Method Statement - Roof Installation 06.01.22
Method Statement - Roof Installation 06.01.22
Revision No. 00
METHOD OF STATETEMENT
FOR
ROOF CLADDING
THIS DOCUMENT IS INTENDED FOR USE BY ARCCO AND ITS NOMINATED CONSULTANTS, CONTRACTORS, MANUFACTURERS AND SUPPLIERS.
REVISIONS
HOLDS
Rev. No. Section Description
Table of Contents
Contract No. R12 Project No.: T09B02
2. Installation:
2.1. Roof cladding
2.1.1. Preliminaries – Safety considerations
2.1.2. Lifting (by Boom Lift)
2.1.3. Lifting (by Crane)
2.1.4. Installation procedure
2.1.5. Skylight installation procedure
2.1.6. Ridge Panel Installation
2.1.7. Eave Gutter & Downspout Installation
2.1.8. Installation Of Gutter, Support, Downspout And Strap
1500mm
16mm 16mm
dia. bolt dia. bolt
Install life line anchor point pole at the corner side of the building as
shown above.
Specification of lifeline 16mm wire rope as shown below.
Prepare the power supply lines for the power hand tools.
Check for eventual overhanging power lines, and strictly observe
precautions and safety measures.
Lift the panel by the use of boom lift (JCB540) for at least one line of
panel composed of (1pc for downstream and 1pc for upstream).
Line 1 Line 2
Pre-assemble eave gutter on the flat ground and identify its end for
smaller opening mark A to bigger opening mark B
Smaller opening mark A is on the top of bigger opening mark B,
overlap for maximum of 80mm and join together with a double strip
of silicone and two lines of pop rivet.
Pre-joint eave gutter, bring up to the roof for assemble and join
together.
Start from gable trim corner, fix together with gutter strap at
1100mm C/C and a gutter support of 1100mm C/C respectively.
Continue the installation process up to the end of the building same
procedure for pre-joining of eave gutters as mentioned.
RAKE SECTIONS