BILL OF MATERIALS FOR OPEN TRENCH AS PER LINEAR METER

Project:
Location: Quantity: 250
Owner: Units: m
Subject: Total Cost 40000

SUMMARY
ITEM NO. DESCRIPTION QTY. UNIT UNIT COST
A. EARTHWORKS
A.1 Excavation 0.16 cu.m 1000
A.2 FineSand/Sand Bedding (Encasement) 0.03 cu.m
A.3 Backfill/Compaction (Native soil) 0.11 cu.m

B. CONCRETING WORKS
B.1 Concrete Protection (100mm thk) - 2000 psi 0.02 cu.m
B.1.1 Portland Cement 40kgs bags
B.1.2 Sand cu.m

C. MISCELLANEOUS MATERIALS
Caution tape 2" 1 roll

TOTAL COST PER LINEAR METER


250
m
40000
linear meter 1m
Cross-sectional Area 0.8 0.2
AMOUNT encasement area 0.15 0.2
Backfill 0.55 0.2
160 concrete prot 0.1 0.2
0
0

0
0
0
0
0

160
BILL OF MATERIALS AS PER SINGLE HANDHOLE
Project: FIBERNET KONSTRUKT CORP.
Location: Mabalacat City NO. OF HH: 25
Owner: Sunwuk Choi TOTAL COST: 496,971
Subject: SINGLE HANDHOLE With High Water Table

SUMMARY
ITEM NO. DESCRIPTION QTY. UNIT UNIT COST AMOUNT
A. EARTHWORKS
A.1 Excavation 3.2 cu.m 1,000 3,200
A.2 Backfill/Compaction 2.16 cu.m 0
A.3 G1 Gravel Bedding - 50mm thick 0.11 cu.m 1,100 121

B. CIVIL WORKS
B.1 Reinforced steel bars
B.1.1 16mm Ø x 6m - G33 6 pcs 425 2,550
B.1.2 12mm Ø x 6m - G33 3 pcs 230 690
B.1.3 Tie Wire no.16 - 25kg 1 roll 1,850 1,850

B.2 Concrete works


B.2.1 Chamber Foundation, Top Slab (3500 psi) 0.91 cu.m
B.2.1.1 Portland Cement 40kgs 9 bags 250 2,250
B.2.1.2 Sand 0.46 cu.m 700 320
B.2.1.3 Gravel G1 0.91 cu.m 1,100 1,004

B.2.2 Dry Pack/Dry Mix (1:5) - cu.m


B.2.2.1 Portland Cement 40kgs - bags 250 0
B.2.2.2 Fine Sand - cu.m 900 0

B.2.3 Concrete Mix if w/ High water table (1:3:4) 1.4 cu.m


B.2.3.1 Portland Cement 40kg 13 bags 250 3,250
B.2.3.2 Sand 1.05 cu.m 700 735
B.2.3.3 Gravel G1 1.4 cu.m 1,100 1,540

B.3 Formworks
B.3.1 Phenolic 3/4 (Top Slab) - 4' x 8' 1 pcs 1,074 1,074
B.3.2 Marine plywood 1/2 - 4' x 8' 1 pcs 750 750
B.3.3 Coco Lumber 3" x 2" x 8' 2 pcs 125 250

C. MISCELLANEOUS MATERIALS
C.1 PVC Pipe 4'' x 3m 0.5 pcs 310 155
C.2 PVC Pipe 2" x 3m 1 pcs 140 140

TOTAL COST PER HH: 19,879

Prepared By:
Engr. Adrean Dineros
Top Slab/ Chamber Found vol t; 0.913
Concrete Class Mix A

Cement
Class Sand Gravel Comp.
40 50 Str.
AA 12 9.5 0.5 1 4000
A 9 7 0.5 1 3500
` B 7.5 6 0.5 1 2500
C 6 5 0.5 1 2000

Reinforced Steel bar


Ø16mm by 6m T length 28.063 m
Ø12mm by 6m T length 6.3 m

Dry Pack 1:5 40kg ratio 1.4


Cement: 7.5 1
Fine Sand: 1 5

Coco Lumber Total Length : 11.708 m


Phenolic board: 2.0489 sq.m

Cement Density
1440 kg/m3

Concrete mix 1.4 cu.m


Concrete Mix
1 3 4
BILL OF MATERIALS AS PER COMBINED HANDHOLE
Project: NO. OF CHH: 15
Location: TOTAL COST: 499,987
Scope of Work: COMBINED HANDHOLE

SUMMARY
ITEM NO. DESCRIPTION QTY. UNIT UNIT COST AMOUNT
A. EARTHWORKS
A.1 Excavation 5.73 cu.m 1,000 5,731
A.2 Backfill/Compaction 2.53 cu.m 0
A.3 G1 Gravel Bedding - 50mm Thick 0.19 cu.m 915 175
A.3 G1 Gravel Bedding - 130mm thick (at duct protection) 0.09 cu.m 915 87

B. CIVIL WORKS
B.1 Reinforced steel bars
B.1.1 16mm Ø x 6m - G33 13 pc 425 5,525
B.1.2 12mm Ø x 6m - G33 4 pc 230 920
B.1.3 Tie Wire no.16 - 25kg 2 kg 1,500 3,000

B.2 Concrete works


B.2.1 Chamber Foundation, Top Slab (3500 psi) 1.70 cu.m
B.2.1.1 Portland Cement 40kgs 16 bags 250 4,000
B.2.1.2 Sand 0.85 cu.m 700 595
B.2.1.3 Gravel G1 1.70 cu.m 1,100 1,871

B.2.2 Dry Pack/Dry Mix (1:5) 0.41 cu.m


B.2.2.1 Portland Cement 40kgs 3 bags 250 750
B.2.2.2 Fine Sand 0.41 cu.m 900 372

B.2.3 Concrete Mix if w/ High water table (1:3:4) 1.84 cu.m


B.2.3.1 Portland Cement 40kg 17 bags 250 4,250
B.2.3.2 Sand 1.38 cu.m 700 963
B.2.3.3 Gravel G1 1.84 cu.m 1,100 2,019

B.3 Formworks
B.3.1 Phenollic -3/4" 4'x8' (Top Slab) 1 pcs 900 900
Marine Plywood 1/2" 4'x8' (Half/Full Moon) 2 pcs 750 1,500
B.3.2 Coco Lumber 2"x3"x8m 2 pcs 125 250

B.4 Miscellaneous Materials


B.4.1 PVC Pipe 4'' x 3m 0.5 pcs 310 155
B.4.2 PVC Pipe 2" x 3m 1 pcs 140 140
B.4.3 PVC Pipe 4" elbow 2 pcs 65 130

TOTAL COST PER COMBINED HH: 33,332

Prepared by:
Engr. Adrean Dineros
3500 psi Total Vol. 1.7 cu.m
SPECIFIED CLASS: A
Concrete mixture
Cement
Class Sand Gravel
40 50 Comp. Str.
AA 12 9.5 0.5 1 4000 1 1.5 3
A 9 7 0.5 1 3500 1 2 4
B 7.5 6 0.5 1 2500 1 2.5 5
C 6 5 0.5 1 2000 1 3 6

Reinforced Steel bar


Ø16mm by 6m T length 66.685 m

Ø12mm by 6m T length 16.05 m

Dry Pack 1:5 2.4 cu.m ratio 0.4134


Cement: 6 1
Fine Sand: 1 5

Coco Lumber Total Length : 11.708 m


Phenolic board: 3.3308 sq.m
Marine Ply 2.334 sq.m
Cement Density
1440 kg/m3

Concrete mix 1.835 cu.m


Concrete Mix
1 3 4