Professional Documents
Culture Documents
GEST 80 85 Edition 4
GEST 80 85 Edition 4
GEST 80/85
4th Edition
September 2002
Euro Chlor
***********
This document has been produced by the members of Euro Chlor and should not be
reproduced in whole or in part without the prior written consent of Euro Chlor.
This document was originally prepared in English by our technical experts. For our members’
convenience, it may have been translated into other EU languages by translators / Euro Chlor
members. Although every effort was made to ensure that the translations were accurate, Euro
Chlor shall not be liable for any losses of accuracy or information due to the translation
process.
Prior to 1990, Euro Chlor’s technical activities took place under the name BITC (Bureau
International Technique du Chlore). References to BITC documents may be assumed to be to
Euro Chlor documents.
It has been assumed in the preparation of these publications that the users
will ensure that the contents are relevant to the application selected and are
correctly applied by appropriately qualified and experienced people for whose
guidance they have been prepared. The contents are based on the most
authoritative information available at the time of writing and on good
engineering, medical or technical practice but it is essential to take account of
appropriate subsequent developments or legislation. As a result, the text may
be modified in the future to incorporate evolution of these and other factors.
This edition of the document has been drawn up by the GEST Working Group
to whom all suggestions concerning possible revision should be addressed
through the offices of Euro Chlor.
Section Nature
All sections Wording
4 New title for this section (the old one was: Inspection and
Repairs)
4.1 New title for this section (the old one was: Removal)
4.2.2 Remove of the bellows
4.3 New title for this section (the old one was: Reinstallation)
TABLE OF CONTENTS
1. DEFINITION 5
2. GENERAL PRINCIPALS 5
3. REMOVAL OF VALVES 5
4. REPAIRS 6
4.1. Disassembly 6
4.2. Work to be Carried out 6
4.2.1. Valves with a Packed Gland 6
4.2.2. Bellows Valves 7
4.3. Reassembly 7
5. INSPECTION 7
5.1. Pneumatic Leak Testing 7
5.2. Leak Testing of the Sealing Arrangements (Disc/Seat) 7
5.3. Valves with a Packed Gland - Leak Testing of the Back Seating Arrangement 8
5.3.1. Leak Testing of the Back Seating Facilities 8
5.3.2. Leak Testing of the Packed Gland 8
5.4. Bellows Valves - Leak Testing of the Bellows 8
6. PREPARATION FOR SERVICE 8
7. STORAGE 9
8. CERTIFICATION 9
9. INSTALLATION 9
10. COMMISSIONING 10
11. REFERENCES 10
1. DEFINITION
Practical experience has shown that the installation of dry gaseous and
liquid chlorine valves necessitates specific precautions to avoid their
deterioration and consequent loss of gas tightness. This recommendation
has been written to provide a number of simple rules that will help avoid
deterioration of such valves; the guidance is applicable:
2. GENERAL PRINCIPALS
1. A chlorine valve should not come into contact with water after it has been
installed, because subsequent complete drying out with dry air is virtually
impossible.
3. A valve should not be put back into service without having been checked,
repaired, tested, degreased, dried and confirmed as a chlorine valve
suitable for the required service.
3. REMOVAL OF VALVES
4. REPAIRS
4.1. Disassembly
The valves should be dismantled into all its components parts. All
consumable parts such as joint rings and gland packing should be
discarded.
The valve seat should be made good by welding and then re-machined.
The back seating arrangement used to obtain a gas seal when the
valve is fully opened should be checked, and if necessary, made good
by welding and then re-machining.
4.3. Reassembly
One shall ensure that all components used are the correct materials and
dimensions for the duties envisaged. The reinstallation of the valve shall
be carried out with new joint rings and gland packing. Lubrication of
components which may come into contact with chlorine shall be carried
out with a special grease, compatible with chlorine (chlorofluorinated
greases). All components and the fully reassembled valve shall be dried.
Components which should be greased, notably the thread and the
operating spindle, shall exclusively be treated with a grease which is
compatible with chlorine (chlorofluorinated greases).
5. INSPECTION
The following inspection and tests should be carried out. As a preliminary,
the satisfactory operation of the fully reassembled valve shall be
confirmed.
Machined surfaces, such as flange faces and particularly joint bearing areas
and threaded surfaces, shall avoid any trace of paint. These surfaces should
be coated with a protective layer which is easily removed or with a layer of
grease compatible with chlorine. The valve orifices shall be blanked off and
A plate shall be attached which indicates the name of the valve repairer, the
month and year the repair was carried out, or some identification number
(fixed to the flanges of the bonnet or the valve flanges).
7. STORAGE
To avoid any subsequent confusion, all chlorine valves once assembled shall
be identified specifically for this duty. All precautions must be taken to
maintain valves in an area where they will be protected from moisture. To this
effect, they should be stored in a location which is maintained if possible at a
reasonable temperature. It is a good precaution to keep them in a gas-tight
plastic bag containing a drying aid such as silica gel. For valves which are
waiting installation, another possibility consists of putting them in a cupboard
which is purged by dry gas. The same precautions shall be taken for
removable components, which if they need to be greased, shall be treated
with a chlorofluorinated grease.
8. CERTIFICATION
9. INSTALLATION
10. COMMISSIONING
After installation, the valve shall be subjected to a final operation of drying out
and leak testing as laid down in paragraph 5 of GEST 80/84 – Code of Good
Practice for the Commissioning of Installations for Dry Chlorine Gas and
Liquid.
11. REFERENCES
Euro Chlor
Avenue E Van Nieuwenhuyse 4
Box 2
B-1160 Brussels
Belgium