid
of code2 Rev0.
parts)

Maintenance Instruction System shall


It’s provided in section 8
include EMC2 storage node /units’
4 Comment is still valid of code 2 Rev0.
maintenance instructions guide (In Comply
addition to the Submitted parts)
In the name and index drawing section, It’s provided in section 12
5 drawing references to be provided Comply Not Done of code 2 Rev0.

Missing the Draft warrant section,


T&C Report section and
Equipment schedules section and All the sections are
6
all other sections.......etc as per provided in code 1
section no. 1 (index), contractor
shall provide/update accordingly