Maerial Log UPDATED

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

Green Riyadh, Water Tanks, Materials Log Total Duration in Days 74

Belad Al- Sham CONT. EST.

Project Start Date 9/30/2020 (Wednesday) Display Week 1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
Project Lead Mohamad Dabjan 28 Sep 2020 5 Oct 2020 12 Oct 2020 19 Oct 2020 26 Oct 2020 2 Nov 2020 9 Nov 2020 16 Nov 2020
DAY # 1 2 3 3 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54
28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Days to Recive
WBS TASK START END DAYS % DONE M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
Materials
1 Materials Mobilization -
1.1 N/A Mobilaization of Manpower Wed 9/30/20 Wed 9/30/20 1 0 1%
1.2 N/A Mobilaization of Equipments Wed 9/30/20 Wed 9/30/20 1 0 0%

2 Submital and Approval -


2.1 N/A Approval of Shop Drawings Wed 9/30/20 Wed 9/30/20 1 0 0%
3 Procurment -
3.1 N/A Procurment Process Wed 9/30/20 Wed 9/30/20 1 0 0%

4 Site Preparation -
4.1 N/A Site Preparation Wed 9/30/20 Wed 9/30/20 1 0 0%

5 Earthworks -
5.1 N/A Excavation Wed 9/30/20 Sun 10/04/20 5 0 0%

6 Concrete Works for Foundation -


Polyethylene Vapor Barrier
6.1 Anti-Termite treatment Pouring blind concrete 5 c.m Mon 10/05/20 Mon 10/05/20 1 5 0%
Concrete C25
4mm Roll of Bitumene membrane
6.2 Ground Insulation Tue 10/06/20 Wed 10/07/20 2 3 0%
Primer Layer
6.3 Concrete C25 Pouring blind concrete 5 c.m Thu 10/08/20 Thu 10/08/20 1 0 0%
6.4 Base Steel Bars Fixing the Rebars Fri 10/09/20 Sat 10/10/20 2 3 0%
6.5 Form Timber Form Work Sun 10/11/20 Sun 10/11/20 1 3 0%
6.6 Water stop rolls Installing water stop Sun 10/11/20 Sun 10/11/20 1 3 0%
6.7 Concrete C35 Pouring Concrete Mon 10/12/20 Mon 10/12/20 1 3 0%
7 Concrete Works for Walls -
Scaffolding Materials
7.1 Fixing Formwork from the outside Tue 10/13/20 Wed 10/14/20 2 3 0%
Form Work Tember
Tie Rods Tools
7.2 Fixing Rebars Thu 10/15/20 Sat 10/17/20 3 5 0%
Wall Steel Bars
7.3 N/A MEP works by the main contractor Sun 10/18/20 Sun 10/18/20 1 0 0%
Scaffolding Materials
7.4 Fixing Formwork from the inside Mon 10/19/20 Wed 10/21/20 3 0 0%
Form Work Tember
7.5 Concrete C35 Pouring Concrete Thu 10/22/20 Thu 10/22/20 1 0 0%
7.6 N/A Removing Form Work Fri 10/23/20 Fri 10/23/20 1 0 0%
4mm Roll of Bitumene membrane
7.7 Walls Insulation Sat 10/24/20 Mon 10/26/20 3 3 0%
Primer Layer
8 Concrete Works for Roof Slap -
Scaffolding Materials
8.1 Form Work and PlyWood Tue 10/27/20 Fri 10/30/20 4 3 0%
Timber
Tie Rods Tools
8.2 Roof Steel Bars Fixing the repars Sat 10/31/20 Sun 11/01/20 2 5 0%
Access Door Frames
8.3 N/A MEP works by the main contractor Mon 11/02/20 Mon 11/02/20 1 0 0%
8.4 Concrete C35 Pouring Concrete Tue 11/03/20 Tue 11/03/20 1 0 0%
9 Curing of Cover Slap -
Curing of Cover Slap and removing of
9.1 N/A Tue 11/03/20 Mon 11/16/20 14 0 0%
foam work
10 Insulation -
4mm Roll of Bitumene membrane Installing Walls Insulation (double
10.1 Tue 11/03/20 Thu 11/05/20 3 3 0%
Primer Layer Membrane layers of Bitumen)
4mm Roll of Bitumene membrane Installing Roof Insulation (double
10.2 Fri 11/06/20 Sat 11/07/20 2 4 0%
Primer Layer Membrane layers of Bitumen)
Cementitious
10.3 Installing cementitious Tue 11/17/20 Fri 11/20/20 4 4 0%
Grout
11 Backfilling -
11.1 SubBase Materials Backfilling Sun 11/08/20 Wed 11/11/20 4 3 0%
11.2 Aggregates Laying Agregates Sat 11/21/20 Sat 11/21/20 1 3 0%

12 Handover -
12.1 N/A Close Out Sun 11/22/20 Sun 11/22/20 1 0 0%
12.2 N/A Demobilaization Sun 11/22/20 Sun 11/22/20 1 0 0%

You might also like