EPOXY TERRAZZO SYSTEM FOR HIGHLY AESTHETIC AND LONG-LASTING
FLOOR FINISH

Products required:
Mapefloor I 302 SL - Mapefloor Terrazzo Aggregate G - Mapecolor Paste -
Primer SN - Quartz
PRODUCT DESCRIPTION APPLICATION PROCEDURE compact, strong and clean and must
MAPEFLOOR EPOXY TERRAZZO be dimensioned according to the static
SYSTEM G is a seamless epoxy resin 1. Substrate analysis and dynamic loads to which it will be
terrazzo floor system, combining a blend subjected when in service. The flatness
of clear glass chippings for high aesthetic Before applying MAPEFLOOR must be defined according to the final
demand floor finishes. EPOXY TERRAZZO SYSTEM G, use.
the substrate on which the coating is
MAPEFLOOR EPOXY TERRAZZO to be applied must be carefully To achieve the best results, there
SYSTEM G is composed of the epoxy analysed. must be no materials, debris or
binder MAPEFLOOR I 302 SL mixed contaminations left on the substrate
with silica sand powder QUARTZ 0.25 The concrete or cementitious screed which could potentially affect the
and QUARTZ 0.5 and the dedicated for the substrate must be sound,
glass aggregates MAPEFLOOR
TERRAZZO AGGREGATE G.

TYPICAL APPLICATION EXAMPLES


• Commercial centers and shops
• Showrooms and meeting halls
• Airports
• Hotels, restaurants and cinemas
• Public buildings and offices
• Theme parks

PROPERTIES AND ADVANTAGES


• High aesthetic appearance
• Easy to clean
• Long lasting solution
• Possibility of many aesthetical
solutions
• Seamless finish (except on dynamic
joints)
• Easy to maintain
• Good chemical resistance to
detergents and cleaning operations
usually adopted for maintenance.
Mapefloor Epoxy TECHNICAL DATA (typical values)
Terrazzo System G
Adhesion on concrete, 7 days (BS EN 13892-8): ≥ 4 N/mm²

Compressive strength (BS EN 13892-2):


adhesion of the coating, such as:- - after 24 hours: ≥ 15 N/mm²
• cement laitance; - after 3 days: ≥ 25 N/mm²
- after 7 days: ≥ 30 N/mm²
• dust or detached or loose materials;
• protective waxes, curing products,
paraffin or efflorescence; Flexural strength (BS EN 13892-2):
• oil stains or layers of dirty resin; - after 24 hours: ≥ 6 N/mm²
• traces of paint or chemical products. - after 3 days: ≥ 10 N/mm²
- after 7 days: ≥ 14 N/mm²
Any other kind of material or substance
that could affect adhesion of the Shore D hardness, 7 days (DIN 53505): ≥ 80
coating must be removed before
starting work. If such materials or
substances are present, the substrate
must be prepared by carrying out a damaged joints.
specific preparation cycle. Please Mix MAPEFLOOR I 302 SL, silica
contact Mapei Technical Services for The surrounding temperature must be sand and glass aggregates until a
advice and information. higher than +8°C and the temperature homogeneous mixture is achieved. The
of the substrate must be at least 3°C mixture is then poured onto the primed
The substrate pull-off strength must higher than the dew-point temperature. surface and spread by means of a
be achieved minimum 1.5 MPa. The straight-edge trowel, etc. The minimum
substrate’s moisture content shall not If any of the above conditions are not thickness is 7mm.
be more than 4%. A proper moisture strictly adhered to, the quality of the
barrier system shall be placed prior coating may be poor. After the resin has hardened, polishing
to the application of MAPEFLOOR operations can take place. Use suitable
EPOXY TERRAZZO SYSTEM G. 3. Priming the substrate diamond grinder equipment and
tools. During polishing operations, the
If all the above conditions are met, Mix the components of PRIMER SN application of MAPEFLOOR I 910 as
MAPEFLOOR EPOXY TERRAZZO with a low-speed mechanical stirrer pore filler may be required.
SYSTEM G may be applied on until a homogeneous mix is obtained.
concrete floors, conventional or Add 20% by weight of QUARTZ During polishing operation, the floor
polymer-modified cementitious screeds 0.25 and re-mix until homogeneous. surface must be maintained wet
and shrinkage-compensated screeds Pour the mixed PRIMER SN onto to avoid black marks due to high
such as those made from MAPECEM, the floor surface and spread it by temperatures triggered by the high-
TOPCEM or TOPCEM PRONTO. means of a straight steel trowel, then speed rotating tools. In case some
fully broadcast the wet surface with profiles have to be placed to obtain
2. Substrate preparation QUARTZ 1.0 or 1.2. Once the specific drawings or to divide different
PRIMER SN has hardened, remove areas with different colours, it is
It is very important that the surface the excess quartz by sweeping and advisable to use either PVC or brass or
is prepared as specified to ensure vacuuming. aluminium profile for better result of the
correct application and the best final polished surface.
performance of MAPEFLOOR EPOXY 4. Applying MAPEFLOOR EPOXY
TERRAZZO SYSTEM G. TERRAZZO SYSTEM G 5. Hardening and step-on times

The most suitable method to prepare Mix the components of MAPEFLOOR At +25°C, MAPEFLOOR EPOXY
the surface is by shot-blasting, I 302 SL with a low-speed mechanical TERRAZZO SYSTEM G sets to foot
taking care not to go too deep into stirrer until a homogeneous mix traffic after 16 hours, may be used
the substrate. Any defects present, is obtained. Pour the prepared by light loads after 1 to 2 days and is
such as holes, pitting, cracking, etc., MAPEFLOOR I 302 SL into a ready for final use once fully hardened
must be repaired beforehand using suitable epoxy mortar mixer, then add after approximately 7 days. Lower
either EPORIP or PRIMER SN or MAPECOLOR PASTE and mix until temperatures lead to longer hardening
MAPEFLOOR I 302 SL, depending a homogeneous mixture is achieved. If and step-on times.
on the width and depth of the defects pre-pigmented MAPEFLOOR I 302
and cracks. SL is used, MAPECOLOR PASTE CONSUMPTION
must not be added. Then add the
If the substrate needs to be silica sand mixture of QUARTZ 0.25 Primer:
consolidated, use PRIMER MF. and QUARTZ 0.5 and the mixture PRIMER SN (A + B) 0.3 - 0.7 kg/m2
If there are deep hollows or highly of glass aggregates MAPEFLOOR QUARTZ 0.25 0.06 - 0.14 kg/m2
deteriorated areas on the substrate, TERRAZZO AGGREGATE G
repair these areas beforehand while mixing. For each 20kg kit of Broadcast:
using MAPEFLOOR EP19, three- MAPEFLOOR I 302 SL, add 10kg QUARTZ 1.0 or 1.2 1 - 1.5 kg/m2
component epoxy mortar, or with of QUARTZ 0.25, 10kg of QUARTZ
products from the MAPEGROUT line, 0.5 and 44kg of MAPEFLOOR
which may also be used to integrate TERRAZZO AGGREGATE G. The actual consumption of the primer
is influenced by substrate’s porosity diluted at a concentration of 5% to may cause skin sensitization to those
and absorption, temperature, job-site 10% in water. Special detergents and predisposed. During the mixing and
conditions, etc. cleaning tools are readily available for application of the products, it is
cleaning resin floors. Manufacturers recommended to use protective gloves
Terrazzo system per 10mm of these detergents supply all the
and goggles and to take the usual
thickness: information required for the cleaning
precautions for handling chemicals.
MAPEFLOOR I 302 SL 6.6 kg/m2 procedures to apply. Our Technical
(A + B + MAPECOLOR PASTE) Services Department is available for For further and complete information
any information required. about the safe use of the products,
QUARTZ 0.25 3.0 kg/m2 please refer to the latest version of our
PACKAGING Safety Data Sheets.
QUARTZ 0.5 3.0 kg/m2 PRIMER SN:
20kg/set or 5kg/set (A + B) PRODUCT FOR PROFESSIONAL USE.
MAPEFLOOR TERRAZZO MAPEFLOOR I 302 SL:
AGGREGATE G 13.3 kg/m2 20kg/set (A + B) NOTE
MAPECOLOR PASTE: 1.75kg/tub Information regarding safety equipment
The actual consumption is influenced QUARTZ 0.25: 25kg/bag and handling of the products are
by the substrate and job site QUARTZ 1.0 or 1.2: 25kg/bag contained in the technical data sheets
conditions. QUARTZ 0.5: 25kg/bag for each component. However, we
MAPEFLOOR TERRAZZO recommend that protective googles
CLEANING AND MAINTENANCE AGGREGATE G: 22kg/bag
MAPEFLOOR EPOXY TERRAZZO and glooves are always used when
SYSTEM G must be treated with STORAGE mixing and applying the products.
MAPELUX LUCIDA or MAPELUX Store in a dry, sheltered place in
OPACA to make the surface easier to original, unopened packaging. If the products are to be applied
clean and maintain. on surfaces or under climatic and/
SAFETY INSTRUCTIONS FOR or service conditions which are
Regular cleaning and maintenance PREPARATION AND APPLICATION different from those indicated in the
operations increase the life of a Component A of PRIMER SN technical data sheet for the system,
coated floor, improves its aesthetic and MAPEFLOOR I 302 SL may please contact MAPEI’s Technical
properties and reduces its tendency cause skin and eye irritation, while
Services Department.
to collect dirt. Floors created using Component B of MAPEFLOOR I 302
MAPEFLOOR SYSTEMS are SL is corrosive and may cause burns.
generally easy to wash with neutral Components A and B of PRIMER
detergents, or with alkali detergents SN and MAPEFLOOR I 302 SL
6011-9-2019 (GB x Far East)

Mapei Far East Pte Ltd


28, Tuas West Road - Singapore 638383
Tel (65) 6862 3488 - Fax (65) 6862 1012/3
Email: mapei@mapei.com.sg - Website: www.mapei.com.sg

www.mapei.com