Project Name
Project Package Data Date 7-May-22
Material Submittal Date Material Approval Date PO Issued Manufacture Started Shipment Date Clearance Delivery to Site / Store
Material Submittal Date Material Approval Date PO Issued Manufacture Started Shipment Date Clearance Delivery to Site / Store
M-051 M-051-MS Nourishment equipment 16-Nov-22 6-Dec-22 13-Dec-22 60 20-Dec-22 18-Feb-23 20-Mar-23 22-Mar-23
DIVISION 12 : FURNISHINGS
M-052 M-052-MS VANITY TOP 8-Mar-23 28-Mar-23 4-Apr-23 60 11-Apr-23 10-Jun-23 10-Jul-23 12-Jul-23
DIVISION 13 : SPECIAL CONSTRUCTION WORKS
M-053 M-053-MS Fountain water wall 3-Aug-22 23-Aug-22 30-Aug-22 60 6-Sep-22 5-Nov-22 5-Dec-22 7-Dec-22
DIVISION 14 : CONVEYING SYSTEMS
M-054 M-054-MS Elevator 14-Jun-23 4-Jul-23 11-Jul-23 60 18-Jul-23 16-Sep-23 16-Oct-23 18-Oct-23
M-055 M-055-MS workstation 8-Oct-22 28-Oct-22 4-Nov-22 60 11-Nov-22 10-Jan-23 9-Feb-23 11-Feb-23
DIVISION 21 : FIRE SUPPRESSION
M-056 M-056-MS PIPES 7-Mar-22 27-Mar-22 3-Apr-22 60 10-Apr-22 9-Jun-22 9-Jul-22 11-Jul-22
M-064 M-064-MS NOVEC 1230 SYSTEM 17-Aug-22 6-Sep-22 13-Sep-22 60 20-Sep-22 19-Nov-22 19-Dec-22 21-Dec-22
M-057 M-057-MS VALVES & ACCESSORIES 5-Nov-22 25-Nov-22 2-Dec-22 60 9-Dec-22 7-Feb-23 9-Mar-23 11-Mar-23
FIRE DEPARTMENT INLET
M-059 M-059-MS 19-Nov-22 9-Dec-22 16-Dec-22 60 23-Dec-22 21-Feb-23 23-Mar-23 25-Mar-23
CONNECTION
M-060 M-060-MS FIRE HOSE CABINET 3-Dec-22 23-Dec-22 30-Dec-22 60 6-Jan-23 7-Mar-23 6-Apr-23 8-Apr-23
M-058 M-058-MS SPRINKLERS 17-Dec-22 6-Jan-23 13-Jan-23 60 20-Jan-23 21-Mar-23 20-Apr-23 22-Apr-23
M-061 M-061-MS FIRE EXTINGUISHER CABINET 31-Dec-22 20-Jan-23 27-Jan-23 60 3-Feb-23 4-Apr-23 4-May-23 6-May-23
M-062 M-062-MS FIRE PUMPS SET 14-Jan-23 3-Feb-23 10-Feb-23 60 17-Feb-23 18-Apr-23 18-May-23 20-May-23
M-063 M-063-MS JOCKEY PUMP 28-Jan-23 17-Feb-23 24-Feb-23 60 3-Mar-23 2-May-23 1-Jun-23 3-Jun-23
DIVISION 22 : PLUMBING WORKS
Domestic cold Water & Hot water
M-086 M-086-MS 10-Feb-22 2-Mar-22 9-Mar-22 60 16-Mar-22 15-May-22 14-Jun-22 16-Jun-22
Supply Pipe:
M-094 M-094-MS Clean Out ( CO ) 15-Jan-22 4-Feb-22 11-Feb-22 60 18-Feb-22 19-Apr-22 19-May-22 21-May-22
SANITARY DRAINAGE, STORM
M-087 M-087-MS 28-Mar-22 17-Apr-22 24-Apr-22 60 1-May-22 30-Jun-22 30-Jul-22 1-Aug-22
WATER & VENT PIPING
MEDICAL AIR COMPRESSORS
M-113 M-113-MS 26-Sep-22 16-Oct-22 23-Oct-22 60 30-Oct-22 29-Dec-22 28-Jan-23 30-Jan-23
SYSTEM
M-088 M-088-MS Floor Drain ( FD ) 13-Mar-22 2-Apr-22 9-Apr-22 60 16-Apr-22 15-Jun-22 15-Jul-22 17-Jul-22
MAIN WATER TREATMENT PLANT
M-097 M-097-MS 5-Oct-22 25-Oct-22 1-Nov-22 60 8-Nov-22 7-Jan-23 6-Feb-23 8-Feb-23
(RO)
M-093 M-093-MS Roof Drain ( RD ) 13-Apr-23 3-May-23 10-May-23 60 17-May-23 16-Jul-23 15-Aug-23 17-Aug-23
M-095 M-095-MS Trench Drain ( TD ) 21-Jul-22 10-Aug-22 17-Aug-22 60 24-Aug-22 23-Oct-22 22-Nov-22 24-Nov-22
M-099 M-099-MS FILTER PUMP 14-May-22 3-Jun-22 10-Jun-22 60 17-Jun-22 16-Aug-22 15-Sep-22 17-Sep-22
M-114 M-114-MS MEDICAL VACUUM PUMP SKID 4-Oct-22 24-Oct-22 31-Oct-22 60 7-Nov-22 6-Jan-23 5-Feb-23 7-Feb-23
M-085 M-085-MS Sanitary Fixtures 21-May-22 10-Jun-22 17-Jun-22 60 24-Jun-22 23-Aug-22 22-Sep-22 24-Sep-22
M-089 M-089-MS Area Drain ( AD ) 4-Jun-22 24-Jun-22 1-Jul-22 60 8-Jul-22 6-Sep-22 6-Oct-22 8-Oct-22
M-090 M-090-MS Floor Clean Out ( GCO ) 18-Jun-22 8-Jul-22 15-Jul-22 60 22-Jul-22 20-Sep-22 20-Oct-22 22-Oct-22
M-091 M-091-MS Floor Clean Out ( FCO ) 2-Jul-22 22-Jul-22 29-Jul-22 60 5-Aug-22 4-Oct-22 3-Nov-22 5-Nov-22
Material Submittal Date Material Approval Date PO Issued Manufacture Started Shipment Date Clearance Delivery to Site / Store
M-092 M-092-MS Parking Drain ( PD ) 16-Jul-22 5-Aug-22 12-Aug-22 60 19-Aug-22 18-Oct-22 17-Nov-22 19-Nov-22
M-096 M-096-MS HOSE BIBB 30-Jul-22 19-Aug-22 26-Aug-22 60 2-Sep-22 1-Nov-22 1-Dec-22 3-Dec-22
M-098 M-098-MS LAB WATER TREATMENT PLANT (RO) 5-Oct-22 25-Oct-22 1-Nov-22 60 8-Nov-22 7-Jan-23 6-Feb-23 8-Feb-23
M-120 M-120-MS Axial Inline Exhaust Fans Two Speed 12-Jun-23 2-Jul-23 9-Jul-23 60 16-Jul-23 14-Sep-23 14-Oct-23 16-Oct-23
M-158 M-158-MS CHILLED WATER PIPING CLADDING 23-Apr-22 13-May-22 20-May-22 60 27-May-22 26-Jul-22 25-Aug-22 27-Aug-22
M-153 M-153-MS Disk Valve 10-Nov-22 30-Nov-22 7-Dec-22 60 14-Dec-22 12-Feb-23 14-Mar-23 16-Mar-23
Fresh Air Louvers (Intake with Sand Trap
M-154 M-154-MS 16-Nov-22 6-Dec-22 13-Dec-22 60 20-Dec-22 18-Feb-23 20-Mar-23 22-Mar-23
Louvers)
M-135 M-135-MS PRIMARY CHILLED WATER PUMPS 4-Jun-22 24-Jun-22 1-Jul-22 60 8-Jul-22 6-Sep-22 6-Oct-22 8-Oct-22
M-141 M-141-MS MOTORIZED FIRE DAMPER 10-Nov-22 30-Nov-22 7-Dec-22 60 14-Dec-22 12-Feb-23 14-Mar-23 16-Mar-23
M-152 M-152-MS Transfer Grill 18-Jun-23 8-Jul-23 15-Jul-23 60 22-Jul-23 20-Sep-23 20-Oct-23 22-Oct-23
EXPANSION TANK FOR CHILLED
M-132 M-132-MS 11-Oct-22 31-Oct-22 7-Nov-22 60 14-Nov-22 13-Jan-23 12-Feb-23 14-Feb-23
WATER PIPIN SYSTEM
CONDENSER WATER PUMPS for
M-137 M-137-MS 10-Nov-22 30-Nov-22 7-Dec-22 60 14-Dec-22 12-Feb-23 14-Mar-23 16-Mar-23
Cooling Tower (CTP)
AIR HANDLING UNIT (CONSTANT AIR
M-118 M-118-MS 6-May-23 26-May-23 2-Jun-23 60 9-Jun-23 8-Aug-23 7-Sep-23 9-Sep-23
VOLUME)
M-119 M-119-MS FAN COIL UNITS 10-Nov-22 30-Nov-22 7-Dec-22 60 14-Dec-22 12-Feb-23 14-Mar-23 16-Mar-23
M-121 M-121-MS Axial Inline Exhaust Fans 12-Jun-23 2-Jul-23 9-Jul-23 60 16-Jul-23 14-Sep-23 14-Oct-23 16-Oct-23
M-122 M-122-MS Axial Inline supply Fans 12-Jun-23 2-Jul-23 9-Jul-23 60 16-Jul-23 14-Sep-23 14-Oct-23 16-Oct-23
M-123 M-123-MS Axial Inline Exhaust Fans: 12-Jun-23 2-Jul-23 9-Jul-23 60 16-Jul-23 14-Sep-23 14-Oct-23 16-Oct-23
Material Submittal Date Material Approval Date PO Issued Manufacture Started Shipment Date Clearance Delivery to Site / Store
M-140 M-140-MS MOTORIZED FIRE/SMOKE DAMPER 25-Feb-23 17-Mar-23 24-Mar-23 60 31-Mar-23 30-May-23 29-Jun-23 1-Jul-23
M-143 M-143-MS Ceiling Diffusers 11-Mar-23 31-Mar-23 7-Apr-23 60 14-Apr-23 13-Jun-23 13-Jul-23 15-Jul-23
M-146 M-146-MS Grills 25-Mar-23 14-Apr-23 21-Apr-23 60 28-Apr-23 27-Jun-23 27-Jul-23 29-Jul-23
M-155 M-155-MS AIR TERMINAL - VAV 8-Apr-23 28-Apr-23 5-May-23 60 12-May-23 11-Jul-23 10-Aug-23 12-Aug-23
M-159 M-159-MS Motor Control Center (MCC'S) 22-Apr-23 12-May-23 19-May-23 60 26-May-23 25-Jul-23 24-Aug-23 26-Aug-23
DIVISION 25: BUILDING MANAGEMENT SYSTEM
M-160 M-160-MS BUILDING MANAGEMENT SYSTEM 14-May-22 3-Jun-22 10-Jun-22 60 17-Jun-22 16-Aug-22 15-Sep-22 17-Sep-22
FACILITY MANAGEMENT SYSTEM
M-161 M-161-MS 14-May-22 3-Jun-22 10-Jun-22 60 17-Jun-22 16-Aug-22 15-Sep-22 17-Sep-22
(FMS) FOR INTEGRATION ONLY
DIVISION 26 : ELECTRICAL WORKS
M-162 M-162-MS ELECTRICAL WORKS 11-Jul-22 31-Jul-22 7-Aug-22 60 14-Aug-22 13-Oct-22 12-Nov-22 14-Nov-22
M-177 M-177-MS Cable Trays. 7-Mar-22 27-Mar-22 3-Apr-22 60 10-Apr-22 9-Jun-22 9-Jul-22 11-Jul-22
M-176 M-176-MS LV CABLES 13-Mar-22 2-Apr-22 9-Apr-22 60 16-Apr-22 15-Jun-22 15-Jul-22 17-Jul-22
M-169 M-169-MS DISTRIBUTION BOARDS 19-Mar-22 8-Apr-22 15-Apr-22 60 22-Apr-22 21-Jun-22 21-Jul-22 23-Jul-22
M-164 M-164-MS TRANSFORMERS 1-Sep-22 21-Sep-22 28-Sep-22 60 5-Oct-22 4-Dec-22 3-Jan-23 5-Jan-23
M-170 M-170-MS PANEL BOARDS 19-Mar-22 8-Apr-22 15-Apr-22 60 22-Apr-22 21-Jun-22 21-Jul-22 23-Jul-22
M-163 M-163-MS RING MAIN UNIT RMU) 1-Sep-22 21-Sep-22 28-Sep-22 60 5-Oct-22 4-Dec-22 3-Jan-23 5-Jan-23
M-166 M-166-MS LV SWITCHGEAR 1-Sep-22 21-Sep-22 28-Sep-22 60 5-Oct-22 4-Dec-22 3-Jan-23 5-Jan-23
M-167 M-167-MS GENERATORS 16-Jun-22 6-Jul-22 13-Jul-22 60 20-Jul-22 18-Sep-22 18-Oct-22 20-Oct-22
M-173 M-173-MS BUSWAY 17-Jul-22 6-Aug-22 13-Aug-22 60 20-Aug-22 19-Oct-22 18-Nov-22 20-Nov-22
AUTOMATIC TRANSFER SWITCH
M-172 M-172-MS 11-Jun-22 1-Jul-22 8-Jul-22 60 15-Jul-22 13-Sep-22 13-Oct-22 15-Oct-22
(A.T.S)
M-165 M-165-MS MV CABLE 17-Jul-22 6-Aug-22 13-Aug-22 60 20-Aug-22 19-Oct-22 18-Nov-22 20-Nov-22
M-171 M-171-MS ISOLATED POWER PANELS 18-Jun-22 8-Jul-22 15-Jul-22 60 22-Jul-22 20-Sep-22 20-Oct-22 22-Oct-22
M-181 M-181-MS EXTERIOR LIGHTING FIXTURES 14-Jun-23 4-Jul-23 11-Jul-23 60 18-Jul-23 16-Sep-23 16-Oct-23 18-Oct-23
M-174 M-174-MS PLUG-IN BREAKERS 16-Jul-22 5-Aug-22 12-Aug-22 60 19-Aug-22 18-Oct-22 17-Nov-22 19-Nov-22
M-175 M-175-MS UNINTERRUPTIBLE POWER SUPPLY 10-Aug-22 30-Aug-22 6-Sep-22 60 13-Sep-22 12-Nov-22 12-Dec-22 14-Dec-22
M-168 M-168-MS LV PARALLELING SWICTHGEAR 1-Sep-22 21-Sep-22 28-Sep-22 60 5-Oct-22 4-Dec-22 3-Jan-23 5-Jan-23
ENCLOSED SWITCHES AND CIRCUIT
M-178 M-178-MS 27-Aug-22 16-Sep-22 23-Sep-22 60 30-Sep-22 29-Nov-22 29-Dec-22 31-Dec-22
BREAKERS
M-179 M-179-MS POWER OUTLETS 10-Sep-22 30-Sep-22 7-Oct-22 60 14-Oct-22 13-Dec-22 12-Jan-23 14-Jan-23
Material Submittal Date Material Approval Date PO Issued Manufacture Started Shipment Date Clearance Delivery to Site / Store
M-180 M-180-MS LIGHTING FIXTURES 24-Sep-22 14-Oct-22 21-Oct-22 60 28-Oct-22 27-Dec-22 26-Jan-23 28-Jan-23
M-182 M-182-MS LIGHTING CONTROL SYSTEM 8-Oct-22 28-Oct-22 4-Nov-22 60 11-Nov-22 10-Jan-23 9-Feb-23 11-Feb-23
M-183 M-183-MS GROUNDING SYSTEM 22-Oct-22 11-Nov-22 18-Nov-22 60 25-Nov-22 24-Jan-23 23-Feb-23 25-Feb-23
M-184 M-184-MS LIGHTNING PROTECTION SYSTEM 5-Nov-22 25-Nov-22 2-Dec-22 60 9-Dec-22 7-Feb-23 9-Mar-23 11-Mar-23
DIVISION 27 : COMMUNICATION SYSTEMS WORKS
M-185 M-185-MS STRUCTURED CABLING SYSTEM 3-Apr-22 23-Apr-22 30-Apr-22 60 7-May-22 6-Jul-22 5-Aug-22 7-Aug-22
M-186 M-186-MS CABLE TRUNKING 9-Apr-22 29-Apr-22 6-May-22 60 13-May-22 12-Jul-22 11-Aug-22 13-Aug-22
M-187 M-187-MS AUDIO VISUAL SYSTEM 9-Apr-22 29-Apr-22 6-May-22 60 13-May-22 12-Jul-22 11-Aug-22 13-Aug-22
M-188 M-188-MS IP TELEVISION SYSTEM 9-Apr-22 29-Apr-22 6-May-22 60 13-May-22 12-Jul-22 11-Aug-22 13-Aug-22
M-189 M-189-MS WIRELESS MASTER CLOCK SYSTEM 9-Apr-22 29-Apr-22 6-May-22 60 13-May-22 12-Jul-22 11-Aug-22 13-Aug-22
M-190 M-190-MS IP NURSE CALL SYSTEM 9-Apr-22 29-Apr-22 6-May-22 60 13-May-22 12-Jul-22 11-Aug-22 13-Aug-22
M-191 M-191-MS PUBLIC ADDRESS SYSTEM 9-Apr-22 29-Apr-22 6-May-22 60 13-May-22 12-Jul-22 11-Aug-22 13-Aug-22
CAR PARKING MANAGEMENT
M-192 M-192-MS 9-Apr-22 29-Apr-22 6-May-22 60 13-May-22 12-Jul-22 11-Aug-22 13-Aug-22
SYSTEM
DIVISION 28 : ELECTRONIC SAFETY& SECURITY
M-194 M-194-MS IP CCTV SYSTEM 9-Apr-22 29-Apr-22 6-May-22 60 13-May-22 12-Jul-22 11-Aug-22 13-Aug-22
M-193 M-193-MS FIRE ALARM SYSTEM 9-Apr-22 29-Apr-22 6-May-22 60 13-May-22 12-Jul-22 11-Aug-22 13-Aug-22
IP ACCESS CONTROL & TIME
M-195 M-195-MS 14-Apr-22 4-May-22 11-May-22 60 18-May-22 17-Jul-22 16-Aug-22 18-Aug-22
ATTENDANCE SYSTEM
DIVISION 31 : EARTHWORKS
M-197 M-197-MS Drainage layer 23-Oct-21 12-Nov-21 19-Nov-21 60 26-Nov-21 25-Jan-22 24-Feb-22 26-Feb-22
M-196 M-196-MS Backfilling 20-Jan-22 9-Feb-22 16-Feb-22 60 23-Feb-22 24-Apr-22 24-May-22 26-May-22
M-198 M-198-MS Anti-termite treatment 20-Jan-22 9-Feb-22 16-Feb-22 60 23-Feb-22 24-Apr-22 24-May-22 26-May-22