Professional Documents
Culture Documents
04.introduction To Residential Rov - New Concept of Rov For Oil and Gas Activities
04.introduction To Residential Rov - New Concept of Rov For Oil and Gas Activities
INTRODUCTION TO RESIDENTIAL ROV: NEW CONCEPT OF ROV FOR OIL AND GAS
ACTIVITIES
Husnul Furqon*
Muhammad Iqbal*
Yulian Mahendra*
Driven by described challenges, strong need of Most of residential ROV is manufactured almost
innovation for unlocking the current growth potential identical with non – residential ROV, consist of:
of ROV become one of solution key to be achieved.
Resident systems, which is actually is not a new 1. ROV
concept for some subsea equipment, is developed to
enhance an existing ROV systems by submerging it The scheme diagram of R-ROV equipment
on seabed, called Residential ROV (R-ROV), illustrated in figure 3.
described in the next following sections.
a. Mechanical, Manipulator and Thruster
Before ROV is implemented with resident systems, Properties
several observation class Autonomous Underwater R-ROV is equipped with ultra-compact solid
Vehicles (AUV) is developed for light inspection frame and buoyancy structure similar to non-
maintenance repair (IMR) and inspection task. residential ROV. This ultra-compact size
Commencing intervention task still become a great enhances a power performance correspondence
challenge for this vehicle as it can carry out light with its size ratio. Those are manufactured
intervention task. within certain depth ratings depending on its
class and purposes. This system also provided
The paper is organized as follows. Section II contains with rugged – manipulators requiring less –
the concept of R-ROV then in section III we describe maintenance as resident systems requirement for
the field of its operation, continue to section IV for staying submerged longer in seabed. Glycol, a
its installation method, while last two sections show hydraulic fluid used for this manipulator
the field test results, and conclusions about replacing less environmentally friendly oil.
residential ROV. Electrical thrusters are also provided to meet its
green design. To prolong staying submerged in
SYSTEM CONCEPT AND TECHNICAL seabed, corrosion protection is needed by
SPECIFICATION utilizing aluminum anodes, which are more
reliable and effective than zinc, and considered
Similar to the previous system, Figure 2 describes R- low Hydrogen Induced Stress Cracking (HISC).
ROV system consisting of several equipment; The requirement mass of anodes for protection is
calculated according to DNV-RP-B401.
a. R-ROV, as main system for task execution.
b. Hydraulic Unit
b. Tether Management System (TMS), for Some R-ROV intervention equipment units are
managing ROV tether / umbilical during in the hydraulic powered. This hydraulic unit is
sea for ROV previous system. On R-ROV different with non – resident systems due to oil –
system this equipment is replaced by E-Cage for analyzer installed on this vehicle. A hydraulic
its docking garage. fluid is continuously being monitored for its
quality according to ISO 4406 standard. It is also
c. Winch. This equipment usually is installed featured with internal flushing, to enhance the
together with E-Cage for managing the filtration of oil if it is dropped below its standard.
umbilical. The length usually up to 1 kilometer, Another customization for this vehicle is adding
spooled on the winch drum. two hydraulic hot stabs receptacles, which are
one for high flow tooling and another for low retrieval data and immediate emergency control
flow tooling. These receptacles permanently during hazardous conditions. This link can be
mounted on specially designed bracket on one of installed either with wireless configuration via
vehicle manipulator. satellite or wired subsea fiber cables, or both of
them at the same time to increase the system
c. Electronics and Sensors redundancy. To reduce time latency caused,
Identical with non – resident system ROV, R- similar to non-resident systems, this R-ROV is
ROV is installed with several lights, including a minimizing the processing algorithm on subsea
dimmable one. Electrical pan and tilt unit with side, meanwhile on topside, processing all R-
color zoom camera and low light camera ROV video, sensors data and acknowledgement
purposed as a main screen for pilot, also several signal are processed on topside controller.
cameras for viewing other perspective of R-ROV
itself. To help it navigate, this vehicle is provided 2. Docking, Launch and Recovery System
with a fiber optical gyro giving R-ROV
orientation information. To perceive an R-ROV As requirement for staying submerged in seabed, R-
surrounding environment, along with ROV launch and recovery equipment are specially
unidentified objects, sound propagation based designed similar to parking system, purposing as
sensor is provided and depth sensor for obtaining garage and tether management system for R-ROV
a depth information calculated from mean sea itself, developed fully electric, enabling remote
level. All installed R-ROV sensor data are controlling from control center, also fitted with
transmitted into subsea controller, usually several cameras to inspect components of R-ROV,
located on its control pod processed to providing seen in Figure 5.
its auto functions, such as at auto heading, auto
depth, auto attitude, and dynamic positioning OPERATION CAPABILITIES
system to maintain an ROV position during
unflavored conditions. Furthermore, this control Most of R-ROV is applied for upstream operation,
pod also transmitting actuation command to especially for facilities purpose, which have its phase
controlling the R-ROV movement via thrusters sequence as illustrated in Figure 4. All of subsea
configured and manipulators for intervention facilities operation can be covered, thus this system
task. Some additional sensors are installed for can be installed permanently for the first time since
enhancing navigation purpose such as ultra-short the project is started. In the following, we review in
base line, together with beacon transponder for more detailed selected tasks within its sequences.
positioning purpose to obtaining global earth
position in form of latitude and longitude. Survey
For first time project started, R-ROV is capable
d. Communication and Software Interfaces carrying various survey task within a long period
To establish the communication between topside when it is necessary. This system is more benefit
control center and subsea side and transmit the when emergency survey needs to be carried on,
transmission signal within certain time and its such as suspected leak hull inspection, mine trap
acknowledgement whether the signal has been indicated on seabed survey. The equipment used
transmitted or vice versa by determining its for survey is identical with previous system.
round trip latency to determine the quality of High resolution imaging sonar, either single
transmission signal between R-ROV and the beam or multi beam, several underwater
control center, especially in far distance, cameras, and imaging lasers are main equipment
Ethernet control system, in addition with fiber for this task, with additional acoustic resonance
network providing high bandwidth low latency equipment can be used for more detailed state,
is required enabling less video conversion and such as wall thickness of structures, hulls and
less number of conductor cables. From control pipes, or chemical sensor and optical for leakage
center, an Ethernet network is specially detection.
designated with specified IP address using
TCP/UDP protocol used for R-ROV remote Drilling and Exploration
control. This network configuration also applied This phase involved with a high risk operation,
with subsea side, shown in Figure 4. For link especially with riser connection on seabed floor,
establishment, a dedicated fiber network equal to which R-ROV primarily serves activity
4G LTE Mobile Broadband system for offshore monitoring on seabed, such as casing spud in
vessel and rigs is provided enabling instant survey, and to take pre cautious if it has some
fluid leakage occurred, either on riser above, and additional 10,000 psi Hydraulic
connection, Blowout Preventer (BOP), or Power Unit to deliver pressure to hot-stab
wellhead itself, and bubbles on seabed floor, since it uses a different fluid. The main
especially in deep water applications, even well advantage of R-ROV, these equipment
control is still enough to prevent any leakage due exclude FLOT and Torque tool are already
to high pressure activities from topside. The become of its main part, with additional
equipment used mostly identical during survey features, which are reviewed in last chapter
activities. II.
Completions, Installation, and Commissioning Completions phase is done when all testing
After being drilled, offshore wells must be procedures on X-Tree is completed and R-ROV is
completed with variety subsea equipment to already put an X-Tree Inner Tree Cap, BOP and
allow oil and gas be produced. Referring to tubing hanger retrieval, indicating well is ready for
components zone installation by R-ROV, production stage, in addition with Subsea Production
completion task is divided by two, Systems (SPS). This SPS is constructed with these
required components Subsea Drilling Systems,
a. Lower Completions Subsea X-Tree and Wellhead (these two components
Since it happens in well across the are already mentioned in previous), Umbilical and
production or injection zone, not many task riser system, Subsea Structure (Pipeline End
are carried on by R-ROV. For preparation to Termination / Pipeline End Manifold and Inline
commencing this phase, R-ROV needs to Structure, Subsea Manifold, Jumper), Subsea Tie-In
remove tree cap in Wellhead letting BOP and flowline System, and its control system. These
and Subsea Christmas Tree (X-Tree) latched components are divided into several subsea tasks in
into Wellhead and report to topside once it is order to install them. In Table 3, general subsea task
completed. R-ROV remain stand by at are listed and ROV quantity requirement minimum
docking station, and require immediate needed.
preparation if emergency situation
happened. Once this phase is finished, R- Production
ROV goes back to well location to Most of commercial ROV are being used in this
monitoring BOP retrieval from wellhead phase. This phase referred to Inspection,
while X-Tree is permanently residing on top Maintenance, and Repair (IMR) activities, either
of wellhead, then install back a wellhead tree on offshore facilities (i.e. rig, platform) or subsea
cap, then prepare for next task. production facilities (i.e. pipeline, subsea
structure) to maintain the effectiveness of oil
b. Upper Completions and gas production system, either on sea
After conduct several well testing and well surface or seabed. With R-ROV featured on
stimulation inside pre-production well, this phase, regular inspection and preventive
several preparations needed in order to maintenance can be carried out. The authors
complete this phase. This phase consist of divide these activities into several works types,
several Intervention and Work Over Control shown in Table 4.
System (IWOCS) tasks need to be done by
R-ROV. After tubing hanger and BOP Decommissioning
landed on X-Tree, verifying all electrical and All activities from this phases mostly identical
hydraulic connections from subsea riser to with the previous phases, only with a different
X-Tree. Nowadays for subsea application, purpose, such as subsea riser flowline removal,
subsea X-Tree is developed integrated with pipeline decommissioning, offshore loading
ROV valve interface and hot stab port. buoys removal, pipeline cutting operations. R-
During this phase, R-ROV manipulator ROV carried out all the operations in seabed
capability is tested through opening and while crane lifting operation still required in
closing X-Tree valves and 5000 psi hot stab order to lift the equipment from seabed into the
injection using non-hydrocarbon fluid surface.
glycol, for testing purpose. So, rugged
manipulator with most of degree of freedom Based on previous statement, in general the
required with some additional completion task can be carried out by R-ROV is similar
tools, i.e. Flying Lead Orientation Tool with the previous system, with additional
(FLOT) with Torque Tool Class 1-4 or advantage,
1. Reduce a number of offshore crews, while enter the installation phase. ROV perform
keeping full ROV crews team at control touchdown monitoring until the system is landed
center, increasing project efficiency by on seabed and dive bench test need to be
accommodation saving, travel cost, weather performed, making all system online and function
independent. properly. R-ROV requires real-time condition
monitoring after installation to maintain its
2. Provide an immediate “on – site” technical utilization, illustrated in Figure 9.
support solution. Offshore crews and
onshore crews can discuss in a same building FIELD INSTALLATION RESULTS
to achieve a real – time solution.
The authors use IKM Subsea Merlin UCV to present
3. In emergency situation, ROV can be the R-ROV installation test results in 14 January
controlled from onshore center for minimum 2018. This system submerged permanently on 345
casualties occurred. This is can be done meters water depth at Statoil’s Snorre B platform,
because ROV pilots can easily toggle ROV referred in Figure 7 and recovered after every 3rd
control between 2 or more different control months for regular maintenances. Closed loop round
stations at once. trip latency from input to feedback control consist of
encoding, decoding and debugging the IP based
INSTALLATION SCHEME AND video and output control signals to R-ROV between
PROCEDURE the system and onshore control center is being
monitored due to main considerations of the system.
In resident systems, power supply source and Table 5 gives the R-ROV installation results, while
communication are items that need to be the R-ROV example of light intervention operation
considered during system installation. In this paper can be shown in Figure 10. The results above still
referred to IKM Subsea R-ROV installation report indicated a high latency causing a delay during video
in Snorre field, Snorre B rig power supply is being and signal transmission which can be improved and
used to erect the system. Communication is served as a benchmark for references in a future.
established between this system with rig using
wired fiber network on umbilical and IKM Subsea CONCLUSION
Bryne onshore control center using dedicated fiber
network, connected from shore, creating A field installation results was described above to
redundancy system toggling the control scheme explain a new concept of ROV towards resident
between onshore control center and rig / platform system giving more advantages from technical and
control. Back- up ROV non-resident systems economic terms, since it can be operated
(Work Class Merlin WR 200, Work Class UCV, immediately, through availability of ROV asset
and Observation Class Seaeye tiger ) are provided onsite and reduction in weather dependency based
to support R-ROV installation and perform the operations and HSE risk possibility occurred, leading
operation task given if R-ROV has issues, which to safer operations and cost reductions due to
are two ROVs are installed in Visund rig, the other operation loss time and logistic issues. The high
is in same rig, shown in Figure 7. Similar latency results still become a major and can be
approaching the way of SPS installation can be reduced in a future and served as a reference for oil
used in order to operate this equipment. In this and gas industries, especially for ROV itself
paper, the installation procedure is shown at
flowchart Figure 8. The sequences processes REFERENCES
installation taken after R-ROV is mobilized from
workshop after being prepared and tested. As Petter Bryn, Lars & Muller, G. (2017). Evolving
arrival on location site, pre-installation seabed tolerance management for increased robustness of
survey is mandatory in order to determine system subsea installation operations. INCOSE International
location. This survey can be done by existing ROV Symposium. 27. 242-256. 10.1002/j.2334-
and several requirements need to meet, such as 5837.2017.00357.x.
adequate space flat seabed floor with system
Liljebäck, Pål, Mills, Richard (2017). Eelume: A
footprint size as reference, clearance from other
Flexible and Subsea Resident IMR Vehicle
equipment or sea cliff and operation range
surrounding the SPS. Before start the installation, DNV GL Oil and Gas. (2014). Subsea Facilities –
final inspection to the system and bench test Technology Developments, Incidents, and Future
needed to be done ensuring all system is ready to Trends. Report No. 2014-0113, Rev. 03.
Furuholmen, Marcus & Hanssen, Alfred & Carter, R Weller, Robert A., Lund John, O’Brien Jeff, Kemp
& Hatlen, K & Solutions, Aker & Siesjo, J. (2013). John, Kostel, Ken, Waldorf, Walt, Holm, Christ,
Resident autonomous underwater vehicle systems – Risien Crag, Matthewson, Michael, Trowbridge,
a review of drivers, applications, and integration John. (2012). WHOI – 2012 – 07 Technical Report.
options for the subsea oil and gas market. Offshore OOI CGSN 3207 – 0034
Mediterranean Conference. Volume Technologies
for the Future 2. Norwegian Technology Centre. (2003). Norsok
Standard U - 102 Remotely Operated Vehicles
(ROV) Services Rev. 1, October 2003.
TABLE 1
TABLE 2
TABLE 3
Pull-in, Cross-haul 1 1
Tie-Ins 2 1
Hydro test 2
TABLE 4
R-ROV TASK CLASSIFICATION DURING OIL AND GAS PRODUCTION STAGE (ADAPTED
FROM FURUHOLMEN ET. AL (2013))
o Seabed survey
o 3D scanning
o Radioactivity monitoring
o Seabed mapping
o Sand detection
flying leads
o Advanced manipulation
o SPS repair
TABLE 5
System Installation Method Crane lifting operation with buoyancy handling and automatic
spacing.
Figure 1 -Typical Commercial ROV Operation Environment (Long Beach School District, adapted from
Oceaneering)
E‐Cage TMS
R‐ROV
E‐Winch
Figure 3 - R-ROV equipment scheme diagram (IKM Subsea AS)
Switch
10.3.0.2
Cisco Router NAS
Sonic Wall Router
10.3.0.1 10.3.0.8 Printer 10.3.0.5 PLC/SCADA HMI Pilot T4 Moxa Pilot HMI Co‐Pilot T4 Moxa Co‐Pilot
10.3.0.9
10.3.0.40 10.3.0.70 10.3.0.71 10.3.0.75 10.3.0.76
Top side
Subsea
Fiber
Internet for remote Multiple networks
control
Figure 4 - Network communication for video and data retrieval scheme diagram (IKM Subsea AS)
Figure 5 - R-ROV E-Cage Docking, Launch and Recovery Equipment (IKM Subsea AS)
Completion, Installation,
Survey Drilling and Exploration Production Decommissioning
and Commissioning
Figure 7 - R-ROV installation scheme on vessel / rig / platform (IKM Subsea AS)
Start
1
Pre‐installation seabed survey by existing ROV
System lifting preparation, hooked to lifting
crane
Determine an system location from survey data
result
no
Is the system lifting
points secured? 2
yes
Is the location suitable
for system installation? no
Identify and troubleshoot
the system problem on the Begin to lift down the system into seabed Release the system lifting hook by existing ROV
yes surface
no
yes
End
Is the problem solved Arrive on seabed, perform dive bench test
Perform surface bench test
during diving?
Identify and troubleshoot no
Is the system function no Identify and troubleshoot Is the system online
the system problem during
properly? the system problem during diving?
submerged on seabed
1 2
Figure 9 - R-ROV installation scheme, Crane lifting operation (left), Rig and R-ROV installation positioning
(right) (IKM Subsea AS)
Figure 10 - R-ROV commence Lower Marine Riser Package (LMRP) valves operation (IKM Subsea AS)