DAILY ACTIVITY

Name of Project : JKT3 DATA CENTER , CIBITUNG


Job No. : K-20-74 Day : JUMAT
Location : MM 2100, CIBITUNG Date : 20-11-2020

No DESCRIPTION LOCATION LABOUR ASS. FOREMAN/GROUP TARGET FINISH REMARK

SUGIARTO
ASEP M.
INDRA
1 INSTALLING CANAL C FOR LAMP WORKSHOP OFFICE MACHRUF 20/11/2020 T
SUNARDI
MARSON
MIKRI

2 FABRICATING PIPE & FLANGE 400 WORKSHOP TEMPORARY ON PROGRESS T


SURYANA
JAELANI
JONIH
SARWIN
SOBIRIN
SAPTO
SAEFULLAH
RUKMAN
CONTINUE WELDING PIPE & FLANGE DEDE
3 WORKSHOP TEMPORARY ON PROGRESS P
400

FABRICATING CONDENSER PIPE


4 600A (CUTTING AND SETTING WORKSHOP TEMPORARY ON PROGRESS P
PROGRESS) NANDAR
JONIH
SUGIANI
JAMAL
ALVIN
MUDIANTO
ERWIN

INSTALLING SUPPORT & PIPE


5 2ND FLOOR ON PROGRESS T
CONDENSOR

OGAS
FABRICATING SUPPORT COOLING TARDI JONIH
6 WORKSHOP SUA ON PROGRESS P
CORR ‐ D1L202 AHMAD KUSMADUN
TOPIK

7 MARKING OPENING DUCTING ALL AREA – 2ND FLOOR T

RONI
DENI
AHYAR 22/11/2020
RIKO
NANANG
8 FABRICATING SUPPORT TEMPORARY WORKSHOP P

FM.OPR - 13 Rev 00
DAILY ACTIVITY
Name of Project : JKT3 DATA CENTER , CIBITUNG
Job No. : K-20-74 Day : JUMAT
Location : MM 2100, CIBITUNG Date : 20-11-2020

No DESCRIPTION LOCATION LABOUR ASS. FOREMAN/GROUP TARGET FINISH REMARK

MUDIONO ASEP M.
INSTALL SUPPORT C TRAY 300
9 CHILLER ROOM YUDI SAEFUDIN 21/11/2020 T
CABANG 800
FERDI CHOLIL (SAFETY)

RIAN ASEP M.
10 FABRICATING BRACKET SUPPORT WORKSHOP SUA 20/11/2020 P
RIFI RAHMAT

SAFETY OFFICER WORKSHOP DANIEL DIMAS

DOCUMENT CONTROL ALL AREA ANSON E.

WAREHOUSE KEEPER WAREHOUSE OGAS DODY E.

AGUS

SANDYA

CHECKED BY, PREPARED BY, SAFETY OFFICER

Site Manager FOREMAN

( SARIM ) ( JONIH.BR ) ( DIMAS )

INFORMATION INSTRUCTION

1. LOKASI TUGAS KERJA HARAP DISESUAIKAN DENGAN GRUPNYA

2. JAGA DAN PERHATIKAN ALAT KERJA YANG DIPERGUNAKAN

3. CEK SEMUA ALAT YANG BERMUATAN LISTRIK

4. JAGA KESELAMATAN KERJA

FM.OPR - 13 Rev 00

You might also like