Reference TOF-PROC-2022-0001

LOAD TEST Version 0


PROCEDURE Type Procedure
Project OTWAY NEARSHORE PHASE 2
Issue date 21/07/2022

LOAD TEST FOR HPU/WHCP EQUIPEMENTS


CLIENT : CONTROL & ELECTRICS PTE LTE
VENDOR : TOF YEHAR SGR PTE LTD
PROJECT : OTWAY NEARSHORE PHASE 2
JOB NO : 22- 592

TOF YEHAR SGR PTE LTD 280, Woodlands Industrial Park E5, Blk 2, #09-12, Harvest @ Woodlands, Singapore –
757322 Tel: +65 62640792|Fax: +65 62640153 |Email: sales@tof.com.sg |Web: www.tof.com.sg
pg. 1
Reference TOF-PROC-2022-0001
LOAD TEST Version 0
PROCEDURE Type Procedure
Project OTWAY NEARSHORE PHASE 2
Issue date 21/07/2022

Contents
1. OBJECTIVE...................................................................................................................3
2. SCOPE OF WORK........................................................................................................3
2.1 OTWAY NEARSHORE PHASE2 PROJECT SKIDS..............................................3
3. PRE-TEST REQUIREMENTS AND CHECK LIST ........................................................4
3.1 Risk Assessment....................................................................................................4
4. TEST DETAILS..............................................................................................................4
4.1 Test setup- OTWAY NEARSHORE PHASE 2 HPU ............................………………..5
4.2 Test setup- OTWAY NEARSHORE PHASE 2 WHCP…………………………………...6
5. TEST FLOW CHART ....................................................................................................7

1. OBJECTIVE

TOF YEHAR SGR PTE LTD 280, Woodlands Industrial Park E5, Blk 2, #09-12, Harvest @ Woodlands, Singapore –
757322 Tel: +65 62640792|Fax: +65 62640153 |Email: sales@tof.com.sg |Web: www.tof.com.sg
pg. 2
Reference TOF-PROC-2022-0001
LOAD TEST Version 0
PROCEDURE Type Procedure
Project OTWAY NEARSHORE PHASE 2
Issue date 21/07/2022

The objective of this procedure is to ensure that the process of conducting the load test in safe
manner. The supervisor shall brief the scope of work to the TOF Representative,
Customer Representative & All other attendees prior to the load test and this document shall be
used in conjunction with other relevant safety procedures such as risk assessment.

2. SCOPE OF WORK
To conduct load test on client’s structural skid according to client specification requirements using
crane and weights. Locations and orientation of the lifting eye bolt are as below:

2.1 OTWAY NEARSHORE PHASE 2 SKIDS


Test load value provided by the client are as indicated in the table below:

S.NO DESCRIPTION WEIGHT SAFETY TEST TARE WEIGHT DETAILS


FACTO VALUE
R (MT)
HPU Structure Approx. Weight -
OTWAY
1MT to 1.2MT + Lifting set Approx.
NEARSHORE
a. HPU DRY 1.5 13 MT weight 0.25MT
PHASE 2
WEIGHT - 8.5 Total = 1.25 MT to 1.45 MT
HPU SKID- 5900L X
MT (Approx.)
2000D X 2150H
*Calculation weights are estimated
weight. Actual weights to be verified
during the load test
WHCP Structure Approx. weight -
OTWAY
0.2MT to 0.3MT + Lifting set
NEARSHORE
b. HPU DRY 1.5 2.5 MT Approx. weight -0.12MT
PHASE 2
WEIGHT - 1.5 Total = 0.32MT to 0.42MT (Approx.)
WHCP SKID- 1250L
MT *Calculation weights are estimated
X 1200D X 2000H
weight. Actual weights to be verified
during the load test

3. PRE-TEST REQUIREMENTS AND CHECK LIST


Prior to load test, a pre-test check is to be conducted to ensure that everything goes in
accordance to pre- determined plan.

No. Description Reference

a. General Arrangement Drawing Approved HPU/WHCP GA drawings


b. 6MT & 25MT Link Type Load Cell Valid Calibration certificate attached. These
certificates will be verified by the TPI.
{Load cell calibration party is SAC Accredited}

c. Toolbox meting for briefing the load test Tool box meeting record will be enclosed, along
procedure. with load test report.

d. Rigging Hardware for lifting


All rigging items are tagged, stenciled and
stickers (with serial numbers) will be provided Valid test certificate
for verification.
The applicable certificates will be verified by the
witnessing TPI.

TOF YEHAR SGR PTE LTD 280, Woodlands Industrial Park E5, Blk 2, #09-12, Harvest @ Woodlands, Singapore –
757322 Tel: +65 62640792|Fax: +65 62640153 |Email: sales@tof.com.sg |Web: www.tof.com.sg
pg. 3
Reference TOF-PROC-2022-0001
LOAD TEST Version 0
PROCEDURE Type Procedure
Project OTWAY NEARSHORE PHASE 2
Issue date 21/07/2022

e. Lifting Ring,
*DLP-M24GRABIQ (WLL4.10 MT X 2) TPI can verify the mill certificate on site.
*DLP-M36GRABIQ (WLL7.00 MT X 2)

f. NDT (PT test) on lifting lug & Frame weld NDT technician as per approved NDT procedure.
joints prior to Commencement of load test and
after load test.

3.1 RISK ASSESSMENT

No. Risk Control Measure Category


1 Equipment failure Annual maintenance and recertification Low to None
2 Rigging Failure Certification and pre-test visual Low to None
inspection
3 Specimen failure Engineering information and expectation Medium to Low
4 Incorrect test details Pre-Test Requirement check list Low to None

4. TEST DETAILS

a. The skid shall be rigged up with riggings (provided by the client) to the load cell which will be attached to
the crane hook.

b. Pre-verified blocks (with weight marking) will be distributed considering the COG of HPU & WHCP
structure, Refer section 4.1 & 4.2 for weight distribution details (There is no intermediate loading during
the load test).

c. Forklift will be used for loading & removing the load from HPU / WHCP structure.

d. Crane will be operated to raise the structure clear of the ground until reading on the load cell reaches the
required test load reading, that is 1.5 times the dry weight of HPU and WHCP.

e. 1.5 times safety factor is in accordance with client WHCP specification

f. Holding time for the load test shall be 5 minutes.

g. After 5 minutes HPU & WHCP structures will be lowered slowly and steadily onto the ground, releasing
the load, prior to NDT. Once the load has been released, the Structure shall be inspected for any bending
or other deformation.

h. At any point if any bending in base channel is observed, the subsequent loading will be stopped & load
test will be discontinued. Any plastic deformation or crack formation (base frame bending) in HPU or
WHCP structures would be cause for rejection of the structures, the load test shall be stopped and an
NCR will be raised.

i. Load test will be performed in the presence of client representative


j.

k. Pre & post load test, dye penetrant test will be performed to ensure integrity of weld joints and also to
check any post load test defects in the weld joints.

l. The reports of pre and post load test NDE reports will be part of fabrication MRB.

TOF YEHAR SGR PTE LTD 280, Woodlands Industrial Park E5, Blk 2, #09-12, Harvest @ Woodlands, Singapore –
757322 Tel: +65 62640792|Fax: +65 62640153 |Email: sales@tof.com.sg |Web: www.tof.com.sg
pg. 4
Reference TOF-PROC-2022-0001
LOAD TEST Version 0
PROCEDURE Type Procedure
Project OTWAY NEARSHORE PHASE 2
Issue date 21/07/2022

4.1 TEST SETUP - OTWAY NEARSHORE PHASE 2 HPU

Weights will be placed into the HPU structure frame,


Supported on beams/channels from the client if required.

4.2 TEST SETUP - OTWAY NEARSHORE PHASE 2 WHCP

TOF YEHAR SGR PTE LTD 280, Woodlands Industrial Park E5, Blk 2, #09-12, Harvest @ Woodlands, Singapore –
757322 Tel: +65 62640792|Fax: +65 62640153 |Email: sales@tof.com.sg |Web: www.tof.com.sg
pg. 5
Reference TOF-PROC-2022-0001
LOAD TEST Version 0
PROCEDURE Type Procedure
Project OTWAY NEARSHORE PHASE 2
Issue date 21/07/2022

Weights will be placed into the WHCP structure frame,


Supported on beams/channels from the client if required

5. TEST FLOW

Load test Check list needs


to be used and completed
through the load test
TOF YEHAR SGR PTE LTD 280, Woodlands Industrial Park E5, Blk 2, #09-12, Harvest @ Woodlands, Singapore –
757322 Tel: +65 62640792|Fax: +65 62640153 |Email: sales@tof.com.sg |Web: www.tof.com.sg
pg. 6
Reference TOF-PROC-2022-0001
LOAD TEST Version 0
PROCEDURE Type Procedure
Project OTWAY NEARSHORE PHASE 2
Issue date 21/07/2022

Review rigging plan

Rig up (Refer point 3.d)

Tare handheld reading to zero


to remove weight of below the
hook rigging equipment
(Refer section 2.1)

Apply calculated load

Clear the test area of non-


essential personnel

Audible failure noise, visual


The Structure along with the structural deformation, Stop the test failure
dead weight will be lifted off the structural, rigging failure (or) and raise NCR (Refer
ground and load cell values any form of failure section 4)
shall be checked (Refer section 4)

Hold load for 5 minutes

Release load gradually Prepare report

Derig and housekeep

Visual Inspection and NDT

TOF YEHAR SGR PTE LTD 280, Woodlands Industrial Park E5, Blk 2, #09-12, Harvest @ Woodlands, Singapore –
757322 Tel: +65 62640792|Fax: +65 62640153 |Email: sales@tof.com.sg |Web: www.tof.com.sg
pg. 7