Unit Cost Analysis
Unit Cost Analysis
Project : Quantity: 50
Scope of Work : Units: sq.m
MATERIALS
ITEM NAME AND DESCRIPTION OF MATERIAL QUANTITY UNIT
1 Portland Cement 5 bag
2 Sand 1 cu.m
3 Gravel - G1 1.5 cu.m
4 Caution Tape 3"x 300m 1 ln m
5 RSB 8mm dia. (Grade 33 - 6m) 12 pcs
6 Tie wires 5 roll
7 PVC - 4'' pcs
8
9
MANPOWER
ITEM DESIGNATION OF PERSONNEL NO. OF MEN NO. OF HOURS
1 Civil Engineer 1 8
2 Foreman 1 8
4 Operator 1 8
5 Skilled 2 8
6 Labor/ Helper 4 8
MANPOWER (PAKYAWAN)
ITEM DESIGNATION OF PERSONNEL NO. OF MEN NO. FINISHED
1 Excavator 1 50
2 Chamber 1 50
3 Top slab 1 50
1433.673
1200
HOURLY RATE AMOUNT
150 600
150 600
0
0
0
0
29200
UNIT COST AMOUNT
700 5600
900 7200
650 5200
700 11200
500 16000
225000
UNIT COST AMOUNT
1000 50000
1500 75000
2000 100000
271170
270000
541170
10,823.41