Download as pdf or txt
Download as pdf or txt
You are on page 1of 14

IPA18-588-F

PROCEEDINGS, INDONESIAN PETROLEUM ASSOCIATION


Forty-Second Annual Convention & Exhibition, May 2018

INTRODUCTION TO RESIDENTIAL ROV: NEW CONCEPT OF ROV FOR OIL AND GAS
ACTIVITIES

Husnul Furqon*
Muhammad Iqbal*
Yulian Mahendra*

ABSTRACT Keywords: Remotely Operated Vehicle, Resident


Systems, Residential ROV, Round-trip latency
Currently, the requirements of advanced
technologies for oil and gas operation becomes very INTRODUCTION
much the focus of Subsea Operators and Clients
alike. Remotely Operated Vehicle (ROV), subsea Remotely Operated Vehicle (ROV), an underwater
technologies that currently used in a variety of remote controlling and sensing device require
applications, including oil and gas activities, is sophisticated technologies as offshore task
looking for a new concept that can be integrated field difficulties are increasing, including oil and gas
support and demand of industry pushing towards activities (Figure 1). As technology advances, subsea
resident systems enabling rapid development and industry, as well for ROV industry is facing toward
addressing the various technology gaps and great prospects with great challenges. Several
challenges, from the perspective of both from constraints toward ROV development due to its
operational and cost issues. These lead to introduce a harsh environment and mostly located in remote
different approach to ROV System, called area, requiring higher standards of ROV and its
Residential ROV (R-ROV). This system provides operation procedures. Several challenges face by the
permanent installation on the seabed for long time previous ROV system, are reviewed in the following,
periods. By “parking” it on the seabed, operational
time is being increased significantly, meanwhile, a 1. Logistical Cost, such as travel and
requirement time of deployment is none and not accommodation. These are affect into a high
weather dependent anymore. Furthermore, there is amount of operational expenditures. Amount of
no splash zone during launch and recovery operation. non – resident systems installation also
It also reduces offshore crewing due to onshore determined by the overall dimension
operation from control station center via Tampnet, a requirement of system itself, number of system
dedicated fiber-based network system that equals to requirement (main system and back-up system)
operate on a 4G mobile broadband system, and the size of vessel. In addition, consumables
meanwhile, as for docking, it uses an existing items, such solar for generator for power supply
method. For another subsea scope of work, the become most main cost issue.
requirement of support vessel is being reduced. This
new concept able to work out until 1000 meters 2. Operation and Human Safety Environmental
radius and is supported with a new trend of ROV Risk. Non-resident systems has high risks
electrification, which is electrical power designed operation, especially during launch and recovery
with a new communication method based on operation due to weather dependent and ‘splash
previous statement. The new concept also comes zone’. Also number of crews on board in vessel
with a new challenges in order to controlling the also contribute to increasing risk. Table 1 shows
R-ROV real-time due to its round-trip latency,. number ROV crew requirements according to
This major challenges served as a benchmark that Norsok Standard U-102 2013.
can be improved in the future. In the end, this
3. Mobilization time. To install this system, it
system represents the future of ROV technology
requires amount of days due to weather
for safer operations and cost reductions for the
dependent and availability of equipment and
industry, especially for oil and gas companies.
personnel.

* IKM Subsea Indonesia


 
4. Emergency Response Action. It needs a time to d. Buoy Surface Communication Equipment, an
react until it is ready to commence an operation additional equipment for remote areas to
if something happens that require fast response, establish the communication between R-ROV
so, winch capability become a vital part in order system and onshore control center.
to satisfy this condition. In Table 2 present some
ROV and its manufacturers with its winch As described above, the previous system is
capabilities according to their specification. distinguished with another main equipment, control
container as control center for ROV, which can
5. Data Retrieval and Immediate Onshore Visual. installed as main control center complement with
No real-time data transmitting from offshore site onshore control center and can override each other,
to onshore. System black box will record all purposed giving R-ROV a command control and data
operation activities then collected once the retrieval from it. The communication method is
project is done. described in installation method.

Driven by described challenges, strong need of Most of residential ROV is manufactured almost
innovation for unlocking the current growth potential identical with non – residential ROV, consist of:
of ROV become one of solution key to be achieved.
Resident systems, which is actually is not a new 1. ROV
concept for some subsea equipment, is developed to
enhance an existing ROV systems by submerging it The scheme diagram of R-ROV equipment
on seabed, called Residential ROV (R-ROV), illustrated in figure 3.
described in the next following sections.
a. Mechanical, Manipulator and Thruster
Before ROV is implemented with resident systems, Properties
several observation class Autonomous Underwater R-ROV is equipped with ultra-compact solid
Vehicles (AUV) is developed for light inspection frame and buoyancy structure similar to non-
maintenance repair (IMR) and inspection task. residential ROV. This ultra-compact size
Commencing intervention task still become a great enhances a power performance correspondence
challenge for this vehicle as it can carry out light with its size ratio. Those are manufactured
intervention task. within certain depth ratings depending on its
class and purposes. This system also provided
The paper is organized as follows. Section II contains with rugged – manipulators requiring less –
the concept of R-ROV then in section III we describe maintenance as resident systems requirement for
the field of its operation, continue to section IV for staying submerged longer in seabed. Glycol, a
its installation method, while last two sections show hydraulic fluid used for this manipulator
the field test results, and conclusions about replacing less environmentally friendly oil.
residential ROV. Electrical thrusters are also provided to meet its
green design. To prolong staying submerged in
SYSTEM CONCEPT AND TECHNICAL seabed, corrosion protection is needed by
SPECIFICATION utilizing aluminum anodes, which are more
reliable and effective than zinc, and considered
Similar to the previous system, Figure 2 describes R- low Hydrogen Induced Stress Cracking (HISC).
ROV system consisting of several equipment; The requirement mass of anodes for protection is
calculated according to DNV-RP-B401.
a. R-ROV, as main system for task execution.
b. Hydraulic Unit
b. Tether Management System (TMS), for Some R-ROV intervention equipment units are
managing ROV tether / umbilical during in the hydraulic powered. This hydraulic unit is
sea for ROV previous system. On R-ROV different with non – resident systems due to oil –
system this equipment is replaced by E-Cage for analyzer installed on this vehicle. A hydraulic
its docking garage. fluid is continuously being monitored for its
quality according to ISO 4406 standard. It is also
c. Winch. This equipment usually is installed featured with internal flushing, to enhance the
together with E-Cage for managing the filtration of oil if it is dropped below its standard.
umbilical. The length usually up to 1 kilometer, Another customization for this vehicle is adding
spooled on the winch drum. two hydraulic hot stabs receptacles, which are

 
one for high flow tooling and another for low retrieval data and immediate emergency control
flow tooling. These receptacles permanently during hazardous conditions. This link can be
mounted on specially designed bracket on one of installed either with wireless configuration via
vehicle manipulator. satellite or wired subsea fiber cables, or both of
them at the same time to increase the system
c. Electronics and Sensors redundancy. To reduce time latency caused,
Identical with non – resident system ROV, R- similar to non-resident systems, this R-ROV is
ROV is installed with several lights, including a minimizing the processing algorithm on subsea
dimmable one. Electrical pan and tilt unit with side, meanwhile on topside, processing all R-
color zoom camera and low light camera ROV video, sensors data and acknowledgement
purposed as a main screen for pilot, also several signal are processed on topside controller.
cameras for viewing other perspective of R-ROV
itself. To help it navigate, this vehicle is provided 2. Docking, Launch and Recovery System
with a fiber optical gyro giving R-ROV
orientation information. To perceive an R-ROV As requirement for staying submerged in seabed, R-
surrounding environment, along with ROV launch and recovery equipment are specially
unidentified objects, sound propagation based designed similar to parking system, purposing as
sensor is provided and depth sensor for obtaining garage and tether management system for R-ROV
a depth information calculated from mean sea itself, developed fully electric, enabling remote
level. All installed R-ROV sensor data are controlling from control center, also fitted with
transmitted into subsea controller, usually several cameras to inspect components of R-ROV,
located on its control pod processed to providing seen in Figure 5.
its auto functions, such as at auto heading, auto
depth, auto attitude, and dynamic positioning OPERATION CAPABILITIES
system to maintain an ROV position during
unflavored conditions. Furthermore, this control Most of R-ROV is applied for upstream operation,
pod also transmitting actuation command to especially for facilities purpose, which have its phase
controlling the R-ROV movement via thrusters sequence as illustrated in Figure 4. All of subsea
configured and manipulators for intervention facilities operation can be covered, thus this system
task. Some additional sensors are installed for can be installed permanently for the first time since
enhancing navigation purpose such as ultra-short the project is started. In the following, we review in
base line, together with beacon transponder for more detailed selected tasks within its sequences.
positioning purpose to obtaining global earth
position in form of latitude and longitude.  Survey
For first time project started, R-ROV is capable
d. Communication and Software Interfaces carrying various survey task within a long period
To establish the communication between topside when it is necessary. This system is more benefit
control center and subsea side and transmit the when emergency survey needs to be carried on,
transmission signal within certain time and its such as suspected leak hull inspection, mine trap
acknowledgement whether the signal has been indicated on seabed survey. The equipment used
transmitted or vice versa by determining its for survey is identical with previous system.
round trip latency to determine the quality of High resolution imaging sonar, either single
transmission signal between R-ROV and the beam or multi beam, several underwater
control center, especially in far distance, cameras, and imaging lasers are main equipment
Ethernet control system, in addition with fiber for this task, with additional acoustic resonance
network providing high bandwidth low latency equipment can be used for more detailed state,
is required enabling less video conversion and such as wall thickness of structures, hulls and
less number of conductor cables. From control pipes, or chemical sensor and optical for leakage
center, an Ethernet network is specially detection.
designated with specified IP address using
TCP/UDP protocol used for R-ROV remote  Drilling and Exploration
control. This network configuration also applied This phase involved with a high risk operation,
with subsea side, shown in Figure 4. For link especially with riser connection on seabed floor,
establishment, a dedicated fiber network equal to which R-ROV primarily serves activity
4G LTE Mobile Broadband system for offshore monitoring on seabed, such as casing spud in
vessel and rigs is provided enabling instant survey, and to take pre cautious if it has some

 
fluid leakage occurred, either on riser above, and additional 10,000 psi Hydraulic
connection, Blowout Preventer (BOP), or Power Unit to deliver pressure to hot-stab
wellhead itself, and bubbles on seabed floor, since it uses a different fluid. The main
especially in deep water applications, even well advantage of R-ROV, these equipment
control is still enough to prevent any leakage due exclude FLOT and Torque tool are already
to high pressure activities from topside. The become of its main part, with additional
equipment used mostly identical during survey features, which are reviewed in last chapter
activities. II.

 Completions, Installation, and Commissioning Completions phase is done when all testing
After being drilled, offshore wells must be procedures on X-Tree is completed and R-ROV is
completed with variety subsea equipment to already put an X-Tree Inner Tree Cap, BOP and
allow oil and gas be produced. Referring to tubing hanger retrieval, indicating well is ready for
components zone installation by R-ROV, production stage, in addition with Subsea Production
completion task is divided by two, Systems (SPS). This SPS is constructed with these
required components Subsea Drilling Systems,
a. Lower Completions Subsea X-Tree and Wellhead (these two components
Since it happens in well across the are already mentioned in previous), Umbilical and
production or injection zone, not many task riser system, Subsea Structure (Pipeline End
are carried on by R-ROV. For preparation to Termination / Pipeline End Manifold and Inline
commencing this phase, R-ROV needs to Structure, Subsea Manifold, Jumper), Subsea Tie-In
remove tree cap in Wellhead letting BOP and flowline System, and its control system. These
and Subsea Christmas Tree (X-Tree) latched components are divided into several subsea tasks in
into Wellhead and report to topside once it is order to install them. In Table 3, general subsea task
completed. R-ROV remain stand by at are listed and ROV quantity requirement minimum
docking station, and require immediate needed.
preparation if emergency situation
happened. Once this phase is finished, R-  Production
ROV goes back to well location to Most of commercial ROV are being used in this
monitoring BOP retrieval from wellhead phase. This phase referred to Inspection,
while X-Tree is permanently residing on top Maintenance, and Repair (IMR) activities, either
of wellhead, then install back a wellhead tree on offshore facilities (i.e. rig, platform) or subsea
cap, then prepare for next task. production facilities (i.e. pipeline, subsea
structure) to maintain the effectiveness of oil
b. Upper Completions and gas production system, either on sea
After conduct several well testing and well surface or seabed. With R-ROV featured on
stimulation inside pre-production well, this phase, regular inspection and preventive
several preparations needed in order to maintenance can be carried out. The authors
complete this phase. This phase consist of divide these activities into several works types,
several Intervention and Work Over Control shown in Table 4.
System (IWOCS) tasks need to be done by
R-ROV. After tubing hanger and BOP  Decommissioning
landed on X-Tree, verifying all electrical and All activities from this phases mostly identical
hydraulic connections from subsea riser to with the previous phases, only with a different
X-Tree. Nowadays for subsea application, purpose, such as subsea riser flowline removal,
subsea X-Tree is developed integrated with pipeline decommissioning, offshore loading
ROV valve interface and hot stab port. buoys removal, pipeline cutting operations. R-
During this phase, R-ROV manipulator ROV carried out all the operations in seabed
capability is tested through opening and while crane lifting operation still required in
closing X-Tree valves and 5000 psi hot stab order to lift the equipment from seabed into the
injection using non-hydrocarbon fluid surface.
glycol, for testing purpose. So, rugged
manipulator with most of degree of freedom Based on previous statement, in general the
required with some additional completion task can be carried out by R-ROV is similar
tools, i.e. Flying Lead Orientation Tool with the previous system, with additional
(FLOT) with Torque Tool Class 1-4 or advantage,

 
1. Reduce a number of offshore crews, while enter the installation phase. ROV perform
keeping full ROV crews team at control touchdown monitoring until the system is landed
center, increasing project efficiency by on seabed and dive bench test need to be
accommodation saving, travel cost, weather performed, making all system online and function
independent. properly. R-ROV requires real-time condition
monitoring after installation to maintain its
2. Provide an immediate “on – site” technical utilization, illustrated in Figure 9.
support solution. Offshore crews and
onshore crews can discuss in a same building FIELD INSTALLATION RESULTS
to achieve a real – time solution.
The authors use IKM Subsea Merlin UCV to present
3. In emergency situation, ROV can be the R-ROV installation test results in 14 January
controlled from onshore center for minimum 2018. This system submerged permanently on 345
casualties occurred. This is can be done meters water depth at Statoil’s Snorre B platform,
because ROV pilots can easily toggle ROV referred in Figure 7 and recovered after every 3rd
control between 2 or more different control months for regular maintenances. Closed loop round
stations at once. trip latency from input to feedback control consist of
encoding, decoding and debugging the IP based
INSTALLATION SCHEME AND video and output control signals to R-ROV between
PROCEDURE the system and onshore control center is being
monitored due to main considerations of the system.
In resident systems, power supply source and Table 5 gives the R-ROV installation results, while
communication are items that need to be the R-ROV example of light intervention operation
considered during system installation. In this paper can be shown in Figure 10. The results above still
referred to IKM Subsea R-ROV installation report indicated a high latency causing a delay during video
in Snorre field, Snorre B rig power supply is being and signal transmission which can be improved and
used to erect the system. Communication is served as a benchmark for references in a future.
established between this system with rig using
wired fiber network on umbilical and IKM Subsea CONCLUSION
Bryne onshore control center using dedicated fiber
network, connected from shore, creating A field installation results was described above to
redundancy system toggling the control scheme explain a new concept of ROV towards resident
between onshore control center and rig / platform system giving more advantages from technical and
control. Back- up ROV non-resident systems economic terms, since it can be operated
(Work Class Merlin WR 200, Work Class UCV, immediately, through availability of ROV asset
and Observation Class Seaeye tiger ) are provided onsite and reduction in weather dependency based
to support R-ROV installation and perform the operations and HSE risk possibility occurred, leading
operation task given if R-ROV has issues, which to safer operations and cost reductions due to
are two ROVs are installed in Visund rig, the other operation loss time and logistic issues. The high
is in same rig, shown in Figure 7. Similar latency results still become a major and can be
approaching the way of SPS installation can be reduced in a future and served as a reference for oil
used in order to operate this equipment. In this and gas industries, especially for ROV itself
paper, the installation procedure is shown at
flowchart Figure 8. The sequences processes REFERENCES
installation taken after R-ROV is mobilized from
workshop after being prepared and tested. As Petter Bryn, Lars & Muller, G. (2017). Evolving
arrival on location site, pre-installation seabed tolerance management for increased robustness of
survey is mandatory in order to determine system subsea installation operations. INCOSE International
location. This survey can be done by existing ROV Symposium. 27. 242-256. 10.1002/j.2334-
and several requirements need to meet, such as 5837.2017.00357.x.
adequate space flat seabed floor with system
Liljebäck, Pål, Mills, Richard (2017). Eelume: A
footprint size as reference, clearance from other
Flexible and Subsea Resident IMR Vehicle
equipment or sea cliff and operation range
surrounding the SPS. Before start the installation, DNV GL Oil and Gas. (2014). Subsea Facilities –
final inspection to the system and bench test Technology Developments, Incidents, and Future
needed to be done ensuring all system is ready to Trends. Report No. 2014-0113, Rev. 03.

 
Furuholmen, Marcus & Hanssen, Alfred & Carter, R Weller, Robert A., Lund John, O’Brien Jeff, Kemp
& Hatlen, K & Solutions, Aker & Siesjo, J. (2013). John, Kostel, Ken, Waldorf, Walt, Holm, Christ,
Resident autonomous underwater vehicle systems – Risien Crag, Matthewson, Michael, Trowbridge,
a review of drivers, applications, and integration John. (2012). WHOI – 2012 – 07 Technical Report.
options for the subsea oil and gas market. Offshore OOI CGSN 3207 – 0034
Mediterranean Conference. Volume Technologies
for the Future 2. Norwegian Technology Centre. (2003). Norsok
Standard U - 102 Remotely Operated Vehicles
(ROV) Services Rev. 1, October 2003.

 
TABLE 1

NUMBER OF CREW REQUIREMENTS CLASSIFICATION REGARDING THE ROV CLASS


USED (NORSOK STANDARD U-102, 2013)

Class Description Crew (12h) Crew (24h)


I Pure observation vehicles 2 4

II Observation vehicles with payload option 2 4

III Work class vehicles 3 6

IV Seabed working vehicles 4 8

TABLE 2

ROV AND ITS MANUFACTURER WINCH CAPABILITIES STATUS

ROV Manufacturer Winch Speed


Quarsar MK II SMD 50 meters per minute

Merlin WR 200 IKM Subsea AS 0-80 meters per minute

Magnum Oceaneering 30-60 meters per minute

TABLE 3

SPS INSTALLATION TASK WITH ROV / R-ROV REQUIREMENTS (ADAPTED


FROM DNV OIL AND GAS REPORT, 2014)

Subsea Task Working R-ROVs Observation R-ROVs

Lay Monitoring, A&R Activities 1 1

Subsea Structure Installation 2

Pull-in, Cross-haul 1 1

Tie-Ins 2 1

Hydro test 2

 
TABLE 4

R-ROV TASK CLASSIFICATION DURING OIL AND GAS PRODUCTION STAGE (ADAPTED
FROM FURUHOLMEN ET. AL (2013))

Task Subtask Specified IMR Task

Inspection General Visual Inspection o SPS inspection

o Seabed survey

o FPSO / Mooring inspection

o Oil and gas facilities inspection

o Touch down monitoring

Sensor-based Inspection o Thermal leak inspection

o Hydrocarbon leak detection

o 3D scanning

o Wireless sensor harvesting

o Radioactivity monitoring

o Seabed mapping

Contact Inspection o NDT measurement

o Pipeline stress measurement

o Cathodic Protection measurement

o Wall thickness measurement

o Sand detection

Intervention Light Intervention o Connect / disconnect electrical / hydraulic

flying leads

o Override remotely actuated valves

o Cleaning with water jet activity

Heavy Intervention o Component replacement

o Advanced manipulation

o SPS repair

 
TABLE 5

R-ROV INSTALLATION INFORMATION AND FIELD INSTALLATION RESULTS

Location Snorre Oil Field, Norwegian Sea, Norway

Vessel Snorre B Statoil

Remote Operation Distance ±384 km (starting from Bryne to vessel)

Communication Method via Tampnet dedicated fiber network

System Installation Method Crane lifting operation with buoyancy handling and automatic

release system, 40 metres from load with 6 of 55 kg

buoyancies 2.5 m spacing and 8 of 25 kg buoyancies 2.5 m

spacing.

Video latency 150 – 180 ms

Round trip latency 250 – 300 ms

 
Figure 1 -Typical Commercial ROV Operation Environment (Long Beach School District, adapted from
Oceaneering)

E‐Cage TMS 

R‐ROV 

E‐Winch 

Figure 2 - R-ROV system equipment (IKM Subsea AS)

 
Figure 3 - R-ROV equipment scheme diagram (IKM Subsea AS)

DVI Matrix Sonar PC Video Multiviewer 1 Multiviewer 2 Spare BlackBox


10.3.0.39 10.3.0.11 10.3.0.10 10.3.0.13 10.3.0.14 10.3.0.12 10.3.0.15 Moxa 16 channel
Patch Panel
10.3.0.41

Switch
10.3.0.2

Cisco Router NAS
Sonic Wall Router
10.3.0.1 10.3.0.8 Printer 10.3.0.5 PLC/SCADA HMI Pilot T4 Moxa Pilot HMI Co‐Pilot T4 Moxa Co‐Pilot
10.3.0.9
10.3.0.40 10.3.0.70 10.3.0.71 10.3.0.75 10.3.0.76
Top side

Subsea
Fiber

Internet for remote  Multiple networks
control

Figure 4 - Network communication for video and data retrieval scheme diagram (IKM Subsea AS)

 
Figure 5 - R-ROV E-Cage Docking, Launch and Recovery Equipment (IKM Subsea AS)

Completion, Installation, 
Survey Drilling and Exploration Production Decommissioning
and Commissioning

Figure 6 - Phase sequence of upstream subsea facilities operation

Figure 7 - R-ROV installation scheme on vessel / rig / platform (IKM Subsea AS)

 
Start
1

Pre‐installation seabed survey by existing ROV
System lifting preparation, hooked to lifting 
crane

Determine an system location from survey data 
result
no
Is the system lifting 
points secured? 2

yes
Is the location suitable 
for system installation? no
Identify and troubleshoot 
the system problem on the  Begin to lift down the system into seabed Release the system lifting hook by existing ROV
yes surface

Lift up the system back to  Perform touchdown monitoring while lifting  Post installation seabed survey by existing ROV 


System assembly and preparation surface down the system by existing ROV or the installed system

no
yes
End
Is the problem solved  Arrive on seabed, perform dive bench test
Perform surface bench test
during diving?

Identify and troubleshoot  no
Is the system function  no Identify and troubleshoot  Is the system online 
the system problem during 
properly? the system problem during diving?
submerged on seabed

1 2

Figure 8 -R-ROV installation procedure flowchart

Figure 9 - R-ROV installation scheme, Crane lifting operation (left), Rig and R-ROV installation positioning
(right) (IKM Subsea AS)

 
Figure 10 - R-ROV commence Lower Marine Riser Package (LMRP) valves operation (IKM Subsea AS)

You might also like