4 Project: R12-T09B02 – DB Mock-Up Zone Facilities Contractor

? Client Warehouse Contract (ARCCO)


Document Title: Method Statement for Roof Cladding
(Sandwich Panel)
Aconex Doc. No. R12-T09B02-RCO-MTS-ST-0003

Revision No. 00

METHOD OF STATETEMENT
FOR
ROOF CLADDING

Rev. Date Purpose of Issue Prepared By Checked By Approved By

00 03/01/2022 For Approval ARCCO ARCCO TRSDC

THIS DOCUMENT IS INTENDED FOR USE BY ARCCO AND ITS NOMINATED CONSULTANTS, CONTRACTORS, MANUFACTURERS AND SUPPLIERS.
REVISIONS

Rev. No. Section Revision Description


00 All Issued for review

HOLDS
Rev. No. Section Description

Table of Contents
Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 2 OF 41
1. Handling and Storage:

2. Installation:
2.1. Roof cladding
2.1.1. Preliminaries – Safety considerations
2.1.2. Lifting (by Boom Lift)
2.1.3. Lifting (by Crane)
2.1.4. Installation procedure
2.1.5. Skylight installation procedure
2.1.6. Ridge Panel Installation
2.1.7. Eave Gutter & Downspout Installation
2.1.8. Installation Of Gutter, Support, Downspout And Strap

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 3 OF 41
1. Handling and Storage.
Panel’s packages handling (unloading and movement) and storage @ project site is a
delicate phase during which panels might get damaged. For these reasons, the
following instructions should be thoroughly observed.

Unloading with Forklifts:


 Recommend only in case of leveled and smooth terrain.
 Forks should be longer than package’s width.
 Forks should be spread apart as much possible.
 Forks upper surface should be clean and smooth, in order damages of panels
surface
 Never unload more than one package at a time.

Storing Panel at Project Site:

 Place package on smooth, level and rigid terrain.


 Support packages on wooden or polystyrene spacer’s width 200mm, every
1.00m.
 Packages should be placed slightly inclined to allow for eventual infiltration - /
condensation water drainage.
 Maximum 2 or 3 packages should be stacked in height (as transported)
 Packages should be stored at sheltered places. If not possible, they should be
protected from rain and sun rays with rainproof membrane, ensuring, at the
same time, adequate ventilation of the packages.
 The removable film of panels’ surface should not be exposed to sun rays for
prolonged periods. In any case, it should be removed within 45 days from
panel’s production date.

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 4 OF 41
Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 5 OF 41
Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 6 OF 41
2. Installation

2.1 Roof Cladding:


2.1.1. Preliminaries – Safety Considerations
 Check that the panels have been stored as recommended.
 Check that the purlins (supporting structures of the panel) comply
with the project drawing (span length, width of purlins flange etc.)
they are not deformed and they form a plane. Panels are designed
for installation on plane surface of minimum slope 7%.
 Check that safety measures have been implemented.
 Check the installation workers bear the appropriate (PPE).
 Prepare a lifeline during roof panel installation.

Life Line Plan

1500mm

16mm dia. Bolt

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 7 OF 41
Shackle & Turn Buckle Shackle & Turn Buckle

16mm Wire 16mm Wire


Rope (Lifeline) Rope (Lifeline)

Welded at 16mm Welded at


16mm
3” dia. pipe dia. bolt 3” dia. pipe
dia. bolt

16mm 16mm
dia. bolt dia. bolt

 Install life line anchor point pole at the corner side of the building as
shown above.
 Specification of lifeline 16mm wire rope as shown below.

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 8 OF 41
 Prepare a temporary staircase
made of scaffolding and step
ladder at both ends corner of
the building for erectors’
access.

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 9 OF 41
 Use scissor lift for access of personnel.

 Prepare the power supply lines for the power hand tools.
 Check for eventual overhanging power lines, and strictly observe
precautions and safety measures.

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 10 OF 41
 Installation workers are recommended to bear hand gloves (cutting
precautions) and footwear with soft soles in order avoids eventual
panels’ surface scratching / damaging.

2.1.2. Lifting (by Boom Lift):


 Package should be placed on the roof longitudinal to the purlins and
perpendicular to the main rafter load bearing.
 Package should be secured on the roof structure against slipping and
uplifting forces.

Lift Performance – Stabilizers Extended

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 11 OF 41
Lift Performance – Stabilizers Retracted

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 12 OF 41
2.1.3 Lifting (by Crane):
 Package should be placed on the roof purlins, close to the main
trusses (load bearing structure) and distributed along roof’s length,
taking into considerations the installation direction.
 Package should be secured on the roof structure against slipping and
uplifting forces.
 Capacity of lifting belt and beam should be atleast 10 tons minimum.

2.1.4 Installation Procedure:


 The polyethylene protective film on the internal side be remove
before panels’ edges - joint installation.
 On the external side, the protective film should be partially removed
(along panel’s edges – joint) in order to allow additional protection
during installation works.
 Film should be completely removed by the end of the working shift,
and any case, before panel’s fixing on the internal trapezoidal ribs.
 Any eventual traces of adhesive (from the film) on panel’s surfaces
should be removed with the use of a water – detergent mixture.

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 13 OF 41
 Bring the package of panel near the end wall of building longitudinal
in position.

 Lift the panel by the use of boom lift (JCB540) for at least one line of
panel composed of (1pc for downstream and 1pc for upstream).

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 14 OF 41
 Installation direction of the panels should be opposite to the
prevailing wind direction.
 Place the first strip panel (downstream) and fix it in place, making
sure that it is perfectly aligned and square with the roof structure.

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 15 OF 41
 The first strip panel is secured on the roof gable edge.
 After installation of the first strip panels (downstream) the second
strip panels are installed by longitudinal overlapping.
 Application of beadmastic, see detail-1 side lap detail and End Lap
detail drawing.

ROOF DETAIL SECTION

 Longitudinal overlapping of the upstream panel can vary between


100mm and 300mm, also depending on roof slope.
 The second line panel are installed by overlapping its first (empty rib
on the last (full) rib of the first strip panel (downstream) and fixing
them together on the roof purlins.

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 16 OF 41
 The second line upstream are installed by overlapping its first (empty
rib on the last (full) rib of the second strip panel (upstream) and
fixing them together on the roof purlins.
 Third line of panel and so forth will follow the same procedure as
mentioned above. See figure below.

Line 1 Line 2

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 17 OF 41
2

After installation of the first strip panels


(downstream), the second strip panels are
installed by longitudinal overlapping

 The required number of screws and types to be used, will be decided


according to the supplier’s data.

 During drilling, fixing (and eventually cutting) operations, metal


chippings are produced, that can damage panel’s surface either by
scratching or by their rapid corrosion, and such metal chippings
should be carefully removed.

2.1.5 Skylight Installation Procedure:

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 18 OF 41
 Install sheeting angle at the downstream, middle and upper stream
of the sky light as per materials supplied. As shown below.

 Install the specified flashing prior to the installation of the skylight as


shown below.

 Use panel fastener as specified by the supplier.

2.1.6 Ridge Panel Installation:

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 19 OF 41
2.1.7 Eave Gutter & Downspout Installation:

 Pre-assemble eave gutter on the flat ground and identify its end for
smaller opening mark A to bigger opening mark B
 Smaller opening mark A is on the top of bigger opening mark B,
overlap for maximum of 80mm and join together with a double strip
of silicone and two lines of pop rivet.
 Pre-joint eave gutter, bring up to the roof for assemble and join
together.
 Start from gable trim corner, fix together with gutter strap at
1100mm C/C and a gutter support of 1100mm C/C respectively.
 Continue the installation process up to the end of the building same
procedure for pre-joining of eave gutters as mentioned.

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 20 OF 41
2.1.8 Installation Of Gutter, Support, Downspout And Strap:

 The correct installation of gutters and downspout cannot be over-


emphasized. The overall appearance of the building depends
primarily on the quality of the installation of the gutters. Keep all
gutter lines straight with a strap and make all bends sharp and neat.
Be sure edges are jagged, dented, crimped or serrated. End joints
and lapse must be closely controlled.

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 21 OF 41
GUTTER AND DOWNSPOUT REQUIREMENTS 

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 22 OF 41
  TYPICAL DOWNSPOUT DETAIL      TYPICAL DOWNSPOUT DETAIL     
AT FULLY OPEN SIDEWALL        AT PARTIALLY OPEN SIDEWALL 
   

RAKE SECTIONS 
 
 
 
 

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 23 OF 41
GUTTER AT SIDE WALL SECTIONS 
 
 

 
 
 

Contract No. R12 Project No.: T09B02

DOC. NO. R12-T09B02-RCO-MTS-ST-0003


METHOD STATEMENT
FOR ROOF CLADDING REV. 00 DATE: 03/01/22
(SANDWICH PANEL)
PAGE 24 OF 41