DAFTAR HARGA SATUAN BAHAN

A. Harga Satuan Bahan

NO KODE NAMA BARANG MERK SATUAN

A B C

BAHAN KIMIA
BHK.RSD Residu / Kolter Liter

CAT
CAT.BS Cat besi kansai property gloss 1 lt Liter
CAT.DSR Cat dasar Kg
CAT.EMC Cat emco 1 lt Kg
CAT.MNE.BS Cat menie besi kanzai 1 lt Liter
CAT.MNE.KY Cat menie kayu Kg
CAT.TBK.DCL Cat tembok decolith Kg
CAT.TBK.DLXINT Cat tembok dulux interior Liter
CAT.TBK.DLXEXT Cat tembok dulux weathershield Liter
CAT.TBK.EMC Cat tembok emco Kg
CAT.TBK.PRG Cat tembok paragon Kg
CAT.TBK.TYP Cat tembok toyopaint Kg
CAT.TBK.VLX Cat tembok vinilex Kg
CAT.TBK.VNP Cat tembok vinippaint Kg

PLAMIR
PMR.KY Plamir kayu Kg
PMR.TBK Plamir tembok Kg

OLI
OLI Oli Liter

CAT/MINYAK/FINISHING
1 Amplas lbr
#REF! Dempul sanpolac ltr
#REF! Kuas star 4" bh
#REF! Mill zak
#REF! Minyak cat ltr
#REF! Politur ultra lasur ltr
#REF! Politur Movilex ltr
#REF! Thiner A Bonanza ltr
#REF! Thiner B Spesial ltr
#REF! Soda api kg
#REF! Sabun kg
#REF! Woodstain kg
#REF! Wood filler kg
#REF! Sanding sealer kg
#REF! Melamic kg
#REF! Cornice adhesive kg
35 Coating natural propan kg
36 Sikabon kg
37 Sikacoat kg
38 Kapi bh
38 Roll bh

SENG
SNG.GLB.0,20 Seng BJLS 0,20 gelombang Lembar
SNG.GLB.0,25 Seng BJLS 0,25 gelombang Lembar
SNG.GLB.0,28 Seng BJLS 0,28 gelombang Lembar
SNG.GLB.0,32 Seng BJLS 0,32 gelombang Lembar
SNG.PLT Seng plat 3" x 6" BJLS 28 Lembar

IJUK
IJK Ijuk Kg

BESI BAJA PROFIL


BS.BJ.PRF.WF6 Besi profil WF P.6 m Kg
BS.BJ.PRF.WF12 Besi profil WF P.12 m Kg
BS.BJ.PRF.WF Baja/ Besi WF Kg

BESI SIKU
BS.SK.30x30x3 Besi siku 30 x 30 x 3 mm Kg

PENUTUP ATAP
#REF! Alang-alang panjang 2,4 m x 1m lbr
#REF! Alluminium foil solartek 1,2x25x4mm roll
#REF! Alluminium foil D 1,2x25x4mm roll
#REF! Asbes Bubungan lbr
#REF! Asbes Gelombang 1,80 m x 0,80 m x 5 mm lbr
#REF! Asbes Gelombang 2,4 m x 1,05 m x 4 mm lbr
2

NO KODE NAMA BARANG MERK SATUAN

A B C

#REF! Asbes Rata 2 m x 1 m x 4 mm lbr


#REF! Atap metal Toratora 1 x 4 Extra m2
#REF! Atap metal Toratora 1 x 4 Premium m2
#REF! Atap metal Toratora 2 x 4 Extra m2
#REF! Atap metal Toratora 2 x 4 Premium m2
#REF! Atap metal Toratora 3 x 4 Extra m2
#REF! Atap metal Toratora 3 x 4 Premium m2
#REF! Atap metal Toratora 4 x 4 Extra m2
#REF! Atap metal Toratora 4 x 4 Premium m2
#REF! Atap spandek 0.30 mm m2
#REF! Atap spandek 0.35 mm m2
#REF! Atap spandek 0.40 mm m2
#REF! Atap spandek 0.45 mm m2
#REF! Atap spandek 0.50 mm m2
#REF! Bentala paras 70 cm bh
#REF! Bentala tanah liat 70 cm bh
#REF! Bubung stel gel. 0,92 m lbr
#REF! Bubung stel gel. 1,05 m lbr
#REF! Bubung stel gel. 1,08 m lbr
#REF! Bubungan Biasa bj
#REF! Bubungan Karang Pilang (glazur) isi 3,5/m bj
#REF! Bubungan Karang Pilang isi 3,5/m bj
#REF! Bubungan Ngalayur isi 3,5/m bj
#REF! Bubungan Plentong bj
#REF! Bubungan genteng beton bj
#REF! Bubungan Utama isi 3,5/m bj
#REF! Genteng Kanmuri (glazur) isi 14/m2 bj
#REF! Genteng Kodok Karang Pilang (Bambe) isi 20/m2 bj
#REF! Genteng Kodok Karang Pilang (Bisma) isi 20/m2 bj
#REF! Genteng Kodok Karang Pilang (Good Year) isi 20/m2 bj
#REF! Genteng Flat (Good Year) isi 20/m2 bj
#REF! Genteng Beton JS bj
#REF! Genteng Beton BBC bj
#REF! Genteng Morando Abadi isi 18/m2 bj
#REF! Genteng Morando Jatiwangi isi 18/m2 bj
#REF! Genteng Morando Ngalayur isi 20/m2 bj
#REF! Genteng Plentong bj
#REF! Genteng Plentong besar bj
#REF! Genteng plentong dicat bj
#REF! Genteng Plentong Jatiwangi isi 24/m2 bj
#REF! Ikut celedu paras 80 cm bh
#REF! Ikut celedu tanah liat 80 cm plentong bh
#REF! Murda paras 30 cm bh
#REF! Murda tanah liat 30 cm bh
#REF! Nok Stel Gelombang 80cm lbr
#REF! Nok Stel Gelombang 105cm lbr
#REF! Rooflight Fiberglass lbr
#REF! Sirap Jati bh
#REF! Sirap ulin satu ikat isi 80 bh ikat

TALI
TL.IJK Tali Ijuk Kg
TL.ALG Tali pengikat alang-alang Ikat

KACA
KC.BNG.10 Kaca 10 mm bening m2
KC.BNG.12 Kaca 12 mm bening m2
KC.BNG.19 Kaca 19 mm bening m2
KC.BNG.3 Kaca 3 mm bening m2
KC.BNG.5 Kaca 5 mm bening m2
KC.BNG.6 Kaca 6 mm bening m2
KC.BNG.8 Kaca 8 mm bening m2
KC.CRM.3 Kaca cermin 3 mm m2
KC.CRM.5 Kaca cermin 5 mm m2
KC.CRM.8 Kaca cermin 8 mm Daun
KC.ICE.3 Kaca es / ice glass 3 mm m2
KC.ICE.5 Kaca es / ice glass 5 mm m2
KC.KPR.3 Kaca es / kapur 3 mm m2
KC.KPR.5 Kaca es / kapur 5 mm m2
KC.PRS.3 Kaca es / prosted glass 3 mm m2
KC.PRS.5 Kaca es / prosted glass 5 mm m2
KC.NK Kaca nako m2
KC.NK.TRL.BNG Kaca nako teralis bening m2
KC.RBN.3 Kaca ryben 3 mm m2
KC.RBN.5 Kaca ryben 5 mm m2
KC.TPR.10 Kaca tempered 10 mm m2
KC.TPR.12 Kaca tempered 12 mm m2
KC.TPR.15 Kaca tempered 15 mm m2
KC.TPR.19 Kaca tempered 19 mm m2
KC.TPR.5 Kaca tempered 5 mm m2
KC.TPR.6 Kaca tempered 6 mm m2
KC.TPR.8 Kaca tempered 8 mm m2
3

NO KODE NAMA BARANG MERK SATUAN

A B C

KC.LMN.CLR.10 Laminated glass clear 10+0,38+10 m2


KC.LMN.CLR.3 Laminated glass clear 3+0,38+10 m2
KC.LMN.CLR.4 Laminated glass clear 4+0,38+10 m2
KC.LMN.CLR.5 Laminated glass clear 5+0,38+10 m2
KC.LMN.CLR.6 Laminated glass clear 6+0,38+10 m2
KC.LMN.CLR.8 Laminated glass clear 8+0,38+10 m2
KC.LMN.TPR.10 Laminated glass tempered 10+0,38+10 m2
KC.LMN.TPR.3 Laminated glass tempered 3+0,38+3 m2
KC.LMN.TPR.4 Laminated glass tempered 4+0,38+4 m2
KC.LMN.TPR.5 Laminated glass tempered 5+0,38+5 m2
KC.LMN.TPR.6 Laminated glass tempered 6+0,38+6 m2
KC.LMN.TPR.8 Laminated glass tempered 8+0,38+8 m2

PENGGANTUNG DAN KACA


1 Door closer DEKKSON DCL 300 HO BA / NA set
2 Door closer DEKKSON DCL 300 NHO BA / NA set
3 Door closer DEKKSON DCL 522 NA set
4 Door holder bh
5 Door stopper DEKKSON MDS 889 GP bh
6 Engsel 3" solid ek 16 ps
7 Engsel nylon ps
8 Engesel angin/ hak angin ps
9 Engsel solid 4" EK 02 ps
10 Sping Knipe, Grendel Kodok Solid ps
11 Engsel casement solid 12" bh
12 Engsel casement solid 16" bh
13 Engsel casement solid 24" bh
14 Engsel casement solid 20" bh
15 HINGE DEKKSON NRP ESS DL 3X2.5X2.5MM 2 SSS ps
16 HINGE DEKKSON NRP ESS DL 4X3X3MM 4BB SSS ps
17 HINGE DEKKSON NRP ESS DL 5X3X3MM 4BB SSS ps
18 HINGE DEKKSON ESS DL “H” 4X3X2MM 2 SSS ps
19 Espagnoleth (setara solid) set
20 Grendel biasa bh
21 Grendel hararo bh
113 Hak angin HA641 SOLID bh
114 Kunci pintu TOP bh
115 Kunci pintu Union bh
116 Kunci pintu Vanesa bh
117 Kunci pintu solid bh
118 Kunci pintu YURI bh
119 Kunci pintu dekson H.DK.LHTR0819 SSS bh
120 Kunci lemari/ laci solid 642 CHR bh
121 Sanro Kunci Ekspanda Bellucci 809 PZS bh
122 grendel slot pintu solid " barrel bolt 314" bh
123 Kunci tanam kamar mandi/ Belocca D5791 Satin Nickel Kunci Bulat bh
124 Kunci silinder DC02-60 SCR Solid bh
124 Kunci slot bh
125 Kunci tanam 2 slag bh
126 CYLINDER DEKKSON CYL HC DL40MM SN bh
127 CYLINDER DEKKSON CYL DC DL60MM SN bh
128 CYLINDER DEKKSON CYL DC KK DL60MM PB bh
129 CYLINDER DEKKSON CYL TC DL60MM PB bh
130 CYLINDER DEKKSON CYL BK DL60MM SN bh
131 Security Double Cylinder DC02-60 SCR Solid bh
132 Kunci pintu Solid (E 62.15 ,LC 122 WL- 60 + 4 bh handle unit
133 Grendel Tanam Solid / Flosh Bolt 312 Solid US 26 16" ps

KY KAYU
KY.JT Kayu jati m3
KY.JT.PPN Kayu jati papan m3
KY.MRB.BLK Kayu merbau balok m3
KY.MRB.PPN Kayu merbau papan m3
KY.ULN Kayu ulin m3
KY.KPR.BLK Kayu kamper balok m3
KY.KPR.USK Kayu kamper usuk m3
KY.KPR.RNG Kayu kamper reng m3
KY.KPR.PPN Kayu kamper papan m3
KY.BKR.BLK Kayu bingkirai balok m3
KY.BKR.PPN Kayu bingkirai papan m3
KY.KRG.BLK Kayu kruing balok m3
KY.KRG.USK Kayu kruing usuk m3
KY.KRG.RNG Kayu kruing reng m3
KY.KRG.PPN Kayu kruing papan m3
KY.MRT.BLK Kayu meranti balok m3
KY.MRT.USK Kayu meranti usuk m3
KY.MRT.RNG Kayu meranti reng m3
KY.MRT.PPN Kayu meranti papan m3
KY.DKNKLP.P2,5 Kayu dolken kelapa diameter 18 cm panjang 2,5 m m1
KY.DKNKLP.P3 Kayu dolken kelapa diameter 18 cm panjang 3 m m1
KY.DKNKLP.P4 Kayu dolken kelapa diameter 18 cm panjang 4 m m1
KY.DKN.P4 Kayu dolken / kayu laut Ø 7,5 - 10 / 400 cm Batang
4

NO KODE NAMA BARANG MERK SATUAN

A B C

KY.ALB.BLK Kayu seseh balok m3


KY.SSHDKN Kayu seseh dolken m3
KY.PRF.USK Kayu profil usuk m1
KY.CPK Kayu cempaka m3
MTP.18MM Multiplek 18 mm Lembar
MTP.12MM Multiplek 12 mm Lembar
MTP.9MM Multiplek 9 mm Lembar
MTP.6MM Multiplek 6 mm Lembar
PLW.12MM Plywood 12 mm Lembar
PLW.9MM Plywood 9 mm Lembar
PLW.6MM Plywood 6 mm Lembar
PLW.4MM Plywood 4 mm Lembar
PLW.3MM Plywood 3 mm Lembar
TKW.0,9X2,2 Teak wood (0,90 x 2,20) m2 Lembar
TKW.1,2X2,4 Teak wood (1,20 x 2,40) m2 Lembar
KY.BKT.LPSMRH Kayu bekesting (lepasan merah) m3
GDG.KLT.KLSI Gedeg kulit kelas I m2
CLG.TK.0,62X2,40 Ceiling teak (0,62 x 2,40) m2 Lembar
TKB.18MM Teakblock 18 mm Lembar
BLB.18MM Blockboard 18 mm Lembar
MGT.3MM Megateak 3 mm Lembar
RMG.UKR.JT Ring ukir jati 1.5 x 8 cm m1
TRP.WBP.1 Triplex phenol WBP film 12 mm 1 muka Lembar
TRP.WBP.2 Triplex phenol WBP film 12 mm 2 muka Lembar

BAMBU
BMB.BSR.EXP Bambu besar expose utk saka Batang
BMB.BSR.4 Bambu besar Ukuran 4 m Batang
BMB.SDG.4 Bambu sedang Ukuran 4 m Batang
BMB.KCL.4 Bambu kecil Ukuran 4 m Batang

MINYAK
MYK.BKT Minyak bekisting Liter
SLR Solar Liter
MYK.PLS Minyak pelumas Liter

LIST
LST.GPM.STD List gypsum standar m1
LST.KY List kayu m1
LST.GPM List gypsum 9/9 m1
LST.PFN.FBM List plafond fibercement strip smooth texture square cut edge (8 x 75 x 3000 mm) Lembar

#REF! Eternit lbr


#REF! Formika lbr
#REF! Gypsum board tebal 9 mm lbr
#REF! Hard board MDF lbr
#REF! Kalsiboard 4,5 mm lbr
141a fibercement cellingboard square cut setara shera ukuran (4x120x240) mm lbr
#REF! Lem Aibond kg
#REF! Lem Kayu ltr
#REF!
#REF!
#REF! Plywood aluminium lbr
#REF! Panel Acoustic Armstrong 120x60cm, tebal 9 mm lbr
#REF! Panel Acoustic Armstrong 120x60cm, tebal 15 mm lbr
#REF! Panel Acoustic OWA Constellation 120x60cm, tebal 15 m lbr
#REF! Lumbersering Conwood m2
189a Plafond fibercement splending modern stagger setara shera smooth texture golden teakwood(10x150x3000mm) 1br
#REF!
#REF! Shadowline m1
#REF!
#REF! lisplank fibercement eave pro coral white setara shera (16x240x3000 mm ) lbr
#REF! Tatab fibercement strip smooth texture V cut edge setara shera (8x100x3000 mm ) lbr

KERAMIK LANTAI
Keramik Ikad 20 x 20 cm (minimalist) IKAD m2
Keramik Ikad 20 x 20 cm (mozaic) IKAD m2
Keramik Roman 20 x 20 cm (dDelft) IKAD m2
Keramik Roman 20 x 20 cm (Plano)
Keramik Roman 20 x 20 cm (Graniti)
Keramik Roman 20 x 20 cm (Minima)
Keramik Roman 20 x 20 cm (Oceanus)
Keramik Roman 20 x 20 cm (Sandstone)
Keramik Roman 20 x 20 cm (dCervia)
Keramik Roman 20 x 20 cm (Venere)
Keramik Ikad 25 x 25 cm (minimalist) IKAD m2
Keramik Ikad 25 x 25 cm (mozaic) IKAD m2
Keramik Ikad 25 x 25 cm (retro) IKAD m2
Keramik Ikad 25 x 25 cm (stone) IKAD m2
Keramik Habitat 25 x 25 (Granada Smoke) / Matt Textured / Floor / Linea
Keramik Habitat 25 x 25 (Granada Maple) / Matt Textured / Floor / Linea
Keramik Habitat 25 x 25 (Granada Ash) / Matt Textured / Floor / Linea
5

NO KODE NAMA BARANG MERK SATUAN

A B C

Keramik Habitat 25 x 25 (Linea Cherry) / Matt / Floor / Wall / Linea


Keramik Habitat 25 x 25 (Linea Maple) / Matt / Floor / Wall / Linea
Keramik Habitat 25 x 25 (Godiva Grey) / Matt Textured / Floor / Contempo Arc
Keramik Habitat 25 x 25 (Godiva Black) / Matt Textured / Floor / Contempo Arc
Keramik Habitat 25 x 25 (Godiva Brown) / Matt Textured / Floor / Contempo Arc
Keramik Habitat 25 x 25 (Godiva Cream) / Matt Textured / Floor / Contempo Arc
Keramik Habitat 25 x 25 (Spark Sand) / Matt / Floor / Contempo Arc
Keramik Habitat 25 x 25 (Spark Carbon) / Matt / Floor / Contempo Arc
Keramik Habitat 25 x 25 (Spark Bronze) / Matt / Floor / Contempo Arc
Keramik Habitat 25 x 25 (Spark Canvas) / Matt / Floor / Contempo Arc
Keramik Habitat 25 x 25 cm (Alpha Nero) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 25 x 25 cm (Alpha Gris) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 25 x 25 cm (Alpha Bianca) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 25 x 25 cm (Alpha Ebano) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 25 x 25 cm (Alpha Ivory) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 25 x 25 (Andara White) / Glossy / Floor / Pop Art
Keramik Habitat 25 x 25 (Andara Crema) / Glossy / Floor / Pop Art
Keramik Habitat 25 x 25 (Andara Black) / Glossy / Floor / Pop Art
Keramik Habitat 25 x 25 (Claire White) / Glossy / Wall / Pop Art
Keramik Habitat 25 x 25 (Claire Black) / Glossy / Wall / Pop Art
Keramik Habitat 25 x 25 (Stella Light Cream) / Matt Textured / Wall / Shabby Chic
Keramik Habitat 25 x 25 (Stella Light Bone) / Matt Textured / Wall / Shabby Chic
Keramik Ikad 30 x 30 cm (minimalist) IKAD m2
Keramik Ikad 30 x 30 cm (mozaic) IKAD m2
Keramik Ikad 30 x 30 cm (marble) IKAD m2
Keramik Roman 30 x 30 cm (Osaka) IKAD m2
Keramik Roman 30 x 30 cm (Rocktile)
Keramik Roman 30 x 30 cm (Vivaz)
Keramik Roman 30 x 30 cm (dLastrico)
Keramik Roman 30 x 30 cm (dBorra)
Keramik Roman 30 x 30 cm (dBrava)
Keramik Roman 30 x 30 cm (Faenza)
Keramik Roman 30 x 30 cm (dBolonia)
Keramik Roman 30 x 30 cm (Stark)
Keramik Roman 30 x 30 cm (dBatur)
Keramik Roman 30 x 30 cm (Graniti 30)
Keramik Roman 30 x 30 cm (dNatuna)
Keramik Roman 30 x 30 cm (Dallas)
Keramik Roman 30 x 30 cm (dBanda)
Keramik Roman 30 x 30 cm (Monte)
Keramik Platinum 30 x 30 cm (Cargo Brown)
Keramik Platinum 30 x 30 cm (Cargo Dark Brown)
Keramik Platinum 30 x 30 cm (Cargo Grey)
Keramik Platinum 30 x 30 cm (Cargo Dark Grey)
Keramik Habitat 30 x 30 cm (Alpha Nero) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 30 x 30 cm (Alpha Gris) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 30 x 30 cm (Alpha Bianca) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 30 x 30 cm (Alpha Ebano) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 30 x 30 cm (Alpha Ivory) / Glossy Textured / Floor / Warm Embrace
Keramik Ikad 40 x 40 cm (minimalist) IKAD m2
Keramik Ikad 40 x 40 cm (mozaic) IKAD m2
Keramik Ikad 40 x 40 cm (retro) IKAD m2
Keramik Ikad 40 x 40 cm (marble) IKAD m2
Keramik Ikad 40 x 40 cm (stone) IKAD m2
Keramik Ikad 40 x 40 cm (wood) IKAD m2
Keramik Roman 40 x 40 cm (dLogan)
Keramik Roman 40 x 40 cm (Vivaz 40)
Keramik Roman 40 x 40 cm (dFaro)
Keramik Roman 40 x 40 cm (dBaffin)
Keramik Roman 40 x 40 cm (dAcropolis)
Keramik Roman 40 x 40 cm (Abitare)
Keramik Roman 40 x 40 cm (dStreet)
Keramik Roman 40 x 40 cm (Alexa)
Keramik Roman 40 x 40 cm (dCopertino)
Keramik Roman 40 x 40 cm (Chrysant)
Keramik Roman 40 x 40 cm (dLitura)
Keramik Roman 40 x 40 cm (dAdelaide)
Keramik Roman 40 x 40 cm (dNavarre)
Keramik Roman 40 x 40 cm (dCapri)
Keramik Roman 40 x 40 cm (dKrubera)
Keramik Roman 40 x 40 cm (dVomero)
Keramik Roman 40 x 40 cm (dVaranda)
Keramik Roman 40 x 40 cm (dLaterina)
Keramik Roman 40 x 40 cm (Epoca)
Keramik Roman 40 x 40 cm (dGirona)
Keramik Roman 40 x 40 cm (Pavilion)
Keramik Roman 40 x 40 cm (dMiami)
Keramik Roman 40 x 40 cm (Riviera)
Keramik Roman 40 x 40 cm (dBrisbane)
Keramik Roman 40 x 40 cm (dCoral40)
Keramik Roman 40 x 40 cm (Starlight)
Keramik Roman 40 x 40 cm (dDomica)
6

NO KODE NAMA BARANG MERK SATUAN

A B C

Keramik Roman 40 x 40 cm (dAcera)


Keramik Roman 40 x 40 cm (Monte 40)
Keramik Roman 40 x 40 cm (dCastrum)
Keramik Roman 40 x 40 cm (Sandstone 40)
Keramik Roman 40 x 40 cm (dNagoya)
Keramik Roman 40 x 40 cm (dRegato)
Keramik Platinum 40 x 40 (Alaska Brown)
Keramik Platinum 40 x 40 (Alaska Cream)
Keramik Platinum 40 x 40 (Alaska White)
Keramik Platinum 40 x 40 (Alaska Grey)
Keramik Platinum 40 x 40 (Altoro Brown)
Keramik Platinum 40 x 40 (Altoro Grey)
Keramik Platinum 40 x 40 (Amazon Bone)
Keramik Platinum 40 x 40 (Amazon Beige)
Keramik Platinum 40 x 40 (Amazon Brown)
Keramik Platinum 40 x 40 (Amazon Grey)
Keramik Platinum 40 x 40 (Ancona Bone)
Keramik Platinum 40 x 40 (Ancona Brown)
Keramik Platinum 40 x 40 (Ancona Grey)
Keramik Platinum 40 x 40 (Ancora Bone)
Keramik Platinum 40 x 40 (Ancora Brown)
Keramik Platinum 40 x 40 (Ancora Grey)
Keramik Platinum 40 x 40 (Angelo Bone)
Keramik Platinum 40 x 40 (Angelo Brown)
Keramik Platinum 40 x 40 (Angelo Grey)
Keramik Platinum 40 x 40 (Angelo Bone Decor)
Keramik Platinum 40 x 40 (Angelo Brown Decor)
Keramik Platinum 40 x 40 (Angelo Grey Decor)
Keramik Platinum 40 x 40 (Asher Brown)
Keramik Platinum 40 x 40 (Asher Grey)
Keramik Platinum 40 x 40 (Anthena Brown)
Keramik Platinum 40 x 40 (Anthena Grey)
Keramik Platinum 40 x 40 (Atlanta Brown)
Keramik Platinum 40 x 40 (Atlanta Grey)
Keramik Platinum 40 x 40 (Atlas Brown)
Keramik Platinum 40 x 40 (Atlas Grey)
Keramik Platinum 40 x 40 (Atria Brown)
Keramik Platinum 40 x 40 (Atria Grey)
Keramik Platinum 40 x 40 (Azuvi Brown)
Keramik Platinum 40 x 40 (Azuvi Grey)
Keramik Platinum 40 x 40 (Bailey Basic)
Keramik Platinum 40 x 40 (Bailey Blue)
Keramik Platinum 40 x 40 (Bailey Brown)
Keramik Platinum 40 x 40 (Bailey Green)
Keramik Platinum 40 x 40 (Bailey Mask)
Keramik Platinum 40 x 40 (Bolton Black)
Keramik Platinum 40 x 40 (Bolton Beige)
Keramik Platinum 40 x 40 (Bolton Grey)
Keramik Platinum 40 x 40 (Bonza White)
Keramik Platinum 40 x 40 (Braxton Brown)
Keramik Platinum 40 x 40 (Braxton Cream)
Keramik Platinum 40 x 40 (Braxton Grey)
Keramik Platinum 40 x 40 (Brescia Brown)
Keramik Platinum 40 x 40 (Brescia Grey)
Keramik Platinum 40 x 40 (Brescia Cream)
Keramik Platinum 40 x 40 (Brighton Basic)
Keramik Platinum 40 x 40 (Brighton Black Decor)
Keramik Platinum 40 x 40 (Casa Cream)
Keramik Platinum 40 x 40 (Casa Grey)
Keramik Platinum 40 x 40 (Corso Black)
Keramik Platinum 40 x 40 (Corso Brown)
Keramik Platinum 40 x 40 (Corso Grey)
Keramik Platinum 40 x 40 (Golia Brown)
Keramik Platinum 40 x 40 (Golia Grey)
Keramik Platinum 40 x 40 (Harold Brown)
Keramik Platinum 40 x 40 (Harold Grey)
Keramik Platinum 40 x 40 (Harper Brown)
Keramik Platinum 40 x 40 (Harper Grey)
Keramik Platinum 40 x 40 (Herrera Cream)
Keramik Platinum 40 x 40 (Herrera Grey)
Keramik Platinum 40 x 40 (Hilton Cream)
Keramik Platinum 40 x 40 (Hilton Grey)
Keramik Platinum 40 x 40 (Holly Brown)
Keramik Platinum 40 x 40 (Holly Grey)
Keramik Platinum 40 x 40 (Lexus Cream)
Keramik Platinum 40 x 40 (Lexus Grey)
Keramik Platinum 40 x 40 (Maldives Grey)
Keramik Platinum 40 x 40 (Maldives Brown)
Keramik Platinum 40 x 40 (Niko Cream)
Keramik Platinum 40 x 40 (Niko Grey)
Keramik Platinum 40 x 40 (Vegas Brown)
Keramik Milan 40 x 40 (Alpino Cheznut) / Glossy / Floor / Marble
7

NO KODE NAMA BARANG MERK SATUAN

A B C

Keramik Milan 40 x 40 (Alpino Vanilla) / Glossy / Floor / Marble


Keramik Milan 40 x 40 (Celina Brown) / Glossy / Floor / Marble
Keramik Milan 40 x 40 (Celina Charcoal) / Glossy / Floor / Marble
Keramik Milan 40 x 40 (Celina Crema) / Glossy / Floor / Marble
Keramik Milan 40 x 40 (Celina Grey) / Glossy / Floor / Marble
Keramik Milan 40 x 40 (Celina White) / Glossy / Floor / Marble
Keramik Milan 40 x 40 (Deepika Bone) / Glossy / Floor / Marble
Keramik Milan 40 x 40 (Deepika Grey) / Glossy / Floor / Marble
Keramik Milan 40 x 40 (Dublin White) / Glossy / Floor / Marble
Keramik Milan 40 x 40 (Madison Bone) / Glossy / Floor / Marble
Keramik Milan 40 x 40 (Madison Cream) / Glossy / Floor / Marble
Keramik Milan 40 x 40 (Manhattan L Grey) / Glossy / Floor / Marble
Keramik Milan 40 x 40 (Manhattan L Beige) / Glossy / Floor / Marble
Keramik Milan 40 x 40 (Priyanka Bone) / Glossy / Floor / Marble
Keramik Milan 40 x 40 (Taffana Bone) / Glossy / Floor / Marble
Keramik Milan 40 x 40 (Moscow Brown) / Glossy / Floor / Wood
Keramik Milan 40 x 40 (Moscow Cream) / Glossy / Floor / Wood
Keramik Milan 40 x 40 (Origami Ebano) / Matt Structure / Floor / Wood
Keramik Milan 40 x 40 (Origami Maple) / Matt Structure / Floor / Wood
Keramik Milan 40 x 40 (Texas Maple) / Matt Textured / Floor / Wood
Keramik Milan 40 x 40 (Texas Walnut) / Matt Textured / Floor / Wood
Keramik Milan 40 x 40 (Texas Oak) / Matt Textured / Floor / Wood
Keramik Milan 40 x 40 (Texas Forest) / Matt Textured / Floor / Wood
Keramik Milan 40 x 40 (Arizona Brown) / Matt Structure / Floor / Stone
Keramik Milan 40 x 40 (Arizona Gris) / Matt Structure / Floor / Stone
Keramik Milan 40 x 40 (Canberra Brown) / Matt Structure / Floor / Stone
Keramik Milan 40 x 40 (Canberra Cream) / Matt Structure / Floor / Stone
Keramik Milan 40 x 40 (Canberra Paxi Brown) / Matt Structure / Floor / Stone
Keramik Milan 40 x 40 (Grisel Black) / Matt Textured / Floor / Stone
Keramik Milan 40 x 40 (Grisel Grey) / Matt Textured / Floor / Stone
Keramik Milan 40 x 40 (Grisel Brown) / Matt Textured / Floor / Stone
Keramik Milan 40 x 40 (Grisel L Brown) / Matt Textured / Floor / Stone
Keramik Milan 40 x 40 (Grisel Coffee) / Matt Textured / Floor / Stone
Keramik Milan 40 x 40 (Nevada Brown) / Matt Structure / Floor / Stone
Keramik Milan 40 x 40 (Nevada Gris) / Matt Structure / Floor / Stone
Keramik Milan 40 x 40 (Certa Bianco) / Gloss / Floor / Deco
Keramik Milan 40 x 40 (Certa Nero) / Gloss / Floor / Deco
Keramik Milan 40 x 40 (Evo Deco) / Gloss / Floor / Deco
Keramik Milan 40 x 40 (Evo Grey) / Gloss / Floor / Deco
Keramik Milan 40 x 40 (Evo L Grey) / Gloss / Floor / Deco
Keramik Milan 40 x 40 (Harvest Deco Brown) / Matt / Floor / Deco
Keramik Milan 40 x 40 (Harvest Brown) / Matt / Floor / Deco
Keramik Milan 40 x 40 (Harvest Grey) / Matt / Floor / Deco
Keramik Milan 40 x 40 (Harvest Deco Grey) / Matt / Floor / Deco
Keramik Milan 40 x 40 (Zarco Gris) / Matt Sattine / Floor / Deco
Keramik Milan 40 x 40 (Zarco Ebano) / Matt Sattine / Floor / Deco
Keramik Milan 40 x 40 (Balkan Brown) / Matt / Floor / Rustic
Keramik Milan 40 x 40 (Balkan Sand) / Matt / Floor / Rustic
Keramik Milan 40 x 40 (Calm Bronze) / Matt Textured / Floor / Rustic
Keramik Milan 40 x 40 (Calm Vanilla) / Matt Textured / Floor / Rustic
Keramik Milan 40 x 40 (Calm Royal) / Matt Textured / Floor / Rustic
Keramik Milan 40 x 40 (Calm Aqua) / Matt Textured / Floor / Rustic
Keramik Milan 40 x 40 (Calm Olive) / Matt Textured / Floor / Rustic
Keramik Milan 40 x 40 (Cotton Bone) / Matt Textured / Floor / Rustic
Keramik Milan 40 x 40 (Cotton Brown) / Matt Textured / Floor / Rustic
Keramik Milan 40 x 40 (Cotton Black) / Matt Textured / Floor / Rustic
Keramik Milan 40 x 40 (Lincoln Black) / Matt / Floor / Rustic
Keramik Hercules 40 x 40 (Marius Bone) / Glossy / Floor
Keramik Hercules 40 x 40 (Uluwatu) / Glossy / Floor
Keramik Hercules 40 x 40 (Xenon Bone) / Glossy / Floor
Keramik Hercules 40 x 40 (Xenon Grey) / Glossy / Floor
Keramik Ikad 50 x 50 cm (minimalist) IKAD m2
Keramik Ikad 50 x 50 cm (marble) IKAD m2
Keramik Ikad 50 x 50 cm (stone) IKAD m2
Keramik Ikad 50 x 50 cm (wood) IKAD m2
Keramik Roman 50 x 50 (dTimber)
Keramik Roman 50 x 50 (Ancona)
Keramik Roman 50 x 50 (Austin)
Keramik Roman 50 x 50 (Caliza)
Keramik Roman 50 x 50 (Carrara)
Keramik Roman 50 x 50 (Colusseum)
Keramik Roman 50 x 50 (Continental)
Keramik Roman 50 x 50 (Crystalline)
Keramik Roman 50 x 50 (dAstana)
Keramik Roman 50 x 50 (dAtlanta)
Keramik Roman 50 x 50 (dBoulevard)
Keramik Roman 50 x 50 (dBudapest)
Keramik Roman 50 x 50 (dCervino)
Keramik Roman 50 x 50 (dColorado)
Keramik Roman 50 x 50 (dKanawa)
Keramik Roman 50 x 50 (dMegapolis)
Keramik Roman 50 x 50 (dMissouri)
8

NO KODE NAMA BARANG MERK SATUAN

A B C

Keramik Roman 50 x 50 (dParquet)


Keramik Roman 50 x 50 (dPebble)
Keramik Roman 50 x 50 (dPlaza)
Keramik Roman 50 x 50 (dTimber)
Keramik Roman 50 x 50 (dTreccia)
Keramik Roman 50 x 50 (Fusion)
Keramik Roman 50 x 50 (Newcastle)
Keramik Roman 50 x 50 (Perlino)
Keramik Roman 50 x 50 (Starlight 50)
Keramik Roman 50 x 50 (Terrace)
Keramik Platinum 50 x 50 (Dallas Brown)
Keramik Platinum 50 x 50 (Dallas Grey)
Keramik Platinum 50 x 50 (Dalton Brown)
Keramik Platinum 50 x 50 (Dalton Grey)
Keramik Platinum 50 x 50 (Denver Brown)
Keramik Platinum 50 x 50 (Denver Grey)
Keramik Platinum 50 x 50 (Detroit Brown)
Keramik Platinum 50 x 50 (Detroit Dark Grey)
Keramik Platinum 50 x 50 (Detroit Grey)
Keramik Platinum 50 x 50 (Dexter Brown)
Keramik Platinum 50 x 50 (Dexter White)
Keramik Platinum 50 x 50 (Dolomite Beige)
Keramik Platinum 50 x 50 (Dolomite Grey)
Keramik Platinum 50 x 50 (Dominic Grey)
Keramik Platinum 50 x 50 (Dover Brown)
Keramik Platinum 50 x 50 (Dover Grey)
Keramik Platinum 50 x 50 (Dublin Brown)
Keramik Platinum 50 x 50 (Dublin Grey)
Keramik Platinum 50 x 50 (Duomo Brown)
Keramik Platinum 50 x 50 (Duomo Grey)
Keramik Platinum 50 x 50 (Dupont Grey)
Keramik Platinum 50 x 50 (Dustin Grey)
Keramik Platinum 50 x 50 (Dustin Brown)
Keramik Platinum 50 x 50 (Dustin Black)
Keramik Platinum 50 x 50 (Hampton Brown)
Keramik Platinum 50 x 50 (Hampton Grey)
Keramik Platinum 50 x 50 (Havard Brown)
Keramik Platinum 50 x 50 (Havard Grey)
Keramik Platinum 50 x 50 (Havana Cream)
Keramik Platinum 50 x 50 (Havana Grey)
Keramik Platinum 50 x 50 (Hazel Brown)
Keramik Platinum 50 x 50 (Hazel Grey)
Keramik Platinum 50 x 50 (Heston Cream)
Keramik Platinum 50 x 50 (Heston Grey)
Keramik Platinum 50 x 50 (Hilton Cream)
Keramik Platinum 50 x 50 (Hilton Grey)
Keramik Platinum 50 x 50 (Lexus Cream)
Keramik Platinum 50 x 50 (Lexus Grey)
Keramik Milan 50 x 50 (Aerys Cream) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Aerys Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Alpino Cheznut) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Alpino Vanilla) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Austin Bone) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Austin Brown) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Austin Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Bilbao Cream) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Bilbao Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Celina Crema) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Celina Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Celina White) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Circa Cream) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Circa Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Deepika Bone) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Deepika Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Deepika Cream) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Dublin White) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Fantastic Brown) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Fantastic Coffee) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Lisbon Cream) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Lisbon Gold) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Lyon Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Lyon Mocca) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Madison Bone) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Madison Cream) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Majesty Cream) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Majesty Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Manhattan L Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Manhattan L Beige) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Odesa Brown) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Odesa Cream) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Padova Brown) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Padova Cream) / Glossy / Floor / Marble
9

NO KODE NAMA BARANG MERK SATUAN

A B C

Keramik Milan 50 x 50 (Padova Grey) / Glossy / Floor / Marble


Keramik Milan 50 x 50 (Priyanka Bone) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Priyanka Cream) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Priyanka Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Saga Cream) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Saga Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Samara Brown) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Samara Cream) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Santos Beige) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Santos Brown) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Savia Cream) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Savia Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Savory Cream) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Savory Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Seattle Cream) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Seattle Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Sevilla Brown) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Sevilla Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Shanghai Bone) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Shanghai Brown) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Shelby Cream) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Shelby Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Siena Cream) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Siena Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Sonata Cream) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Sonata Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Sydney Bone) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Sydney Grey) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Taffana Bone) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Trento Brown) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Trento Nero) / Glossy / Floor / Marble
Keramik Milan 50 x 50 (Rio Deco) / Matt Texture / Floor / Wood
Keramik Milan 50 x 50 (Rio Natural) / Matt Texture / Floor / Wood
Keramik Milan 50 x 50 (Rio Walnut) / Matt Texture / Floor / Wood
Keramik Milan 50 x 50 (Venetta Ebano) / Matt Sattine / Floor / Wood
Keramik Milan 50 x 50 (Venetta Ebano Violia) / Matt Sattine / Floor / Wood
Keramik Milan 50 x 50 (Venetta Maple) / Matt Sattine / Floor / Wood
Keramik Milan 50 x 50 (Venetta Maple Violia) / Matt Sattine / Floor / Wood
Keramik Milan 50 x 50 (Porto Verda) / Matt Structure / Floor / Stone
Keramik Milan 50 x 50 (Corsica) / Gloss / Floor / Deco
Keramik Milan 50 x 50 (Gregorio Uno) / Matt Structure / Floor / Deco
Keramik Milan 50 x 50 (Simply White) / Glossy / Floor / Deco
Keramik Milan 50 x 50 (Nu Santorini) / Glossy / Floor / Deco
Keramik Habitat 50 x 50 (Granada Smoke) / Matt Textured / Floor / Linea
Keramik Habitat 50 x 50 (Granada Maple) / Matt Textured / Floor / Linea
Keramik Habitat 50 x 50 (Granada Ash) / Matt Textured / Floor / Linea
Keramik Habitat 50 x 50 (Kinal Teak) / Matt Structured / Floor / Linea
Keramik Habitat 50 x 50 (Linea Cherry) / Matt / Floor / Wall / Linea
Keramik Habitat 50 x 50 (Linea Maple) / Matt / Floor / Wall / Linea
Keramik Habitat 50 x 50 (Aspen Bianco) / Matt / Floor / Contempo Arc
Keramik Habitat 50 x 50 (Aspen Gris) / Matt Textured / Floor / Contempo Arc
Keramik Habitat 50 x 50 (Aspen Nero) / Matt Textured / Floor / Contempo Arc
Keramik Habitat 50 x 50 (Aspen Beige) / Matt Textured / Floor / Contempo Arc
Keramik Habitat 50 x 50 (Aspen Brown) / Matt Textured / Floor / Contempo Arc
Keramik Habitat 50 x 50 (Godiva Grey) / Matt Textured / Floor / Contempo Arc
Keramik Habitat 50 x 50 (Godiva Black) / Matt Textured / Floor / Contempo Arc
Keramik Habitat 50 x 50 (Godiva Brown) / Matt Textured / Floor / Contempo Arc
Keramik Habitat 50 x 50 (Godiva Cream) / Matt Textured / Floor / Contempo Arc
Keramik Habitat 50 x 50 (Pavilion Brown) / Matt Structured / Floor / Contempo Arc
Keramik Habitat 50 x 50 (Pavilion Gris) / Matt Structured / Floor / Contempo Arc
Keramik Habitat 50 x 50 (Pedra Sand) / Matt Structured / Floor / Contempo Arc
Keramik Habitat 50 x 50 (Spark Sand) / Matt / Floor / Contempo Arc
Keramik Habitat 50 x 50 (Spark Carbon) / Matt / Floor / Contempo Arc
Keramik Habitat 50 x 50 (Spark Bronze) / Matt / Floor / Contempo Arc
Keramik Habitat 50 x 50 (Spark Canvas) / Matt / Floor / Contempo Arc
Keramik Habitat 50 x 50 (Kanae Latte) / Matt / Floor / Warm Embrace
Keramik Habitat 50 x 50 (Kanae Mocca) / Matt / Floor / Warm Embrace
Keramik Habitat 50 x 50 (Secilia Sand) / Matt Satin / Floor / Warm Embrace
Keramik Habitat 50 x 50 (Secilia Classico) / Matt Satin / Floor / Warm Embrace
Keramik Habitat 50 x 50 (Tanami Mocca) / Matt Structure / Floor / Warm Embrace
Keramik Habitat 50 x 50 (Tanami Smoke) / Matt Structure / Floor / Warm Embrace
Keramik Habitat 50 x 50 (Victoria) / Matt Structure / Floor / Warm Embrace
Keramik Habitat 50 x 50 (Andara White) / Glossy / Floor / Pop Art
Keramik Habitat 50 x 50 (Andara Crema) / Glossy / Floor / Pop Art
Keramik Habitat 50 x 50 (Andara Black) / Glossy / Floor / Pop Art
Keramik Habitat 50 x 50 (Trazzo Sunkist) / Matt / Floor / Pop Art
Keramik Essenza 60 x 60 (Marble Crema)
Keramik Essenza 60 x 60 (Marble Tevere White)
Keramik Essenza 60 x 60 (Stone Landmark White)
Keramik Essenza 60 x 60 (Classic Absolute White)
Keramik Essenza 60 x 60 (Lavagna White)
Keramik Essenza 60 x 60 (Marble Tevere Beige)
10

NO KODE NAMA BARANG MERK SATUAN

A B C

Keramik Essenza 60 x 60 (Marble Lara)


Keramik Essenza 60 x 60 (Stone Landmark Beige)
Keramik Essenza 60 x 60 (Marble Pietra)
Keramik Essenza 60 x 60 (Stone Landmark Grey)
Keramik Essenza 60 x 60 (Stone Landmark Dark Grey)
Keramik Essenza 60 x 60 (Graniti Beola Grey)
Keramik Essenza 60 x 60 (Classic Absolute Grey)
Keramik Essenza 60 x 60 (Lavagna Grey)
Keramik Essenza 60 x 60 (Cemento Gris)
Keramik Essenza 60 x 60 (Cemento Grigio)
Keramik Essenza 60 x 60 (Graniti Grigio Perla)
Keramik Essenza 60 x 60 (Classic Absolute Black)
Keramik Essenza 60 x 60 (Graniti Carbone)
Keramik Essenza 60 x 60 (Cemento Carbone)
Keramik Essenza 60 x 60 (Lavagna Black)
Keramik Essenza 60 x 60 (Essenza Wood Ash)
Keramik Essenza 60 x 60 (Wood Pine)
Keramik Essenza 60 x 60 (Wood Maple)
Keramik Essenza 60 x 60 (Wood Oak)
Keramik Essenza 60 x 60 (Lexus Rec Cream)
Keramik Essenza 60 x 60 (Lexus Rec Grey)
Keramik Essenza 60 x 60 (Safari Rec Brown)
Keramik Essenza 60 x 60 (Safari Rec Dark Brown)
Keramik Essenza 60 x 60 (Safari Rec Cream)
Keramik Essenza 60 x 60 (Safari Rec Brown)
Keramik Essenza 60 x 60 (Saigon Rec Grey)
Keramik Essenza 60 x 60 (Salvatore Rec Brown)
Keramik Essenza 60 x 60 (Salvatore Rec Green)
Keramik Essenza 60 x 60 (Salvatore Rec White)
Keramik Essenza 60 x 60 (Santiago Rec Dark Grey)
Keramik Essenza 60 x 60 (Santiago Rec Grey)
Keramik Essenza 60 x 60 (Santiago Rec Beige)
Keramik Essenza 60 x 60 (Sapporo Rec Cream)
Keramik Essenza 60 x 60 (Sapporo Rec Grey)
Keramik Essenza 60 x 60 (Savannah Rec Brown)
Keramik Essenza 60 x 60 (Savannah Rec Grey)
Keramik Essenza 60 x 60 (Savoy Rec Grey)
Keramik Essenza 60 x 60 (Selena Rec Brown)
Keramik Essenza 60 x 60 (Selena Rec Grey)
Keramik Essenza 60 x 60 (Serenity Rec Grey)
Keramik Essenza 60 x 60 (Serenity Rec Brown)
Keramik Essenza 60 x 60 (Servanda Rec Grey)
Keramik Essenza 60 x 60 (Sevilla Rec Brown)
Keramik Essenza 60 x 60 (Sevilla Rec Grey)
Keramik Essenza 60 x 60 (Sierra Rec Dark Grey)
Keramik Essenza 60 x 60 (Sierra Rec Grey)
Keramik Essenza 60 x 60 (Sierra Rec Cream)
Keramik Essenza 60 x 60 (Sovia Rec White)
Keramik Essenza 60 x 60 (Sovia Rec Grey)
Keramik Essenza 60 x 60 (Sovia Rec Brown)
Keramik Essenza 60 x 60 (Sparta Rec Brown)
Keramik Essenza 60 x 60 (Sparta Rec Grey)
Keramik Essenza 60 x 60 (Stamford Rec Brown)
Keramik Essenza 60 x 60 (Stamford Rec Grey)
Keramik Essenza 60 x 60 (Sydney Rec White)
Keramik Essenza 60 x 60 (Sydney Rec Cream)
Keramik Essenza 60 x 60 (Sydney Rec Grey)
Keramik Habitat 60 x 60 (Aria Gris) / Glossy / Floor / Marbella
Keramik Habitat 60 x 60 (Aria Beige) / Glossy / Floor / Marbella
Keramik Habitat 60 x 60 (Calacata Gold) / Glossy / Floor / Marbella
Keramik Habitat 60 x 60 (Carrara Silver) / Glossy / Floor / Marbella
Keramik Habitat 60 x 60 (Dolomite) / Glossy / Floor / Marbella
Keramik Habitat 60 x 60 (Duomo Beige) / Glossy / Floor / Marbella
Keramik Habitat 60 x 60 (Duomo Gris) / Glossy / Floor / Marbella
Keramik Habitat 60 x 60 (Eden Gris) / Glossy / Floor / Marbella
Keramik Habitat 60 x 60 (Eden Beige) / Glossy / Floor / Marbella
Keramik Habitat 60 x 60 (Statuario Snow) / Glossy / Floor / Marbella
Keramik Habitat 60 x 60 (Trista) / Glossy / Floor / Marbella
Keramik Habitat 60 x 60 (Valencia Gold) / Glossy / Floor / Marbella
Keramik Habitat 60 x 60 (Valencia Cream) / Glossy / Floor / Marbella
Keramik Habitat 60 x 60 (Baltic Ash) / Glossy / Floor / Linea
Keramik Habitat 60 x 60 (Baltic Teak) / Glossy / Floor / Linea
Keramik Habitat 60 x 60 (Borneo Pine) / Glossy / Floor / Linea
Keramik Habitat 60 x 60 (Borneo Teak) / Glossy / Floor / Linea
Keramik Habitat 60 x 60 (Carilo Bianco) / Matt Textured / Floor / Contempo Arc
Keramik Habitat 60 x 60 (Carilo Gris) / Matt Textured / Floor / Contempo Arc
Keramik Habitat 60 x 60 (Carilo Beige) / Matt Textured / Floor / Contempo Arc
Keramik Habitat 60 x 60 (Carilo Talipe) / Matt Textured / Floor / Contempo Arc
Keramik Habitat 60 x 60 (Cementi D Griss) / Matt / Floor / Contempo Arc
Keramik Habitat 60 x 60 (Cementi Griss) / Matt / Floor / Contempo Arc
Keramik Habitat 60 x 60 (Cementi Brown) / Matt / Floor / Contempo Arc
Keramik Habitat 60 x 60 (Cementi Cream) / Matt / Floor / Contempo Arc
11

NO KODE NAMA BARANG MERK SATUAN

A B C

Keramik Habitat 60 x 60 (Lyra Cream) / Glossy / Floor / Contempo Arc


Keramik Habitat 60 x 60 (Lyra Cream Matt) / Matt Satin / Floor / Contempo Arc
Keramik Habitat 60 x 60 (Ara Bella) / Matt Satin / Floor / Wall / Warm Embrace
Keramik Habitat 60 x 60 (Chinos Nero) / Matt Satin / Floor / Warm Embrace
Keramik Habitat 60 x 60 (Chinos Serie) / Matt Satin / Floor / Warm Embrace

KERAMIK DINDING
Keramik Ikad 20 x 25 cm (mozaic) IKAD m2
Keramik Ikad 20 x 25 cm (retro) IKAD m2
Keramik Ikad 20 x 25 cm (marble) IKAD m2
Keramik Roman 20 x 40 cm (Serenity)
Keramik Roman 20 x 40 cm (Twinkle)
Keramik Roman 20 x 40 cm (dLivorno)
Keramik Roman 20 x 40 cm (Urban)
Keramik Roman 20 x 40 cm (dKrikos)
Keramik Roman 20 x 40 cm (dGalleria)
Keramik Roman 20 x 40 cm (Brillo)
Keramik Roman 20 x 40 cm (dRavello)
Keramik Roman 20 x 40 cm (dCanna)
Keramik Roman 20 x 40 cm (dCardiff)
Keramik Roman 20 x 40 cm (dExotic)
Keramik Roman 20 x 40 cm (dTroyes)
Keramik Roman 20 x 40 cm (dNeapolis)
Keramik Roman 20 x 40 cm (dPatron)
Keramik Roman 20 x 40 cm (dTrieste)
Keramik Roman 20 x 40 cm (dTropico)
Keramik Roman 20 x 40 cm (Polka)
Keramik Roman 30 x 30 cm (dPacific)
Keramik Roman 30 x 30 cm (dAtlantic)
Keramik Roman 30 x 30 cm (Radiant)
Keramik Roman 30 x 30 cm (dVitreo)
Keramik Ikad 25 x 40 cm (minimalist) IKAD m2
Keramik Ikad 25 x 40 cm (mozaic) IKAD m2
Keramik Ikad 25 x 40 cm (retro) IKAD m2
Keramik Ikad 25 x 40 cm (marble) IKAD m2
Keramik Platinum 25 x 40 cm (Adore Basic)
Keramik Platinum 25 x 40 cm (Adore Brown Decor Embossed)
Keramik Platinum 25 x 40 cm (Adore Brown Embossed)
Keramik Platinum 25 x 40 cm (Adore Grey Decor Embossed)
Keramik Platinum 25 x 40 cm (Adore Grey Embossed)
Keramik Platinum 25 x 40 cm (Bailey Basic)
Keramik Platinum 25 x 40 cm (Bailey Blue)
Keramik Platinum 25 x 40 cm (Bailey Brown)
Keramik Platinum 25 x 40 cm (Bailey Green)
Keramik Platinum 25 x 40 cm (Bailey Mask)
Keramik Platinum 25 x 40 cm (Balkan Brown)
Keramik Platinum 25 x 40 cm (Balkan Brown Decor Embossed)
Keramik Platinum 25 x 40 cm (Balkan Grey)
Keramik Platinum 25 x 40 cm (Balkan Grey Decor Embossed)
Keramik Platinum 25 x 40 cm (Balkan Brown Basic)
Keramik Platinum 25 x 40 cm (Balkan Grey Basic)
Keramik Platinum 25 x 40 cm (Bari Basic)
Keramik Platinum 25 x 40 cm (Bari Dark Blue)
Keramik Platinum 25 x 40 cm (Bari Dark Grey)
Keramik Platinum 25 x 40 cm (Bari Blue Decor Embossed)
Keramik Platinum 25 x 40 cm (Bari Grey Decor Embossed)
Keramik Platinum 25 x 40 cm (Beatrix Basic / White)
Keramik Platinum 25 x 40 cm (Beatrix Blue)
Keramik Platinum 25 x 40 cm (Beatrix Brown)
Keramik Platinum 25 x 40 cm (Beatrix Green)
Keramik Platinum 25 x 40 cm (Beatrix Grey)
Keramik Platinum 25 x 40 cm (Berlin Brown)
Keramik Platinum 25 x 40 cm (Berlin Brown Decor)
Keramik Platinum 25 x 40 cm (Berlin Grey)
Keramik Platinum 25 x 40 cm (Berlin Grey Decor)
Keramik Platinum 25 x 40 cm (Bianca Blue)
Keramik Platinum 25 x 40 cm (Bianca Brown)
Keramik Platinum 25 x 40 cm (Bianca Green)
Keramik Platinum 25 x 40 cm (Bianca Grey)
Keramik Platinum 25 x 40 cm (Blacius Grey)
Keramik Platinum 25 x 40 cm (Blacius Grey Decor)
Keramik Platinum 25 x 40 cm (Blacius Brown)
Keramik Platinum 25 x 40 cm (Blacius Brown Decor)
Keramik Platinum 25 x 40 cm (Bohemia Basic)
Keramik Platinum 25 x 40 cm (Bohemia Brown)
Keramik Platinum 25 x 40 cm (Bohemia Green)
Keramik Platinum 25 x 40 cm (Bohemia Grey)
Keramik Platinum 25 x 40 cm (Bonia Blue)
Keramik Platinum 25 x 40 cm (Bonia Basic)
Keramik Platinum 25 x 40 cm (Bonia Grey)
Keramik Platinum 25 x 40 cm (Bonia Green)
Keramik Platinum 25 x 40 cm (Bonia Brown)
12

NO KODE NAMA BARANG MERK SATUAN

A B C

Keramik Platinum 25 x 40 cm (Bonza White)


Keramik Platinum 25 x 40 cm (Bonza Matt White)
Keramik Platinum 25 x 40 cm (Bonza Black Embossed)
Keramik Platinum 25 x 40 cm (Boston Basic)
Keramik Platinum 25 x 40 cm (Boston Blue)
Keramik Platinum 25 x 40 cm (Boston Brown)
Keramik Platinum 25 x 40 cm (Boston Green)
Keramik Platinum 25 x 40 cm (Boston Grey)
Keramik Platinum 25 x 40 cm (Brandon Grey)
Keramik Platinum 25 x 40 cm (Brandon Grey Decor)
Keramik Platinum 25 x 40 cm (Brandon Brown)
Keramik Platinum 25 x 40 cm (Brandon Brown Decor)
Keramik Platinum 25 x 40 cm (Brandy Brown)
Keramik Platinum 25 x 40 cm (Brandy Grey)
Keramik Platinum 25 x 40 cm (Brandy White)
Keramik Platinum 25 x 40 cm (Brianna White Embossed)
Keramik Platinum 25 x 40 cm (Brianna Grey Embossed)
Keramik Platinum 25 x 40 cm (Brianna Blue Embossed)
Keramik Platinum 25 x 40 cm (Brianna Green Embossed)
Keramik Platinum 25 x 40 cm (Britania Basic)
Keramik Platinum 25 x 40 cm (Britania Blue)
Keramik Platinum 25 x 40 cm (Britania Green)
Keramik Platinum 25 x 40 cm (Britania Grey)
Keramik Platinum 25 x 40 cm (Brooklyn Grey)
Keramik Platinum 25 x 40 cm (Brooklyn Basic)
Keramik Platinum 25 x 40 cm (Brooklyn Green)
Keramik Platinum 25 x 40 cm (Brooklyn Brown)
Keramik Platinum 25 x 40 cm (Brooklyn Blue)
Keramik Platinum 25 x 40 cm (Hakone Basic)
Keramik Platinum 25 x 40 cm (Hakone Blue)
Keramik Platinum 25 x 40 cm (Hakone Brown)
Keramik Platinum 25 x 40 cm (Hakone Grey)
Keramik Platinum 25 x 40 cm (Hayden Blue)
Keramik Platinum 25 x 40 cm (Hayden Blue Decor)
Keramik Platinum 25 x 40 cm (Hayden Green)
Keramik Platinum 25 x 40 cm (Hayden Green Decor)
Keramik Platinum 25 x 40 cm (Hayden Orange)
Keramik Platinum 25 x 40 cm (Hayden Orange Decor)
Keramik Platinum 25 x 40 cm (Hayden Purple)
Keramik Platinum 25 x 40 cm (Hayden Purple Decor)
Keramik Platinum 25 x 40 cm (Hector Brown Basic)
Keramik Platinum 25 x 40 cm (Hector Grey Basic)
Keramik Platinum 25 x 40 cm (Hector Brown Basic)
Keramik Platinum 25 x 40 cm (Hector Grey Embossed)
Keramik Platinum 25 x 40 cm (Hellios Brown Basic)
Keramik Platinum 25 x 40 cm (Hellios Grey Basic)
Keramik Platinum 25 x 40 cm (Hellios Brown Embossed)
Keramik Platinum 25 x 40 cm (Hellios Grey Embossed)
Keramik Platinum 25 x 40 cm (Holden Basic)
Keramik Platinum 25 x 40 cm (Holden Brown Embossed)
Keramik Platinum 25 x 40 cm (Holden Grey Embossed)
Keramik Platinum 25 x 40 cm (Holden Dark Grey)
Keramik Platinum 25 x 40 cm (Nino Basic)
Keramik Platinum 25 x 40 cm (Nino Cream)
Keramik Platinum 25 x 40 cm (Nino Cream Decor)
Keramik Platinum 25 x 40 cm (Nino Grey)
Keramik Platinum 25 x 40 cm (Nino Grey Decor)
Keramik Ikad 25 x 50 cm (dHouston)
Keramik Ikad 25 x 50 cm (dArtemis)
Keramik Ikad 25 x 50 cm (dParma)
Keramik Ikad 25 x 50 cm (dBrussel)
Keramik Ikad 25 x 50 cm (dPescara)
Keramik Ikad 25 x 50 cm (dStrenna)
Keramik Ikad 25 x 50 cm (dTeramo)
Keramik Ikad 25 x 50 cm (Rhapsody)
Keramik Ikad 25 x 50 cm (dMadeleine)
Keramik Ikad 25 x 50 cm (dFresno)
Keramik Platinum 25 x 50 cm (Calvin Basic)
Keramik Platinum 25 x 50 cm (Calvin Blue)
Keramik Platinum 25 x 50 cm (Calvin Brown)
Keramik Platinum 25 x 50 cm (Calvin Green)
Keramik Platinum 25 x 50 cm (Calvin Grey)
Keramik Platinum 25 x 50 cm (Calypso Basic Embossed)
Keramik Platinum 25 x 50 cm (Calypso Brown Embossed)
Keramik Platinum 25 x 50 cm (Calypso Blue Embossed)
Keramik Platinum 25 x 50 cm (Calypso Green Embossed)
Keramik Platinum 25 x 50 cm (Carla Basic)
Keramik Platinum 25 x 50 cm (Carla Blue)
Keramik Platinum 25 x 50 cm (Carla Brown)
Keramik Platinum 25 x 50 cm (Carla Green)
Keramik Platinum 25 x 50 cm (Carla Grey)
Keramik Platinum 25 x 50 cm (Carmen Grey)
13

NO KODE NAMA BARANG MERK SATUAN

A B C

Keramik Platinum 25 x 50 cm (Carmen Brown)


Keramik Platinum 25 x 50 cm (Carmen Grey Decor)
Keramik Platinum 25 x 50 cm (Carmen Brown Decor)
Keramik Platinum 25 x 50 cm (Chloe Basic)
Keramik Platinum 25 x 50 cm (Chloe Blue)
Keramik Platinum 25 x 50 cm (Chloe Brown)
Keramik Platinum 25 x 50 cm (Chloe Green)
Keramik Platinum 25 x 50 cm (Chloe Grey)
Keramik Platinum 25 x 50 cm (Chloe Grey Basic)
Keramik Platinum 25 x 50 cm (Claire Brown Basic)
Keramik Platinum 25 x 50 cm (Claire Grey Decor)
Keramik Platinum 25 x 50 cm (Claire Brown Decor)
Keramik Platinum 25 x 50 cm (Clarin Basic)
Keramik Platinum 25 x 50 cm (Clarin Blue)
Keramik Platinum 25 x 50 cm (Clarin Brown)
Keramik Platinum 25 x 50 cm (Clarin Green)
Keramik Platinum 25 x 50 cm (Clarin Grey)
Keramik Habitat 25 x 50 cm (Filippo) / Glossy / Wall / Marbella
Keramik Habitat 25 x 50 cm (Filippo Chess) / Glossy / Wall / Marbella
Keramik Habitat 25 x 50 cm (Filippo Geos) / Glossy / Wall / Marbella
Keramik Habitat 25 x 50 cm (Gaudi) / Glossy / Wall / Marbella
Keramik Habitat 25 x 50 cm (Gaudi Geos) / Glossy Textured / Wall / Marbella
Keramik Habitat 25 x 50 cm (Visconti) / Glossy / Wall / Marbella
Keramik Habitat 25 x 50 cm (Biella Antique) / Matt Textured / Wall / Floor / Linea
Keramik Habitat 25 x 50 cm (Biella Walnut) / Matt Textured / Wall / Floor / Linea
Keramik Habitat 25 x 50 cm (Biella Ebony) / Matt Textured / Wall / Floor / Linea
Keramik Habitat 25 x 50 cm (Biella Gold) / Matt Textured / Wall / Floor / Linea
Keramik Habitat 25 x 50 cm (Biella Cherry) / Matt Textured / Wall / Floor / Linea
Keramik Habitat 25 x 50 cm (Biella Natural) / Matt Textured / Wall / Floor / Linea
Keramik Habitat 25 x 50 cm (Granada Smoke) / Matt Textured / Wall / Floor / Linea
Keramik Habitat 25 x 50 cm (Granada Maple) / Matt Textured / Wall / Floor / Linea
Keramik Habitat 25 x 50 cm (Granada Ash) / Matt Textured / Wall / Floor / Linea
Keramik Habitat 25 x 50 (Linea Cherry) / Matt / Wall / Floor / Linea
Keramik Habitat 25 x 50 (Linea Maple) / Matt / Wall / Floor / Linea
Keramik Habitat 25 x 50 (Godiva Black) / Matt Textured / Wall / Floor / Contempo Arc
Keramik Habitat 25 x 50 (Godiva Grey) / Matt Textured / Wall / Floor / Contempo Arc
Keramik Habitat 25 x 50 (Godiva Cream) / Matt Textured / Wall / Floor / Contempo Arc
Keramik Habitat 25 x 50 (Godiva Brown) / Matt Textured / Wall / Floor / Contempo Arc
Keramik Habitat 25 x 50 (Lotus Grey) / Matt / Wall / Floor / Contempo Arc
Keramik Habitat 25 x 50 (Lyra Cream) / Glossy / Wall / Contempo Arc
Keramik Habitat 25 x 50 (Lyra Cream Matt) / Matt Satin / Wall / Contempo Arc
Keramik Habitat 25 x 50 (Metro Brown) / Matt Structured / Wall / Contempo Arc
Keramik Habitat 25 x 50 (Metro Gris) / Matt Structured / Wall / Contempo Arc
Keramik Habitat 25 x 50 (Spark Carbon) / Matt / Wall / Floor / Contempo Arc
Keramik Habitat 25 x 50 (Spark Sand) / Matt / Wall / Floor / Contempo Arc
Keramik Habitat 25 x 50 (Spark Canvas) / Matt / Wall / Floor / Contempo Arc
Keramik Habitat 25 x 50 (Spark Bronze) / Matt / Wall / Floor / Contempo Arc
Keramik Habitat 25 x 50 (Terra Cotta) / Matt Structured / Wall / Contempo Arc
Keramik Habitat 25 x 50 (Terra White) / Matt Structured / Wall / Contempo Arc
Keramik Habitat 25 x 50 (Terra Gris) / Matt Structured / Wall / Contempo Arc
Keramik Habitat 25 x 50 cm (Alpha Nero) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 25 x 50 cm (Alpha Gris) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 25 x 50 cm (Alpha Bianca) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 25 x 50 cm (Alpha Ebano) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 25 x 50 cm (Alpha Ivory) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 25 x 50 cm (Isla Oyster) / Glossy / Wall / Warm Embrace
Keramik Habitat 25 x 50 cm (Isla Light Oyster) / Glossy / Wall / Warm Embrace
Keramik Habitat 25 x 50 (Andara White) / Glossy / Wall / Pop Art
Keramik Habitat 25 x 50 (Andara Crema) / Glossy / Wall / Pop Art
Keramik Habitat 25 x 50 (Andara Black) / Glossy / Wall / Pop Art
Keramik Habitat 25 x 50 (Bricks White) / Glossy Structured / Wall / Pop Art
Keramik Habitat 25 x 50 (Bricks Nero) / Glossy Structured / Wall / Pop Art
Keramik Habitat 25 x 50 (Bricks Deco) / Glossy Structured / Wall / Pop Art
Keramik Habitat 25 x 50 (Ciro Bianco) / Glossy / Wall / Pop Art
Keramik Habitat 25 x 50 (Claire White) / Glossy / Wall / Pop Art
Keramik Habitat 25 x 50 (Claire Black) / Glossy / Wall / Pop Art
Keramik Keramik Habitat 50 x 50 (Keramik Habitat 25 x 50 (Trazzo Sunkist) / Matt Satin / Wall / Pop Art Keramik H
Keramik Habita
Keramik Habitat 25 x 50 (Stella Light Cream) / Matt Textured / Wall / Shabby Chic
Keramik Habitat 25 x 50 (Stella Fiore Light Cream) / Matt Textured / Wall / Shabby Chic
Keramik Habitat 25 x 50 (Stella Light Bone) / Matt Textured / Wall / Shabby Chic
Keramik Habitat 25 x 50 (Stella Fiore Light Bone) / Matt Textured / Wall / Shabby Chic
Keramik Ikad 30 x 60 cm (minimalist) IKAD m2
Keramik Ikad 30 x 60 cm (mozaic) IKAD m2
Keramik Ikad 30 x 60 cm (retro) IKAD m2
Keramik Ikad 30 x 60 cm (marble) IKAD m2
Keramik Ikad 30 x 60 cm (stone) IKAD m2
Keramik Roman 30 x 60 cm (SnowWhite)
Keramik Roman 30 x 60 cm (dNeutra)
Keramik Roman 30 x 60 cm (Blink)
Keramik Roman 30 x 60 cm (dCaliza)
Keramik Roman 30 x 60 cm (dCampania)
Keramik Roman 30 x 60 cm (dCleopatra)
14

NO KODE NAMA BARANG MERK SATUAN

A B C

Keramik Roman 30 x 60 cm (dColosseum)


Keramik Roman 30 x 60 cm (dMarmo)
Keramik Roman 30 x 60 cm (dMohave)
Keramik Roman 30 x 60 cm (Carrara WT 30x60)
Keramik Roman 30 x 60 cm (dRubix)
Keramik Roman 30 x 60 cm (dSerio)
Keramik Roman 30 x 60 cm (dSimpleza)
Keramik Essenza 30 x 60 (Marble Crema)
Keramik Essenza 30 x 60 (Marble Tevere White)
Keramik Essenza 30 x 60 (Stone Landmark White)
Keramik Essenza 30 x 60 (Classic Absolute White)
Keramik Essenza 30 x 60 (Lavagna White)
Keramik Essenza 30 x 60 (Marble Tevere Beige)
Keramik Essenza 30 x 60 (Marble Lara)
Keramik Essenza 30 x 60 (Stone Landmark Beige)
Keramik Essenza 30 x 60 (Marble Pietra)
Keramik Essenza 30 x 60 (Stone Landmark Grey)
Keramik Essenza 30 x 60 (Stone Landmark Dark Grey)
Keramik Essenza 30 x 60 (Graniti Beola Grey)
Keramik Essenza 30 x 60 (Classic Absolute Grey)
Keramik Essenza 30 x 60 (Lavagna Grey)
Keramik Essenza 30 x 60 (Cemento Gris)
Keramik Essenza 30 x 60 (Cemento Grigio)
Keramik Essenza 30 x 60 (Graniti Grigio Perla)
Keramik Essenza 30 x 60 (Classic Absolute Black)
Keramik Essenza 30 x 60 (Graniti Carbone)
Keramik Essenza 30 x 60 (Cemento Carbone)
Keramik Essenza 30 x 60 (Lavagna Black)
Keramik Essenza 30 x 60 (Essenza Wood Ash)
Keramik Essenza 30 x 60 (Wood Pine)
Keramik Essenza 30 x 60 (Wood Maple)
Keramik Essenza 30 x 60 (Wood Oak)
Keramik Platinum 30 x 60 (Bonza White) IKAD m2
Keramik Platinum 30 x 60 (Dexa Cream Basic) IKAD m2
Keramik Platinum 30 x 60 (Dexa Grey Basic)
Keramik Platinum 30 x 60 (Dexa Cream Decor)
Keramik Platinum 30 x 60 (Dexa Grey Decor)
Keramik Platinum 30 x 60 (Dexa Cream Embossed)
Keramik Platinum 30 x 60 (Dexa Grey Embossed)
Keramik Platinum 30 x 60 (Taylor Green)
Keramik Platinum 30 x 60 (Taylor Basic)
Keramik Platinum 30 x 60 (Taylor Grey)
Keramik Platinum 30 x 60 (Taylor Brown)
Keramik Platinum 30 x 60 (Taylor Blue)
Keramik Platinum 30 x 60 (Tiffany Rec Grey Decor Embossed)
Keramik Platinum 30 x 60 (Tiffany Rec Basic Embossed)
Keramik Platinum 30 x 60 (Toronto Rec Grey Embossed)
Keramik Platinum 30 x 60 (Toronto Rec Grey)
Keramik Platinum 30 x 60 (Toronto Rec Grey Decor)
Keramik Platinum 30 x 60 (Toscana Blue)
Keramik Platinum 30 x 60 (Toscana Blue Decor)
Keramik Platinum 30 x 60 (Toscana Grey)
Keramik Platinum 30 x 60 (Toscana Grey Decor)
Keramik Platinum 30 x 60 (Toscana Brown)
Keramik Platinum 30 x 60 (Toscana Brown Decor)
Keramik Platinum 30 x 60 (Tracy Rec Grey)
Keramik Platinum 30 x 60 (Tracy Rec Basic)
Keramik Platinum 30 x 60 (Trevor Cream Decor Embossed)
Keramik Platinum 30 x 60 (Trevor Cream Basic Embossed)
Keramik Platinum 30 x 60 (Trevor Grey Decor Embossed)
Keramik Platinum 30 x 60 (Trevor Grey Basic Embossed)
Keramik Platinum 30 x 60 (Trinity Brown)
Keramik Platinum 30 x 60 (Trinity Grey)
Keramik Platinum 30 x 60 (Trinity White)
Keramik Platinum 30 x 60 (Tristan Basic)
Keramik Platinum 30 x 60 (Tristan Blue)
Keramik Platinum 30 x 60 (Tristan Green)
Keramik Platinum 30 x 60 (Tristan Grey)
Keramik Platinum 30 x 60 (Tunisia Rec Grey Basic)
Keramik Platinum 30 x 60 (Tunisia Rec Grey Decor)
Keramik Platinum 30 x 60 (Tunisia Rec Brown Basic)
Keramik Platinum 30 x 60 (Tunisia Rec Brown Decor)
Keramik Habitat 30 x 60 (Brescia Gris) / Glossy / Wall / Marbella
Keramik Habitat 30 x 60 (Brescia Bone) / Glossy / Wall / Marbella
Keramik Habitat 30 x 60 (Brescia Deco) / Glossy / Wall / Marbella
Keramik Habitat 30 x 60 (Brescia Brown) / Glossy / Wall / Marbella
Keramik Habitat 30 x 60 (Brescia Ivory) / Glossy / Wall / Marbella
Keramik Habitat 30 x 60 (Briana) / Glossy Structured / Wall / Marbella
Keramik Habitat 30 x 60 (Briana Nero) / Glossy Structured / Wall / Marbella
Keramik Habitat 30 x 60 cm (Gaudi Naturale) / Matt Satin / Wall / Floor / Marbella
Keramik Habitat 30 x 60 cm (Trista) / Glossy / Wall / Marbella
Keramik Habitat 30 x 60 cm (Trista Geo) / Glossy Textured / Wall / Marbella
15

NO KODE NAMA BARANG MERK SATUAN

A B C

Keramik Habitat 30 x 60 cm (Ventino Bone) / Glossy / Wall / Marbella


Keramik Habitat 30 x 60 cm (Ventino Mocca) / Glossy / Wall / Marbella
Keramik Habitat 30 x 60 cm (Ventino Deco Bone) / Glossy Textured / Wall / Marbella
Keramik Habitat 30 x 60 cm (Ventino Deco Mocca) / Glossy Textured / Wall / Marbella
Keramik Habitat 30 x 60 cm (Visconti) / Glossy / Wall / Marbella
Keramik Habitat 30 x 60 cm (Visconti Naturale) / Matt Satin / Wall / Marbella
Keramik Habitat 30 x 60 cm (Visconti Deco) / Glossy / Wall / Marbella
Keramik Habitat 30 x 60 cm (Zelda Gris) / Glossy / Wall / Marbella
Keramik Habitat 30 x 60 cm (Zelda Beige) / Glossy / Wall / Marbella
Keramik Habitat 30 x 60 cm (Zelda Deco Gris) / Glossy Textured / Wall / Marbella
Keramik Habitat 30 x 60 cm (Zelda Deco Beige) / Glossy Textured / Wall / Marbella
Keramik Habitat 30 x 60 cm (Allure Cream) / Glossy Structured / Wall / Warm Embrace
Keramik Habitat 30 x 60 cm (Allure Deco Cream) / Glossy Structured / Wall / Warm Embrace
Keramik Habitat 30 x 60 cm (Alpha Nero) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 30 x 60 cm (Alpha Gris) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 30 x 60 cm (Alpha Bianca) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 30 x 60 cm (Alpha Ebano) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 30 x 60 cm (Alpha Ivory) / Glossy Textured / Floor / Warm Embrace
Keramik Habitat 30 x 60 (Ara Bella) / Matt Satin / Floor / Wall / Warm Embrace
Keramik Habitat 30 x 60 (Ara Cream) / Matt Satin / Floor / Wall / Warm Embrace
Keramik Habitat 30 x 60 (Azure Ice) / Glossy Textured / Wall / Warm Embrace
Keramik Habitat 30 x 60 (Azure Smoke) / Glossy Textured / Wall / Warm Embrace
Keramik Habitat 30 x 60 (Oreo Black) / Matt Satin / Wall / Floor / Shabby Chic
Keramik Habitat 30 x 60 (Snow White) / Matt Satin / Wall / Floor / Shabby Chic
Keramik Platinum 30 x 75 (Bonza White)
Keramik Platinum 30 x 75 (Edeco Dark Grey Embossed)
Keramik Platinum 30 x 75 (Edeco White Embossed)
Keramik Platinum 30 x 75 (Edeco Dark Grey Panel)
Keramik Platinum 30 x 75 (Edeco Dark Grey Decor)
Keramik Platinum 30 x 75 (Edeco Bonza White)
Keramik Platinum 30 x 75 (Edeco Dark Grey Decor Panel)
Keramik Platinum 30 x 75 (Elena Dark Grey Embossed)
Keramik Platinum 30 x 75 (Elena Dark Yellow Embossed)
Keramik Platinum 30 x 75 (Elena Grey Decor Rec)
Keramik Platinum 30 x 75 (Elena Yellow Decor Rec)
Keramik Platinum 30 x 75 (Elia Brown Panel Embossed 1)
Keramik Platinum 30 x 75 (Elia Grey Panel Embossed 1)
Keramik Platinum 30 x 75 (Elia Brown Basic Embossed)
Keramik Platinum 30 x 75 (Elia Grey Basic Embossed)
Keramik Platinum 30 x 75 (Elia Grey Panel Embossed 2)
Keramik Platinum 30 x 75 (Elia Brown Panel Embossed 2)
Keramik Platinum 30 x 75 (Elia Brown Panel Embossed 3)
Keramik Platinum 30 x 75 (Elia Grey Panel Embossed 3)
Keramik Platinum 30 x 75 (Elia Grey Embossed)
Keramik Platinum 30 x 75 (Elia Brown Embossed)
Keramik Platinum 30 x 75 (Enova Basic Rec)
Keramik Platinum 30 x 75 (Enova Cream Rec)
Keramik Platinum 30 x 75 (Enova Decor Rec)
Keramik Platinum 30 x 75 (Enova Grey Rec)
Keramik Platinum 30 x 75 (Epic Brown Basic)
Keramik Platinum 30 x 75 (Epic Grey Basic)
Keramik Platinum 30 x 75 (Epic Brown Decor)
Keramik Platinum 30 x 75 (Epic Grey Decor)
Keramik Platinum 30 x 75 (Epic Grey Embossed)
Keramik Platinum 30 x 75 (Epic Brown Embossed)
Keramik Platinum 30 x 75 (Etore Cream Decor Embossed)
Keramik Platinum 30 x 75 (Etore Cream Basic)
Keramik Platinum 30 x 75 (Etore Cream)
Keramik Platinum 30 x 75 (Etore Bonza Matt White)
Keramik Platinum 30 x 75 (Evora Dark Brown Embossed)
Keramik Platinum 30 x 75 (Evora Dark Grey Embossed)
Keramik Platinum 30 x 75 (Evora Brown Decor 3)
Keramik Platinum 30 x 75 (Evora Grey Decor 3)
Keramik Ikad 40 x 80 cm (marble)
Keramik Ikad 40 x 80 cm (wood)

INESA
#REF! Keramik 30 x 30 Kelas I (Onyx Phyrus Ruby Jade, P) m2
#REF! Keramik 30 x 30 Kelas I (Onyx Phyrus Ruby Jade, UP) m2
#REF! Keramik 30 x 30 Kelas I (Pearl Ghita Cat Eye, P) m2
#REF! Keramik 30 x 30 Kelas I (Pearl Ghita Cat Eye, UP) m2
#REF! Keramik 30 x 30 Kelas I (Sand Wheat Spruce Clay Charcoal, R) m2
#REF! Keramik 40 x 40 Kelas I (Corypha Roystonea Raphia, P) m2
#REF! Keramik 40 x 40 Kelas I (Onyx Phyrus Ruby Jade, P) m2
#REF! Keramik 40 x 40 Kelas I (Onyx Phyrus Ruby Jade, UP) m2
#REF! Keramik 40 x 40 Kelas I (Pearl Ghita Cat Eye, P) m2
#REF! Keramik 40 x 40 Kelas I (Pearl Ghita Cat Eye, UP) m2
#REF! Keramik 60 x 60 Kelas I (Corypha Roystonea Raphia, P) m2

SINCERE
#REF! Granit rocktile brown L.60 m2
#REF! Granit polished nano L.60 m2
16

NO KODE NAMA BARANG MERK SATUAN

A B C

#REF! Granit micro crystal L.60 m2


#REF! Granit white nano L.60 m2
#REF! Granit natural marble wht L.60 m2
#REF! Granit popular wht L.60 m2
#REF! Granit micro diamond wht L. 60 m2
#REF! Granit micro diamond blk L. 60 m2
#REF! Granit poly cristal cream L. 60 m2

GRANITO
#REF! Granito Castello Tera 60 x 60 m2
#REF! Granito Monalisa TD6602 60 x 60 m2
#REF! Granito Monalisa TD6602 80 x 80 m2
#REF! Granito Niro FR660IY 60 x 60 m2
#REF! Granito Essenza Grey 60 x 60 m2
#REF! Granito Indogress Cristallo 80 x 80 m2
#REF! Granito salsa ivary 40 x 40 polished m2
#REF! Granito salsa ivary 40 x 40 unpolished m2
#REF! Granito salsa ivary 60 x 60 polished m2
#REF! Granito salsa ivary 60 x 60 unpolished m2
#REF! Granito salsa ivary 80 x 80 polished m2
#REF! Granito salsa ivary 30 x 60 polished m2
#REF! Granito palazzo monza 60 x 60 polished m2
#REF! Granito Aurora silk 60 x 60 polished m2
#REF! Granito Aurora silk 30 x 60 polished m2
#REF! Granito sabbia villa 60 x 60 polished m2
#REF! Granito castello rosso 40 x 40 unpolished m2
#REF! Granito castello pietra 60 x 60 unpolished m2
#REF! Granito lunar terra 30 x 60 unpolished m2
#REF! Granito lunar terra 60 x 60 unpolished m2
#REF! Granito lunar alumina 60 x 60 unpolished m2
#REF! Granito lunar alumina 30 x 60 unpolished m2

MARMER
#REF! Marmer cream BA 60 x 60 m2
#REF! Marmer cream BA 40 x 40 m2
#REF! Marmer cream BA 30 x 30 m2
#REF! Marmer Bianco Rhino 100 x 100 m2
#REF! Marmer White Pearl m2
#REF! Marmer Bianco Turco m2
#REF! Marmer Astana Silver m2
#REF! Marmer Rosso Alicante m2
#REF! Marmer Crystal Blue m2
#REF! Batu Granit Black m2

MOZAIK
#REF! Mozaik keramik zehn MC 04 green crystal glass 30 x 30 biji
#REF! Mozaik batu alam 30 x 30 biji
#REF! Venus Indigo rimple black 30 x 30 x 8 mm m2
#REF! Venus Indigo linear 30 x 30 x 8 mm m2
#REF! Venus Indigo rimple black 30 x 30 x 8 mm m2
#REF! Venus painting 30 x 30 x 8 mm m2
#REF! Venus indigo rimple blue combination 30 x 30 x 8 mm m2
#REF! Venus indigo grey 30 x 30 x 8 mm m2
#REF! Venus indigo gold 30 x 30 x 8 mm m2

ASIA
#REF! Keramik 20 x 25 kelas I m2
#REF! Keramik 30 x 30 kelas I nirwana cream m2
#REF! Keramik 30 x 30 kelas I ocsar taupe m2
#REF! Keramik 40 x 40 kelas I nirwana green m2
#REF! Keramik 10 x 20 kelas II m2
#REF! Keramik 20 x 20 kelas I m2
#REF! Keramik 20 x 30 kelas II m2
#REF! Keramik 30 x 30 kelas II m2
#REF! Keramik 40 x 40 kelas II m2

MULIA
#REF! Keramik 10 x 20 cm kelas I m2
#REF! Keramik 20 x 20 cm kelas I m2
#REF! Keramik 20 x 30 cm kelas I m2
#REF! Keramik 30 x 30 cm kelas I m2
#REF! Keramik 40 x 40 cm kelas I signature neo pebble sand m2
#REF! Keramik 10 x 20 cm kelas II m2
#REF! Keramik 20 x 20 cm kelas II m2
#REF! Keramik 20 x 30 cm kelas II m2
#REF! Keramik 30 x 30 cm kelas II m2
#REF! Keramik 40 x 40 cm kelas II m2

UBIN/ TEGEL LANTAI


#REF! Ubin/ tegel polos m2
#REF! Ubin/ tegel warna m2
#REF! Ubin terasso m2
17

NO KODE NAMA BARANG MERK SATUAN

A B C

KARPET
#REF! Karpet roll loop atrium m2
#REF! Karpet roll loop Bali m2
#REF! Karpet roll loop Breeze Plus m2
#REF! Karpet roll loop Callaway m2
#REF! Karpet roll loop caprice m2
#REF! Karpet roll loop checkmate m2
#REF! Karpet roll loop crown m2
#REF! Karpet roll loop emperor m2
#REF! Karpet roll loop florance m2
#REF! Underlayer /pelapis bawah karpet m2

PARQUET/ FLOORING/ DECKING/HPL


#REF! Parquet Jati 1.2cm x 5cm x 17cm m2
#REF! Parquet Jati 1.2cm x 5cm x 20cm m2
#REF! Parquet Jati 1.2cm x 5cm x 25cm m2
#REF! Parquet Jati 1.2cm x 5cm x 30cm m2
#REF! Lamparquet (lantai kayu merbau) 1 cm x 5cm x 20cm m2
#REF! Lamparquet (lantai kayu merbau) 1 cm x 5cm x 25cm m2
#REF! Lamparquet (lantai kayu merbau) 1 cm x 5cm x 30cm m2
#REF! Flooring 1.5cm x 9cm x 30cm – 90cm m2
#REF! Flooring Lokal 1.5cm x 8.5cm x 30cm m2
#REF! Flooring Lokal 1.5cm x 12cm x 30cm -40cm (jumbo) m2
#REF! Flooring Lokal 1.5cm x 12cm x 60cm up (jumbo export) m2
#REF! Decking Kayu Merbau 1,9cm x 9cm x 140cm -up m2
#REF! Decking Kayu Bengkirai 1,9cm x 9cm x 180cm -up m2
#REF! Decking Kayu Kruing 1,9cm x 9cm x 180cm -up m2
#REF! Decking Kayu Ulin 1,9cm x 9cm x 100cm – up m2
#REF! HPL ( MATTE AND TEXTURE ) m2
#REF! Wallpaper motif clear spirit 10 x 0.5 roll

SANITAIR
#REF! Bak mandi fibre glass 55x55x60 cm bh
#REF! Bak mandi keramik 50x50 bh
#REF! Floor Drain " TOTO TypeTx 1 Bv 1 " Square Flange " bh
#REF! Floor drain plastik bh
#REF! Floor drain stainless bh
#REF! Jetwasher TOTO THX20MCRB bh
#REF! Kloset duduk Amerika Standar ECST wht bh
#REF! Kloset duduk OULU A626 wht bh
#REF! Kloset duduk Zehn 040 A wht bh
#REF! Kloset duduk "TOTO Type CW 421 + TCW 07 tangki bulat bh
#REF! Kloset duduk "TOTO Type CW 660 + TCW 07 tangki kotak bh
#REF! Kloset duduk "TOTO Type AVANTE CW 821J"/SW 821JP COMPLIT bh
#REF! Kloset duduk " TOTO Type AVANTE CW 823 J bh
#REF! Kloset duduk " TOTO Type CW 660J complit bh
#REF! Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT bh
#REF! Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT WARNA bh
#REF! Kloset duduk " TOTO Type CW 420 wht bh
#REF! Kloset duduk " TOTO Type CW 637 wht bh
#REF! Kloset duduk " TOTO Type CW 661JT1" / SW 661JP COMPLIT bh
#REF! Kloset duduk " TOTO Type CW 661JT1" / SW 784JP COMPLIT bh
#REF! Kloset jongkok " TOTO komplit wht Ce 6 bh
#REF! Kloset jongkok " TOTO komplit wht Ce 9 bh
#REF! Kloset jongkok " TOTO CE -7P ivory CL bh
#REF! Kloset jongkok " TOTO CE-7 white CL bh
#REF! Kloset porselin jongkok Kia (standar) bh
#REF! Kloset porselin jongkok pozzi bh
#REF! Kloset porselin jongkok liga bh
#REF! Kloset porselin jongkok Ina (standar) bh
#REF! Kran TOTO T 205 LCSC bh
#REF! Kran TOTO T 205 MC bh
#REF! Kran TOTO T 23 B13 bh
#REF! Kran TOTO T 23 B13V7N bh
#REF! Kran TOTO T 26-13 bh
#REF! Kran TOTO TX 109 LD bh
#REF! Penyekat Urinoir " TOTO " Type A 100 "white bh
#REF! Shower Spray " TOTO Tx 403SPIV ( Pastel Ivory ) bh
#REF! Soap holder " TOTO Type S 6 N'' bh
#REF! Shower Spray " TOTO Tx 474 SRR REIR single lever bh
#REF! Shower Spray " TOTO Tv 471 SP plano single lever B ath bh
#REF! Shower head Spray TOTO bh
#REF! Shower Spray " ONDA bh
#REF! Soap holder Biasa Trisensa bh
#REF! Seal tape ONDA bh
#REF! Urinoir " TOTO komplit bh
#REF! Urinoir " American standard m1w bh
#REF! Urinoir " HCG u999m bh
#REF! Wastafel american Standard studio bh
#REF! Wastafel HCG l61 bh
#REF! Wastafel Komplit " Tidy 001b bh
18

NO KODE NAMA BARANG MERK SATUAN

A B C

#REF! Wastafel Komplit top Counter" TOTO " Type CERABO LW 523 " bh
#REF! Wastafel Toto komplit LW631JW/F segi 4 bh
#REF! Wastafel Toto LW352JW/F bulat bh
#REF! Wastafel Toto komplit LW645+T6JV5 kotak bh
#REF! Wastafel Toto LW248JR bh
#REF! Waterdrain bh
#REF! Shower ONDA exclusive s.80 bh
#REF! Shower ONDA eco sense bh
#REF! Shower ONDA eco sns.931 bh
#REF! Shower CARLO exclusive bh
#REF! Tidy cuci piring doble bh
#REF! Tidy cuci piring single bh
#REF! Zehn cuci piring doble bh
#REF! Biotank Pabrikan unit
#REF! Stop Kran bh

PAKU
PK.10 Paku 10 cm Kg
PK.KLSBRD Paku kalsiboard Kg
PK.LST Paku list SQ Kg
PK.PCG Paku pancing 60 x 230 Kg
PK.RNG/USK Paku reng/usuk SQ Kg
PK.SNG Paku seng Kg
PK.SNG.IPT Paku seng import Biji
PK.SKP.1/2 Paku skrup 1/2" Kg
PK.SKP.2 Paku skrup 2" Kg
PK.SKP.3,5 Paku skrup 3.5" Kg
PK.SBT.1/2 Paku sumbat 1/2" Kg
PK.BTN.5 Paku beton 5 cm Kg
DNB.12 Dinabolt Ø 12mm M12 X 75 Buah

PASIR
PSR.HLS Pasir halus (diayak) m3
PSR.BTN Pasir beton / cor Ex. 4 per 2,75 m3 m3
PSR.PSG Pasir pasang m3
PSR.URG Pasir urug m3
SRT Sirtu m3

BATU PECAH
BT.PCH.BSR Batu pecah besar m3
BT.PCH-5-7 Batu pecah 5-7 cm (manual) m3
BT.PCH.3-5 Batu pecah 3-5 cm (manual) m3
BT.PCH.2-3 Batu pecah 2-3 cm (manual) m3
KRL.BTN.2-3 Koral Beton 2/3 Ex. 4 per 2,75 m3 m3

BATA MERAH
BT.MRH.5 Bata merah tebal 5 cm Biji
BT.MRH.7 Bata merah tebal 7 cm Biji

BATU KALI
BT.KL Batu kali / batu bulat 15/20 cm m3

KAPUR
KPR.PDM Kapur padam / hydrated lime Kg

TANAH
TNH.LT Tanah liat m3
TNH.URG Tanah urug m3

BATAKO
BTK.BNT Batako kelas I buntu Biji
BTK.LBG Batako kelas I lubang Biji

ROSTER
RST.BT Roster bata Buah
RST.KMK Roster keramik Buah

BATA RINGAN
BT.RGN.70/20 Bata ringan uk. 70/20cm Biji
BT.RGN.7,5x60x20 Bata ringan T.7,5cm, P.60cm, L.20cm, 111 pcs m3
BT.RGN.7,5x60x20.BH Bata ringan T.7,5cm, P.60cm, L.20cm Biji
BT.RGN.10x60x20 Bata ringan T.10cm, P.60cm, L.20cm, 83 pcs m3
BT.RGN.10x60x20.BH Bata ringan T.10cm, P.60cm, L.20cm Biji
BT.RGN.12,5x60x20 Bata ringan T.12,5cm, P.60cm, L.20cm, 66 pcs m3
BT.RGN.12,5x60x20.BH Bata ringan T.12,5cm, P.60cm, L.20cm Biji
BT.RGN.15x60x20 Bata ringan T.15cm, P.60cm, L.20cm, 55 pcs m3
BT.RGN.15x60x20.BH Bata ringan T.15cm, P.60cm, L.20cm Biji
BT.RGN.17,5x60x20 Bata ringan T.17,5cm, P.60cm, L.20cm, 47 pcs m3
BT.RGN.17,5x60x20.BH Bata ringan T.17,5cm, P.60cm, L.20cm Biji
BT.RGN.20x60x20 Bata ringan T.20cm, P.60cm, L.20cm, 41 pcs m3
BT.RGN.20x60x20.BH Bata ringan T.20cm, P.60cm, L.20cm Biji
19

NO KODE NAMA BARANG MERK SATUAN

A B C

PASIR, BATU, KERIKIL, BATA DAN PARAS


1 Bata gosok ex Tulikup bj
377 Bata press bj
#REF! Batu karang m3
#REF! Batu lahar Singaraja m3
#REF! Batu pipih Singaraja m3
#REF! Bata ryan ( abble ) bj
#REF! Roster Keramik bh
#REF! Limestone m3
#REF! Paras Batik bh
#REF! Paras Buahan bh
#REF! Paras Karang Bukit Tebal 6 cm bh
#REF! Paras Tulung Agung bh
#REF! Paras Malem bh
#REF! Paras Putih Bukit Tebal 6 cm M2
#REF! Paras Silakarang tebal m2
#REF! Paras Silakarang tipis bh
#REF! Paras untuk pondasi bh
#REF! Batu alam RTM hijau 10 x 20 halus m2
#REF! Batu alam RTM hijau 20 x 20 halus m2
#REF! Batu alam RTS hijau 10 x 20 kasar m2
#REF! Batu pilah Jember 30 x 30 m2
#REF! Batu pilah Jember 20 x 30 m2
#REF! Batu pilah Jember 40 x 40 m2
#REF! Batu pilah Singaraja 30 x 30 m2
#REF! Batu pilah Singaraja 20 x 20 m2
#REF! Batu hitam Jember 5 x 20 halus m2
#REF! Batu hitam Jember 20 x 40 halus m2
#REF! Batu hitam Jember 15 x 30 halus m2
#REF! Batu hitam Singaraja 15 x 30 halus m2
#REF! Batu hitam Singaraja 20 x 40 halus m2
#REF! Batu AND 60 x 60 abu m2
#REF! Batu AND 50 x 50 hitam m2
#REF! Batu AND 40 x 40 hitam bkr m2
#REF! Batu AND 30 x 60 hitam bkr m2
#REF! Batu AND 40 x 60 hitam kilap m2
#REF! Batu AND 30 x 40 abu SS m2
#REF! Batu marmer kuning 10 x 20 m2
#REF! Batu marmer kuning PB1 10 x 20 m2
#REF! Batu marmer kuning PB2 10 x 20 m2
#REF! Batu marmer kuning 15 x 30 m2
#REF! Batu kuning serat 30 x 30 m2
#REF! Batu kuning serat 20 x 30 m2
#REF! Batu palimanan cirebon 20 x 30 m2
#REF! Batu palimanan cirebon 20 x 40 m2
#REF! Batu paras Jogja 60 x 60 m2
#REF! Batu paras Jogja putih 20 x 30 bh
#REF! Batu candi hitam 60 x 60 m2
#REF! Batu candi hitam 20 x 20 m2
#REF! Batu candi hitam 30 x 30 m2
#REF! Batu candi hitam 40 x 40 T.5cm m2
#REF! Batu candi hitam 20 x 30 m2
#REF! Batu Bali green gelombang 20 x 40 m2
#REF! Batu Bali green kombinasi 20 x 40 m2
#REF! Batu serayu 20 x 60 m2
#REF! Batu/biji terasso/ batu padalarang kg
#REF! Batu gunung ex karang asem bj
#REF! Loster Ukir paras Cor 30x30 bh
#REF! Terasso cor m3
#REF! Agregat halus m3
#REF! Agregat kasar m3
#REF! Grave I m3
#REF! Bahan Agr. Base kelas A m3
#REF! Bahan Agr. Base kelas B m3
#REF! Bahan Agr. Base kelas C m3
#REF! Paras ex tegal saat bh
#REF! Loster Keramik 30x30 bh

ASPAL DAN BAHAN PELENGKAP JALAN


#REF! Aspal kg
#REF! Filler kg
#REF! Kerosen/ Minyak tanah ltr
#REF! Cat marka kg
#REF! Geotextile m2
#REF! Aspal emulsi kg
#REF! Gebalan rumput m2
#REF! Glass bead kg
#REF! Pelat rambu (eng. Grade) bh
#REF! Pelat rambu (high I. grade) bh
#REF! Rel pengaman m1
#REF! Pemantul cahaya bh
#REF! Asbuton halus ton
20

NO KODE NAMA BARANG MERK SATUAN

A B C

m2
BETON PRACETAK
#REF! SBP Tipe U 30/20/60 (pelaluan air), T=5 (K-350) bh
#REF! SBP Tipe U 30/30/120, T= 10(K-350) bh
#REF! SBP Tipe U 30/50/120, T= 10(K-350) bh
#REF! SBP Tipe U 40/60/120, T= 10(K-350) bh
#REF! SBP Tipe U 60/80/120, T= 10(K-350) bh
#REF! SBP Tipe U 80/80/120, T= 10(K-350) bh
#REF! SBP Tipe U 80/100/120, T= 10(K-350) bh
#REF! SBP Tipe U 100/100/120, T= 10(K-350) bh
#REF! Tutup SBP Tipe U 30 T = 10 (K-350) bh
#REF! Tutup SBP Tipe U 40 T = 10 (K-350) bh
#REF! Tutup SBP Tipe U 50 T = 10 (K-350) bh
#REF! Tutup SBP Tipe U 60 T = 60 (K-350) bh
#REF! Tutup SBP Tipe U 80 T = 10 (K-350) bh
#REF! Tutup SBP Tipe U 100 T = 10 (K-350) bh
#REF! Box Culvert Pracetak Tipe 60/60/120, T = 20 (K-350) bh
#REF! Box Culvert Pracetak Tipe 80/80/120, T = 20 (K-350) bh
#REF! Box Culvert Pracetak Tipe 100/100/120, T = 20 (K-350) bh
#REF! Box Culvert Pracetak Tipe 150/150/120, T = 20 (K-350) bh
#REF! Box Culvert Pracetak Tipe 200/200/120, T = 20 (K-350) bh
#REF! Box Culvert Pracetak Tipe 300/200/120, T = 20 (K-350) bh
#REF! Box Culvert Pracetak Tipe 300/300/120, T = 20 (K-350) bh
#REF! Frame manhole (precast K-350) set
#REF! Cover manhole (precast K-350) set
#REF! Box tangkapan air, T = 10 (K-350) set
#REF! Tutup box tangkapan air, T = 10 (K-350) set
#REF! L Shape 30.60.30.6 cm kg
#REF! L Shape 30.50.30.6 cm ltr
#REF! Penutup 30.30.7 kg
#REF! U 80.15.30.8 cm m2
#REF! Dinding 115.30.8 cm kg
#REF! Penutup 1/2 diad rad R 40-30 cm m2

PIPA
#REF! Pipa Galvanis 1/2" m1
#REF! Pipa Galvanis 3/4" m1
#REF! Pipa Galvanis 1 1/4" m1
#REF! Pipa Galvanis 1 1/2" m1
#REF! Pipa Galvanis 1" m1
#REF! Pipa Galvanis 1,5 BSA m1
#REF! Pipa Galvanis 2" m1
#REF! Pipa Galvanis 3" m1
#REF! Pipa Galvanis 4" m1
#REF! Pipa Maspion AW 1 ljr
#REF! Pipa Maspion AW 1/2 ljr
#REF! Pipa Maspion AW 10 ljr
#REF! Pipa Maspion AW 1-1/2 ljr
#REF! Pipa Maspion AW 1-1/4 ljr
#REF! Pipa Maspion AW 12 ljr
#REF! Pipa Maspion AW 14 ljr
#REF! Pipa Maspion AW 16 ljr
#REF! Pipa Maspion AW 2 ljr
#REF! Pipa Maspion AW 2-1/2 ljr
#REF! Pipa Maspion AW 3 ljr
#REF! Pipa Maspion AW 3/4 ljr
#REF! Pipa Maspion AW 4 ljr
#REF! Pipa Maspion AW 5 ljr
#REF! Pipa Maspion AW 6 ljr
#REF! Pipa Maspion AW 8 ljr
#REF! Pipa AW 10 ljr
#REF! Pipa Maspion C 1 ljr
#REF! Pipa Maspion C 1-1/2 ljr
#REF! Pipa Maspion C 1-1/4 ljr
#REF! Pipa Maspion C 2 ljr
#REF! Pipa Maspion C 2-1/2 ljr
#REF! Pipa Maspion C 3 ljr
#REF! Pipa Maspion C 3/4 ljr
#REF! Pipa Maspion C 4 ljr
#REF! Pipa Maspion C 5/8 ljr
#REF! Pipa Maspion D 10 ljr
#REF! Pipa Maspion D 1-1/2 ljr
#REF! Pipa Maspion D 1-1/4 ljr
#REF! Pipa Maspion D 12 ljr
#REF! Pipa Maspion D 14 ljr
#REF! Pipa Maspion D 16 ljr
#REF! Pipa Maspion D 2 ljr
#REF! Pipa Maspion D 2-1/2 ljr
#REF! Pipa Maspion D 3 ljr
#REF! Pipa Maspion D 4 ljr
#REF! Pipa Maspion D 5 ljr
#REF! Pipa Maspion D 6 ljr
21

NO KODE NAMA BARANG MERK SATUAN

A B C

#REF! Pipa Maspion D 8 ljr


#REF! Pipa HDPE m1
#REF! Pipa Gas Hitan 1/2 m1

PIPA
PIP.STL Pipa stainless 2" m1

AKSESSORIS PIPA
#REF! Stop kran 1' bh
#REF! Roof Drain bh
#REF! Pompa Jet Pump GRUNDFOS JDF 18 bh
#REF! Pompa Jet Pump GRUNDFOS JD Basic 3 bh
#REF! Pompa Jet Pump SHIMIZU PC-250 BIT bh

KRAN AIR
#REF! TOTO T.30AR13V7N bh
#REF! TOTO T.60N bh
#REF! TOTO TX-116 LI bh
#REF! TOTO TX-116 LEBR bh
#REF! TOTO TX 101 LB bh
#REF! ONDA exclusive walltaps bh
#REF! ONDA exclusive basintaps bh
#REF! ONDA walltaps bh
#REF! ONDA sinktaps bh
#REF! ONDA swinging basin bh
#REF! Kran biasa bh
#REF! Kran Sun ei bh

HANDEL PINTU
#REF! Gradino Handel Luar HP.6106 bh
#REF! Gradino Handel Luar HP.99.01 bh
#REF! Solid HRE 99.14 bh
#REF! ELT handle pintu dobel P99.62 set
#REF! ELT handle pintu dobel PR 511.05 set
#REF! ELT bulat PHB 308SS bh
#REF! PALOMA HPP 502 bh
#REF! PALOMA HRP 215 bh
#REF! PALOMA PHP 241 bh
#REF! DEKSON HPT 021 bh
#REF! DEKSON HPT 017 bh
#REF! DEKSON LHP set
#REF! TIDY handle set 905 set
#REF! PALOMA set handle set
#REF! DLD handle bulat set

SEMEN
SMN.BSW.50 Semen bosowa 50 kg Zak
SMN.BSW.KG Semen bosowa Kg
SMN.GRK.40 Semen gresik 40 kg Zak
SMN.GRK.50 Semen gresik 50 kg Zak
SMN.GRK.KG Semen gresik Kg
SMN.TGR.40 Semen tiga roga 40 kg Zak
SMN.TGR.KG Semen tiga roda Kg
SMN.TNS.40 Semen tonasa 40 kg Zak
SMN.TNS.KG Semen tonasa Kg
SMN.WRN Semen warna Kg
SMN.GRT Semen grouting Kg

PANEL BETON
PNL.BTN.40 Panel beton uk. 5 x 40 x 240 Lembar
PNL.BTN.45 Panel beton uk. 5 x 45 x 240 Lembar
PNL.BTN.50 Panel beton uk. 5 x 50 x 240 Lembar

AIR
AIR Air Liter

ZAT ADITIF
ZAT.ADD.STX Damdex/ Strorox - 100 (additive) Liter

MORTAR
MRT.MU-800 Mortar utama (MU-800) non-shrink grout 40 kg Zak
MRT.MU-800.KG Mortar utama (MU-800) non-shrink grout Kg
MSP Mortar siap pakai kg
MRT.MU-100 Mortar utama (MU-100) plesteran premium 40 kg Zak
MRT.MU-100.KG Mortar utama (MU-100) plesteran premium Kg
MRT.MU-200 Mortar utama (MU-200) acian plester dan beton 40 kg Zak
MRT.MU-200.KG Mortar utama (MU-200) acian plester dan beton Kg

READY MIX, SEMEN & AIR CAMPURAN BETON


#REF! Beton Ready Mix m3
- K100 m3
22

NO KODE NAMA BARANG MERK SATUAN

A B C

- K125 m3
- K150 m3
- K175 m3
- K200 m3
- K225 m3
- K275 m3
- K300 m3
- K325 m3
- K350 m3
- K400 m3
- K450 m3
- K500 m3
#REF! Tiang beton uk. 320 x 17 x 18 btg
#REF! Floor hardener kg

WATERSTOP
WTS.PVC.150 Waterstop PVC wsh 150 lebar 150 mm m1
WTS.PVC.200 Waterstop PVC wsh 200 lebar 200 mm m1
WTS.PVC.320 Waterstop PVC wsa 320 lebar 320 mm m1

KAWAT
KWT.BDR Kawat berduri Roll
KWT.BTN.RRT Kawat beton RRT Kg
KWT.LAS.MLD Kawat las untuk mild steel, high tensile steel dan pipe line welding Kg
KWT.LAS.STS Kawat las untuk stainless steel Kg
KWT.LAS.HRD Kawat las untuk hard surfacing Kg
KWT.LAS.CRN Kawat las untuk cast iron Kg
KWT.JRG.GNV.20x20 Kawat jaring galvanis BWG 16 (20mm x 20mm) m2
KWT.JRG.GNV.30x30 Kawat jaring galvanis BWG 16 (30mm x 30mm) m2
KWT.JRG.GNV.45x45 Kawat jaring galvanis BWG 16 (45mm x 45mm) m2
KWT.JRG.GNV.55x55 Kawat jaring galvanis BWG 16 (55mm x 55mm) m2
KWT.NMK Kawat nyamuk m2

BESI BETON
BS.BTN.6PLS Besi beton Ø 6 polos Batang
BS.BTN.6PLS.KG Besi beton Ø 6 polos Kg
BS.BTN.8PLS Besi beton Ø 8 polos Batang
BS.BTN.8PLS.KG Besi beton Ø 8 polos Kg
BS.BTN.10PLS Besi beton Ø 10 polos Batang
BS.BTN.10PLS.KG Besi beton Ø 10 polos Kg
BS.BTN.12PLS Besi beton Ø 12 polos Batang
BS.BTN.12PLS.KG Besi beton Ø 12 polos Kg
BS.BTN.16PLS Besi beton Ø 16 polos Batang
BS.BTN.16PLS.KG Besi beton Ø 16 polos Kg
BS.BTN.10ULR Besi beton Ø 10 ulir Batang
BS.BTN.10ULR.KG Besi beton Ø 10 ulir Kg
BS.BTN.10ULR Besi beton Ø 13 ulir Batang
BS.BTN.10ULR.KG Besi beton Ø 13 ulir Kg
BS.BTN.10ULR Besi beton Ø 16 ulir Batang
BS.BTN.10ULR.KG Besi beton Ø 16 ulir Kg
BS.BTN.10ULR Besi beton Ø 19 ulir Batang
BS.BTN.10ULR.KG Besi beton Ø 19 ulir Kg
BS.BTN.10ULR Besi beton Ø 22 ulir Batang
BS.BTN.10ULR.KG Besi beton Ø 22 ulir Kg

BESI STRIP
BS.STP.KG Besi plat strip Kg
BS.STP.6M Besi plat strip panjang 4 x 30 mm panjang 6 m Batang

WIREMESH
WRM.M4.ROL Wiremesh M4 Roll
WRM.M4.LBR Wiremesh M4 Lembar
WRM.M4.KG Wiremesh M4 Kg
WRM.M5.ROL Wiremesh M5 Roll
WRM.M5.LBR Wiremesh M5 Lembar
WRM.M5.KG Wiremesh M5 Kg
WRM.M6.ROL Wiremesh M6 Roll
WRM.M6.LBR Wiremesh M6 Lembar
WRM.M6.KG Wiremesh M6 Kg
WRM.M7.ROL Wiremesh M7 Roll
WRM.M7.LBR Wiremesh M7 Lembar
WRM.M7.KG Wiremesh M7 Kg
WRM.M8.ROL Wiremesh M8 Roll
WRM.M8.LBR Wiremesh M8 Lembar
WRM.M8.KG Wiremesh M8 Kg

FLOOR DECK
FLR.DCK.0,75 Floor dek 0.75 mm m2
FLR.DCK.0,80 Floor dek 0.8 mm m2

ROLLING DOOR
PTU.RLG.DOR.ALM Pintu rolling door alumunium m2
23

NO KODE NAMA BARANG MERK SATUAN

A B C

PTU.RLG.DOR.BS Pintu rolling door besi m2

PINTU LIPAT
PTU.FLD.DOR.PVC Folding door / pintu lipat PVC m2

ALUMINIUM
ALM.YKK.4 Aluminium 4 inch YKK m1
ALM.STP Aluminium strip / jalusi m1

SEALANT
SLN Sealant Tube

TIRAI
VTS.BLD Venetions blinds dan vertical blinds (tirai) m1

HOLLOW
BS.HLW.50X50X3 Besi hollow (50x50x3) mm panjang 6 m Batang
BS.HLW.40X40X2 Besi hollow (40x40x2) mm panjang 6 m m1

BAJA RINGAN
BJ.RGN.C75 Baja ringan C 75 axis Batang
BJ.RGN.C75.KG Baja ringan C 75 axis Kg
BJ.RGN.C65 Baja ringan C 65 axis Batang
BJ.RGN.C65.KG Baja ringan C 65 axis Kg
BJ.RGN.C55 Baja ringan C 55 axis Batang
BJ.RGN.C55.KG Baja ringan C 55 axis Kg
BJ.RGN.UK75.0,75 Baja ringan UK 75 0.75 axis Batang
BJ.RGN.UK75.0,75.KG Baja ringan UK 75 0.75 axis Kg
BJ.RGN.UK75.0,55 Baja ringan UK 75 0.55 axis Batang
BJ.RGN.UK75.0,55.KG Baja ringan UK 75 0.55 axis Kg
BJ.RGN.UK60.0,55 Baja ringan UK 60 0.55 axis Batang
BJ.RGN.UK60.0,55.KG Baja ringan UK 60 0.55 axis Kg
RNG.BJ.RGN.0,45 Reng baja ringan 0.45 Batang
RNG.BJ.RGN.0,45.M Reng baja ringan 0.45 m1
RNG.BJ.RGN.0,45 Reng baja ringan 0.40 Batang
RNG.BJ.RGN.0,45.M Reng baja ringan 0.40 m1

BESI BETON, ALUMUNIUM DAN PAGAR


#REF! Pagar BRC asli T.120 diameter 6mm m'
#REF! Pagar BRC asli T.150 diameter 6mm m'
#REF! Pagar BRC asli T.175 diameter 7mm m'
#REF! Pagar BRC asli T.190 diameter 7mm m'
#REF! Pagar BRC asli T.90 diameter 6mm m'
#REF! Pagar HotDip Galvanized T.120 diameter 6mm m'
#REF! Pagar HotDip Galvanized T.150 diameter 7mm m'
#REF! Pagar HotDip Galvanized T.175 diameter 7mm m'
#REF! Pagar HotDip Galvanized T.190 diameter 7mm m'
#REF! Pagar HotDip Galvanized T.90 diameter 6mm m'
#REF! Tiang BRC asli T. 120 diameter 1 1/2" bh
#REF! Tiang BRC asli T. 150 diameter 2" bh
#REF! Tiang BRC asli T. 175 diameter 2" bh
#REF! Tiang BRC asli T. 190 diameter 2" bh
#REF! Tiang BRC asli T. 90 diameter 1 1/2" bh
#REF! Tiang HotDip Galvanized T. 120 diameter 1 1/2" bh
#REF! Tiang HotDip Galvanized T. 150 diameter 2" bh
#REF! Tiang HotDip Galvanized T. 175 diameter 2" bh
#REF! Tiang HotDip Galvanized T. 190 diameter 2" bh
#REF! Tiang HotDip Galvanized T. 90 diameter 1 1/2" bh

BAHAN LISTRIK
663 Box panel MCB Inbow isi 4 MCB Hager bh
664 Box panel MCB outbow isi 5 MCB Hager bh
665 Box panel MCB Mini pragma Schneider isi 4 MCB bh
666 Box panel MCB outbow golf isi 4 MCB Hager bh
667 Box panel MCB inbow golf isi 4 MCB Hager bh
668 Isolasi bh
669 Saklar tunggal ( Clipsal) bh
670 Saklar seri (clipsal) bh
Saklar triple (clipsal) bh
671 Stop Kontak (setara clipsal) bh
Stop Kontak AC setara broco bh
672 Fitting bh
673 Steker bh
674 Coaxial cable 5C - 75 ohm commscof m1
675 Kabel NYM 3 x 2.5 mm ex. Supreme m1
676 Kabel NYM 4 mm m1
677 Kabel telephone m1
Kabel antena 5C Beldcu m1
Kabel Data Belden m1
678 Lampu pijar 8 Watt (Philip) bh
679 Lampu pijar 10 Watt (Philip) bh
680 Lampu pijar 15 Watt (Philip) bh
24

NO KODE NAMA BARANG MERK SATUAN

A B C

681 Lampu pijar 25 Watt (Philip) bh


682 Lampu TL 10 Watt (10 Watt) Philip bh
683 Lampu TL 20 Watt (10 Watt) Philip bh
684 Lampu TL 25 Watt (10 Watt) Philip bh
685 Lampu TL 2 x 18 watt RMI Philips TL LED unt
685A Lampu TL 2 x 18 watt RMI Hori TL LED unt
686 Lampu TL 2 x 36 watt RMI Philips TL LED unt
686a Lampu LED Strips / Lampu Selang 7.2 watt m1
686b Led Ultra Thin Downlight DQ-MBR-002 ( Ø145mm) 9 Watt setara Hori bh
687 MCB 6 A Schneider bh
688 MCB 4 A Schneider bh
689 Outlet TV clipsal bh
690 Outlet telepon bh
Outlet data panasonic WEJ2488 bh
691 Pipa clipsal 20 mm bt
692 Pipa flexible clipsal 20 mm m1
693 Sock clipsal 20 mm bj
694 Tee dos clipsal 20 mm bh
695 Klem clipsal 20 mm bj
696 Inbow dos plastik clipsal E 157 P bj
697 Stop kontak terminal tv tanam panasinic wej 2501 + plat wej 78019 bj
698 MCCB 80A 3P MG bj
699 MCB 25A 3P MG bj
700 MCB16A 1P MG bj
701 MCB10A 1P MG bj
702 MCB 6A 1P MG bj
703 Pilot lamp / indikator lamp 220 V bj
704 Voltmeter 0 - 500V bj
705 Ampere meter 0 - 200A bj
706 Travo Arus / CT bj
707 selector Volt 7 position bj
708 Wiring material bj
709 Box indoor 600 x 400 x 250 EX- HAGER bj
710 CU bars + asesoris bj
711 fire extinguizer 9 kg setara VIKING unit
712 AC Wall Mounted 2 PK Setara DAIKIN unit
713 AC Wall Mounted 1 PK Setara DAIKIN unit
714 Exaust pan celling PANASONIC FV-20TGU 8" unit
715 Exaust Hood Modena PX 6001 unit

BUIS BETON
579 Buis beton 20 x 75 x 3 bh
580 Buis beton 25 x 75 x 3 bh
581 Buis beton 30 x 75 x 3 bh
582 Buis beton 40 x 75 x 5 bh
583 Buis beton 50 x 75 x 5 bh
584 Buis beton 80 x 75 x 7.5 bh

PAVING
585 Paving 10 x 20 cm tebal 6 cm K225 Pc m2
586 Paving 10 x 20 cm tebal 6 cm K225 merah m2
587 Paving 10 x 20 cm tebal 6 cm K225 hitam m2
588 Paving 10 x 20 cm tebal 6 cm K300 Pc m2
589 Paving 10 x 20 cm tebal 6 cm K300 merah m2
590 Paving 10 x 20 cm tebal 6 cm K300 hitam m2
591 Paving 10 x 20 cm tebal 6 cm K350 Pc m2
592 Paving 10 x 20 cm tebal 6 cm K350 merah m2
593 Paving 10 x 20 cm tebal 6 cm K350 hitam m2
594 Paving 10 x 20 cm tebal 8 cm K225 Pc m2
595 Paving 10 x 20 cm tebal 8 cm K225 merah m2
596 Paving 10 x 20 cm tebal 8 cm K225 hitam m2
597 Paving 10 x 20 cm tebal 8 cm K300 Pc m2
598 Paving 10 x 20 cm tebal 8 cm K300 merah m2
599 Paving 10 x 20 cm tebal 8 cm K300 hitam m2
600 Paving 10 x 20 cm tebal 8 cm K350 Pc m2
601 Paving 10 x 20 cm tebal 8 cm K350 merah m2
602 Paving 10 x 20 cm tebal 8 cm K350 hitam m2
603 Paving 10 x 20 cm tebal 8 cm K400 Pc m2
604 Paving 10 x 20 cm tebal 8 cm K400 merah m2
605 Paving 10 x 20 cm tebal 8 cm K400 hitam m2
606 Paving 20 x 20 cm tebal 6 cm K225 Pc m2
607 Paving 20 x 20 cm tebal 6 cm K225 merah m2
608 Paving 20 x 20 cm tebal 6 cm K225 hitam m2
609 Paving 20 x 20 cm tebal 6 cm K300 Pc m2
610 Paving 20 x 20 cm tebal 6 cm K300 merah m2
611 Paving 20 x 20 cm tebal 6 cm K300 hitam m2
612 Paving 20 x 20 cm tebal 6 cm K350 Pc m2
613 Paving 20 x 20 cm tebal 6 cm K350 merah m2
614 Paving 20 x 20 cm tebal 6 cm K350 hitam m2
615 Paving 20 x 20 cm tebal 8 cm K225 Pc m2
616 Paving 20 x 20 cm tebal 8 cm K225 merah m2
617 Paving 20 x 20 cm tebal 8 cm K225 hitam m2
25

NO KODE NAMA BARANG MERK SATUAN

A B C

618 Paving 20 x 20 cm tebal 8 cm K300 Pc m2


619 Paving 20 x 20 cm tebal 8 cm K300 merah m2
620 Paving 20 x 20 cm tebal 8 cm K300 hitam m2
621 Paving 20 x 20 cm tebal 8 cm K350 Pc m2
622 Paving 20 x 20 cm tebal 8 cm K350 merah m2
623 Paving 20 x 20 cm tebal 8 cm K350 hitam m2
624 Paving 20 x 20 cm tebal 8 cm K400 Pc m2
625 Paving 20 x 20 cm tebal 8 cm K400 merah m2
626 Paving 20 x 20 cm tebal 8 cm K400 hitam m2
627 Paving 20 x 20 cm tebal 10 cm K225 Pc m2
628 Paving 20 x 20 cm tebal 10 cm K225 merah m2
629 Paving 20 x 20 cm tebal 10 cm K225 hitam m2
630 Paving 20 x 20 cm tebal 10 cm K300 Pc m2
631 Paving 20 x 20 cm tebal 10 cm K300 merah m2
632 Paving 20 x 20 cm tebal 10 cm K300 hitam m2
633 Paving 20 x 20 cm tebal 10 cm K350 Pc m2
634 Paving 20 x 20 cm tebal 10 cm K350 merah m2
635 Paving 20 x 20 cm tebal 10 cm K350 hitam m2
636 Paving 20 x 20 cm tebal 10 cm K400 Pc m2
637 Paving 20 x 20 cm tebal 10 cm K400 merah m2
638 Paving 20 x 20 cm tebal 10 cm K400 hitam m2
639 Paving segi enam xexagon 6 cm K225 Pc m2
640 Paving segi enam xexagon 6 cm K225 merah m2
641 Paving segi enam xexagon 6 cm K225 hitam m2
642 Paving segi enam xexagon 6 cm K300 Pc m2
643 Paving segi enam xexagon 6 cm K300 merah m2
644 Paving segi enam xexagon 6 cm K300 hitam m2
645 Paving segi enam xexagon 6 cm K350 Pc m2
646 Paving segi enam xexagon 6 cm K350 merah m2
647 Paving segi enam xexagon 6 cm K350 hitam m2
648 Paving segi enam xexagon 6 cm K400 Pc m2
649 Paving segi enam xexagon 6 cm K400 merah m2
650 Paving segi enam xexagon 6 cm K400 hitam m2
651 Paving kotak bujur sangkar tanpa tias 6 cm K225 Pc m2
652 Paving kotak bujur sangkar tanpa tias 6 cm K225 merah m2
653 Paving kotak bujur sangkar tanpa tias 6 cm K225 hitam m2
654 Paving kotak bujur sangkar tanpa tias 8 cm K225 Pc m2
655 Paving kotak bujur sangkar tanpa tias 8 cm K225 merah m2
656 Paving kotak bujur sangkar tanpa tias 8 cm K225 hitam m2
657 Paving Tiga Berlian tebal 6 cm K225 Pc m2
658 Paving Tiga Berlian tebal 6 cm K350 Pc m2
659 Kanstein kotak (P:50,T:20,La:10,Lb:16 cm K225) bh
660 Kanstein Bulat (P:50,T:30,La:10,Lb:16 cm K225) bh
661 Kanstein Jumbo (P:50,L:15,T:30 cm K225) bh
662 Kanstein Segi Lima (P:50,L:15, T:20 cm K225) bh
663 Kanstein Segi Lima (P:40,L:10, T:20 cm K225) bh
664 Kanstein Segi Lima jumbo(P:50,L:15, T:40 cm K225) bh
665 Kanstein kursi ( P:50, L:10, T:40 cm, lb 17,5 cm K225 ) bh
666 Kanstein kursi ( P:50, L:10, T:40 cm, lb 17,5 cm K300 ) bh
667 Grass Block lobang 8, 36 X 54 cm tebal 9 cm K 225 m2
668 Grass Block lobang 5, 30 X 30 cm tebal 7 cm K 225 m2
669 Tutup got (grill) P. 45, L. 24, T.9cm K350 bh
670 Tutup got (grill) P. 30, L. 24, T.9cm K350 bh
671 Tutup kabel PLN P.20, L.40, T.6cm bh
672 Tutup uskup 8 cm bj
673 Koral Sikat Lokal (10 Kg) zak
674 Koral Sikat Alor (8 Kg) zak

LAIN-LAIN + STYLE BALI


674 Wall papper 30,5 x 30,5 lembar
675 Wall papper 70 x 100 lembar
676 Wall papper 50 x 100 lembar
677 Wall papper 30 x 60 lembar
678 Glass block bj
679 Dugul batu hitam 50 x 50 x 200 tempel unit
680 Dugul batu hitam 60 x 70 x 250 tempel unit
681 Dugul batu hitam 70 x 70 x 250 tempel unit
682 Padmasari batu hitam 50 x 50 x 200 tempel unit
683 Padmasari batu hitam 65 x 75 x 255 tempel unit
684 Padmasari batu hitam 70 x 70 x 250 tempel unit
685 Dugul batu hitam 50 x 50 x 200 masive unit
686 Dugul batu hitam 60 x 70 x 250 masive unit
687 Dugul batu hitam 70 x 70 x 300 masive unit
688 Padmasari batu hitam 50 x 50 x 200 masive unit
689 Padmasari batu hitam 65 x 75 x 255 masive unit
690 Padmasari batu hitam 70 x 70 x 250 masive unit
691 Padmasari paras taro 50 x 70 x 250 unit
692 Padmasari paras taro 65 x 65 x 250 unit
693 Padmasari paras taro 65 x 65 x 250 unit
694 Pilar/saka ukir Bali+cahngawang, kayu jati unit
695 Lambang ukir Bali komplit, kayu jati m1
696 Tugeh ukir Bali komplit+patung, kayu jati unit
26

NO KODE NAMA BARANG MERK SATUAN

A B C

697 Waton + barba ukir Bali komplit, kayu jati unit

PEKERJAAN SOFTSCAPE
A POHON
698 Tanaman Kamboja dia 10 cm phn
699 Tanaman Kamboja dia 15 cm phn
700 Tanaman Pule dia 60 - 75 cm phn
701 Tanaman Pule dia 75 - 90 cm phn
702 Jepun Fosil dia 30 - 50 cm phn
703 Pohon Dolar t= 2 - 3 cm phn
704 Jepun Fosil dia 15 - 25 cm phn
705 Tanaman Glodogan dia 10 cm phn
706 Tanaman Glodogan dia 15 cm phn
707 Tanaman Ketapang Kencana Tinggi = 3 m phn
708 Tanaman Puuk Merah Tinggi 1 m phn
709 Tanaman Dadap Merah dia 10 cm phn
710 Tanaman Dadap Merah dia 15 cm phn
711 Tanaman Rumput Mutiara m2
712 Tanaman Rumput Bermuda m2
713 Tanaman Pisang - Pisangan m2
714 Penanaman Rumput Jepang m2

B SEMAK PERDU
715 Kaki Laba - Laba ( Ararea ) m2
716 Corrymbousa Mini m2
717 Pangkas Kuning m2
718 Kacang - Kacangan m2
719 Penanaman Le Kwan Yew m1
720 Bambu Jakarta rumpun
721 Puring Kirana phn
722 Puring Nuri phn
723 Puring Bor Merah phn
724 Puring Bor Kuning phn
725 Soka India phn
726 Walisongo phn
727 Bougenville Variegata phn
728 Bunga Kembang Pukul Sembilan phn
729 Tanah Urug Subur Tebal 15 cm m3
730 Pupuk Kandang / Kompos m3
27

DAFTAR HARGA SATUAN BAHAN

HARGA SATUAN

Rp 4,000.00
Rp 40,000.00
Rp 18,333.33
Rp 14,500.00
Rp 28,250.00
Rp 102,000.00
Rp 76,500.00
Rp 27,500.00
Rp 19,000.00
Rp 20,750.00
Rp 11,000.00
Rp 73,166.67
Rp 40,750.00
Rp 69,833.33
Rp 70,166.67
Rp 9,250.00
Rp 85,500.00
Rp 79,000.00
Rp 212,500.00
Rp 10,000.00
Rp 15,000.00

Rp 21,550.00
Rp 344,150.00
Rp 139,450.00
Rp 41,250.00
Rp 41,000.00
Rp 48,500.00
28

HARGA SATUAN

Rp 70,000.00
Rp 91,000.00
Rp 134,500.00
Rp 80,750.00
Rp 118,000.00
Rp 83,250.00
Rp 121,000.00
Rp 85,000.00
Rp 122,000.00
Rp 73,925.00
Rp 79,550.00
Rp 89,275.00
Rp 96,700.00
Rp 102,325.00
Rp 162,500.00
Rp 137,500.00
Rp 38,400.00
Rp 47,500.00
Rp 51,500.00
Rp 5,500.00
Rp 18,500.00
Rp 16,000.00
Rp 6,500.00
Rp 6,000.00
Rp 16,500.00
Rp 13,500.00
Rp 13,750.00
Rp 6,750.00
Rp 5,500.00
Rp 4,750.00
Rp 5,900.00
Rp 6,500.00
Rp 11,801.50
Rp 13,930.00
Rp 14,180.00
Rp 9,620.00
Rp 1,350.00
Rp 1,650.00
Rp 1,900.00
Rp 4,973.50
Rp 80,000.00
Rp 82,500.00
Rp 155,000.00
Rp 87,500.00
Rp 174,750.00
Rp 40,500.00
Rp 43,100.00
Rp 7,000.00
Rp 188,250.00
29

HARGA SATUAN

Rp 371,000.00
Rp 337,500.00
Rp 782,500.00
Rp 36,875.00
Rp 56,750.00
Rp 44,500.00
Rp 40,500.00
Rp 44,750.00
Rp 50,500.00
Rp 42,000.00
Rp 56,750.00
Rp 79,000.00
Rp 142,250.00
Rp 144,750.00
Rp 74,600.00
Rp 143,500.00
Rp 162,500.00
Rp 87,250.00
Rp 135,000.00
Rp 7,000.00
Rp 126,300.00
Rp 29,937.50
Rp 218,837.50
Rp 207,062.50
Rp 337,087.50
Rp 337,087.50
Rp 296,875.00
Rp 392,625.00
Rp 21,750.00
Rp 242,500.00
Rp 69,000.00
Rp 97,000.00
Rp 118,750.00
Rp 123,875.00
Rp 307,125.00
Rp 109,025.00
Rp 123,875.00
Rp 148,100.00
Rp 137,500.00
Rp 123,875.00
Rp 108,212.50
Rp 796,250.00
Rp 181,000.00
30

HARGA SATUAN

Rp 53,787.50
Rp 149,700.00
Rp 58,000.00
Rp 75,150.00
Rp 92,375.00
Rp 95,750.00
Rp 40,000.00
Rp 62,000.00
Rp 12,000.00
Rp 10,000.00
Rp 111,750.00
Rp 45,500.00
Rp 43,500.00
Rp 40,500.00
Rp 86,500.00
Rp 103,750.00
Rp 15,762.50
Rp 16,250.00
Rp 45,500.00
Rp 158,750.00
Rp 59,750.00
31

HARGA SATUAN
32

HARGA SATUAN
33

HARGA SATUAN
34

HARGA SATUAN
35

HARGA SATUAN
36

HARGA SATUAN
37

HARGA SATUAN
38

HARGA SATUAN
39

HARGA SATUAN

Keramik Habitat 50 x 50
40

HARGA SATUAN
41

HARGA SATUAN

Rp 250,650.00
Rp 202,100.00
Rp 236,000.00
Rp 187,450.00
Rp 216,250.00
Rp 274,350.00
Rp 274,600.00
Rp 210,000.00
Rp 258,050.00
Rp 205,250.00
Rp 248,750.00

Rp 313,750.00
Rp 313,750.00
42

HARGA SATUAN

Rp 939,396.00
Rp 452,691.00
Rp 379,350.00
Rp 290,500.00
Rp 336,900.00
Rp 462,700.00
Rp 262,850.00

Rp 359,287.50
Rp 359,287.50
Rp 359,287.50
Rp 359,287.50
Rp 359,287.50
Rp 359,287.50
Rp 302,500.00
Rp 275,250.00
Rp 330,250.00
Rp 232,100.00
Rp 668,450.00
Rp 277,145.00
Rp 393,590.00
Rp 423,185.40
Rp 431,587.20
Rp 538,057.30
Rp 256,807.65
Rp 369,126.45
Rp 433,623.30
Rp 417,847.10
Rp 546,723.10
Rp 523,503.20

Rp 439,855.00
Rp 341,380.00
Rp 282,295.00
Rp 2,602,500.00
Rp 2,202,500.00
Rp 1,400,000.00
Rp 2,500,000.00
Rp 1,400,000.00
Rp 2,200,000.00
Rp 1,960,000.00

Rp 76,550.00
Rp 76,550.00
Rp 1,399,000.00
Rp 999,900.00
Rp 2,199,900.00
Rp 1,724,950.00
Rp 1,295,450.00
Rp 1,399,000.00
Rp 1,499,000.00

Rp 61,666.67
Rp 46,666.67
Rp 61,666.67
Rp 66,666.67
Rp 47,171.50
Rp 50,862.50
Rp 64,000.00
Rp 46,250.00
Rp 55,000.00

Rp 66,900.00
Rp 65,750.00
Rp 72,900.00
Rp 105,250.00
Rp 62,700.00
Rp 71,750.00
Rp 63,775.00
Rp 68,775.00
Rp 61,800.00
Rp 78,750.00

Rp 68,750.00
Rp 152,750.00
Rp 297,500.00
43

HARGA SATUAN

Rp 182,200.00
Rp 83,250.00
Rp 155,500.00
Rp 194,250.00
Rp 182,200.00
Rp 155,500.00
Rp 83,250.00
Rp 100,000.00
Rp 159,200.00
Rp 55,500.00

Rp 181,250.00
Rp 244,700.00
Rp 264,500.00
Rp 291,000.00
Rp 165,000.00
Rp 176,000.00
Rp 187,500.00
Rp 418,500.00
Rp 275,500.00
Rp 440,500.00
Rp 461,500.00
Rp 495,000.00
Rp 429,000.00
Rp 428,500.00
Rp 714,500.00
Rp 193,000.00
Rp 424,500.00

Rp 311,000.00
Rp 524,000.00
Rp 460,500.00
Rp 36,000.00
Rp 155,000.00
Rp 369,000.00
Rp 1,350,000.00
Rp 1,165,000.00
Rp 1,151,500.00
Rp 2,790,000.00
Rp 2,790,000.00
Rp 4,800,000.00
Rp 6,420,000.00
Rp 3,075,000.00
Rp 2,933,333.33
Rp 2,825,000.00
Rp 1,933,333.33
Rp 3,165,000.00
Rp 3,215,000.00
Rp 2,874,540.00
Rp 645,000.00
Rp 2,935,000.00
Rp 395,000.00
Rp 394,500.00
Rp 240,000.00
Rp 150,000.00
Rp 120,000.00
Rp 185,000.00
Rp 325,000.00
Rp 255,000.00
Rp 279,045.00
Rp 294,399.00
Rp 398,223.00
Rp 777,500.00
Rp 1,665,000.00
Rp 219,000.00
Rp 130,605.00
Rp 1,739,862.00
Rp 1,524,343.50
Rp 585,000.00
Rp 102,500.00
Rp 37,500.00
Rp 5,500.00
Rp 2,111,000.00
Rp 1,955,450.00
Rp 555,525.00
Rp 316,650.00
Rp 1,075,000.00
Rp 1,840,000.00
44

HARGA SATUAN

Rp 2,020,000.00
Rp 2,350,000.00
Rp 1,080,000.00
Rp 2,185,684.00
Rp 726,765.00
Rp 35,150.00
Rp 462,500.00
Rp 888,500.00
Rp 714,500.00
Rp 285,000.00
Rp 590,000.00
Rp 178,756.03
Rp 741,628.75
Rp 2,911,212.50
Rp 285,818.75
45

HARGA SATUAN

Rp 4,750.00
Rp 3,750.00
Rp 223,000.00
Rp 664,500.00
Rp 669,500.00
Rp 33,000.00
Rp 57,500.00
Rp 86,650.00
Rp 45,500.00
Rp 19,850.00
Rp 402,500.00
Rp 9,900.00
Rp 26,250.00
Rp 8,500.00
Rp 29,250.00
Rp 25,500.00
Rp 17,350.00
Rp 100,000.00
Rp 120,000.00
Rp 93,333.33
Rp 78,333.33
Rp 73,333.33
Rp 85,000.00
Rp 82,500.00
Rp 75,000.00
Rp 81,750.00
Rp 88,750.00
Rp 83,000.00
Rp 105,000.00
Rp 110,500.00
Rp 312,500.00
Rp 340,000.00
Rp 225,250.00
Rp 285,000.00
Rp 317,500.00
Rp 149,000.00
Rp 109,000.00
Rp 125,000.00
Rp 110,000.00
Rp 120,000.00
Rp 112,500.00
Rp 95,000.00
Rp 91,000.00
Rp 93,333.33
Rp 209,250.00
Rp 15,750.00
Rp 247,500.00
Rp 80,000.00
Rp 95,000.00
Rp 220,000.00
Rp 83,000.00
Rp 110,000.00
Rp 323,500.00
Rp 127,000.00
Rp 26,750.00
Rp 22,500.00
Rp 38,500.00
Rp 7,105,350.00
Rp 276,500.00
Rp 205,000.00
Rp 207,250.00
Rp 183,000.00
Rp 177,000.00
Rp 177,000.00
Rp 26,000.00
Rp 66,500.00

Rp 14,100.00
Rp 1,550.00
Rp 10,500.00
Rp 79,000.00
Rp 40,500.00
Rp 15,500.00
Rp 40,500.00
Rp 40,500.00
Rp 370,000.00
Rp 400,000.00
Rp 715,000.00
Rp 9,500.00
Rp 339,000.00
46

HARGA SATUAN

Rp 38,500.00

Rp 199,200.00
Rp 368,650.00
Rp 521,200.00
Rp 692,550.00
Rp 1,148,050.00
Rp 1,609,750.00
Rp 2,122,900.00
Rp 2,302,500.00
Rp 215,850.00
Rp 345,450.00
Rp 427,800.00
Rp 518,475.00
Rp 673,250.00
Rp 885,090.00
Rp 2,168,680.00
Rp 3,056,000.00
Rp 4,069,000.00
Rp 9,250,050.00
Rp 18,736,000.00
Rp 23,773,380.00
Rp 26,247,000.00
Rp 791,345.00
Rp 634,100.00
Rp 216,175.00
Rp 94,970.00
Rp 153,510.00
Rp 142,405.00
Rp 129,740.00
Rp 61,810.00
Rp 343,450.00
Rp 329,280.00

Rp 48,827.00
Rp 62,218.00
Rp 96,146.50
Rp 117,163.50
Rp 89,564.00
Rp 357,000.00
Rp 164,984.00
Rp 247,589.00
Rp 321,514.50
Rp 42,373.33
Rp 28,680.00
Rp 1,565,480.00
Rp 77,333.33
Rp 63,393.33
Rp 2,248,800.00
Rp 3,179,520.00
Rp 3,977,000.00
Rp 109,900.00
Rp 150,450.00
Rp 204,000.00
Rp 33,246.67
Rp 298,460.00
Rp 522,470.00
Rp 711,160.00
Rp 1,109,160.00
Rp 1,934,260.00
Rp 21,500.00
Rp 32,650.00
Rp 27,180.00
Rp 49,160.00
Rp 62,320.00
Rp 72,080.00
Rp 14,640.00
Rp 92,906.67
Rp 7,880.00
Rp 1,143,460.00
Rp 46,010.00
Rp 40,640.00
Rp 1,542,300.00
Rp 2,064,120.00
Rp 2,638,080.00
Rp 59,640.00
Rp 84,520.00
Rp 120,740.00
Rp 180,040.00
Rp 303,950.00
Rp 364,870.00
47

HARGA SATUAN

Rp 651,940.00
Rp 839,125.00
Rp 75,922.50

Rp 29,333.33
Rp 207,500.00
Rp 2,255,000.00
Rp 1,906,500.00
Rp 1,888,170.00

Rp 401,000.00
Rp 1,143,977.50
Rp 3,735,500.00
Rp 2,666,250.00
Rp 1,093,500.00
Rp 109,500.00
Rp 107,050.00
Rp 76,250.00
Rp 85,500.00
Rp 97,000.00
Rp 42,300.00
Rp 51,100.00

Rp 181,700.00
Rp 409,250.00
Rp 299,000.00
Rp 327,250.00
Rp 600,500.00
Rp 512,250.00
Rp 995,250.00
Rp 633,250.00
Rp 1,114,500.00
Rp 257,000.00
Rp 287,500.00
Rp 178,250.00
Rp 105,500.00
Rp 337,500.00
Rp 101,000.00

Rp 658,250.00
Rp 810,237.50
48

HARGA SATUAN

Rp 822,292.50
Rp 839,125.00
Rp 878,567.50
Rp 803,850.00
Rp 895,400.00
Rp 979,062.50
Rp 1,006,950.00
Rp 1,096,890.00
Rp 1,192,612.50
Rp 1,221,000.00
Rp 1,316,500.00
Rp 1,451,150.00
Rp 283,900.00
Rp 9,650.00
49

HARGA SATUAN

Rp 299,000.00
Rp 364,000.00
Rp 533,000.00
Rp 624,000.00
Rp 275,600.00
Rp 208,208.00
Rp 284,056.00
Rp 304,876.00
Rp 327,184.00
Rp 178,735.00
Rp 743,600.00
Rp 486,200.00
Rp 800,800.00
Rp 858,000.00
Rp 572,000.00
Rp 218,619.00
Rp 255,799.00
Rp 282,568.00
Rp 297,440.00
Rp 188,875.00

Rp 72,500.00
Rp 105,000.00
Rp 58,000.00
Rp 180,500.00
Rp 190,500.00
Rp 8,933.33
Rp 19,333.33
Rp 31,333.33
Rp 47,000.00
Rp 25,666.67
Rp 52,333.33
Rp 9,000.00
Rp 11,666.67
Rp 21,500.00
Rp 12,500.00
Rp 12,250.00
Rp 5,000.00
Rp 5,750.00
Rp 6,250.00
Rp 15,912.50
Rp 25,000.00
Rp 30,000.00
50

HARGA SATUAN

Rp 32,000.00
Rp 15,500.00
Rp 15,000.00
Rp 85,850.00
Rp 362,520.00
Rp 787,025.00
Rp 696,000.00
Rp 42,500.00
Rp 189,631.50
Rp 53,000.00
Rp 61,000.00
Rp 52,000.00
Rp 51,500.00
Rp 66,000.00
Rp 11,833.33
Rp 4,500.00
Rp 1,066.67
Rp 6,166.67
Rp 1,100.00
Rp 4,000.00
Rp 49,750.00
Rp 1,060,000.00
Rp 349,367.50
Rp 72,200.00
Rp 41,833.33
Rp 36,000.00
Rp 12,500.00
Rp 136,250.00
Rp 125,500.00
Rp 72,500.00
Rp 77,500.00
Rp 1,004,925.00
Rp 2,244,000.00
Rp 965,736.50
Rp 1,979,250.00
Rp 9,706,125.00
Rp 6,669,850.00
Rp 261,838.50
Rp 851,250.00

Rp 64,592.23
Rp 75,927.18
Rp 88,374.00
Rp 99,621.60
Rp 111,940.40
Rp 141,662.50

Rp 70,250.00
Rp 100,750.00
Rp 102,500.00
Rp 81,875.00
Rp 111,250.00
Rp 112,500.00
Rp 87,750.00
Rp 117,500.00
Rp 117,500.00
Rp 81,250.00
Rp 113,000.00
Rp 114,000.00
Rp 91,500.00
Rp 122,000.00
Rp 120,500.00
Rp 95,500.00
Rp 124,500.00
Rp 124,500.00
Rp 102,500.00
Rp 130,250.00
Rp 130,250.00
Rp 70,750.00
Rp 99,500.00
Rp 105,000.00
Rp 81,125.00
Rp 109,375.00
Rp 112,500.00
Rp 87,750.00
Rp 114,375.00
Rp 114,250.00
Rp 81,250.00
Rp 110,000.00
Rp 110,000.00
51

HARGA SATUAN

Rp 97,250.00
Rp 126,000.00
Rp 122,500.00
Rp 104,975.00
Rp 141,150.00
Rp 125,500.00
Rp 100,500.00
Rp 130,500.00
Rp 130,500.00
Rp 98,000.00
Rp 136,500.00
Rp 136,500.00
Rp 110,000.00
Rp 147,500.00
Rp 146,500.00
Rp 117,000.00
Rp 155,750.00
Rp 154,750.00
Rp 130,500.00
Rp 167,875.00
Rp 166,750.00
Rp 69,250.00
Rp 98,250.00
Rp 100,500.00
Rp 80,625.00
Rp 109,250.00
Rp 112,500.00
Rp 85,125.00
Rp 114,000.00
Rp 117,500.00
Rp 92,750.00
Rp 122,500.00
Rp 122,500.00
Rp 68,680.00
Rp 97,717.50
Rp 95,625.00
Rp 83,830.00
Rp 115,140.00
Rp 113,500.00
Rp 78,275.00
Rp 190,500.00
Rp 64,135.00
Rp 76,255.00
Rp 38,903.13
Rp 31,012.50
Rp 21,210.00
Rp 49,490.00
Rp 76,250.00
Rp 84,250.00
Rp 95,750.00
Rp 84,750.00
Rp 79,975.00
Rp 70,875.00
Rp 6,075.00
Rp 7,250.00
Rp 50,000.00
Rp 100,000.00

Rp 97,736.50
Rp 114,111.00
Rp 92,112.50
Rp 49,724.00
Rp 38,906.50
Rp 7,453,875.00
Rp 6,776,250.00
Rp 7,818,750.00
Rp 8,600,625.00
Rp 8,913,375.00
Rp 9,382,500.00
Rp 6,098,625.00
Rp 7,860,450.00
Rp 8,402,550.00
Rp 6,098,625.00
Rp 7,724,925.00
Rp 8,131,500.00
Rp 948,675.00
Rp 1,016,437.50
Rp 1,219,725.00
Rp 1,707,750.00
Rp 853,875.00
Rp 1,707,750.00
52

HARGA SATUAN

Rp 2,846,250.00

Rp 3,500,000.00
Rp 4,500,000.00
Rp 66,000,000.00
Rp 82,000,000.00
Rp 37,000,000.00
Rp 9,000,000.00
Rp 12,500,000.00
Rp 227,500.00
Rp 250,500.00
Rp 450,000.00
Rp 200,000.00
Rp 375,000.00
Rp 575,000.00
Rp 37,500.00
Rp 10,000.00
Rp 10,000.00
Rp 36,000.00

Rp 1,365,500.00
Rp 1,365,500.00
Rp 517,500.00
Rp 445,500.00
Rp 45,500.00
Rp 60,000.00
Rp 12,000.00
Rp 12,000.00
Rp 12,000.00
Rp 12,000.00
Rp 20,500.00
Rp 11,500.00
Rp 70,000.00
Rp 2,650.00
Rp 205,000.00
Rp 225,000.00
DAFTAR HARGA PEKERJAAN PELINGGIH, CANDI BENTAR DAN TEMBOK PENYENGKER
( SUDAH TERPASANG DI ATAS PONDASI )

No JENIS BAHAN/BANGUNAN UK/BAHAN SAT KETERANGAN HARGA

1 Apit Surang T = 1.7 unit Bata Press 15,750,000.00


###
Apit Surang T = 2 unit Bata Press 23,100,000.00
Apit Surang T = 2 unit Paras 21,000,000.00
Apit Surang T = 2 unit Paras Cetakan 23,100,000.00
Apit Surang T = 2.5 unit Bata Press 24,150,000.00
Apit Surang T = 2.5 unit Paras Cetakan 25,200,000.00
Apit Surang T = 2.5 unit Batu Candi 26,250,000.00
Apit Surang T = 2.5 unit Batu Karangasem 28,350,000.00
Apit Surang T = 2.5 unit Paras Cor 26,250,000.00
Apit Surang T = 2.7 unit Paras Bata - Lengisan 26,250,000.00
Apit Surang T = 2.7 unit Paras Bata - Ukir 36,750,000.00
Apit Surang T = 3 unit Batu Karangasem 31,500,000.00
Apit Surang T = 3 unit Paras Bata 29,400,000.00
Apit Surang T = 3 unit Batu Karangasem 31,500,000.00
Apit Surang T = 3 unit Bata Press 28,000,000.00
Apit Surang T = 3.5 unit Paras 30,000,000.00
Apit Surang T = 3.5 unit Batu Candi 47,250,000.00
Apit Surang T = 3.5 unit Paras Bata - Polos 42,000,000.00
Apit Surang T = 3.5 unit Paras Bata - Ukir 63,000,000.00
Apit Surang T = 3.5 unit Batu Karangasem 73,500,000.00
Apit Surang T = 4 unit Paras Bata 44,100,000.00
Apit Surang T = 5 unit Batu Candi 50,400,000.00
Apit Surang T = 5 unit Paras Bata 47,250,000.00
Apit Surang T = 5 unit Batu Karangasem 52,500,000.00
Apit Surang T = 7 unit Batu Karangasem 81,900,000.00
Apit Surang T = 7 unit Paras Bata 73,500,000.00
Apit Surang T = 8 unit Batu Karangasem 89,250,000.00
Apit Surang T = 8 unit Paras Bata 84,000,000.00

2 m1 Batu Karangasem 2,940,000.00


Tembok Penyengker T = 1 Bata Press 2,782,500.00
Paras Bata 2,625,000.00
Tembok Penyengker T = 1.25 m1 Paras 2,520,000.00
1.25 ml Bata Press 2,835,000.00
Tembok Penyengker T = 1.25 ml Bata Tabas 3,150,000.00
1.25 ml Batu Karangasem 3,675,000.00
1.2 m m1 Batu Karangasem 3,675,000.00
Tembok Penyengker T = 1 m1 Paras 2,625,000.00
Tembok Penyengker T = 1 m1 Batu Karangasem 3,150,000.00
m1 Polos 4,725,000.00
Tembok Penyengker T = 1
m1 Ukir 5,775,000.00
m1 Polos 4,725,000.00
Tembok Penyengker T = 1.5
m1 Ukir 7,350,000.00
Tembok Penyengker T = 1.5 ml Batu Candi 4,725,000.00
Tembok Penyengker T = 1.5 m1 Paras Cor 4,410,000.00
Tembok Penyengker T = 1.5 m1 Bata Press 4,935,000.00
Tembok Penyengker T = 2 m1 Bata Press 7,350,000.00
Tembok Penyengker T = 2 m1 Paras Bata 5,775,000.00
Tembok Penyengker T = 2 m1 Paras Cor 5,040,000.00
Tembok Penyengker T = 2 m1 Batu Karangasem 8,400,000.00

3 Paduraksa. T = 60 cm bh Paras 3,675,000.00


Batu Karangasem 4,725,000.00
Paduraksa. T = 1.25 bh
Bata Press 4,200,000.00
Paduraksa. T = 1.25 bh Paras 7,350,000.00
2 Paras Ukir 10,500,000.00
Paduraksa. T = bh
2 Paras Cor 9,450,000.00
Paduraksa. T = 1 bh Batu Karangasem 5,250,000.00
Paduraksa. T = 1.5 bh Bata Press 9,450,000.00
Paduraksa. T = 1.5 bh Batu Karangasem 5,775,000.00
Paduraksa. T = 2 mepanak bh Bata Press 15,750,000.00
Mepanak bh Paras Bata 13,650,000.00
Paduraksa. T = 2 bh Bata Press 8,400,000.00
Paduraksa. T = 2 bh Batu Karangasem 12,000,000.00
Paduraksa. T = 1.2 bh Batu Karangasem 6,300,000.00
Paduraksa. T = 1.75 bh Paras 9,975,000.00

4 Atap Ijuk 12,075,000.00


Pelinggih Surya, Taksu, Penungun karang, Rong 22cm Taksu 40 x 40 unit
Atap Genteng 9,056,250.00
ukir prada 9,660,000.00
Pelinggih Surya, Taksu, Penungun karang, Rong 22cm 35 x 35 Atap Ijuk unit
Atap Genteng 8,452,500.00
Surya 6,037,500.00
Pelinggih Surya, Taksu, Penungun karang, Rong 22cm Taksu unit Paras Cor 6,037,500.00
Tugu Karang 6,037,500.00
Surya 10,867,500.00
Pelinggih Surya, Rong 22cm unit Paras/ Bata
Rong 8,452,500.00
No JENIS BAHAN/BANGUNAN UK/BAHAN SAT KETERANGAN HARGA

Surya 12,075,000.00
Pelinggih Surya, Taksu, Penungun karang, Rong 22cm Taksu unit Batu Bata 9,660,000.00
Tugu Karang 10,075,000.00
Surya 14,490,000.00
Pelinggih Surya, Taksu, Penungun karang, Rong 22cm Taksu unit Batu Candi 12,075,000.00
Tugu Karang 14,490,000.00
Surya 16,905,000.00
Pelinggih Surya, Taksu, Penungun karang, Rong 22cm Taksu unit Batu Karangasem 14,490,000.00
Tugu Karang 16,905,000.00
Bata Press 4,226,250.00
Pelinggih Surya, Taksu, Penungun karang, Rong 22cm Surya 22cm unit
Batu Karangasem 8,452,500.00
Bata Press 5,226,250.00
Pelinggih Surya, Taksu, Penungun karang, Rong 22cm Bataran Taksu 70 x 80 unit
Batu Karangasem 10,056,250.00
Bataran Tugu Karang Bata Press 4,226,250.00
Pelinggih Surya, Taksu, Penungun karang, Rong 22cm unit
60 x 70 Batu Karangasem 9,056,250.00
Surya 60x70 7,245,000.00
Pelinggih Surya, Taksu, Penungun karang, Rong 22cm Taksu 60x70 unit Batu Karangasem 7,245,000.00
T.Karang 60x70 7,245,000.00
Pelinggih Surya, Taksu, Penungun karang, Rong 22cm Taksu 38 x 3 unit Atap Ijuk /Prada 12,075,000.00
Pelinggih Surya, Taksu, Penungun karang, Rong 22cm saka 40cm unit Atap Ijuk /Prada 9,056,250.00
Taksu 40 x 40 jaba
Pelinggih Surya, Taksu, Penungun karang, Rong 22cm unit Batu Karangasem 7,848,750.00
saka
Atap Ijuk 9,056,250.00
Pelinggih Surya, Taksu, Penungun karang, Rong 22cm Surya 22cm Atap Ijuk unit
Bataran Batu Karangasem 9,056,250.00
Pelinggih Surya, Taksu, Penungun karang, Rong 22cm Surya 22cm bataran unit Batu Karangasem 18,112,500.00
Polos 5,433,750.00
Pelinggih Surya, Taksu, Penungun karang, Rong 22cm Surya 22cm unit
Ukir 7,245,000.00
Padma Copan unit 4,830,000.00
Pelinggih Surya, Taksu, Penungun karang, Rong 22cm Double Bataran
Paras Cor 9,660,000.00
Taksu 37 unit Atap Ijuk + Cor Prada 16,905,000.00
Pelinggih Surya, Taksu, Penungun karang, Rong 22cm
Bataran + Bungan Bataran 4,226,250.00
Atap Ijuk 9,660,000.00
Pelinggih Surya, Taksu, Penungun karang, Rong 23cm Taksu 23cm unit
Bataran Batu Karangasem 9,056,250.00
Atap Ijuk 14,490,000.00
Pelinggih Surya, Taksu, Penungun karang, Rong 23cm Rong 3 90 x90 unit
Atap Genteng 13,282,500.00
Atap Ijuk 10,263,750.00
Pelinggih Surya, Taksu, Penungun karang, Rong 25cm Taksu 25cm unit
Batu/Pondasi 9,660,000.00
Pelinggih Surya, Taksu, Penungun karang, Rong 28cm Rong 28 cm unit Batu Karangasem 6,037,500.00
Pelinggih Surya, Taksu, Penungun karang, Rong 28cm kemulan 80 x80 unit Batu Karangasem 15,093,750.00

5 Bale Kulkul. L = 60,375,000.00


1.5 x 1.5 m Saka 8 unit Atap Genteng
Atap Ijuk 78,487,500.00
Bale Kulkul. L =
1.5 x 1.5 m saka 4 unit Atap Genteng /Kayu Jati 36,225,000.00
Bale Kulkul. L = 1.20x1.20 saka 8 unit Atap Ijuk 86,600,000.00
Bale Kulkul. L = 2 x 2 m Saka 8 Atap Ijuk 96,600,000.00
unit
Atap Genteng 78,487,500.00
Bale Kulkul. L = Atap Ijuk - Cat Prada 30,187,500.00
Kayu Jati 0.9x0.9 m
unit Atap Ijuk 42,262,500.00
Saka 4
Atap Genteng 38,640,000.00
Bale Kulkul. L = Atap Pasir Semen 30,187,500.00
1 x 1 Saka 4 Bungan unit Atap Genteng 18,112,500.00
Atap Ijuk 33,810,000.00
Bale Kulkul. L = 1x1 Aatap Ijuk 54,337,500.00
Paras Cor Diatas Pondasi 30,187,500.00
Bale Kulkul. L = Batu diluar Pasir 60,375,000.00
1.5 x 1.5 Saka 8
unit Atap Genteng Semen 48,300,000.00
Batu
Atap Ijuk 78,487,500.00
Bale Kulkul. L = Paras Bata 30,187,500.00
Tinggi 3m unit
Batu Katangasem 38,640,000.00

Bataran
Bale Kulkul. L = 3 x 3 bataran unit batu bata / paras 84,000,000.00 80 jt
Bale Kulkul. L = 3 x 3 bataran unit Batu Karangasem 99,750,000.00
Bale Kulkul. L = 2.5x2.5 bataran unit batu bata / paras 63,000,000.00
Bale Kulkul. L = 2.5x2.5 bataran unit Batu Karangasem 78,750,000.00
Bata - Atap Alang - Alang 66,412,500.00
Bale Kulkul. L = 2.5 x 2.5 Bataran unit Bata - Atap Ijuk 72,450,000.00
Bata - Atap Genteng 48,300,000.00
Bata - Atap Ijuk 108,675,000.00
Bale Kulkul. L = 3x3T.4m unit Bata - Atap Genteng 60,375,000.00
Bata - Atap Alang - Alang 84,525,000.00
Bata - Atap Alang - Alang 120,750,000.00
Bale Kulkul. L = 3.5 x 3.5 unit Bata - Atap Ijuk 150,937,500.00
Bata - Atap Genteng 96,600,000.00
2 Ande 10,867,500.00
Bale Kulkul. L = 4 m2 unit
3 Ande 15,697,500.00

6 Padmasari T = 2.5 m unit Batu / Paras 6,562,500.00


Padmasari T = 2.5 m unit Batu Karangasem 7,350,000.00
Padmasari T = 3m unit Batu / Paras 8,925,000.00
No JENIS BAHAN/BANGUNAN UK/BAHAN SAT KETERANGAN HARGA

Padmasari T = 3m unit Batu Karangasem 11,550,000.00


4.5 m Batu / Paras 66,412,500.00
Padmasana T = 4.5 m unit Batu Karangasem 84,525,000.00
4.5 m Paras Cetak 26,250,000.00
Padmasana T = 5.5 m unit Batu / Paras 102,637,500.00
Padmasana T = 5.5 m unit Batu Karangasem 108,675,000.00
Padmasana T = 5.5 m unit Paras Cetak 72,450,000.00
Padmasana T = Rong 35cm T.5m unit Bata Press 102,637,500.00
Padmasana T = Rong 50cm T.6.5m unit Bata Press 120,750,000.00
Padmasana T = 6m unit Batu Karangasem 150,937,500.00

7 Bungan Rong 3. T = 93 x 40 cm Atap Ijuk 24,150,000.00


unit
Atap Genteng 19,320,000.00
Bungan Rong 3. T = 30 x 30 cm Atap Ijuk 18,716,250.00
unit
Atap Genteng 13,886,250.00
Bungan Rong 3. T = 104 x 45 cm Atap Ijuk 30,187,500.00
unit
Atap Genteng 24,753,750.00
Bataran + Bungan Rong 3. T = 90 x 40 + 35 x 80 Atap Ijuk 22,575,000.00
cm unit Atap Genteng 15,750,000.00
Batu Karangasem 12,600,000.00
Bataran + Bungan Rong 3. T = 105 x 50 x 51 cm Atap Ijuk 28,350,000.00
unit Atap Genteng 25,200,000.00
Batu Karangasem 13,282,500.00
Bungan Rong 3. T = 85 x 40 cm Atap Ijuk 21,000,000.00
unit
Atap Genteng 15,750,000.00
Bungan Rong 3. T = 100 x 40 cm Atap Ijuk 26,250,000.00
unit
Atap Genteng 21,000,000.00
90x90 kemulan
Bataran Rong 3. T = unit Batu Karangasem 16,301,250.00
mebanjah
Bataran Rong 3. T = unit Batu Candi 12,075,000.00
Bungan Rong 3. T = 1.40 m unit Tanpa Patung 10,867,500.00
Bata Press 6,641,250.00
Bataran Rong 3. T = 80x80x40
Batu Karangasem 16,301,250.00
Bata Press 5,433,750.00
Bataran Rong 3. T = 40x80
Batu Karangasem 9,056,250.00
1 x 1 m Kayu Atap Ijuk Finshing Prada
Bungan Rong 3. T = 26,565,000.00
Cempaka
Paras Taro + Kayu
Bataran + Bungan Rong 3. T = 3.5 12,075,000.00
Termasuk Kayu Atap Genteng
Batu Karangasem + Kayu
Bataran + Bungan Rong 3. T = 3.5 20,527,500.00
Bata Press + Kayu
Bataran + Bungan Rong 3. T = 3.5 30,187,500.00
Isi Saka didepan + Patung Singa
Paras Taro
Bataran Rong 3. T = 2.5 - 65 x 100 2,415,000.00
Batu Karangasem
Bataran Rong 3. T = 2.5 - 65 x 110 2 Ande 10,263,750.00

8 Sambang Saka 6 unit Atap Genteng 48,300,000.00


Sambang Saka 8
Saka 6 Saka Lambang - Atap Genteng 169,050,000.00
Saka 8 Cepaka Usuk - Atap Genteng 199,237,500.00
unit
Saka 12 Kamper - Atap Genteng 313,950,000.00
Sambang Saka 3 x 2 atap kayu diatas Atap Ijuk 90,562,500.00
unit
sendi Atap Genteng 181,125,000.00

9 Lumbung 1.80 x 2.20 1.80 x 2.20 unit Atap Genteng


102,637,500.00

10 Atap Ijuk 141,333,420.00


Meru (Bungan) = Tumpang 3
Atap Genteng 89,646,206.00

11 Atap Ijuk 235,555,699.00


Meru (Bungan) = Tumpang 5
Atap Genteng 149,410,342.00

12 Atap Ijuk 329,777,977.00


Meru (Bungan) = Tumpang 7
Atap Genteng 209,174,479.00
13 Atap Ijuk 424,000,257.00
Meru (Bungan) = Tumpang 9
Atap Genteng 268,938,616.00
14 Atap Ijuk 518,222,536.00
Meru (Bungan) = Tumpang 11
Atap Genteng 328,702,751.00
15 Atap Genteng 26,565,000.00
Bungan Pelik Sari 1.15 x 1.5
Atap Ijuk 54,337,500.00

16 Pelinggih Indra Blaka T= 2.25m set Batu Karangasem 10,263,750.00


Pelinggih Indra Blaka full set Batu Karangasem 10,867,500.00
No JENIS BAHAN/BANGUNAN UK/BAHAN SAT KETERANGAN HARGA

17 5.5 m Batu Karangasem 132,825,000.00


5.5 m Paras Bata 119,542,500.00
Kori Agung T = unit
8. m Batu Karangasem 682,500,000.00
8. m Paras Bata 525,000,000.00

1 Bale Pepelik
1.1 Bale Pepelik Atap Ijuk
a.a Bale Pepelik Caka 1.25 x 1.25 66,150,000.00
###
Bangunan Bawah 1 unit Bataran Batu Karangasem 29,400,000.00
###
Bangunan Atas 1 unit Kayu Kelas I ukir Finishing 36,750,000.00
###

a.b Caka 175 x 175 (3.06 m2) 81,900,000.00


###
Bangunan Bawah 1 unit Bataran Batu Karangasem 31,500,000.00
###
Bangunan Atas 1 unit Kayu Kelas I ukir Finishing 50,400,000.00
###

a.c Caka 225 x 225 (5.06 m2) 132,825,000.00


###
Bangunan Bawah 1 unit Bataran Batu Karangasem 59,325,000.00
###
Bangunan Atas 1 unit Kayu Kelas I ukir Finishing 73,500,000.00
###

b.a Bale Pepelik Caka 1.25 x 1.25 63,000,000.00


###
Bangunan Bawah 1 unit Bataran Batu Paras dan Bata 26,250,000.00
###
Bangunan Atas 1 unit Kayu Kelas I ukir Finishing 36,750,000.00
###

b.b Caka 175 x 175 78,750,000.00


###
Bangunan Bawah 1 unit Bataran Batu Paras dan Bata 28,350,000.00
###
Bangunan Atas 1 unit Kayu Kelas I ukir Finishing 50,400,000.00
###

b.c Caka 225 x 225 126,000,000.00


###
Bangunan Bawah 1 unit Bataran Batu Paras dan Bata 52,500,000.00
###
Bangunan Atas 1 unit Kayu Kelas I ukir Finishing 73,500,000.00
###

1.2 Bale Pepelik Atap Genteng


a.a Bale Pepelik Caka 1.25 x 1.25 58,800,000.00
###
Bangunan Bawah 1 unit Bataran Batu Karangasem 29,400,000.00
###
Bangunan Atas 1 unit Kayu Kelas I ukir Finishing 29,400,000.00
###

a.b Caka 175 x 175 71,400,000.00


###
Bangunan Bawah 1 unit Bataran Batu Karangasem 31,500,000.00
###
Bangunan Atas 1 unit Kayu Kelas I ukir Finishing 39,900,000.00
###

a.c Caka 225 x 225 121,800,000.00


###
Bangunan Bawah 1 unit Bataran Batu Karangasem 58,800,000.00
###
Bangunan Atas 1 unit Kayu Kelas I ukir Finishing 63,000,000.00
###

b.a Bale Pepelik Caka 1.25 x 1.25 55,650,000.00


###
Bangunan Bawah 1 unit Bataran Batu Paras dan Bata 26,250,000.00
###
Bangunan Atas 1 unit Kayu Kelas I ukir Finishing 29,400,000.00
###

b.b Caka 175 x 175 70,350,000.00


###
Bangunan Bawah 1 unit Bataran Batu Paras dan Bata 28,350,000.00
###
Bangunan Atas 1 unit Kayu Kelas I ukir Finishing 42,000,000.00
###

b.c Caka 225 x 225 115,500,000.00


###
Bangunan Bawah 1 unit Bataran Batu Paras dan Bata 52,500,000.00
###
Bangunan Atas 1 unit Kayu Kelas I ukir Finishing 63,000,000.00
###

2 Bale Gong
a. Bale Gong 375 x 375 m1 Caka 4 Ukir (14.66 m2) 163,800,000.00
###
Bangunan Bawah Pondasi 1 unit Bataran Batu Karangasem Lantai 52,500,000.00
###
Bangunan Atas 1 unit Kayu Kelas I Atap Finishing 111,300,000.00
###

b. Bale Gong 250 x 500 m1 Caka 6 Ukir (12.5 m2) 144,900,000.00


###
Bangunan Bawah 1 unit Bataran Karangasem Hitam Lantai 42,000,000.00
###
Bangunan Atas 1 unit Kayu Kelas I Atap Finishing 102,900,000.00
###

c. Bale Gong 300 x 600 m1 Caka 6 Ukir 210,900,000.00


###
Bangunan Bawah 1 unit Bataran Karangasem Hitam Lantai 55,500,000.00
###
Bangunan Atas 1 unit Kayu Kelas I Atap Finishing 155,400,000.00
###

d. Bale Gong 250 x 750 m1 Caka 8 Ukir (18.75 m2) 224,300,000.00


###
Bangunan Bawah 1 unit Bataran Batu Karangasem Lantai 60,500,000.00
###
Bangunan Atas 1 unit Kayu Kelas I Atap Finishing 163,800,000.00
###

2.2 Bale Gong ( Kupakan )


a. Bale Gong 375 x 375 m1 Caka 4 (Kupakan) 110,250,000.00
###
Bangunan Bawah 1 unit Bataran Batu Karangasem Lantai 42,000,000.00
###
Bangunan Atas 1 unit Kayu Kelas I Atap Finishing 68,250,000.00
###

b. Bale Gong 250 x 500 m1 Caka 6 (Kupakan) 96,600,000.00


###
Bangunan Bawah 1 unit Bataran Batu Karangasem Lantai 33,600,000.00
###
Bangunan Atas 1 unit Kayu Kelas I Atap Finishing 63,000,000.00
###
No JENIS BAHAN/BANGUNAN UK/BAHAN SAT KETERANGAN HARGA

c. Bale Gong 300 x 600 m1 Caka 6 ( Kupakan ) 138,600,000.00


###
Bangunan Bawah 1 unit Bataran Batu Karangasem Lantai 44,100,000.00
###
Bangunan Atas 1 unit Kayu Kelas I Atap Finishing 94,500,000.00
###

d. Bale Gong 250 x 750 m1 Caka 8 (Kupakan) 143,850,000.00


###
Bangunan Bawah 1 unit Bataran Batu Karangasem Lantai 47,250,000.00
###
Bangunan Atas 1 unit Kayu Kelas I Atap Finishing 96,600,000.00
###

3.1 Bale Pengerahuan/Pengiasan

a. Bale Pengerauhan/Pengiasan 250 x 300 m1 Caka 4 Ukir 102,900,000.00


###

Bangunan Bawah 1 unit Bataran Batu Karangasem Lantai 36,750,000.00


###
Kayu Kelas I Atap Finishing Plus Bale
Bangunan Atas 1 unit 66,150,000.00
###
Parba

b. Bale Pengerauhan/Pengiasan 250 x 600 m1 Caka 6 Ukir 183,750,000.00


###

Bangunan Bawah 1 unit Bataran Batu Karangasem Lantai 39,900,000.00


###
Kayu Kelas I Atap Finishing Plus Bale
Bangunan Atas 1 unit 143,850,000.00
###
Parba

c. Bale Pengerauhan/Pengiasan 250 x 750 m1 Caka 8 Ukir 225,750,000.00


###

Bangunan Bawah 1 unit Bataran Batu Karangasem Lantai 42,000,000.00


###
Kayu Kelas I Atap Finishing Plus Bale
Bangunan Atas 1 unit 183,750,000.00
###
Parba

3.2 Bale Pengerahuan/Pengiasan


Bale Pengerauhan/Pengiasan 250 x 300 m1 Caka 4
a. 73,500,000.00
###
Kupakan
Bangunan Bawah 1 unit Bataran Batu Karangasem Lantai 21,000,000.00
###
Kayu Kelas I Atap Finishing Plus Bale
Bangunan Atas 1 unit 52,500,000.00
###
Parba

Bale Pengerauhan/Pengiasan 250 x 600 m1 Caka 6 Ukir


b. 115,500,000.00
###
Kupakan
Bangunan Bawah 1 unit Bataran Batu Karangasem Lantai 31,500,000.00
###
Kayu Kelas I Atap Finishing Plus Bale
Bangunan Atas 1 unit 84,000,000.00
###
Parba

Bale Pengerauhan/Pengiasan 250 x 750 m1 Caka 8 Ukir


c. 178,500,000.00
###
Kupakan
Bangunan Bawah 1 unit Bataran Batu Karangasem Lantai 42,000,000.00
###
Kayu Kelas I Atap Finishing Plus Bale
Bangunan Atas 1 unit 136,500,000.00
###
Parba

4 Bale Gedong
4.1 Bale Gedong ijuk Batu Karangasem
a. Bale Gedong 150 x 175 m1 131,250,000.00
###
Pondasi Bataran Batu Karangasem
Bangunan Bawah 1 unit 57,750,000.00
###
Pintu Bali
Bangunan Atas 1 unit Kayu Kelas I Ukir Finishing 73,500,000.00
###

b. Bale Gedong 225 x 225 m1 204,750,000.00


###
Pondasi Bataran Batu Karangasem
Bangunan Bawah 1 unit 89,250,000.00
###
Pintu Bali
Bangunan Atas 1 unit Kayu Kelas I Ukir Finishing 115,500,000.00
###

c. Bale Gedong 250 x 250 m1 288,750,000.00


###
Pondasi Bataran Batu Karangasem
Bangunan Bawah 1 unit 131,250,000.00
###
Pintu Bali
Bangunan Atas 1 unit Kayu Kelas I Ukir Finishing 157,500,000.00
###

4.2 Bale Gedong Bataran Bata/Paras


a. Bale Gedong 150 x 175 m1 126,000,000.00
###
Pondasi Bataran Batu Bata/Paras Pintu
Bangunan Bawah 1 unit 68,250,000.00
###
Bali
Bangunan Atas 1 unit Kayu Kelas I Ukir Finishing 57,750,000.00
###

b. Bale Gedong 225 x 225 m1 189,000,000.00


###
Pondasi Bataran Batu Bata/Paras Pintu
Bangunan Bawah 1 unit 84,000,000.00
###
Bali
Bangunan Atas 1 unit Kayu Kelas I Ukir Finishing 105,000,000.00
###

c. Bale Gedong 250 x 250 m1 262,500,000.00


###
Pondasi Bataran Batu Bata/Paras Pintu
Bangunan Bawah 1 unit 126,000,000.00
###
Bali
Bangunan Atas 1 unit Kayu Kelas I Ukir Finishing 136,500,000.00
###
No JENIS BAHAN/BANGUNAN UK/BAHAN SAT KETERANGAN HARGA

5.0 Bale Piyasan


a. Bale Piyasan 100 x 150 cm 39,270,000.00
###
Bangunan Bawah 1 unit Bataran Batu Hitam Karangasem 19,057,500.00
###
Bangunan Atas 1 unit Kayu Kelas I Ukir Finishing (genteng) 20,212,500.00
###

b. Bale Piyasan 120 x 180 cm 56,595,000.00


###
Bangunan Bawah 1 unit Bataran Batu Hitam Karangasem 27,720,000.00
###
Bangunan Atas 1 unit Kayu Kelas I Ukir Finishing (genteng) 28,875,000.00
###

c. Bale Piyasan 150 x 200 cm 79,117,500.00


###
Bangunan Bawah 1 unit Bataran Batu Hitam Karangasem 38,461,500.00
###
Bangunan Atas 1 unit Kayu Kelas I Ukir Finishing (genteng) 40,656,000.00
###

Disetujui :
Pejabat Pembuat Komitmen / PPK Mangupura, Maret 2020
Kepala Bidang Cipta Karya Disusun Oleh :
Dinas Pekerjaan Umum dan Penataan Ruang CV. Wahana Design
Kabupaten Badung Konsultan Perencana

IGA. Ngr. Arinda Trisnawati ST, MT


Pembina I Wayan Gunarsa
Nip.19690524 19980321 005 Direktur

Mengetahui :
Kepala Dinas Pekerjaan Umum dan Penataan Ruang
Kabupaten Badung

Ida Bagus Surya Suamba, ST, MT


Pembina Utama Muda
Nip.19720916 199703 1 004
DAFTAR HARGA SATUAN ALAT-ALAT MEKANIS

NO URAIAN KODE HARGA SATUAN


A B C D E
Aggregat (chip) spreader
Alat grouting
Alat las (karbit)
Alat pemasangan rivet
Alat tambahan batubara (direct)
Alat tambahan gas batubara
Asphalt tanker
Asphalt distrbibutor
Asphalt finisher
Asphalt liquid mixer
Asphalt mixing plant
Asphalt sprayer
Bar bender/rebar bender, bar straightener
Bar cutter/rebar cutter
Bekisting/acuan tetap untuk jalan beton (pelat baja tebal 5 mm)
Blending equipment (pencampur agregat)
Boat/speed boat
Bor beton
Bore pile machine
Breaker
Bulldozer (100-150) HP
Cement tanker
Chain saw
Cetakan armor
Cold milling
Cold recycler
Compressor (4000-6500) L/menit
Concrete mixer 250 L
Concrete mixer 300-600 L
Concrete pan mixer 1200 L
Conrete pump
Concrete vibrator
Crane (….ton)
Diamond grinding machine (untuk beton)
Drilling rig
Dump truck (….m3)
Flat bed truck (3-4) m3
Fixed form Paver
Forklift
Palvi mixer
Generator set
Geolistrik
Gondola
Grouting pump
Hot recycler
Jack hammer
Jack hidraulic
Kapal keruk (dredger ship)
Lift kerja
Mesin potong rumput
Mobil (kendaraan roda empat)
Motor grader > 300 HP
Mud pump
Pedestrian roller
Penarik kabel
Perahu
Pile driver + hammer
Pipe jacking
Pipe line cutter
Polisher
Ponton
Rakit
Sand pump/dredger
Slip form paver
Sondir (dutch cone penetrometer)
Stone crusher
Stressing jack
Stressing machine
Submersible pump
Tamper
Tandem roller (6 - 8) ton
Theodolit/waterpass
Three wheel roller (6 - 8) ton
Tire roller (8 - 10) ton
Tongkang
Track loader (75 - 100) HP
Trailer 20 ton
Trawel
Tripod/tackle
Tronton
Truck mixer (agigator)
Tunneling boring machine
Vibrating rammer
Vibratory roller (5 - 8) ton
Water jet
Water pump (70 - 100) mm
Water tanker (3000 - 4500) L
Wheel loader (1.0 - 1.6) m3
DAFTAR HARGA SATUAN ALAT BANTU

NO URAIAN KODE HARGA SATUAN


A B C D E
Ganto/balincong
Cangkul
Sekop
Sabit
Sapu lidi
Ekrak/pengki
Kereta dorong
Cetok/sendok tembok
Ember/timba
Garu
Sikat ijuk
Hammer/martil
Parang
Palu
Linggis
Kereta dorong besar
Alat sifat datar/waterpass/nipo
Tempat penggorengan aspal
Kuas
Ampelas
Sikat baja
Gunting potong baja
Kunci pembengkok
Helmet
Rompi
Sepatu
Roskam
Gergaji
Kapak
Pahat kayu
Pahat beton
Dolag/dolak
Kayu kasut/mistar
Kayu pemikul/tanpar
Unting-unting
Pemotong ubin/keramik/granit tile
Timbris
Pasekon
Jaring pengaman
Sling cable
Tang/kakatua
Serutan (manual/mesin)
Mesin amplas
Kape/skrap
Bor kayu/tembok/beton
DAFTAR HARGA SATUAN UPAH PEKERJA

NO TENAGA KERJA KODE HARGA SATUAN


A B C D E
1 Pekerja L.01 112,500.00 Org/Hari
2 Tukang gali L.02 120,000.00 OH
3 Tukang batu L.03 127,500.00 OH
4 Tukang kayu L.04 132,500.00 OH
5 Tukang besi L.05 127,500.00 OH
6 Tukang cat L.06 127,500.00 OH
7 Tukang pipa L.07 127,500.00 OH
8 Tukang style Bali L.08 157,000.00 OH
9 Tukang listrik L.09 130,000.00 OH
Tukang las L.10a 130,000.00 OH
10
Tukang las konstruksi L.10b 130,000.00 OH
11 Tukang vibrator L.11 OH
12 Tukang aluminium L.12 130,000.00 OH
13 Tukang ereksi L.13 OH
14 Kepala tukang L.14 147,500.00 OH
15 Kepala tukang style bali L.15 175,000.00 OH
16 Mandor style bali L.16 190,000.00 OH
17 Mandor L.17 150,000.00 OH
18 Juru ukur L.18 132,500.00 OH
19 Pembantu juru ukur L.19 122,500.00 OH
20 Mekanik alat berat L.20 145,000.00 OH
Operator alat berat L.21a 175,000.00 OH
21
Operator crane L.21b OH
Pembantu operator L.22a 150,000.00 OH
22
Pembantu operator crane L.22b OH
23 Supir truk L.23 162,500.00 OH
24 Kenek truk L.24 110,000.00 OH
25 Juru gambar (drafter) L.25 125,000.00 OH
26 Operator printer/plotter L.26 120,000.00 OH
Tenaga ahli utama (S1 min 13 th) L.27a 1,381,905.00 OH
Tenaga ahli madya (S1 min 9 th) L.27b 1,071,945.00 OH
27
Tenaga ahli muda (S1 min 5 th) L.27c 807,905.00 OH
Tenaga ahli pratama (S1 min 3 th) L.27d OH
Narasumber pejabat eselon L.28a OH
28
Narasumber praktisi L.28b OH
29 Lainnya L.29 OH
62

DAFTAR HARGA SATUAN BAHAN

NO KODE NAMA BARANG SATUAN MERK

A B C D E

A MATERIAL ALAM
I Batu / Biji Terasso
1 M1 Batu / Biji Terasso / Batu Padalarang kg
II Batu Alam
2 M2 Batu Alam RTM Hijau 10 x 20 halus m2
3 M3 Batu Alam RTM Hijau 20 x 20 halus m2
4 M4 Batu Alam RTS Hijau 10 x 20 kasar m2
III Batu Andesit
5 M5 Batu Andesit 30 x 40 Abu SS m2
6 M6 Batu Andesit 30 x 60 Hitam Bakar m2
7 M7 Batu Andesit 40 x 40 Hitam Bakar m2
8 M8 Batu Andesit 40 x 60 Hitam Kilap m2
9 M9 Batu Andesit 50 x 50 Hitam m2
10 M10 Batu Andesit 60 x 60 Abu m2
IV Batu Bali
11 M11 Batu Bali Green Gelombang 20 x 40 m2
12 M12 Batu Bali Green Kombinasi 20 x 40 m2
V Batu Belah & Split
13 M13 Batu Kali truk (8,5 m3)
14 M14 Batu Kali m3
15 M15 Batu Kali Belah / Batu Bulat 15/20 cm m3
16 M16 Batu Kali Belah / Batu Bulat 15/20 cm truk (8,5 m3)
17 M17 Batu Karang m3
18 M18 Batu Karang truk (8,5 m3)
19 M19 Batu Lahar Singaraja m3
20 M20 Batu Lahar Singaraja truk (8,5 m3)
21 M21 Batu Makadam m3
22 M22 Batu Makadam truk (8,5 m3)
23 M23 Batu Pecah 2-3 cm (Manual) m3
24 M24 Batu Pecah 3-5 cm (Manual) m3
25 M25 Batu Pecah 5-7 cm (Manual) m3
26 M26 Batu Pecah Besar m3
27 M27 Batu Pecah Besar truk (8,5 m3)
28 M28 Batu Pecah Mesin 1/2 m3
29 M29 Batu Pecah Mesin 2/3 m3
30 M30 Batu Split m3
31 M31 Batu Split truk (8,5 m3)
32 M32 Koral Beton 2/3 Ex. 4 per 2,75 m3 m3
33 M33 Koral Beton 2/3 Ex. 4 per 2,75 m4 kg
34 M34 Limestone m3
35 M35 Limestone truk (8,5 m3)
36 M36 Sirdam Urug m3
37 M37 Sirdam Urug truk (8,5 m3)
38 M38 Sirtu Urug m3
39 M39 Sirtu Urug truk (8,5 m3)
VI Batu Candi
40 M40 Batu Candi Hitam 20 x 20 m2
41 M41 Batu Candi Hitam 20 x 30 m2
42 M42 Batu Candi Hitam 30 x 30 m2
43 M43 Batu Candi Hitam 40 x 40 m2
44 M44 Batu Candi Hitam 60 x 60 m2
VII Batu Gunung
45 M45 Batu Gunung ex. Karangasem buah
VIII Batu Hitam
46 M46 Batu Hitam Jember 15 x 30 Halus m2
47 M47 Batu Hitam Jember 20 x 40 Halus m2
48 M48 Batu Hitam Jember 5 x 20 Halus m2
49 M49 Batu Hitam Singaraja 15 x 30 Halus m2
50 M50 Batu Hitam Singaraja 20 x 40 Halus m2
IX Batu Kuning
51 M51 Batu Kuning Serat 20 x 30 m2
52 M52 Batu Kuning Serat 30 x 30 m2
X Batu Marmer
53 M53 Batu Marmer Kuning 10 x 20 m2
54 M54 Batu Marmer Kuning 15 x 39 m2
55 M55 Batu Marmer Kuning PB 1 10 x 20 m2
56 M56 Batu Marmer Kuning PB 2 10 x 20 m2
XI Batu Palimanan
57 M57 Batu Palimanan Cirebon 20 x 30 m2
58 M58 Batu Palimanan Cirebon 20 x 40 m2
XII Batu Paras
59 M59 Batu Paras Jogja 60 x 60 m2
60 M60 Batu Paras Jogja Putih 20 x 30 buah
XIII Batu Pilah
61 M61 Batu Pilah Jember 20 x 30 m2
62 M62 Batu Pilah Jember 30 x 30 m2
63 M63 Batu Pilah Jember 40 x 40 m2
64 M64 Batu Pilah Singaraja 20 x 20 m2
65 M65 Batu Pilah Singaraja 30 x 30 m2
XIV Batu Pipih
63

NO KODE NAMA BARANG SATUAN MERK

A B C D E
66 M66 Batu Pipih Singaraja m3
XV Batu Serayu
67 M67 Batu Serayu 20 x 60 m2
XVI Kapur
68 M68 Kapur Padam / Hydrated Lime kg
XVII Loster
69 M69 Loster Ukir Paras Cor 30 x 30 buah
70 M70 Bata roster 12 x 11 x 24 buah
XVIII Paras
71 M71 Paras Batik buah
72 M72 Paras Batik m2
73 M73 Paras Buahan buah
74 M74 Paras Buahan m2
75 M75 Paras Karang Bukit Tebal 6 cm buah
76 M76 Paras Karang Bukit Tebal 6 cm m2
77 M77 Paras Malem buah
78 M78 Paras Malem m2
79 M79 Paras Putih Bukit Tebal 6 cm buah
80 M80 Paras Putih Bukit Tebal 6 cm m2
81 M81 Paras Silakarang Tebal buah
82 M82 Paras Silakarang Tebal m2
83 M83 Paras Silarakang Tipis buah
84 M84 Paras Silarakang Tipis m2
85 M85 Paras Tulung Agung buah
86 M86 Paras Tulung Agung m2
87 M87 Paras Untuk Pondasi buah
88 M88 Paras Untuk Pondasi m2
XIX Pasir
89 M89 Pasir Beton / Cor Ex. 4 per 2,75 m3 m3
90 M90 Pasir Beton / Cor Ex. 4 per 2,75 m4 kg
91 M91 Pasir Halus (Diayak) m3
92 M92 Pasir Pasang m3
93 M93 Pasir Urug m3
94 M94 Sirtu (Pasir dan Batu) m3
XX Tanah
95 M95 Tanah Liat m3
96 M96 Tanah Urug m3
XXI Terasso
97 M97 Terasso Cor m3

B MATERIAL ALUMINIUM COMPOSITE PANEL (ACP)


I ACP Ukuran 2400x1220 mm Tebal 3mm
98 M98 ACP Goodsense Wooden Series lembar
99 M99 ACP Goodsense Brushed Series lembar
100 M100 ACP Goodsense Normal Series lembar
101 M101 ACP Goodsense Normal Series Glossy lembar
II ACP Ukuran 2400x1220 mm Tebal 4mm
102 M102 ACP Goodsense Brushed Series lembar
103 M103 ACP Goodsense Mirror Series lembar
104 M104 ACP Goodsense PE lembar
105 M105 ACP Goodsense PVDF lembar
106 M106 ACP Goodsense PVDF 3003 lembar
107 M107 ACP Goodsense PVDF FR lembar
108 M108 ACP Goodsense PVDF FR 3003 lembar
109 M109 ACP Goodsense PVDF Wooden lembar
III ACP Ukuran 2440x1220 mm Tebal 4mm
110 M110 ACP Aluclad 0.21 mm PE lembar
111 M111 ACP Aluclad 0.30 mm PVDF lembar
112 M112 ACP Aluclad 0.50 mm PVDF lembar
113 M113 ACP Alumebond 0.21 mm lembar
114 M114 ACP Alumebond 0.31 mm lembar
115 M115 ACP Aluprima Insta Motif 3 mm lembar
116 M116 ACP Aluprima Insta Polos 3 mm lembar
117 M117 ACP Alustar 0.21 mm lembar
118 M118 ACP Alustar 0.30 mm lembar
119 M119 ACP Decobond 2 mm lembar
120 M120 ACP Decobond 3 mm lembar
121 M121 ACP Decobond 3 mm DS lembar
122 M122 ACP Decobond 4 mm lembar
123 M123 ACP Decobond 4 mm DS lembar
124 M124 ACP Ferobond .50 mm PVDF lembar
125 M125 ACP Ferobond 0.21 mm PE lembar
126 M126 ACP Ferobond 0.30 mm PVDF lembar
127 M127 ACP Globond PE 0.30 mm lembar
128 M128 ACP Globond PVDF 0.3 mm lembar
129 M129 ACP JIYU FEVE PVDF 0.3 mm Doff lembar
130 M130 ACP JIYU FEVE PVDF 0.3 mm Glossy lembar
131 M131 ACP JIYU PE 0.21 mm lembar
132 M132 ACP JIYU PE 0.21 mm Double Side lembar
133 M133 ACP Luminate 0.21 mm lembar
134 M134 ACP Luminate 0.30 mm lembar
135 M135 ACP Seven PE 0.21 mm Glossy lembar
136 M136 ACP Seven PE 0.21 mm Standard lembar
64

NO KODE NAMA BARANG SATUAN MERK

A B C D E
137 M137 ACP Seven PVDF 0.30 mm Glossy lembar
138 M138 ACP Seven PVDF 0.30 mm Glossy lembar
139 M139 ACP Seven PVDF 0.30 mm Sparkling lembar
140 M140 ACP Seven PVDF 0.30 mm Standard lembar
141 M141 ACP Seven PVDF 0.30 mm Standard lembar
IV ACP Ukuran 4880x1220 mm Tebal 4mm
142 M142 ACP Alucobon 0.30 mm lembar
143 M143 ACP Alucobon 0.40 mm lembar
144 M144 ACP Alumetal 0.21 mm lembar
145 M145 ACP Alumetal 0.30 mm lembar

C MATERIAL ATAP
I Aksesoris
146 M146 Lisplank siku (gelombang besar 6) buah
147 M147 Lisplank siku (gelombang kecil 11) buah
148 M148 Lisplank siku (gelombang kecil 14) buah
149 M149 Lisplank simteris (gelombang besar 6) buah
150 M150 Nok Stel Gelombang (gelombang besar 6) buah
151 M151 Nok Stel Gelombang (gelombang kecil 11) buah
152 M152 Nok Stel Gelombang (gelombang kecil 14) buah
153 M153 Nok Stel Rata (gelombang besar 6) buah
154 M154 Nok Stel Rata (gelombang kecil 14) buah
155 M155 Ujung Nok Stel (gelombang besar 6) buah
156 M156 Ujung Nok Stel (gelombang kecil 11) buah
157 M157 Ujung Nok Stel (gelombang kecil 14) buah
II Atap Asbes Gelombang
158 M158 Djabesmen gelombang, 150×105 cm lembar
159 M159 Djabesmen gelombang, 180×105 cm lembar
160 M160 Djabesmen gelombang, 210×105 cm lembar
161 M161 Djabesmen gelombang, 240×105 cm lembar
162 M162 Djabesmen gelombang, 270×105 cm lembar
163 M163 Djabesmen gelombang, 300×105 cm lembar
164 M164 Djabesmen Nok Asbes pasang
165 M165 Harflex 150 x 105 x 0.4 lembar
166 M166 Harflex 150 x 80 x 0.35 lembar
167 M167 Harflex 180 x 105 x 0.4 lembar
168 M168 Harflex 180 x 80 x 0.35 lembar
169 M169 Harflex 210 x 105 x 0.4 lembar
170 M170 Harflex 210 x 80 x 0.35 lembar
171 M171 Harflex 240 x 105 x 0.4 lembar
172 M172 Harflex 240 x 80 x 0.35 lembar
173 M173 Harflex 270 x 105x 0.4 lembar
174 M174 Harflex 270 x 80 x 0.35 lembar
175 M175 Harflex 300 x 105 x 0.4 lembar
176 M176 Harflex 300 x 80 x 0.35 lembar
177 M177 Harflex Asbes Genteng 85cm x 115cm x 0.4cm lembar
178 M178 Harflex Nok Asbes Genteng 105cm pasang
179 M179 Harflex Nok Stel Gelombang 105cm pasang
180 M180 Harflex Nok Stel Gelombang 80cm pasang
III Atap Metal Spandek
181 M181 Atap Spandek Pasir 0.30 mm, lebar 1 meter m1
182 M182 Atap Spandek Pasir 0.35 mm, lebar 1 meter m1
183 M183 Atap Spandek Pasir 0.40 mm, lebar 1 meter m1
184 M184 Atap Spandek Pasir 0.45 mm, lebar 1 meter m1
185 M185 Atap Spandek Pasir 0.50 mm, lebar 1 meter m1
186 M186 Atap Spandek Tebal 0.25 mm, lebar 1 meter m1
187 M187 Atap Spandek Tebal 0.30 mm, lebar 1 meter m1
188 M188 Atap Spandek Tebal 0.35 mm, lebar 1 meter m1
189 M189 Atap Spandek Tebal 0.40 mm, lebar 1 meter m1
190 M190 Atap Spandek Tebal 0.45 mm, lebar 1 meter m1
191 M191 Atap Spandek Tebal 0.50 mm, lebar 1 meter m1
192 M192 Atap Spandek Warna 0.30 mm, lebar 750mm m1
193 M193 Atap Spandek Warna 0.35 mm, lebar 750mm m1
194 M194 Atap Spandek Warna 0.40 mm, lebar 750mm m1
195 M195 Atap Spandek Warna 0.45 mm, lebar 750mm m1
196 M196 Atap Spandek Warna 0.50 mm, lebar 750mm m1
197 M197 Atap Spandek Zincalume 0.25 mm, lebar 1 meter m1
198 M198 Atap Spandek Zincalume 0.30 mm, lebar 1 meter m1
199 M199 Atap Spandek Zincalume 0.35 mm, lebar 1 meter m1
200 M200 Atap Spandek Zincalume 0.40 mm, lebar 1 meter m1
201 M201 Atap Spandek Zincalume 0.45 mm, lebar 1 meter m1
202 M202 Atap Spandek Zincalume 0.45 mm, lebar 1 meter buah
IV Atap Non Asbes Gelombang
203 M203 Eter11 3,5, 800x1800mm, tebal 3,5mm (gelombang kecil) lembar
204 M204 Eter11 3,5, 800x2100mm, tebal 3,5mm (gelombang kecil) lembar
205 M205 Eter11 3,5, 800x2400mm, tebal 3,5mm (gelombang kecil) lembar
206 M206 Eter14 4, 1050x1800mm, tebal 4mm (gelombang kecil) lembar
207 M207 Eter14 4, 1050x2100mm, tebal 4mm (gelombang kecil) lembar
208 M208 Eter14 4, 1050x2400mm, tebal 4mm (gelombang kecil) lembar
209 M209 Eter14 4, 1050x2700mm, tebal 4mm (gelombang kecil) lembar
210 M210 Eter14 4, 1050x3000mm, tebal 4mm (gelombang kecil) lembar
211 M211 Eter6 5, 1000x1500mm tebal 5mm (gelombang besar) lembar
212 M212 Eter6 5, 1000x1800mm tebal 5mm (gelombang besar) lembar
65

NO KODE NAMA BARANG SATUAN MERK

A B C D E
213 M213 Eter6 5, 1000x2000mm tebal 5mm (gelombang besar) lembar
214 M214 Eter6 5, 1000x2250mm tebal 5mm (gelombang besar) lembar
215 M215 Eter6 5, 1000x2500mm tebal 5mm (gelombang besar) lembar
216 M216 Eter6 5, 1000x3050mm tebal 5mm (gelombang besar) lembar
217 M217 Eter6 6, 1000x1500mm, tebal 6mm (gelombang besar) lembar
218 M218 Eter6 6, 1000x1800mm, tebal 6mm (gelombang besar) lembar
219 M219 Eter6 6, 1000x2000mm, tebal 6mm (gelombang besar) lembar
220 M220 Eter6 6, 1000x2250mm, tebal 6mm (gelombang besar) lembar
221 M221 Eter6 6, 1000x2500mm, tebal 6mm (gelombang besar) lembar
222 M222 Eter6 6, 1000x3050mm, tebal 6mm (gelombang besar) lembar
223 M223 Eter6 6, 1000x3650mm, tebal 6mm (gelombang besar) lembar
V Genteng Beton
224 M224 Genteng AM Flat
225 M225 Genteng AM flat
226 M226 Genteng Cisangkan Flat
227 M227 Genteng Elabana
228 M228 Genteng Flat Multiline
229 M229 Genteng Garuda
230 M230 Genteng Moenir Gelombang
231 M231 Genteng Moenir gelombang
232 M232 Genteng Mutiara Jakarta
233 M233 Genteng Mutiara Jakarta Flat
234 M234 Genteng Mutiara Yogyakarta Flat
235 M235 Genteng Rabi Flat
236 M236 Genteng Rabi flat
237 M237 Genteng Triple S Flat
238 M238 Genteng Triple S flat
VI Genteng Beton Cisangkan
239 M239 Apex buah
240 M240 Apex O buah
241 M241 Bok Bawah (All Vic & Dual Slate) buah
242 M242 Double Tile (All Vic) buah
243 M243 Genteng Bawah O/RR buah
244 M244 Genteng Dual Slate 1 m2 = 8,8 buah buah
245 M245 Genteng Excellent 1 m2 = 8,8 buah buah
246 M246 Genteng Floral 1 m2 = 8,8 buah buah
247 M247 Genteng Kaca 5mm (M/O/RR/Ex) buah
248 M248 Genteng Kaca 6mm (Vic/Dual Slate/F) buah
249 M249 Genteng Kiri/Kanan M buah
250 M250 Genteng Kiri/Kanan O buah
251 M251 Genteng Majestic 1 m2 = 8,8 buah buah
252 M252 Genteng New Royal 1 m2 = 12 buah buah
253 M253 Genteng Oriental 1 m2 = 12 buah buah
254 M254 Genteng Sudut Kiri/Kanan O buah
255 M255 Genteng Victoria Classic 1 m2 = 9,8 buah buah
256 M256 Genteng Victoria Multiline 1 m2 = 9,8 buah buah
257 M257 Genteng Victoria Onyx 1 m2 = 9,8 buah buah
258 M258 Genteng Victoria Pine 1 m2 = 9,8 buah buah
259 M259 Genteng Victoria Slate 1 m2 = 9,8 buah buah
260 M260 Nok Atas buah
261 M261 Nok Samping buah
262 M262 Nok Siku (All Vic & Dual Slate) buah
263 M263 Nok Ujung buah
264 M264 Starter buah
265 M265 Starter Siku (All Vic & Dual Slate) buah
266 M266 Tepi Kiri/Kanan M buah
267 M267 Tepi Kiri/Kanan O buah
VII Genteng Keramik
268 M268 Genteng GMI buah
269 M269 Genteng Kanmuri Espanica buah
270 M270 Genteng Kanmuri Espanica Brown Glossy buah
271 M271 Genteng Kanmuri Full Flat buah
272 M272 Genteng Kanmuri Full Flat Medi Grey Glasur buah
273 M273 Genteng Kanmuri Full Flat Silky Silk Black buah
274 M274 Genteng Kanmuri Milenio buah
275 M275 Genteng Kanmuri Milenio Medy Magnolia buah
276 M276 Genteng KIA Choco Brown buah
277 M277 Genteng KIA Jade Green buah
278 M278 Genteng KIA Jasper Brown buah
279 M279 Genteng KIA Jasper Grey buah
280 M280 Genteng KIA Ruby Maroon buah
281 M281 Genteng KIA Solar Brown buah
282 M282 Genteng KIA Solar Brown kw 2 buah
283 M283 Genteng M-Class Copper kw 1 buah
284 M284 Genteng M-Class Dark Brown Kw 1 buah
285 M285 Genteng M-Class Green kw 1 buah
286 M286 Genteng M-Class Mahogany kw 1 buah
287 M287 Genteng M-Class Matt Black Kw 1 buah
288 M288 Genteng M-Class Matt grey kw 1 buah
289 M289 Genteng M-Class Matt Orange buah
290 M290 Genteng M-Class Matt Yellow kw 1 buah
291 M291 Genteng M-Class Purple Blue buah
292 M292 Genteng Monier Marron buah
66

NO KODE NAMA BARANG SATUAN MERK

A B C D E
VIII Genteng Metal Berpasir
293 M293 Addesia, G. Metal Batuan 2×4 T.0.25, 77x 80×0.25 cm lembar
294 M294 Addesia, Genteng Metal Batuan 2×4 T.0.25*, 77x80x0.25 cm lembar
295 M295 Genteng Metal Biasa; Warna; T: 0.3mm; Type 4×2, Uk. 87x47cm lembar
296 M296 Genteng Metal Pasir GMT, T= 0.35mm, UK. 80x80cm lembar
297 M297 Genteng Metal Polos GMT, T= 0.25mm, UK. 80x80cm lembar
298 M298 Genteng Metal Polos GMT, T= 0.35mm, UK. 80cm lembar
299 M299 Inti Roof 1×4 T.0.25 Batuan, 38.5x80x0.25 cm lembar
300 M300 Inti Roof 1×4 T.0.25, 38.5x80x0.25 cm lembar
301 M301 Inti Roof 1×4 T.0.30 Batuan, 38.5 x80x0.30 cm lembar
302 M302 Inti Roof 1×4 T.0.30 Batuan, 77 x100x0.35 cm lembar
303 M303 Inti Roof 1×4 T.0.35 Batuan, 38.5x80x0.35 cm lembar
304 M304 Inti Roof 2×4 T.0.25 Batuan, 77x80x0.25 cm lembar
305 M305 Inti Roof 2×4 T.0.25 Batuan, 77x80x0.35 cm lembar
306 M306 Inti Roof 2×4 T.0.3, 77x80x0.25 cm lembar
307 M307 Inti Roof 2×4 T.0.35 Batuan, 77x80x0.35 cm lembar
308 M308 Nok Genteng Metal Polos GMT, T= 0,25mm, UK. 80cm lembar
309 M309 Rainbow Arista Costa 2 susun; berpasir; type 2×4, T: 0,35; Uk. 82x75cm lembar
310 M310 Rainbow Arista Costa 2 susun; tidak berpasir; type 2×4, T: 0,35; Uk. 82x75cm lembar
311 M311 Rainbow Minimalis Allure Berpasir, Type :1×4, T: 0,3mm; Uk. 82.5x36cm lembar
312 M312 Rainbow Minimalis Allure, Berpasir, Type :1×4, T: 0,35mm; Uk. 82.5x36cm lembar
313 M313 Rainbow Minimalis Dwi Warna, Berpasir;Type 1×4, T: 0.35mm; Uk. 83x37cm lembar
314 M314 Rainbow Minimalis Dwi Warna, Berpasir;Type 1×4, T: 0.45mm; Uk. 83x37cm lembar
315 M315 Rainbow Minimalis Elegant, Berpasir Type 1×4, T: 0.35mm; UK. 85.5x40cm lembar
316 M316 Rainbow Minimalis Elegant, Berpasir Type 1×4, T= 0.3mm, UK. 85.5x40cm lembar
317 M317 Rainbow Toscano, Berpasir, Type 1×4, T: 0.3mm; Uk. 87.5×47.5cm lembar
318 M318 Sakura 2×4 Color T.0.25, 77x80x0.25 cm lembar
319 M319 Sakura Batuan 2×4 T.0.25, 77x80x0.25 cm lembar
320 M320 Sakura Batuan 2×4 T.0.25, 77x80x0.25 cm lembar
321 M321 Soka Batuan 2×4 T.0.25, 740 x80x0.25 cm lembar
322 M322 Super Batuan / Prima Roof, 77x80x0.25 cm lembar
323 M323 Super Batuan 1×4 T.0.25, 38.5x80x0.25 cm lembar
324 M324 Surya 2×4 Batuan T.0.30, 77x80x0.25 cm lembar
325 M325 Tiger Star, G Metal Color 2×4 + Peredam*, G Metal + Foil (laminating) lembar
IX Genteng Tanah Liat
326 M326 Genteng Garuda buah
327 M327 Genteng Kodok/ Prentul/ Goodyear buah
328 M328 Genteng Mintili Jumbo/ Turbo buah
329 M329 Genteng Plentong buah
330 M330 Genteng Super Gojer/ Morando buah
Seng Gelombang
331 M331 Gajah Berlian BJLS 0,20 - 0,50 mm 762 mm / 5 feet (1524 mm) lembar
332 M332 Gajah Berlian BJLS 0,20 - 0,50 mm 762 mm / 6 feet (1829 mm) lembar
333 M333 Gajah Berlian BJLS 0,20 - 0,50 mm 762 mm / 7 feet (2134 mm) lembar
334 M334 Gajah Berlian BJLS 0,20 - 0,50 mm 762 mm / 8 feet (2438 mm) lembar
335 M335 Gajah Berlian BJLS 0,20 - 0,50 mm 762 mm / 9 feet (2743 mm) lembar
336 M336 Gajah Berlian BJLS 0,20 - 0,50 mm 762 mm / 10 feet (3048 mm) lembar
337 M337 Gajah Berlian BJLS 0,20 - 0,50 mm 914 mm / 5 feet (1524 mm) lembar
338 M338 Gajah Berlian BJLS 0,20 - 0,50 mm 914 mm / 6 feet (1829 mm) lembar
339 M339 Gajah Berlian BJLS 0,20 - 0,50 mm 914 mm / 7 feet (2134 mm) lembar
340 M340 Gajah Berlian BJLS 0,20 - 0,50 mm 914 mm / 8 feet (2438 mm) lembar
341 M341 Gajah Berlian BJLS 0,20 - 0,50 mm 914 mm / 9 feet (2743 mm) lembar
342 M342 Gajah Berlian BJLS 0,20 - 0,50 mm 914 mm / 10 feet (3048 mm) lembar
343 M343 Gajah Berlian BJLS 0,20 - 0,30 mm 762 mm / 5 feet (1524 mm) lembar
344 M344 Gajah Berlian BJLS 0,20 - 0,30 mm 762 mm / 6 feet (1829 mm) lembar
345 M345 Gajah Berlian BJLS 0,20 - 0,30 mm 762 mm / 7 feet (2134 mm) lembar
346 M346 Gajah Berlian BJLS 0,20 - 0,30 mm 762 mm / 8 feet (2438 mm) lembar
347 M347 Gajah Berlian BJLS 0,20 - 0,0 mm 762 mm / 9 feet (2743 mm) lembar
348 M348 Gajah Berlian BJLS 0,20 - 0,30 mm 762 mm / 10 feet (3048 mm) lembar
349 M349 Gajah Berlian BJLS 0,20 - 0,30 mm 914 mm / 5 feet (1524 mm) lembar
350 M350 Gajah Berlian BJLS 0,20 - 0,30 mm 914 mm / 6 feet (1829 mm) lembar
351 M351 Gajah Berlian BJLS 0,20 - 0,30 mm 914 mm / 7 feet (2134 mm) lembar
352 M352 Gajah Berlian BJLS 0,20 - 0,30 mm 914 mm / 8 feet (2438 mm) lembar
353 M353 Gajah Berlian BJLS 0,20 - 0,30 mm 914 mm / 9 feet (2743 mm) lembar
354 M354 Gajah Berlian BJLS 0,20 - 0,30 mm 914 mm / 10 feet (3048 mm) lembar

D MATERIAL BAJA RINGAN


I Baja Ringan Alfa Truss
355 M355 Kaso Baja Ringan Alfa Truss C75.100 6 Meter
356 M356 Kaso Baja Ringan Alfa Truss C75.100 m1
357 M357 Kaso Baja Ringan Alfa Truss C75.65 6 Meter
358 M358 Kaso Baja Ringan Alfa Truss C75.65 m1
359 M359 Kaso Baja Ringan Alfa Truss C75.75 6 Meter
360 M360 Kaso Baja Ringan Alfa Truss C75.75 Kg
361 M361 Kaso Baja Ringan Alfa Truss C75.75 m1
362 M362 Reng Baja Ringan Alfa Truss 31.45 6 Meter
363 M363 Reng Baja Ringan Alfa Truss 31.45 m1
II Baja Ringan BMT Truss
364 M364 Kaso Baja Ringan BMT C75.100 6 Meter
365 M365 Kaso Baja Ringan BMT C75.100 m1
366 M366 Kaso Baja Ringan BMT C75.60 6 Meter
367 M367 Kaso Baja Ringan BMT C75.60 m1
368 M368 Kaso Baja Ringan BMT C75.70 6 Meter
67

NO KODE NAMA BARANG SATUAN MERK

A B C D E
369 M369 Kaso Baja Ringan BMT C75.70 m1
370 M370 Kaso Baja Ringan BMT C75.75 6 Meter
371 M371 Kaso Baja Ringan BMT C75.75 m1
372 M372 Reng Baja Ringan BMT 28.45 6 Meter
373 M373 Reng Baja Ringan BMT 28.45 m1
374 M374 Reng Baja Ringan BMT 30.45 6 Meter
375 M375 Reng Baja Ringan BMT 30.45 m1
III Baja Ringan Kencana Truss
376 M376 Kaso Baja Ringan Kencana Truss 100 mm 6 Meter
377 M377 Kaso Baja Ringan Kencana Truss 100 mm m1
378 M378 Kaso Baja Ringan Kencana Truss 60 mm 6 Meter
379 M379 Kaso Baja Ringan Kencana Truss 60 mm m1
380 M380 Kaso Baja Ringan Kencana Truss 65 mm 6 Meter
381 M381 Kaso Baja Ringan Kencana Truss 65 mm m1
382 M382 Kaso Baja Ringan Kencana Truss 70 mm 6 Meter
383 M383 Kaso Baja Ringan Kencana Truss 70 mm m1
384 M384 Kaso Baja Ringan Kencana Truss 75 mm 6 Meter
385 M385 Kaso Baja Ringan Kencana Truss 75 mm m1
386 M386 Reng Baja Ringan Kencana 45 mm 6 Meter
387 M387 Reng Baja Ringan Kencana 45 mm m1
IV Baja Ringan Prima Truss
388 M388 Kaso Baja Ringan Prima Truss 0.65 mm 6 Meter
389 M389 Kaso Baja Ringan Prima Truss 0.65 mm m1
390 M390 Kaso Baja Ringan Prima Truss 0.70 mm 6 Meter
391 M391 Kaso Baja Ringan Prima Truss 0.70 mm m1
392 M392 Kaso Baja Ringan Prima Truss 0.75 mm 6 Meter
393 M393 Kaso Baja Ringan Prima Truss 0.75 mm m1
394 M394 Kaso Baja Ringan Prima Truss 1.00 mm 6 Meter
395 M395 Kaso Baja Ringan Prima Truss 1.00 mm m1
396 M396 Reng Baja Ringan Prima Truss 0.40 mm 6 Meter
397 M397 Reng Baja Ringan Prima Truss 0.40 mm m1
398 M398 Reng Baja Ringan Prima Truss 0.45 mm 6 Meter
399 M399 Reng Baja Ringan Prima Truss 0.45 mm m1
V Harga Baja Ringan TASO
400 M400 Kaso Baja Ringan Taso 0.65 mm 6 Meter
401 M401 Kaso Baja Ringan Taso 0.65 mm m1
402 M402 Kaso Baja Ringan Taso 0.70 mm 6 Meter
403 M403 Kaso Baja Ringan Taso 0.70 mm m1
404 M404 Kaso Baja Ringan Taso 0.75 mm 6 Meter
405 M405 Kaso Baja Ringan Taso 0.75 mm m1
406 M406 Kaso Baja Ringan Taso 1.00 mm 6 Meter
407 M407 Kaso Baja Ringan Taso 1.00 mm m1
408 M408 Reng Baja Ringan Taso Tebal 0.40 mm 6 Meter
409 M409 Reng Baja Ringan Taso Tebal 0.40 mm m1
410 M410 Reng Baja Ringan Taso Tebal 0.45 mm 6 Meter
411 M411 Reng Baja Ringan Taso Tebal 0.45 mm m1
VI Hollow Rangka Plafond
412 M412 Hollow Aplus 2/4 Tali Hitam, t=0,3 4 meter
413 M413 Hollow Aplus 2/4 Tali Hitam, t=0,3 m1
414 M414 Hollow Aplus 2/4 Tali Kuning Hitam, t=0,45 4 meter
415 M415 Hollow Aplus 2/4 Tali Kuning Hitam, t=0,45 m1
416 M416 Hollow Aplus 2/4 Tali Kuning, t=0,5 4 meter
417 M417 Hollow Aplus 2/4 Tali Kuning, t=0,5 m1
418 M418 Hollow Aplus 2/4 Tali Merah, t=0,35 4 meter
419 M419 Hollow Aplus 2/4 Tali Merah, t=0,35 m1
420 M420 Hollow Aplus 2/4 Tali Putih, t=0,25 4 meter
421 M421 Hollow Aplus 2/4 Tali Putih, t=0,25 m1
422 M422 Hollow Aplus 4/4 Tali Hitam, t=0,3 4 meter
423 M423 Hollow Aplus 4/4 Tali Hitam, t=0,3 m1
424 M424 Hollow Aplus 4/4 Tali Kuning Hitam, t=0,45 4 meter
425 M425 Hollow Aplus 4/4 Tali Kuning Hitam, t=0,45 m1
426 M426 Hollow Aplus 4/4 Tali Kuning, t=0,5 4 meter
427 M427 Hollow Aplus 4/4 Tali Kuning, t=0,5 m1
428 M428 Hollow Aplus 4/4 Tali Merah Hijau, t=0,4 4 meter
429 M429 Hollow Aplus 4/4 Tali Merah Hijau, t=0,4 m1
430 M430 Hollow Aplus 4/4 Tali Merah, t=0,35 4 meter
431 M431 Hollow Aplus 4/4 Tali Merah, t=0,35 m1
432 M432 Hollow Aplus 4/4 Tali Putih, t=0,25 4 meter
433 M433 Hollow Aplus 4/4 Tali Putih, t=0,25 m1
434 M434 Hollow Aplus2/4 Tali Merah Hijau, t=-,4 4 meter
435 M435 Hollow Aplus2/4 Tali Merah Hijau, t=-,4 m1
436 M436 Hollow CBM Galvalume Profil 2/4 t 0.35 4 meter
437 M437 Hollow CBM Galvalume Profil 2/4 t 0.35 m1
438 M438 Hollow CBM Glavalume Profil 4/4 t 0.35 4 meter
439 M439 Hollow CBM Glavalume Profil 4/4 t 0.35 m1
440 M440 Hollow HFG Galvalume Profil 2/4 t 0.30 (1,6x3,2) 4 meter
441 M441 Hollow HFG Galvalume Profil 2/4 t 0.30 (1,6x3,2) m1
442 M442 Hollow HFG Galvalume Profil 4/4 t 0.30 (3,2x3,2) 4 meter
443 M443 Hollow HFG Galvalume Profil 4/4 t 0.30 (3,2x3,2) m1

E MATERIAL BATA & BATA RINGAN


I Bata Merah
444 M444 Bata Merah (Biasa) 200x100x50mm buah
68

NO KODE NAMA BARANG SATUAN MERK

A B C D E
445 M445 Bata Merah (Oven) 200x100x50mm buah
II Bata Ringan
446 M446 Bata Ringan Grand Elephant 600x200x100mm m3
447 M447 Bata Ringan Grand Elephant 600x200x100mm buah
448 M448 Bata Ringan Grand Elephant 600x200x75mm m3
449 M449 Bata Ringan Grand Elephant 600x200x75mm buah
450 M450 Bata Ringan Leichtbric (Broco) 600x200x100mm m3
451 M451 Bata Ringan Leichtbric (Broco) 600x200x100mm buah
452 M452 Bata Ringan Leichtbric (Broco) 600x200x75mm m3
453 M453 Bata Ringan Leichtbric (Broco) 600x200x75mm buah
454 M454 Bata Ringan NSR 600x200x100mm m3
455 M455 Bata Ringan NSR 600x200x100mm buah
456 M456 Bata Ringan NSR 600x200x75mm m3
457 M457 Bata Ringan NSR 600x200x75mm buah
458 M458 Bata Ringan Powerblock 600x200x100mm m3
459 M459 Bata Ringan Powerblock 600x200x100mm buah
460 M460 Bata Ringan Powerblock 600x200x75mm m3
461 M461 Bata Ringan Powerblock 600x200x75mm buah
III Batako
462 M462 Batako 400x200x80mm buah
IV Hollow Block
463 M463 Hollow Block HB 10 buah
464 M464 Hollow Block HB 15 buah
465 M465 Hollow Block HB 20 buah

F MATERIAL BESI/BAJA
I Besi Beton
466 M466 Besi Beton 8 MSS BJKU 6,2 mm batang
467 M467 Besi Beton 8 MSS BJKU 6,2 mm kg
468 M468 Besi Beton 10 IBD SNI 9,8 mm batang
469 M469 Besi Beton 10 IBD SNI 9,8 mm kg
470 M470 Besi Beton 10 MSS BJKU 8 mm batang
471 M471 Besi Beton 10 MSS BJKU 8 mm kg
472 M472 Besi Beton 10 SPI BJKU 8,7 mm batang
473 M473 Besi Beton 10 SPI BJKU 8,7 mm kg
474 M474 Besi Beton 10 SRB SNI 9,1 mm batang
475 M475 Besi Beton 10 SRB SNI 9,1 mm kg
476 M476 Besi Beton 10 TJ SNI 9,5 mm batang
477 M477 Besi Beton 10 TJ SNI 9,5 mm kg
478 M478 Besi Beton 12 IBD SNI 11,8 mm batang
479 M479 Besi Beton 12 IBD SNI 11,8 mm kg
480 M480 Besi Beton 12 MSS BJKU 9,5 mm batang
481 M481 Besi Beton 12 MSS BJKU 9,5 mm kg
482 M482 Besi Beton 12 SPI BJKU 10,5 mm batang
483 M483 Besi Beton 12 SPI BJKU 10,5 mm kg
484 M484 Besi Beton 12 SRB SNI 11,2 mm batang
485 M485 Besi Beton 12 SRB SNI 11,2 mm kg
486 M486 Besi Beton 12 TJ SNI 11,5 mm batang
487 M487 Besi Beton 12 TJ SNI 11,5 mm kg
488 M488 Besi Beton 16 TJ SNI (Polos) 15,5 mm batang
489 M489 Besi Beton 16 TJ SNI (Polos) 15,5 mm kg
490 M490 Besi Beton 8 IBD SNI 7,8 mm batang
491 M491 Besi Beton 8 IBD SNI 7,8 mm kg
492 M492 Besi Beton 8 SPI BJKU 7 mm batang
493 M493 Besi Beton 8 SPI BJKU 7 mm kg
494 M494 Besi Beton 8 SRB SNI 7,1 mm batang
495 M495 Besi Beton 8 SRB SNI 7,1 mm kg
496 M496 Besi Beton 8 TJ SNI 7,5 mm batang
497 M497 Besi Beton 8 TJ SNI 7,5 mm kg
498 M498 Besi Beton D 10 TJ SNI 9,5 mm batang
499 M499 Besi Beton D 10 TJ SNI 9,5 mm kg
500 M500 Besi Beton D 13 IBD SNI (Ulir) 12,8 mm batang
501 M501 Besi Beton D 13 IBD SNI (Ulir) 12,8 mm kg
502 M502 Besi Beton D 13 SRB SNI 12,2 mm batang
503 M503 Besi Beton D 13 SRB SNI 12,2 mm kg
504 M504 Besi Beton D 13 TJ SNI 12,5 mm batang
505 M505 Besi Beton D 13 TJ SNI 12,5 mm kg
506 M506 Besi Beton D 16 IBD SNI (Ulir) 15,8 mm batang
507 M507 Besi Beton D 16 IBD SNI (Ulir) 15,8 mm kg
508 M508 Besi Beton D 16 SRB SNI 15,2 mm batang
509 M509 Besi Beton D 16 SRB SNI 15,2 mm kg
510 M510 Besi Beton D 16 TJ SNI 15,5 mm batang
511 M511 Besi Beton D 16 TJ SNI 15,5 mm kg
512 M512 Besi Beton D 19 IBD SNI (Ulir) 18,8 mm batang
513 M513 Besi Beton D 19 IBD SNI (Ulir) 18,8 mm kg
514 M514 Besi Beton D 19 TJ SNI 18,5 mm batang
515 M515 Besi Beton D 19 TJ SNI 18,5 mm kg
516 M516 Besi Beton TARIK 4 mm 3,8 mm batang
517 M517 Besi Beton TARIK 4 mm 3,8 mm kg
518 M518 Besi Beton TARIK 4 mm 4 mm batang
519 M519 Besi Beton TARIK 4 mm 4 mm kg
520 M520 Besi Beton TARIK 5 mm 4,2 mm batang
521 M521 Besi Beton TARIK 5 mm 4,2 mm kg
69

NO KODE NAMA BARANG SATUAN MERK

A B C D E
522 M522 Besi Beton TARIK 6 mm 5,2 mm batang
523 M523 Besi Beton TARIK 6 mm 5,2 mm kg
524 M524 Besi Beton TARIK 6 mm 5,6 mm batang
525 M525 Besi Beton TARIK 6 mm 5,6 mm kg
526 M526 Besi Beton TARIK 6 mm 5,8 mm batang
527 M527 Besi Beton TARIK 6 mm 5,8 mm kg
528 M528 Besi Beton Polos kg
529 M529 Besi Beton Ulir kg
II Besi Hollow
530 M530 Hollow Steel 20 x 20 x 1,5 mm m1
531 M531 Hollow Steel 20 x 20 x 1,5 mm 6 meter batang
532 M532 Hollow Steel 30 x 15 x 1,5 mm m1
533 M533 Hollow Steel 30 x 15 x 1,5 mm 6 meter batang
534 M534 Hollow Steel 30 x 30 x 1,5 mm m1
535 M535 Hollow Steel 30 x 30 x 1,5 mm 6 meter batang
536 M536 Hollow Steel 30 x 30 x 1,7 mm m1
537 M537 Hollow Steel 30 x 30 x 1,7 mm 6 meter batang
538 M538 Hollow Steel 40 x 20 x 1,5 mm m1
539 M539 Hollow Steel 40 x 20 x 1,5 mm 6 meter batang
540 M540 Hollow Steel 40 x 20 x 1,7 mm m1
541 M541 Hollow Steel 40 x 20 x 1,7 mm 6 meter batang
542 M542 Hollow Steel 40 x 40 x 1,7 mm m1
543 M543 Hollow Steel 40 x 40 x 1,7 mm 6 meter batang
544 M544 Hollow Steel 40 x 40 x 2,7 mm m1
545 M545 Hollow Steel 40 x 40 x 2,7 mm 6 meter batang
546 M546 Hollow Steel 50 x 100 x 1,8 mm m1
547 M547 Hollow Steel 50 x 100 x 1,8 mm 6 meter batang
548 M548 Hollow Steel 50 x 50 x 1,7 mm m1
549 M549 Hollow Steel 50 x 50 x 1,7 mm 6 meter batang
550 M550 Hollow Steel 50 x 50 x 2,7 mm m1
551 M551 Hollow Steel 50 x 50 x 2,7 mm 6 meter batang
552 M552 Hollow Steel 50 x 50 x 2,7 mm kg
553 M553 Hollow Steel 60 x 30 x 1,5 mm m1
554 M554 Hollow Steel 60 x 30 x 1,5 mm 6 meter batang
555 M555 Hollow Steel 60 x 30 x 1,7 mm m1
556 M556 Hollow Steel 60 x 30 x 1,7 mm 6 meter batang
557 M557 Hollow Steel 60 x 40 x 1,7 mm m1
558 M558 Hollow Steel 60 x 40 x 1,7 mm 6 meter batang
559 M559 Hollow Steel 75 x 75 x 2,7 mm m1
560 M560 Hollow Steel 75 x 75 x 2,7 mm 6 meter batang
III Besi Kanal C (CNP)
561 M561 Kanal C 100x50x20x2,3mm m1
562 M562 Kanal C 100x50x20x2,3mm 6 meter batang
563 M563 Kanal C 100x50x20x3,2mm m1
564 M564 Kanal C 100x50x20x3,2mm 6 meter batang
565 M565 Kanal C 125x50x20x2,3mm m1
566 M566 Kanal C 125x50x20x2,3mm 6 meter batang
567 M567 Kanal C 125x50x20x3,2mm m1
568 M568 Kanal C 125x50x20x3,2mm 6 meter batang
569 M569 Kanal C 150x50x20x2,3mm m1
570 M570 Kanal C 150x50x20x2,3mm 6 meter batang
571 M571 Kanal C 150x50x20x3,2mm m1
572 M572 Kanal C 150x50x20x3,2mm 6 meter batang
573 M573 Kanal C 150x65x20x2,3mm m1
574 M574 Kanal C 150x65x20x2,3mm 6 meter batang
575 M575 Kanal C 150x65x20x3,2mm m1
576 M576 Kanal C 150x65x20x3,2mm 6 meter batang
577 M577 Kanal C 200x75x20x2,3mm m1
578 M578 Kanal C 200x75x20x2,3mm 6 meter batang
579 M579 Kanal C 200x75x20x3,2mm m1
580 M580 Kanal C 200x75x20x3,2mm 6 meter batang
581 M581 Kanal C 60x30x10x1,6mm m1
582 M582 Kanal C 60x30x10x1,6mm 6 meter batang
583 M583 Kanal C 75x45x15x2,3mm m1
584 M584 Kanal C 75x45x15x2,3mm 6 meter batang
IV Besi Kanal U (UNP)
585 M585 Besi UNP Kanal U 100 uk. 100x50x5 mm batang (6 meter)
586 M586 Besi UNP Kanal U 100 uk. 100x50x5 mm m1
587 M587 Besi UNP Kanal U 120 uk. 120x55x6 mm batang (6 meter)
588 M588 Besi UNP Kanal U 120 uk. 120x55x6 mm m1
589 M589 Besi UNP Kanal U 150 uk. 150x75x6,5 mm batang (6 meter)
590 M590 Besi UNP Kanal U 150 uk. 150x75x6,5 mm m1
591 M591 Besi UNP Kanal U 200 uk. 200x80x7,5 mm batang (6 meter)
592 M592 Besi UNP Kanal U 200 uk. 200x80x7,5 mm m1
593 M593 Besi UNP Kanal U 50 uk. 50x38x5 mm batang (6 meter)
594 M594 Besi UNP Kanal U 50 uk. 50x38x5 mm m1
595 M595 Besi UNP Kanal U 65 uk. 65x42x5 mm batang (6 meter)
596 M596 Besi UNP Kanal U 65 uk. 65x42x5 mm m1
597 M597 Besi UNP Kanal U 80 uk. 80x45x6 mm batang (6 meter)
598 M598 Besi UNP Kanal U 80 uk. 80x45x6 mm m1
V Besi Pipa Hitam Medium
599 M599 Pipa Besi Medium 1 Inch tebal 3,0 mm m1
600 M600 Pipa Besi Medium 1 Inch tebal 3,0 mm panjang 6 meter batang
70

NO KODE NAMA BARANG SATUAN MERK

A B C D E
601 M601 Pipa Besi Medium 1/2 Inch tebal 2,45 mm m1
602 M602 Pipa Besi Medium 1/2 Inch tebal 2,45 mm panjang 6 meter batang
603 M603 Pipa Besi Medium 1¼ Inch tebal 3,10 mm m1
604 M604 Pipa Besi Medium 1¼ Inch tebal 3,10 mm panjang 6 meter batang
605 M605 Pipa Besi Medium 1½ Inch tebal 3,10 mm m1
606 M606 Pipa Besi Medium 1½ Inch tebal 3,10 mm panjang 6 meter batang
607 M607 Pipa Besi Medium 2 Inch tebal 3,40 mm m1
608 M608 Pipa Besi Medium 2 Inch tebal 3,40 mm panjang 6 meter batang
609 M609 Pipa Besi Medium 2½ Inch tebal 3,40 mm m1
610 M610 Pipa Besi Medium 2½ Inch tebal 3,40 mm panjang 6 meter batang
611 M611 Pipa Besi Medium 3 Inch tebal 3,75 mm m1
612 M612 Pipa Besi Medium 3 Inch tebal 3,75 mm panjang 6 meter batang
613 M613 Pipa Besi Medium 3/4 Inch tebal 2,45 mm m1
614 M614 Pipa Besi Medium 3/4 Inch tebal 2,45 mm panjang 6 meter batang
615 M615 Pipa Besi Medium 4 Inch tebal 4,20 mm m1
616 M616 Pipa Besi Medium 4 Inch tebal 4,20 mm panjang 6 meter batang
617 M617 Pipa Besi Medium 5 Inch tebal 4,60 mm m1
618 M618 Pipa Besi Medium 5 Inch tebal 4,60 mm panjang 6 meter batang
619 M619 Pipa Besi Medium 6 Inch tebal 4,60 mm m1
620 M620 Pipa Besi Medium 6 Inch tebal 4,60 mm panjang 6 meter batang
621 M621 Pipa Besi Medium 8 Inch tebal 6,10 mm m1
622 M622 Pipa Besi Medium 8 Inch tebal 6,10 mm panjang 6 meter batang
VI Besi Pipa Hitam SCH40
623 M623 Pipa Besi Hitam 1 Inch tebal 3,20 mm m1
624 M624 Pipa Besi Hitam 1 Inch tebal 3,20 mm panjang 6 meter batang
625 M625 Pipa Besi Hitam 1/2 Inch tebal 2,63 mm m1
626 M626 Pipa Besi Hitam 1/2 Inch tebal 2,63 mm panjang 6 meter batang
627 M627 Pipa Besi Hitam 1¼ Inch tebal 3,40 mm m1
628 M628 Pipa Besi Hitam 1¼ Inch tebal 3,40 mm panjang 6 meter batang
629 M629 Pipa Besi Hitam 1½ Inch tebal 3,50 mm m1
630 M630 Pipa Besi Hitam 1½ Inch tebal 3,50 mm panjang 6 meter batang
631 M631 Pipa Besi Hitam 2 Inch tebal 3,70 mm m1
632 M632 Pipa Besi Hitam 2 Inch tebal 3,70 mm panjang 6 meter batang
633 M633 Pipa Besi Hitam 2½ Inch tebal 4,90 mm m1
634 M634 Pipa Besi Hitam 2½ Inch tebal 4,90 mm panjang 6 meter batang
635 M635 Pipa Besi Hitam 3 Inch tebal 5,20 mm m1
636 M636 Pipa Besi Hitam 3 Inch tebal 5,20 mm panjang 6 meter batang
637 M637 Pipa Besi Hitam 3/4 Inch tebal 2,72 mm m1
638 M638 Pipa Besi Hitam 3/4 Inch tebal 2,72 mm panjang 6 meter batang
639 M639 Pipa Besi Hitam 4 Inch tebal 5,70 mm m1
640 M640 Pipa Besi Hitam 4 Inch tebal 5,70 mm panjang 6 meter batang
641 M641 Pipa Besi Hitam 5 Inch tebal 6,20 mm m1
642 M642 Pipa Besi Hitam 5 Inch tebal 6,20 mm panjang 6 meter batang
643 M643 Pipa Besi Hitam 6 Inch tebal 6,70 mm m1
644 M644 Pipa Besi Hitam 6 Inch tebal 6,70 mm panjang 6 meter batang
645 M645 Pipa Besi Hitam 8 Inch tebal 7,80 mm m1
646 M646 Pipa Besi Hitam 8 Inch tebal 7,80 mm panjang 6 meter batang
VII Besi Siku
647 M647 Besi siku 30 x 30 x 1.4mm x 6m (22 x 22 x 1.4mm x 6m) batang
648 M648 Besi siku 30 x 30 x 1.4mm x 6m (22 x 22 x 1.4mm) m1
649 M649 Besi siku 30 x 30 x 2.0mm x 6m (28 x 28 x 2.0mm x 6m) batang
650 M650 Besi siku 30 x 30 x 2.0mm x 6m (28 x 28 x 2.0mm) m1
651 M651 Besi siku 30 x 30 x 2.2mm x 6m (28 x 28 x 2.2mm x 6m) batang
652 M652 Besi siku 30 x 30 x 2.2mm x 6m (28 x 28 x 2.2mm) m1
653 M653 Besi siku 30 x 30 x 2.4mm x 6m (28 x 28 x 2.4mm x 6m) batang
654 M654 Besi siku 30 x 30 x 2.4mm x 6m (28 x 28 x 2.4mm) m1
655 M655 Besi siku 30 x 30 x 2.8mm x 6m (28 x 28 x 2.8mm x 6m) batang
656 M656 Besi siku 30 x 30 x 2.8mm x 6m (28 x 28 x 2.8mm) m1
657 M657 Besi siku 30 x 30 x 2.8mm x 6m (28 x 28 x 2.8mm) kg
658 M658 Besi siku 40 x 40 x 2.2mm x 6m (34 x 34 x 2.2mm x 6m) batang
659 M659 Besi siku 40 x 40 x 2.2mm x 6m (34 x 34 x 2.2mm) m1
660 M660 Besi siku 40 x 40 x 2.4mm x 6m (34 x 34 x 2.4mm x 6m) batang
661 M661 Besi siku 40 x 40 x 2.4mm x 6m (34 x 34 x 2.4mm) m1
662 M662 Besi siku 40 x 40 x 2.8mm x 6m (38 x 38 x 2.8mm x 6m) batang
663 M663 Besi siku 40 x 40 x 2.8mm x 6m (38 x 38 x 2.8mm) m1
664 M664 Besi siku 40 x 40 x 3.0mm x 6m (38 x 38 x 3.0mm x 6m) batang
665 M665 Besi siku 40 x 40 x 3.0mm x 6m (38 x 38 x 3.0mm) m1
666 M666 Besi siku 40 x 40 x 3.2mm x 6m (38 x 38 x 3.2mm x 6m) batang
667 M667 Besi siku 40 x 40 x 3.2mm x 6m (38 x 38 x 3.2mm) m1
668 M668 Besi siku 40 x 40 x 3.4mm x 6m (44 x 44 x 3.4mm x 6m) batang
669 M669 Besi siku 40 x 40 x 3.4mm x 6m (44 x 44 x 3.4mm) m1
670 M670 Besi siku 40 x 40 x 3.8mm x 6m (48 x 48 x 3.8mm x 6m) batang
671 M671 Besi siku 40 x 40 x 3.8mm x 6m (48 x 48 x 3.8mm) m1
672 M672 Besi siku 50 x 50 x 2.5mm x 6m (44 x 44 x 2.5mm x 6m) batang
673 M673 Besi siku 50 x 50 x 2.5mm x 6m (44 x 44 x 2.5mm) m1
674 M674 Besi siku 50 x 50 x 3.4mm x 6m (44 x 44 x 3.4mm x 6m) batang
675 M675 Besi siku 50 x 50 x 3.4mm x 6m (44 x 44 x 3.4mm) m1
676 M676 Besi siku 50 x 50 x 3.8mm x 6m (48 x 48 x 3.8mm x 6m) batang
677 M677 Besi siku 50 x 50 x 3.8mm x 6m (48 x 48 x 3.8mm) m1
678 M678 Besi siku 50 x 50 x 4.0mm x 6m (48 x 48 x 4.0mm x 6m) batang
679 M679 Besi siku 50 x 50 x 4.0mm x 6m (48 x 48 x 4.0mm) m1
680 M680 Besi siku 50 x 50 x 4.2mm x 6m (48 x 48 x 4.2mm x 6m) batang
681 M681 Besi siku 50 x 50 x 4.2mm x 6m (48 x 48 x 4.2mm) m1
71

NO KODE NAMA BARANG SATUAN MERK

A B C D E
682 M682 Besi siku 50 x 50 x 4.4mm x 6m (48 x 48 x 4.4mm x 6m) batang
683 M683 Besi siku 50 x 50 x 4.4mm x 6m (48 x 48 x 4.4mm) m1
684 M684 Besi siku 50 x 50 x 4.6mm x 6m (48 x 48 x 4.6mm x 6m) batang
685 M685 Besi siku 50 x 50 x 4.6mm x 6m (48 x 48 x 4.6mm) m1
686 M686 Besi siku 50 x 50 x 4.8mm x 6m (48 x 48 x 4.8mm x 6m) batang
687 M687 Besi siku 50 x 50 x 4.8mm x 6m (48 x 48 x 4.8mm) m1
688 M688 Besi siku 60 x 60 x 5.8mm x 6m (58 x 58 x 5.8mm x 6m) batang
689 M689 Besi siku 60 x 60 x 5.8mm x 6m (58 x 58 x 5.8mm) m1
690 M690 Besi siku 70 x 70 x 6.8mm x 6m (68 x 68 x 6.8mm x 6m) batang
691 M691 Besi siku 70 x 70 x 6.8mm x 6m (68 x 68 x 6.8mm) m1
VIII Besi/Baja H Beam
692 M692 L 150x150x7x10 mm m1
693 M693 L 150x150x7x10 mm panjang 12 meter batang
694 M694 L 200x200x8x12 mm m1
695 M695 L 200x200x8x12 mm panjang 12 meter batang
696 M696 L 250x250x9x14 mm m1
697 M697 L 250x250x9x14 mm panjang 12 meter batang
698 M698 L 250x350x12x19 mm m1
699 M699 L 250x350x12x19 mm panjang 12 meter batang
700 M700 L 300x300x10x15 mm m1
701 M701 L 300x300x10x15 mm panjang 12 meter batang
702 M702 L 400x400x13x21 mm m1
703 M703 L 400x400x13x21 mm panjang 12 meter batang
IX Besi/Baja WF
704 M704 WF 150x75x5x7 mm m1
705 M705 WF 150x75x5x7 mm kg
706 M706 WF 150x75x5x7 mm panjang 12 meter batang
707 M707 WF 200x100x5,5x8 mm m1
708 M708 WF 200x100x5,5x8 mm kg
709 M709 WF 200x100x5,5x8 mm panjang 12 meter batang
710 M710 WF 250x125x6x9 mm m1
711 M711 WF 250x125x6x9 mm kg
712 M712 WF 250x125x6x9 mm panjang 12 meter batang
713 M713 WF 300x150x6,5x9 mm m1
714 M714 WF 300x150x6,5x9 mm kg
715 M715 WF 300x150x6,5x9 mm panjang 12 meter batang
716 M716 WF 350x175x7x11 mm m1
717 M717 WF 350x175x7x11 mm kg
718 M718 WF 350x175x7x11 mm panjang 12 meter batang
719 M719 WF 400x200x8x13 mm m1
720 M720 WF 400x200x8x13 mm kg
721 M721 WF 400x200x8x13 mm panjang 12 meter batang
722 M722 WF 450x200x9x14 mm m1
723 M723 WF 450x200x9x14 mm kg
724 M724 WF 450x200x9x14 mm panjang 12 meter batang
725 M725 WF 500x200x10x16 mm m1
726 M726 WF 500x200x10x16 mm kg
727 M727 WF 500x200x10x16 mm panjang 12 meter batang
728 M728 WF 600x200x11x17 mm m1
729 M729 WF 600x200x11x17 mm kg
730 M730 WF 600x200x11x17 mm panjang 12 meter batang
X Kawat
731 M731 Kawat Bendrat 20 kg 20 kg
732 M732 Kawat Bendrat BWG 10 kg
733 M733 Kawat Bendrat BWG 12 kg
734 M734 Kawat Bendrat BWG 14 kg
735 M735 Kawat Bendrat BWG 16 kg
736 M736 Kawat Bendrat BWG 6 kg
737 M737 Kawat Bendrat BWG 8 kg
738 M738 Kawat Bendrat Per Kilo kg
739 M739 Kawat Bendrat Per Rol rol
740 M740 Kawat Duri m1
741 M741 Kawat Jaring lembar
742 M742 Kawat Las kg
XI Pipa Besi Galvanis Medium
743 M743 Pipa Galvanis Medium 1 Inch tebal 3,0 mm m1
744 M744 Pipa Galvanis Medium 1 Inch tebal 3,0 mm panjang 6 meter batang
745 M745 Pipa Galvanis Medium 1/2 Inch tebal 2,45 mm m1
746 M746 Pipa Galvanis Medium 1/2 Inch tebal 2,45 mm panjang 6 meter batang
747 M747 Pipa Galvanis Medium 1¼ Inch tebal 3,10 mm m1
748 M748 Pipa Galvanis Medium 1¼ Inch tebal 3,10 mm panjang 6 meter batang
749 M749 Pipa Galvanis Medium 1½ Inch tebal 3,10 mm m1
750 M750 Pipa Galvanis Medium 1½ Inch tebal 3,10 mm panjang 6 meter batang
751 M751 Pipa Galvanis Medium 2 Inch tebal 3,40 mm m1
752 M752 Pipa Galvanis Medium 2 Inch tebal 3,40 mm panjang 6 meter batang
753 M753 Pipa Galvanis Medium 2½ Inch tebal 3,40 mm m1
754 M754 Pipa Galvanis Medium 2½ Inch tebal 3,40 mm panjang 6 meter batang
755 M755 Pipa Galvanis Medium 3 Inch tebal 3,75 mm m1
756 M756 Pipa Galvanis Medium 3 Inch tebal 3,75 mm panjang 6 meter batang
757 M757 Pipa Galvanis Medium 3/4 Inch tebal 2,45 mm m1
758 M758 Pipa Galvanis Medium 3/4 Inch tebal 2,45 mm panjang 6 meter batang
759 M759 Pipa Galvanis Medium 4 Inch tebal 4,20 mm m1
760 M760 Pipa Galvanis Medium 4 Inch tebal 4,20 mm panjang 6 meter batang
72

NO KODE NAMA BARANG SATUAN MERK

A B C D E
761 M761 Pipa Galvanis Medium 5 Inch tebal 4,60 mm m1
762 M762 Pipa Galvanis Medium 5 Inch tebal 4,60 mm panjang 6 meter batang
763 M763 Pipa Galvanis Medium 6 Inch tebal 4,60 mm m1
764 M764 Pipa Galvanis Medium 6 Inch tebal 4,60 mm panjang 6 meter batang
765 M765 Pipa Galvanis Medium 8 Inch tebal 6,10 mm m1
766 M766 Pipa Galvanis Medium 8 Inch tebal 6,10 mm panjang 6 meter batang
XII Pipa Besi Galvanis SCH40
767 M767 Pipa Galvanis 1 Inch tebal 3,20 mm m1
768 M768 Pipa Galvanis 1 Inch tebal 3,20 mm panjang 6 meter batang
769 M769 Pipa Galvanis 1/2 Inch tebal 2,63 mm m1
770 M770 Pipa Galvanis 1/2 Inch tebal 2,63 mm panjang 6 meter batang
771 M771 Pipa Galvanis 1¼ Inch tebal 3,40 mm m1
772 M772 Pipa Galvanis 1¼ Inch tebal 3,40 mm panjang 6 meter batang
773 M773 Pipa Galvanis 1½ Inch tebal 3,50 mm m1
774 M774 Pipa Galvanis 1½ Inch tebal 3,50 mm panjang 6 meter batang
775 M775 Pipa Galvanis 2 Inch tebal 3,70 mm m1
776 M776 Pipa Galvanis 2 Inch tebal 3,70 mm panjang 6 meter batang
777 M777 Pipa Galvanis 2½ Inch tebal 4,90 mm m1
778 M778 Pipa Galvanis 2½ Inch tebal 4,90 mm panjang 6 meter batang
779 M779 Pipa Galvanis 3 Inch tebal 5,20 mm m1
780 M780 Pipa Galvanis 3 Inch tebal 5,20 mm panjang 6 meter batang
781 M781 Pipa Galvanis 3/4 Inch tebal 2,72 mm m1
782 M782 Pipa Galvanis 3/4 Inch tebal 2,72 mm panjang 6 meter batang
783 M783 Pipa Galvanis 4 Inch tebal 5,70 mm m1
784 M784 Pipa Galvanis 4 Inch tebal 5,70 mm panjang 6 meter batang
785 M785 Pipa Galvanis 5 Inch tebal 6,20 mm m1
786 M786 Pipa Galvanis 5 Inch tebal 6,20 mm panjang 6 meter batang
787 M787 Pipa Galvanis 6 Inch tebal 6,70 mm m1
788 M788 Pipa Galvanis 6 Inch tebal 6,70 mm panjang 6 meter batang
789 M789 Pipa Galvanis 8 Inch tebal 7,80 mm m1
790 M790 Pipa Galvanis 8 Inch tebal 7,80 mm panjang 6 meter batang
XIII Plat Besi Bordes
791 M791 Plat Besi Bordes 2 mm uk. 1220x2440mm lembar
792 M792 Plat Besi Bordes 2 mm uk. 1220x2440mm m2
793 M793 Plat Besi Bordes 2.1 mm uk. 1220x2440mm lembar
794 M794 Plat Besi Bordes 2.1 mm uk. 1220x2440mm m2
795 M795 Plat Besi Bordes 2.3 mm uk. 1220x2440mm lembar
796 M796 Plat Besi Bordes 2.3 mm uk. 1220x2440mm m2
797 M797 Plat Besi Bordes 3 mm uk. 1220x2440mm lembar
798 M798 Plat Besi Bordes 3 mm uk. 1220x2440mm m2
XIV Plat Besi Galvanil
799 M799 Plat Besi Galvanil 0.7 mm uk. 1220x2440mm lembar
800 M800 Plat Besi Galvanil 0.7 mm uk. 1220x2440mm m2
801 M801 Plat Besi Galvanil 0.8 mm uk. 1220x2440mm lembar
802 M802 Plat Besi Galvanil 0.8 mm uk. 1220x2440mm m2
803 M803 Plat Besi Galvanil 0.9 mm uk. 1220x2440mm lembar
804 M804 Plat Besi Galvanil 0.9 mm uk. 1220x2440mm m2
805 M805 Plat Besi Galvanil 1 mm uk. 1220x2440mm lembar
806 M806 Plat Besi Galvanil 1 mm uk. 1220x2440mm m2
807 M807 Plat Besi Galvanil 1.2 mm uk. 1220x2440mm lembar
808 M808 Plat Besi Galvanil 1.2 mm uk. 1220x2440mm m2
XV Plat Besi Galvanis
809 M809 Plat Besi Galvanis 1 mm uk. 1220x2440mm lembar
810 M810 Plat Besi Galvanis 1 mm uk. 1220x2440mm m2
811 M811 Plat Besi Galvanis 1.2 mm uk. 1220x2440mm lembar
812 M812 Plat Besi Galvanis 1.2 mm uk. 1220x2440mm m2
813 M813 Plat Besi Galvanis 1.5 mm uk. 1220x2440mm lembar
814 M814 Plat Besi Galvanis 1.5 mm uk. 1220x2440mm m2
815 M815 Plat Besi Galvanis 2 mm uk. 1220x2440mm lembar
816 M816 Plat Besi Galvanis 2 mm uk. 1220x2440mm m2
XVI Plat Besi Hitam
817 M817 Plat Besi Hitam 1 mm uk. 1220x2440mm lembar
818 M818 Plat Besi Hitam 1 mm uk. 1220x2440mm m2
819 M819 Plat Besi Hitam 1 mm uk. 1220x2440mm kg
820 M820 Plat Hitam 1.2 mm uk. 1220x2440mm lembar
821 M821 Plat Hitam 1.2 mm uk. 1220x2440mm m2
822 M822 Plat Hitam 1.2 mm uk. 1220x2440mm kg
823 M823 Plat Hitam 10 mm uk. 1220x2440mm lembar
824 M824 Plat Hitam 10 mm uk. 1220x2440mm m2
825 M825 Plat Hitam 10 mm uk. 1220x2440mm kg
826 M826 Plat Hitam 12 mm uk. 1220x2440mm lembar
827 M827 Plat Hitam 12 mm uk. 1220x2440mm m2
828 M828 Plat Hitam 12 mm uk. 1220x2440mm kg
829 M829 Plat Hitam 2 mm uk. 1220x2440mm lembar
830 M830 Plat Hitam 2 mm uk. 1220x2440mm m2
831 M831 Plat Hitam 2 mm uk. 1220x2440mm kg
832 M832 Plat Hitam 2.3 mm uk. 1220x2440mm lembar
833 M833 Plat Hitam 2.3 mm uk. 1220x2440mm m2
834 M834 Plat Hitam 2.3 mm uk. 1220x2440mm kg
835 M835 Plat Hitam 2.5 mm uk. 1220x2440mm lembar
836 M836 Plat Hitam 2.5 mm uk. 1220x2440mm m2
837 M837 Plat Hitam 2.5 mm uk. 1220x2440mm kg
838 M838 Plat Hitam 3 mm uk. 1220x2440mm lembar
73

NO KODE NAMA BARANG SATUAN MERK

A B C D E
839 M839 Plat Hitam 3 mm uk. 1220x2440mm m2
840 M840 Plat Hitam 3 mm uk. 1220x2440mm kg
841 M841 Plat Hitam 4 mm uk. 1220x2440mm lembar
842 M842 Plat Hitam 4 mm uk. 1220x2440mm m2
843 M843 Plat Hitam 4 mm uk. 1220x2440mm kg
844 M844 Plat Hitam 5 mm uk. 1220x2440mm lembar
845 M845 Plat Hitam 5 mm uk. 1220x2440mm m2
846 M846 Plat Hitam 5 mm uk. 1220x2440mm kg
847 M847 Plat Hitam 6 mm uk. 1220x2440mm lembar
848 M848 Plat Hitam 6 mm uk. 1220x2440mm m2
849 M849 Plat Hitam 6 mm uk. 1220x2440mm kg
850 M850 Plat Hitam 8 mm uk. 1220x2440mm lembar
851 M851 Plat Hitam 8 mm uk. 1220x2440mm m2
852 M852 Plat Hitam 8 mm uk. 1220x2440mm kg
XVII Wiremesh (Non SNI)
853 M853 Wiremesh M12 (11.5mm) ukuran 2,1 m x 5,4 m lembar
854 M854 Wiremesh M12 (11.5mm) ukuran 2,1 m x 5,4 m m2
855 M855 Wiremesh M12 (11.5mm) ukuran 2,1 m x 5,4 m kg
856 M856 Wiremesh M5 (4.5mm) ukuran 2,1 m x 5,4 m lembar
857 M857 Wiremesh M5 (4.5mm) ukuran 2,1 m x 5,4 m m2
858 M858 Wiremesh M5 (4.5mm) ukuran 2,1 m x 5,4 m kg
859 M859 Wiremesh M6 (5.2mm) ukuran 2,1 m x 5,4 m lembar
860 M860 Wiremesh M6 (5.2mm) ukuran 2,1 m x 5,4 m m2
861 M861 Wiremesh M6 (5.2mm) ukuran 2,1 m x 5,4 m kg
862 M862 Wiremesh M6 (5.5mm) ukuran 2,1 m x 5,4 m lembar
863 M863 Wiremesh M6 (5.5mm) ukuran 2,1 m x 5,4 m m2
864 M864 Wiremesh M6 (5.5mm) ukuran 2,1 m x 5,4 m kg
865 M865 Wiremesh M6 (5.6mm) ukuran 2,1 m x 5,4 m lembar
866 M866 Wiremesh M6 (5.6mm) ukuran 2,1 m x 5,4 m m2
867 M867 Wiremesh M6 (5.6mm) ukuran 2,1 m x 5,4 m kg
868 M868 Wiremesh M7 (6.5mm) ukuran 2,1 m x 5,4 m lembar
869 M869 Wiremesh M7 (6.5mm) ukuran 2,1 m x 5,4 m m2
870 M870 Wiremesh M7 (6.5mm) ukuran 2,1 m x 5,4 m kg
871 M871 Wiremesh M8 (7.2mm) ukuran 2,1 m x 5,4 m lembar
872 M872 Wiremesh M8 (7.2mm) ukuran 2,1 m x 5,4 m m2
873 M873 Wiremesh M8 (7.2mm) ukuran 2,1 m x 5,4 m kg
874 M874 Wiremesh M8 (7.5mm) ukuran 2,1 m x 5,4 m lembar
875 M875 Wiremesh M8 (7.5mm) ukuran 2,1 m x 5,4 m m2
876 M876 Wiremesh M8 (7.5mm) ukuran 2,1 m x 5,4 m kg
877 M877 Wiremesh M8 (7.6mm) ukuran 2,1 m x 5,4 m lembar
878 M878 Wiremesh M8 (7.6mm) ukuran 2,1 m x 5,4 m m2
879 M879 Wiremesh M8 (7.6mm) ukuran 2,1 m x 5,4 m kg
XVIII Wiremesh (SNI)
880 M880 Wiremesh M10 ukuran 2,1 m x 5,4 m lembar
881 M881 Wiremesh M10 ukuran 2,1 m x 5,4 m m2
882 M882 Wiremesh M10 ukuran 2,1 m x 5,4 m kg
883 M883 Wiremesh M12 ukuran 2,1 m x 5,4 m lembar
884 M884 Wiremesh M12 ukuran 2,1 m x 5,4 m m2
885 M885 Wiremesh M12 ukuran 2,1 m x 5,4 m kg
886 M886 Wiremesh M4 ukuran 2,1 m x 5,4 m lembar
887 M887 Wiremesh M4 ukuran 2,1 m x 5,4 m m2
888 M888 Wiremesh M4 ukuran 2,1 m x 5,4 m kg
889 M889 Wiremesh M5 ukuran 2,1 m x 5,4 m lembar
890 M890 Wiremesh M5 ukuran 2,1 m x 5,4 m m2
891 M891 Wiremesh M5 ukuran 2,1 m x 5,4 m kg
892 M892 Wiremesh M6 ukuran 2,1 m x 5,4 m lembar
893 M893 Wiremesh M6 ukuran 2,1 m x 5,4 m m2
894 M894 Wiremesh M6 ukuran 2,1 m x 5,4 m kg
895 M895 Wiremesh M7 ukuran 2,1 m x 5,4 m lembar
896 M896 Wiremesh M7 ukuran 2,1 m x 5,4 m m2
897 M897 Wiremesh M7 ukuran 2,1 m x 5,4 m kg
898 M898 Wiremesh M8 ukuran 2,1 m x 5,4 m lembar
899 M899 Wiremesh M8 ukuran 2,1 m x 5,4 m m2
900 M900 Wiremesh M8 ukuran 2,1 m x 5,4 m kg
901 M901 Wiremesh M9 ukuran 2,1 m x 5,4 m lembar
902 M902 Wiremesh M9 ukuran 2,1 m x 5,4 m m2
903 M903 Wiremesh M9 ukuran 2,1 m x 5,4 m kg
904 M904 Wiremesh kg
XIX Baja Profil
905 M905 Baja Profil kg

G MATERIAL BETON INSTAN


I Beton Instan
906 M906 Beton Instan Jayamix K 175 zak (50 kg)
907 M907 Beton Instan Jayamix K 175 kg
908 M908 Beton Instan Jayamix K 225 zak (50 kg)
909 M909 Beton Instan Jayamix K 225 kg
910 M910 Beton Instan Jayamix K 250 zak (50 kg)
911 M911 Beton Instan Jayamix K 250 kg
912 M912 Beton Instan Jayamix K 300 zak (50 kg)
913 M913 Beton Instan Jayamix K 300 kg
914 M914 Beton Instan Jayamix K 350 zak (50 kg)
915 M915 Beton Instan Jayamix K 350 kg
74

NO KODE NAMA BARANG SATUAN MERK

A B C D E
916 M916 Beton Instan Jayamix K 400 zak (50 kg)
917 M917 Beton Instan Jayamix K 400 kg
918 M918 Beton Instan Jayamix K 450 zak (50 kg)
919 M919 Beton Instan Jayamix K 450 kg
920 M920 Beton Instan Jayamix K 500 zak (50 kg)
921 M921 Beton Instan Jayamix K 500 kg
922 M922 Beton Instan Jayamix K B0 zak (50 kg)
923 M923 Beton Instan Jayamix K B0 kg

H MATERIAL BETON READY MIX


I Ready Mix
924 M924 Beton Cor Ready Mix K175 m3
925 M925 Beton Cor Ready Mix K150 m3
926 M926 Beton Cor Ready Mix K200 m3
927 M927 Beton Cor Ready Mix K225 m3
928 M928 Beton Cor Ready Mix K250 m3
929 M929 Beton Cor Ready Mix K275 m3
930 M930 Beton Cor Ready Mix K300 m3
931 M931 Beton Cor Ready Mix K325 m3
932 M932 Beton Cor Ready Mix K350 m3
933 M933 Beton Cor Ready Mix K375 m3
934 M934 Beton Cor Ready Mix K400 m3
935 M935 Beton Cor Ready Mix K425 m3
936 M936 Beton Cor Ready Mix K450 m3
937 M937 Beton Cor Ready Mix K500 m3
938 M938 Beton Cor Ready Mix KB0 m3

I MATERIAL BUIS BETON & BUIS BETON BELAH (GREFFEL)


I Asiacon
939 M939 Buis Beton Ø 100x50 cm buah
940 M940 Buis Beton Ø 20x100 cm buah
941 M941 Buis Beton Ø 30x100 cm buah
942 M942 Buis Beton Ø 40x100 cm buah
943 M943 Buis Beton Ø 50x100 cm buah
944 M944 Buis Beton Ø 60x100 cm buah
945 M945 Buis Beton Ø 80x50 cm buah
946 M946 Greffel Ø 100x50 cm buah
947 M947 Greffel Ø 20x100 cm buah
948 M948 Greffel Ø 30x100 cm buah
949 M949 Greffel Ø 40x100 cm buah
950 M950 Greffel Ø 50x100 cm buah
951 M951 Greffel Ø 60x100 cm buah
952 M952 Greffel Ø 80x50 cm buah
II Cisangkan
953 M953 Buis Beton Ø 100x50 cm buah
954 M954 Buis Beton Ø 20x100 cm buah
955 M955 Buis Beton Ø 30x100 cm buah
956 M956 Buis Beton Ø 40x100 cm buah
957 M957 Buis Beton Ø 50x100 cm buah
958 M958 Buis Beton Ø 60x100 cm buah
959 M959 Buis Beton Ø 80x50 cm buah
960 M960 Greffel Ø 100x50 cm buah
961 M961 Greffel Ø 20x100 cm buah
962 M962 Greffel Ø 30x100 cm buah
963 M963 Greffel Ø 40x100 cm buah
964 M964 Greffel Ø 50x100 cm buah
965 M965 Greffel Ø 60x100 cm buah
966 M966 Greffel Ø 80x50 cm buah
III Terra Conblock
967 M967 Buis Beton Ø 100x50 cm buah
968 M968 Buis Beton Ø 20x100 cm buah
969 M969 Buis Beton Ø 30x100 cm buah
970 M970 Buis Beton Ø 40x100 cm buah
971 M971 Buis Beton Ø 50x100 cm buah
972 M972 Buis Beton Ø 60x100 cm buah
973 M973 Buis Beton Ø 80x50 cm buah
974 M974 Greffel Ø 100x50 cm buah
975 M975 Greffel Ø 20x100 cm buah
976 M976 Greffel Ø 30x100 cm buah
977 M977 Greffel Ø 40x100 cm buah
978 M978 Greffel Ø 50x100 cm buah
979 M979 Greffel Ø 60x100 cm buah
980 M980 Greffel Ø 80x50 cm buah

J MATERIAL CAT
I Avitex Alkali Resisting Primer
981 M981 Avitex Alkali Resisting Primer 4 kg
982 M982 Avitex Alkali Resisting Primer 21 kg
II Avitex Cat Genteng & Seng
983 M983 Avitex Cat Genteng & Seng 4 kg
984 M984 Avitex Cat Genteng & Seng 20 kg
985 M985 Cat Genteng liter
III Avitex One Coat
75

NO KODE NAMA BARANG SATUAN MERK

A B C D E
986 M986 Avitex One Coat 4,5 kg
987 M987 Avitex One Coat 21 kg
IV Avitex Plamir Tembok
988 M988 Avitex Plamir 5 kg
989 M989 Avitex Plamir 25 kg
990 M990 Avitex Plamir kg
V Cat Avitex Exterior
991 M991 Avitex Exterior 1 kg
992 M992 Avitex Exterior 25 kg
993 M993 Avitex Exterior 5 kg
VI Cat Avitex Interior
994 M994 Avitex Interior 1 kg
995 M995 Avitex Interior 5 kg
996 M996 Avitex Interior 25 kg
VII Cat Dasar Dulux
997 M997 Dulux Alkali Killer 2.5 Liter
998 M998 Dulux Cat Dasar Alkali Resisting Interior 20 Liter
999 M999 Dulux Cat Dasar Alkali Resisting Interior 2.5 Liter
1000 M1000 Dulux Catylac Cat Dasar Exterior 4 Kg
1001 M1001 Dulux Catylac Cat Dasar Exterior 21 Kg
1002 M1002 Dulux Catylac Cat Dasar Exterior kg
1003 M1003 Dulux Catylac Cat Dasar Interior 4 Kg
1004 M1004 Dulux Catylac Cat Dasar Interior 21 Kg
1005 M1005 Dulux Catylac Cat Dasar Interior kg
VIII Cat Dulux Ambiance (Texture)
1006 M1006 Dulux Ambiance Base 2.5 Liter
1007 M1007 Dulux Ambiance Base 20 Liter
1008 M1008 Dulux Ambiance Colour Motion 1 Liter
1009 M1009 Dulux Ambiance Diamond Glo 2.5 Liter
1010 M1010 Dulux Ambiance Diamond Glo 20 Liter
1011 M1011 Dulux Ambiance Linen 1 Liter
1012 M1012 Dulux Ambiance Marble 1 Liter
1013 M1013 Dulux Ambiance Metallic Bronze 1 Liter
1014 M1014 Dulux Ambiance Metallic Copper 1 Liter
1015 M1015 Dulux Ambiance Metallic Gold 1 Liter
1016 M1016 Dulux Ambiance Metallic Silver 1 Liter
1017 M1017 Dulux Ambiance Velvet Gold 1 Liter
1018 M1018 Dulux Ambiance Velvet Silver 1 Liter
IX Cat Dulux Eksterior
1019 M1019 Dulux AquaShield 1 Kg
1020 M1020 Dulux AquaShield 4 Kg
1021 M1021 Dulux AquaShield 20 Kg
1022 M1022 Dulux Catylac Exterior 5 Kg
1023 M1023 Dulux Catylac Exterior 25 kg
1024 M1024 Dulux Weathershield Flash 2.5 Liter
1025 M1025 Dulux Weathershield Flash 20 Liter
1026 M1026 Dulux Weathershield Gloss 1 Liter
1027 M1027 Dulux Weathershield PowerFlexx 2.5 Liter
1028 M1028 Dulux Weathershield PowerFlexx 20 Liter
1029 M1029 Dulux Weathershield Pro 2.5 Liter
1030 M1030 Dulux Weathershield Pro 20 Liter
1031 M1031 Dulux Weathershield Putty Exterior 3.5 Kg
1032 M1032 Dulux Weathershield Roof 2.5 Liter
X Cat Dulux Interior
1033 M1033 Dulux Catylac Interior Glow 4,5 Kg
1034 M1034 Dulux Catylac Interior Glow 22 Kg
1035 M1035 Dulux Catylac Interior Glow kg
1036 M1036 Dulux Light & Space 5 Kg
1037 M1037 Dulux Light & Space kg
1038 M1038 Dulux Pentalite 5 Kg
1039 M1039 Dulux Pentalite 25 Kg
1040 M1040 Dulux Pentalite kg
1041 M1041 Dulux Pentalite Ceiling 5 Kg
1042 M1042 Dulux Pentalite Ceiling 25 Kg
1043 M1043 Dulux Pentalite Ceiling kg
XI Cat Dulux Kayu & Besi
1044 M1044 Dulux Catylac Hi-Gloss 1 kg
1045 M1045 Dulux V-Gloss 1 kg
1046 M1046 Dulux V-Gloss Doff 1 Liter
XII Cat Jotun Exterior
1047 M1047 Jotashield Antifade Colours 2,5 liter
1048 M1048 Jotashield Antifade Colours 20 liter
1049 M1049 Jotashield Colour Extreme 2,5 liter
1050 M1050 Jotashield Colour Extreme 20 liter
1051 M1051 Jotashield Flex 2,5 liter
1052 M1052 Jotashield Flex 20 liter
1053 M1053 Jotun Essence Tough Shield 2,5 liter
1054 M1054 Jotun Essence Tough Shield 18 liter
1055 M1055 Jotun Jotaroof 2,5 liter
1056 M1056 Jotun Jotashield Primer 3,5 liter
1057 M1057 Jotun Jotashield Primer 20 liter
1058 M1058 Jotun Ultra Primer 2,5 liter
1059 M1059 Jotun Ultra Primer 20 liter
76

NO KODE NAMA BARANG SATUAN MERK

A B C D E
1060 M1060 Jotun Waterguard 2,5 liter
1061 M1061 Jotun Waterguard 20 liter
XIII Cat Jotun Interior
1062 M1062 Jotun Essence Easy Wipe 2,5 liter
1063 M1063 Jotun Essence Easy Wipe 18 liter
1064 M1064 Jotun Jotaplast 2,5 liter
1065 M1065 Jotun Jotaplast 18 liter
1066 M1066 Jotun Majestic Perfect Beauty and Care 2,5 liter
1067 M1067 Jotun Majestic Perfect Beauty and Care 20 liter
1068 M1068 Jotun Majestic True Beauty Sheen and Matt 2,5 liter
1069 M1069 Jotun Majestic True Beauty Sheen and Matt 20 liter
XIV Cat Mowilex Exterior
1070 M1070 Mowilex Elastomeric 2,5 Liter
1071 M1071 Mowilex Elastomeric 20 Liter
1072 M1072 Mowilex Roof Paint 2,5 Liter
1073 M1073 Mowilex Roof Paint 20 Liter
1074 M1074 Mowilex Surface Tex 2,5 Liter
1075 M1075 Mowilex Weathercoat 2,5 Liter
1076 M1076 Mowilex Weathercoat 20 Liter
1077 M1077 Mowilex WP02 Waterproof 1 Liter
1078 M1078 Mowilex WP02 Waterproof 2,5 Liter
1079 M1079 Mowilex WP02 Waterproof 20 Liter
XV Cat Mowilex Interior
1080 M1080 Mowilex Emulsion 1 Liter
1081 M1081 Mowilex Emulsion 2,5 Liter
1082 M1082 Mowilex Emulsion 20 Liter
1083 M1083 Mowilex Emulsion VIP 2,5 Liter
1084 M1084 Mowilex Emulsion VIP 20 Liter
1085 M1085 Mowilex Vinyl Silk 2,5 Liter
1086 M1086 Mowilex Vinyl Silk 20 Liter
XVI Cat Nippon Paint Exterior
1087 M1087 Nippon Metallic Paint 0.75 Liter
1088 M1088 Nippon PU Recoatable Finish 1 Liter
1089 M1089 Nippon PU Recoatable Finish 5 Liter
1090 M1090 Nippon Roof Coating 2.5 Liter
1091 M1091 Nippon Weatherbond 0.9 Liter
1092 M1092 Nippon Weatherbond 1 Liter
1093 M1093 Nippon Weatherbond 2.5 Liter
1094 M1094 Nippon Weatherbond 20 Liter
1095 M1095 Nippon Weatherbond Solareflect 1 Liter
1096 M1096 Nippon Weatherbond Solareflect 2.5 Liter
1097 M1097 Nippon Weatherbond Solareflect 20 Liter
XVII Cat Nippon Paint Interior
1098 M1098 Nippon 3 In 1 1 Liter
1099 M1099 Nippon 3 In 1 2.5 Liter
1100 M1100 Nippon 3 In 1 5 Liter
1101 M1101 Nippon Ea-9 Finish HB 1 Liter
1102 M1102 Nippon Ea-9 Finish HB 5 Liter
1103 M1103 Nippon Flaw Less 1 Liter
1104 M1104 Nippon Flaw Less 2.5 Liter
1105 M1105 Nippon Flaw Less 20 Liter
1106 M1106 Nippon Matex Ceiling White 5 Kg
1107 M1107 Nippon Matex Gold 1 Liter
1108 M1108 Nippon Matex Gold 2.5 Liter
1109 M1109 Nippon Matex Gold 20 Liter
1110 M1110 Nippon Odourless Premium All In One 1 Liter
1111 M1111 Nippon Odourless Premium All In One 2.5 Liter
1112 M1112 Nippon Odourless Premium All In One 5 Liter
1113 M1113 Nippon Paint EA4 Finish 5 Liter
1114 M1114 Nippon Paint Kimex 3 Liter
1115 M1115 Nippon Paint Kimex 14 Liter
1116 M1116 Nippon Paint Metallic Paint 1 Liter
1117 M1117 Nippon Paint Platone 3 Liter
1118 M1118 Nippon Paint Platone 3 Liter
1119 M1119 Nippon Repellent Solution 1 Liter
1120 M1120 Nippon Repellent Solution 2.5 Liter
1121 M1121 Nippon Satin Glo 1 Liter
1122 M1122 Nippon Satin Glo 2.5 Liter
1123 M1123 Nippon Satin Glo 20 Liter
1124 M1124 Nippon Spot Less 1 Liter
1125 M1125 Nippon Spot Less 2.5 Liter
1126 M1126 Nippon Spot Less 20 Liter
1127 M1127 Nippon Spot Less Plus 1 Liter
1128 M1128 Nippon Spot Less Plus 2.5 Liter
1129 M1129 Nippon Spot Less Plus 20 Liter
1130 M1130 Nippon Vinilex 1 Kg
1131 M1131 Nippon Vinilex 25 Kg
1132 M1132 Nippon Vinilex Fresh 1 Liter
1133 M1133 Nippon Vinilex Fresh 2.5 Liter
1134 M1134 Nippon Vinilex Fresh 5 Liter
XVIII Jotun Cat Kayu & Besi
1135 M1135 Jotun Essence Hi-Gloss 1 liter
1136 M1136 Jotun Gardex Premium Gloss 1 liter
77

NO KODE NAMA BARANG SATUAN MERK

A B C D E
1137 M1137 Jotun Gardex Primer 1 liter
XIX Plamir Tembok Dulux
1138 M1138 Dulux Catylac Plamur Interior 5 Kg
1139 M1139 Dulux Catylac Plamur Interior 25 Kg
1140 M1140 Dulux Wallfiller 4 Kg
XX Propan Anti Karat
1141 M1141 Propan Aqua Metal Primer AP-860 WB kg
1142 M1142 Propan Aqua Metal Primer AP-860 WB liter
XXI Propan Coating
1143 M1143 Sicosol Invisible Water Repellent liter
1144 M1144 Sicosol Invisible Water Repellent kg
XXII Propan Politur
1145 M1145 Aqua Politur liter
1146 M1146 Aqua Politur kg
XXIII Avian Brands
1147 M1147 No Lumut Solvent Based kg

K MATERIAL CAT PELAPIS ANTI BOCOR (WATERPROOFING)


I Aquaproof
1148 M1148 Aquaproof 1 kg
1149 M1149 Aquaproof 4 kg
1150 M1150 Aquaproof 20 kg
II Bitadur
1151 M1151 Bitadur 1 kg
1152 M1152 Bitadur 4 kg
1153 M1153 Bitadur 20 kg
III Mowilex Waterproof Wp02
1154 M1154 Mowilex Waterproof Wp02 1 kg
1155 M1155 Mowilex Waterproof Wp02 4 kg
1156 M1156 Mowilex Waterproof Wp02 20 kg
IV Nippon Elastex
1157 M1157 Elastex Waterproof 1 kg
1158 M1158 Elastex Waterproof 4 kg
1159 M1159 Elastex Waterproof 20 kg
V No Drop
1160 M1160 No Drop 1 kg
1161 M1161 No Drop 4 kg
1162 M1162 No Drop 20 kg
VI Sika Rain Tite
1163 M1163 Sika Rain Tite 1 kg
1164 M1164 Sika Rain Tite 4 kg
1165 M1165 Sika Rain Tite 20 kg

L MATERIAL HOMOGENEOUS TILE (GRANIT TILE)


I Essenza Tile 60x60
1166 M1166 Essenza Crystalline Series Aqva polished dus (4 buah)
1167 M1167 Essenza Crystalline Series Aqva polished buah
1168 M1168 Essenza Crystalline Series Diamante polished dus (4 buah)
1169 M1169 Essenza Crystalline Series Diamante polished buah
1170 M1170 Essenza Crystalline Series Hyperwhite polished dus (4 buah)
1171 M1171 Essenza Crystalline Series Hyperwhite polished buah
1172 M1172 Essenza Graniti Imperiali Rock Beola Grey dus (4 buah)
1173 M1173 Essenza Graniti Imperiali Rock Beola Grey buah
1174 M1174 Essenza Landmark Polished Beige dus (4 buah)
1175 M1175 Essenza Landmark Polished Beige buah
1176 M1176 Essenza Landmark Polished Grey dus (4 buah)
1177 M1177 Essenza Landmark Polished Grey buah
1178 M1178 Essenza Landmark Polished White dus (4 buah)
1179 M1179 Essenza Landmark Polished White buah
1180 M1180 Essenza Marble Look Polished Alexandra dus (4 buah)
1181 M1181 Essenza Marble Look Polished Alexandra buah
1182 M1182 Essenza Marble Look Polished Alexandra dus (4 buah)
1183 M1183 Essenza Marble Look Polished Alexandra buah
1184 M1184 Essenza Marble Look Polished Copernicia dus (4 buah)
1185 M1185 Essenza Marble Look Polished Copernicia buah
1186 M1186 Essenza Marble Look Polished Copernicia dus (4 buah)
1187 M1187 Essenza Marble Look Polished Copernicia buah
1188 M1188 Essenza Salt & Pepper Polished Coral Bell All Var dus (4 buah)
1189 M1189 Essenza Salt & Pepper Polished Coral Bell All Var buah
1190 M1190 Essenza Salt & Pepper Polished Prince Rubert dus (4 buah)
1191 M1191 Essenza Salt & Pepper Polished Prince Rubert buah
II Garuda Tile 60x60
1192 M1192 Garuda GS62001 Madrid dus (4 buah)
1193 M1193 Garuda GS62001 Madrid buah
1194 M1194 Garuda Motif Kayu dus (4 buah)
1195 M1195 Garuda Motif Kayu buah
1196 M1196 Garuda R6217S Santa FE MED Cream dus (4 buah)
1197 M1197 Garuda R6217S Santa FE MED Cream buah
1198 M1198 Garuda R6221S Santa FE MED Grey dus (4 buah)
1199 M1199 Garuda R6221S Santa FE MED Grey buah
1200 M1200 Garuda R6515S Huelva dus (4 buah)
1201 M1201 Garuda R6515S Huelva buah
1202 M1202 Garuda Tile Broken White dus (4 buah)
78

NO KODE NAMA BARANG SATUAN MERK

A B C D E
1203 M1203 Garuda Tile Broken White buah
III Granito Tile 60x60
1204 M1204 Granito Aurora Mirror Polished Latte dus (4 buah)
1205 M1205 Granito Aurora Mirror Polished Latte buah
1206 M1206 Granito Aurora Mirror Polished Silk dus (4 buah)
1207 M1207 Granito Aurora Mirror Polished Silk buah
1208 M1208 Granito Aurora Mirror Polished Waffle dus (4 buah)
1209 M1209 Granito Aurora Mirror Polished Waffle buah
1210 M1210 Granito Castello Rustic Unpolished Crema dus (4 buah)
1211 M1211 Granito Castello Rustic Unpolished Crema buah
1212 M1212 Granito Castello Rustic Unpolished Espresso dus (4 buah)
1213 M1213 Granito Castello Rustic Unpolished Espresso buah
1214 M1214 Granito Castello Rustic Unpolished Marrone dus (4 buah)
1215 M1215 Granito Castello Rustic Unpolished Marrone buah
1216 M1216 Granito Castello Rustic Unpolished Rombo dus (4 buah)
1217 M1217 Granito Castello Rustic Unpolished Rombo buah
1218 M1218 Granito Castello Rustic Unpolished Rosso dus (4 buah)
1219 M1219 Granito Castello Rustic Unpolished Rosso buah
1220 M1220 Granito Castello Rustic Unpolished Vento dus (4 buah)
1221 M1221 Granito Castello Rustic Unpolished Vento buah
1222 M1222 Granito Lunar dus (4 buah)
1223 M1223 Granito Lunar buah
1224 M1224 Granito Palazzo Mirror Polished Arezzo dus (4 buah)
1225 M1225 Granito Palazzo Mirror Polished Arezzo buah
1226 M1226 Granito Palazzo Mirror Polished Estate dus (4 buah)
1227 M1227 Granito Palazzo Mirror Polished Estate buah
1228 M1228 Granito Palazzo Mirror Polished Monza dus (4 buah)
1229 M1229 Granito Palazzo Mirror Polished Monza buah
1230 M1230 Granito Palazzo Mirror Polished Palermo dus (4 buah)
1231 M1231 Granito Palazzo Mirror Polished Palermo buah
1232 M1232 Granito Palazzo Touch Unpolished Arezzo dus (4 buah)
1233 M1233 Granito Palazzo Touch Unpolished Arezzo buah
1234 M1234 Granito Palazzo Touch Unpolished Estate dus (4 buah)
1235 M1235 Granito Palazzo Touch Unpolished Estate buah
1236 M1236 Granito Sabbia dus (4 buah)
1237 M1237 Granito Sabbia buah
1238 M1238 Granito Sabbia Casa dus (4 buah)
1239 M1239 Granito Sabbia Casa buah
1240 M1240 Granito Sabbia Villa dus (4 buah)
1241 M1241 Granito Sabbia Villa buah
1242 M1242 Granito Salsa Crystal Polished Aluminium dus (4 buah)
1243 M1243 Granito Salsa Crystal Polished Aluminium buah
1244 M1244 Granito Salsa Crystal Polished Black dus (4 buah)
1245 M1245 Granito Salsa Crystal Polished Black buah
1246 M1246 Granito Salsa Crystal Polished Coffee dus (4 buah)
1247 M1247 Granito Salsa Crystal Polished Coffee buah
1248 M1248 Granito Salsa Crystal Polished Frost White dus (4 buah)
1249 M1249 Granito Salsa Crystal Polished Frost White buah
1250 M1250 Granito Salsa Crystal Polished Greystone dus (4 buah)
1251 M1251 Granito Salsa Crystal Polished Greystone buah
1252 M1252 Granito Salsa Crystal Polished Honey dus (4 buah)
1253 M1253 Granito Salsa Crystal Polished Honey buah
1254 M1254 Granito Salsa Crystal Polished Ivory dus (4 buah)
1255 M1255 Granito Salsa Crystal Polished Ivory buah
1256 M1256 Granito Salsa Crystal Polished Pearl White dus (4 buah)
1257 M1257 Granito Salsa Crystal Polished Pearl White buah
1258 M1258 Granito Salsa Crystal Polished Steel dus (4 buah)
1259 M1259 Granito Salsa Crystal Polished Steel buah
1260 M1260 Granito Salsa Crystal Polished Water Stone dus (4 buah)
1261 M1261 Granito Salsa Crystal Polished Water Stone buah
1262 M1262 Granito Salsa Crystal Polished White Sands dus (4 buah)
1263 M1263 Granito Salsa Crystal Polished White Sands buah
1264 M1264 Granito Salsa Oasis Unpolished Aluminium dus (4 buah)
1265 M1265 Granito Salsa Oasis Unpolished Aluminium buah
1266 M1266 Granito Salsa Oasis Unpolished Black dus (4 buah)
1267 M1267 Granito Salsa Oasis Unpolished Black buah
1268 M1268 Granito Salsa Oasis Unpolished Coffee dus (4 buah)
1269 M1269 Granito Salsa Oasis Unpolished Coffee buah
1270 M1270 Granito Salsa Oasis Unpolished Frost White dus (4 buah)
1271 M1271 Granito Salsa Oasis Unpolished Frost White buah
1272 M1272 Granito Salsa Oasis Unpolished Greystone dus (4 buah)
1273 M1273 Granito Salsa Oasis Unpolished Greystone buah
1274 M1274 Granito Salsa Oasis Unpolished Honey dus (4 buah)
1275 M1275 Granito Salsa Oasis Unpolished Honey buah
1276 M1276 Granito Salsa Oasis Unpolished Ivory dus (4 buah)
1277 M1277 Granito Salsa Oasis Unpolished Ivory buah
1278 M1278 Granito Salsa Oasis Unpolished Pearl White dus (4 buah)
1279 M1279 Granito Salsa Oasis Unpolished Pearl White buah
1280 M1280 Granito Salsa Oasis Unpolished Steel dus (4 buah)
1281 M1281 Granito Salsa Oasis Unpolished Steel buah
1282 M1282 Granito Salsa Rustic Unpolished Abey dus (4 buah)
1283 M1283 Granito Salsa Rustic Unpolished Abey buah
1284 M1284 Granito Salsa Rustic Unpolished Temple dus (4 buah)
79

NO KODE NAMA BARANG SATUAN MERK

A B C D E
1285 M1285 Granito Salsa Rustic Unpolished Temple buah
IV Indogress Tile 60x60
1286 M1286 Indogress Granit Cristallo Polished dus (4 buah)
1287 M1287 Indogress Granit Cristallo Polished buah
1288 M1288 Indogress Granit Foresta Satin dus (4 buah)
1289 M1289 Indogress Granit Foresta Satin buah
1290 M1290 Indogress Granit Marmaro Polished dus (4 buah)
1291 M1291 Indogress Granit Marmaro Polished buah
1292 M1292 Indogress Granit Marmo Polished dus (4 buah)
1293 M1293 Indogress Granit Marmo Polished buah
1294 M1294 Indogress Granit Natura Polished dus (4 buah)
1295 M1295 Indogress Granit Natura Polished buah
1296 M1296 Indogress Granit Salt & Pepper Polished dus (4 buah)
1297 M1297 Indogress Granit Salt & Pepper Polished buah
1298 M1298 Indogress Granit Uni Color Polished dus (4 buah)
1299 M1299 Indogress Granit Uni Color Polished buah

M MATERIAL HPL (122x244 cm)


I App Timber
1300 M1300 APP TIMBER H Natural Zebrawood lembar
1301 M1301 APP TIMBER Fumed Maple lembar
II Eco
1302 M1302 ECO Woodgrain 001 lembar
1303 M1303 ECO Woodgrain P 042 lembar
1304 M1304 ECO Solid Eco 006 lembar
1305 M1305 ECO Woodgrain P 058 RL lembar
III Taco
1306 M1306 Taco HPL AA / B / H Putih lembar
1307 M1307 Taco HPL AA / B / H Polos lembar
1308 M1308 Taco HPL AA / B / H Warna Kayu lembar
1309 M1309 Taco HPL AD / G Dove Polos lembar
1310 M1310 Taco HPL D / G Gloss Polos lembar
1311 M1311 Taco HPL Solid Brush lembar
1312 M1312 Taco HPL Tekture lembar
1313 M1313 Taco HPL New Texture lembar
1314 M1314 Taco HPL Vir Line lembar
1315 M1315 Taco HPL Floral (BU) lembar
1316 M1316 Taco HPL Asian Oak lembar
1317 M1317 Taco HPL Light Grey Gloss lembar
1318 M1318 Taco HPL Sagrada lembar
1319 M1319 Taco HPL Light Pesaro lembar
1320 M1320 Taco HPL Golden Foil lembar

N MATERIAL KACA
I Kaca Bening
1321 M1321 Kaca Bening 10 mm m2
1322 M1322 Kaca Bening 3 mm m2
1323 M1323 Kaca Bening 5 mm m2
1324 M1324 Kaca Bening 8 mm m2
II Kaca Cermin
1325 M1325 Kaca Cermin 3mm m2
1326 M1326 Kaca Cermin 5mm m2
III Kaca Rayben
1327 M1327 Kaca Rayben 10 mm m2
1328 M1328 Kaca Rayben 3 mm m2
1329 M1329 Kaca Rayben 5 mm m2
1330 M1330 Kaca Rayben 8 mm m2
IV Kaca Tempered
1331 M1331 Kaca Tempered Clear 10mm m2
1332 M1332 Kaca Tempered Clear 12mm m2
1333 M1333 Kaca Tempered Clear 15mm m2
1334 M1334 Kaca Tempered Clear 19mm m2
1335 M1335 Kaca Tempered Clear 3mm m2
1336 M1336 Kaca Tempered Clear 4mm m2
1337 M1337 Kaca Tempered Clear 5mm m2
1338 M1338 Kaca Tempered Clear 6mm m2
1339 M1339 Kaca Tempered Clear 8mm m2
1340 M1340 Kaca Tempered Stopsol Blue Green 6mm m2
1341 M1341 Kaca Tempered Stopsol Blue Green 8mm m2
1342 M1342 Kaca Tempered Stopsol Dark Blue 5mm m2
1343 M1343 Kaca Tempered Stopsol Dark Blue 6mm m2
1344 M1344 Kaca Tempered Stopsol Dark Blue 8mm m2
1345 M1345 Kaca Tempered Stopsol Euro Grey 6mm m2
1346 M1346 Kaca Tempered Stopsol Euro Grey 8mm m2
1347 M1347 Kaca Tempered Stopsol Green 5mm m2
1348 M1348 Kaca Tempered Stopsol Green 6mm m2
1349 M1349 Kaca Tempered Stopsol Green 8mm m2
1350 M1350 Kaca Tempered Tinted Blue Green 5mm m2
1351 M1351 Kaca Tempered Tinted Blue Green 6mm m2
1352 M1352 Kaca Tempered Tinted Blue Green 8mm m2
1353 M1353 Kaca Tempered Tinted Bronze 5mm m2
1354 M1354 Kaca Tempered Tinted Dark Blue 12mm m2
1355 M1355 Kaca Tempered Tinted Dark Blue 5mm m2
80

NO KODE NAMA BARANG SATUAN MERK

A B C D E
1356 M1356 Kaca Tempered Tinted Dark Blue 6mm m2
1357 M1357 Kaca Tempered Tinted Dark GREY 3mm m2
1358 M1358 Kaca Tempered Tinted Dark GREY 5mm m2
1359 M1359 Kaca Tempered Tinted Dark GREY 6mm m2
1360 M1360 Kaca Tempered Tinted Euro Grey 8mm m2
1361 M1361 Kaca Tempered Tinted Euro Grey 5mm m2
1362 M1362 Kaca Tempered Tinted Euro Grey 6mm m2
1363 M1363 Kaca Tempered Tinted Green 12mm m2
1364 M1364 Kaca Tempered Tinted Green 5mm m2
1365 M1365 Kaca Tempered Tinted Green 6mm m2
1366 M1366 Kaca Tempered Tinted Green 8mm m2

O MATERIAL KAYU
I Kayu Balok
1367 M1367 Borneo 6 x 12 x 400 batang
1368 M1368 Borneo 6 x 12 x 400 m3
1369 M1369 Borneo 8 x 12 x 400 batang
1370 M1370 Borneo 8 x 12 x 400 m3
1371 M1371 Kamper 6 x 12 x 400 batang
1372 M1372 Kamper 6 x 12 x 400 m3
1373 M1373 Kamper 8 x 12 x 400 batang
1374 M1374 Kamper 8 x 12 x 400 m3
1375 M1375 Meranti 6 x 12 x 400 batang
1376 M1376 Meranti 6 x 12 x 400 m3
1377 M1377 Meranti 8 x 12 x 400 batang
1378 M1378 Meranti 8 x 12 x 400 m3
II Kayu Galar
1379 M1379 Borneo 5 x 10 x 400 batang
1380 M1380 Borneo 5 x 10 x 400 m3
1381 M1381 Kamper 5 x 10 x 400 batang
1382 M1382 Kamper 5 x 10 x 400 m3
1383 M1383 Meranti 5 x 10 x 400 batang
1384 M1384 Meranti 5 x 10 x 400 m3
III Kayu Kaso
1385 M1385 Borneo 4 x 6 x 400 batang
1386 M1386 Borneo 4 x 6 x 400 m3
1387 M1387 Borneo 5 x 7 x 400 batang
1388 M1388 Borneo 5 x 7 x 400 m3
1389 M1389 Kamper 4 x 6 x 400 batang
1390 M1390 Kamper 4 x 6 x 400 m3
1391 M1391 Kamper 5 x 7 x 400 batang
1392 M1392 Kamper 5 x 7 x 400 m3
1393 M1393 Meranti 4 x 6 x 400 batang
1394 M1394 Meranti 4 x 6 x 400 m3
1395 M1395 Meranti 5 x 7 x 400 batang
1396 M1396 Meranti 5 x 7 x 400 m3
IV Kayu Papan
1397 M1397 Papan Kayu Borneo 3x20x400 m3
1398 M1398 Papan Kayu Jambi 2x20x400 m3
1399 M1399 Papan Kayu Kamper 3x20x400 m3
1400 M1400 Papan Kayu Meranti 2x20x400 m3
V Kayu Reng
1401 M1401 Kayu Borneo 2 x 3 x 400 batang
1402 M1402 Kayu Borneo 2 x 3 x 400 m3
1403 M1403 Kayu Borneo 3 x 4 x 400 batang
1404 M1404 Kayu Borneo 3 x 4 x 400 m3
1405 M1405 Kayu Kamper 2 x 3 x 400 batang
1406 M1406 Kayu Kamper 2 x 3 x 400 m3
1407 M1407 Kayu Kamper 3 x 4 x 400 batang
1408 M1408 Kayu Kamper 3 x 4 x 400 m3
1409 M1409 Kayu Meranti 2 x 3 x 400 batang
1410 M1410 Kayu Meranti 2 x 3 x 400 m3
1411 M1411 Kayu Meranti 3 x 4 x 400 batang
1412 M1412 Kayu Meranti 3 x 4 x 400 m3
VI Kayu Triplek
1413 M1413 Triplek Tebal 12 mm 122x244 cm lembar
1414 M1414 Triplek Tebal 15 mm 122x244 cm lembar
1415 M1415 Triplek Tebal 18 mm 122x244 cm lembar
1416 M1416 Triplek Tebal 18 mm 122x244 cm lembar
1417 M1417 Triplek Tebal 3 mm 122x244 cm lembar
1418 M1418 Triplek Tebal 4 mm 122x244 cm lembar
1419 M1419 Triplek Tebal 6 mm 122x244 cm lembar
1420 M1420 Triplek Tebal 9 mm 122x244 cm lembar
VII Kayu Triplek Phenolic
1421 M1421 Triplek Phenolic 12mm MR 122x244 cm lembar
1422 M1422 Triplek Phenolic 12mm WSB 122x244 cm lembar
1423 M1423 Triplek Phenolic 15mm MR 122x244 cm lembar
1424 M1424 Triplek Phenolic 15mm WSB 122x244 cm lembar
1425 M1425 Triplek Phenolic 18mm MR 122x244 cm lembar
1426 M1426 Triplek Phenolic 18mm WSB 122x244 cm lembar
VIII Kayu Dolken
1427 M1427 Dolken kayu dia. 8-10 panjang 4 m batang
81

NO KODE NAMA BARANG SATUAN MERK

A B C D E
P MATERIAL KERAMIK
I Arwana Keramik
1428 M1428 Keramik Warna Fancy 30 x 30 m2
1429 M1429 Keramik Warna Marble 30 x 30 m2
1430 M1430 Keramik Warna Marble 40 x 40 m2
1431 M1431 Keramik Warna Muda 20 x 20 m2
1432 M1432 Keramik Warna Putih 30 x 30 m2
1433 M1433 Keramik Warna Putih 40 x 40 m2
1434 M1434 Keramik Warna Tua 20 x 20 m2
II Herkules Keramik
1435 M1435 Keramik Hercules Gelap 40 x 40 m2
1436 M1436 Keramik Hercules Motif Dasar Gelap 40 x 40 m2
1437 M1437 Keramik Hercules Motif Dasar Putih 40 x 40 m2
1438 M1438 Keramik Hercules Motif Khusus 40 x 40 m2
1439 M1439 Keramik Hercules Putih 40 x 40 m2
1440 M1440 Keramik Lantai Hercules Aragon 40 x 40 m2
1441 M1441 Keramik Lantai Hercules Jamaica 40 x 40 m2
1442 M1442 Keramik Lantai Hercules Uluwatu 40 x 40 m2
III Keramik Lantai Motif Kayu 40x40
1443 M1443 Ceramica Serat Kayu dus (6 buah)
1444 M1444 KITA Meranti Beige dus (6 buah)
1445 M1445 MCC Kalimantan dus (6 buah)
1446 M1446 MCC Tridi dus (6 buah)
1447 M1447 Picasso Glossy Grey dus (6 buah)
1448 M1448 Spectrum Wilow dus (6 buah)
IV Keramik Lantai Motif Kayu 50x50
1449 M1449 Concord Tyron Bone dus (4 buah)
1450 M1450 Hemlock Beige dus (4 buah)
1451 M1451 Icarus Wooden Beige dus (4 buah)
1452 M1452 Icarus Wooden Beige dus (4 buah)
1453 M1453 Jupiter Hazel Beige dus (4 buah)
1454 M1454 KIA Hickory Beige dus (4 buah)
1455 M1455 Milan Rio Walnut dus (4 buah)
1456 M1456 Opera Acacia Brown dus (4 buah)
1457 M1457 Opera Acacia Crema dus (4 buah)
1458 M1458 Roman D’Kauri Avana dus (4 buah)
1459 M1459 Roman D’Treccia Naturale dus (4 buah)
1460 M1460 Roman dAstana Noce dus (4 buah)
1461 M1461 Roman Dparquet Cream dus (4 buah)
1462 M1462 Sunpower DF 5361 Parquet Sand dus (4 buah)
1463 M1463 Uno Motif Fortuna Matte dus (4 buah)
1464 M1464 Uno Motif Untario Matte dus (4 buah)
V Keramik Lantai Motif Kayu 60x60
1465 M1465 Concord Balsawood dus (4 buah)
1466 M1466 Platinum Lexus dus (4 buah)
1467 M1467 Platinum Nama dus (4 buah)
1468 M1468 Platinum Nigel dus (4 buah)
1469 M1469 Sungkai Athena Tile dus (4 buah)
VI Milan Keramik
1470 M1470 Keramik Accent Color 25 x 25 m2
1471 M1471 Keramik Accent Color 25 x 25 buah
1472 M1472 Keramik Accent Color 25 x 50 m2
1473 M1473 Keramik Accent Color 25 x 50 buah
1474 M1474 Keramik Accent Color 50 x 50 m2
1475 M1475 Keramik Accent Color 50 x 50 buah
1476 M1476 Keramik Classy Color 25 x 25 m2
1477 M1477 Keramik Classy Color 25 x 25 buah
1478 M1478 Keramik Classy Color 25 x 50 m2
1479 M1479 Keramik Classy Color 25 x 50 buah
1480 M1480 Keramik Classy Color 50 x 50 m2
1481 M1481 Keramik Classy Color 50 x 50 buah
1482 M1482 Keramik Fancy Color 25 x 25 m2
1483 M1483 Keramik Fancy Color 25 x 25 buah
1484 M1484 Keramik Fancy Color 25 x 50 m2
1485 M1485 Keramik Fancy Color 25 x 50 buah
1486 M1486 Keramik Fancy Color 50 x 50 m2
1487 M1487 Keramik Fancy Color 50 x 50 buah
1488 M1488 Keramik Gelap 40 x 40 m2
1489 M1489 Keramik Gelap 40 x 40 buah
1490 M1490 Keramik Median 40 x 40 m2
1491 M1491 Keramik Median 40 x 40 buah
1492 M1492 Keramik Pure Color 25 x 25 m2
1493 M1493 Keramik Pure Color 25 x 25 buah
1494 M1494 Keramik Pure Color 25 x 50 m2
1495 M1495 Keramik Pure Color 25 x 50 buah
1496 M1496 Keramik Pure Color 50 x 50 m2
1497 M1497 Keramik Pure Color 50 x 50 buah
1498 M1498 Keramik Putih 40 x 40 m2
1499 M1499 Keramik Putih 40 x 40 buah
1500 M1500 Keramik Rustic 33 x 33 m2
1501 M1501 Keramik Rustic 33 x 33 buah
1502 M1502 Keramik Rustic 40 x 40 m2
1503 M1503 Keramik Rustic 40 x 40 buah
82

NO KODE NAMA BARANG SATUAN MERK

A B C D E
1504 M1504 Keramik Supermilan 25 x 33 Golongan A m2
1505 M1505 Keramik Supermilan 25 x 33 Golongan A buah
1506 M1506 Keramik Supermilan 25 x 33 Golongan B m2
1507 M1507 Keramik Supermilan 25 x 33 Golongan B buah
1508 M1508 Keramik Supermilan 40 x 40 Gelap m2
1509 M1509 Keramik Supermilan 40 x 40 Gelap buah
1510 M1510 Keramik Supermilan 40 x 40 Median m2
1511 M1511 Keramik Supermilan 40 x 40 Median buah
1512 M1512 Keramik Supermilan 40 x 40 Putih m2
1513 M1513 Keramik Supermilan 40 x 40 Putih buah
1514 M1514 Keramik Supermilan 50 x 50 Putih m2
1515 M1515 Keramik Supermilan 50 x 50 Putih buah
VII Platinum Keramik
1516 M1516 Keramik Alpha blue, green 20×20 m2
1517 M1517 Keramik Alpha blue, green 20×20 buah
1518 M1518 Keramik Bintan, bone, brown, cream 30×30 m2
1519 M1519 Keramik Bintan, bone, brown, cream 30×30 buah
1520 M1520 Keramik Capri brown, grey m2
1521 M1521 Keramik Capri brown, grey buah
1522 M1522 Keramik Cargo, brown, grey, dark brown, dark grey 30×30 m2
1523 M1523 Keramik Cargo, brown, grey, dark brown, dark grey 30×30 buah
1524 M1524 Keramik Cavalli, cream, white 60×60 m2
1525 M1525 Keramik Cavalli, cream, white 60×60 buah
1526 M1526 Keramik Clarin, bone, brown, grey 30×30 m2
1527 M1527 Keramik Clarin, bone, brown, grey 30×30 buah
1528 M1528 Keramik Cordon, bone, brown, cream 30×30 m2
1529 M1529 Keramik Cordon, bone, brown, cream 30×30 buah
1530 M1530 Keramik Ecco grey, brown 50×50 m2
1531 M1531 Keramik Ecco grey, brown 50×50 buah
1532 M1532 Keramik Fredo, cream, grey 60×60 m2
1533 M1533 Keramik Fredo, cream, grey 60×60 buah
1534 M1534 Keramik Fresno, cream, grey 60×60 m2
1535 M1535 Keramik Fresno, cream, grey 60×60 buah
1536 M1536 Keramik Galaxy black, brown, cream, grey, white 20×20 m2
1537 M1537 Keramik Galaxy black, brown, cream, grey, white 20×20 buah
1538 M1538 Keramik Gobi cream, grey 50×50 m2
1539 M1539 Keramik Gobi cream, grey 50×50 buah
1540 M1540 Keramik Jungle red, green, grey, red 30×30 m2
1541 M1541 Keramik Jungle red, green, grey, red 30×30 buah
1542 M1542 Keramik Mahoni brown, cream 30×30 m2
1543 M1543 Keramik Mahoni brown, cream 30×30 buah
1544 M1544 Keramik Marble brown 30×30 m2
1545 M1545 Keramik Marble brown 30×30 buah
1546 M1546 Keramik Newton brown, green, grey 30×30 m2
1547 M1547 Keramik Newton brown, green, grey 30×30 buah
1548 M1548 Keramik Petra cream, terracota 20×20 m2
1549 M1549 Keramik Petra cream, terracota 20×20 buah
1550 M1550 Keramik Roxy black, blue, brown, green, grey, red 20×20 m2
1551 M1551 Keramik Roxy black, blue, brown, green, grey, red 20×20 buah
1552 M1552 Keramik Salsa, cream, grey 60×60 m2
1553 M1553 Keramik Salsa, cream, grey 60×60 buah
1554 M1554 Keramik Sicillia, grey 60×60 m2
1555 M1555 Keramik Sicillia, grey 60×60 buah
1556 M1556 Keramik Sonata, brown 60×60 m2
1557 M1557 Keramik Sonata, brown 60×60 buah
1558 M1558 Keramik Strata, cream, grey 60×60 m2
1559 M1559 Keramik Strata, cream, grey 60×60 buah
1560 M1560 Keramik Teakwood, beige, brown, latte60×60 m2
1561 M1561 Keramik Teakwood, beige, brown, latte60×60 buah
1562 M1562 Keramik Tequila, cream, white 60×60 m2
1563 M1563 Keramik Tequila, cream, white 60×60 buah
1564 M1564 Keramik Tosca, cream, white 60×60 m2
1565 M1565 Keramik Tosca, cream, white 60×60 buah
1566 M1566 Keramik Track brown, grey 20×20 m2
1567 M1567 Keramik Track brown, grey 20×20 buah
1568 M1568 Keramik Tudor, cream, white 60×60 m2
1569 M1569 Keramik Tudor, cream, white 60×60 buah
VIII Roman Keramik
1570 M1570 Keramik Roman 16.5 x 66.6 Golongan A m2
1571 M1571 Keramik Roman 16.5 x 66.6 Golongan A buah
1572 M1572 Keramik Roman 20 x 20 Golongan A m2
1573 M1573 Keramik Roman 20 x 20 Golongan A buah
1574 M1574 Keramik Roman 20 x 20 Golongan B m2
1575 M1575 Keramik Roman 20 x 20 Golongan B buah
1576 M1576 Keramik Roman 20 x 20 Golongan D m2
1577 M1577 Keramik Roman 20 x 20 Golongan D buah
1578 M1578 Keramik Roman 30 x 30 Golongan B m2
1579 M1579 Keramik Roman 30 x 30 Golongan B buah
1580 M1580 Keramik Roman 30 x 30 Golongan C m2
1581 M1581 Keramik Roman 30 x 30 Golongan C buah
1582 M1582 Keramik Roman 33.3 x 33.3 Golongan A m2
1583 M1583 Keramik Roman 33.3 x 33.3 Golongan A buah
1584 M1584 Keramik Roman 33.3 x 33.3 Golongan C m2
83

NO KODE NAMA BARANG SATUAN MERK

A B C D E
1585 M1585 Keramik Roman 33.3 x 33.3 Golongan C buah
1586 M1586 Keramik Roman 33.3 x 66.6 Golongan A m2
1587 M1587 Keramik Roman 33.3 x 66.6 Golongan A buah
1588 M1588 Keramik Roman 33.3 x 66.6 Golongan B m2
1589 M1589 Keramik Roman 33.3 x 66.6 Golongan B buah
1590 M1590 Keramik Roman 33.3 x 66.6 Golongan C m2
1591 M1591 Keramik Roman 33.3 x 66.6 Golongan C buah
1592 M1592 Keramik Roman 40 x 40 Golongan A m2
1593 M1593 Keramik Roman 40 x 40 Golongan A buah
1594 M1594 Keramik Roman 40 x 40 Golongan B m2
1595 M1595 Keramik Roman 40 x 40 Golongan B buah
1596 M1596 Keramik Roman 40 x 40 Golongan C m2
1597 M1597 Keramik Roman 40 x 40 Golongan C buah
1598 M1598 Keramik Roman 40 x 40 Golongan D m2
1599 M1599 Keramik Roman 40 x 40 Golongan D buah
1600 M1600 Keramik Roman 45 x 45 Golongan A m2
1601 M1601 Keramik Roman 45 x 45 Golongan A buah
1602 M1602 Keramik Roman 45 x 45 Golongan B m2
1603 M1603 Keramik Roman 45 x 45 Golongan B buah
1604 M1604 Keramik Roman 45 x 45 Golongan E m2
1605 M1605 Keramik Roman 45 x 45 Golongan E buah
1606 M1606 Keramik Roman 50 x 50 Golongan A m2
1607 M1607 Keramik Roman 50 x 50 Golongan A buah
1608 M1608 Keramik Roman 50 x 50 Golongan B m2
1609 M1609 Keramik Roman 50 x 50 Golongan B buah
1610 M1610 Keramik Roman 50 x 50 Golongan C m2
1611 M1611 Keramik Roman 50 x 50 Golongan C buah
1612 M1612 Keramik Roman 60 x 60 Golongan A m2
1613 M1613 Keramik Roman 60 x 60 Golongan A buah
1614 M1614 Keramik Roman 60 x 60 Golongan B m2
1615 M1615 Keramik Roman 60 x 60 Golongan B buah
1616 M1616 Keramik Roman 60 x 60 Golongan C m2
1617 M1617 Keramik Roman 60 x 60 Golongan C buah

Q MATERIAL PAKU, DYNABOLT, BAUT, DLL


I Dynabolt
1618 M1618 Dynabolt type 3114 ukuran 8x 45mm buah
1619 M1619 Dynabolt type 3124 ukuran 8x 67 mm buah
1620 M1620 Dynabolt type 3134 ukuran 8x 97 mm buah
1621 M1621 Dynabolt type 3710 ukuran 10x 50 mm buah
1622 M1622 Dynabolt type 3717 ukuran 10x 60 mm buah
1623 M1623 Dynabolt type 3730 ukuran 10 x 80 mm buah
1624 M1624 Dynabolt type 3740 ukuran 10 x 105 mm buah
1625 M1625 Dynabolt type 5020 ukuran 8x 45mm buah
1626 M1626 Dynabolt type 5022 ukuran 8x 67 mm buah
1627 M1627 Dynabolt type 5030 ukuran 8x 97 mm buah
1628 M1628 Dynabolt type 5040 ukuran 10x 50 mm buah
1629 M1629 Dynabolt type 5050 ukuran 10x 60 mm buah
1630 M1630 Dynabolt type 5060 ukuran 10x 60 mm buah
1631 M1631 Dynabolt type 6222 ukuran 10 x 105 mm buah
1632 M1632 Dynabolt type 6235 ukuran 16x100mm buah
1633 M1633 Dynabolt type 6245 ukuran 16x125mm buah
1634 M1634 Dynabolt type 7532 ukuran 5/8x96mm buah
1635 M1635 Dynabolt type 7540 ukuran 5/8x125mm buah
II Paku Beton Hitam
1636 M1636 Paku Beton Hitam Hensel 5 cm 100 buah
1637 M1637 Paku Beton Hitam Hensel 5 cm buah
1638 M1638 Paku Beton Hitam Hensel 7 cm 100 buah
1639 M1639 Paku Beton Hitam Hensel 7 cm buah
1640 M1640 Paku Beton Hitam Marabu 3 cm 100 buah
1641 M1641 Paku Beton Hitam Marabu 3 cm buah
1642 M1642 Paku Beton Hitam Marabu 4 cm 100 buah
1643 M1643 Paku Beton Hitam Marabu 4 cm buah
1644 M1644 Paku Beton Hitam Marabu 5 cm 100 buah
1645 M1645 Paku Beton Hitam Marabu 5 cm buah
1646 M1646 Paku Beton Hitam Marabu 7 cm 100 buah
1647 M1647 Paku Beton Hitam Marabu 7 cm buah
III Paku Beton Putih
1648 M1648 Paku Beton Camel 1 1/2 inch (4 cm) kg
1649 M1649 Paku Beton Camel 1 1/4 inch (3 cm) kg
1650 M1650 Paku Beton Camel 1 inch (2.5 cm) kg
1651 M1651 Paku Beton Camel 2 inch (5 cm) kg
1652 M1652 Paku Beton Camel 3 inch (7.5 cm) kg
1653 M1653 Paku Beton Camel 4 inch (10 cm) kg
1654 M1654 Paku Beton Marabu 1 1/2 inch (4 cm) kg
1655 M1655 Paku Beton Marabu 1 1/4 inch (3 cm) kg
1656 M1656 Paku Beton Marabu 1 inch (2.5 cm) kg
1657 M1657 Paku Beton Marabu 2 inch (5 cm) kg
1658 M1658 Paku Beton Marabu 3 inch (7.5 cm) kg
1659 M1659 Paku Beton Marabu 4 inch (10 cm) kg
IV Paku Kayu
1660 M1660 Paku kayu 1 1/2" Inch (4 cm) 200 gram
1661 M1661 Paku kayu 1 1/2" Inch (4 cm) 26 kg
84

NO KODE NAMA BARANG SATUAN MERK

A B C D E
1662 M1662 Paku kayu 1 1/4" Inch (3 cm) 26 kg
1663 M1663 Paku kayu 1 1/4" Inch (3 cm) kg
1664 M1664 Paku Kayu 10 cm kg
1665 M1665 Paku Kayu 12 cm kg
1666 M1666 Paku kayu 2" inch (5 cm) 200 gram
1667 M1667 Paku kayu 2" Inch (5 cm) 26 kg
1668 M1668 Paku kayu 2" Inch (5 cm) kg
1669 M1669 Paku kayu 3" Inch (7 cm) 200 gram
1670 M1670 Paku kayu 3" Inch (7 cm) 26 kg
1671 M1671 Paku kayu 3" Inch (7 cm) kg
1672 M1672 Paku Kayu 4 cm kg
1673 M1673 Paku kayu 4" inch (10 cm) 26 kg
1674 M1674 Paku kayu 4" Inch 10 cm 200 gram
1675 M1675 Paku kayu 4" Inch 10 cm kg
1676 M1676 Paku Kayu 5 cm kg
1677 M1677 Paku kayu 5" Inch (12 cm) 200 gram
1678 M1678 Paku kayu 5" Inch (12 cm) 26 kg
1679 M1679 Paku kayu 5" Inch (12 cm) kg
1680 M1680 Paku Kayu 7 cm kg
V Paku Payung
1681 M1681 Paku Payung/Seng 10 cm kg
1682 M1682 Paku Payung/Seng 5 cm kg
1683 M1683 Paku Payung/Seng 7 cm kg
VI Paku Rivet
1684 M1684 Paku Rivet 3,2 mm x 11 mm 50 buah
1685 M1685 Paku Rivet 3,2 mm x 11 mm buah
1686 M1686 Paku Rivet 3,2 mm x 11 mm 1000 buah
1687 M1687 Paku Rivet 3,2 mm x 11 mm buah
1688 M1688 Paku Rivet 4 mm x 11 mm 50 buah
1689 M1689 Paku Rivet 4 mm x 11 mm buah
1690 M1690 Paku Rivet 4 mm x 12.7 mm 20 buah
1691 M1691 Paku Rivet 4 mm x 12.7 mm buah
1692 M1692 Paku Rivet 4 mm x 9.5 mm 100 buah
1693 M1693 Paku Rivet 4 mm x 9.5 mm buah
1694 M1694 Paku Rivet 4,0 mm x 11 mm 1000 buah
1695 M1695 Paku Rivet 4,0 mm x 11 mm buah
1696 M1696 Paku Rivet 4,8 mm x 11 mm 50 buah
1697 M1697 Paku Rivet 4,8 mm x 11 mm buah
1698 M1698 Paku Rivet 4,8 mm x 11 mm 500 buah
1699 M1699 Paku Rivet 4,8 mm x 11 mm buah
1700 M1700 Paku Rivet 4,8 mm x 16 mm 30 buah
1701 M1701 Paku Rivet 4,8 mm x 16 mm buah
VII Paku Triplek
1702 M1702 Paku Triplek 10 cm kg
1703 M1703 Paku Triplek 12 cm kg
1704 M1704 Paku Triplek 2 cm kg
1705 M1705 Paku Triplek 2,5 cm kg
1706 M1706 Paku Triplek 3 cm kg
1707 M1707 Paku Triplek 4 cm kg
1708 M1708 Paku Triplek 5 cm kg
1709 M1709 Paku Triplek 7 cm kg

R MATERIAL PAVING BLOCK & KANSTIN


I Asiacon Paving Block & Kanstin (K300)
1710 M1710 Car Stopper 60x15x22 cm buah
1711 M1711 Grass Block L5 40x40x8 cm buah
1712 M1712 Grass Block L8 45x30x6 cm buah
1713 M1713 Grass Block L8 45x30x8 cm buah
1714 M1714 Kanstin DKI 60x30x25x20 cm buah
1715 M1715 Kanstin Jalan 60x25x22x18 cm buah
1716 M1716 Kanstin L 40x15+15x23 buah
1717 M1717 Kanstin S 40x30x15x8 cm buah
1718 M1718 Kanstin Taman 40x20x10 cm buah
1719 M1719 Kanstin Trotoar 40x25x15x13 cm buah
1720 M1720 Kanstin Trotoar 40x28x15x13 cm buah
1721 M1721 Paving Bata 10 cm Natural (10,5x21 cm) m2 (44 buah)
1722 M1722 Paving Bata 6 cm Natural (10,5x21 cm) m2 (44 buah)
1723 M1723 Paving Bata 8 cm Natural (10,5x21 cm) m2 (44 buah)
1724 M1724 Paving Cacing 6 cm Natural (22,5x11,2 cm) m2 (39 buah)
1725 M1725 Paving Cacing 8 cm Natural (22,5x11,2 cm) m2 (39 buah)
1726 M1726 Paving Segi Enam 6 cm Natural (20x20 cm) m2 (27 buah)
1727 M1727 Paving Segi Enam 8 cm Natural (20x20 cm) m2 (27 buah)
1728 M1728 Paving Tahu 6 cm Natural (10,5x10,5 cm) m2 (88 buah)
1729 M1729 Paving Tahu 8 cm Natural (10,5x10,5 cm) m2 (88 buah)
1730 M1730 Paving Trihex 6 cm Natural (19,7x9,6 cm) m2 (39 buah)
1731 M1731 Paving Trihex 8 cm Natural (19,7x9,6 cm) m2 (39 buah)
1732 M1732 Paving Ubin Full 6 cm Natural (21x21 cm) m2 (22 buah)
1733 M1733 Paving Ubin Full 8 cm Natural (21x21 cm) m2 (22 buah)
1734 M1734 Paving Ubin Set 6 cm Natural (21x21 cm & 10,5x10,5 cm) m2 (22+5,5 buah)
1735 M1735 Topi Uskup 6 cm Natural (30x21 cm) m1 (3,3 buah)
1736 M1736 Topi Uskup 8 cm Natural (30x21 cm) m1 (3,3 buah)
II Cisangkan Paving Block & Kanstin (K300)
1737 M1737 Car Stopper 600x140x150 mm buah
85

NO KODE NAMA BARANG SATUAN MERK

A B C D E
1738 M1738 Car Stopper 600x140x210 mm buah
1739 M1739 Grass Block GB 10 45x30x10 cm m2 (7,5 buah)
1740 M1740 Grass Block GB 10.2 30x30x10 cm m2 (11 buah)
1741 M1741 Grass Block GB 6 45x30x6 cm m2 (7,5 buah)
1742 M1742 Grass Block GB 8 40x40x8 cm m2 (6,25 buah)
1743 M1743 Kanstin 200x140x210 mm buah
1744 M1744 Kanstin 200x140x300 mm buah
1745 M1745 Kanstin 600x140x210 mm buah
1746 M1746 Kanstin 600x140x300 mm buah
1747 M1747 Kanstin L 200x300x230 mm buah
1748 M1748 Kanstin L 600x300x230 mm buah
1749 M1749 Kanstin S 200x300x180 mm buah
1750 M1750 Kanstin S 600x300x180 mm buah
1751 M1751 Paving Fullpave 20x20x6 cm Natural m2 (24,5 buah)
1752 M1752 Paving Fullpave 20x20x6 cm Warna m2 (24,5 buah)
1753 M1753 Paving Fullpave 20x20x8 cm Natural m2 (24,5 buah)
1754 M1754 Paving Fullpave 20x20x8 cm Warna m2 (24,5 buah)
1755 M1755 Paving Halfpave 10x10x6 cm Natural m2 (98 buah)
1756 M1756 Paving Halfpave 10x10x6 cm Warna m2 (98 buah)
1757 M1757 Paving Halfpave 10x10x8 cm Natural m2 (98 buah)
1758 M1758 Paving Halfpave 10x10x8 cm Warna m2 (98 buah)
1759 M1759 Paving Hexagonal 20x20x6 cm Natural m2 (29 buah)
1760 M1760 Paving Hexagonal 20x20x6 cm Warna m2 (29 buah)
1761 M1761 Paving Hexagonal 20x20x8 cm Natural m2 (29 buah)
1762 M1762 Paving Hexagonal 20x20x8 cm Warna m2 (29 buah)
1763 M1763 Paving Intepave (Model Cacing) 20,6x10,2x6 cm Natural m2 (48 buah)
1764 M1764 Paving Intepave (Model Cacing) 20,6x10,2x6 cm Warna m2 (48 buah)
1765 M1765 Paving Intepave (Model Cacing) 20,6x10,2x8 cm Natural m2 (48 buah)
1766 M1766 Paving Intepave (Model Cacing) 20,6x10,2x8 cm Warna m2 (48 buah)
1767 M1767 Paving Truepave 20x10x10 cm Natural m2 (49 buah)
1768 M1768 Paving Truepave 20x10x10 cm Warna m2 (49 buah)
1769 M1769 Paving Truepave 20x10x6 cm Natural m2 (49 buah)
1770 M1770 Paving Truepave 20x10x6 cm Warna m2 (49 buah)
1771 M1771 Paving Truepave 20x10x8 cm Natural m2 (49 buah)
1772 M1772 Paving Truepave 20x10x8 cm Warna m2 (49 buah)
1773 M1773 Rectangular-pave 30x20x8 cm Natural m2 (16 buah)
1774 M1774 Rectangular-pave 30x20x8 cm Warna m2 (16 buah)
1775 M1775 Spectra-pave 30x30x6 cm Natural m2 (11 buah)
1776 M1776 Spectra-pave 30x30x8 cm Natural m2 (11 buah)
1777 M1777 Topi Uskup 6 cm (30x21 cm) Natural m2 (20 buah)
1778 M1778 Topi Uskup 6 cm (30x21 cm) Warna m2 (20 buah)
1779 M1779 Topi Uskup 8 cm (30x21 cm) Natural m2 (20 buah)
1780 M1780 Topi Uskup 8 cm (30x21 cm) Warna m2 (20 buah)
III Conbloc Paving Block (K300)
1781 M1781 Grass Block 40x20x6 cm m2 (12,5 buah)
1782 M1782 Grass Block 40x20x8 cm m2 (12,5 buah)
1783 M1783 Paving Fullpave (Cobblestone) 21x21x6 cm Natural m2 (22,5 buah)
1784 M1784 Paving Fullpave (Cobblestone) 21x21x6 cm Warna m2 (22,5 buah)
1785 M1785 Paving Fullpave (Cobblestone) 21x21x8 cm Natural m2 (22,5 buah)
1786 M1786 Paving Fullpave (Cobblestone) 21x21x8 cm Warna m2 (22,5 buah)
1787 M1787 Paving Fullpave (Cobblestone) 31x31x8 cm Natural m2 (10 buah)
1788 M1788 Paving Fullpave (Cobblestone) 31x31x8 cm Warna m2 (10 buah)
1789 M1789 Paving Halfblock 10,5x10,5x6 cm Natural m2 (90 buah)
1790 M1790 Paving Halfblock 10,5x10,5x6 cm Warna m2 (90 buah)
1791 M1791 Paving Halfblock 10,5x10,5x8 cm Natural m2 (90 buah)
1792 M1792 Paving Halfblock 10,5x10,5x8 cm Warna m2 (90 buah)
1793 M1793 Paving Intepave (Model Cacing) 22,5x11,5x6 cm Natural m2 (40 buah)
1794 M1794 Paving Intepave (Model Cacing) 22,5x11,5x6 cm Warna m2 (40 buah)
1795 M1795 Paving Intepave (Model Cacing) 22,5x11,5x8 cm Natural m2 (40 buah)
1796 M1796 Paving Intepave (Model Cacing) 22,5x11,5x8 cm Warna m2 (40 buah)
1797 M1797 Paving Truepave (Conbloc 4) 21x10,5x10 cm Natural m2 (45 buah)
1798 M1798 Paving Truepave (Conbloc 4) 21x10,5x10 cm Warna m2 (45 buah)
1799 M1799 Paving Truepave (Conbloc 4) 21x10,5x6 cm Natural m2 (45 buah)
1800 M1800 Paving Truepave (Conbloc 4) 21x10,5x6 cm Warna m2 (45 buah)
1801 M1801 Paving Truepave (Conbloc 4) 21x10,5x8 cm Natural m2 (45 buah)
1802 M1802 Paving Truepave (Conbloc 4) 21x10,5x8 cm Warna m2 (45 buah)
1803 M1803 Topi Uskup 6 cm (30x21 cm) Natural m2 (25 buah)
1804 M1804 Topi Uskup 6 cm (30x21 cm) Warna m2 (25 buah)
1805 M1805 Topi Uskup 8 cm (30x21 cm) Natural m2 (25 buah)
1806 M1806 Topi Uskup 8 cm (30x21 cm) Warna m2 (25 buah)
IV Terra Conblock & Kanstin
1807 M1807 Grass Block L5 40x40x8 cm buah
1808 M1808 Grass Block L8 45x30x6 cm buah
1809 M1809 Grass Block L8 45x30x8 cm buah
1810 M1810 Kanstin DKI 60x25x22x18 cm buah
1811 M1811 Kanstin DKI 60x30x25x20 cm buah
1812 M1812 Kanstin S 40x30x16 cm buah
1813 M1813 Kanstin Taman 40x20x10 cm buah
1814 M1814 Kanstin Taman 40x20x15x13 cm buah
1815 M1815 Kanstin Trotoar 40x25x16x13 cm buah
1816 M1816 Kanstin Trotoar 40x28x15x13 cm buah
1817 M1817 Paving Fullpave 21x21x6 cm Natural m2 (22 buah)
1818 M1818 Paving Fullpave 21x21x6 cm Warna m2 (22 buah)
86

NO KODE NAMA BARANG SATUAN MERK

A B C D E
1819 M1819 Paving Fullpave 21x21x8 cm Natural m2 (22 buah)
1820 M1820 Paving Fullpave 21x21x8 cm Warna m2 (22 buah)
1821 M1821 Paving Fullpave Set 6 cm Natural m2 (22+5,5 buah)
1822 M1822 Paving Fullpave Set 6 cm Warna m2 (22+5,5 buah)
1823 M1823 Paving Fullpave Set 8 cm Natural m2 (22+5,5 buah)
1824 M1824 Paving Fullpave Set 8 cm Warna m2 (22+5,5 buah)
1825 M1825 Paving Hallpave 10,5x10,5x6 Natural m2 (88 buah)
1826 M1826 Paving Hallpave 10,5x10,5x6 Warna m2 (88 buah)
1827 M1827 Paving Hallpave 10,5x10,5x8 Natural m2 (88 buah)
1828 M1828 Paving Hallpave 10,5x10,5x8 Warna m2 (88 buah)
1829 M1829 Paving Hexagonal 20x20x6 cm Natural m2 (25 buah)
1830 M1830 Paving Hexagonal 20x20x6 cm Warna m2 (25 buah)
1831 M1831 Paving Hexagonal 20x20x8 cm Natural m2 (25 buah)
1832 M1832 Paving Hexagonal 20x20x8 cm Warna m2 (25 buah)
1833 M1833 Paving Intepave (Model Cacing) 22,5x11,5x6 cm Natural m2 (39 buah)
1834 M1834 Paving Intepave (Model Cacing) 22,5x11,5x6 cm Warna m2 (39 buah)
1835 M1835 Paving Intepave (Model Cacing) 22,5x11,5x8 cm Natural m2 (39 buah)
1836 M1836 Paving Intepave (Model Cacing) 22,5x11,5x8 cm Warna m2 (39 buah)
1837 M1837 Paving Truepave (Model Bata) 21x10,2x6 cm Natural m2 (44 buah)
1838 M1838 Paving Truepave (Model Bata) 21x10,2x6 cm Warna m2 (44 buah)
1839 M1839 Paving Truepave (Model Bata) 21x10,2x8 cm Natural m2 (44 buah)
1840 M1840 Paving Truepave (Model Bata) 21x10,2x8 cm Warna m2 (44 buah)
1841 M1841 Topi Uskup 28x21x10,5 cm tebal 6 cm Natural m1 (3,3 buah)
1842 M1842 Topi Uskup 28x21x10,5 cm tebal 8 cm Natural m1 (3,3 buah)
1843 M1843 Trihex 19,7x9,6 cm tebal 6 cm Natural m2 (39 buah)
1844 M1844 Trihex 19,7x9,6 cm tebal 6 cm Warna m2 (39 buah)
1845 M1845 Trihex 19,7x9,6 cm tebal 8 cm Natural m2 (39 buah)
1846 M1846 Trihex 19,7x9,6 cm tebal 8 cm Warna m2 (39 buah)

S MATERIAL PINTU & JENDELA


I Daun Pintu Solid Engineering Wood
1847 M1847 Ukuran 3,5x82x210 cm Finishing Duco buah
1848 M1848 Ukuran 3,5x82x210 cm Finishing Melamic buah
1849 M1849 Ukuran 4,5x82x210 cm Finishing Duco buah
1850 M1850 Ukuran 4,5x82x210 cm Finishing Melamic buah
1851 M1851 Ukuran 4x82x210 cm Finishing Dyco buah
1852 M1852 Ukuran 4x82x210 cm Finishing Melamic buah
1853 M1853 Ukuran 5x82x210 cm Finishing Duco buah
1854 M1854 Ukuran 5x82x210 cm Finishing Melamic buah
II Kusen Aluminium Shopfront Alexindo
1855 M1855 Kusen 3" Anodized Silver m1
1856 M1856 Kusen 3" Powder Coating Coklat m1
1857 M1857 Kusen 3" Powder Coating Hitam m1
1858 M1858 Kusen 4" Anodized Silver m1
1859 M1859 Kusen 4" Powder Coating Coklat m1
1860 M1860 Kusen 4" Powder Coating Hitam m1
III Kusen Aluminium Shopfront Superex
1861 M1861 Kusen 3" Anodized Silver m1
1862 M1862 Kusen 3" Powder Coating Coklat m1
1863 M1863 Kusen 3" Powder Coating Hitam m1
1864 M1864 Kusen 4" Anodized Silver m1
1865 M1865 Kusen 4" Powder Coating Coklat m1
1866 M1866 Kusen 4" Powder Coating Hitam m1
IV Kusen Aluminium Shopfront YKK
1867 M1867 Kusen 3" Anodized Silver m1
1868 M1868 Kusen 3" Powder Coating Coklat m1
1869 M1869 Kusen 3" Powder Coating Putih m1
1870 M1870 Kusen 3" Powder Urat Kayu m1
1871 M1871 Kusen 4" Anodized Silver m1
1872 M1872 Kusen 4" Powder Coating Coklat m1
1873 M1873 Kusen 4" Powder Coating Putih m1
1874 M1874 Kusen 4" Powder Urat Kayu m1
V Kusen Double Teakwood Rangka Kayu
1875 M1875 Pintu Double Teakwood Rangka Kayu Meranti buah
1876 M1876 Pintu Double Teakwood Rangka Kayu Kamper buah
1877 M1877 Pintu Double Teakwood Rangka Kayu Kamper Samarinda buah
VI Pintu Aluminium Model Spandrel
1878 M1878 Pintu Sprandel Aluminum Double 80x200 cm buah
1879 M1879 Pintu Sprandel Aluminum Single 70x200 cm buah
1880 M1880 Pintu Sprandel Double Aluminum (Tebal) 80x200 cm buah
VII Pintu Jendela Kayu Jati
1881 M1881 Daun Jendela Kayu Jati 3x10 m1
1882 M1882 Daun Pintu Kayu Jati buah
1883 M1883 Kusen Kayu Jati 4x10 m1
1884 M1884 Kusen Kayu Jati 6x12 m1
1885 M1885 Kusen Kayu Jati 6x15 m1
1886 M1886 Lubang Angin Kayu Jati buah
VIII Pintu Jendela Kayu Kamper Samarinda
1887 M1887 Daun Jendela Kayu Kamper Samarinda 3x10 m1
1888 M1888 Daun Pintu Kayu Kamper Samarinda buah
1889 M1889 Kusen Kayu Kamper Samarinda 4x10 m1
1890 M1890 Kusen Kayu Kamper Samarinda 6x12 m1
1891 M1891 Kusen Kayu Kamper Samarinda 6x15 m1
87

NO KODE NAMA BARANG SATUAN MERK

A B C D E
1892 M1892 Lubang Angin Kamper Samarinda buah
IX Pintu Jendela Kayu Mahoni
1893 M1893 Kusen Kayu Mahoni 6x15 m1
1894 M1894 Kusen Kayu Mahoni 6x12 m1
1895 M1895 Kusen Kayu Mahoni 4x10 m1
1896 M1896 Daun Jendela Kayu Mahoni 3x10 m1
1897 M1897 Daun Pintu Kayu Mahoni buah
1898 M1898 Lubang Angin Kayu Mahoni buah
X Pintu Jendela Kayu Meranti
1899 M1899 Daun Jendela Kayu Meranti 3x10 m1
1900 M1900 Daun Pintu Kayu Meranti buah
1901 M1901 Kusen Kayu Meranti 4x10 m1
1902 M1902 Kusen Kayu Meranti 6x12 m1
1903 M1903 Kusen Kayu Meranti 6x15 m1
1904 M1904 Lubang Angin Kayu Meranti buah

T MATERIAL PIPA PPR


I Pipa PP-R Rucika Green (Wavin Tigris) PN 10
(Untuk Air Dingin Bertekanan)
1905 M1905 Pipa PPR Rucika Green 1" (32mm) - 4 meter batang
1906 M1906 Pipa PPR Rucika Green 1" (32mm) m
1907 M1907 Pipa PPR Rucika Green 1/2" (20mm) - 4 meter batang
1908 M1908 Pipa PPR Rucika Green 1/2" (20mm) m
1909 M1909 Pipa PPR Rucika Green 1-1/2" (50mm) - 4 meter batang
1910 M1910 Pipa PPR Rucika Green 1-1/2" (50mm) m
1911 M1911 Pipa PPR Rucika Green 1-1/4" (40mm) - 4 meter batang
1912 M1912 Pipa PPR Rucika Green 1-1/4" (40mm) m
1913 M1913 Pipa PPR Rucika Green 2" (63mm) - 4 meter batang
1914 M1914 Pipa PPR Rucika Green 2" (63mm) m
1915 M1915 Pipa PPR Rucika Green 2-1/2" (75mm) - 4 meter batang
1916 M1916 Pipa PPR Rucika Green 2-1/2" (75mm) m
1917 M1917 Pipa PPR Rucika Green 3" (90mm) - 4 meter batang
1918 M1918 Pipa PPR Rucika Green 3" (90mm) m
1919 M1919 Pipa PPR Rucika Green 3/4" (25mm) - 4 meter batang
1920 M1920 Pipa PPR Rucika Green 3/4" (25mm) m
1921 M1921 Pipa PPR Rucika Green 4" (110mm) - 4 meter batang
1922 M1922 Pipa PPR Rucika Green 4" (110mm) m
1923 M1923 Pipa PPR Rucika Green 5" (125mm) - 4 meter batang
1924 M1924 Pipa PPR Rucika Green 5" (125mm) m
1925 M1925 Pipa PPR Rucika Green 6" (160mm) - 4 meter batang
1926 M1926 Pipa PPR Rucika Green 6" (160mm) m
II Pipa PP-R Rucika Green (Wavin Tigris) PN 16
(Untuk Air Dingin & Air Panas Bertekanan)
1927 M1927 Pipa PPR Rucika Green 1" (32mm) - 4 meter batang
1928 M1928 Pipa PPR Rucika Green 1" (32mm) m
1929 M1929 Pipa PPR Rucika Green 1/2" (20mm) - 4 meter batang
1930 M1930 Pipa PPR Rucika Green 1/2" (20mm) m
1931 M1931 Pipa PPR Rucika Green 1-1/2" (50mm) - 4 meter batang
1932 M1932 Pipa PPR Rucika Green 1-1/2" (50mm) m
1933 M1933 Pipa PPR Rucika Green 1-1/4" (40mm) - 4 meter batang
1934 M1934 Pipa PPR Rucika Green 1-1/4" (40mm) m
1935 M1935 Pipa PPR Rucika Green 2" (63mm) - 4 meter batang
1936 M1936 Pipa PPR Rucika Green 2" (63mm) m
1937 M1937 Pipa PPR Rucika Green 2-1/2" (75mm) - 4 meter batang
1938 M1938 Pipa PPR Rucika Green 2-1/2" (75mm) m
1939 M1939 Pipa PPR Rucika Green 3" (90mm) - 4 meter batang
1940 M1940 Pipa PPR Rucika Green 3" (90mm) m
1941 M1941 Pipa PPR Rucika Green 3/4" (25mm) - 4 meter batang
1942 M1942 Pipa PPR Rucika Green 3/4" (25mm) m
1943 M1943 Pipa PPR Rucika Green 4" (110mm) - 4 meter batang
1944 M1944 Pipa PPR Rucika Green 4" (110mm) m
1945 M1945 Pipa PPR Rucika Green 5" (125mm) - 4 meter batang
1946 M1946 Pipa PPR Rucika Green 5" (125mm) m
1947 M1947 Pipa PPR Rucika Green 6" (160mm) - 4 meter batang
1948 M1948 Pipa PPR Rucika Green 6" (160mm) m
III Pipa PP-R Rucika Green (Wavin Tigris) PN 20
(Untuk Air Panas Bertekanan)
1949 M1949 Pipa PPR Rucika Green 1" (32mm) - 4 meter batang
1950 M1950 Pipa PPR Rucika Green 1" (32mm) m
1951 M1951 Pipa PPR Rucika Green 1/2" (20mm) - 4 meter batang
1952 M1952 Pipa PPR Rucika Green 1/2" (20mm) m
1953 M1953 Pipa PPR Rucika Green 1-1/2" (50mm) - 4 meter batang
1954 M1954 Pipa PPR Rucika Green 1-1/2" (50mm) m
1955 M1955 Pipa PPR Rucika Green 1-1/4" (40mm) - 4 meter batang
1956 M1956 Pipa PPR Rucika Green 1-1/4" (40mm) m
1957 M1957 Pipa PPR Rucika Green 2" (63mm) - 4 meter batang
1958 M1958 Pipa PPR Rucika Green 2" (63mm) m
1959 M1959 Pipa PPR Rucika Green 2-1/2" (75mm) - 4 meter batang
1960 M1960 Pipa PPR Rucika Green 2-1/2" (75mm) m
1961 M1961 Pipa PPR Rucika Green 3" (90mm) - 4 meter batang
1962 M1962 Pipa PPR Rucika Green 3" (90mm) m
1963 M1963 Pipa PPR Rucika Green 3/4" (25mm) - 4 meter batang
1964 M1964 Pipa PPR Rucika Green 3/4" (25mm) m
88

NO KODE NAMA BARANG SATUAN MERK

A B C D E
1965 M1965 Pipa PPR Rucika Green 4" (110mm) - 4 meter batang
1966 M1966 Pipa PPR Rucika Green 4" (110mm) m
1967 M1967 Pipa PPR Rucika Green 5" (125mm) - 4 meter batang
1968 M1968 Pipa PPR Rucika Green 5" (125mm) m
1969 M1969 Pipa PPR Rucika Green 6" (160mm) - 4 meter batang
1970 M1970 Pipa PPR Rucika Green 6" (160mm) m

U MATERIAL PIPA PVC


I Pipa PVC Intilon AW
1971 M1971 1" - (32 mm) - 4 meter batang
1972 M1972 1" - (32 mm) m
1973 M1973 1/2" - (22 mm) - 4 meter batang
1974 M1974 1/2" - (22 mm) m
1975 M1975 10" - (267 mm) - 4 meter batang
1976 M1976 10" - (267 mm) m
1977 M1977 1-1/2" - (48 mm) - 4 meter batang
1978 M1978 1-1/2" - (48 mm) m
1979 M1979 1-1/4" - (42 mm) - 4 meter batang
1980 M1980 1-1/4" - (42 mm) m
1981 M1981 12" - (318 mm) - 4 meter batang
1982 M1982 12" - (318 mm) m
1983 M1983 2" - (60 mm) - 4 meter batang
1984 M1984 2" - (60 mm) m
1985 M1985 2-1/2" - (76 mm) - 4 meter batang
1986 M1986 2-1/2" - (76 mm) m
1987 M1987 3" - (89 mm) - 4 meter batang
1988 M1988 3" - (89 mm) m
1989 M1989 3/4" - (26 mm) - 4 meter batang
1990 M1990 3/4" - (26 mm) m
1991 M1991 4" - (114 mm) - 4 meter batang
1992 M1992 4" - (114 mm) m
1993 M1993 5" - (140 mm) - 4 meter batang
1994 M1994 5" - (140 mm) m
1995 M1995 6" - (165 mm) - 4 meter batang
1996 M1996 6" - (165 mm) m
1997 M1997 8" - (216 mm) - 4 meter batang
1998 M1998 8" - (216 mm) m
II Pipa PVC Intilon D
1999 M1999 1" - (32 mm) - 4 meter batang
2000 M2000 1" - (32 mm) m
2001 M2001 1/2" - (22 mm) - 4 meter batang
2002 M2002 1/2" - (22 mm) m
2003 M2003 10" - (267 mm) - 4 meter batang
2004 M2004 10" - (267 mm) m
2005 M2005 1-1/2" - (48 mm) - 4 meter batang
2006 M2006 1-1/2" - (48 mm) m
2007 M2007 1-1/4" - (42 mm) - 4 meter batang
2008 M2008 1-1/4" - (42 mm) m
2009 M2009 12" - (318 mm) - 4 meter batang
2010 M2010 12" - (318 mm) m
2011 M2011 2" - (60 mm) - 4 meter batang
2012 M2012 2" - (60 mm) m
2013 M2013 2-1/2" - (76 mm) - 4 meter batang
2014 M2014 2-1/2" - (76 mm) m
2015 M2015 3" - (89 mm) - 4 meter batang
2016 M2016 3" - (89 mm) m
2017 M2017 3/4" - (26 mm) - 4 meter batang
2018 M2018 3/4" - (26 mm) m
2019 M2019 4" - (114 mm) - 4 meter batang
2020 M2020 4" - (114 mm) m
2021 M2021 5" - (140 mm) - 4 meter batang
2022 M2022 5" - (140 mm) m
2023 M2023 6" - (165 mm) - 4 meter batang
2024 M2024 6" - (165 mm) m
2025 M2025 8" - (216 mm) - 4 meter batang
2026 M2026 8" - (216 mm) m
III Pipa PVC Pralon AW
2027 M2027 1" - (32 mm) - 4 meter batang
2028 M2028 1" - (32 mm) m
2029 M2029 1/2" - (22 mm) - 4 meter batang
2030 M2030 1/2" - (22 mm) m
2031 M2031 10" - (267 mm) - 4 meter batang
2032 M2032 10" - (267 mm) m
2033 M2033 1-1/2" - (48 mm) - 4 meter batang
2034 M2034 1-1/2" - (48 mm) m
2035 M2035 1-1/4" - (42 mm) - 4 meter batang
2036 M2036 1-1/4" - (42 mm) m
2037 M2037 12" - (318 mm) - 4 meter batang
2038 M2038 12" - (318 mm) m
2039 M2039 2" - (60 mm) - 4 meter batang
2040 M2040 2" - (60 mm) m
2041 M2041 2-1/2" - (76 mm) - 4 meter batang
2042 M2042 2-1/2" - (76 mm) m
89

NO KODE NAMA BARANG SATUAN MERK

A B C D E
2043 M2043 3" - (89 mm) - 4 meter batang
2044 M2044 3" - (89 mm) m
2045 M2045 3/4" - (26 mm) - 4 meter batang
2046 M2046 3/4" - (26 mm) m
2047 M2047 4" - (114 mm) - 4 meter batang
2048 M2048 4" - (114 mm) m
2049 M2049 5" - (140 mm) - 4 meter batang
2050 M2050 5" - (140 mm) m
2051 M2051 6" - (165 mm) - 4 meter batang
2052 M2052 6" - (165 mm) m
2053 M2053 8" - (216 mm) - 4 meter batang
2054 M2054 8" - (216 mm) m
IV Pipa PVC Pralon D
2055 M2055 1" - (32 mm) - 4 meter batang
2056 M2056 1" - (32 mm) m
2057 M2057 1/2" - (22 mm) - 4 meter batang
2058 M2058 1/2" - (22 mm) m
2059 M2059 10" - (267 mm) - 4 meter batang
2060 M2060 10" - (267 mm) m
2061 M2061 1-1/2" - (48 mm) - 4 meter batang
2062 M2062 1-1/2" - (48 mm) m
2063 M2063 1-1/4" - (42 mm) - 4 meter batang
2064 M2064 1-1/4" - (42 mm) m
2065 M2065 12" - (318 mm) - 4 meter batang
2066 M2066 12" - (318 mm) m
2067 M2067 2" - (60 mm) - 4 meter batang
2068 M2068 2" - (60 mm) m
2069 M2069 2-1/2" - (76 mm) - 4 meter batang
2070 M2070 2-1/2" - (76 mm) m
2071 M2071 3" - (89 mm) - 4 meter batang
2072 M2072 3" - (89 mm) m
2073 M2073 3/4" - (26 mm) - 4 meter batang
2074 M2074 3/4" - (26 mm) m
2075 M2075 4" - (114 mm) - 4 meter batang
2076 M2076 4" - (114 mm) m
2077 M2077 5" - (140 mm) - 4 meter batang
2078 M2078 5" - (140 mm) m
2079 M2079 6" - (165 mm) - 4 meter batang
2080 M2080 6" - (165 mm) m
2081 M2081 8" - (216 mm) - 4 meter batang
2082 M2082 8" - (216 mm) m
V Pipa PVC Rucika Standard AW
2083 M2083 1" - (32 mm) - 4 meter batang
2084 M2084 1" - (32 mm) m
2085 M2085 1/2" - (22 mm) - 4 meter batang
2086 M2086 1/2" - (22 mm) m
2087 M2087 10" - (267 mm) - 4 meter batang
2088 M2088 10" - (267 mm) m
2089 M2089 1-1/2" - (48 mm) - 4 meter batang
2090 M2090 1-1/2" - (48 mm) m
2091 M2091 1-1/4" - (42 mm) - 4 meter batang
2092 M2092 1-1/4" - (42 mm) m
2093 M2093 12" - (318 mm) - 4 meter batang
2094 M2094 12" - (318 mm) m
2095 M2095 2" - (60 mm) - 4 meter batang
2096 M2096 2" - (60 mm) m
2097 M2097 2-1/2" - (76 mm) - 4 meter batang
2098 M2098 2-1/2" - (76 mm) m
2099 M2099 3" - (89 mm) - 4 meter batang
2100 M2100 3" - (89 mm) m
2101 M2101 3/4" - (26 mm) - 4 meter batang
2102 M2102 3/4" - (26 mm) m
2103 M2103 4" - (114 mm) - 4 meter batang
2104 M2104 4" - (114 mm) m
2105 M2105 5" - (140 mm) - 4 meter batang
2106 M2106 5" - (140 mm) m
2107 M2107 6" - (165 mm) - 4 meter batang
2108 M2108 6" - (165 mm) m
2109 M2109 8" - (216 mm) - 4 meter batang
2110 M2110 8" - (216 mm) m
VI Pipa PVC Rucika Standard D
2111 M2111 1" - (32 mm) - 4 meter batang
2112 M2112 1" - (32 mm) m
2113 M2113 1/2" - (22 mm) - 4 meter batang
2114 M2114 1/2" - (22 mm) m
2115 M2115 10" - (267 mm) - 4 meter batang
2116 M2116 10" - (267 mm) m
2117 M2117 1-1/2" - (48 mm) - 4 meter batang
2118 M2118 1-1/2" - (48 mm) m
2119 M2119 1-1/4" - (42 mm) - 4 meter batang
2120 M2120 1-1/4" - (42 mm) m
2121 M2121 12" - (318 mm) - 4 meter batang
2122 M2122 12" - (318 mm) m
90

NO KODE NAMA BARANG SATUAN MERK

A B C D E
2123 M2123 2" - (60 mm) - 4 meter batang
2124 M2124 2" - (60 mm) m
2125 M2125 2-1/2" - (76 mm) - 4 meter batang
2126 M2126 2-1/2" - (76 mm) m
2127 M2127 3" - (89 mm) - 4 meter batang
2128 M2128 3" - (89 mm) m
2129 M2129 3/4" - (26 mm) - 4 meter batang
2130 M2130 3/4" - (26 mm) m
2131 M2131 4" - (114 mm) - 4 meter batang
2132 M2132 4" - (114 mm) m
2133 M2133 5" - (140 mm) - 4 meter batang
2134 M2134 5" - (140 mm) m
2135 M2135 6" - (165 mm) - 4 meter batang
2136 M2136 6" - (165 mm) m
2137 M2137 8" - (216 mm) - 4 meter batang
2138 M2138 8" - (216 mm) m

V MATERIAL PLAFOND & PARTISI


I Aplus
2139 M2139 Aplus G-Strength 9 mm 1200x2400mm lembar
2140 M2140 Aplus Sound 12 mm 1200x2400mm lembar
2141 M2141 Aplus Standard 12 mm 1200x2400mm lembar
2142 M2142 Aplus Standard 9 mm 1200x2400mm lembar
2143 M2143 Aplus Water Resitance 9 mm 1200x2400mm lembar
II Conwood Ceiling
2144 M2144 Ceiling Border 50x3050x11mm buah
2145 M2145 Conwood Lath 3” Cut 76x3050x11mm buah
2146 M2146 Conwood Lath 3” UG 1200x2400x8mm buah
2147 M2147 Conwood Lath 3” UG 600x1200x8mm buah
2148 M2148 Conwood Lath 4” Cut 100x3050x11mm buah
III Conwood Wall
2149 M2149 Conwood Decorative Panel 600x1200x11mm buah
2150 M2150 Conwood Lap Siding 6” BG 152x3050x11mm buah
2151 M2151 Conwood Lap Siding 8” G1 200x3050x11mm buah
2152 M2152 Conwood Lap Siding 8” G2 200x3050x11mm buah
2153 M2153 Conwood Lap Siding 8” GO 200x3050x11mm buah
2154 M2154 Cwd. Decor/n Panel *V Groove 305x3050x11mm buah
IV Elephant
2155 M2155 Elephant Fire Resistance 9 mm 1200x2400mm lembar
2156 M2156 Elephant Moisture Shield 9 mm 1200x2400mm lembar
2157 M2157 Elephant Standard 12 mm 1200x2400mm lembar
2158 M2158 Elephant Standard 9 mm 1200x2400mm lembar
V Eternit Djabesmen
2159 M2159 Eternit Djabesmen 1500x1050mm buah
2160 M2160 Eternit Djabesmen 1800x1050mm buah
2161 M2161 Eternit Djabesmen 210 x 105 cm buah
2162 M2162 Eternit Djabesmen 240 x 105 cm buah
2163 M2163 Eternit Djabesmen 300 x 105 cm buah
2164 M2164 Eternit Djbesmen 270 x 105 cm buah
VI GRC Aplus
2165 M2165 GRC Board Aplus 10 mm 1220x2440mm lembar
2166 M2166 GRC Board Aplus 15 mm 1220x2440mm lembar
2167 M2167 GRC Board Aplus 3.5 mm 1220x2440mm lembar
2168 M2168 GRC Board Aplus 6 mm 1220x2440mm lembar
2169 M2169 GRC Board Aplus 8 mm 1220x2440mm lembar
VII GRC Board
2170 M2170 GRC Board 10 mm 1220x2440mm lembar
2171 M2171 GRC Board 4 mm 1220x2440mm lembar
2172 M2172 GRC Board 6 mm 1220x2440mm lembar
2173 M2173 GRC Board 8 mm 1220x2440mm lembar
VIII GRC Super Panel
2174 M2174 GRC Board Super Panel 12 mm 1220x2440mm lembar
2175 M2175 GRC Board Super panel 15 mm 1220x2440mm lembar
2176 M2176 GRC Board Super Panel 20 mm 1220x2440mm lembar
2177 M2177 GRC Board Super Panel 9 mm 1220x2440mm lembar
IX Gyproc
2178 M2178 Gyproc Standard 12 mm 1200x2400mm lembar
2179 M2179 Gyproc Standard 9 mm 1200x2400mm lembar
2180 M2180 Gyproc Water Resistance (Aqualine) 9 mm 1200x2400mm lembar
X Jayaboard
2181 M2181 Jayaboard Firestop 13 mm 1200x2400mm lembar
2182 M2182 Jayaboard Heatstop 9 mm 1200x2400mm lembar
2183 M2183 Jayaboard Indoboard 9 mm 1200x2400mm lembar
2184 M2184 Jayaboard Sheetrock 12 mm 1200x2400mm lembar
2185 M2185 Jayaboard Sheetrock 6,5 mm 1200x2400mm lembar
2186 M2186 Jayaboard Sheetrock 9 mm 1200x2400mm lembar
2187 M2187 Jayaboard Wet Area Optimum 13 mm 1200x2400mm lembar
2188 M2188 Jayaboard Wet Area Optimum 9 mm 1200x2400mm lembar
2189 M2189 Jayaboard Jayaakustik 9 mm 600x600mm lembar
2190 M2190 Jayaboard Jayaakustik 9 mm 600x1200mm lembar
2191 M2191 Jayaboard Jayaakustik 12 mm 600x600mm lembar
2192 M2192 Jayaboard Jayaakustik 12 mm 600x1200mm lembar
XI Kalsiboard
91

NO KODE NAMA BARANG SATUAN MERK

A B C D E
2193 M2193 KalsiBoard Ling 3,5 mm 1200x2400mm lembar
2194 M2194 KalsiBoard Ling 3,5 mm 1200x2400mm lembar
2195 M2195 KalsiBoard Ling 4,5 mm 1200x2400mm lembar
2196 M2196 KalsiBoard Ling 4,5 mm 1200x2400mm lembar
2197 M2197 KalsiBoard Ling 6 mm 1200x2400mm lembar
2198 M2198 KalsiBoard Ling 6 mm 1200x2400mm lembar
2199 M2199 KalsiBoard Ling 6 mm 1200x2700mm lembar
2200 M2200 KalsiBoard Ling 6 mm 1200x3000mm lembar
2201 M2201 KalsiClad 10 mm 1200x2400mm lembar
2202 M2202 KalsiClad 10 mm 1200x2400mm lembar
2203 M2203 KalsiClad 10 mm 1200x2700mm lembar
2204 M2204 KalsiClad 10 mm 1200x3000mm lembar
2205 M2205 KalsiClad 12 mm 1200x2400mm lembar
2206 M2206 KalsiClad 12 mm 1200x2400mm lembar
2207 M2207 KalsiClad 12 mm 1200x2700mm lembar
2208 M2208 KalsiClad 12 mm 1200x3000mm lembar
2209 M2209 KalsiFloor 20 mm 1200x2400mm lembar
2210 M2210 KalsiPart 8 mm 1200x2400mm lembar
2211 M2211 KalsiPart 8 mm 1200x2400mm lembar
2212 M2212 KalsiPart 8 mm 1200x2700mm lembar
2213 M2213 KalsiPart 8 mm 1200x3000mm lembar
2214 M2214 KalsiQua 8 mm 1200x2400mm lembar
2215 M2215 KalsiRata 3 mm 1000x1000mm lembar
2216 M2216 KalsiRata 3 mm 1000x2000mm lembar
2217 M2217 KalsiRata 3 mm 500x2000mm lembar
XII Knauf
2218 M2218 Knauf Moisture Shield 12 mm 1200x2400mm lembar
2219 M2219 Knauf Moisture Shield 9 mm 1200x2400mm lembar
2220 M2220 Knauf Standard 12 mm 1200x2400mm lembar
2221 M2221 Knauf Standard 9 mm 1200x2400mm lembar
XIII Shunda Plafond PVC
2222 M2222 Esbeen Plafon PVC, 1000x20x7mm buah
2223 M2223 Plafon PVC Alica Interior Corak Kayu, 1000x20x8mm buah
2224 M2224 Plafonesia PG106, 1000x20x8mm buah
2225 M2225 Plafonesia PG1117, 1000x20x8mm buah
2226 M2226 Plafonesia PG1120, 1000x20x8mm buah
2227 M2227 Plafonesia PP005, 1500x20x8mm buah
2228 M2228 Plafonesia PS009, 1000x20x7mm buah
2229 M2229 Plafonesia PS014, 1000x20x7mm buah
2230 M2230 Plafonesia PS015, 1000x20x7mm buah
2231 M2231 Shunda Plafon Kingfon K-9109, 1000x30x8mm buah
2232 M2232 Shunda Plafon Kingfon K-9208, 1000x30x8mm buah
2233 M2233 Shunda Plafon Kingfon K-9252, 1000x30x8mm buah
2234 M2234 Shunda Plafon PL 08.001, 1000x20x8mm buah
2235 M2235 Shunda Plafon PVC Dark Teak Wood, 3000x20x10mm buah
2236 M2236 Shunda Plafon PVC Dark Teak Wood, 5000x20x10mm buah
2237 M2237 Shunda Plafon PVC K-9151, 1000x30x8mm buah
2238 M2238 Shunda Plafon Silver Gold Flowers, 3000x25x7mm buah
2239 M2239 Shunda Plafon Silver Wood Linears, 4000x20x8mm buah
2240 M2240 Upton Plafon PVC, 1000x20x8mm buah
2241 M2241 Wifon Plafon PVC, 1000x20x8mm buah
XIV Versaboard
2242 M2242 Versaboard 4 mm 1200x240mm lembar
2243 M2243 Versaboard 6 mm 1200x2400mm lembar
2244 M2244 Versaboard 9 mm 1200x2400mm lembar

W MATERIAL SEMEN & MORTAR


I Mortar MU
2245 M2245 MU-100 Plester Premium 40 kg
2246 M2246 MU-100 Plester Premium kg
2247 M2247 MU-200 Acian Plester dan Beton 5 kg
2248 M2248 MU-200 Acian Plester dan Beton 40 kg
2249 M2249 MU-200 Acian Plester dan Beton kg
2250 M2250 MU-270 Acian Putih 25 kg
2251 M2251 MU-270 Acian Putih kg
2252 M2252 MU-300 Pasangan Bata 40 kg
2253 M2253 MU-300 Pasangan Bata kg
2254 M2254 MU-301 Pas Bata dan Plester 10 kg
2255 M2255 MU-301 Pas Bata dan Plester 40 kg
2256 M2256 MU-301 Pas Bata dan Plester kg
2257 M2257 MU-380 Perekat Bata Ringan 5 kg
2258 M2258 MU-380 Perekat Bata Ringan 40 kg
2259 M2259 MU-380 Perekat Bata Ringan kg
2260 M2260 MU-400 Perekat Keramik Dinding 5 kg
2261 M2261 MU-400 Perekat Keramik Dinding kg
2262 M2262 MU-408 Color Fill kg
2263 M2263 MU-408 Color Kitchen kg
2264 M2264 MU-408 Color Outdoor kg
2265 M2265 MU-408 Power Bathroom kg
2266 M2266 MU-408 Power Pool kg
2267 M2267 MU-410 Self Leveling Floor 25 kg
2268 M2268 MU-410 Self Leveling Floor kg
2269 M2269 MU-440 Perata Lantai 40 kg
92

NO KODE NAMA BARANG SATUAN MERK

A B C D E
2270 M2270 MU-440 Perata Lantai kg
2271 M2271 Mu-445 Perata Lantai Premium 40 kg
2272 M2272 Mu-445 Perata Lantai Premium kg
2273 M2273 MU-450 Perekat Keramik Lantai 5 kg
2274 M2274 MU-450 Perekat Keramik Lantai 40 kg
2275 M2275 MU-450 Perekat Keramik Lantai kg
2276 M2276 MU-460 Perekat Keramik Daerah Basah 25 kg
2277 M2277 MU-460 Perekat Keramik Daerah Basah kg
2278 M2278 MU-470 White Tile Addesive 25 kg
2279 M2279 MU-470 White Tile Addesive kg
2280 M2280 MU-480 Perekat Keramik Di Atas Keramik 5 kg
2281 M2281 MU-480 Perekat Keramik Di Atas Keramik kg
2282 M2282 MU-500 Perekat Mortar dan Beton 2 kg
2283 M2283 MU-500 Perekat Mortar dan Beton kg
2284 M2284 MU-600 Pelapis Kedap Air 3 kg
2285 M2285 MU-600 Pelapis Kedap Air 30 kg
2286 M2286 MU-600 Pelapis Kedap Air kg
2287 M2287 MU-700 Floor Hardener 25 kg
2288 M2288 MU-700 Floor Hardener kg
2289 M2289 MU-800 Non-Shrink Grout 40 kg
2290 M2290 MU-800 Non-Shrink Grout kg
2291 M2291 MU-830 Perbaikan Permukaan Beton 40 kg
2292 M2292 MU-830 Perbaikan Permukaan Beton kg
2293 M2293 MU-840 Finish Coat Repair 25 kg
2294 M2294 MU-840 Finish Coat Repair kg
II Semen PC & PCC
2295 M2295 Semen Batu Raja 40 Kg
2296 M2296 Semen Batu Raju 50 Kg
2297 M2297 Semen Batu Raju kg
2298 M2298 Semen Bima 40 Kg
2299 M2299 Semen Bima 50 Kg
2300 M2300 Semen Bima kg
2301 M2301 Semen Garuda 40 Kg
2302 M2302 Semen Garuda 50 Kg
2303 M2303 Semen Garuda kg
2304 M2304 Semen Gresik 40 Kg
2305 M2305 Semen Gresik 50 Kg
2306 M2306 Semen Gresik kg
2307 M2307 Semen Holcim 40 Kg
2308 M2308 Semen Holcim 50 Kg
2309 M2309 Semen Holcim kg
2310 M2310 Semen Jakarta 40 Kg
2311 M2311 Semen Jakarta 50 Kg
2312 M2312 Semen Jakarta kg
2313 M2313 Semen Merah Putih 40 Kg
2314 M2314 Semen Merah Putih 50 Kg
2315 M2315 Semen Merah Putih kg
2316 M2316 Semen Padang 40 Kg
2317 M2317 Semen Padang 50 Kg
2318 M2318 Semen Padang kg
2319 M2319 Semen Tiga Roda 40 Kg
2320 M2320 Semen Tiga Roda 50 Kg
2321 M2321 Semen Tiga Roda kg
III Semen Putih
2322 M2322 Semen Putih Gresik 40 kg
2323 M2323 Semen Putih Gresik kg
2324 M2324 Semen Putih Tiga Roda 40 kg
2325 M2325 Semen Putih Tiga Roda kg
2326 M2326 Semen Putih Tiga Roda White Mortar 40 kg
2327 M2327 Semen Putih Tiga Roda White Mortar kg

X MATERIAL TIANG PANCANG


I Tiang Pancang Segi Empat
2328 M2328 20 x 20 (4D10 – 3 meter) m1
2329 M2329 20 x 20 (4D10 – 6 meter) m1
2330 M2330 20 x 20 (4D13 – 3 meter) m1
2331 M2331 20 x 20 (4D13 – 6 meter) m1
2332 M2332 25 x 25 (4D13 – 3 meter) m1
2333 M2333 25 x 25 (4D13 – 6 meter) m1
II Tiang Pancang Segi Tiga
2334 M2334 28 x 28 (3D10 – 3 meter) m1
2335 M2335 28 x 28 (3D10 – 6 meter) m1
2336 M2336 32 x 32 (3D10 – 3 meter) m1
2337 M2337 32 x 32 (3D10 – 6 meter) m1

Y MATERIAL U-DITCH & BOX CULVERT


I Asiacon Box Culvert
2338 M2338 1000 x 1000 x 1000 mm
2339 M2339 1200 x 1200 x 1000 mm
2340 M2340 1500 x 1500 x 1000 mm
2341 M2341 2000 x 2000 x 1000 mm
2342 M2342 400 x 400 x 1000 mm
2343 M2343 500 x 500 x 1000 mm
93

NO KODE NAMA BARANG SATUAN MERK

A B C D E
2344 M2344 600 x 600 x 1000 mm
2345 M2345 800 x 800 x 1000 mm
II Asiacon Cover U-Ditch
2346 M2346 Tutup U 100 @60 cm HD (Heavy Duty)
2347 M2347 Tutup U 120 @60 cm HD (Heavy Duty)
2348 M2348 Tutup U 140 @60 cm HD (Heavy Duty)
2349 M2349 Tutup U 30 @60 cm HD (Heavy Duty)
2350 M2350 Tutup U 40 @60 cm HD (Heavy Duty)
2351 M2351 Tutup U 50 @60 cm HD (Heavy Duty)
2352 M2352 Tutup U 60 @60 cm HD (Heavy Duty)
2353 M2353 Tutup U 60 @60 cm LD (Light Duty)
2354 M2354 Tutup U 80 @60 cm HD (Heavy Duty)
III Asiacon U-Ditch
2355 M2355 1000 x 1000 x 1200 mm
2356 M2356 1000 x 1200 x 1200 mm
2357 M2357 1200 x 1200 x 1200 mm
2358 M2358 1400 x 1400 x 1200 mm
2359 M2359 300 x 300 x 1200 mm
2360 M2360 300 x 400 x 1200 mm
2361 M2361 300 x 500 x 1200 mm
2362 M2362 400 x 400 x 1200 mm
2363 M2363 400 x 500 x 1200 mm
2364 M2364 400 x 600 x 1200 mm
2365 M2365 500 x 500 x 1200 mm
2366 M2366 500 x 600 x 1200 mm
2367 M2367 500 x 700 x 1200 mm
2368 M2368 600 x 600 x 1200 mm
2369 M2369 600 x 700 x 1200 mm
2370 M2370 600 x 800 x 1200 mm
2371 M2371 800 x 1000 x 1200 mm
2372 M2372 800 x 800 x 1200 mm
IV Megacon Beton Box Culvert
2373 M2373 1000 x 1000 x 1000 mm buah
2374 M2374 1200 x 1200 x 1000 mm buah
2375 M2375 1500 x 1500 x 1000 mm buah
2376 M2376 1600 x 1600 x 1000 mm buah
2377 M2377 2000 x 2000 x 1000 mm buah
2378 M2378 400 x 400 x 1000 mm buah
2379 M2379 500 x 500 x 1000 mm buah
2380 M2380 600 x 600 x 1000 mm buah
2381 M2381 800 x 800 x 1000 mm buah
V Megacon Beton Cover U-Ditch
2382 M2382 Tutup U 100 @60 cm HD (Heavy Duty) buah
2383 M2383 Tutup U 100 @60 cm LD (Light Duty) buah
2384 M2384 Tutup U 120 @60 cm HD (Heavy Duty) buah
2385 M2385 Tutup U 140 @60 cm HD (Heavy Duty) buah
2386 M2386 Tutup U 30 @60 cm HD (Heavy Duty) buah
2387 M2387 Tutup U 40 @60 cm HD (Heavy Duty) buah
2388 M2388 Tutup U 40 @60 cm LD (Light Duty) buah
2389 M2389 Tutup U 50 @60 cm HD (Heavy Duty) buah
2390 M2390 Tutup U 50 @60 cm LD (Light Duty) buah
2391 M2391 Tutup U 60 @60 cm HD (Heavy Duty) buah
2392 M2392 Tutup U 60 @60 cm LD (Light Duty) buah
2393 M2393 Tutup U 80 @60 cm HD (Heavy Duty) buah
2394 M2394 Tutup U 80 @60 cm LD (Light Duty) buah
VI Megacon Beton U-Ditch
2395 M2395 1000 x 1000 x 1200 mm buah
2396 M2396 1000 x 1200 x 1200 mm buah
2397 M2397 1200 x 1200 x 1200 mm buah
2398 M2398 1200 x 1400 x 1200 mm buah
2399 M2399 1400 x 1400 x 1200 mm buah
2400 M2400 300 x 300 x 1200 mm buah
2401 M2401 300 x 400 x 1200 mm buah
2402 M2402 300 x 500 x 1200 mm buah
2403 M2403 400 x 400 x 1200 mm buah
2404 M2404 400 x 600 x 1200 mm buah
2405 M2405 500 x 500 x 1200 mm buah
2406 M2406 500 x 600 x 1200 mm buah
2407 M2407 500 x 700 x 1200 mm buah
2408 M2408 600 x 600 x 1200 mm buah
2409 M2409 600 x 700 x 1200 mm buah
2410 M2410 600 x 800 x 1200 mm buah
2411 M2411 800 x 1000 x 1200 mm buah
2412 M2412 800 x 800 x 1200 mm buah
VII Terra Conblock Box Culvert
2413 M2413 1000 x 1000 x 1000 mm
2414 M2414 1200 x 1200 x 1000 mm
2415 M2415 1500 x 1500 x 1000 mm
2416 M2416 1600 x 1600 x 1000 mm
2417 M2417 2000 x 2000 x 1000 mm
2418 M2418 400 x 400 x 1000 mm
2419 M2419 500 x 500 x 1000 mm
2420 M2420 600 x 600 x 1000 mm
94

NO KODE NAMA BARANG SATUAN MERK

A B C D E
2421 M2421 800 x 800 x 1000 mm
VIII Terra Conblock Cover U-Ditch
2422 M2422 Tutup U 100 @60 cm LD (Light Duty)
2423 M2423 Tutup U 100 @60 cm LD (Light Duty)
2424 M2424 Tutup U 120 @60 cm LD (Light Duty)
2425 M2425 Tutup U 120 @60 cm LD (Light Duty)
2426 M2426 Tutup U 140 @60 cm LD (Light Duty)
2427 M2427 Tutup U 140 @60 cm LD (Light Duty)
2428 M2428 Tutup U 150 @60 cm LD (Light Duty)
95

DAFTAR HARGA SATUAN BAHAN

HARGA SATUAN

F
96

HARGA SATUAN

F
97

HARGA SATUAN

F
98

HARGA SATUAN

F
99

HARGA SATUAN

F
100

HARGA SATUAN

F
101

HARGA SATUAN

F
102

HARGA SATUAN

F
103

HARGA SATUAN

F
104

HARGA SATUAN

F
105

HARGA SATUAN

F
106

HARGA SATUAN

F
107

HARGA SATUAN

F
108

HARGA SATUAN

F
109

HARGA SATUAN

F
110

HARGA SATUAN

F
111

HARGA SATUAN

F
112

HARGA SATUAN

F
113

HARGA SATUAN

F
114

HARGA SATUAN

F
115

HARGA SATUAN

F
116

HARGA SATUAN

F
117

HARGA SATUAN

F
118

HARGA SATUAN

F
119

HARGA SATUAN

F
120

HARGA SATUAN

F
121

HARGA SATUAN

F
122

HARGA SATUAN

F
123

HARGA SATUAN

F
124

HARGA SATUAN

F
125

HARGA SATUAN

F
126

HARGA SATUAN

F
127

HARGA SATUAN

F
128

DAFTAR HARGA SATUAN BAHAN


KABUPATEN BADUNG 2022
TRIWULAN I

A. Harga Satuan Bahan

NO NAMA BARANG SATUAN HARGA SATUAN

A B C

CAT/MINYAK/FINISHING
1 Amplas lbr Rp 5,333.33
2 Cat besi kansai property gloss 1 lt ltr Rp 65,000.00
3 Cat dasar kg Rp 48,500.00
4 Cat Antara kg Rp 45,000.00
5 Cat emco 1 lt kg Rp 70,333.33
6 Cat menie besi kanzai 1 lt ltr Rp 45,000.00
7 Cat menie B ltr Rp 45,000.00
8 Cat menie kayu kg Rp 37,750.00
9 Cat tembok Decolith kg Rp 65,000.00
10 Cat tembok Dulux 2,5lt (setara watershield) ltr Rp 307,500.00
11 Cat tembok Dulux 2,5 lt interior ltr Rp 160,500.00
12 Cat tembok Emco kg Rp 49,000.00
13 Cat tembok Paragon kg Rp 57,250.00
14 Cat tembok Toyopaint kg Rp 45,000.00
15 Cat tembok Vinilex kg Rp 34,333.33
16 Cat tembok Vinippaint kg Rp 32,000.00
17 Dempul sanpolac ltr Rp 40,000.00
18 Kuas star 4" bh Rp 21,250.00
19 Mill zak Rp 12,666.67
20 Minyak cat ltr Rp 25,000.00
21 Plamir kayu kg Rp 36,333.33
22 Plamir tembok kg Rp 20,500.00
23 Politur ultra lasur ltr Rp 107,333.33
24 Politur Jadi ltr Rp 107,500.00
25 Politur Movilex ltr Rp 80,000.00
26 Thiner A Bonanza ltr Rp 120,000.00
27 Thiner B Spesial ltr Rp 40,000.00
28 Residu/Kolter ltr Rp 29,000.00
29 Soda api kg Rp 27,333.33
30 Sabun kg Rp 7,500.00
31 Solar ltr Rp 8,000.00
32 Minyak pelumas ltr Rp 60,000.00
33 Woodstain kg Rp 75,000.00
34 Wood filler kg Rp 46,750.00
35 Sanding sealer kg Rp 86,000.00
36 Melamic kg Rp 86,000.00
37 Cornice adhesive kg Rp 5,812.50
38 Coating natural propan kg Rp 80,333.33
39 Sikabon kg Rp 55,000.00
40 Sikacoat kg Rp 220,000.00
41 Sikat besi bh Rp 12,000.00
42 Cat Epoxy kg Rp 127,000.00
43 Larutan Termisida ml Rp 1,200.00
44 Air ltr Rp 100.00
44a Cat Prada Gold Leaf 450 ml ml Rp 325,000.00
###
PENUTUP ATAP ###
45 Alang-alang panjang 2,4 m x 1m lbr Rp 27,000.00
46 Alluminium foil solartek 1,2x25x4mm roll Rp 23,000.00
47 Alluminium foil D 1,2x25x4mm roll Rp 265,000.00
48 Asbes Bubungan lbr Rp 27,500.00
49 Asbes Gelombang 1,80 m x 0,80 m x 5 mm lbr Rp 33,333.33
50 Asbes Gelombang 2,4 m x 1,05 m x 4 mm lbr Rp 35,000.00
129

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
51 Asbes Rata 2 m x 1 m x 4 mm lbr Rp 75,500.00
52 Atap metal Toratora 1 x 4 Extra m2 Rp 98,000.00
53 Atap metal Toratora 1 x 4 Premium m2 Rp 138,000.00
54 Atap metal Toratora 2 x 4 Extra m2 Rp 83,000.00
55 Atap metal Toratora 2 x 4 Premium m2 Rp 125,000.00
56 Atap metal Toratora 3 x 4 Extra m2 Rp 84,000.00
57 Atap metal Toratora 3 x 4 Premium m2 Rp 125,000.00
58 Atap metal Toratora 4 x 4 Extra m2 Rp 87,000.00
59 Atap metal Toratora 4 x 4 Premium m2 Rp 127,000.00
60 Atap spandek 0.30 mm m2 Rp 44,000.00
61 Atap spandek 0.35 mm m2 Rp 81,000.00
62 Atap spandek 0.40 mm m2 Rp 67,000.00
63 Atap spandek 0.45 mm m2 Rp 100,000.00
64 Atap spandek 0.50 mm m2 Rp 80,000.00
65 Bentala paras 70 cm bh Rp 150,000.00
66 Bentala tanah liat 70 cm bh Rp 120,000.00
67 Besi profil WF P.6m kg Rp 20,000.00
68 Besi profil WF P.12m kg Rp 20,000.00
69 Besi siku 30 x 30 x 3 mm kg Rp 13,000.00
70 Bubung stel gel. 0,92 m lbr Rp 39,000.00
71 Bubung stel gel. 1,05 m lbr Rp 48,000.00
72 Bubung stel gel. 1,08 m lbr Rp 52,000.00
73 Bubungan Biasa bj Rp 4,000.00
74 Bubungan Karang Pilang (glazur) isi 3,5/m bj Rp 15,000.00
75 Bubungan Karang Pilang isi 3,5/m bj Rp 17,000.00
76 Bubungan Ngalayur isi 3,5/m bj Rp 5,000.00
77 Bubungan Plentong bj Rp 6,000.00
78 Bubungan genteng beton bj Rp 12,000.00
79 Bubungan Utama isi 3,5/m bj Rp 14,000.00
80 Genteng Kanmuri (glazur) isi 14/m2 bj Rp 11,000.00
81 Genteng Kodok Karang Pilang (Bambe) isi 20/m2 bj Rp 5,000.00
82 Genteng Kodok Karang Pilang (Bisma) isi 20/m2 bj Rp 4,800.00
83 Genteng Kodok Karang Pilang (Good Year) isi 20/m2 bj Rp 4,500.00
84 Genteng Flat (Good Year) isi 20/m2 bj Rp 6,000.00
85 Genteng Beton JS bj Rp 6,200.00
86 Genteng Beton BBC bj Rp 8,900.00
87 Genteng Morando Abadi isi 18/m2 bj Rp 13,000.00
88 Genteng Morando Jatiwangi isi 18/m2 bj Rp 10,000.00
89 Genteng Morando Ngalayur isi 20/m2 bj Rp 10,000.00
90 Genteng Plentong bj Rp 2,650.00
91 Genteng Plentong besar bj Rp 3,800.00
92 Genteng plentong dicat bj Rp 3,500.00
93 Genteng Plentong Jatiwangi isi 24/m2 bj Rp 2,800.00
94 Ijuk kg Rp 16,000.00
95 Ikut celedu paras 80 cm bh Rp 90,000.00
96 Ikut celedu tanah liat 80 cm plentong bh Rp 120,000.00
97 Murda paras 30 cm bh Rp 120,000.00
98 Murda tanah liat 30 cm bh Rp 120,000.00
99 Nok Stel Gelombang 80cm lbr Rp 34,000.00
100 Nok Stel Gelombang 105cm lbr Rp 44,000.00
101 Seng BJLS 0,20 gelombang lbr Rp 68,000.00
102 Seng BJLS 0,25 gelombang lbr Rp 72,500.00
103 Seng BJLS 0,28 gelombang lbr Rp 82,000.00
104 Seng BJLS 0,32 gelombang lbr Rp 80,000.00
105 Seng Plat 3" x 6" BJLS 28 lbr Rp 295,000.00
106 Rooflight Fiberglass lbr Rp 43,500.00
107 Sirap Jati bh Rp 7,000.00
108 Sirap ulin satu ikat isi 80 bh ikat Rp 190,000.00
109 Tali Ijuk kg Rp 9,500.00
110 Tali pengikat alang-alang ikat Rp 18,500.00
111 Nok genteng metal bh Rp 25,000.00
###
130

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
PENGGANTUNG DAN KACA ###
112 Door closer DEKKSON DCL 300 HO BA / NA set Rp 292,500.00
113 Door closer DEKKSON DCL 300 NHO BA / NA set Rp 285,000.00
114 Door closer DEKKSON DCL 522 NA set Rp 352,500.00
115 Door holder bh Rp 38,000.00
116 Door stopper DEKKSON MDS 889 GP bh Rp 235,000.00
117 Engsel 3" solid ek 16 ps Rp 50,000.00
118 Engsel nylon ps Rp 40,000.00
119 Engesel angin/ hak angin ps Rp 27,000.00
120 Engsel solid 4" EK 02 ps Rp 77,500.00
121 Sping Knipe, Grendel Kodok Solid ps Rp 65,000.00
122 Engsel casement solid 12" bh Rp 60,000.00
123 Engsel casement solid 16" bh Rp 80,000.00
124 Engsel casement solid 24" bh Rp 145,000.00
125 Engsel casement solid 20" bh Rp 145,000.00
126 HINGE DEKKSON NRP ESS DL 3X2.5X2.5MM 2 SSS ps Rp 77,000.00
127 HINGE DEKKSON NRP ESS DL 4X3X3MM 4BB SSS ps Rp 145,000.00
128 HINGE DEKKSON NRP ESS DL 5X3X3MM 4BB SSS ps Rp 165,000.00
129 HINGE DEKKSON ESS DL “H” 4X3X2MM 2 SSS ps Rp 88,000.00
130 Espagnoleth (setara solid) set Rp 172,500.00
131 Grendel biasa bh Rp 12,666.67
132 Grendel hararo bh Rp 35,000.00
133 Kaca 3 mm bening m2 Rp 97,500.00
134 Kaca 5 mm bening m2 Rp 142,500.00
135 Kaca 6 mm bening m2 Rp 182,500.00
136 Kaca 8 mm bening m2 Rp 250,000.00
137 Kaca 10 mm bening m2 Rp 275,000.00
138 Kaca 12 mm bening m2 Rp 345,000.00
139 Kaca 19 mm bening m2 Rp 850,000.00
140 Kaca Es/Kapur 3 mm m2 Rp 135,000.00
141 Kaca Es/Kapur 5 mm m2 Rp 180,000.00
142 Kaca nako daun Rp 18,000.00
143 Kaca nako teralis bening m2 Rp 130,000.00
144 Kaca ryben 3 mm m2 Rp 120,000.00
145 Kaca ryben 5 mm m2 Rp 170,000.00
146 Laminated Glass Clear 3+0,38+10 m2 Rp 375,000.00
147 Laminated Glass Clear 4+0,38+10 m2 Rp 460,000.00
148 Laminated Glass Clear 5+0,38+10 m2 Rp 525,500.00
149 Laminated Glass Clear 6+0,38+10 m2 Rp 650,000.00
150 Laminated Glass Clear 8+0,38+10 m2 Rp 935,000.00
151 Laminated Glass Clear 10+0,38+10 m2 Rp 1,150,500.00
152 Laminated Glass Tempered 3+0,38+3 m2 Rp 725,000.00
153 Laminated Glass Tempered 4+0,38+4 m2 Rp 845,000.00
154 Laminated Glass Tempered 5+0,38+5 m2 Rp 995,000.00
155 Laminated Glass Tempered 6+0,38+6 m2 Rp 1,175,000.00
156 Laminated Glass Tempered 8+0,38+8 m2 Rp 1,752,000.00
157 Laminated Glass Tempered 10+0,38+10 m2 Rp 1,925,000.00
158 Prosted Glass/kaca es 3 mm m2 Rp 145,000.00
159 Prosted Glass/kaca es 5 mm m2 Rp 178,000.00
160 Tempered Glass 5 mm m2 Rp 185,000.00
161 Tempered Glass 6 mm m2 Rp 255,000.00
162 Tempered Glass 8 mm m2 Rp 375,000.00
163 Tempered Glass 10 mm m2 Rp 452,000.00
164 Tempered Glass 12 mm m2 Rp 500,000.00
165 Tempered Glass 15 mm m2 Rp 960,000.00
166 Tempered Glass 19 mm m2 Rp 1,325,000.00
167 Ice Glass 3 mm/kaca es m2 Rp 125,000.00
168 Ice Glass 5 mm/kaca es m2 Rp 169,000.00
169 Mirror Glass 3 mm m2 Rp 160,000.00
170 Mirror Glass 5 mm m2 Rp 215,000.00
171 Mirror Glass 8 mm m2 Rp 460,000.00
172 Hak angin HA641 SOLID bh Rp 37,500.00
131

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
173 Kunci pintu TOP bh Rp 65,000.00
174 Kunci pintu Union bh Rp 155,000.00
175 Kunci pintu Vanesa bh Rp 125,000.00
176 Kunci pintu solid bh Rp 445,000.00
177 Kunci pintu YURI bh Rp 175,000.00
178 Kunci pintu dekson H.DK.LHTR0819 SSS bh Rp 225,000.00
179 Kunci lemari/ laci solid 642 CHR bh Rp 30,000.00
180 Sanro Kunci Ekspanda Bellucci 809 PZS bh Rp 215,000.00
181 grendel slot pintu solid " barrel bolt 314" bh Rp 75,000.00
182 Kunci tanam kamar mandi/ Belocca D5791 Satin Nickel Kunci Bulat bh Rp 65,000.00
183 Kunci silinder DC02-60 SCR Solid bh Rp 105,000.00
184 Kunci slot bh Rp 45,000.00
185 Kunci tanam 2 slag bh Rp 105,000.00
186 CYLINDER DEKKSON CYL HC DL40MM SN bh Rp 45,000.00
187 CYLINDER DEKKSON CYL DC DL60MM SN bh Rp 50,000.00
188 CYLINDER DEKKSON CYL DC KK DL60MM PB bh Rp 55,000.00
189 CYLINDER DEKKSON CYL TC DL60MM PB bh Rp 60,000.00
190 CYLINDER DEKKSON CYL BK DL60MM SN bh Rp 75,000.00
191 Security Double Cylinder DC02-60 SCR Solid bh Rp 90,000.00
192 Kunci pintu Solid (E 62.15 ,LC 122 WL- 60 + 4 bh handle unit Rp 625,000.00
193 Grendel Tanam Solid / Flosh Bolt 312 Solid US 26 16" ps Rp 135,000.00
194 Rel pintu sorong set Rp 345,000.00
###
KAYU DAN PLAFOND ###
195 Bambu besar expose utk saka btg Rp 15,000.00
196 Bambu besar Ukuran 4 m btg Rp 17,500.00
197 Bambu sedang Ukuran 4 m btg Rp 10,000.00
198 Bambu kecil Ukuran 4 m btg Rp 9,666.67
199 Celling teak (0,62 x 2,40) m2 lbr Rp 112,000.00
200 Eternit lbr Rp 35,000.00
201 Formika lbr Rp 150,500.00
202 Gedeg kulit kelas I m2 Rp 46,500.00
203 Gypsum Old (tebal 9 mm) lbr Rp 49,000.00
204 Hard board MDF lbr Rp 68,000.00
205 Kalsiboard 4,5 mm lbr Rp 65,000.00
206 Fibercement cellingboard square cut setara shera ukuran (6x120x240) mm lbr Rp 173,600.00
207 Kayu bekesting (Lepasan merah) m3 Rp 4,000,000.00
208 Kayu bingkirai balok m3 Rp 16,000,000.00
209 Kayu bingkirai papan m3 Rp 19,000,000.00
210 Kayu dolken kelapa diameter 18 cm P.2,5m m1 Rp 160,000.00
211 Kayu dolken kelapa diameter 18 cm P.3m m1 Rp 165,000.00
212 Kayu dolken kelapa diameter 18 cm P.4m m1 Rp 195,000.00
213 Kayu dolken/Kayu Laut Ø 8 - 10 / 400 cm btg Rp 28,000.00
214 Kayu cempaka m3 Rp 12,500,000.00
215 Kayu jati m3 Rp 29,300,000.00
216 Kayu jati papan m3 Rp 42,300,000.00
217 Kayu kamper balok m3 Rp 9,625,000.00
218 Kayu kamper usuk/reng m3 Rp 8,775,000.00
219 Kayu kamper papan m3 Rp 10,950,000.00
220 Kayu kruing balok m3 Rp 7,366,666.67
221 Kayu kruing usuk/reng m3 Rp 7,100,000.00
222 Kayu kruing papan m3 Rp 8,362,500.00
223 Kayu meranti balok m3 Rp 7,500,000.00
224 Kayu meranti usuk/reng m3 Rp 5,300,000.00
225 Kayu meranti papan m3 Rp 7,900,500.00
226 Kayu merbau balok m3 Rp 14,300,000.00
227 Kayu merbau papan m3 Rp 15,650,000.00
228 Kayu profil usuk m1 Rp 32,500.00
229 Kayu seseh balok m3 Rp 4,708,333.33
230 Kayu seseh dolken m3 Rp 7,500,000.00
231 Lem Aibond kg Rp 47,500.00
232 Lem Kayu ltr Rp 19,750.00
132

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
233 List Gypsum standar m' Rp 17,000.00
234 List kayu m1 Rp 26,000.00
235 List kayu profil m1 Rp 22,500.00
236 Ring ring ukir jati 1.5 x 8 cm m1 Rp 67,000.00
237 Minyak bekisting ltr Rp 17,500.00
238 Multiplek 12 mm lbr Rp 196,666.67
239 Multiplek 18 mm lbr Rp 300,000.00
240 Multiplek 6 mm lbr Rp 82,500.00
241 Multiplek 9 mm lbr Rp 150,000.00
242 Plywood 12 mm lbr Rp 185,000.00
243 Plywood 3 mm lbr Rp 80,000.00
244 Plywood 4 mm lbr Rp 100,000.00
245 Plywood 6 mm lbr Rp 157,500.00
246 Plywood 9 mm lbr Rp 225,000.00
247 Plywood aluminium lbr Rp 122,500.00
248 Teak wood (0,9x2,20) m2 lbr Rp 78,000.00
249 Teak wood (1,20x2,40) m2 lbr Rp 86,000.00
250 Panel Acoustic Armstrong 120x60cm, tebal 9 mm lbr Rp 46,000.00
251 Panel Acoustic Armstrong 120x60cm, tebal 15 mm lbr Rp 44,000.00
252 Panel Acoustic OWA Constellation 120x60cm, tebal 15 m lbr Rp 42,000.00
253 Triplex Phenol WBP film 12 mm 1 muka lbr Rp 315,000.00
254 Triplex Phenol WBP film 12 mm 2 muka lbr Rp 380,000.00
255 Lumbersering Conwood m2 Rp 89,000.00
Plafond fibercement splending modern stagger setara shera smooth texture 1br
256 golden teakwood(10x150x3000mm) Rp 107,000.00
Plafond fibercement splending modern stagger setara shera smooth texture 1br
257 golden teakwood(10x200x3000mm) Rp 142,000.00
258 List gifsum 9/9 m1 Rp 16,000.00
259 Blockboard 18 mm lbr Rp 265,000.00
260 Teakblock 18 mm lbr Rp 300,000.00
261 Megateak 3 mm lbr Rp 107,500.00
262 Shadowline m1 Rp 20,333.33
263 Lis plafond fibercement strip smooth texture square cut edge(8x75x3000mm) lbr Rp 45,000.00
264 lisplank fibercement eave pro coral white setara shera (16x240x3000 mm ) lbr Rp 175,000.00
265 Tatab fibercement strip smooth texture V cut edge setara shera (8x100x3000 mm lbr Rp 65,000.00
266 Kayu Ulin m3 Rp 17,500,000.00
267 Glasswool m2 Rp 50,000.00
###
KERAMIK : ###
IKAD ###
268 Ikad (Keramik) Kw. I 10 x 20 cm m2 Rp 75,000.00
269 Ikad (Keramik) Kw. I 20 x 20 cm m2 Rp 64,000.00
270 Ikad (Keramik) Kw. I 20 x 30 cm m2 Rp 82,000.00
271 Ikad (Keramik) Kw. I 30 x 30 cm m2 Rp 43,000.00
272 Ikad (Keramik) Kw. I 40 x 40 cm m2 Rp 48,000.00
273 Ikad (Keramik) Kw. I 20 x 40 cm m2 Rp 62,000.00
274 Ikad (Keramik) Kw. II 20 x 20 cm m2 Rp 62,000.00
275 Ikad (Keramik) Kw. II 20 x 30 cm m2 Rp 80,500.00
276 Ikad (Keramik) Kw. II 30 x 30 cm m2 Rp 60,000.00
277 Ikad (Keramik) Kw. II 40 x 40 cm m2 Rp 40,000.00
###
INESA ###
278 Keramik 30 x 30 Kelas I (Onyx Phyrus Ruby Jade, P) m2 Rp 147,500.00
279 Keramik 30 x 30 Kelas I (Onyx Phyrus Ruby Jade, UP) m2 Rp 129,250.00
280 Keramik 30 x 30 Kelas I (Pearl Ghita Cat Eye, P) m2 Rp 145,000.00
281 Keramik 30 x 30 Kelas I (Pearl Ghita Cat Eye, UP) m2 Rp 122,500.00
282 Keramik 30 x 30 Kelas I (Sand Wheat Spruce Clay Charcoal, R) m2 Rp 135,250.00
283 Keramik 40 x 40 Kelas I (Corypha Roystonea Raphia, P) m2 Rp 171,500.00
284 Keramik 40 x 40 Kelas I (Onyx Phyrus Ruby Jade, P) m2 Rp 170,000.00
285 Keramik 40 x 40 Kelas I (Onyx Phyrus Ruby Jade, UP) m2 Rp 141,500.00
286 Keramik 40 x 40 Kelas I (Pearl Ghita Cat Eye, P) m2 Rp 164,250.00
133

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
287 Keramik 40 x 40 Kelas I (Pearl Ghita Cat Eye, UP) m2 Rp 137,500.00
288 Keramik 60 x 60 Kelas I (Corypha Roystonea Raphia, P) m2 Rp 182,000.00
###
ESSENZA ###
289 Keramik 30 x 30 Kelas I (Black Orchid, Coral Bell, P) m2 Rp 222,500.00
290 Keramik 30 x 30 Kelas I (Black Orchid, Coral Bell, UP) m2 Rp 200,000.00
291 Keramik 30 x 30 Kelas I (Pepper G Price Rubert Silver star, P) m2 Rp 160,500.00
292 Keramik 30 x 30 Kelas I (Pepper G Price Rubert Silver star,UP) m2 Rp 115,000.00
293 Keramik 40 x 40 Kelas I (Pepper G Price Rubert Silver star, P) m2 Rp 230,000.00
294 Keramik 40 x 40 Kelas I (Pepper G Price Rubert Silver star,UP) m2 Rp 200,000.00
295 Keramik 60 x 60 Kelas I (Pepper G Price Rubert Silver star, P) m2 Rp 280,000.00
296 Keramik Kelas I Domus m2 Rp 300,000.00
297 Keramik Kelas I Granity Imperiali m2 Rp 267,500.00
298 Keramik Kelas I Lavagna m2 Rp 257,500.00
299 Keramik Kelas I Mountain Peak m2 Rp 357,000.00
300 Granit 30 x 60 magnetite rock m2 Rp 255,500.00
301 Granit 60 x 60 magnetite rock m2 Rp 315,000.00
302 Granit 60 x 60 pepper grey polished m2 Rp 305,000.00
303 Granit 60 x 60 coral bell polished m2 Rp 378,500.00
304 Granit 60 x 60 ivory polished m2 Rp 270,000.00
305 Granit 60 x 60 unica gold polished m2 Rp 348,000.00
306 Granit 60 x 60 alexandra polished m2 Rp 340,500.00
307 Granit 60 x 60 elit unpolished m2 Rp 340,200.00
308 Granit 60 x 60 absolute black unpolished m2 Rp 343,250.00
309 Granit 60 x 60 cosmo white unpolished m2 Rp 310,000.00
310 Granit 60 x 60 cotton brown unpolished m2 Rp 312,500.00
###
ROMAN ###
311 Keramik Dcasila rigio 50 x 50 m2 Rp 155,000.00
312 Keramik Dcolorado sand 50 x 50 m2 Rp 125,000.00
313 Keramik 20 x 20 G223001 granity loth m2 Rp 94,500.00
314 Keramik 25 x 33 kelas I m2 Rp 123,000.00
315 Keramik 25 x 45 motif halus kelas I m2 Rp 162,000.00
316 Keramik 30 x 30 standard m2 Rp 95,000.00
317 Keramik 30 x 30 kelas I T. 1cm m2 Rp 180,000.00
318 Keramik 33 x 33 kelas I T. 1cm m2 Rp 165,500.00
319 Keramik 20 x 60 kelas I T. 1cm m2 Rp 169,000.00
320 Keramik 20 x 40 kelas I Motif standard serenity white m2 Rp 110,000.00
321 Keramik 30 x 60 kelas I Motif Dasar Muda Dserio lite m2 Rp 140,000.00
322 Keramik 40 x 40 kelas I krem sandstone cream m2 Rp 102,000.00
323 Keramik 40 x 40 kelas I white m2 Rp 102,000.00
324 Keramik 50 x 50 kelas I warna muda colosseum bovie m2 Rp 119,000.00
325 Internal cove bh Rp 15,000.00
326 Keramik artistik m2 Rp 60,000.00
###
PLATINUM ###
327 Keramik naxos cream 50 x 50 m2 Rp 85,000.00
328 Keramik 25 x 33 kelas I m2 Rp 65,000.00
329 Keramik 25 x 40 kelas I m2 Rp 63,000.00
330 Keramik 30 x 60 kelas II bulgari m2 Rp 75,000.00
331 Keramik 40 x 40 kelas I vegas brown m2 Rp 62,500.00
332 Keramik 20 x 50 kelas I m2 Rp 78,000.00
333 Keramik 25 x 40 kelas II m2 Rp 68,000.00
334 Keramik 40 x 40 kelas II cream m2 Rp 68,000.00
###
134

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
ANEKA KERAMIK DAN GRANIT ###
335 Habitat seville cinco 50 x 50 m2 Rp 85,000.00
336 Habitat omnia beige 50 x 50 m2 Rp 85,000.00
337 Habitat belle tetrik beige 50 x 50 m2 Rp 68,000.00
338 Centro lamborghini grey 50 x 50 m2 Rp 70,000.00
339 Milan monkada 50 x 50 m2 Rp 70,000.00
340 Milan Torino basic 50 x 50 m2 Rp 70,000.00
341 Milan gregory brown 50 x 50 m2 Rp 69,000.00
342 Milan Leon beige 50 x 50 m2 Rp 70,000.00
343 Hercules malaka light 50 x 50 m2 Rp 78,000.00
344 Granite Tile GG 605 white crystal 60 x 60 m2 Rp 160,000.00
345 Niro GMA 02 carroline polist nano 60 x 60 m2 Rp 157,500.00
###
SINCERE ###
346 Granit rocktile brown L.60 m2 Rp 325,000.00
347 Granit polished nano L.60 m2 Rp 320,000.00
348 Granit micro crystal L.60 m2 Rp 941,000.00
349 Granit white nano L.60 m2 Rp 450,000.00
350 Granit natural marble wht L.60 m2 Rp 379,500.00
351 Granit popular wht L.60 m2 Rp 292,500.00
352 Granit micro diamond wht L. 60 m2 Rp 338,500.00
353 Granit micro diamond blk L. 60 m2 Rp 463,000.00
354 Granit poly cristal cream L. 60 m2 Rp 265,500.00
###
GRANITO ###
355 Granito Castello Tera 60 x 60 m2 Rp 170,000.00
356 Granito Monalisa TD6602 60 x 60 m2 Rp 366,500.00
357 Granito Monalisa TD6602 80 x 80 m2 Rp 366,500.00
358 Granito Niro FR660IY 60 x 60 m2 Rp 366,500.00
359 Granito Essenza Grey 60 x 60 m2 Rp 366,500.00
360 Granito Indogress Cristallo 80 x 80 m2 Rp 175,000.00
361 Granito salsa ivary 40 x 40 polished m2 Rp 302,500.00
362 Granito salsa ivary 40 x 40 unpolished m2 Rp 279,000.00
363 Granito salsa ivary 60 x 60 polished m2 Rp 250,000.00
364 Granito salsa ivary 60 x 60 unpolished m2 Rp 235,000.00
365 Granito salsa ivary 80 x 80 polished m2 Rp 672,750.00
366 Granito salsa ivary 30 x 60 polished m2 Rp 185,000.00
367 Granito palazzo monza 60 x 60 polished m2 Rp 225,000.00
368 Granito Aurora silk 60 x 60 polished m2 Rp 335,000.00
369 Granito Aurora silk 30 x 60 polished m2 Rp 431,000.00
370 Granito sabbia villa 60 x 60 polished m2 Rp 543,500.00
371 Granito castello rosso 40 x 40 unpolished m2 Rp 258,000.00
372 Granito castello pietra 60 x 60 unpolished m2 Rp 370,500.00
373 Granito lunar terra 30 x 60 unpolished m2 Rp 453,000.00
374 Granito lunar terra 60 x 60 unpolished m2 Rp 420,000.00
375 Granito lunar alumina 60 x 60 unpolished m2 Rp 550,000.00
376 Granito lunar alumina 30 x 60 unpolished m2 Rp 525,000.00
###
MARMER ###
377 Marmer cream BA 60 x 60 m2 Rp 445,000.00
378 Marmer cream BA 40 x 40 m2 Rp 347,000.00
379 Marmer cream BA 30 x 30 m2 Rp 285,000.00
380 Marmer Bianco Rhino 100 x 100 m2 Rp 2,605,000.00
381 Marmer White Pearl m2 Rp 2,200,000.00
382 Marmer Bianco Turco m2 Rp 1,420,000.00
383 Marmer Astana Silver m2 Rp 2,545,000.00
384 Marmer Rosso Alicante m2 Rp 1,400,000.00
385 Marmer Crystal Blue m2 Rp 2,205,000.00
386 Batu Granit Black m2 Rp 1,945,000.00
387 Batu granit kg Rp 25,000.00
388 Teraso cor m3 Rp 7,000,000.00
###
135

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
###
136

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
MOZAIK ###
389 Mozaik keramik zehn MC 04 green crystal glass 30 x 30 biji Rp 77,500.00
390 Mozaik batu alam 30 x 30 biji Rp 76,800.00
391 Venus Indigo rimple black 30 x 30 x 8 mm m2 Rp 1,395,000.00
392 Venus Indigo linear 30 x 30 x 8 mm m2 Rp 1,005,800.00
393 Venus Indigo rimple black 30 x 30 x 8 mm m2 Rp 2,199,500.00
394 Venus painting 30 x 30 x 8 mm m2 Rp 1,725,500.00
395 Venus indigo rimple blue combination 30 x 30 x 8 mm m2 Rp 1,290,500.00
396 Venus indigo grey 30 x 30 x 8 mm m2 Rp 1,402,000.00
397 Venus indigo gold 30 x 30 x 8 mm m2 Rp 1,505,000.00
###
ASIA ###
398 Keramik 20 x 25 kelas I m2 Rp 49,000.00
399 Keramik 30 x 30 kelas I nirwana cream m2 Rp 56,500.00
400 Keramik 30 x 30 kelas I ocsar taupe m2 Rp 57,000.00
401 Keramik 40 x 40 kelas I nirwana green m2 Rp 60,000.00
402 Keramik 10 x 20 kelas II m2 Rp 45,000.00
403 Keramik 20 x 20 kelas I m2 Rp 44,500.00
404 Keramik 20 x 30 kelas II m2 Rp 60,000.00
405 Keramik 30 x 30 kelas II m2 Rp 39,000.00
406 Keramik 40 x 40 kelas II m2 Rp 48,500.00
###
MULIA ###
407 Keramik 10 x 20 cm kelas I m2 Rp 67,000.00
408 Keramik 20 x 20 cm kelas I m2 Rp 65,000.00
409 Keramik 20 x 30 cm kelas I m2 Rp 72,500.00
410 Keramik 30 x 30 cm kelas I m2 Rp 110,000.00
411 Keramik 40 x 40 cm kelas I signature neo pebble sand m2 Rp 57,000.00
412 Keramik 10 x 20 cm kelas II m2 Rp 72,250.00
413 Keramik 20 x 20 cm kelas II m2 Rp 65,000.00
414 Keramik 20 x 30 cm kelas II m2 Rp 68,500.00
415 Keramik 30 x 30 cm kelas II m2 Rp 62,000.00
416 Keramik 40 x 40 cm kelas II m2 Rp 75,500.00
###
UBIN/ TEGEL LANTAI ###
417 Ubin/ tegel polos m2 Rp 70,500.00
418 Ubin/ tegel warna m2 Rp 150,500.00
419 Ubin terasso m2 Rp 302,500.00
###
KARPET ###
420 Karpet roll loop atrium m2 Rp 183,500.00
421 Karpet roll loop Bali m2 Rp 83,500.00
422 Karpet roll loop Breeze Plus m2 Rp 155,500.00
423 Karpet roll loop Callaway m2 Rp 195,250.00
424 Karpet roll loop caprice m2 Rp 182,500.00
425 Karpet roll loop checkmate m2 Rp 155,500.00
426 Karpet roll loop crown m2 Rp 83,500.00
427 Karpet roll loop emperor m2 Rp 102,000.00
428 Karpet roll loop florance m2 Rp 162,250.00
429 Underlayer /pelapis bawah karpet m2 Rp 57,000.00
###
PARQUET/ FLOORING/ DECKING/HPL ###
430 Parquet Jati 1.2cm x 5cm x 17cm m2 Rp 184,500.00
431 Parquet Jati 1.2cm x 5cm x 20cm m2 Rp 247,000.00
432 Parquet Jati 1.2cm x 5cm x 25cm m2 Rp 271,000.00
433 Parquet Jati 1.2cm x 5cm x 30cm m2 Rp 295,000.00
434 Lamparquet (lantai kayu merbau) 1 cm x 5cm x 20cm m2 Rp 165,000.00
435 Lamparquet (lantai kayu merbau) 1 cm x 5cm x 25cm m2 Rp 178,000.00
436 Lamparquet (lantai kayu merbau) 1 cm x 5cm x 30cm m2 Rp 187,000.00
437 Flooring 1.5cm x 9cm x 30cm – 90cm m2 Rp 428,000.00
438 Flooring Lokal 1.5cm x 8.5cm x 30cm m2 Rp 277,000.00
439 Flooring Lokal 1.5cm x 12cm x 30cm -40cm (jumbo) m2 Rp 445,000.00
137

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
440 Flooring Lokal 1.5cm x 12cm x 60cm up (jumbo export) m2 Rp 460,500.00
441 Decking Kayu Merbau 1,9cm x 9cm x 140cm -up m2 Rp 495,000.00
442 Decking Kayu Bengkirai 1,9cm x 9cm x 180cm -up m2 Rp 435,000.00
443 Decking Kayu Kruing 1,9cm x 9cm x 180cm -up m2 Rp 428,000.00
444 Decking Kayu Ulin 1,9cm x 9cm x 100cm – up m2 Rp 719,000.00
445 HPL ( MATTE AND TEXTURE ) m2 Rp 195,000.00
446 Wallpaper motif clear spirit 10 x 0.5 roll Rp 428,000.00
###
SANITAIR ###
447 Bak mandi fibre glass 55x55x60 cm bh Rp 225,000.00
448 Bak mandi keramik 50x50 bh Rp 550,000.00
449 Floor Drain " TOTO TypeTx 1 Bv 1 " Square Flange " bh Rp 235,000.00
450 Floor drain plastik bh Rp 23,500.00
451 Floor drain stainless bh Rp 32,500.00
452 Jetwasher TOTO THX20MCRB bh Rp 495,000.00
453 Kloset duduk Amerika Standar ECST wht bh Rp 1,325,000.00
454 Kloset duduk OULU A626 wht bh Rp 575,000.00
455 Kloset duduk Zehn 040 A wht bh Rp 475,000.00
456 Kloset duduk "TOTO Type CW 421 + TCW 07 tangki bulat bh Rp 1,850,000.00
457 Kloset duduk "TOTO Type CW 660 + TCW 07 tangki kotak bh Rp 1,550,000.00
458 Kloset duduk "TOTO Type AVANTE CW 821J"/SW 821JP COMPLIT bh Rp 4,473,000.00
459 Kloset duduk " TOTO Type AVANTE CW 823 J bh Rp 6,729,000.00
460 Kloset duduk " TOTO Type CW 660J complit bh Rp 3,175,000.00
461 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT bh Rp 2,390,000.00
462 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT WARNA bh Rp 2,825,000.00
463 Kloset duduk " TOTO Type CW 420 wht bh Rp 1,762,500.00
464 Kloset duduk " TOTO Type CW 637 wht bh Rp 1,887,500.00
465 Kloset duduk " TOTO Type CW 661JT1" / SW 661JP COMPLIT bh Rp 3,215,000.00
466 Kloset duduk " TOTO Type CW 661JT1" / SW 784JP COMPLIT bh Rp 2,935,000.00
467 Kloset jongkok " TOTO komplit wht Ce 6 bh Rp 650,000.00
468 Kloset jongkok " TOTO komplit wht Ce 9 bh Rp 2,925,000.00
469 Kloset jongkok " TOTO CE -7P ivory CL bh Rp 395,000.00
470 Kloset jongkok " TOTO CE-7 white CL bh Rp 337,666.67
471 Kloset porselin jongkok Kia (standar) bh Rp 240,000.00
472 Kloset porselin jongkok pozzi bh Rp 153,000.00
473 Kloset porselin jongkok liga bh Rp 125,000.00
474 Kloset porselin jongkok Ina (standar) bh Rp 220,000.00
475 Kran TOTO T 205 LCSC bh Rp 335,000.00
476 Kran TOTO T 205 MC bh Rp 277,500.00
477 Kran TOTO T 23 B13 bh Rp 230,000.00
478 Kran TOTO T 23 B13V7N bh Rp 235,000.00
479 Kran TOTO T 26-13 bh Rp 305,000.00
480 Kran TOTO TX 109 LD bh Rp 570,000.00
481 Penyekat Urinoir " TOTO " Type A 100 "white bh Rp 425,000.00
482 Shower Spray " TOTO Tx 403SPIV ( Pastel Ivory ) bh Rp 455,000.00
483 Soap holder " TOTO Type S 6 N'' bh Rp 415,000.00
484 Shower Spray " TOTO Tx 474 SRR REIR single lever bh Rp 410,000.00
485 Shower Spray " TOTO Tv 471 SP plano single lever B ath bh Rp 435,000.00
486 Shower head Spray TOTO bh Rp 165,000.00
487 Shower Spray " ONDA bh Rp 145,000.00
488 Soap holder Biasa Trisensa bh Rp 16,250.00
489 Seal tape ONDA bh Rp 5,000.00
490 Urinoir " TOTO komplit bh Rp 2,215,500.00
491 Urinoir " American standard m1w bh Rp 969,000.00
492 Urinoir " HCG u999m bh Rp 540,000.00
493 Wastafel american Standard studio bh Rp 535,500.00
494 Wastafel HCG l61 bh Rp 1,095,500.00
495 Wastafel Komplit " Tidy 001b bh Rp 1,876,500.00
496 Wastafel Komplit top Counter" TOTO " Type CERABO LW 523 " bh Rp 1,905,000.00
497 Wastafel Toto komplit LW631JW/F segi 4 bh Rp 1,095,000.00
498 Wastafel Toto LW352JW/F bulat bh Rp 1,025,000.00
138

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
499 Wastafel Toto komplit LW645+T6JV5 kotak bh Rp 2,320,000.00
500 Wastafel Toto LW248JR bh Rp 445,000.00
501 Waterdrain bh Rp 35,000.00
502 Shower ONDA exclusive s.80 bh Rp 460,000.00
503 Shower ONDA eco sense bh Rp 895,000.00
504 Shower ONDA eco sns.931 bh Rp 705,000.00
505 Shower CARLO exclusive bh Rp 293,500.00
506 Tidy cuci piring doble bh Rp 1,900,000.00
507 Tidy cuci piring single bh Rp 975,000.00
508 Zehn cuci piring doble bh Rp 1,520,000.00
509 Biotank Pabrikan unit Rp 2,850,000.00
510 Stop Kran bh Rp 65,000.00
511 tempat sabun bh Rp 50,000.00
###
###
PAKU ###
512 Paku 10 cm kg Rp 20,666.67
513 Paku kalsiboard kg Rp 28,500.00
514 Paku list SQ kg Rp 21,500.00
515 Paku pancing 60 x 230 kg Rp 29,000.00
516 Paku reng/usuk SQ kg Rp 20,000.00
517 Paku seng kg Rp 36,000.00
518 Paku seng import bj Rp 40,000.00
519 Paku skrup 1/2" kg Rp 25,000.00
520 Paku skrup 2" kg Rp 18,000.00
521 Paku skrup 3.5" kg Rp 35,000.00
522 Paku sumbat 1/2" kg Rp 40,000.00
523 Paku beton 5 cm kg Rp 30,000.00
524 Dinabolt ø 12mm M12 X 75 bh Rp 8,000.00
525 Paku 12 cm kg Rp 22,000.00
###
PASIR, BATU, KERIKIL, BATA DAN PARAS ###
526 Bata gosok ex Tulikup bj Rp 4,850.00
527 Bata press bj Rp 2,750.00
528 Bata Merah tebal 5 cm bj Rp 1,000.00
529 Bata Merah tebal 7 cm bj Rp 1,300.00
530 Bata ringan uk. 70/20cm bj Rp 8,500.00
531 Bata ringan T. 7,5cm,P. 60cm, L. 20cm, 111pcs bj Rp 9,000.00
532 Bata ringan T. 10cm,P. 60cm, L. 20cm, 83pcs bj Rp 9,950.00
533 Bata ringan T. 12,5cm,P. 60cm, L. 20cm, 66pcs bj Rp 16,250.00
534 Bata ringan T. 15cm,P. 60cm, L. 20cm, 55pcs m3 Rp 920,000.00
535 Bata ringan T. 17,5cm,P. 60cm, L. 20cm, 47pcs m3 Rp 920,000.00
536 Bata ringan T. 20cm,P. 60cm, L. 20cm, 41pcs m3 Rp 920,000.00
537 Batako kelas I Buntu bj Rp 2,400.00
538 Batako kelas I Lobang bj Rp 2,600.00
539 Batu bulat 15/20 cm m3 Rp 292,000.00
540 Batu Belah m3 Rp 290,000.00
541 Batu karang m3 Rp 223,000.00
542 Batu lahar Singaraja m3 Rp 664,500.00
543 Batu pecah besar m3 Rp 275,500.00
544 Batu pecah 5-7 cm (manual) m3 Rp 285,500.00
545 Batu pecah 3-5 cm (manual) m3 Rp 295,000.00
546 Batu pecah 2-3 cm (manual) m3 Rp 300,000.00
547 Batu pipih Singaraja m3 Rp 670,000.00
548 Bata ryan ( abble ) bj Rp 35,000.00
549 Roster Keramik bh Rp 66,500.00
550 Bata rooster bh Rp 16,000.00
551 Koral Beton 2/3 Ex. 4 per 2,75 M3 m3 Rp 255,000.00
552 Limestone m3 Rp 85,000.00
553 Paras Batik bh Rp 45,500.00
554 Paras Buahan bh Rp 20,250.00
139

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
555 Paras Karang Bukit Tebal 6 cm bh Rp 410,500.00
556 Paras Tulung Agung bh Rp 9,250.00
557 Paras Malem bh Rp 26,250.00
558 Paras Putih Bukit Tebal 6 cm m2 Rp 8,500.00
559 Paras Silakarang tebal m2 Rp 29,500.00
560 Paras Silakarang tipis bh Rp 25,500.00
561 Paras untuk pondasi bh Rp 17,500.00
562 Batu alam RTM hijau 10 x 20 halus m2 Rp 111,000.00
563 Batu alam RTM hijau 20 x 20 halus m2 Rp 122,500.00
564 Batu alam RTS hijau 10 x 20 kasar m2 Rp 102,500.00
565 Batu pilah Jember 30 x 30 m2 Rp 95,000.00
566 Batu pilah Jember 20 x 30 m2 Rp 87,500.00
567 Batu pilah Jember 40 x 40 m2 Rp 107,500.00
568 Batu pilah Singaraja 30 x 30 m2 Rp 95,000.00
569 Batu pilah Singaraja 20 x 20 m2 Rp 85,000.00
570 Batu hitam Jember 5 x 20 halus m2 Rp 77,500.00
571 Batu hitam Jember 20 x 40 halus m2 Rp 88,750.00
572 Batu hitam Jember 15 x 30 halus m2 Rp 81,250.00
573 Batu hitam Singaraja 15 x 30 halus m2 Rp 84,000.00
574 Batu hitam Singaraja 20 x 40 halus m2 Rp 91,250.00
575 Batu AND 60 x 60 abu m2 Rp 220,000.00
576 Batu AND 50 x 50 hitam m2 Rp 222,500.00
577 Batu AND 40 x 40 hitam bkr m2 Rp 176,000.00
578 Batu AND 30 x 60 hitam bkr m2 Rp 175,000.00
579 Batu AND 40 x 60 hitam kilap m2 Rp 235,250.00
580 Batu AND 30 x 40 abu SS m2 Rp 112,500.00
581 Batu marmer kuning 10 x 20 m2 Rp 125,000.00
582 Batu marmer kuning PB1 10 x 20 m2 Rp 115,000.00
583 Batu marmer kuning PB2 10 x 20 m2 Rp 115,000.00
584 Batu marmer kuning 15 x 30 m2 Rp 130,000.00
585 Batu kuning serat 30 x 30 m2 Rp 112,500.00
586 Batu kuning serat 20 x 30 m2 Rp 97,500.00
587 Batu palimanan cirebon 20 x 30 m2 Rp 92,500.00
588 Batu palimanan cirebon 20 x 40 m2 Rp 97,500.00
589 Batu paras Jogja 60 x 60 m2 Rp 181,000.00
590 Batu paras Jogja putih 20 x 30 T.5 cm bh Rp 14,250.00
591 Batu candi hitam 60 x 60 m2 Rp 247,500.00
592 Batu candi hitam 20 x 20 m2 Rp 80,000.00
593 Batu candi hitam 30 x 30 m2 Rp 92,000.00
594 Batu candi hitam 40 x 40 T.5cm m2 Rp 229,000.00
595 Batu candi hitam 20 x 30 m2 Rp 83,000.00
596 Batu Bali green gelombang 20 x 40 m2 Rp 120,000.00
597 Batu Bali green kombinasi 20 x 40 m2 Rp 120,000.00
598 Batu serayu 20 x 60 m2 Rp 125,000.00
599 Batu/biji terasso/ batu padalarang kg Rp 28,000.00
600 Batu gunung ex karang asem bj Rp 25,000.00
601 Loster Ukir paras Cor 30x30 bh Rp 40,000.00
602 Karang Tapel Tulungagung bh Rp 38,000.00
603 Karang Simbar Tulungagung bh Rp 48,000.00
604 Karang Gajah Batu Karangasem bh Rp 275,000.00
605 Karang Simbar Batu Karangasem bh Rp 65,000.00
606 Karang Tapel Batu Karangasem bh Rp 65,000.00
607 Karang Garuda Batu Karangasem bh Rp 1,250,000.00
608 Karang Wisnu Batu Karangasem bh Rp 750,000.00
609 Karang Angsa Batu Karangasem bh Rp 425,000.00
610 Ulon Batu Karangasem bh Rp 225,000.00
611 Tabing Ulon Motif Naga Batu Karangasem bh Rp 125,000.00
612 Ikut Celedu Batu Karangasem bh Rp 90,000.00
613 Terasso cor m3 Rp 7,115,000.00
614 Kapur padam / Hydrated Lime kg Rp 1,850.00
615 Tanah liat m3 Rp 1,850.00
616 Pasir halus ( diayak) m3 Rp 306,666.67
140

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
617 Pasir beton / cor Ex. 4 per 2,75 M3 m3 Rp 200,000.00
618 Pasir pasang m3 Rp 240,000.00
619 Pasir urug m3 Rp 272,727.27
620 Sirtu m3 Rp 240,000.00
621 Tanah urug m3 Rp 83,333.33
622 Agregat halus m3 Rp 285,000.00
623 Agregat kasar m3 Rp 210,000.00
624 Grave I m3 Rp 210,000.00
625 Bahan Agr. Base kelas A m3 Rp 195,000.00
626 Bahan Agr. Base kelas B m3 Rp 180,000.00
627 Bahan Agr. Base kelas C m3 Rp 180,000.00
628 Paras ex tegal saat bh Rp 28,500.00
629 Loster Keramik 30x30 bh Rp 67,500.00
630 Pas. Bata merah tebal 1 bata m3 Rp 680,500.00
631 Buis Beton 80 x 50 bh Rp 110,500.00
632 materail pengisi batu apung m2 Rp 165,000.00
633 Materail pengisi Ijuk m3 Rp 35,000.00
634 Batu Tulung Agung Penyengker m1 Rp 2,750,000.00
635 Batu Tulung Agung Paduraksa bh Rp 3,750,000.00
636 Candi Bentar T= 4.25 m Batu Karangasem unit Rp 48,500,000.00
637 Candi Bentar T= 2.50 m Batu Karangasem unit Rp 27,500,000.00
638 Batu Karangasem Penyengker m1 Rp 3,000,000.00
639 Batu Karangasem Paduraksa unit Rp 8,000,000.00
640 Candi Bentar T= 4.25 m Tulung Agung unit Rp 41,200,000.00
641 Candi Bentar T= 2.50 m Tulung Agung unit Rp 28,750,000.00
###
ASPAL DAN BAHAN PELENGKAP JALAN ###
642 Aspal kg Rp 13,200.00
643 Filler kg Rp 1,350.00
644 Kerosen/ Minyak tanah ltr Rp 10,000.00
645 Cat marka kg Rp 67,000.00
646 Geotextile m2 Rp 39,000.00
647 Aspal emulsi kg Rp 13,500.00
648 Gebalan rumput m2 Rp 37,500.00
649 Glass bead kg Rp 35,000.00
650 Pelat rambu (eng. Grade) bh Rp 565,000.00
651 Pelat rambu (high I. grade) bh Rp 455,000.00
652 Rel pengaman m1 Rp 715,000.00
653 Pemantul cahaya bh Rp 30,000.00
654 Asbuton halus ton Rp 348,500.00
m2 Rp 40,000.00
###
BETON PRACETAK ###
655 SBP Tipe U 30/20/60 (pelaluan air), T=5 (K-350) bh Rp 125,000.00
656 SBP Tipe U 30/30/120, T= 10(K-350) bh Rp 400,000.00
657 SBP Tipe U 30/50/120, T= 10(K-350) bh Rp 557,000.00
658 SBP Tipe U 40/60/120, T= 10(K-350) bh Rp 811,000.00
659 SBP Tipe U 60/80/120, T= 10(K-350) bh Rp 1,183,000.00
660 SBP Tipe U 80/80/120, T= 10(K-350) bh Rp 1,625,000.00
661 SBP Tipe U 80/100/120, T= 10(K-350) bh Rp 1,834,000.00
662 SBP Tipe U 100/100/120, T= 10(K-350) bh Rp 2,542,000.00
663 Tutup SBP Tipe U 30 T = 10 (K-350) bh Rp 284,000.00
664 Tutup SBP Tipe U 40 T = 10 (K-350) bh Rp 385,000.00
665 Tutup SBP Tipe U 50 T = 10 (K-350) bh Rp 479,000.00
666 Tutup SBP Tipe U 60 T = 60 (K-350) bh Rp 533,000.00
667 Tutup SBP Tipe U 80 T = 10 (K-350) bh Rp 798,000.00
668 Tutup SBP Tipe U 100 T = 10 (K-350) bh Rp 859,000.00
669 Box Culvert Pracetak Tipe 60/60/120, T = 20 (K-350) bh Rp 1,950,000.00
670 Box Culvert Pracetak Tipe 80/80/120, T = 20 (K-350) bh Rp 2,656,000.00
671 Box Culvert Pracetak Tipe 100/100/120, T = 20 (K-350) bh Rp 4,400,000.00
672 Box Culvert Pracetak Tipe 150/150/120, T = 20 (K-350) bh Rp 9,848,000.00
673 Box Culvert Pracetak Tipe 200/200/120, T = 20 (K-350) bh Rp 12,243,000.00
141

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
674 Box Culvert Pracetak Tipe 300/200/120, T = 20 (K-350) bh Rp 23,000,000.00
675 Box Culvert Pracetak Tipe 300/300/120, T = 20 (K-350) bh Rp 26,250,000.00
676 Frame manhole (precast K-350) set Rp 905,000.00
677 Cover manhole (precast K-350) set Rp 425,000.00
678 Box tangkapan air, T = 10 (K-350) set Rp 750,000.00
679 Tutup box tangkapan air, T = 10 (K-350) set Rp 185,000.00
680 L Shape 30.60.30.6 cm kg Rp 155,000.00
681 L Shape 30.50.30.6 cm ltr Rp 150,000.00
682 Penutup 30.30.7 kg Rp 135,000.00
683 U 80.15.30.8 cm m2 Rp 365,000.00
684 Dinding 115.30.8 cm kg Rp 354,000.00
685 Penutup 1/2 diad rad R 40-30 cm m2 Rp 385,000.00
###
PIPA ###
686 Pipa Galvanis 1/2" m1 Rp 49,500.00
687 Pipa Galvanis 3/4" m1 Rp 63,000.00
688 Pipa Galvanis 1 1/4" m1 Rp 99,000.00
689 Pipa Galvanis 1 1/2" m1 Rp 120,000.00
690 Pipa Galvanis 1" m1 Rp 91,500.00
691 Pipa Galvanis 1,5 BSA m1 Rp 360,500.00
692 Pipa Galvanis 2" m1 Rp 168,000.00
693 Pipa Galvanis 3" m1 Rp 250,000.00
694 Pipa Galvanis 4" m1 Rp 325,000.00
695 Pipa Maspion AW 1 ljr Rp 60,000.00
696 Pipa Maspion AW 1/2 ljr Rp 36,000.00
697 Pipa Maspion AW 10 ljr Rp 1,803,000.00
698 Pipa Maspion AW 1-1/2 ljr Rp 98,000.00
699 Pipa Maspion AW 1-1/4 ljr Rp 76,000.00
700 Pipa Maspion AW 12 ljr Rp 2,577,000.00
701 Pipa Maspion AW 14 ljr Rp 3,626,000.00
702 Pipa Maspion AW 16 ljr Rp 4,532,000.00
703 Pipa Maspion AW 2 ljr Rp 146,000.00
704 Pipa Maspion AW 2-1/2 ljr Rp 188,000.00
705 Pipa Maspion AW 3 ljr Rp 268,000.00
706 Pipa Maspion AW 3/4 ljr Rp 43,000.00
707 Pipa Maspion AW 4 ljr Rp 391,000.00
708 Pipa Maspion AW 5 ljr Rp 618,000.00
709 Pipa Maspion AW 6 ljr Rp 816,000.00
710 Pipa Maspion AW 8 ljr Rp 1,270,000.00
711 Pipa AW 10 ljr Rp 1,945,000.00
712 Pipa Maspion C 1 ljr Rp 25,000.00
713 Pipa Maspion C 1-1/2 ljr Rp 37,000.00
714 Pipa Maspion C 1-1/4 ljr Rp 32,000.00
715 Pipa Maspion C 2 ljr Rp 60,000.00
716 Pipa Maspion C 2-1/2 ljr Rp 87,000.00
717 Pipa Maspion C 3 ljr Rp 90,000.00
718 Pipa Maspion C 3/4 ljr Rp 17,000.00
719 Pipa Maspion C 4 ljr Rp 112,000.00
720 Pipa Maspion C 5/8 ljr Rp 10,000.00
721 Pipa Maspion D 10 ljr Rp 1,296,000.00
722 Pipa Maspion D 1-1/2 ljr Rp 54,000.00
723 Pipa Maspion D 1-1/4 ljr Rp 50,000.00
724 Pipa Maspion D 12 ljr Rp 1,767,000.00
725 Pipa Maspion D 14 ljr Rp 2,313,000.00
726 Pipa Maspion D 16 ljr Rp 2,994,000.00
727 Pipa Maspion D 2 ljr Rp 80,000.00
728 Pipa Maspion D 2-1/2 ljr Rp 104,000.00
729 Pipa Maspion D 3 ljr Rp 150,000.00
730 Pipa Maspion D 4 ljr Rp 212,000.00
731 Pipa Maspion D 5 ljr Rp 346,000.00
732 Pipa Maspion D 6 ljr Rp 420,000.00
733 Pipa Maspion D 8 ljr Rp 743,000.00
142

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
734 Pipa HDPE m1 Rp 845,500.00
735 Pipa Gas Hitan 1/2 m1 Rp 76,500.00
736 Pipa Stainless 2" m1 Rp 775,250.00
###
AKSESSORIS PIPA ###
737 Stop kran 1' bh Rp 32,500.00
738 Roof Drain bh Rp 210,000.00
739 Pompa Jet Pump GRUNDFOS JDF 18 bh Rp 2,305,000.00
740 Pompa Jet Pump GRUNDFOS JD Basic 3 bh Rp 1,910,000.00
741 Pompa Jet Pump SHIMIZU PC-250 BIT bh Rp 475,000.00
742 Tangki air stainless 1000ltr unit Rp 3,225,000.00
743 Pompa Submersible SHIMIZU h=80m unit Rp 2,600,000.00
744 Tanki air 1000 L unit Rp 3,325,000.00
###
KRAN AIR ###
745 TOTO T.30AR13V7N bh Rp 375,000.00
746 TOTO T.60N bh Rp 820,500.00
747 TOTO TX-116 LI bh Rp 3,775,000.00
748 TOTO TX-116 LEBR bh Rp 2,300,000.00
749 TOTO TX 101 LB bh Rp 1,075,000.00
750 ONDA exclusive walltaps bh Rp 112,000.00
751 ONDA exclusive basintaps bh Rp 110,500.00
752 ONDA walltaps bh Rp 77,500.00
753 ONDA sinktaps bh Rp 89,000.00
754 ONDA swinging basin bh Rp 66,000.00
755 Kran biasa bh Rp 28,750.00
756 Kran Sun ei bh Rp 52,000.00
###
HANDEL PINTU ###
757 Gradino Handel Luar HP.6106 bh Rp 187,500.00
758 Gradino Handel Luar HP.99.01 bh Rp 412,000.00
759 Solid HRE 99.14 bh Rp 305,000.00
760 ELT handle pintu dobel P99.62 set Rp 330,500.00
761 ELT handle pintu dobel PR 511.05 set Rp 610,250.00
762 ELT bulat PHB 308SS bh Rp 515,500.00
763 PALOMA HPP 502 bh Rp 998,000.00
764 PALOMA HRP 215 bh Rp 637,000.00
765 PALOMA PHP 241 bh Rp 1,120,000.00
766 DEKSON HPT 021 bh Rp 257,000.00
767 DEKSON HPT 017 bh Rp 295,000.00
768 DEKSON LHP set Rp 180,500.00
769 TIDY handle set 905 set Rp 105,500.00
770 PALOMA set handle set Rp 339,250.00
771 DLD handle bulat set Rp 105,000.00
###
READY MIX, SEMEN & AIR CAMPURAN BETON ###
772 Beton Ready Mix ###
- K100 m3 Rp 933,000.00
- K125 m3 Rp 946,000.00
- K150 m3 Rp 959,000.00
- K175 m3 Rp 973,000.00
- K200 m3 Rp 986,000.00
- K225 m3 Rp 999,000.00
- K275 m3 Rp 1,025,000.00
- K300 m3 Rp 1,109,000.00
- K325 m3 Rp 1,122,000.00
- K350 m3 Rp 1,132,000.00
- K400 m3 Rp 1,173,000.00
- K450 m3 Rp 1,225,000.00
- K500 m3 Rp 1,251,000.00
773 Damdex/ Strorox - 100 (additive) ltr Rp 58,000.00
774 Panel beton uk. 5 x 40 x 240 lbr Rp 165,000.00
143

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
775 Panel beton uk. 5 x 45 x 240 lbr Rp 170,000.00
776 Panel beton uk. 5 x 50 x 240 lbr Rp 195,000.00
777 Tiang beton uk. 320 x 17 x 18 btg Rp 295,000.00
778 Semen Bosowa 50 kg zak Rp 62,000.00
779 Semen Gresik 40 kg zak Rp 53,000.00
780 Semen Gresik 50 kg zak Rp 65,000.00
781 Semen Tiga Roga 40 kg zak Rp 52,333.33
782 Semen Tonasa 40 kg zak Rp 47,000.00
783 Semen warna/semen grouting kg Rp 15,000.00
784 MU-800 Non-Shrink Grout 40 kg zak Rp 132,000.00
785 Mortar Utama ( MU-380) Perekat Bata Ringan atau Bata Hebel 40 kg zak Rp 117,000.00
786 Mortar Utama ( MU-100) Plesteran premium 40 kg zak Rp 115,000.00
787 Mortar Utama ( MU-200) Acian plester dan beton 40 kg zak Rp 140,000.00
788 Air Campuran Beton ltr Rp 55.00
789 Floor hardener kg Rp 10,000.00
790 Waterstop PVC wsh 150 lebar 150 mm m Rp 55,000.00
791 Waterstop PVC wsh 200 lebar 200 mm m Rp 85,000.00
792 Waterstop PVC wsa 320 lebar 320 mm m Rp 145,000.00
793 Penjaga Jarak Begesting / spacer bh Rp 5,000.00
###
###
BESI BETON, ALUMUNIUM DAN PAGAR ###
794 Besi beton kg Rp 12,500.00
795 Besi beton Ø 6 polos btg Rp 34,166.67
796 Besi beton Ø 8 polos btg Rp 55,500.00
797 Besi beton Ø 10 polos btg Rp 86,333.33
798 Besi beton Ø 12 polos btg Rp 126,800.00
799 Besi beton Ø 16 polos btg Rp 227,450.00
800 Besi beton Ø 10 ulir btg Rp 90,850.00
801 Besi beton Ø 13 ulir btg Rp 153,625.00
802 Besi beton Ø 16 ulir btg Rp 233,125.00
803 Besi beton Ø 19 ulir btg Rp 330,170.00
804 Besi beton Ø 22 ulir btg Rp 446,000.00
805 Baja/ Besi WF kg Rp 16,850.00
806 Baja Ringan C 75 Axis btg Rp 120,000.00
807 Baja Ringan C 65 Axis btg Rp 110,000.00
808 Baja Ringan C 55 Axis btg Rp 82,000.00
809 Baja Ringan UK 75 0.75 Axis btg Rp 245,000.00
810 Baja Ringan UK 75 0.55 Axis btg Rp 165,000.00
811 Baja Ringan UK 60 0.55 Axis btg Rp 135,000.00
812 Reng Axix 27 0.45 btg Rp 47,500.00
813 Reng Axix 27 0.40 btg Rp 45,000.00
814 Besi plat strip kg Rp 13,500.00
815 Besi plat strip panjang 4 x 30 mm panjang 6m btg Rp 55,500.00
816 Floor dek 0.75mm m2 Rp 154,500.00
817 Floor dek 0.8mm m2 Rp 166,500.00
818 Kawat berduri roll Rp 125,000.00
819 Kawat beton RRT kg Rp 17,500.00
820 Kawat las untuk mild steel, high tensile steel dan pipe line welding kg Rp 35,000.00
821 Kawat las untuk stainless steel kg Rp 195,000.00
822 Kawat las untuk hard surfacing kg Rp 56,000.00
823 Kawat las untuk cast iron kg Rp 510,000.00
824 Kawat jaring galvanis BWG 16 (20mm x 20mm) m2 Rp 36,000.00
825 Kawat jaring galvanis BWG 16 (30mm x 30mm) m2 Rp 20,500.00
826 Kawat jaring galvanis BWG 16 (45mm x 45mm) m2 Rp 18,000.00
827 Kawat jaring galvanis BWG 16 (55mm x 55mm) m2 Rp 22,500.00
828 Kawat nyamuk m3 Rp 320,000.00
829 Pagar BRC asli T.120 diameter 6mm m' Rp 305,000.00
830 Pagar BRC asli T.150 diameter 6mm m' Rp 379,500.00
831 Pagar BRC asli T.175 diameter 7mm m' Rp 460,000.00
832 Pagar BRC asli T.190 diameter 7mm m' Rp 483,000.00
833 Pagar BRC asli T.90 diameter 6mm m' Rp 265,000.00
144

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
834 Pagar HotDip Galvanized T.120 diameter 6mm m' Rp 205,500.00
835 Pagar HotDip Galvanized T.150 diameter 7mm m' Rp 282,000.00
836 Pagar HotDip Galvanized T.175 diameter 7mm m' Rp 310,000.00
837 Pagar HotDip Galvanized T.190 diameter 7mm m' Rp 335,000.00
838 Pagar HotDip Galvanized T.90 diameter 6mm m' Rp 190,000.00
839 Tiang BRC asli T. 120 diameter 1 1/2" bh Rp 755,500.00
840 Tiang BRC asli T. 150 diameter 2" bh Rp 780,500.00
841 Tiang BRC asli T. 175 diameter 2" bh Rp 820,500.00
842 Tiang BRC asli T. 190 diameter 2" bh Rp 875,000.00
843 Tiang BRC asli T. 90 diameter 1 1/2" bh Rp 575,000.00
844 Tiang HotDip Galvanized T. 120 diameter 1 1/2" bh Rp 225,000.00
845 Tiang HotDip Galvanized T. 150 diameter 2" bh Rp 256,000.00
846 Tiang HotDip Galvanized T. 175 diameter 2" bh Rp 285,000.00
847 Tiang HotDip Galvanized T. 190 diameter 2" bh Rp 302,000.00
848 Tiang HotDip Galvanized T. 90 diameter 1 1/2" bh Rp 190,000.00
849 Wiremess M4 2,1 x 5,3 Roll Rp 2,300,000.00
850 Wiremess M5 2,1 x 5,4 Roll Rp 2,450,000.00
851 Wiremess M6 2,1 x 5,5 Roll Rp 3,691,500.00
852 Wiremess M7 2,1 x 5,6 lbr Rp 566,750.00
853 Wiremess M8 2,1 x 5,4 lbr Rp 742,000.00
854 Besi hollow (50x50x3) mm panjang 6 m btg Rp 135,500.00
855 Besi hollow (40x40x2) mm panjang 6 m btg Rp 38,000.00
856 Besi hollow (20x40x2) mm panjang 6 m btg Rp 17,500.00
857 Pintu rolling door alumunium m2 Rp 465,000.00
858 Pintu rolling door besi m3 Rp 325,000.00
859 Folding door/ pintu lipat PVC m2 Rp 1,250,000.00
860 Aluminium 4 inch YKK m1 Rp 200,000.00
861 Aluminium strip/ jalusi m1 Rp 35,000.00
862 Sealant tube Rp 45,000.00
863 Venetions blinds dan vertical blinds (tirai) m Rp 145,000.00
864 Skrup SDS 8 x 16 bh Rp 150.00
865 Skrup SDS 12 x 20 bh Rp 175.00
866 Skrup SDS 10 x 16 bh Rp 175.00
867 Dynabol 10 x 65 bh Rp 3,350.00
868 Diafrakma (PLD) bh Rp 275.00
869 Sepatu UK (PK) bh Rp 1,000.00
870 Pintu harmonika + ACC m2 Rp 1,100,000.00
871 Endstop Floordeck(side closer) m1 Rp 6,750.00
872 cross brace P220 pcs Rp 4,700.00
873 cross brace P193 pcs Rp 4,500.00
874 Main Frame 120 x 170 cm pcs Rp 8,000.00
875 Main Frame 120 x 190 cm pcs Rp 8,000.00
876 End Frame 120 x 90 cm pcs Rp 7,000.00
877 Jointpen bh Rp 2,000.00
878 jack base bh Rp 5,000.00
879 U head bh Rp 5,000.00
880 Besi lis kaca (1x1) cm m Rp 7,000.00
881 Sunscreen Alumunium m2 Rp 450,000.00
882 Pengelasan cm Rp 7,200.00
883 Rangka C 75068 @ 7 m galvalume btg Rp 125,000.00
884 Reng (butten Ω 30) @ 6 m Btg Rp 45,000.00
885 Reng pengikat kuda-kuda @ 6 m Btg Rp 40,000.00
886 Pelat strips @ 1 m Bh Rp 15,000.00
887 Baut kuda-kuda SDS 6-19 Bh Rp 200.00
888 Baut reng SDS 6-16 Btg Rp 200.00
889 Baut listplank Ø 6-70 Bh Rp 700.00
890 Dinabold Ø 10-65 Bh Rp 2,850.00
###
###
###
###
###
145

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
BAHAN LISTRIK ###
891 Box panel MCB Inbow isi 4 MCB Hager bh Rp 215,000.00
892 Box panel MCB outbow isi 5 MCB Hager bh Rp 245,000.00
893 Box panel MCB Mini pragma Schneider isi 4 MCB bh Rp 30,000.00
894 Box panel MCB outbow golf isi 4 MCB Hager bh Rp 200,000.00
895 Box panel MCB inbow golf isi 4 MCB Hager bh Rp 210,000.00
896 Isolasi bh Rp 10,000.00
897 Saklar tunggal ( Clipsal) bh Rp 24,500.00
898 Saklar seri (clipsal) bh Rp 37,000.00
899 Saklar triple (clipsal) bh Rp 51,250.00
900 Stop Kontak (setara clipsal) bh Rp 29,500.00
901 Stop Kontak AC setara broco bh Rp 58,000.00
902 Fitting bh Rp 11,500.00
903 Steker bh Rp 11,500.00
904 Coaxial cable 5C - 75 ohm commscof m1 Rp 5,000.00
905 Kabel NYM 3 x 2.5 mm ex. Supreme m1 Rp 17,850.00
906 Kabel NYM 4 mm m1 Rp 22,000.00
907 Kabel telephone m1 Rp 4,000.00
908 Kabel antena 5C Beldcu m1 Rp 5,000.00
909 Kabel Data Belden m1 Rp 6,000.00
910 Lampu pijar 8 Watt (Philip) bh Rp 23,000.00
911 Lampu pijar 10 Watt (Philip) bh Rp 23,333.33
912 Lampu pijar 15 Watt (Philip) bh Rp 19,000.00
913 Lampu pijar 25 Watt (Philip) bh Rp 20,000.00
914 Lampu TL 10 Watt (10 Watt) Philip bh Rp 60,000.00
915 Lampu TL 20 Watt (10 Watt) Philip bh Rp 20,000.00
916 Lampu TL 25 Watt (10 Watt) Philip bh Rp 25,000.00
917 Lampu TL 2 x 18 watt RMI Philips TL LED unt Rp 425,000.00
918 Lampu TL 2 x 18 watt RMI Hori TL LED unt Rp 795,000.00
919 Lampu TL 2 x 36 watt RMI Philips TL LED unt Rp 625,000.00
920 Lampu LED Strips / Lampu Selang 7.2 watt m1 Rp 35,000.00
921 Led Ultra Thin Downlight DQ-MBR-002 ( Ø145mm) 9 Watt setara Hori bh Rp 93,000.00
922 Downlight/ PLC 13 watt bh Rp 182,000.00
923 Fitting plafond + led bulb 13 watt hori bh Rp 80,000.00
924 Led bulb 13 watt hori bh Rp 70,000.00
925 Fitting Tempel bh Rp 13,500.00
926 MCB 6 A Schneider bh Rp 53,000.00
927 MCB 4 A Schneider bh Rp 61,666.67
928 Outlet TV clipsal bh Rp 58,000.00
929 Outlet telepon bh Rp 56,000.00
930 Outlet data panasonic WEJ2488 bh Rp 73,000.00
931 Outlet exausfan bh Rp 6,000.00
932 Pipa clipsal 20 mm bt Rp 17,000.00
933 Pipa flexible clipsal 20 mm m1 Rp 6,900.00
934 Sock clipsal 20 mm bj Rp 5,333.33
935 Tee dos clipsal 20 mm bh Rp 8,833.33
936 Klem clipsal 20 mm bj Rp 1,150.00
937 Inbow dos plastik clipsal E 157 P bj Rp 9,333.33
938 Stop kontak terminal tv tanam panasinic wej 2501 + plat wej 78019 bj Rp 51,500.00
939 MCCB 80A 3P MG bj Rp 525,000.00
940 MCB 25A 3P MG bj Rp 187,500.00
941 MCB16A 1P MG bj Rp 59,500.00
942 MCB10A 1P MG bj Rp 54,500.00
943 MCB 6A 1P MG bj Rp 54,500.00
944 Pilot lamp / indikator lamp 220 V bj Rp 90,000.00
945 Voltmeter 0 - 500V bj Rp 125,000.00
946 Ampere meter 0 - 200A bj Rp 115,000.00
947 Travo Arus / CT bj Rp 98,000.00
948 selector Volt 7 position bj Rp 125,000.00
949 Wiring material bj Rp 1,005,000.00
146

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
950 Box indoor 600 x 400 x 250 EX- HAGER bj Rp 2,900,000.00
951 CU bars + asesoris bj Rp 975,000.00
952 fire extinguizer 9 kg setara VIKING unit Rp 2,100,000.00
953 AC Wall Mounted 2 PK Setara DAIKIN unit Rp 6,610,000.00
954 AC Wall Mounted 1 PK Setara DAIKIN unit Rp 4,200,000.00
955 Exaust pan celling PANASONIC FV-20TGU 8" unit Rp 350,000.00
956 Exaust Hood Modena PX 6001 unit Rp 795,000.00
957 Blacksem 1" bh Rp 85,000.00
958 Sok Galvanis 1" bh Rp 15,000.00
959 Kawat BC 50 mm2 m1 Rp 87,000.00
960 Klem Begel 1" bh Rp 3,500.00
961 Klem sisir 50 mm2 bh Rp 25,000.00
962 Kotak Kontrol 10 cm x 15 cm bh Rp 55,000.00
963 Perluv sok 1" bh Rp 5,000.00
964 Pipa Conduit PVC 3/4" bt Rp 21,000.00
###
###
BUIS BETON ###
965 Buis beton 20 x 75 x 3 bh Rp 45,000.00
966 Buis beton 25 x 75 x 3 bh Rp 51,500.00
967 Buis beton 30 x 75 x 3 bh Rp 67,500.00
968 Buis beton 40 x 75 x 5 bh Rp 82,500.00
969 Buis beton 50 x 75 x 5 bh Rp 117,500.00
970 Buis beton 80 x 75 x 7.5 bh Rp 105,000.00
971 Buis beton 100 x 50 x 7.5 bh Rp 139,500.00
###
PAVING ###
972 Paving 10 x 20 cm tebal 6 cm K225 Pc m2 Rp 71,000.00
973 Paving 10 x 20 cm tebal 6 cm K225 merah m2 Rp 99,000.00
974 Paving 10 x 20 cm tebal 6 cm K225 hitam m2 Rp 101,000.00
975 Paving 10 x 20 cm tebal 6 cm K300 Pc m2 Rp 83,500.00
976 Paving 10 x 20 cm tebal 6 cm K300 merah m2 Rp 103,500.00
977 Paving 10 x 20 cm tebal 6 cm K300 hitam m2 Rp 118,500.00
978 Paving 10 x 20 cm tebal 6 cm K350 Pc m2 Rp 91,000.00
979 Paving 10 x 20 cm tebal 6 cm K350 merah m2 Rp 111,000.00
980 Paving 10 x 20 cm tebal 6 cm K350 hitam m2 Rp 126,000.00
981 Paving 10 x 20 cm tebal 8 cm K225 Pc m2 Rp 81,000.00
982 Paving 10 x 20 cm tebal 8 cm K225 merah m2 Rp 106,000.00
983 Paving 10 x 20 cm tebal 8 cm K225 hitam m2 Rp 121,000.00
984 Paving 10 x 20 cm tebal 8 cm K300 Pc m2 Rp 93,500.00
985 Paving 10 x 20 cm tebal 8 cm K300 merah m2 Rp 113,500.00
986 Paving 10 x 20 cm tebal 8 cm K300 hitam m2 Rp 128,500.00
987 Paving 10 x 20 cm tebal 8 cm K350 Pc m2 Rp 92,000.00
988 Paving 10 x 20 cm tebal 8 cm K350 merah m2 Rp 112,000.00
989 Paving 10 x 20 cm tebal 8 cm K350 hitam m2 Rp 142,000.00
990 Paving 10 x 20 cm tebal 8 cm K400 Pc m2 Rp 92,000.00
991 Paving 10 x 20 cm tebal 8 cm K400 merah m2 Rp 112,000.00
992 Paving 10 x 20 cm tebal 8 cm K400 hitam m2 Rp 142,000.00
993 Paving 20 x 20 cm tebal 6 cm K225 Pc m2 Rp 76,333.33
994 Paving 20 x 20 cm tebal 6 cm K225 merah m2 Rp 99,000.00
995 Paving 20 x 20 cm tebal 6 cm K225 hitam m2 Rp 101,000.00
996 Paving 20 x 20 cm tebal 6 cm K300 Pc m2 Rp 83,500.00
997 Paving 20 x 20 cm tebal 6 cm K300 merah m2 Rp 103,500.00
998 Paving 20 x 20 cm tebal 6 cm K300 hitam m2 Rp 106,000.00
999 Paving 20 x 20 cm tebal 6 cm K350 Pc m2 Rp 82,000.00
1000 Paving 20 x 20 cm tebal 6 cm K350 merah m2 Rp 102,000.00
1001 Paving 20 x 20 cm tebal 6 cm K350 hitam m2 Rp 132,000.00
1002 Paving 20 x 20 cm tebal 8 cm K225 Pc m2 Rp 91,000.00
1003 Paving 20 x 20 cm tebal 8 cm K225 merah m2 Rp 102,000.00
1004 Paving 20 x 20 cm tebal 8 cm K225 hitam m2 Rp 132,000.00
1005 Paving 20 x 20 cm tebal 8 cm K300 Pc m2 Rp 83,500.00
147

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
1006 Paving 20 x 20 cm tebal 8 cm K300 merah m2 Rp 108,500.00
1007 Paving 20 x 20 cm tebal 8 cm K300 hitam m2 Rp 128,500.00
1008 Paving 20 x 20 cm tebal 8 cm K350 Pc m2 Rp 106,000.00
1009 Paving 20 x 20 cm tebal 8 cm K350 merah m2 Rp 112,000.00
1010 Paving 20 x 20 cm tebal 8 cm K350 hitam m2 Rp 142,000.00
1011 Paving 20 x 20 cm tebal 8 cm K400 Pc m2 Rp 92,000.00
1012 Paving 20 x 20 cm tebal 8 cm K400 merah m2 Rp 112,000.00
1013 Paving 20 x 20 cm tebal 8 cm K400 hitam m2 Rp 142,000.00
1014 Paving 20 x 20 cm tebal 10 cm K225 Pc m2 Rp 87,000.00
1015 Paving 20 x 20 cm tebal 10 cm K225 merah m2 Rp 107,000.00
1016 Paving 20 x 20 cm tebal 10 cm K225 hitam m2 Rp 137,000.00
1017 Paving 20 x 20 cm tebal 10 cm K300 Pc m2 Rp 92,000.00
1018 Paving 20 x 20 cm tebal 10 cm K300 merah m2 Rp 112,000.00
1019 Paving 20 x 20 cm tebal 10 cm K300 hitam m2 Rp 142,000.00
1020 Paving 20 x 20 cm tebal 10 cm K350 Pc m2 Rp 97,000.00
1021 Paving 20 x 20 cm tebal 10 cm K350 merah m2 Rp 117,000.00
1022 Paving 20 x 20 cm tebal 10 cm K350 hitam m2 Rp 147,000.00
1023 Paving 20 x 20 cm tebal 10 cm K400 Pc m2 Rp 102,000.00
1024 Paving 20 x 20 cm tebal 10 cm K400 merah m2 Rp 122,000.00
1025 Paving 20 x 20 cm tebal 10 cm K400 hitam m2 Rp 152,000.00
1026 Paving segi enam xexagon 6 cm K225 Pc m2 Rp 72,000.00
1027 Paving segi enam xexagon 6 cm K225 merah m2 Rp 98,000.00
1028 Paving segi enam xexagon 6 cm K225 hitam m2 Rp 102,000.00
1029 Paving segi enam xexagon 6 cm K300 Pc m2 Rp 77,000.00
1030 Paving segi enam xexagon 6 cm K300 merah m2 Rp 97,000.00
1031 Paving segi enam xexagon 6 cm K300 hitam m2 Rp 127,000.00
1032 Paving segi enam xexagon 6 cm K350 Pc m2 Rp 92,000.00
1033 Paving segi enam xexagon 6 cm K350 merah m2 Rp 112,000.00
1034 Paving segi enam xexagon 6 cm K350 hitam m2 Rp 142,000.00
1035 Paving segi enam xexagon 6 cm K400 Pc m2 Rp 97,000.00
1036 Paving segi enam xexagon 6 cm K400 merah m2 Rp 117,000.00
1037 Paving segi enam xexagon 6 cm K400 hitam m2 Rp 147,000.00
1038 Paving kotak bujur sangkar tanpa tias 6 cm K225 Pc m2 Rp 75,000.00
1039 Paving kotak bujur sangkar tanpa tias 6 cm K225 merah m2 Rp 95,000.00
1040 Paving kotak bujur sangkar tanpa tias 6 cm K225 hitam m2 Rp 105,000.00
1041 Paving kotak bujur sangkar tanpa tias 8 cm K225 Pc m2 Rp 85,000.00
1042 Paving kotak bujur sangkar tanpa tias 8 cm K225 merah m2 Rp 105,000.00
1043 Paving kotak bujur sangkar tanpa tias 8 cm K225 hitam m2 Rp 115,000.00
1044 Paving Tiga Berlian tebal 6 cm K225 Pc m2 Rp 72,000.00
1045 Paving Tiga Berlian tebal 6 cm K350 Pc m2 Rp 92,000.00
1046 Kanstein kotak (P:50,T:20,La:10,Lb:16 cm K225) bh Rp 70,000.00
1047 Kanstein Bulat (P:50,T:30,La:10,Lb:16 cm K225) bh Rp 80,000.00
1048 Kanstein Jumbo (P:50,L:15,T:30 cm K225) bh Rp 80,000.00
1049 Kanstein Segi Lima (P:50,L:15, T:20 cm K225) bh Rp 50,000.00
1050 Kanstein Segi Lima (P:40,L:10, T:20 cm K225) bh Rp 80,000.00
1051 Kanstein Segi Lima jumbo(P:50,L:15, T:40 cm K225) bh Rp 80,000.00
1052 Kanstein kursi ( P:50, L:10, T:40 cm, lb 17,5 cm K225 ) bh Rp 90,000.00
1053 Kanstein kursi ( P:50, L:10, T:40 cm, lb 17,5 cm K300 ) bh Rp 95,000.00
1054 Grass Block lobang 8, 36 X 54 cm tebal 9 cm K 225 m2 Rp 82,000.00
1055 Grass Block lobang 5, 30 X 30 cm tebal 7 cm K 225 m2 Rp 76,000.00
1056 Tutup got (grill) P. 45, L. 24, T.9cm K350 bh Rp 40,000.00
1057 Tutup got (grill) P. 30, L. 24, T.9cm K350 bh Rp 37,000.00
1058 Tutup kabel PLN P.20, L.40, T.6cm bh Rp 6,000.00
1059 Tutup uskup 8 cm bj Rp 9,500.00
1060 Koral Sikat Lokal (10 Kg) zak Rp 46,000.00
1061 Koral Sikat Alor (8 Kg) zak Rp 112,000.00
###
LAIN-LAIN + STYLE BALI ###
1062 Wall papper 30,5 x 30,5 lembar Rp 112,000.00
1063 Wall papper 70 x 100 lembar Rp 116,000.00
1064 Wall papper 50 x 100 lembar Rp 94,500.00
148

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
1065 Wall papper 30 x 60 lembar Rp 50,000.00
1066 Glass block bj Rp 30,000.00
1067 Dugul batu hitam 50 x 50 x 200 tempel unit Rp 7,500,000.00
1068 Dugul batu hitam 60 x 70 x 250 tempel unit Rp 10,000,000.00
1069 Dugul batu hitam 70 x 70 x 250 tempel unit Rp 11,000,000.00
1070 Padmasari batu hitam 50 x 50 x 200 tempel unit Rp 7,000,000.00
1071 Padmasari batu hitam 65 x 75 x 255 tempel unit Rp 9,500,000.00
1072 Padmasari batu hitam 70 x 70 x 250 tempel unit Rp 10,500,000.00
1073 Dugul batu hitam 50 x 50 x 200 masive unit Rp 7,500,000.00
1074 Dugul batu hitam 60 x 70 x 250 masive unit Rp 10,000,000.00
1075 Dugul batu hitam 70 x 70 x 300 masive unit Rp 11,000,000.00
1076 Padmasari batu hitam 50 x 50 x 200 masive unit Rp 7,000,000.00
1077 Padmasari batu hitam 65 x 75 x 255 masive unit Rp 9,500,000.00
1078 Padmasari batu hitam 70 x 70 x 250 masive unit Rp 10,500,000.00
1079 Padmasari paras taro 50 x 70 x 250 unit Rp 1,500,000.00
1080 Padmasari paras taro 65 x 65 x 250 unit Rp 1,500,000.00
1081 Padmasari paras taro 65 x 65 x 250 unit Rp 1,500,000.00
1082 Ukiran Bunga Besar paras jogya bh Rp 90,000.00
1083 Ukiran Bunga Kecil paras jogya bh Rp 55,000.00
1084 Apit-apit kayu profil m1 Rp 50,000.00
1085 Saka Kayu Jati Ukir bh Rp 775,000.00
1086 Saka Kayu Jati Kupak bh Rp 425,000.00
1087 Saka Kayu Merbau Ukir bh Rp 1,475,000.00
1088 Saka Kayu Merbau Kupak bh Rp 1,125,000.00
1089 Kencut Saka Kayu Jati bh Rp 150,000.00
1090 Kencut Saka Kayu Merbau bh Rp 450,000.00
1091 Cangah Wang Kayu Jati Ukir bh Rp 550,000.00
1092 Cangah Wang Kayu Jati Kupak bh Rp 200,000.00
1093 Cangah Wang Kayu Merbau Ukir bh Rp 850,000.00
1094 Cangah Wang Kayu Merbau Kupak bh Rp 500,000.00
1095 Pementang Kayu Jati ukir m1 Rp 1,050,000.00
1096 Pementang Kayu Jati kupak m1 Rp 350,000.00
1097 Pementang Kayu Merbau ukir m1 Rp 1,550,000.00
1098 Pementang Kayu Merbau kupak m1 Rp 850,000.00
1099 Dedeleg Kayu Jati ukir m1 Rp 1,550,000.00
1100 Dedeleg Kayu Merbau ukir m1 Rp 850,000.00
1101 Tugeh Kayu Jati Ukir bh Rp 450,000.00
1102 Tugeh Kayu Jati Kupak bh Rp 200,000.00
1103 Tugeh Kayu Merbau Ukir bh Rp 660,000.00
1104 Tugeh Kayu Merbau Kupak bh Rp 410,000.00
1105 Barba Kayu Jati Ukir bh Rp 9,000,000.00
1106 Sendi Marmer bh Rp 200,000.00
###
###
PEKERJAAN SOFTSCAPE ###
A POHON ###
1107 Tanaman Kamboja dia 10 cm phn Rp 625,000.00
1108 Tanaman Kamboja dia 15 cm phn Rp 875,000.00
1109 Tanaman Pule dia 60 - 75 cm phn Rp 3,000,000.00
1110 Tanaman Pule dia 75 - 90 cm phn Rp 1,800,000.00
1111 Jepun Fosil dia 30 - 50 cm phn Rp 6,000,000.00
1112 Pohon Dolar t= 2 - 3 cm phn Rp 7,000.00
1113 Jepun Fosil dia 15 - 25 cm phn Rp 4,500,000.00
1114 Tanaman Glodogan dia 10 cm phn Rp 600,000.00
1115 Tanaman Glodogan dia 15 cm phn Rp 800,000.00
1116 Tanaman Ketapang Kencana Tinggi = 3 m phn Rp 1,200,000.00
1117 Tanaman Pucuk Merah Tinggi 1 m phn Rp 220,000.00
1118 Tanaman Dadap Merah dia 10 cm phn Rp 250,000.00
1119 Tanaman Dadap Merah dia 15 cm phn Rp 450,000.00
149

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
1120 Tanaman Rumput Mutiara m2 Rp 30,000.00
1121 Tanaman Rumput Bermuda m2 Rp 50,000.00
1122 Tanaman Pisang - Pisangan m2 Rp 30,000.00
1123 Penanaman Rumput Jepang m2 Rp 30,000.00
###
B SEMAK PERDU ###
1124 Kaki Laba - Laba ( Ararea ) m2 Rp 7,500.00
1125 Corrymbousa Mini m2 Rp 10,000.00
1126 Pangkas Kuning m2 Rp 2,250.00
1127 Kacang - Kacangan m2 Rp 2,250.00
1128 Penanaman Le Kwan Yew m1 Rp 2,500.00
1129 Bambu Jakarta rumpun Rp 50,000.00
1130 Puring Kirana phn Rp 20,000.00
1131 Puring Nuri phn Rp 5,000.00
1132 Puring Bor Merah phn Rp 5,000.00
1133 Puring Bor Kuning phn Rp 5,500.00
1134 Soka India phn Rp 10,000.00
1135 Walisongo phn Rp 7,500.00
1136 Bougenville Variegata phn Rp 15,000.00
1137 Bunga Kembang Pukul Sembilan phn Rp 3,000.00
1138 Tanah Urug Subur m3 Rp 1,500.00
1139 Pupuk Kandang / Kompos m3 Rp 2,500,000.00
1140 Tanaman Pandan Merah phn Rp 25,000.00
1141 Tanaman Pandan Afrika phn Rp 25,000.00
1142 Tanaman Jaburan Hijau phn Rp 2,250.00
1143 Tanaman Jaburan Putih phn Rp 2,250.00
1144 Tanaman Leli phn Rp 5,000.00
1145 Tanaman Sirih Belanda phn Rp 4,000.00
1146 Tanaman Rosalia phn Rp 4,500.00
1147 Tanaman Pasok 1,5 m phn Rp 350,000.00
1148 Tanaman Andong 1 m phn Rp 15,000.00
1149 Tanaman Kembang Sepatu 1,5 m phn Rp 25,000.00
1150 Tanaman Bunga Portulaca phn Rp 50,000.00
1151 Tanaman Onje 1,2 m phn Rp 25,000.00
1152 Tanaman Soka 1 m phn Rp 20,000.00
1153 Pohon Maja phn Rp 750,000.00
1154 Plumera Rubra ( Kamboja Merah) dia 40 - 60 cm phn Rp 1,250,000.00
1155 Pisang Karibia phn Rp 80,000.00
1156 Cortadera Selloana phn Rp 30,000.00
1157 Bambusa Vulgaris (Bambu Kuning) phn Rp 47,500.00
1158 Calathea Lutea phn Rp 25,000.00
1159 Ruellia Brittoniana phn Rp 4,000.00
1160 Lantana Camara phn Rp 2,500.00

PIPA & ACCESSORIES


1161 PVC PIPA Ts. S. 10 Ø 1" m1 Rp 10,833.33
1162 PVC PIPA Ts S. 10 Ø 1 1/2" m1 Rp 25,293.33
1163 PVC PIPA R - R S. 10 Ø 2" m1 Rp 41,726.67
1164 PVC PIPA R - R S. 10 Ø Ø 3" m1 Rp 83,861.67
1165 PVC PIPA R - R S. 10 Ø Ø 4" m1 Rp 125,703.33
1166 PVC PIPA R - R S. 10 Ø Ø 6" m1 Rp 263,616.67
1167 PVC PIPA R - R S. 10 Ø Ø 8" m1 Rp 422,041.67
1168 PVC PIPA R - R S. 10 Ø Ø 10" m1 Rp 360,706.67
1169 PVC PIPA R - R S. 10 Ø Ø 12" m1 Rp 538,576.67
1170 PVC PIPA R - R S. 10 Ø Ø 14" m1 Rp 1,573,504.17
1171 PVC PIPA R - R S. 10 Ø Ø 16" m1 Rp 904,240.83
1172 PVC PIPA R - R S. 10 Ø Ø 18" m1 Rp 1,106,021.67
1173 PVC PIPA R - R S. 10 Ø 20" m1 Rp 2,638,985.00
1174 PVC PIPA R - R S. 10 Ø 24" m1 Rp 3,977,449.17
1175 GI PIPA MEDIUM SII Ø 1/2" m1 Rp 2,284,029.17
1176 GI PIPA MEDIUM SII Ø 3/4" m1 Rp 96,166.67
150

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
1177 GI PIPA MEDIUM SII Ø 1" m1 Rp 128,889.17
1178 GI PIPA MEDIUM SII Ø 1 1/2" m1 Rp 186,901.67
1179 GI PIPA MEDIUM SII Ø 2" m1 Rp 93,683.33
1180 GI PIPA MEDIUM SII Ø 2 1/2" m1 Rp 287,554.17
1181 GI PIPA MEDIUM SII Ø 3" m1 Rp 427,930.00
1182 GI PIPA MEDIUM SII Ø 4" m1 Rp 580,175.83
1183 GI PIPA MEDIUM SII Ø 6" m1 Rp 910,851.67
1184 GI PIPA MEDIUM SII Ø 8" m1 Rp 976,396.67
1185 BS PIPA SCH 40 Ø 4" m1 Rp 230,808.33
1186 BS PIPA SCH 40 Ø 5" m1 Rp 255,066.67
1187 BS PIPA SCH 40 Ø 6" m1 Rp 380,771.67
1188 BS PIPA SCH 40 Ø 8" m1 Rp 601,936.67
1189 PIPA HDPE Ø 20 mm m1 Rp 29,330.00
1190 PIPA HDPE Ø 25 mm m1 Rp 889,050.00
1191 PIPA HDPE Ø 32 mm m1 Rp 1,165,600.00
1192 WM Lengkap Brass Meter Coup Ø 1/2" bh Rp 1,644,500.00
1193 WM Lengkap Brass Meter Coup Ø 3/4" bh Rp 581,000.00
1194 WM Lengkap Brass Meter Coup Ø 1" bh Rp 973,625.00
1195 WM Lengkap Brass Meter Coup Ø 1 1/2" bh Rp 1,235,455.00
1196 Bronze Gate Valve Ø 1/2" bh Rp 86,750.00
1197 Bronze Gate Valve Ø 3/4" bh Rp 129,000.00
1198 Bronze Gate Valve Ø 1" bh Rp 230,000.00
1199 Bronze Gate Valve Ø 1 1/2" bh Rp 444,500.00
1200 Bronze Gate Valve Ø 2" bh Rp 634,500.00
1201 Bronze Gate Valve Ø 3" bh Rp 1,841,750.00
1202 Gate Valve Drat 125 PSI FH Ø 1/4" bh Rp 269,286.00
1203 Gate Valve Drat 125 PSI FH Ø 3/8" bh Rp 269,286.00
1204 Gate Valve Drat 125 PSI FH Ø 1/2" bh Rp 271,728.00
1205 Gate Valve Drat 125 PSI FH Ø 3/4" bh Rp 340,215.00
1206 Gate Valve Drat 125 PSI FH Ø 1" bh Rp 471,306.00
1207 Gate Valve Drat 125 PSI FH Ø 1 1/4" bh Rp 656,232.00
1208 Gate Valve Drat 125 PSI FH Ø 1 1/2" bh Rp 827,283.00
1209 Gate Valve Drat 125 PSI FH Ø 2" bh Rp 1,243,422.00
1210 Gate Valve Drat 125 PSI FH Ø 2 1/2" bh Rp 2,652,012.00
1211 Gate Valve Drat 125 PSI FH Ø 3" bh Rp 3,616,491.00
1212 Strainer Valve F/F 10 K Ø 2" bh Rp 2,733,264.00
1213 Strainer Valve F/F 10 K Ø 2 1/2" bh Rp 4,425,570.00
1214 Strainer Valve F/F 10 K Ø 3" bh Rp 5,354,529.00
1215 Strainer Valve F/F 10 K Ø 4" bh Rp 7,466,415.00
1216 Strainer Valve F/F 10 K Ø 5" bh Rp 11,325,330.00
1217 Strainer Valve F/F 10 K Ø 6" bh Rp 15,693,624.00
1218 Strainer Valve F/F 10 K Ø 8" bh Rp 23,466,399.00
1219 Strainer Valve F/F 10 K Ø 10" bh Rp 40,339,287.00
1220 Strainer Valve F/F 10 K Ø 12" bh Rp 67,515,306.00
1221 Strainer Valve F/F 16 K Ø 2" bh Rp 7,737,921.00
1222 Strainer Valve F/F 16 K Ø 2 1/2" bh Rp 11,741,469.00
1223 Strainer Valve F/F 16 K Ø 3" bh Rp 14,563,089.00
1224 Strainer Valve F/F 16 K Ø 4" bh Rp 19,476,837.00
1225 Strainer Valve F/F 16 K Ø 5" bh Rp 30,945,357.00
1226 Strainer Valve F/F 16 K Ø 6" bh Rp 39,318,309.00
1227 Strainer Valve F/F 16 K Ø 8" bh Rp 53,697,138.00
1228 Strainer Valve F/F 16 K Ø 10" bh Rp 92,103,804.00
1229 GI Double Nipple Ø 1/2" bh Rp 5,660.00
1230 GI Double Nipple Ø 3/4" bh Rp 7,550.00
1231 GI Double Nipple Ø 1" bh Rp 10,570.00
1232 GI Double Nipple Ø 1 1/4" bh Rp 15,470.00
1233 GI Double Nipple Ø 1 1/2" bh Rp 21,510.00
1234 GI Double Nipple Ø 2" bh Rp 29,440.00
1235 GI Double Nipple Ø 3" bh Rp 83,030.00
1236 GI Double Nipple Ø 4" bh Rp 141,340.00
1237 GI Elbow / Knee Ø 1/2" bh Rp 6,420.00
151

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
1238 GI Elbow / Knee Ø 3/4" bh Rp 9,700.00
1239 GI Elbow / Knee Ø 1" bh Rp 14,130.00
1240 GI Elbow / Knee Ø 1 1/4" bh Rp 22,610.00
1241 GI Elbow / Knee Ø 1 1/2" bh Rp 28,270.00
1242 GI Elbow / Knee Ø 2" bh Rp 44,420.00
1243 GI Elbow / Knee Ø 2 1/2" bh Rp 84,800.00
1244 GI Elbow / Knee Ø 3" bh Rp 129,220.00
1245 GI Elbow / Knee Ø 4" bh Rp 234,210.00
1246 PVC Elbow Ts Ø 1/2" bh Rp 2,950.00
1247 PVC Elbow Ts Ø 3/4" bh Rp 3,850.00
1248 PVC Elbow Ts Ø 1" bh Rp 5,500.00
1249 PVC Elbow Ts Ø 1 1/4" bh Rp 9,500.00
1250 PVC Elbow Ts Ø 1 1/2" bh Rp 13,300.00
1251 PVC Elbow Ts Ø 2" bh Rp 19,900.00
1252 PVC Elbow Ts Ø 3" bh Rp 52,500.00
1253 PVC Elbow Ts Ø 4" bh Rp 96,500.00
1254 PVC Bend R - R Ø 3" x 90" bh Rp 202,400.00
1255 PVC Bend R - R Ø 3" x 45" bh Rp 177,750.00
1256 PVC Bend R - R Ø 4" x 45" bh Rp 254,390.00
1257 PVC Bend R - R Ø 4" x 90" bh Rp 278,360.00
1258 PVC Bend R - R Ø 6" x 45" bh Rp 501,910.00
1259 PVC Bend R - R Ø 6" x 90" bh Rp 560,030.00
1260 PVC Bend R - R Ø 8" x 45" bh Rp 855,880.00
1261 PVC Bend R - R Ø 8" x 90" bh Rp 976,400.00
1262 GI Plug Ø 1/2" bh Rp 4,850.00
1263 GI Plug Ø 3/4" bh Rp 5,660.00
1264 GI Plug Ø 1" bh Rp 8,080.00
1265 GI Plug Ø 1 1/4" bh Rp 12,110.00
1266 GI Plug Ø 1 1/2" bh Rp 14,130.00
1267 GI Plug Ø 2" bh Rp 20,190.00
1268 GI Plug Ø 2 1/2" bh Rp 40,380.00
1269 GI Plug Ø 3" bh Rp 56,530.00
1270 GI Cap / Dop Ø 1/2" bh Rp 5,660.00
1271 GI Cap / Dop Ø 3/4" bh Rp 6,870.00
1272 GI Cap / Dop Ø 1" bh Rp 9,700.00
1273 GI Cap / Dop Ø 1 1/4" bh Rp 14,130.00
1274 GI Cap / Dop Ø 1 1/2" bh Rp 18,570.00
1275 GI Cap / Dop Ø 2" bh Rp 25,850.00
1276 GI Cap / Dop Ø 2 1/2" bh Rp 52,500.00
1277 GI Cap / Dop Ø 3" bh Rp 72,690.00
1278 Gi Tee Ø 1/2" x 1/2" bh Rp 8,480.00
1279 Gi Tee Ø 3/4" 1/2" bh Rp 16,550.00
1280 Gi Tee Ø 3/4" x 3/4" bh Rp 12,510.00
1281 Gi Tee Ø 1" x 1/2" bh Rp 25,440.00
1282 Gi Tee Ø 1" x 3/4" bh Rp 25,440.00
1283 Gi Tee Ø 1" x 1" bh Rp 19,790.00
1284 Gi Tee Ø 1 1/2" x 1/2" bh Rp 48,460.00
1285 Gi Tee Ø 1 1/2" x 3/4" bh Rp 48,460.00
1286 Gi Tee Ø 1 1/2" x 1" bh Rp 48,460.00
1287 Gi Tee Ø 1 1/2" x 1 1/2" bh Rp 37,960.00
1288 Gi Tee Ø 2" x 3/4" bh Rp 68,650.00
1289 Gi Tee Ø 2" x 1" bh Rp 69,650.00
1290 Gi Tee Ø 2" x 1 1/2" bh Rp 68,650.00
1291 Gi Tee Ø 2" x 2" bh Rp 56,530.00
1292 Gi Tee Ø 3" x 1 1/2" bh Rp 201,910.00
1293 Gi Tee Ø 3" x 2" bh Rp 183,550.00
1294 Gi Tee Ø 3" x 3" bh Rp 169,600.00
1295 GI Coupling Ø 1/2" bh Rp 5,660.00
1296 GI Coupling Ø 3/4" bh Rp 7,270.00
1297 GI Coupling Ø 1" bh Rp 12,140.00
1298 GI Coupling Ø 1 1/4" bh Rp 16,960.00
152

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
1299 GI Coupling Ø 1 1/2" bh Rp 21,000.00
1300 GI Coupling Ø 2" bh Rp 32,310.00
1301 GI Coupling Ø 2 1/2" bh Rp 60,570.00
1302 GI Coupling Ø 3" bh Rp 88,840.00
1303 GI Coupling Ø 4" bh Rp 145,730.00
1304 GI Coupling Ø 3/4 x 1/2" bh Rp 9,700.00
1305 GI Reducer Ø 1' x 1/2" bh Rp 12,920.00
1306 GI Reducer Ø 1" x 3/4" bh Rp 12,920.00
1307 GI Reducer Ø 2 x 3/4" bh Rp 34,320.00
1308 GI Reducer Ø 2" x 1" bh Rp 34,320.00
1309 GI Reducer Ø 2 x 1/2" bh Rp 34,320.00
1310 GI Reducer Ø 3" x 2" bh Rp 100,960.00
1311 GI Reducer Ø 3" x 2 1/2" bh Rp 100,960.00
1312 GI Water Moer Ø 1/2" bh Rp 23,020.00
1313 GI Water Moer Ø 3/4" bh Rp 26,420.00
1314 GI Water Moer Ø 1" bh Rp 32,080.00
1315 GI Water Moer Ø 1 1/4" bh Rp 48,460.00
1316 GI Water Moer Ø 1 1/2" bh Rp 64,610.00
1317 GI Water Moer Ø 2" bh Rp 92,880.00
1318 GI Water Moer Ø 2 1/2" bh Rp 161,530.00
1319 GI Water Moer Ø 3" bh Rp 254,400.00
1320 GI Water Moer Ø 4" bh Rp 254,400.00
1321 GI Water Moer Ø 5" bh Rp 484,580.00
1322 PVC Valve Socket Ø 1/2" bh Rp 7,500.00
1323 PVC Valve Socket Ø 3/4" bh Rp 9,450.00
1324 PVC Valve Socket Ø 1" bh Rp 13,100.00
1325 PVC Valve Socket Ø 1 1/2" bh Rp 28,800.00
1326 PVC Valve Socket Ø 2" bh Rp 39,100.00
1327 PVC Valve Socket Ø 3" bh Rp 132,900.00
1328 PVC Valve Socket Ø 4" bh Rp 254,150.00
1329 PVC Tapper Core / Flange Socket Ø 2" bh Rp 39,400.00
1330 PVC Tapper Core / Flange Socket Ø 3" bh Rp 60,900.00
1331 PVC Tapper Core / Flange Socket Ø 4" bh Rp 100,500.00
1332 PVC Tapper Core / Flange Socket Ø 6" bh Rp 229,300.00
1333 PVC Tee Ts Ø 1/2" x 1/2" bh Rp 4,000.00
1334 PVC Tee Ts Ø 3/4" x 1/2" bh Rp 5,000.00
1335 PVC Tee Ts Ø 3/4" x 3/4" bh Rp 5,000.00
1336 PVC Tee Ts Ø 1" x 1/2" bh Rp 7,500.00
1337 PVC Tee Ts Ø 1" x 3/4" bh Rp 8,000.00
1338 PVC Tee Ts Ø 1" x 1" bh Rp 8,500.00
1339 PVC Tee Ts Ø 1 1/2" x 1/2" bh Rp 15,000.00
1340 PVC Tee Ts Ø 1 1/2" x 3/4" bh Rp 15,000.00
1341 PVC Tee Ts Ø 1 1/2" x 1" bh Rp 16,000.00
1342 PVC Tee Ts Ø 1 1/2" x 1 1/2" bh Rp 18,000.00
1343 PVC Tee Ts Ø 2" x 1/2" bh Rp 18,000.00
1344 PVC Tee Ts Ø 2" x 3/4" bh Rp 18,000.00
1345 PVC Tee Ts Ø 2" x 1" bh Rp 19,000.00
1346 PVC Tee Ts Ø 2" x 1 1/2" bh Rp 26,000.00
1347 PVC Tee Ts Ø 2" x 2" bh Rp 28,000.00
1348 PVC Reducer Ø 3/4" x 1/2" bh Rp 3,300.00
1349 PVC Reducer Ø 1" x 3/4" bh Rp 4,350.00
1350 PVC Reducer Ø 1 1/4" x 3/4" bh Rp 5,400.00
1351 PVC Reducer Ø 1 1/4" x 1" bh Rp 6,350.00
1352 PVC Reducer Ø 1 1/2" x 3/4" bh Rp 7,000.00
1353 PVC Reducer Ø 1 1/2" x 1" bh Rp 8,500.00
1354 PVC Reducer Ø 2" x 3/4" bh Rp 10,800.00
1355 PVC Reducer Ø 2" x 1" bh Rp 11,850.00
1356 PVC Reducer Ø 2" x 1 1/4" bh Rp 13,800.00
1357 PVC Reducer Ø 2" x 1 1/2" bh Rp 14,500.00
1358 PVC Reducer Ø 3" x 3/4" bh Rp 16,950.00
1359 PVC Reducer Ø 3" x 1" bh Rp 17,500.00
153

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
1360 PVC Reducer Ø 3" x 1 1/4" bh Rp 21,400.00
1361 PVC Reducer Ø 3" x 1 1/2" bh Rp 23,850.00
1362 PVC Reducer Ø 3" x 2" bh Rp 25,450.00
1363 PVC Reducer Ø 3" x 2 1/2" bh Rp 37,850.00
1364 PVC Reducer Ø 4" x 3" bh Rp 72,300.00
1365 PVC Reducer Ø 6" x 4" bh Rp 135,000.00
1366 CI Single Air Valve Ø 2" bh Rp 833,810.00
1367 Strainer Valve Drat 150 PSI Y Ø 3/8" bh Rp 337,773.00
1368 Strainer Valve Drat 150 PSI Y Ø 1/2" bh Rp 350,094.00
1369 Strainer Valve Drat 150 PSI Y Ø 3/4" bh Rp 509,379.00
1370 Strainer Valve Drat 150 PSI Y Ø 1" bh Rp 749,250.00
1371 Strainer Valve Drat 150 PSI Y Ø 1 1/4" bh Rp 1,083,138.00
1372 Strainer Valve Drat 150 PSI Y Ø 1 1/2" bh Rp 1,428,237.00
1373 Strainer Valve Drat 150 PSI Y Ø 2" bh Rp 2,180,817.00
1374 Strainer Valve Drat 150 PSI Y Ø 2 1/2" bh Rp 6,403,035.00
1375 Strainer Valve Drat 150 PSI Y Ø 3" bh Rp 8,461,419.00
1376 CI Y Strainer Ø 1" bh Rp 749,250.00
1377 CI Y Strainer Ø 1 1/2" bh Rp 1,428,237.00
1378 CI Y Strainer Ø 2" bh Rp 2,180,817.00
1379 CI Y Strainer Ø 2 1/2" bh Rp 6,403,035.00
1380 CI Y Strainer Ø 3" bh Rp 8,461,419.00
1381 Strainer Valve F/F 16 K Ø 2" bh Rp 7,737,921.00
1382 Strainer Valve F/F 16 K Ø 2 1/2" bh Rp 11,741,469.00
1383 Strainer Valve F/F 16 K Ø 3" bh Rp 14,563,089.00
1384 Strainer Valve F/F 16 K Ø 4" bh Rp 19,476,837.00
1385 Strainer Valve F/F 16 K Ø 5" bh Rp 30,945,357.00
1386 Strainer Valve F/F 16 K Ø 6" bh Rp 39,318,309.00
1387 Strainer Valve F/F 16 K Ø 8" bh Rp 53,697,138.00
1388 Strainer Valve F/F 16 K Ø 10" bh Rp 92,103,809.00
1389 PVC Socket/Coupling Ø 1/2" bh Rp 2,500.00
1390 PVC Socket/Coupling Ø 3/4" bh Rp 2,900.00
1391 PVC Socket/Coupling Ø 1" bh Rp 3,700.00
1392 PVC Socket/Coupling Ø 1 1/4" bh Rp 6,600.00
1393 PVC Socket/Coupling Ø 1 1/2" bh Rp 9,100.00
1394 PVC Socket/Coupling Ø 2" bh Rp 13,200.00
1395 PVC Socket/Coupling Ø 2 1/2" bh Rp 14,800.00
1396 PVC Socket/Coupling Ø 3" bh Rp 30,800.00
1397 Check Valve Drat 125 PSI FH Ø 3/8" bh Rp 281,718.00
1398 Check Valve Drat 125 PSI FH Ø 1/2" bh Rp 259,518.00
1399 Check Valve Drat 125 PSI FH Ø 3/4" bh Rp 369,630.00
1400 Check Valve Drat 125 PSI FH Ø 1" bh Rp 558,108.00
1401 Check Valve Drat 125 PSI FH Ø 1 1/4" bh Rp 806,748.00
1402 Check Valve Drat 125 PSI FH Ø 1 1/2" bh Rp 1,044,066.00
1403 Check Valve Drat 125 PSI FH Ø 2" bh Rp 1,636,362.00
1404 Check Valve Drat 125 PSI FH Ø 2 1/2" bh Rp 3,465,753.00
1405 Check Valve Drat 125 PSI FH Ø 3" bh Rp 4,695,855.00
1406 Check Valve Drat 125 PSI FH Ø 4" bh Rp 9,365,736.00
1407 CI Check Valve FL - FL 10 K Ø 3" bh Rp 6,883,665.00
1408 CI Check Valve FL - FL 10 K Ø 4" bh Rp 10,068,810.00
1409 CI Check Valve FL - FL 10 K Ø 6" bh Rp 20,443,092.00
1410 CI Check Valve FL - FL 10 K Ø 8" bh Rp 36,079,218.00
1411 CI Check Valve FL - FL 10 K Ø 10" bh Rp 56,502,330.00
1412 CI Check Valve FL - FL 10 K Ø 12" bh Rp 101,589,642.00
1413 Karet Packing Ø 3" bh Rp 13,620.00
1414 Karet Packing Ø 4" bh Rp 13,930.00
1415 Mour Baut Ø 3/4" x 4" bh Rp 15,950.00
1416 Mour Baut Ø 5/8" x 3" bh Rp 8,120.00
1417 Mour Baut Ø 5" x 3/4" bh Rp 18,460.00
1418 Bak Water Meter bh Rp 40,360.00
1419 Water Meter Dia Ø 1/2" Unit Rp 295,000.00
154

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
HDPE
1420 PIPA HDPE S.13,6 Ø 1/2" m1 Rp 6,080.00
1421 PIPA HDPE S.13,6 Ø 3/4" m1 Rp 8,820.00
1422 PIPA HDPE S.13,6 Ø 1" m1 Rp 12,660.00
1423 PIPA HDPE S.13,6 Ø 1 1/4" m1 Rp 19,640.00
1424 PIPA HDPE S.13,6 Ø 1 1/2" m1 Rp 30,690.00
1425 PIPA HDPE S.13,6 Ø 2" m1 Rp 48,470.00
1426 PIPA HDPE S.13,6 Ø 2 1/2" m1 Rp 68,740.00
1427 PIPA HDPE S.13,6 Ø 3" m1 Rp 98,670.00
1428 PIPA HDPE S.13,6 Ø 4" m1 Rp 145,990.00
1429 PIPA HDPE S.13,6 Ø 6" m1 Rp 308,790.00
1430 PIPA HDPE S.13,6 Ø 8" m1 Rp 480,350.00
1431 PIPA HDPE S.13,6 Ø 10" m1 Rp 752,620.00
1432 PIPA HDPE S.13,6 Ø 12" m1 Rp 1,195,760.00
1433 PIPA HDPE S.13,6 Ø 14" m1 Rp 1,516,610.00
1434 PIPA HDPE S.13,6 Ø 16" m1 Rp 1,924,320.00
1435 PIPA HDPE S.13,6 Ø 18" m1 Rp 2,320,900.00
1436 PIPA HDPE S.13,6 Ø 20" m1 Rp 6,080.00
1437 STUB FLANGE Ø 63 mm bh Rp 248,600.00
1438 STUB FLANGE Ø 75 mm bh Rp 282,700.00
1439 STUB FLANGE Ø 90 mm bh Rp 407,000.00
1440 STUB FLANGE Ø 110 mm bh Rp 480,700.00
1441 STUB FLANGE Ø 140 mm bh Rp 660,000.00
1442 STUB FLANGE Ø 160 mm bh Rp 880,000.00
1443 STUB FLANGE Ø 200 mm bh Rp 1,375,000.00
1444 STUB FLANGE Ø 250 mm bh Rp 1,705,000.00
1445 STUB FLANGE Ø 315 mm bh Rp 2,530,000.00
1446 STUB FLANGE Ø 355 mm bh Rp 3,080,000.00
1447 STUB FLANGE Ø 400 mm bh Rp 3,630,000.00
1448 STUB FLANGE Ø 450 mm bh Rp 5,335,000.00
1449 STUB FLANGE Ø 500 mm bh Rp 6,270,000.00
1450 EQUAL TEE Ø 63 mm bh Rp 66,850.00
1451 EQUAL TEE Ø 75 mm bh Rp 96,310.00
1452 EQUAL TEE Ø 90 mm bh Rp 187,970.00
1453 EQUAL TEE Ø 110 mm bh Rp 273,050.00
1454 EQUAL TEE Ø 140 mm bh Rp 454,330.00
1455 EQUAL TEE Ø 160 mm bh Rp 602,200.00
1456 EQUAL TEE Ø 200 mm bh Rp 957,390.00
1457 EQUAL TEE Ø 250 mm bh Rp 1,574,870.00
1458 EQUAL TEE Ø 315 mm bh Rp 4,962,540.00
1459 EQUAL TEE Ø 355 mm bh Rp 6,458,100.00
1460 EQUAL TEE Ø 400 mm bh Rp 8,384,200.00
1461 EQUAL TEE Ø 450 mm bh Rp 10,650,200.00
1462 EQUAL TEE Ø 500 mm bh Rp 13,454,380.00
1463 REDUCING TEE Ø 63 mm x 50 mm bh Rp 137,260.00
1464 REDUCING TEE Ø 75 mm x 50 mm bh Rp 230,020.00
1465 REDUCING TEE Ø 75 mm x 63 mm bh Rp 214,980.00
1466 REDUCING TEE Ø 90 mm x 63 mm bh Rp 203,460.00
1467 REDUCING TEE Ø 90 mm x 75 mm bh Rp 299,320.00
1468 REDUCING TEE Ø 160 mm x 110 mm bh Rp 618,510.00
1469 REDUCING TEE Ø 160 mm x 110 mm bh Rp 618,510.00
1470 REDUCING TEE Ø 200 mm x 110 mm bh Rp 1,223,760.00
1471 REDUCING TEE Ø 200 mm x 160 mm bh Rp 1,476,890.00
1472 REDUCING TEE Ø 250 mm x 160 mm bh Rp 4,258,340.00
1473 REDUCING TEE Ø 250 mm x 200 mm bh Rp 4,983,450.00
1474 REDUCER Ø 63 mm x 50 mm bh Rp 20,000.00
1475 REDUCER Ø 110 mm x 63 mm bh Rp 175,350.00
1476 REDUCER Ø 110 mm x 75 mm bh Rp 183,910.00
1477 REDUCER Ø 110 mm x 90 mm bh Rp 192,980.00
1478 REDUCER Ø 160 mm x 90 mm bh Rp 310,740.00
1479 REDUCER Ø 160 mm x 110 mm bh Rp 352,800.00
155

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
1480 REDUCER Ø 200 mm x 160 mm bh Rp 642,480.00
1481 REDUCER Ø 250 mm x 160 mm bh Rp 954,990.00
1482 REDUCER Ø 250 mm x 200 mm bh Rp 1,180,780.00
1483 BEND Ø 63 mm x 90" bh Rp 130,120.00
1484 BEND Ø 75 mm x 90" bh Rp 163,490.00
1485 BEND Ø 90 mm x 90" bh Rp 202,400.00
1486 BEND Ø 110 mm x 90" bh Rp 278,360.00
1487 BEND Ø 160 mm x 90" bh Rp 560,030.00
1488 BEND Ø 200 mm x 90" bh Rp 976,400.00
1489 BEND Ø 250 mm x 90" bh Rp 1,687,820.00
1490 BEND Ø 315 mm x 90" bh Rp 2,800,290.00
1491 BEND Ø 355 mm x 90" bh Rp 8,512,080.00
1492 BEND Ø 400 mm x 90" bh Rp 12,627,810.00
1493 BEND Ø 450 mm x 90" bh Rp 18,863,690.00
1494 BEND Ø 500 mm x 90" bh Rp 28,217,100.00
1495 BEND Ø 63 mm x 45" bh Rp 118,610.00
1496 BEND Ø 75 mm x 45" bh Rp 145,160.00
1497 BEND Ø 90 mm x 45" bh Rp 177,750.00
1498 BEND Ø 110 mm x 45" bh Rp 254,390.00
1499 BEND Ø 160 mm x 45" bh Rp 501,910.00
1500 BEND Ø 200 mm x 45" bh Rp 855,880.00
1501 BEND Ø 250 mm x 45" bh Rp 1,552,760.00
1502 BEND Ø 315 mm x 45" bh Rp 2,547,460.00
1503 BEND Ø 355 mm x 45" bh Rp 5,596,750.00
1504 BEND Ø 400 mm x 45" bh Rp 10,086,520.00
1505 BEND Ø 450 mm x 45" bh Rp 15,200,020.00
1506 BEND Ø 500 mm x 45" bh Rp 21,671,930.00
1507 BEND Ø 63 mm x 22 1/2" bh Rp 112,420.00
1508 BEND Ø 75 mm x 22 1/2" bh Rp 137,260.00
1509 BEND Ø 90 mm x 22 1/2" bh Rp 166,950.00
1510 BEND Ø 110 mm x 22 1/2" bh Rp 235,400.00
1511 BEND Ø 160 mm x 22 1/2" bh Rp 427,120.00
1512 BEND Ø 200 mm x 22 1/2" bh Rp 750,220.00
1513 BEND Ø 250 mm x 22 1/2" bh Rp 1,323,800.00
1514 BEND Ø 315 mm x 22 1/2" bh Rp 2,135,760.00
1515 BEND Ø 355 mm x 22 1/2" bh Rp 5,113,350.00
1516 BEND Ø 400 mm x 22 1/2" bh Rp 9,166,640.00
1517 BEND Ø 450 mm x 22 1/2" bh Rp 11,910,530.00
1518 BEND Ø 500 mm x 22 1/2" bh Rp 16,906,490.00
1519 BEND Ø 63 mm x 11 1/4" bh Rp 109,150.00
1520 BEND Ø 75 mm x 11 1/4" bh Rp 132,630.00
1521 BEND Ø 90 mm x 11 1/4" bh Rp 155,960.00
1522 BEND Ø 110 mm x 11 1/4" bh Rp 221,500.00
1523 BEND Ø 160 mm x 11 1/4" bh Rp 413,120.00
1524 BEND Ø 200 mm x 11 1/4" bh Rp 676,740.00
1525 BEND Ø 250 mm x 11 1/4" bh Rp 1,167,800.00
1526 BEND Ø 315 mm x 11 1/4" bh Rp 1,850,610.00
1527 BEND Ø 355 mm x 11 1/4" bh Rp 5,113,350.00
1528 BEND Ø 400 mm x 11 1/4" bh Rp 9,116,640.00
1529 BEND Ø 450 mm x 11 1/4" bh Rp 11,910,530.00
1530 BEND Ø 500 mm x 11 1/4" bh Rp 16,840,830.00
156

NO NAMA BARANG SATUAN HARGA SATUAN

A B C
RK3K
1531 Topi Pelindung (Safety Helmet) bh Rp 75,000.00
1532 Pelindung pernafasan dan mulut (Masker) kotak Rp 50,000.00
1533 Sarung tangan (safety gloves) bh Rp 5,000.00
1534 Rompi keselamatan (safety vest) bh Rp 25,000.00
1535 Peralatan K3 (Kotak P3k, Obat Luka, Perban, Dll) bh Rp 500,000.00
KEGIATAN :
PEKERJAAN :
LOKASI :
TAHUN :

NO URAIAN PEKERJAAN VOL

I PEKERJAAN PERSIAPAN
1 Pek. Bowplank 41.60

II PEKERJAAN GALIAN DAN URUGAN


1 Pek. Galian tanah pondasi footplat 9.00
2 Pek. Urugan tanah peninggian lantai 4.76
3 Pek. Urugan kembali galian tanah footplat 1.80
4 Pek. Urugan pasir di bawah footplat 0.90
5 Pek. Urugan pasir di bawah sloof 0.90

III PEKERJAAN PONDASI


1 Pek. Footplat (FP1)
a Pek. Beton K250 9.00
b Pek. Pembesian 152.75
c Pek. Bekisting 24.00

IV PEKERJAAN LANTAI 1
IV.1 PEKERJAAN STRUKTUR
1 Pek. Sloof (S1)
a Pek. Beton K250 3.02
b Pek. Pembesian 476.04
Utama 285.82
Sengkang 190.22
c Pek. Bekisting 6.89
2 Pek. Kolom (K1)
a Pek. Beton K250 2.36
b Pek. Pembesian 533.81
391.03
142.79
c Pek. Bekisting 30.84
3 Pek. Pelat lantai (PL1)
a Pek. Beton K250 4.88
b Pek. Pembesian wiremesh M6 279.44
c Pek. Bekisting 0.01
4 Pek. Pelat meja beton
a Pek. Beton K250 0.21
b Pek. Pembesian wiremesh M6 12.13
c Pek. Bekisting 2.90
5 Pek. Tangga
a Pek. Beton K250 1.18
b Pek. Pembesian 94.54
c Pek. Bekisting 12.46

IV.2 PEKERJAAN PASANGAN DINDING, PLESTERAN, DAN ACIAN


1 Pek. Pas. Dinding batako 47.46
2 Pek. Pas. Dinding cubicle kamar mandi 17.19
3 Pek. Plesteran dinding trasram 1:2 62.89
4 Pek. Plesteran kamprot 77.77

IV.3 PEKERJAAN PINTU, JENDELA, DAN KACA


1 Pek. Pintu aluminium kamar mandi 2.00
2 Pek. Pintu cubicle kamar mandi 2.00

IV.4 PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Pek. Screeding lantai 48.84
2 Pek. Keramik dinding kamar mandi 20x40 34.74

IV.5 PEKERJAAN RAILING


1 Pek. Railing tangga 14.15
2 Pek. Politur railing 16.98

IV.6 PEKERJAAN ELEKTRIKAL


1 Pek. Instalasi titik lampu 11.00
2 Pek. Instalasi stop kontak 10.00
3 Pek. Pas. Lampu LED 9 watt 11.00
4 Pek. Pas. Saklar single 1.00
5 Pek. Pas. Saklar ganda 5.00
6 Pek. Pas. Stop kontak 2.00

IV.7 PEKERJAAN SANITASI DAN PLUMBING


1 Pek. Pas. Kloset duduk 3.00
2 Pek. Pas. Urinoir 1.00
3 Pek. Pas. Wastafel 2.00
4 Pek. Pas. Floor drain 3.00
5 Pek. Pas. Kran 1/2" 3.00
6 Pek. Pas. Kran wastafel 2.00
7 Pek. Pipa air bersih 2" 15.00
8 Pek. Pipa air bersih PVC 3/4" 5.00
9 Pek. Pipa air kotor PVC 3" 15.00
10 Pek. Pipa air limbah PVC 3" 15.00

V PEKERJAAN LANTAI 2
V.1 PEKERJAAN STRUKTUR
1 Pek. Balok (B1)
a Pek. Beton K250 3.20
b Pek. Pembesian 635.01
433.80
201.21
c Pek. Bekisting 42.86
2 Pek. Kolom (K2)
a Pek. Beton K250 1.50
b Pek. Pembesian 352.02
244.49
107.53
c Pek. Bekisting 24.00
3 Pek. Pelat lantai (PL2)
a Pek. Beton K250 5.76
b Pek. Pembesian wiremesh M8 2 layer 523.10
c Pek. Bekisting 33.40
4 Pek. Trap tangga
a Pek. Beton K250 0.16
b Pek. Pembesian 11.27
c Pek. Bekisting 1.66

V.2 PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Pek. Screeding lantai 48.00

V.3 PEKERJAAN STYLE BALI


1 Pek. Sendi kolom marmer 8.00

V.4 PEKERJAAN RAILING


1 Pek. Railing 24.89
2 Pek. Politur railing 33.60

V.5 PEKERJAAN ELEKTRIKAL


1 Pek. Instalasi titik lampu 6.00
2 Pek. Instalasi stop kontak 8.00
3 Pek. Pas. Lampu LED 9 watt 6.00
4 Pek. Pas. Saklar tunggal 3.00
5 Pek. Pas. Stop kontak 8.00

VI PEKERJAAN ATAP DAN PENUTUP ATAP


VI.1 PEKERJAAN RANGKA ATAP EXPOSE
1 Pek. Kayu Pemade 6 x 12 0.56
2 Pek. Kayu Lambang 6 x 15 0.24
3 Pek. Balok Dedeleg 6 x 12 0.04
4 Pek. Cover Nok (Tapel Dedeleg) 3 x 30 3.30
5 Pek. Bebed Iga-Iga Kayu Uk. 2 x 6 (profil) 0.02
6 Pek. Kayu Usuk Uk. 4 x 6 225.12
7 Pek. Kayu Reng Uk. 2 x 3 225.12
8 Pek. List Plank Uk. 2 x 20 37.60
9 Pek. List Plank Uk. 2 x 15 37.60
10 Pek. Tatab Uk. 3 x 10 37.60
11 Pek. Lambersering Seseh Uk. 1 x 10 225.12

VI.2 PEKERJAAN PENUTUP ATAP


1 Pek. Penutup atap genteng good year 225.12
2 Pek. Bubungan atap good year 17.20
3 Pek. Ikut celedu paras ukir 6.00
4 Pek. Bentala paras ukir 1.00
SAT PANJANG LEBAR TINGGI JUMLAH 1 JUMLAH 2

m1 12.90 7.90

m3 1.50 1.50 0.50 8.00


m3 9.53 5.00 0.10
m3 1.50 1.50 0.10 8.00
m3 1.50 1.50 0.05 8.00
m3 1.50 1.50 0.05 8.00

m3
kg 2.20 11.00 4.00
m2

m3
kg
34.50 5.00
1.06 277.00
m2

m3
kg
23.60 10.00
1.16 190.00
m2

m3
kg
m2

m3
kg
m2

m3
kg
m2

m2
m2
m2
m2

unit 2.00
unit 2.00

m2
m2

m1
m2

titik 11.00
titik 10.00
buah 17.00
buah 1.00
buah 5.00
buah 2.00

unit 3.00
unit 1.00
unit 2.00
buah 3.00
buah 3.00
unit 2.00
m1 15.00
m1 5.00
m1 15.00
m1 15.00

m3
kg
36.50 7.00
1.06 293.00
m2

m3
kg
24.00 6.00
0.86 193.00
m2

m3
kg 2.00
m2

m3
kg
m2

m2 48.00

buah 8.00

m1
m2

titik 6.00
titik 8.00
buah 6.00
buah 3.00
buah 8.00

m3
m3
m3
m3
m3
m2
m2
m1
m1
m1
m2

m2
m1
buah
buah
LUAS KELILING BERAT JENIS WASTE

1.58

1.58 1.05
0.62 1.05
1.58 1.05
0.62 1.05

48.84 5.45 1.05

2.12 5.45 1.05


1.62 1.05
0.62 1.05

1.62 1.05
0.62 1.05

48.00 5.45 1.05


REKAPITULASI

KEGIATAN : Bali Pelataran


PEKERJAAN : Pembangunan Bali Pelataran
LOKASI : Area Puspem Badung
TAHUN : 2022

NO URAIAN PEKERJAAN JUMLAH HARGA


1 2 3

I PEKERJAAN PERSIAPAN Rp 6,076,449.60


II PEKERJAAN GALIAN DAN URUGAN Rp 2,188,470.60
III PEKERJAAN PONDASI Rp 15,927,572.86
IV PEKERJAAN LANTAI 1
IV.1 PEKERJAAN STRUKTUR Rp 48,061,169.58
IV.2 PEKERJAAN PASANGAN DINDING, PLESTERAN, DAN ACIAN Rp 25,135,760.96
IV.3 PEKERJAAN PINTU, JENDELA, DAN KACA Rp 4,500,000.00
IV.4 PEKERJAAN PENUTUP LANTAI DAN DINDING Rp 17,403,819.45
IV.5 PEKERJAAN RAILING Rp 4,925,049.00
IV.6 PEKERJAAN ELEKTRIKAL Rp 10,642,185.00
IV.7 PEKERJAAN SANITASI DAN PLUMBING Rp 16,253,038.00
V PEKERJAAN LANTAI 2
V.1 PEKERJAAN STRUKTUR Rp 91,542,127.02
V.2 PEKERJAAN PENUTUP LANTAI DAN DINDING Rp 2,041,500.00
V.3 PEKERJAAN STYLE BALI Rp 1,600,000.00
V.4 PEKERJAAN RAILING Rp 8,968,180.00
V.5 PEKERJAAN ELEKTRIKAL Rp 7,621,354.33
VI PEKERJAAN ATAP DAN PENUTUP ATAP
VI.1 PEKERJAAN RANGKA ATAP EXPOSE Rp 131,852,026.28
VI.2 PEKERJAAN PENUTUP ATAP Rp 21,779,286.60
JUMLAH Rp 416,517,989.28
PPN 11% Rp 45,816,978.82
TOTAL REAL COST Rp 462,334,968.10
Empat Ratus Enam Puluh Dua Juta Tiga Ratus Tiga Puluh Empat
TERBILANG :
Ribu Sembilan Ratus Enam Puluh Delapan Rupiah
RENCANA ANGARAN BIAYA

KEGIATAN : Bali Pelataran


PEKERJAAN : Pembangunan Bali Pelataran
LOKASI : Area Puspem Badung
TAHUN : 2022

NO URAIAN PEKERJAAN VOL SAT HARGA SATUAN JUMLAH HARGA


1 2 3 4 5 6=3*5
I PEKERJAAN PERSIAPAN
1 Pek. Bowplank 41.60 m1 Rp 146,068.50 Rp 6,076,449.60

TOTAL I Rp 6,076,449.60
II PEKERJAAN GALIAN DAN URUGAN
1 Pek. Galian tanah pondasi footplat 9.00 m3 Rp 88,125.00 Rp 793,125.00
2 Pek. Urugan tanah peninggian lantai 4.76 m3 Rp 131,875.00 Rp 628,054.69
3 Pek. Urugan kembali galian tanah footplat 1.80 m3 Rp 63,750.00 Rp 114,750.00
4 Pek. Urugan pasir di bawah footplat 0.90 m3 Rp 362,522.73 Rp 326,270.45
5 Pek. Urugan pasir di bawah sloof 0.90 m3 Rp 362,522.73 Rp 326,270.45

TOTAL II Rp 2,188,470.60
III PEKERJAAN PONDASI
1 Pek. Footplat (FP1)
a Pek. Beton K250 9.00 m3 Rp 1,083,716.63 Rp 9,753,449.70
b Pek. Pembesian 152.75 kg Rp 15,230.75 Rp 2,326,503.15
c Pek. Bekisting 24.00 m2 Rp 160,317.50 Rp 3,847,620.00

TOTAL III Rp 15,927,572.86


IV PEKERJAAN LANTAI 1
IV.1 PEKERJAAN STRUKTUR
1 Pek. Sloof (S1)
a Pek. Beton K250 3.02 m3 Rp 1,083,716.63 Rp 3,272,824.23
b Pek. Pembesian 476.04 kg Rp 15,230.75 Rp 7,250,400.04
c Pek. Bekisting 6.89 m2 Rp 160,317.50 Rp 1,104,587.58
2 Pek. Kolom (K1)
a Pek. Beton K250 2.36 m3 Rp 1,083,716.63 Rp 2,557,571.26
b Pek. Pembesian 533.81 kg Rp 15,230.75 Rp 8,130,395.81
c Pek. Bekisting 30.84 m2 Rp 298,671.25 Rp 9,211,021.35
3 Pek. Pelat lantai (PL1)
a Pek. Beton K250 4.88 m3 Rp 1,083,716.63 Rp 5,288,537.17
b Pek. Pembesian wiremesh M6 279.44 kg Rp 13,319.83 Rp 3,722,036.02
c Pek. Bekisting 0.01 m2 Rp 160,317.50 Rp 1,603.18
4 Pek. Pelat meja beton
a Pek. Beton K250 0.21 m3 Rp 1,083,716.63 Rp 227,580.49
b Pek. Pembesian wiremesh M6 12.13 kg Rp 13,319.83 Rp 161,562.58
c Pek. Bekisting 2.90 m2 Rp 354,671.25 Rp 1,028,546.63
5 Pek. Tangga
a Pek. Beton K250 1.18 m3 Rp 1,083,716.63 Rp 1,278,785.63
b Pek. Pembesian 94.54 kg Rp 15,230.75 Rp 1,439,915.11
c Pek. Bekisting 12.46 m2 Rp 271,733.75 Rp 3,385,802.53

TOTAL IV.1 Rp 48,061,169.58


IV.2 PEKERJAAN PASANGAN DINDING, PLESTERAN, DAN ACIAN
1 Pek. Pas. Dinding batako 47.46 m2 Rp 192,695.73 Rp 9,145,339.39
2 Pek. Pas. Dinding cubicle kamar mandi 17.19 m2 Rp 300,000.00 Rp 5,157,000.00
3 Pek. Plesteran dinding trasram 1:2 62.89 m2 Rp 101,292.40 Rp 6,370,279.04
4 Pek. Plesteran kamprot 77.77 m2 Rp 57,389.00 Rp 4,463,142.53

TOTAL IV.2 Rp 25,135,760.96


NO URAIAN PEKERJAAN VOL SAT HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 6=3*5
IV.3 PEKERJAAN PINTU, JENDELA, DAN KACA
1 Pek. Pintu aluminium kamar mandi 2.00 unit Rp 1,250,000.00 Rp 2,500,000.00
2 Pek. Pintu cubicle kamar mandi 2.00 unit Rp 1,000,000.00 Rp 2,000,000.00

TOTAL IV.3 Rp 4,500,000.00


IV.4 PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Pek. Screeding lantai 48.84 m2 Rp 42,531.25 Rp 2,077,226.25
2 Pek. Keramik dinding kamar mandi 20x40 34.74 m2 Rp 441,180.00 Rp 15,326,593.20

TOTAL IV.4 Rp 17,403,819.45


IV.5 PEKERJAAN RAILING
1 Pek. Railing tangga 14.15 m1 Rp 250,000.00 Rp 3,537,500.00
2 Pek. Politur railing 16.98 m2 Rp 81,716.67 Rp 1,387,549.00

TOTAL IV.5 Rp 4,925,049.00


IV.6 PEKERJAAN ELEKTRIKAL
1 Pek. Instalasi titik lampu 11.00 titik Rp 277,931.67 Rp 3,057,248.33
2 Pek. Instalasi stop kontak 10.00 titik Rp 567,911.17 Rp 5,679,111.67
3 Pek. Pas. Lampu LED 9 watt 11.00 buah Rp 130,175.00 Rp 1,431,925.00
4 Pek. Pas. Saklar single 1.00 buah Rp 50,175.00 Rp 50,175.00
5 Pek. Pas. Saklar ganda 5.00 buah Rp 62,675.00 Rp 313,375.00
6 Pek. Pas. Stop kontak 2.00 buah Rp 55,175.00 Rp 110,350.00

TOTAL IV.6 Rp 10,642,185.00


IV.7 PEKERJAAN SANITASI DAN PLUMBING
1 Pek. Pas. Kloset duduk 3.00 unit Rp 1,941,475.00 Rp 5,824,425.00
2 Pek. Pas. Urinoir 1.00 unit Rp 1,535,405.00 Rp 1,535,405.00
3 Pek. Pas. Wastafel 2.00 unit Rp 1,082,304.00 Rp 2,164,608.00
4 Pek. Pas. Floor drain 3.00 buah Rp 48,600.00 Rp 145,800.00
5 Pek. Pas. Kran 1/2" 3.00 buah Rp 87,650.00 Rp 262,950.00
6 Pek. Pas. Kran wastafel 2.00 unit Rp 433,900.00 Rp 867,800.00
7 Pek. Pipa air bersih 2" 15.00 m1 Rp 78,457.50 Rp 1,176,862.50
8 Pek. Pipa air bersih PVC 3/4" 5.00 m1 Rp 30,300.00 Rp 151,500.00
9 Pek. Pipa air kotor PVC 3" 15.00 m1 Rp 137,456.25 Rp 2,061,843.75
10 Pek. Pipa air limbah PVC 3" 15.00 m1 Rp 137,456.25 Rp 2,061,843.75

TOTAL IV.7 Rp 16,253,038.00


TOTAL IV Rp 126,921,021.99
V PEKERJAAN LANTAI 2
V.1 PEKERJAAN STRUKTUR
1 Pek. Balok (B1)
a Pek. Beton K250 3.20 m3 Rp 1,083,716.63 Rp 3,467,893.23
b Pek. Pembesian 635.01 kg Rp 15,230.75 Rp 9,671,677.46
c Pek. Bekisting 42.86 m2 Rp 619,442.50 Rp 26,549,305.55
2 Pek. Kolom (K2)
a Pek. Beton K250 1.50 m3 Rp 1,083,716.63 Rp 1,625,574.95
b Pek. Pembesian 352.02 kg Rp 15,230.75 Rp 5,361,536.89
c Pek. Bekisting 24.00 m2 Rp 298,671.25 Rp 7,168,110.00
3 Pek. Pelat lantai (PL2)
a Pek. Beton K250 5.76 m3 Rp 1,083,716.63 Rp 6,242,207.81
b Pek. Pembesian wiremesh M8 2 layer 523.10 kg Rp 13,319.83 Rp 6,967,658.40
c Pek. Bekisting 33.40 m2 Rp 709,342.50 Rp 23,692,039.50
4 Pek. Trap tangga
a Pek. Beton K250 0.16 m3 Rp 1,083,716.63 Rp 173,394.66
b Pek. Pembesian 11.27 kg Rp 15,230.75 Rp 171,650.55
c Pek. Bekisting 1.66 m2 Rp 271,733.75 Rp 451,078.03

TOTAL V.1 Rp 91,542,127.02


V.2 PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Pek. Screeding lantai 48.00 m2 Rp 42,531.25 Rp 2,041,500.00
NO URAIAN PEKERJAAN VOL SAT HARGA SATUAN JUMLAH HARGA
1 2 3 4 5 6=3*5
TOTAL V.2 Rp 2,041,500.00
V.3 PEKERJAAN STYLE BALI
1 Pek. Sendi kolom marmer 8.00 unit Rp 200,000.00 Rp 1,600,000.00

TOTAL V.3 Rp 1,600,000.00


V.4 PEKERJAAN RAILING
1 Pek. Railing 24.89 m1 Rp 250,000.00 Rp 6,222,500.00
2 Pek. Politur railing 33.60 m2 Rp 81,716.67 Rp 2,745,680.00

TOTAL V.4 Rp 8,968,180.00


V.5 PEKERJAAN ELEKTRIKAL
1 Pek. Instalasi titik lampu 6.00 titik Rp 277,931.67 Rp 1,667,590.00
2 Pek. Instalasi stop kontak 8.00 titik Rp 567,911.17 Rp 4,543,289.33
3 Pek. Pas. Lampu LED 9 watt 6.00 buah Rp 130,175.00 Rp 781,050.00
4 Pek. Pas. Saklar ganda 3.00 buah Rp 62,675.00 Rp 188,025.00
5 Pek. Pas. Stop kontak 8.00 buah Rp 55,175.00 Rp 441,400.00

TOTAL V.5 Rp 7,621,354.33


TOTAL V Rp 111,773,161.36
VI PEKERJAAN ATAP DAN PENUTUP ATAP
VI.1 PEKERJAAN RANGKA ATAP EXPOSE
1 Pek. Kayu Pemade 6 x 12 0.56 m3 Rp 12,135,558.33 Rp 6,795,912.67
2 Pek. Kayu Lambang 6 x 15 0.24 m3 Rp 12,135,558.33 Rp 2,912,534.00
3 Pek. Balok Dedeleg 6 x 12 0.04 m3 Rp 12,135,558.33 Rp 485,422.33
4 Pek. Cover Nok (Tapel Dedeleg) 3 x 30 3.30 m3 Rp 134,470.83 Rp 443,753.75
5 Pek. Bebed Iga-Iga Kayu Uk. 2 x 6 (profil) 0.02 m3 Rp 95,716.67 Rp 1,914.33
6 Pek. Kayu Usuk Uk. 4 x 6 225.12 m2 Rp 95,716.67 Rp 21,547,736.00
7 Pek. Kayu Reng Uk. 2 x 3 225.12 m2 Rp 68,020.00 Rp 15,312,662.40
8 Pek. List Plank Uk. 2 x 20 37.60 m1 Rp 75,933.33 Rp 2,855,093.33
9 Pek. List Plank Uk. 2 x 15 37.60 m1 Rp 67,570.83 Rp 2,540,663.33
10 Pek. Tatab Uk. 3 x 10 37.60 m1 Rp 67,570.83 Rp 2,540,663.33
11 Pek. Lambersering Seseh Uk. 1 x 10 225.12 m2 Rp 339,444.17 Rp 76,415,670.80

TOTAL VI.1 Rp 131,852,026.28


VI.2 PEKERJAAN PENUTUP ATAP
1 Pek. Penutup atap genteng good year 225.12 m2 Rp 83,192.50 Rp 18,728,295.60
2 Pek. Bubungan atap good year 17.20 m1 Rp 117,030.00 Rp 2,012,916.00
3 Pek. Ikut celedu paras ukir 6.00 buah Rp 139,725.00 Rp 838,350.00
4 Pek. Bentala paras ukir 1.00 buah Rp 199,725.00 Rp 199,725.00

TOTAL VI.2 Rp 21,779,286.60


TOTAL VI Rp 153,631,312.88
TOTAL REAL COST Rp 416,517,989.28
REKAPITULASI ANALISIS HARGA SATUAN PEKERJAAN

NO
JENIS PEKERJAAN HARGA
PEKERJAAN
1 2 3
A HARGA SATUAN PEKERJAAN PERSIAPAN
I (PERMEN NOMOR 28/PRT/M/2016)
A.I.1. (K3) Pembuatan 1 m2 pagar sementara dari kayu tinggi 2 meter Rp 77,450.00
A.I.2. (K3) Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter Rp 81,450.00
A.I.3. (K3) Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1,8 meter Rp 68,200.00
A.I.4. Pengukuran dan pemasangan 1 m1 bouwplank Rp 146,068.50
A.I.5. (K3) Pembuatan 1 m2 kantor sementara lantai plesteran Rp 662,500.00
A.I.6. (K3) Pembuatan 1 m2 rumah jaga (konstruksi kayu) Rp 340,875.00
A.I.7. (K3) Pembuatan 1 m2 gudang semen dan peralatan Rp 414,500.00
A.I.8. (K3) Pembuatan 1 m2 bedeng pekerja Rp 414,500.00
A.I.9. (K3) Pembersihan 1 m2 lapangan dan perataan Rp 18,750.00
A.I.10. (K3) Pembuatan 1 m2 steger/perancah dari bambu Rp 414,500.00
A.I.11. Pembuatan 1 buah kotak adukan ukuran 40 cm x 50 cm x 25 cm Rp 44,175.00
A.I.12. Pembuatan 1 m2 jalan sementara Rp 113,250.00
A.I.13. Pembongkaran 1 m3 beton bertulang Rp 1,599,975.00
A.I.14. Pembongkaran 1 m3 dinding tembok bata Rp 799,987.50
A.I.15. Pemasangan 1 m2 pagar kawat jaring galvanis panjang 240 cm Rp 11,830.00
A.I.16. Pemasangan 1 m2 panel beton pracetak 5 x 50 x 240 cm Rp 62,745.00
II ANALISA SENDIRI
A.II.1. Pembuatan 1 m2 stegger dengan scaffolding 120 x 180, h 190 (sewa) Rp 41,002.50
A.II.2. Pemasangan 1 unit alat pemadam api ringan (APAR) 6 kg powder Rp 84,375.00

B HARGA SATUAN PEKERJAAN TANAH


I (PERMEN NOMOR 28/PRT/M/2016)
B.I.1. Penggalian 1 m3 tanah biasa sedalam 1 m Rp 88,125.00
B.I.2. Penggalian 1 m3 tanah biasa sedalam 2 m Rp 108,000.00
B.I.3. Penggalian 1 m3 tanah biasa sedalam 3 m Rp 128,175.00
B.I.4. Penggalian 1 m3 tanah keras sedalam 1 m Rp 117,300.00
B.I.5. Penggalian 1 m3 tanah cadas sedalam 1 m Rp 177,750.00
B.I.6. Penggalian 1 m3 tanah lumpur sedalam 1 m Rp 141,750.00
B.I.7. Pengerjaan stripping 1 m2 tanah tebing setinggi 1 meter Rp 6,375.00
B.I.8. (K3) Pembuangan 1 m3 tanah sejauh 30 meter Rp 38,625.00
B.I.9. Pengurugan kembali 1 m3 galian tanah Rp 63,750.00
B.I.10. (K3) Pemadatan tanah 1 m3 tanah (per 20 cm) Rp 63,750.00
B.I.11. Pengurugan 1 m3 dengan pasir urug Rp 362,522.73
B.I.12. Pemasangan 1 m3 lapisan pudel campuran 1KP : 3PP : 7TL Rp 158,900.00
B.I.13. Pemasangan 1 m2 lapisan ijuk tebal 10 cm untuk bidang resapan Rp 19,125.00
B.I.14. Pengurugan 1 m3 sirtu padat Rp 31,875.00
II (SNI 03-2835-2002)
B.II.1. Pembuangan 1 m3 tanah sejauh 150 m Rp 65,550.00
B.II.2. Pemasangan 1 m3 lapisan pudel campuran 1KP : 5TL Rp 164,950.00
III ANALISA SENDIRI
B.III.1. Pemasangan 1 m3 tanah dengan stamper Rp 63,750.00
B.III.2. Pengurugan 1 m3 tanah urug Rp 131,875.00

C HARGA SATUAN PEKERJAAN PONDASI


I (PERMEN NOMOR 28/PRT/M/2016)
C.I.1. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 3PP Rp 286,687.50
C.I.2. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 4PP Rp 286,687.50
C.I.3. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP Rp 286,687.50
C.I.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP Rp 286,687.50
C.I.5. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 8PP Rp 286,687.50
C.I.6. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 1KP : 2PP Rp 286,687.50
C.I.7. Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 3 KP : 10 PP Rp 286,687.50
C.I.8. Pemasangan 1 m3 pondasi batu belah campuran 1/4 SP : 1 KP : 4PP Rp 286,687.50
C.I.9. (K3) Pemasangan 1 m3 batu kosong (anstamping) Rp 149,077.50
C.I.10. Pemasangan 1 m3 pondasi siklop, 60% beton campuran 1SP : 2PB : 3KR dan 40% batu belah Rp 528,912.50
C.I.11. Pemasangan 1 m3 pondasi sumuran, diameter 100 cm Rp 401,650.00
II (SNI 03-2836-2002)
C.II.1. Pemasangan 1 m3 pondasi batu kali 1SP : 1PP Rp 265,350.00
C.II.2. Pemasangan 1 m3 pondasi batu kali 1SP : 2PP Rp 265,350.00
C.II.3. Pemasangan 1 m3 pondasi batu kali 1SP : 2,5PP Rp 265,350.00
C.II.4. Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 1/4 KP : 4PP Rp 265,350.00
C.II.5. Pembuatan 1 m3 tiang pancang 40 x 40 cm beton bertulang Rp 215,307.50
C.II.6. Pembuatan 1 m3 tiang pancang 35 x 35 cm beton bertulang Rp 167,125.00
III ANALISA SENDIRI
C.III.1. Pengeboran 1 m1 pondasi bored pile diameter 30 cm Rp 20,400.00

D HARGA SATUAN PEKERJAAN BETON


I (PERMEN NOMOR 28/PRT/M/2016)
D.I.1. Membuat 1 m3 beton mutu f’c = 7,4 Mpa, (K.100), slump (12 ± 2) cm, w/c = 0,87 Rp 237,267.50
D.I.2. Membuat 1 m3 beton mutu f’c = 9,8 Mpa, (K.125), slump (12 ± 2) cm, w/c = 0,78 Rp 237,267.50
D.I.3. Membuat 1 m3 beton mutu f’c = 12,2 Mpa, (K.150), slump (12 ± 2) cm, w/c = 0,72 Rp 237,267.50
D.I.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 Mpa, (K.100), slump (3 - 6) cm, w/c = 0,87 Rp 172,450.00
NO
JENIS PEKERJAAN HARGA
PEKERJAAN
D.I.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa, (K.175), slump (12 ± 2) cm, w/c = 0,66 Rp 237,193.75
D.I.6. Membuat 1 m3 beton mutu f’c = 16,9 Mpa, (K.200), slump (12 ± 2) cm, w/c = 0,61 Rp 237,193.75
D.I.7. Membuat 1 m3 beton mutu f’c = 19,3 Mpa, (K225), slump (12 ± 2) cm, w/c = 0,58 Rp 237,193.75
D.I.8. Membuat 1 m3 beton mutu f’c = 21,7 Mpa, (K.250), slump (12 ± 2) cm, w/c = 0,56 Rp 1,083,716.63
D.I.9. Membuat 1 m3 beton mutu f’c = 24,0 Mpa, (K.275), slump (12 ± 2) cm, w/c = 0,53 Rp 237,193.75
D.I.10. Membuat 1 m3 beton mutu f’c = 26,4 Mpa, (K.300), slump (12 ± 2) cm, w/c = 0,52 Rp 237,193.75
D.I.11. Membuat 1 m3 beton mutu f’c = 28,8 Mpa, (K.325), slump (12 ± 2) cm, w/c = 0,49 Rp 301,787.50
D.I.12. Membuat 1 m3 beton mutu f’c = 31,2 MPa, (K.350), slump (12 ± 2) cm, w/c = 0,48 Rp 301,787.50
D.I.13. Membuat 1 m3 beton kedap air dengan strorox - 100 Rp 301,787.50
D.I.14. Pemasangan 1 m1 PVC waterstop lebar 150 mm Rp 11,467.50
D.I.15. Pemasangan 1 m1 PVC waterstop lebar 200 mm Rp 13,977.50
D.I.16. Pemasangan 1 m1 PVC waterstop lebar 230 mm - 320 mm Rp 15,290.00
D.I.17. Pembesian 10 kg dengan besi polos atau besi ulir Rp 152,307.50
D.I.17a. Pembesian 1 kg dengan besi polos atau besi ulur Rp 15,230.75
D.I.18. Pembesian 10 kg kabel presstressed polos/strands Rp 13,187.50
D.I.18a. Pembesian 1 kg kabel presstressed polos/strands Rp 1,318.75
D.I.19. Pemasangan 10 kg jaring kawat baja (wiremesh) Rp 133,198.34
D.I.19a. Pembesian 1 kg jaring kawat baja (wiremesh) Rp 13,319.83
D.I.20. (K3) Pemasangan 1 m2 bekisting untuk pondasi Rp 320,635.00
D.I.20a. (K3) Pemasangan 1m2 bekisting untuk pondasi 2x pakai Rp 160,317.50
D.I.21. (K3) Pemasangan 1 m2 bekisting untuk sloof Rp 100,685.00
D.I.21a. (K3) Pemasangan 1m2 bekisting untuk sloof 2x pakai Rp 50,342.50
D.I.22. (K3) Pemasangan 1 m2 bekisting untuk kolom Rp 597,342.50
D.I.22a. (K3) Pemasangan 1m2 bekisting untuk kolom 2x pakai Rp 298,671.25
D.I.23. (K3) Pemasangan 1 m2 bekisting untuk balok Rp 619,442.50
D.I.23a. (K3) Pemasangan 1m2 bekisting untuk balok 2x pakai Rp 309,721.25
D.I.24. (K3) Pemasangan 1 m2 bekisting untuk lantai Rp 709,342.50
D.I.24a. (K3) Pemasangan 1m2 bekisting untuk lantai 2x pakai Rp 354,671.25
D.I.25. (K3) Pemasangan 1 m2 bekisting untuk dinding Rp 127,792.50
D.I.25a. (K3) Pemasangan 1m2 bekisting untuk dinding 2x pakai Rp 63,896.25
D.I.26. Pemasangan 1 m2 bekisting untuk tangga Rp 543,467.50
D.I.26a. Pemasangan 1m2 bekisting untuk tangga 2x pakai Rp 271,733.75
D.I.27. Pemasangan 1 m2 jembatan untuk pengecoran beton Rp 25,437.50
D.I.28. Membuat 1 m1 kolom praktis beton bertulang (11 x 11) cm Rp 30,235.00
D.I.29. Membuat 1 m1 ring balok beton bertulang (10 x 15) cm Rp 49,925.00
II (PERMEN NO.11/PRT/M/2013)
D.II.1. Membuat 1 m3 pondasi beton bertulang (150 Kg besi + bekisting) Rp 1,015,832.50
D.II.2. Membuat 1 m3 sloof beton bertulang (200 Kg besi + bekisting) Rp 1,145,980.00
D.II.3. Membuat 1 m3 kolom beton bertulang (300 Kg besi + bekisting) Rp 1,426,955.00
D.II.4. Membuat 1 m3 balok beton bertulang (200 Kg besi + bekisting) Rp 1,243,380.00
D.II.5. Membuat 1 m3 kolom beton bertulang (150 Kg besi + bekisting) Rp 1,016,275.00
D.II.6. Membuat 1 m3 dinding beton bertulang (150 Kg besi + bekisting) Rp 1,015,832.50
D.II.7. Membuat 1 m3 dinding beton bertulang (200 Kg besi + bekisting) Rp 1,145,980.00
III ANALISA SENDIRI
D.III.1. Pemasangan 1 m2 floor deck Rp 79,312.50
D.III.2. Pemasangan 1 m1 endstop floor deck (side closer) Rp 3,337.50
D.III.3. Pemasangan 1 m2 plastik cor Rp 2,882.50

E A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK


I (PERMEN NOMOR 28/PRT/M/2016)
E.I.1. (K3) Pembuatan 1 m2 lahan produksi tebal 8 cm beton f’c 14,5 MPa, (K.175), slump (120 ± 20) mm Rp 19,029.50
E.I.2. (K3) Pembuatan 1 m2 lahan produksi tebal 10 cm beton f’c 14,5 MPa, (K.175), slump (120 ± 20) mm Rp 23,745.50
E.I.3. (K3) Pembuatan 1 m2 lahan produksi tebal 12 cm beton f’c 14,5 MPa, (K.175), slump (120 ± 20) mm Rp 28,469.25
E.I.4. (K3) Pembuatan 1 m2 lahan produksi tebal 15 cm beton f’c 14,5 MPa, (K.175), slump (120 ± 20) mm Rp 35,667.50
E.I.5. Pembuatan 1 m2 bekisting untuk pelat beton pracetak (5 kali pakai) Rp 12,128.50
E.I.6. Pembuatan 1 m2 bekisting untuk balok beton pracetak (10-12 kali pakai) Rp 6,225.00
E.I.7. Pembuatan 1 m2 bekisting untuk kolom beton pracetak (10-12 kali pakai) Rp 6,225.00
E.I.8. Pemasangan dan membuka bekisting 1 buah komponen pelat beton pracetak Rp 9,097.50
E.I.9. Pemasangan dan membuka bekisting 1 buah komponen balok beton pracetak Rp 14,737.50
E.I.10. Pemasangan dan membuka bekisting 1 buah komponen kolom beton pracetak Rp 11,917.50
E.I.11. Penuangan/menebar beton 1 m3 komponen untuk pelat pracetak Rp 54,275.00
E.I.12. Penuangan/menebar beton 1 m3 komponen untuk balok pracetak Rp 55,025.00
E.I.13. Penuangan/menebar beton 1 m3 komponen untuk kolom pracetak Rp 49,837.50
E.I.14. Ereksi dan mendirikan 1 buah komponen untuk pelat pracetak Rp 36,012.50
E.I.15. Ereksi dan mendirikan 1 buah komponen untuk balok pracetak Rp 32,787.50
E.I.16. Ereksi dan mendirikan 1 buah komponen untuk kolom pracetak Rp 44,612.50
E.I.17. Langsir 1 buah komponen untuk pelat pracetak (± 20 m) Rp 6,982.50
E.I.18. Langsir 1 buah komponen untuk balok pracetak (± 20 m) Rp 6,982.50
E.I.19. Langsir 1 buah komponen untuk kolom pracetak (± 20 m) Rp 6,982.50
E.I.20. Bahan 1 m3 grout campuran Rp -
E.I.21. Bahan 1 m3 grout (tidak campuran) Rp -
E.I.22. Upah melakukan 1 titik grouting pada join pracetak Rp 63,257.50
E.I.23. Pemasangan 1 titik bekisting join pracetak Rp 38,977.50
E.I.24. Upah 1 titik join dengan sling Rp 57,365.00

F HARGA SATUAN PEKERJAAN BESI DAN ALUMINIUM


I (PERMEN NOMOR 28/PRT/M/2016)
NO
JENIS PEKERJAAN HARGA
PEKERJAAN
F.I.1. Pemasangan 1 kg besi profil Rp 15,885.00
F.I.2. Pemasangan 1 kg rangka kuda-kuda baja IWF Rp 15,885.00
F.I.3. Pengerjaan 100 kg pekerjaan perakitan Rp 24,897.50
F.I.3a Pengerjaan 1 kg pekerjaan perakitan Rp 248.98
F.I.4. Pembuatan 1 m2 pintu besi pelat baja tebal 2 mm rangkap, rangka baja siku Rp 277,912.50
F.I.5. Pengerjaan 10 cm pengelasan dengan las listrik Rp 7,645.00
F.I.5a Pengerjaan 1 cm pengelasan dengan las listrik Rp 764.50
F.I.6. Pembuatan 1 m2 rangka jendela besi scuare tube Rp 172,012.50
F.I.7. Pemasangan 1 m2 pintu rolling door besi Rp 309,600.00
F.I.8. Pemasangan 1 m2 pintu lipat (folding door) bahan plastik/PVC Rp 115,390.00
F.I.9. Pemasangan 1 m2 sunscreen aluminium Rp 125,400.00
F.I.10. Pemasangan 1 m2 rolling door aluminium Rp 264,750.00
F.I.11. Pemasangan 1 m kusen pintu aluminium Rp 11,376.75
F.I.12. Pemasangan 1 m2 pintu aluminium strip lebar 8 cm Rp 22,496.25
F.I.13. Pemasangan 1 m2 pintu kaca rangka aluminium Rp 22,690.00
F.I.14. Pemasangan 1 m2 venetions blinds dan vertical blinds Rp 92,737.50
F.I.15. Pemasangan 1 m2 terali besi strip (2 x 3) mm Rp 442,057.50
F.I.16. Pemasangan 1 m2 kawat nyamuk Rp 26,475.00
F.I.17. Pemasangan 1 m2 jendela nako & tralis Rp 51,600.00
F.I.18. Pemasangan 1 m1 talang datar/jurai seng bjls 28 lebar 90 cm Rp 51,600.00
F.I.19. Pemasangan 1 m talang 1/2 lingkaran D-15 cm, seng pelat bjls 30 lebar 45 cm Rp 61,500.00
F.I.20. Pemasangan 1 m2 rangka besi hollow 1 x 40.40.2 mm, modul 60 x 120 cm, untuk dinding partisi Rp 65,637.50
F.I.21. Pemasangan 1 m2 rangka besi hollow 1 x 40.40.2 mm, modul 60 x 60 cm, untuk plafon Rp 91,862.50
F.I.22. (K3) Pemasangan 1 m2 atap pelana rangka atap baja canai dingin profil C75 Rp 192,477.50
F.I.23. (K3) Pemasangan 1 m2 atap jurai rangka atap baja canai dingin profil C75 Rp 199,406.00
II ANALISA SENDIRI
F.II.1. Pemasangan 1 m2 rangka atap baja ringan UK - galvalume Rp 74,985.00
F.II.2. Pemasangan 1 m2 reng baja ringan Rp 35,300.00
F.II.3. Pemasangan 1 m1 railing hollow galvanis Rp 227,500.00
F.II.4. Pemasangan 1 m1 handrail Rp 113,750.00
F.II.5. Pemasangan 1 m1 railing Rp 50,975.00

G A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


I (PERMEN NOMOR 28/PRT/M/2016)
G.I.1. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 2PP Rp 100,450.00
G.I.2. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP Rp 100,450.00
G.I.3. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 4PP Rp 100,450.00
G.I.4. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 5PP Rp 100,450.00
G.I.5. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 6PP Rp 100,450.00
G.I.6. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3KP : 10PP Rp 100,450.00
G.I.7. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 2PP Rp 50,225.00
G.I.8. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 3PP Rp 50,225.00
G.I.9. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 4PP Rp 50,225.00
G.I.10. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 5PP Rp 50,225.00
G.I.11. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 6PP Rp 50,225.00
G.I.12. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 8PP Rp 50,225.00
G.I.13. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 3KP : 10PP Rp 50,225.00
G.I.14. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SM : 1KP : 1PP Rp 50,225.00
G.I.15. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SM : 1KP : 2PP Rp 50,225.00
G.I.16. Pemasangan 1 m2 dinding conblock HB20 campuran 1SP : 3PP Rp 63,412.50
G.I.17. Pemasangan 1 m2 dinding conblock HB20 campuran 1SP : 4PP Rp 63,412.50
G.I.18. Pemasangan 1 m2 dinding conblock HB15 campuran 1SP : 3PP Rp 55,470.00
G.I.19. Pemasangan 1 m2 dinding conblock HB15 campuran 1SP : 4PP Rp 55,470.00
G.I.20. Pemasangan 1 m2 dinding conblock HB10 campuran 1SP : 3PP Rp 50,225.00
G.I.21. Pemasangan 1 m2 dinding conblock HB10 campuran 1SP : 4PP Rp 192,695.73
G.I.22. Pemasangan 1 m2 dinding terawang (rooster) 12x11x24 campuran 1SP : 3PP Rp 50,225.00
G.I.23. Pemasangan 1 m2 dinding terawang (rooster) 12x11x24 campuran 1SP : 4PP Rp 50,225.00
G.I.24. Pemasangan 1 m2 dinding bata berongga ekspose 12x11x24 campuran 1SP : 3PP Rp 57,337.50
G.I.25. Pemasangan 1 m2 dinding bata ringan tebal 7,5 cm dengan mortar siap pakai Rp 260,750.00
G.I.26. Pemasangan 1 m2 dinding bata ringan tebal 10 cm dengan mortar siap pakai Rp 260,862.50
II (SNI-03-6897-2002)
G.II.1. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 1PP Rp 106,075.00
G.II.2. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 1PP Rp 52,475.00
G.II.3. Pemasangan 1 m2 dinding conblock CB20 Rp 67,729.00
G.II.4. Pemasangan 1 m2 dinding conblock CB15 Rp 60,288.25
G.II.5. Pemasangan 1 m2 dinding conblock CB10 Rp 57,016.50
G.II.6. Pemasangan 1 m2 dinding lantai Rp 20,535.00
G.II.7. Pemasangan 1 m2 dinding anyaman bambu, rangka kayu Rp 18,912.50
III (SNI-6897-2008)
G.III.1. Pemasangan 1 m2 dinding bata berongga ekspose 5x11x24 campuran 1SP : 3PP Rp 57,337.50
IV ANALISA SENDIRI
G.IV.1. Pemasangan 1 buah loster ukir paras 30 x 30 cm Rp 21,350.00

H HARGA SATUAN PEKERJAAN PLESTERAN


I (PERMEN NOMOR 28/PRT/M/2016)
H.I.1. Pemasangan 1 m2 plesteran 1SP : 1PP tebal 15 mm Rp 57,337.50
H.I.2. Pemasangan 1 m2 plesteran 1SP : 2PP tebal 15 mm Rp 57,337.50
NO
JENIS PEKERJAAN HARGA
PEKERJAAN
H.I.3. Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm Rp 57,337.50
H.I.4. Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm Rp 57,337.50
H.I.5. Pemasangan 1 m2 plesteran 1SP : 5PP tebal 15 mm Rp 57,337.50
H.I.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm Rp 57,337.50
H.I.7. Pemasangan 1 m2 plesteran 1SP : 7PP tebal 15 mm Rp 57,337.50
H.I.8. Pemasangan 1 m2 plesteran 1SP : 8PP tebal 15 mm Rp 57,337.50
H.I.9. Pemasangan 1 m2 plesteran 1SP : 1/2KP : 3PP tebal 15 mm Rp 60,270.00
H.I.10. Pemasangan 1 m2 plesteran 1SP : 2KP : 8PP tebal 15 mm Rp 60,270.00
H.I.11. Pemasangan 1 m2 plesteran 1SP : 1KP : 1PP tebal 15 mm Rp 60,270.00
H.I.12. Pemasangan 1 m2 plesteran 1SP : 1KP : 2PP tebal 15 mm Rp 60,270.00
H.I.13. Pemasangan 1 m2 plesteran 1SP : 1PP tebal 20 mm Rp 101,292.40
H.I.14. Pemasangan 1 m2 plesteran 1SP : 3PP tebal 20 mm Rp 58,175.00
H.I.15. Pemasangan 1 m2 plesteran 1SP : 4PP tebal 20 mm Rp 76,750.00
H.I.16. Pemasangan 1 m2 plesteran 1SP : 5PP tebal 20 mm Rp 76,750.00
H.I.17. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 20 mm Rp 76,750.00
H.I.18. Pemasangan 1 m2 plesteran 1SP : 1KP : 2PP tebal 20 mm Rp 81,545.00
H.I.19. Pemasangan 1 m2 berapen 1SP : 5PP tebal 15 mm Rp 28,817.50
H.I.20. Pemasangan 1 m1 plesteran skoning 1SP : 3PP 10 cm Rp 66,500.00
H.I.21. Pemasangan 1 m2 plesteran granit 1SP : 2 granit tebal 1 cm Rp 86,155.00
H.I.22. Pemasangan 1 m2 plesteran traso 1SP : 2 traso tebal 1 cm Rp 86,155.00
H.I.23. Pemasangan 1 m2 plesteran ciprat 1SP : 2PP Rp 57,389.00
H.I.24. Pemasangan 1 m2 finishing siar pasangan bata merah Rp 28,817.50
H.I.25. Pemasangan 1 m2 finishing siar pasangan conblock ekspose Rp 13,527.50
H.I.26. Pemasangan 1 m2 finishing siar pasangan batu kali, campuran 1SP : 2PP Rp 57,337.50
H.I.27. Pemasangan 1 m2 acian Rp 42,531.25
H.I.28. Pemasangan 1 m2 plesteran dengan mortar siap pakai (MSP) Rp -
H.I.29. Pemasangan 1 m2 plesteran acian mortar siap pakai (MSP) Rp -

I HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING


I (PERMEN NOMOR 28/PRT/M/2016)
I.I.1. Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 40 cm x 40 cm Rp 47,930.00
I.I.2. Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 30 cm x 30 cm Rp 47,930.00
I.I.3. Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 20 cm x 20 cm Rp 51,752.50
I.I.4. Pemasangan 1 m2 lantai ubin warna ukuran 40 cm x 40 cm Rp 47,930.00
I.I.5. Pemasangan 1 m2 lantai ubin warna ukuran 30 cm x 30 cm Rp 49,692.50
I.I.6. Pemasangan 1 m2 lantai ubin warna ukuran 20 cm x 20 cm Rp 51,752.50
I.I.7. Pemasangan 1 m2 lantai ubin teraso ukuran 40 cm x 40 cm Rp 47,930.00
I.I.8. Pemasangan 1 m2 lantai ubin teraso ukuran 30 cm x 30 cm Rp 49,692.50
I.I.9. Pemasangan 1 m2 lantai ubin granit ukuran 40 cm x 40 cm Rp 47,930.00
I.I.10. Pemasangan 1 m2 lantai ubin granit ukuran 30 cm x 30 cm Rp 49,692.50
I.I.11. Pemasangan 1 m2 lantai ubin teralux ukuran 40 cm x 40 cm Rp 47,930.00
I.I.12. Pemasangan 1 m2 lantai ubin teralux ukuran 30 cm x 30 cm Rp 49,692.50
I.I.13. Pemasangan 1 m2 lantai ubin teralux marmer ukuran 60 cm x 60 cm Rp 45,870.00
I.I.14. Pemasangan 1 m2 lantai ubin teralux marmer ukuran 40 cm x 40 cm Rp 47,930.00
I.I.15. Pemasangan 1 m2 lantai ubin teralux marmer ukuran 30 cm x 30 cm Rp 49,692.50
I.I.16. Pemasangan 1 m1 plint ubin PC abu-abu ukuran 15 cm x 20 cm Rp 23,677.50
I.I.17. Pemasangan 1 m1 plint ubin PC abu-abu ukuran 10 cm x 30 cm Rp 23,677.50
I.I.18. Pemasangan 1 m1 plint ubin PC abu-abu ukuran 10 cm x 40 cm Rp 23,677.50
I.I.19. Pemasangan 1 m1 plint ubin warna ukuran 10 cm x 20 cm Rp 23,677.50
I.I.20. Pemasangan 1 m1 plint ubin warna ukuran 10 cm x 30 cm Rp 23,677.50
I.I.21. Pemasangan 1 m1 plint ubin warna ukuran 10 cm x 40 cm Rp 23,677.50
I.I.22. Pemasangan 1 m1 plint ubin teraso ukuran 10 cm x 30 cm Rp 23,677.50
I.I.23. Pemasangan 1 m1 plint ubin teraso ukuran 10 cm x 40 cm Rp 23,677.50
I.I.24. Pemasangan 1 m1 plint ubin granit ukuran 10 cm x 40 cm Rp 23,677.50
I.I.25. Pemasangan 1 m1 plint ubin granit ukuran 10 cm x 30 cm Rp 23,677.50
I.I.26. Pemasangan 1 m1 plint ubin teralux kerang ukuran 10 cm x 40 cm Rp 23,677.50
I.I.27. Pemasangan 1 m1 plint ubin teralux kerang ukuran 10 cm x 30 cm Rp 23,677.50
I.I.28. Pemasangan 1 m1 plint ubin teralux marmer ukuran 10 cm x 60 cm Rp 23,677.50
I.I.29. Pemasangan 1 m1 plint ubin teralux marmer ukuran 10 cm x 40 cm Rp 23,677.50
I.I.30. Pemasangan 1 m1 plint ubin teralux marmer ukuran 10 cm x 30 cm Rp 23,677.50
I.I.31. Pemasangan 1 m2 lantai teraso cor di tempat, tebal 3 cm Rp 68,805.00
I.I.32. Pemasangan 1 m2 lantai keramik artistik 10 cm x 20 cm Rp 133,787.50
I.I.33. Pemasangan 1 m2 lantai keramik artistik 10 cm x 10 cm atau 5 cm x 20 cm Rp 133,787.50
I.I.34. Pemasangan 1 m2 lantai keramik ukuran 33 cm x 33 cm Rp 133,787.50
I.I.35. Pemasangan 1 m2 lantai keramik ukuran 30 cm x 30 cm Rp 133,787.50
I.I.36. Pemasangan 1 m2 lantai keramik ukuran 20 cm x 20 cm Rp 133,787.50
I.I.37. Pemasangan 1 m2 lantai keramik ukuran 10 cm x 33 cm untuk variasi/border Rp 200,830.00
I.I.38. Pemasangan 1 m2 lantai keramik mozaik ukuran 30 cm x 30 cm Rp 133,787.50
I.I.39. Pemasangan 1 m1 plint keramik ukuran 10 cm x 20 cm Rp 27,512.50
I.I.40. Pemasangan 1 m1 plint keramik ukuran 10 cm x 10 cm Rp 27,512.50
I.I.41. Pemasangan 1 m1 plint keramik ukuran 5 cm x 20 cm Rp 27,512.50
I.I.42. Pemasangan 1 m1 plint internal cove artistik 5 cm x 5 cm x 20 cm Rp 196,762.50
I.I.43. Pemasangan 1 m2 lantai marmer ukuran 100 cm x 100 cm Rp 133,787.50
I.I.44. Pemasangan 1 m2 lantai karpet Rp 45,507.50
I.I.45. Pemasangan 1 m2 underlayer (pelapis bawah karpet) Rp 32,070.00
I.I.46. Pemasangan 1 m2 lantai parquet kayu Rp 135,537.50
I.I.47. Pemasangan 1 m2 lantai kayu gymfloor Rp 135,537.50
NO
JENIS PEKERJAAN HARGA
PEKERJAAN
I.I.48. Pemasangan 1 m2 dinding porselen 11 cm x 11 cm Rp 191,125.00
I.I.49. Pemasangan 1 m2 dinding porselen 10 cm x 20 cm Rp 172,012.50
I.I.50. Pemasangan 1 m2 dinding porselen 20 cm x 20 cm Rp 172,012.50
I.I.51. Pemasangan 1 m2 dinding keramik artistik 10 cm x 20 cm Rp 172,012.50
I.I.52. Pemasangan 1 m2 dinding keramik artistik 5 cm x 20 cm Rp 172,012.50
I.I.53. Pemasangan 1 m2 dinding keramik 10 cm x 20 cm Rp 172,012.50
I.I.54. Pemasangan 1 m2 dinding keramik 20 cm x 20 cm Rp 172,012.50
I.I.55. Pemasangan 1 m2 dinding marmer 100 cm x 100 cm Rp 248,462.50
I.I.56. Pemasangan 1 m2 dinding bata pelapis 3 cm x 7 cm x 24 cm Rp 191,125.00
I.I.57. Pemasangan 1 m2 dinding batu paras Rp 133,787.50
I.I.58. Pemasangan 1 m2 dinding batu tempel hitam Rp 133,787.50
I.I.59. Pemasangan 1 m2 lantai vinyl ukuran 30 cm x 30 cm Rp 39,412.50
I.I.60. Pemasangan 1 m2 wallpaper lebar 50 cm Rp 64,495.00
I.I.61. Pemasangan 1 m2 floor harderner Rp 31,470.00
I.I.62. Pemasangan 1 m1 plint vinyl 15 cm x 30 cm Rp 20,980.00
I.I.63. Pemasangan 1 m1 plint kayu tebal 2 cm lebar 10 cm Rp 31,470.00
I.I.64. Pemasangan 1 m2 paving block natural 6 cm Rp 99,445.00
I.I.65. Pemasangan 1 m2 paving block natural 8 cm Rp 127,570.00
I.I.66. Pemasangan 1 m2 paving block berwarna tebal 6 cm Rp 99,445.00
I.I.67. Pemasangan 1 m2 paving block berwarna tebal 8 cm Rp 127,570.00
II ANALISA SENDIRI
I.II.1. Pemasangan 1 m2 koral sikat Rp 191,125.00
I.II.2. Pemasangan 1 m1 kanstein jumbo (P:50, L:15, T:30, K225) Rp 170,912.50
I.II.3. Pemasangan 1 m1 kanstein kursi (P:50, L:10, T:40, K225) Rp 170,912.50
I.II.4. Pemasangan 1 m2 lantai granit tile ukuran 60 x 60 cm Rp 32,012.50
I.II.5. Pemasangan 1 m1 plint granit tile ukuran 10 x 60 cm Rp 32,012.50
I.II.6. Pemasangan 1 m2 dinding keramik ukuran 20 x 40 cm Rp 441,180.00
I.II.7. Pemasangan 1 m2 dinding keramik ukuran 25 x 40 cm Rp 172,012.50

J SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)


I (PERMEN NOMOR 28/PRT/M/2016)
J.I.1. Pemasangan 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm Rp 14,282.50
J.I.2. Pemasangan 1 m2 langit-langit akustik ukuran 30 x 30 cm Rp 32,070.00
J.I.3. Pemasangan 1 m2 langit-langit akustik ukuran 30 x 60 cm Rp 32,070.00
J.I.4. Pemasangan 1 m2 langit-langit akustik ukuran 60 x 120 cm Rp 26,725.00
J.I.5. Pemasangan 1 m2 langit-langit tripleks ukuran 120 x 240 cm, tebal 3 mm, 4 mm & 6 mm Rp 26,725.00
J.I.6. Pemasangan 1 m2 langit-langit lambersering kayu, tebal 9 mm Rp 339,444.17
J.I.7. Pemasangan 1 m2 langit-langit gypsum board ukuran 120 x 240 x 9 mm, tebal 9 mm Rp 19,362.50
J.I.8. Pemasangan 1 m2 langit-langit akustik ukuran 60 x 120 cm berikut rangka alluminium Rp 131,125.00
J.I.9. Pemasangan 1 m1 list langit-langit kayu profil Rp 13,437.50
J.I.10. Pemasangan 1 m2 rangka langit-langit besi hollow 40 x 40 Rp 91,862.50
II (SNI 2839:2008)
J.II.1. Pemasangan 1 m1 list plafond gypsum profil Rp 16,035.00
III ANALISA SENDIRI
J.III.1. Pemasangan 1 m2 plafond kalsiboard Rp 42,425.00
J.III.2. Pemasangan 1 m2 plafond PVC Rp 96,625.00
J.III.3. Pemasangan 1 m1 list plafond PVC Rp 19,362.50

K HARGA SATUAN PEKERJAAN PENUTUP ATAP


I (PERMEN NOMOR 28/PRT/M/2016)
K.I.1. Pemasangan 1 m2 atap genteng palentong kecil Rp 29,118.75
K.I.2. Pemasangan 1 m2 atap genteng kodok glazur Rp 29,192.50
K.I.3. Pemasangan 1 m2 atap genteng plentong besar/super Rp 83,192.50
K.I.4. Pemasangan 1 m1 bubung genteng plentong Rp 74,750.00
K.I.5. Pemasangan 1 m1 bubung genteng kodok glazuur Rp 74,750.00
K.I.6. Pemasangan 1 m1 bubung genteng plentong besar Rp 117,030.00
K.I.7. Pemasangan 1 m2 roof light fibreglass 90 x 180 Rp 26,710.00
K.I.8. Pemasangan 1 m2 asbes gelombang 0,92 m x 2,50 m x 5 mm Rp 28,067.50
K.I.9. Pemasangan 1 m2 asbes gelombang 0,92 m x 2,25 m x 5 mm Rp 28,067.50
K.I.10. Pemasangan 1 m2 asbes gelombang 0,92 m x 2,00 m x 5 mm Rp 27,107.50
K.I.11. Pemasangan 1 m2 asbes gelombang 0,92 m x 1,80 m x 5 mm Rp 27,107.50
K.I.12. Pemasangan 1 m2 asbes gelombang 1,05 m x 3,00 m x 4 mm Rp 27,107.50
K.I.13. Pemasangan 1 m2 asbes gelombang 1,05 m x 2,70 m x 4 mm Rp 27,107.50
K.I.14. Pemasangan 1 m2 asbes gelombang 1,05 m x 2,40 m x 4 mm Rp 27,107.50
K.I.15. Pemasangan 1 m2 asbes gelombang 1,05 m x 2,10 m x 4 mm Rp 27,107.50
K.I.16. Pemasangan 1 m2 asbes gelombang 1,05 m x 1.50 m x 4 mm Rp 27,107.50
K.I.17. Pemasangan 1 m2 asbes gelombang 1,08 m x 3.00 m x 6 mm Rp 27,107.50
K.I.18. Pemasangan 1 m2 asbes gelombang 1,08 m x 2.70 m x 6 mm Rp 27,107.50
K.I.19. Pemasangan 1 m2 asbes gelombang 1,08 m x 2.40 m x 6 mm Rp 27,107.50
K.I.20. Pemasangan 1 m2 asbes gelombang 1,08 m x 2.10 m x 6 mm Rp 27,107.50
K.I.21. Pemasangan 1 m2 asbes gelombang 1,08 m x 1,80 m x 6 mm Rp 27,107.50
K.I.22. Pemasangan 1 m1 bubung stel gelombang 0,92 m Rp 28,530.00
K.I.23. Pemasangan 1 m1 bubung stel gelombang 1,05 m Rp 28,530.00
K.I.24. Pemasangan 1 m1 bubung stel gelombang 1,08 m Rp 28,530.00
K.I.25. Pemasangan 1 m1 nok paten 0,92 m Rp 28,530.00
K.I.26. Pemasangan 1 m1 nok paten 1,05 m Rp 28,530.00
K.I.27. Pemasangan 1 m1 nok paten 1,08 m Rp 28,530.00
NO
JENIS PEKERJAAN HARGA
PEKERJAAN
K.I.28. Pemasangan 1 m1 nok stel rata 0,92 m Rp 33,642.50
K.I.29. Pemasangan 1 m1 nok stel rata 1,05 m Rp 28,530.00
K.I.30. Pemasangan 1 m2 genteng beton Rp 38,725.00
K.I.31. Pemasangan 1 m2 genteng aspal Rp 64,192.50
K.I.32. Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap pelana Rp 37,375.00
K.I.33. Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap jurai Rp 37,375.00
K.I.34. Pemasangan 1 m2 atap sirap kayu Rp 56,687.50
K.I.35. Pemasangan 1 m1 nok genteng beton Rp 77,450.00
K.I.36. Pemasangan 1 m1 nok genteng aspal Rp 51,775.00
K.I.37. Pemasangan 1 m1 nok genteng metal Rp 52,162.50
K.I.38. Pemasangan 1 m1 nok sirap Rp 51,775.00
K.I.39. Pemasangan 1 m2 atap seng gelombang Rp 23,235.00
K.I.40. Pemasangan 1 m1 nok atap seng Rp 28,082.50
K.I.41. Pemasangan 1 m2 atap aluminium Rp 128,950.00
K.I.42. Pemasangan 1 m1 nok aluminium Rp 166,000.00
K.I.43. Pemasangan 1 m2 aluminium foil/sisalation Rp 25,437.50
II ANALISA SENDIRI
K.II.1. Pemasangan 1 buah murda paras Rp 49,725.00
K.II.2. Pemasangan 1 buah ikut celedu paras Rp 139,725.00
K.II.3. Pemasangan 1 buah bentala paras Rp 199,725.00

L HARGA SATUAN PEKERJAAN KAYU


I (PERMEN NOMOR 28/PRT/M/2016)
L.I.1. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I Rp 3,932,250.00
L.I.2. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III Rp 3,370,500.00
L.I.3. Pembuatan dan pemasangan 1 m2 pintu klamp standar, kayu kelas II Rp 196,687.50
L.I.4. Pembuatan dan pemasangan 1 m2 pintu klamp sederhana, kayu kelas III Rp 196,687.50
L.I.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau II Rp 561,750.00
L.I.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau II Rp 449,400.00
L.I.7. Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi kayu kelas I atau II Rp 561,750.00
L.I.8. Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90 cm) Rp 393,225.00
L.I.9. Pembuatan 1 m2 pintu plywood rangkap, rangka expose kayu kelas I atau II Rp 449,400.00
L.I.10. Pemasangan 1 m2 jalusi kusen, kayu kelas I atau II Rp 420,125.00
L.I.11. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I Rp 449,400.00
L.I.12. Pemasangan 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas II Rp 477,562.50
L.I.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter Rp 2,247,000.00
L.I.14. Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas I Rp 3,763,725.00
L.I.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II Rp 3,763,725.00
L.I.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II Rp 26,725.00
L.I.17. Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II Rp 26,725.00
L.I.18. Pemasangan 1 m2 rangka atap sirap, kayu kelas II Rp 32,070.00
L.I.19. Pemasangan 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas II atau III Rp 72,300.00
L.I.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III Rp 68,175.00
L.I.21. Pemasangan 1 m1 lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II Rp 41,450.00
L.I.22. Pemasangan 1 m1 lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II Rp 134,470.83
L.I.23. Pemasangan 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas I Rp 84,337.50
II (PERMEN NO.11/PRT/M/2013)
L.II.1. Pemasangan 1 m2 dinding pemisah teakwood rangkap, rangka kayu kelas II Rp 84,337.50
III (SNI-3434-2008)
L.III.1. Pemasangan 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II Rp 112,350.00
L.III.2. Pemasangan 1 m2 dinding lambersering dari papan kayu kelas I Rp 337,050.00
L.III.3. Pemasangan 1 m2 dinding lambersering dari plywood ukuran (120 x 240) cm Rp 24,700.00
L.III.4. Pemasangan 1 m2 dinding bilik, rangka kayu kelas III atau IV Rp 19,362.50
IV ANALISA SENDIRI
L.IV.1. Pekerjaan 1 m2 anti rayap (wood treatment) Rp 20,025.00
L.IV.2. Pemasangan 1 m2 HPL Rp 14,080.00
L.IV.3. Pemasangan 1 m3 balok kayu Rp 12,135,558.33
L.IV.4. Pemasangan 1 m2 usuk kuda-kuda expose Rp 95,716.67
L.IV.5. Pemasangan 1 m2 reng kuda-kuda expose Rp 68,020.00
L.IV.6. Pemasangan 1 m1 lisplank ukuran (2 x 20) cm, kayu kelas I atau kelas II Rp 75,933.33
L.IV.7. Pemasangan 1 m1 lisplank ukuran (2 x 15) cm, kayu kelas I atau kelas II Rp 67,570.83
L.IV.8. Pemasangan 1 m1 tatab ukuran (3 x 10) cm, kayu kelas I atau kelas II Rp 67,570.83

M HARGA SATUAN PEKERJAAN KUNCI DAN KACA


I (PERMEN NOMOR 28/PRT/M/2016)
M.I.1. Pemasangan 1 buah kunci tanam antik Rp 95,550.00
M.I.2. Pemasangan 1 buah kunci tanam biasa Rp 75,500.00
M.I.3. Pemasangan 1 buah kunci kamar mandi Rp 74,637.50
M.I.4. Pemasangan 1 buah kunci silinder Rp 74,637.50
M.I.5. Pemasangan 1 buah engsel pintu Rp 23,895.00
M.I.6. Pemasangan 1 buah engsel jendela kupu-kupu Rp 15,925.00
M.I.7. Pemasangan 1 buah engsel angin Rp 40,775.00
M.I.8. Pemasangan 1 buah spring knip Rp 24,975.00
M.I.9. Pemasangan 1 buah kait angin Rp 24,975.00
M.I.10. Pemasangan 1 buah door closer Rp 79,700.00
M.I.11. Pemasangan 1 buah kunci slot Rp 31,850.00
NO
JENIS PEKERJAAN HARGA
PEKERJAAN
M.I.12. Pemasangan 1 buah door holder Rp 79,700.00
M.I.13. Pemasangan 1 buah door stop Rp 16,600.00
M.I.14. Pemasangan 1 buah rel pintu sorong Rp 95,550.00
M.I.15. Pemasangan 1 buah kunci lemari Rp 39,820.00
M.I.16. Pemasangan 1 m2 kaca tebal 3 mm Rp 23,895.00
M.I.17. Pemasangan 1 m2 kaca tebal 5 mm Rp 23,895.00
M.I.18. Pemasangan 1 m2 kaca tebal 8 mm Rp 27,080.00
M.I.19. Pemasangan 1 m2 kaca buram tebal 12 mm Rp 39,820.00
M.I.20. Pemasangan 1 m2 kaca cermin tebal 5 mm Rp 24,975.00
M.I.21. Pemasangan 1 m2 kaca cermin tebal 8 mm Rp 28,295.00
M.I.22. Pemasangan 1 m2 kaca wireglassed tebal 5 mm Rp 24,975.00
M.I.23. Pemasangan 1 m2 kaca patri tebal 5 mm Rp 31,125.00
II PT-T-30-2000-C
M.II.1. Pemasangan 1 m2 kaca tebal 3 mm dengan kisi-kisi Rp 66,887.50
M.II.2. Pemasangan 1 m2 kaca raiben tebal 5 mm Rp 42,760.00
M.II.3. Pemasangan 1 m2 kaca raiben tebal 10 mm Rp 48,555.00
M.II.4. Pemasangan 1 m2 kaca raiben tebal 12 mm Rp 48,555.00
M.II.5. Pemasangan 1 m2 kaca buram tebal 3 mm Rp 42,760.00
M.II.6. Pemasangan 1 m2 kaca buram tebal 5 mm Rp 42,760.00
M.II.7. Pemasangan 1 m2 kaca buram tebal 3 mm (motif) Rp 42,760.00
M.II.8. Pemasangan 1 m2 kaca buram tebal 5 mm (motif) Rp 42,760.00
III ANALISA SENDIRI
M.III.1. Pemasangan 1 buah handel pintu Rp 79,700.00

N HARGA SATUAN PEKERJAAN PENGECATAN


I (PERMEN NOMOR 28/PRT/M/2016)
N.I.1. Pengikisan/pengerokan 1 m2 permukaan cat lama Rp 17,325.00
N.I.2. Pencucian 1 m2 bidang permukaan tembok yang pernah dicat Rp 17,325.00
N.I.3. Pengerokan 1 m2 karat pada permukaan baja cara manual Rp 18,075.00
N.I.4. Pengecatan 1 m2 bidang kayu baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup) Rp 10,357.50
N.I.5. Pengecatan 1 m2 bidang kayu baru (1 lapis plamur, 1 lapis cat dasar, 3 lapis cat penutup) Rp 22,302.50
N.I.6. Pelaburan 1 m2 bidang kayu dengan teak oil Rp 22,275.00
N.I.7. Pelaburan 1 m2 bidang kayu dengan politur Rp 81,716.67
N.I.8. Pelaburan 1 m2 bidang kayu dengan cat residu dan ter Rp 12,150.00
N.I.9. Pelaburan 1 m2 bidang kayu dengan vernis Rp 41,210.00
N.I.10. Pengecatan 1 m2 tembok baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup) Rp 11,661.75
N.I.11. Pengecatan 1 m2 tembok lama (1 lapis cat dasar, 2 lapis cat penutup) Rp 9,574.50
N.I.12. Pelaburan 1 m2 tembok dengan kalkarium Rp 9,574.50
N.I.13. Pelaburan 1 m2 tembok dengan kapur sirih Rp 17,392.25
N.I.14. Pelaburan 1 m2 tembok lama dengan kapur sirih (pemeliharaan) Rp 5,586.25
N.I.15. Pemasangan 1 m2 wallpaper Rp 31,075.00
N.I.16. Pengecatan 1 m2 permukaan baja dengan menie besi Rp 31,075.00
N.I.17. Pengecatan 1 m2 permukaan baja dengan menie besi dengan perancah Rp 61,256.25
N.I.18. Pengecatan 1 m2 permukaan baja galvanis secara manual 4 lapis Rp 63,882.50
N.I.19. Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 1 lapis cat mutakhir Rp 16,620.00
N.I.20. Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 3 lapis Rp 161,800.00
N.I.21. Pengecatan 1 m2 permukaan baja galvanis secara semprot sistem 3 lapis cat mutakhir Rp 147,575.00
N.I.22. Pengecatan 10 m2 dengan plitur melamic Rp 1,947,000.00
N.I.22a. Pengecatan 1 m2 dengan plitur melamic Rp 194,700.00
II PT-T-38-2000-C
N.II.1. Pengecatan 1 m2 lapis plamir Rp 6,667.50
N.II.2. Pengecatan 1 m2 langit-langit 2 lapis dengan cat tembok, menggunakan kuas termasuk plamur Rp 18,135.00
N.II.3. Pengecatan 1 m2 plafond 2 lapis dengan cat tembok menggunakan roll Rp 12,890.00
III ANALISA SENDIRI
N.III.1. Pengecatan 1 m2 tembok interior Rp 11,617.50
N.III.2. Pengecatan 1 m2 tembok eksterior Rp 20,617.50
N.III.3. Pekerjaan 1 m2 waterproofing Rp 23,632.50
N.III.4. Pekerjaan 1 m2 coating batu alam Rp 23,632.50
N.III.5. Pekerjaan 1 m2 cat lantai epoxy Rp 23,632.50

O HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


I (PERMEN NOMOR 28/PRT/M/2016)
O.I.1. Pemasangan 1 buah closet duduk/monoblock Rp 1,941,475.00
O.I.2. Pemasangan 1 buah closet jongkok porselen Rp 349,875.00
O.I.3. Pemasangan 1 buah closet jongkok teraso Rp 333,375.00
O.I.4. (K3) Pemasangan 1 buah urinoir Rp 1,535,405.00
O.I.5. (K3) Pemasangan 1 buah wastafel Rp 1,082,304.00
O.I.6. (K3) Pemasangan 1 buah bathcuip porselen Rp 115,575.00
O.I.7. (K3) Pemasangan 1 buah bak fibreglass vol 1 m3 Rp 1,053,625.00
O.I.8. (K3) Pemasangan 1 buah bak mandi batu bata vol 0.30 m3 Rp 1,106,250.00
O.I.9. Pemasangan 1 buah bak mandi teraso vol 0.30 m3 Rp 1,053,625.00
O.I.10. Pemasangan 1 buah bak air fibreglass vol 1 m3 Rp 100,012.50
O.I.11. (K3) Pemasangan 1 buah bak beton volume 1 m3 Rp 977,575.00
O.I.12. Pemasangan 1 buah bak cuci piring stainlessteel Rp 48,300.00
O.I.13. Pemasangan 1 buah bak cuci piring teraso Rp 80,500.00
O.I.14. Pemasangan 1 buah floor drain Rp 48,600.00
O.I.15. Pemasangan 1 buah bak kontrol pasangan bata 30 cm x 30 cm tinggi 35 cm Rp 347,070.00
NO
JENIS PEKERJAAN HARGA
PEKERJAAN
O.I.16. Pemasangan 1 buah bak kontrol pasangan bata 45 cm x 45 cm tinggi 50 cm Rp 510,647.50
O.I.17. Pemasangan 1 buah bak kontrol pasangan bata 60 cm x 60 cm tinggi 65 cm Rp 510,647.50
O.I.18. Pemasangan 1 m1 pipa galvanis diameter 1/2" Rp 22,927.50
O.I.19. Pemasangan 1 buah kran diameter 1/2" atau 3/4" Rp 87,650.00
O.I.20. Pemasangan 1 m1 pipa galvanis diameter 3/4" Rp 22,927.50
O.I.21. Pemasangan 1 m1 pipa galvanis diameter 1" Rp 22,927.50
O.I.22. Pemasangan 1 m1 pipa galvanis diameter 1 1/2" Rp 38,505.00
O.I.23. Pemasangan 1 m1 pipa galvanis diameter 3" Rp 48,317.50
O.I.24. Pemasangan 1 m1 pipa galvanis diameter 4" Rp 48,317.50
O.I.25. Pemasangan 1 m1 pipa PVC tipe AW diameter 1/2" Rp 12,885.00
O.I.26. Pemasangan 1 m1 pipa PVC tipe AW diameter 3/4" Rp 30,300.00
O.I.27. Pemasangan 1 m1 pipa PVC tipe AW diameter 1" Rp 12,885.00
O.I.28. Pemasangan 1 m1 pipa PVC tipe AW diameter 1 1/2" Rp 19,327.50
O.I.29. Pemasangan 1 m1 pipa PVC tipe AW diameter 2" Rp 78,457.50
O.I.30. Pemasangan 1 m1 pipa PVC tipe AW diameter 2 1/2" Rp 28,916.25
O.I.31. Pemasangan 1 m1 pipa PVC tipe AW diameter 3" Rp 137,456.25
O.I.32. Pemasangan 1 m1 pipa PVC tipe AW diameter 4" Rp 28,916.25
O.I.33. Pemasangan 1 m1 pipa air limbah jenis pipa tanah diameter 20 cm Rp 15,290.00
O.I.34. Pemasangan 1 m1 pipa air limbah jenis pipa tanah diameter 15 cm Rp 11,467.50
O.I.35. Pemasangan 1 m1 pipa beton diameter 15 - 20 cm Rp 26,757.50
O.I.36. Pemasangan 1 m1 pipa beton diameter 30 - 100 cm Rp 72,627.50
II ANALISA SENDIRI
O.II.1. Pemasangan 1 buah shower spray Rp 58,775.00
O.II.2. Pemasangan 1 buah kran wastafel Rp 433,900.00
O.II.3. Pemasangan 1 unit biotank Rp 4,219,433.18
O.II.4. Pemasangan 1 unit ground tank Rp 2,877,337.22
O.II.5. Pemasangan 1 unit peresapan Rp 763,536.33
O.II.6. Pemasangan 1 unit biopori Rp 617,161.33
O.II.7. Pemasangan 1 buah tempat sabun Rp 16,100.00
O.II.8. Pemasangan 1 unit tangki air stainless kapasitas 1000 liter Rp 752,500.00
O.II.9. Pemasangan 1 unit pompa pendorong Rp 256,250.00
O.II.10. Pemasangan 1 unit pompa submersible Rp 256,250.00
O.II.11. Pemasangan 1 unit pompa transfer Rp 689,200.00
O.II.12. Pemasangan 1 m1 pipa PPR dia. 20 mm (1/2") PN-10 Rp 13,900.00
O.II.13. Pemasangan 1 m1 pipa PPR dia. 25 mm (3/4") PN-10 Rp 13,900.00
O.II.14. Pemasangan 1 m1 pipa PPR dia. 40 mm (1 1/4") PN-10 Rp 19,327.50

P HARGA SATUAN PEKERJAAN PEMASANGAN PIPA DI LUAR GEDUNG


I (PERMEN NOMOR 28/PRT/M/2016)
P.I.1. (K3) Pemasangan 1 m pipa PVC Ø 63 mm Rp 15,540.00
P.I.2. (K3) Pemasangan 1 m pipa PVC Ø 90 mm Rp 17,917.50
P.I.3. (K3) Pemasangan 1 m pipa PVC Ø 110 mm Rp 20,220.00
P.I.4. (K3) Pemasangan 1 m pipa PVC Ø 150 mm Rp 22,597.50
P.I.5. (K3) Pemasangan 1 m pipa PVC Ø 200 mm Rp 36,225.00
P.I.6. (K3) Pemasangan 1 m pipa PVC Ø 250 mm Rp 49,020.00
P.I.7. (K3) Pemasangan 1 m pipa PVC Ø 300 mm Rp 56,167.50
P.I.8. (K3) Pemasangan 1 m pipa PVC Ø 400 mm Rp 103,980.00
P.I.9. (K3) Pemasangan 1 m pipa PVC Ø 450 mm Rp 128,025.00
P.I.10. (K3) Pemasangan 1 m pipa PVC Ø 500 mm Rp 154,800.00
P.I.11. (K3) Pemasangan 1 m pipa PVC Ø 600 mm Rp 183,135.00
P.I.12. (K3) Pemasangan 1 m pipa PVC Ø 800 mm Rp 309,472.50
P.I.13. (K3) Pemasangan 1 m pipa PVC Ø 900 mm Rp 323,452.50
P.I.14. (K3) Pemasangan 1 m pipa PVC Ø 1000 mm Rp 362,557.50
P.I.15. (K3) Pemasangan 1 m pipa PVC Ø 1100 mm Rp 401,512.50
P.I.16. (K3) Pemasangan 1 m pipa PVC Ø 1200 mm Rp 440,467.50
P.I.17. (K3) Pemasangan 1 m pipa HDPE Ø 63 mm Rp 6,555.00
P.I.18. (K3) Pemasangan 1 m pipa HDPE Ø 100 mm Rp 7,650.00
P.I.19. (K3) Pemasangan 1 m pipa HDPE Ø 125 mm Rp 8,745.00
P.I.20. (K3) Pemasangan 1 m pipa HDPE Ø 150 mm Rp 11,827.50
P.I.21. (K3) Pemasangan 1 m pipa HDPE Ø 200 mm Rp 19,477.50
P.I.22. (K3) Pemasangan 1 m pipa HDPE Ø 250 mm Rp 25,455.00
P.I.23. (K3) Pemasangan 1 m pipa HDPE Ø 300 mm Rp 32,512.50
P.I.24. (K3) Pemasangan 1 m pipa HDPE Ø 400 mm Rp 55,462.50
P.I.25. (K3) Pemasangan 1 m pipa HDPE Ø 450 mm Rp 68,737.50
P.I.26. (K3) Pemasangan 1 m pipa HDPE Ø 500 mm Rp 82,702.50
P.I.27. (K3) Pemasangan 1 m pipa HDPE Ø 600 mm Rp 97,890.00
P.I.28. (K3) Pemasangan 1 m pipa HDPE Ø 800 mm Rp 170,677.50
P.I.29. (K3) Pemasangan 1 m pipa HDPE Ø 900 mm Rp 258,780.00
P.I.30. (K3) Pemasangan 1 m pipa HDPE Ø 1000 mm Rp 317,362.50
P.I.31. (K3) Pemasangan 1 m pipa HDPE Ø 1100 mm Rp 347,722.50
P.I.32. (K3) Pemasangan 1 m pipa HDPE Ø 1200 mm Rp 453,262.50
P.I.33. (K3) Pemasangan 1 m pipa GIP Ø 63 mm Rp 65,842.50
P.I.34. (K3) Pemasangan 1 m pipa GIP Ø 100 mm Rp 76,500.00
P.I.35. (K3) Pemasangan 1 m pipa GIP Ø 125 mm Rp 85,710.00
P.I.36. (K3) Pemasangan 1 m pipa GIP Ø 150 mm Rp 96,832.50
P.I.37. (K3) Pemasangan 1 m pipa GIP Ø 200 mm Rp 152,295.00
P.I.38. (K3) Pemasangan 1 m pipa GIP Ø 250 mm Rp 181,575.00
NO
JENIS PEKERJAAN HARGA
PEKERJAAN
P.I.39. (K3) Pemasangan 1 m pipa GIP Ø 300 mm Rp 183,247.50
P.I.40. (K3) Pemasangan 1 m pipa GIP Ø 400 mm Rp 231,765.00
P.I.41. (K3) Pemasangan 1 m pipa GIP Ø 450 mm Rp 258,652.50
P.I.42. (K3) Pemasangan 1 m pipa GIP Ø 500 mm Rp 281,025.00
P.I.43. (K3) Pemasangan 1 m pipa GIP Ø 600 mm Rp 253,897.50
P.I.44. (K3) Pemasangan 1 m pipa GIP Ø 800 mm Rp 445,020.00
P.I.45. (K3) Pemasangan 1 m pipa GIP Ø 900 mm Rp 501,667.50
P.I.46. (K3) Pemasangan 1 m pipa GIP Ø 1000 mm Rp 556,777.50
P.I.47. (K3) Pemasangan 1 m pipa GIP Ø 1100 mm Rp 612,000.00
P.I.48. (K3) Pemasangan 1 m pipa GIP Ø 1200 mm Rp 667,110.00
P.I.49. (K3) Pemasangan 1 m pipa DCI Ø 100 mm Rp 74,857.50
P.I.50. (K3) Pemasangan 1 m pipa DCI Ø 125 mm Rp 83,685.00
P.I.51. (K3) Pemasangan 1 m pipa DCI Ø 150 mm Rp 93,795.00
P.I.52. (K3) Pemasangan 1 m pipa DCI Ø 200 mm Rp 130,740.00
P.I.53. (K3) Pemasangan 1 m pipa DCI Ø 250 mm Rp 145,462.50
P.I.54. (K3) Pemasangan 1 m pipa DCI Ø 300 mm Rp 148,875.00
P.I.55. (K3) Pemasangan 1 m pipa DCI Ø 400 mm Rp 252,585.00
P.I.56. (K3) Pemasangan 1 m pipa DCI Ø 450 mm Rp 302,420.00
P.I.57. (K3) Pemasangan 1 m pipa DCI Ø 500 mm Rp 346,960.00
P.I.58. (K3) Pemasangan 1 m pipa DCI Ø 600 mm Rp 358,917.50
P.I.59. (K3) Pemasangan 1 m pipa DCI Ø 800 mm Rp 676,742.50
P.I.60. (K3) Pemasangan 1 m pipa DCI Ø 900 mm Rp 867,935.00
P.I.61. (K3) Pemasangan 1 m pipa DCI Ø 1000 mm Rp 1,061,177.50
P.I.62. (K3) Pemasangan 1 m pipa DCI Ø 1100 mm Rp 1,202,012.50
P.I.63. (K3) Pemasangan 1 m pipa DCI Ø 1200 mm Rp 1,388,877.50
P.I.64. (K3) Pemasangan 1 m pipa baja Ø 63 mm Rp 76,387.50
P.I.65. (K3) Pemasangan 1 m pipa baja Ø 100 mm Rp 88,627.50
P.I.66. (K3) Pemasangan 1 m pipa baja Ø 125 mm Rp 99,225.00
P.I.67. (K3) Pemasangan 1 m pipa baja Ø 150 mm Rp 108,405.00
P.I.68. (K3) Pemasangan 1 m pipa baja Ø 200 mm Rp 170,295.00
P.I.69. (K3) Pemasangan 1 m pipa baja Ø 250 mm Rp 202,800.00
P.I.70. (K3) Pemasangan 1 m pipa baja Ø 300 mm Rp 216,420.00
P.I.71. (K3) Pemasangan 1 m pipa baja Ø 400 mm Rp 362,032.50
P.I.72. (K3) Pemasangan 1 m pipa baja Ø 450 mm Rp 341,302.50
P.I.73. (K3) Pemasangan 1 m pipa baja Ø 500 mm Rp 372,015.00
P.I.74. (K3) Pemasangan 1 m pipa baja Ø 600 mm Rp 337,905.00
P.I.75. (K3) Pemasangan 1 m pipa baja Ø 800 mm Rp 596,235.00
P.I.76. (K3) Pemasangan 1 m pipa baja Ø 900 mm Rp 571,665.00
P.I.77. (K3) Pemasangan 1 m pipa baja Ø 1000 mm Rp 748,860.00
P.I.78. (K3) Pemasangan 1 m pipa baja Ø 1100 mm Rp 824,205.00
P.I.79. (K3) Pemasangan 1 m pipa baja Ø 1200 mm Rp 901,552.50

Q HARGA SATUAN PEKERJAAN PEMOTONGAN PIPA


I (PERMEN NOMOR 28/PRT/M/2016)
Q.I.1. (K3) Pemotongan 1 buah pipa PVC Ø 63 mm Rp 892.50
Q.I.2. (K3) Pemotongan 1 m pipa PVC Ø 90 mm Rp 2,617.50
Q.I.3. (K3) Pemotongan 1 buah pipa PVC Ø 110 mm Rp 4,177.50
Q.I.4. (K3) Pemotongan 1 buah pipa PVC Ø 150 mm Rp 5,850.00
Q.I.5. (K3) Pemotongan 1 buah pipa PVC Ø 200 mm Rp 15,412.50
Q.I.6. (K3) Pemotongan 1 buah pipa PVC Ø 250 mm Rp 24,510.00
Q.I.7. (K3) Pemotongan 1 buah pipa PVC Ø 300 mm Rp 29,505.00
Q.I.8. (K3) Pemotongan 1 buah pipa PVC Ø 400 mm Rp 63,352.50
Q.I.9. (K3) Pemotongan 1 buah pipa PVC Ø 450 mm Rp 80,325.00
Q.I.10. (K3) Pemotongan 1 buah pipa PVC Ø 500 mm Rp 99,097.50
Q.I.11. (K3) Pemotongan 1 buah pipa PVC Ø 600 mm Rp 119,040.00
Q.I.12. (K3) Pemotongan 1 buah pipa PVC Ø 800 mm Rp 208,350.00
Q.I.13. (K3) Pemotongan 1 buah pipa PVC Ø 900 mm Rp 218,265.00
Q.I.14. (K3) Pemotongan 1 buah pipa PVC Ø 1000 mm Rp 245,895.00
Q.I.15. (K3) Pemotongan 1 buah pipa PVC Ø 1100 mm Rp 273,375.00
Q.I.16. (K3) Pemotongan 1 buah pipa PVC Ø 1200 mm Rp 300,855.00
Q.I.17. (K3) Pemotongan 1 buah pipa HDPE Ø 63 mm Rp 6,332.50
Q.I.18. (K3) Pemotongan 1 buah pipa HDPE Ø 100 mm Rp 13,632.50
Q.I.19. (K3) Pemotongan 1 buah pipa HDPE Ø 125 mm Rp 18,600.00
Q.I.20. (K3) Pemotongan 1 buah pipa HDPE Ø 150 mm Rp 24,295.00
Q.I.21. (K3) Pemotongan 1 buah pipa HDPE Ø 200 mm Rp 38,280.00
Q.I.22. (K3) Pemotongan 1 buah pipa HDPE Ø 250 mm Rp 51,470.00
Q.I.23. (K3) Pemotongan 1 buah pipa HDPE Ø 300 mm Rp 64,637.50
Q.I.24. (K3) Pemotongan 1 buah pipa HDPE Ø 400 mm Rp 98,757.50
Q.I.25. (K3) Pemotongan 1 buah pipa HDPE Ø 450 mm Rp 120,220.00
Q.I.26. (K3) Pemotongan 1 buah pipa HDPE Ø 500 mm Rp 135,510.00
Q.I.27. (K3) Pemotongan 1 buah pipa HDPE Ø 600 mm Rp 163,630.00
Q.I.28. (K3) Pemotongan 1 buah pipa HDPE Ø 800 mm Rp 249,915.00
Q.I.29. (K3) Pemotongan 1 buah pipa HDPE Ø 900 mm Rp 326,927.50
Q.I.30. (K3) Pemotongan 1 buah pipa HDPE Ø 1000 mm Rp 384,942.50
Q.I.31. (K3) Pemotongan 1 buah pipa HDPE Ø 1100 mm Rp 424,222.50
Q.I.32. (K3) Pemotongan 1 buah pipa HDPE Ø 1200 mm Rp 514,510.00
Q.I.33. (K3) Pemotongan 1 buah pipa GIP Ø 63 mm Rp 3,712.50
NO
JENIS PEKERJAAN HARGA
PEKERJAAN
Q.I.34. (K3) Pemotongan 1 buah pipa GIP Ø 100 mm Rp 11,122.50
Q.I.35. (K3) Pemotongan 1 buah pipa GIP Ø 125 mm Rp 17,565.00
Q.I.36. (K3) Pemotongan 1 buah pipa GIP Ø 150 mm Rp 25,102.50
Q.I.37. (K3) Pemotongan 1 buah pipa GIP Ø 200 mm Rp 65,025.00
Q.I.38. (K3) Pemotongan 1 buah pipa GIP Ø 250 mm Rp 90,705.00
Q.I.39. (K3) Pemotongan 1 buah pipa GIP Ø 300 mm Rp 96,330.00
Q.I.40. (K3) Pemotongan 1 buah pipa GIP Ø 400 mm Rp 141,172.50
Q.I.41. (K3) Pemotongan 1 buah pipa GIP Ø 450 mm Rp 162,210.00
Q.I.42. (K3) Pemotongan 1 buah pipa GIP Ø 500 mm Rp 180,015.00
Q.I.43. (K3) Pemotongan 1 buah pipa GIP Ø 600 mm Rp 165,180.00
Q.I.44. (K3) Pemotongan 1 buah pipa GIP Ø 800 mm Rp 299,670.00
Q.I.45. (K3) Pemotongan 1 buah pipa GIP Ø 900 mm Rp 338,512.50
Q.I.46. (K3) Pemotongan 1 buah pipa GIP Ø 1000 mm Rp 377,467.50
Q.I.47. (K3) Pemotongan 1 buah pipa GIP Ø 1100 mm Rp 416,572.50
Q.I.48. (K3) Pemotongan 1 buah pipa GIP Ø 1200 mm Rp 455,527.50
Q.I.49. (K3) Pemotongan 1 buah pipa DCI Ø 100 mm Rp 10,822.50
Q.I.50. (K3) Pemotongan 1 buah pipa DCI Ø 125 mm Rp 17,055.00
Q.I.51. (K3) Pemotongan 1 buah pipa DCI Ø 150 mm Rp 24,367.50
Q.I.52. (K3) Pemotongan 1 buah pipa DCI Ø 200 mm Rp 56,032.50
Q.I.53. (K3) Pemotongan 1 buah pipa DCI Ø 250 mm Rp 72,862.50
Q.I.54. (K3) Pemotongan 1 buah pipa DCI Ø 300 mm Rp 78,255.00
Q.I.55. (K3) Pemotongan 1 buah pipa DCI Ø 400 mm Rp 143,932.50
Q.I.56. (K3) Pemotongan 1 buah pipa DCI Ø 450 mm Rp 173,955.00
Q.I.57. (K3) Pemotongan 1 buah pipa DCI Ø 500 mm Rp 200,655.00
Q.I.58. (K3) Pemotongan 1 buah pipa DCI Ø 600 mm Rp 200,317.50
Q.I.59. (K3) Pemotongan 1 buah pipa DCI Ø 800 mm Rp 397,575.00
Q.I.60. (K3) Pemotongan 1 buah pipa DCI Ø 900 mm Rp 515,610.00
Q.I.61. (K3) Pemotongan 1 buah pipa DCI Ø 1000 mm Rp 615,172.50
Q.I.62. (K3) Pemotongan 1 buah pipa DCI Ø 1100 mm Rp 723,802.50
Q.I.63 (K3) Pemotongan 1 buah pipa DCI Ø 1200 mm Rp 841,725.00
Q.I.64. (K3) Pemotongan 1 buah pipa baja Ø 63 mm Rp 4,365.00
Q.I.65. (K3) Pemotongan 1 buah pipa baja Ø 100 mm Rp 12,930.00
Q.I.66. (K3) Pemotongan 1 buah pipa baja Ø 125 mm Rp 20,355.00
Q.I.67. (K3) Pemotongan 1 buah pipa baja Ø 150 mm Rp 28,117.50
Q.I.68. (K3) Pemotongan 1 buah pipa baja Ø 200 mm Rp 72,862.50
Q.I.69. (K3) Pemotongan 1 buah pipa baja Ø 250 mm Rp 101,445.00
Q.I.70. (K3) Pemotongan 1 buah pipa baja Ø 300 mm Rp 113,910.00
Q.I.71. (K3) Pemotongan 1 buah pipa baja Ø 400 mm Rp 220,320.00
Q.I.72. (K3) Pemotongan 1 buah pipa baja Ø 450 mm Rp 214,087.50
Q.I.73. (K3) Pemotongan 1 buah pipa baja Ø 500 mm Rp 238,455.00
Q.I.74. (K3) Pemotongan 1 buah pipa baja Ø 600 mm Rp 219,855.00
Q.I.75. (K3) Pemotongan 1 buah pipa baja Ø 800 mm Rp 401,437.50
Q.I.76. (K3) Pemotongan 1 buah pipa baja Ø 900 mm Rp 454,522.50
Q.I.77. (K3) Pemotongan 1 buah pipa baja Ø 1000 mm Rp 507,847.50
Q.I.78. (K3) Pemotongan 1 buah pipa baja Ø 1100 mm Rp 561,045.00
Q.I.79. (K3) Pemotongan 1 buah pipa baja Ø 1200 mm Rp 614,370.00

R HARGA SATUAN PEKERJAAN PEMASANGAN AKSESORIS PIPA


I (PERMEN NOMOR 28/PRT/M/2016)
R.I.1. (K3) Pemasangan 1 buah valve Ø 150 mm Rp 273,375.00
R.I.2. (K3) Pemasangan 1 buah valve Ø 200 mm Rp 327,742.50
R.I.3. (K3) Pemasangan 1 buah valve Ø 250 mm Rp 327,742.50
R.I.4. (K3) Pemasangan 1 buah valve Ø 300 mm Rp 382,500.00
R.I.5. (K3) Pemasangan 1 buah valve Ø 400 mm Rp 655,875.00
R.I.6. (K3) Pemasangan 1 buah valve Ø 450 mm Rp 655,875.00
R.I.7. (K3) Pemasangan 1 buah valve Ø 500 mm Rp 765,000.00
R.I.8. (K3) Pemasangan 1 buah valve Ø 600 mm Rp 271,815.00
R.I.9. (K3) Pemasangan 1 buah valve Ø 700 mm Rp 273,375.00
R.I.10. (K3) Pemasangan 1 buah valve Ø 800 mm Rp 341,632.50
R.I.11. (K3) Pemasangan 1 buah valve Ø 900 mm Rp 327,742.50
R.I.12. (K3) Pemasangan 1 buah valve Ø 1000 mm Rp 491,752.50
R.I.13. (K3) Pemasangan 1 buah valve Ø 1100 mm Rp 573,750.00
R.I.14. (K3) Pemasangan 1 buah valve Ø 1200 mm Rp 573,750.00
R.I.15. (K3) Pemasangan 1 buah tee Ø 150 mm Rp 20,332.50
R.I.16. (K3) Pemasangan 1 buah tee Ø 200 mm Rp 41,370.00
R.I.17. (K3) Pemasangan 1 buah tee Ø 250 mm Rp 62,407.50
R.I.18. (K3) Pemasangan 1 buah tee Ø 300 mm Rp 83,445.00
R.I.19. (K3) Pemasangan 1 buah tee Ø 400 mm Rp 125,520.00
R.I.20. (K3) Pemasangan 1 buah tee Ø 450 mm Rp 146,557.50
R.I.21. (K3) Pemasangan 1 buah tee Ø 500 mm Rp 167,595.00
R.I.22. (K3) Pemasangan 1 buah tee Ø 600 mm Rp 209,670.00
R.I.23. (K3) Pemasangan 1 buah tee Ø 700 mm Rp 251,745.00
R.I.24. (K3) Pemasangan 1 buah tee Ø 800 mm Rp 293,820.00
R.I.25. (K3) Pemasangan 1 buah tee Ø 900 mm Rp 335,895.00
R.I.26. (K3) Pemasangan 1 buah tee Ø 1000 mm Rp 377,970.00
R.I.27. (K3) Pemasangan 1 buah tee Ø 1100 mm Rp 420,045.00
R.I.28. (K3) Pemasangan 1 buah tee Ø 1200 mm Rp 462,120.00
NO
JENIS PEKERJAAN HARGA
PEKERJAAN
II ANALISA SENDIRI
R.II.1. Pemasangan 1 buah floating valve 1" Rp 61,602.50

S HARGA SATUAN PEKERJAAN PENYAMBUNGAN PIPA BARU KE PIPA LAMA


I (PERMEN NOMOR 28/PRT/M/2016)
S.I.1. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 80 mm Rp 280,432.50
S.I.2. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 100 mm Rp 314,857.50
S.I.3. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 150 mm Rp 400,920.00
S.I.4. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 200 mm Rp 486,982.50
S.I.5. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 250 mm Rp 573,045.00
S.I.6. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 300 mm Rp 659,107.50
S.I.7. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 400 mm Rp 831,232.50
S.I.8. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 450 mm Rp 917,295.00
S.I.9. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 500 mm Rp 1,003,357.50
S.I.10. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 600 mm Rp 1,175,482.50
S.I.11. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 700 mm Rp 1,347,607.50
S.I.12. (K3) Penyambungan 1 buah 1 buah pipa baru ke pipa yang ada Ø 800 mm Rp 1,519,732.50

T HARGA SATUAN PEKERJAAN PENGETESAN PIPA


I (PERMEN NOMOR 28/PRT/M/2016)
T.I.1. (K3) Pengetesan 1 m pipa Ø 50 mm Rp 1,020.00
T.I.2. (K3) Pengetesan 1 m pipa Ø 75 mm Rp 1,020.00
T.I.3. (K3) Pengetesan 1 m pipa Ø 100 mm Rp 1,020.00
T.I.4. (K3) Pengetesan 1 m pipa Ø 150 mm Rp 1,020.00
T.I.5. (K3) Pengetesan 1 m pipa Ø 200 mm Rp 1,020.00
T.I.6. (K3) Pengetesan 1 m pipa Ø 250 mm Rp 1,020.00
T.I.7. (K3) Pengetesan 1 m pipa Ø 300 mm Rp 1,020.00
T.I.8. (K3) Pengetesan 1 m pipa Ø 400 mm Rp 1,020.00
T.I.9. (K3) Pengetesan 1 m pipa Ø 500 mm Rp 1,020.00
T.I.10. (K3) Pengetesan 1 m pipa Ø 600 mm Rp 1,020.00

U HARGA SATUAN PEKERJAAN MEKANIKAL / ELEKTRIKAL


I ANALISA SENDIRI
U.I.1. Pemasangan 1 titik instalasi lampu Rp 277,931.67
U.I.2. Pemasangan 1 titik instalasi stop kontak Rp 567,911.17
U.I.3. Pemasangan 1 titik instalasi power AC Rp 66,025.00
U.I.4. Pemasangan 1 titik instalasi exhaust fan di toilet Rp 91,900.00
U.I.5. Pemasangan 1 titik instalasi saklar Rp 58,150.00
U.I.6. Pemasangan 1 titik instalasi kabel data Rp 91,900.00
U.I.7. Pemasangan 1 titik instalasi sound system Rp 58,150.00
U.I.8. Pemasangan 1 titik instalasi volume kontrol Rp 48,515.00
U.I.9. Pemasangan 1 titik instalasi detector fire alarm Rp 58,150.00
U.I.10. Pemasangan 1 titik instalasi indicator lamp, alarm bell dan manual push button Rp 48,515.00
U.I.11. Pemasangan 1 titik instalasi CCTV Rp 58,150.00
U.I.12. Pemasangan 1 titik instalasi antena TV Rp 37,975.00
U.I.13. Pemasangan 1 titik instalasi telephone Rp 37,975.00
U.I.14. Pemasangan 1 m1 kabel NYY 4x16 mm2 Rp 23,425.00
U.I.15. Pemasangan 1 m1 kabel NYY 4x25 mm2 Rp 23,425.00
U.I.16. Pemasangan 1 m1 kabel feeder 2x UTP cat 6 Rp 24,410.00
U.I.17. Pemasangan 1 buah saklar tunggal Rp 50,175.00
U.I.18. Pemasangan 1 buah saklar ganda Rp 62,675.00
U.I.19. Pemasangan 1 buah saklar tukar Rp 25,675.00
U.I.20. Pemasangan 1 buah stop kontak Rp 55,175.00
U.I.21. Pemasangan 1 buah stop kontak AC Rp 21,320.00
U.I.22. Pemasangan 1 buah outlet kabel data Rp 9,620.00
U.I.23. Pemasangan 1 buah outlet TV Rp 35,375.00
U.I.24. Pemasangan 1 buah telephone Rp 35,375.00
U.I.25. Pemasangan 1 unit lampu LED 9 watt Rp 130,175.00
U.I.26. Pemasangan 1 buah kap lampu RMI 2x18 watt cover akrilik Rp 25,675.00
U.I.27. Pemasangan 1 buah lampu TL 18 watt Rp 25,675.00
U.I.28. Pemasangan 1 buah lampu baret LED 7 watt Rp 25,675.00
U.I.29. Pemasangan 1 buah lampu periksa Rp 10,505.00
U.I.30. Pemasangan 1 m1 lampu LED strips 7.2 watt Rp 35,375.00
U.I.31. Pemasangan 1 unit AC wall mounted Rp 224,992.50
U.I.32. Pemasangan 1 buah exhaust fan type ceiling Rp 30,910.00
U.I.33. Pemasangan 1 unit panel MDP Rp 1,427,500.00
U.I.34. Pemasangan 1 unit panel SDP Rp 38,950.00
U.I.35. Pemasangan 1 buah dvr 16 channel Rp 124,060.00
U.I.36. Pemasangan 1 buah monitor CCTV Rp 124,060.00
U.I.37. Pemasangan dan instalasi 1 unit komputer storage 2 TB Rp 124,060.00
U.I.38. Pemasangan 1 buah CCTV Rp 124,060.00
U.I.39. Pemasangan 1 buah amplifier 240 watt Rp 100,900.00
U.I.40. Pemasangan 1 buah mixer 12 channel Rp 124,060.00
U.I.41. Pemasangan 1 buah tuner radio dan CD mp3 Rp 100,900.00
U.I.42. Pemasangan 1 buah DVD player Rp 124,060.00
U.I.43. Pemasangan 1 buah speaker selector 10 channel Rp 124,060.00
U.I.44. Pemasangan 1 unit cabinet rack sound system dengan power Rp 100,900.00
NO
JENIS PEKERJAAN HARGA
PEKERJAAN
U.I.45. Pemasangan 1 buah ceiling speaker Rp 58,150.00
U.I.46. Pemasangan 1 buah volume control Rp 58,150.00
U.I.47. Pemasangan 1 unit DP sound system Rp 58,150.00
U.I.48. Pemasangan 1 unit master control FA Rp 124,060.00
U.I.49. Pemasangan 1 unit panel MDF Rp 124,060.00
U.I.50. Pemasangan 1 buah ROR heat detector Rp 100,900.00
U.I.51. Pemasangan 1 buah smoke detector Rp 124,060.00
U.I.52. Pemasangan 1 buah indicator lamp Rp 100,900.00
U.I.53. Pemasangan 1 buah alarm bell Rp 100,900.00
U.I.54. Pemasangan 1 buah manual push button Rp 100,900.00
U.I.55. Pemasangan 1 buah terminal box fire alarm 24 pair Rp 100,900.00
U.I.56. Pemasangan dan instalasi 1 unit komputer ruang server Rp 100,900.00
U.I.57. Pemasangan 1 buah router ceiling wifi Rp 124,060.00
U.I.58. Pemasangan 1 buah switch hub 24 port Rp 100,900.00
U.I.59. Pemasangan 1 buah wall mounted rack 8 U Rp 100,900.00
U.I.60. Pemasangan 1 buah box panel MCB Rp 283,125.00
U.I.61. Pemasangan 1 set air protection 50 m Rp 121,750.00
U.I.62. Pemasangan 1 m1 BC 70 mm Rp 27,870.00
U.I.63. Pemasangan 1 unit kontrol box Rp 27,870.00
U.I.64. Pemasangan 1 unit ground rout Rp 121,750.00
U.I.65. Pemasangan 1 m1 tiang galvanis Rp 34,675.00

V HARGA SATUAN PEKERJAAN SOFTSCAPE


I ANALISA SENDIRI
V.I.1. Pengurugan 1 m3 tanah subur Rp 42,825.00
V.I.2. Pengurugan 1 m3 pupuk kompos Rp 42,825.00
V.I.3. Penanaman 1 m2 rumput jepang Rp 3,675.00
V.I.4. Penanaman 1 buah tanaman pandan merah Rp 3,675.00
V.I.5. Penanaman 1 buah tanaman jaburan hijau Rp 3,675.00
V.I.6. Penanaman 1 buah tanaman jaburan putih Rp 3,675.00
V.I.7. Penanaman 1 buah tanaman leli Rp 3,675.00
V.I.8. Penanaman 1 buah tanaman sirih belanda Rp 3,675.00
V.I.9. Penanaman 1 buah tanaman rosalia Rp 3,675.00
V.I.10. Penanaman 1 buah tanaman pandan afrika Rp 3,675.00
V.I.11. Penanaman 1 buah tanaman pasok 1,5 m Rp 3,675.00
V.I.12. Penanaman 1 buah tanaman andong 1 m Rp 3,675.00
V.I.13. Penanaman 1 buah tanaman kembang sepatu 1,5 m Rp 3,675.00
V.I.14. Penanaman 1 buah tanaman puring 0,9 m Rp 3,675.00
V.I.15. Penanaman 1 buah tanaman onje 1,2 m Rp 3,675.00
V.I.16. Penanaman 1 buah tanaman soka 1 m Rp 3,675.00
V.I.17. Penanaman 1 buah tanaman bunga portulaca Rp 3,675.00
V.I.18. Penanaman 1 buah tanaman jepun / kamboja 3,5 m Rp 169,050.00
V.I.19. Penanaman 1 buah tanaman jepun fosil diameter 15 - 25 Rp 169,050.00
V.I.20. Penanaman 1 buah tanaman ketapang kencana 4 m Rp 3,675.00
V.I.21. Penanaman 1 buah tanaman pule diameter 75 - 90 cm Rp 305,250.00
V.I.22. Penanaman 1 buah tanaman pule diameter 60 -75 cm Rp 305,250.00
V.I.23. Penanaman 1 buah tanaman maja Rp 87,000.00
V.I.24. Penanaman 1 buah tanaman kamboja merah diameter 40 - 60 cm Rp 87,000.00
V.I.25. Penanaman 1 buah tanaman pisang karibia Rp 11,400.00
V.I.26. Penanaman 1 buah tanaman cotadera selloana Rp 2,625.00
V.I.27. Penanaman 1 buah tanaman bambusa vulgaris (bambu kuning) Rp 4,650.00
V.I.28. Penanaman 1 buah tanaman calathea lutea Rp 3,900.00
V.I.29. Penanaman 1 buah tanaman ruellia brittoniana Rp 2,625.00
V.I.30. Penanaman 1 buah tanaman lantana camara Rp 2,625.00
V.I.31. Penanaman 1 buah tanaman pucuk merah tinggi 1 m Rp 29,400.00
V.I.32. Penanaman 1 m1 tanaman lee kuan yu Rp 3,750.00
V.I.33. Penanaman 1 buah pohon dolar Rp 141,000.00
V.I.34. Penanaman 1 m2 pohon kaki laba-laba Rp 3,750.00
V.I.35. Penanaman 1 m2 pohon corrymbousa mini Rp 3,750.00
V.I.36. Penanaman 1 m2 pohon pangkas kuning Rp 3,750.00
V.I.37. Penanaman 1 m2 tanaman kacang-kacangan Rp 3,750.00
V.I.38. Penanaman 1 rumpun pohon bambu jakarta Rp 3,750.00
V.I.39. Penanaman 1 buah pohon puring kirana Rp 3,750.00
V.I.40. Penanaman 1 buah pohon puring nuri Rp 3,750.00
V.I.41. Penanaman 1 buah pohon puring bor merah Rp 3,750.00
V.I.42. Penanaman 1 buah pohon puring bor kuning Rp 3,750.00
V.I.43. Penanaman 1 buah pohon soka india Rp 3,750.00
V.I.44. Penanaman 1 buah pohon walisongo Rp 3,750.00
V.I.45. Penanaman 1 buah pohon bougenville variegata Rp 3,750.00
V.I.46. Penanaman 1 m2 pohon bunga pukul sembilan Rp 3,200.00
V.I.47. Penanaman 1 buah pohon kamboja diameter 10 cm Rp 36,750.00
V.I.48. Penanaman 1 buah pohon kamboja diameter 15 cm Rp 36,750.00
V.I.49. Penanaman 1 buah pohon dadap merah diameter 10 cm Rp 36,750.00
V.I.50. Penanaman 1 buah pohon dadap merah diameter 15 cm Rp 36,750.00
V.I.51. Penanaman 1 m2 rumput mutiara Rp 3,675.00

W HARGA SATUAN PEKERJAAN STYLE BALI


NO
JENIS PEKERJAAN HARGA
PEKERJAAN
I ANALISA SENDIRI
W.I.1. Pemasangan 1 m2 bata gosok 2 muka Rp 445,900.00
W.I.2. Pemasangan 1 m2 batu candi 1 muka Rp 388,750.00
W.I.3. Pemasangan 1 m2 bata press 1 muka Rp 388,750.00
W.I.4. Pemasangan 1 m2 batu paras jogya 1 muka Rp 388,750.00
W.I.5. Pemasangan 1 m2 bata gosok 1 muka Rp 388,750.00
W.I.6. Pemasangan 1 m2 paras dan bata gosok 1 muka Rp 388,750.00
W.I.7. Pemasangan 1 m2 batu jogya diukir 1 muka Rp 388,750.00
W.I.8. Pemasangan 1 m2 batu tulung agung 1 muka Rp 388,750.00
W.I.9. Pemasangan 1 m2 batu karangasem 1 muka Rp 388,750.00
W.I.10. Pembuatan 1 unit aling-aling batu tulung agung Rp 1,746,433.02
W.I.11. Pemasangan 1 m1 tembok penyengker batu tulung agung Rp 231,294.88
W.I.12. Pemasangan 1 unit pilar paduraksa batu tulung agung Rp 231,294.88
W.I.13. Pemasangan 1 Unit Padmasari Batu Karangasem Rp 6,032,656.90
W.I.14. Pemasangan 1 Unit Penunggu Karang Batu Karangasem Rp 5,161,247.94
W.I.15. Pemasangan 1 unit candi bentar t = 4.25 m batu karangasem Rp 3,891,292.08
W.I.16. Pemasangan 1 unit candi bentar t = 2.50 m batu karangasem Rp 2,096,873.66
W.I.17. Pemasangan 1 m1 tembok penyengker batu karangasem Rp 273,989.75
W.I.18. Pemasangan 1 unit pilar paduraksa batu karangasem Rp 231,294.88
W.I.19. Pemasangan 1 unit candi bentar t = 4.25 m batu tulung agung Rp 3,891,292.08
W.I.20. Pemasangan 1 unit candi bentar t = 2.50 m batu tulung agung Rp 2,096,873.66
DAFTAR ANALISA PEKERJAAN

A HARGA SATUAN PEKERJAAN PERSIAPAN


I (PERMEN NOMOR 28/PRT/M/2016)
A.I.1. (K3) Pembuatan 1 m2 pagar sementara dari kayu tinggi 2 meter
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4000 112,500.00 45,000.00
Tukang kayu L.04 OH 0.2000 132,500.00 26,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0200 150,000.00 3,000.00
JUMLAH TENAGA KERJA 77,450.00
B BAHAN

Dolken kayu Ø 8-10/400 cm Batang 1.2500 -

Semen portland Kg 5.0000 -


Pasir beton m3 0.0050 -
Koral beton m3 0.0090 -
Kayu 5/7 m3 0.0720 -
Paku biasa 2" - 5" Kg 0.0600 -
Residu Liter 0.4000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 77,450.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 77,450.00

A.I.2. (K3) Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang kayu L.04 OH 0.4000 132,500.00 53,000.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0200 150,000.00 3,000.00
JUMLAH TENAGA KERJA 81,450.00
B BAHAN

Dolken kayu Ø 8-10/400 cm Batang 1.2500 -

Semen portland Kg 2.5000 -


Seng gelombang Lembar 1.2000 -
Pasir beton m3 0.0050 -
Koral beton m3 0.0090 -
Kayu 5/7 m3 0.0720 -
Paku biasa 2" - 5" Kg 0.0600 -
Meni besi Liter 0.4500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 81,450.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 81,450.00

A.I.3. (K3) Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1,8 meter
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang kayu L.04 OH 0.3000 132,500.00 39,750.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0200 150,000.00 3,000.00
JUMLAH TENAGA KERJA 68,200.00
B BAHAN

Dolken kayu Ø 8-10/400 cm Batang 1.0000 -

Semen portland Kg 2.0000 -


Kawat duri m1 25.0000 -
Pasir beton m3 0.0050 -
Koral beton m3 0.0090 -
Paku biasa 2" - 5" Kg 0.0600 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 68,200.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 68,200.00

A.I.4. Pengukuran dan pemasangan 1 m1 bouwplank


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.1000 132,500.00 13,250.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 26,725.00
B BAHAN
Kayu 5/7 m3 0.0120 5,300,000.00 63,600.00
Paku 2" - 5" Kg 0.0200 22,000.00 440.00
Kayu papan 3/20 m3 0.0070 7,900,500.00 55,303.50
JUMLAH HARGA BAHAN 119,343.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 146,068.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 146,068.50

A.I.5. (K3) Pembuatan 1 m2 kantor sementara lantai plesteran


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.0000 112,500.00 225,000.00
Tukang kayu L.04 OH 2.0000 132,500.00 265,000.00
Tukang batu L.03 OH 1.0000 127,500.00 127,500.00
Kepala tukang L.14 OH 0.3000 147,500.00 44,250.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 662,500.00
B BAHAN

Dolken kayu Ø 8-10/400 cm Batang 1.2500 -

Kayu m3 0.1800 -
Paku biasa Kg 0.0800 -
Besi strip Kg 1.1000 -
Semen portland Kg 35.0000 -
Pasir pasang m3 0.1500 -
Pasir beton m3 0.1000 -
Koral beton m3 0.1500 -
Bata merah Bh 30.0000 -
Seng plat Lembar 0.2500 -
Jendela nako Bh 0.2000 -
Kaca polos m2 0.0800 -
Kunci tanam Bh 0.1500 -
Plywood 4mm Lembar 0.0600 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 662,500.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 662,500.00

A.I.6. (K3) Pembuatan 1 m2 rumah jaga (konstruksi kayu)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang kayu L.04 OH 1.5000 132,500.00 198,750.00
Kepala tukang L.14 OH 0.1500 147,500.00 22,125.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 340,875.00
B BAHAN

Dolken kayu Ø 8-10/400 cm Batang 3.0000 -

Kayu m3 0.2760 -
Paku biasa Kg 0.7000 -
Seng gelombang Kg 1.5000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 340,875.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 340,875.00

A.I.7. (K3) Pembuatan 1 m2 gudang semen dan peralatan


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang kayu L.04 OH 2.0000 132,500.00 265,000.00
Kepala tukang L.14 OH 0.2000 147,500.00 29,500.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 414,500.00
B BAHAN

Dolken kayu Ø 8-10/400 cm Batang 1.7000 -

Kayu m3 0.2100 -
Paku biasa Kg 0.3000 -
Semen portland Kg 10.5000 -
Pasir beton m3 0.0300 -
Koral beton m3 0.0500 -
Seng gelombang Lembar 1.5000 -
Seng plat Lembar 0.2500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 414,500.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 414,500.00

A.I.8. (K3) Pembuatan 1 m2 bedeng pekerja


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang kayu L.04 OH 2.0000 132,500.00 265,000.00
Kepala tukang L.14 OH 0.2000 147,500.00 29,500.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 414,500.00
B BAHAN

Dolken kayu Ø 8-10/400 cm Batang 1.2500 -

Kayu m3 0.1860 -
Paku biasa Kg 0.3000 -
Semen portland Kg 18.0000 -
Pasir beton m3 0.0300 -
Koral beton m3 0.0500 -
Seng gelombang Lembar 1.5000 -
Plywood 4 mm Lembar 1.3500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 414,500.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 414,500.00

A.I.9. (K3) Pembersihan 1 m2 lapangan dan perataan


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 18,750.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 18,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 18,750.00

A.I.10. (K3) Pembuatan 1 m2 steger/perancah dari bambu


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang kayu L.04 OH 2.0000 132,500.00 265,000.00
Kepala tukang L.14 OH 0.2000 147,500.00 29,500.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 414,500.00
B BAHAN

Bambu diameter 6-8/600 cm Batang 1.2500 -

Tali ijuk m3 0.1860 -


JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 414,500.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 414,500.00

A.I.11. Pembuatan 1 buah kotak adukan ukuran 40 cm x 50 cm x 25 cm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Tukang kayu L.04 OH 0.3000 132,500.00 39,750.00
Kepala tukang L.14 OH 0.0300 147,500.00 4,425.00
JUMLAH TENAGA KERJA 44,175.00
B BAHAN
Kayu papan kelas III m3 0.0360 -
Kayu balok 5/7 kelas III m3 0.0140 -
Paku biasa Kg 0.0800 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 44,175.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 44,175.00

A.I.12. Pembuatan 1 m2 jalan sementara


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 113,250.00
B BAHAN
Batu belah m3 0.1500 -
Batu pecah m3 0.0900 -
Pasir pasang m3 0.0100 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 113,250.00
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 113,250.00

A.I.13. Pembongkaran 1 m3 beton bertulang


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 13.3340 112,500.00 1,500,075.00
Mandor L.17 OH 0.6660 150,000.00 99,900.00
JUMLAH TENAGA KERJA 1,599,975.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,599,975.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,599,975.00

A.I.14. Pembongkaran 1 m3 dinding tembok bata


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.6670 112,500.00 750,037.50
Mandor L.17 OH 0.3330 150,000.00 49,950.00
JUMLAH TENAGA KERJA 799,987.50
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 799,987.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 799,987.50

A.I.15. Pemasangan 1 m2 pagar kawat jaring galvanis panjang 240 cm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0420 112,500.00 4,725.00
Tukang besi L.05 OH 0.0040 127,500.00 510.00
Kepala tukang L.14 OH 0.0020 147,500.00 295.00
Mandor L.17 OH 0.0420 150,000.00 6,300.00
JUMLAH TENAGA KERJA 11,830.00
B BAHAN
Kawat jaring M741 Lembar 0.1434 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 11,830.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 11,830.00

A.I.16. Pemasangan 1 m2 panel beton pracetak 5 x 50 x 240 cm


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3750 112,500.00 42,187.50
Tukang batu L.03 OH 0.1250 127,500.00 15,937.50
Kepala tukang L.14 OH 0.0120 147,500.00 1,770.00
Mandor L.17 OH 0.0190 150,000.00 2,850.00
JUMLAH TENAGA KERJA 62,745.00
B BAHAN
Panel beton pracetak Lembar 0.9860 -
Kolom beton pracetak Batang 0.5250
Semen portland Kg 45.0000
Pasir beton m3 0.0740
Koral m3 0.1460
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 62,745.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 62,745.00

II ANALISA SENDIRI

A.II.1. Pembuatan 1 m2 stegger dengan scaffolding 120 x 180, h 190 (sewa)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0170 112,500.00 1,912.50
Tukang kayu L.04 OH 0.0020 132,500.00 265.00
Kepala tukang L.14 OH 0.2500 147,500.00 36,875.00
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 41,002.50
B BAHAN
Batang
Dolken kayu Ø 8-10/400 cm 0.0350 -

Paku biasa Kg 0.2000 -


Main Frame Buah 2.0000 -
End Frame Buah 2.0000 -
Cross Brace Buah 4.0000 -
Join Pen Buah 4.0000 -
U Head Buah 4.0000 -
Jack Base Buah 4.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 41,002.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 41,002.50

A.II.2. Pemasangan 1 unit alat pemadam api ringan (APAR) 6 kg powder


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7500 112,500.00 84,375.00
JUMLAH TENAGA KERJA 84,375.00
B BAHAN
Alat pemadam api ringan
Unit 1.0000 -
(APAR) 6 kg
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 84,375.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 84,375.00
B HARGA SATUAN PEKERJAAN TANAH
I (PERMEN NOMOR 28/PRT/M/2016)
B.I.1. Penggalian 1 m3 tanah biasa sedalam 1 m
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7500 112,500.00 84,375.00
Mandor L.17 OH 0.0250 150,000.00 3,750.00
JUMLAH TENAGA KERJA 88,125.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 88,125.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 88,125.00

B.I.2. Penggalian 1 m3 tanah biasa sedalam 2 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9000 112,500.00 101,250.00
Mandor L.17 OH 0.0450 150,000.00 6,750.00
JUMLAH TENAGA KERJA 108,000.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 108,000.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 108,000.00

B.I.3. Penggalian 1 m3 tanah biasa sedalam 3 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0500 112,500.00 118,125.00
Mandor L.17 OH 0.0670 150,000.00 10,050.00
JUMLAH TENAGA KERJA 128,175.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 128,175.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 128,175.00

B.I.4. Penggalian 1 m3 tanah keras sedalam 1 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Mandor L.17 OH 0.0320 150,000.00 4,800.00
JUMLAH TENAGA KERJA 117,300.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 117,300.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 117,300.00

B.I.5. Penggalian 1 m3 tanah cadas sedalam 1 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 112,500.00 168,750.00
Mandor L.17 OH 0.0600 150,000.00 9,000.00
JUMLAH TENAGA KERJA 177,750.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 177,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 177,750.00

B.I.6. Penggalian 1 m3 tanah lumpur sedalam 1 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.2000 112,500.00 135,000.00
Mandor L.17 OH 0.0450 150,000.00 6,750.00
JUMLAH TENAGA KERJA 141,750.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 141,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 141,750.00

B.I.7. Pengerjaan stripping 1 m2 tanah tebing setinggi 1 meter


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0500 112,500.00 5,625.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 6,375.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 6,375.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 6,375.00
B.I.8. (K3) Pembuangan 1 m3 tanah sejauh 30 meter
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3300 112,500.00 37,125.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 38,625.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 38,625.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 38,625.00

B.I.9. Pengurugan kembali 1 m3 galian tanah


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 63,750.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 63,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 63,750.00

B.I.10. (K3) Pemadatan tanah 1 m3 tanah (per 20 cm)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 63,750.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 63,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 63,750.00

B.I.11. Pengurugan 1 m3 dengan pasir urug


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 35,250.00
B BAHAN
Pasir urug m3 1.2000 272,727.27 327,272.73
JUMLAH HARGA BAHAN 327,272.73
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 362,522.73


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 362,522.73

B.I.12. Pemasangan 1 m3 lapisan pudel campuran 1KP : 3PP : 7TL


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8000 112,500.00 90,000.00
Tukang batu L.03 OH 0.4000 127,500.00 51,000.00
Kepala tukang L.14 OH 0.0400 147,500.00 5,900.00
Mandor L.17 OH 0.0800 150,000.00 12,000.00
JUMLAH TENAGA KERJA 158,900.00
B BAHAN
Kapur padam m3 0.1350 -
Pasir pasang m3 0.4000 -
Tanah liat m3 0.9480 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 158,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 158,900.00

B.I.13. Pemasangan 1 m2 lapisan ijuk tebal 10 cm untuk bidang resapan


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 19,125.00
B BAHAN
Ijuk m3 6.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 19,125.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 19,125.00

B.I.14. Pengurugan 1 m3 sirtu padat


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Mandor L.17 OH 0.0250 150,000.00 3,750.00
JUMLAH TENAGA KERJA 31,875.00
B BAHAN
Sirtu m3 1.2000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 31,875.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 31,875.00

II (SNI 03-2835-2002)
B.II.1. Pembuangan 1 m3 tanah sejauh 150 m
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5160 112,500.00 58,050.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 65,550.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 65,550.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 65,550.00

B.II.2. Pemasangan 1 m3 lapisan pudel campuran 1KP : 5TL


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8330 112,500.00 93,712.50
Tukang batu L.03 OH 0.4160 127,500.00 53,040.00
Kepala tukang L.14 OH 0.0410 147,500.00 6,047.50
Mandor L.17 OH 0.0810 150,000.00 12,150.00
JUMLAH TENAGA KERJA 164,950.00
B BAHAN
Kapur padam m3 0.2000 -
Tanah liat m3 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 164,950.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 164,950.00

III ANALISA SENDIRI


B.III.1. Pemasangan 1 m3 tanah dengan stamper
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 63,750.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN
Stamper Unit/hari 0.0500 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 63,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 63,750.00

B.III.2. Pengurugan 1 m3 tanah urug


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Mandor L.17 OH 0.0250 150,000.00 3,750.00
JUMLAH TENAGA KERJA 31,875.00
B BAHAN
Tanah urug m3 1.2000 83,333.33 100,000.00
JUMLAH HARGA BAHAN 100,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 131,875.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 131,875.00
C HARGA SATUAN PEKERJAAN PONDASI
I (PERMEN NOMOR 28/PRT/M/2016)
C.I.1. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 3PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 112,500.00 168,750.00
Tukang batu L.03 OH 0.7500 127,500.00 95,625.00
Kepala tukang L.14 OH 0.0750 147,500.00 11,062.50
Mandor L.17 OH 0.0750 150,000.00 11,250.00
JUMLAH TENAGA KERJA 286,687.50
B BAHAN
Batu belah m3 1.2000 -
Semen portland Kg 202.0000 -
Pasir pasang m3 0.4850 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 286,687.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 286,687.50

C.I.2. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 4PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 112,500.00 168,750.00
Tukang batu L.03 OH 0.7500 127,500.00 95,625.00
Kepala tukang L.14 OH 0.0750 147,500.00 11,062.50
Mandor L.17 OH 0.0750 150,000.00 11,250.00
JUMLAH TENAGA KERJA 286,687.50
B BAHAN
Batu belah m3 1.2000 -
Semen portland Kg 163.0000 -
Pasir pasang m3 0.5200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 286,687.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 286,687.50

C.I.3. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 112,500.00 168,750.00
Tukang batu L.03 OH 0.7500 127,500.00 95,625.00
Kepala tukang L.14 OH 0.0750 147,500.00 11,062.50
Mandor L.17 OH 0.0750 150,000.00 11,250.00
JUMLAH TENAGA KERJA 286,687.50
B BAHAN
Batu belah m3 1.2000 -
Semen portland Kg 136.0000 -
Pasir pasang m3 0.5440 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 286,687.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 286,687.50

C.I.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 112,500.00 168,750.00
Tukang batu L.03 OH 0.7500 127,500.00 95,625.00
Kepala tukang L.14 OH 0.0750 147,500.00 11,062.50
Mandor L.17 OH 0.0750 150,000.00 11,250.00
JUMLAH TENAGA KERJA 286,687.50
B BAHAN
Batu belah m3 1.2000 -
Semen portland Kg 117.0000 -
Pasir pasang m3 0.5610 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 286,687.50
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 286,687.50

C.I.5. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 8PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 112,500.00 168,750.00
Tukang batu L.03 OH 0.7500 127,500.00 95,625.00
Kepala tukang L.14 OH 0.0750 147,500.00 11,062.50
Mandor L.17 OH 0.0750 150,000.00 11,250.00
JUMLAH TENAGA KERJA 286,687.50
B BAHAN
Batu belah m3 1.2000 -
Semen portland Kg 91.0000 -
Pasir pasang m3 0.5840 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 286,687.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 286,687.50

C.I.6. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 1KP : 2PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 112,500.00 168,750.00
Tukang batu L.03 OH 0.7500 127,500.00 95,625.00
Kepala tukang L.14 OH 0.0750 147,500.00 11,062.50
Mandor L.17 OH 0.0750 150,000.00 11,250.00
JUMLAH TENAGA KERJA 286,687.50
B BAHAN
Batu belah m3 1.2000 -
Kapur m3 0.1700 -
Semen portland Kg 0.1700 -
Pasir pasang m3 0.3400 -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 286,687.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 286,687.50

C.I.7. Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 3 KP : 10 PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 112,500.00 168,750.00
Tukang batu L.03 OH 0.7500 127,500.00 95,625.00
Kepala tukang L.14 OH 0.0750 147,500.00 11,062.50
Mandor L.17 OH 0.0750 150,000.00 11,250.00
JUMLAH TENAGA KERJA 286,687.50
B BAHAN
Batu belah m3 1.2000 -
Kapur Kg 61.0000 -
Semen portland m3 0.1470 -
Pasir pasang m3 0.4920 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 286,687.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 286,687.50

C.I.8. Pemasangan 1 m3 pondasi batu belah campuran 1/4 SP : 1 KP : 4PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 112,500.00 168,750.00
Tukang batu L.03 OH 0.7500 127,500.00 95,625.00
Kepala tukang L.14 OH 0.0750 147,500.00 11,062.50
Mandor L.17 OH 0.0750 150,000.00 11,250.00
JUMLAH TENAGA KERJA 286,687.50
B BAHAN
Batu belah m3 1.2000 -
Kapur Kg 41.0000 -
Semen portland m3 0.1310 -
Pasir pasang m3 0.5230 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 286,687.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 286,687.50

C.I.9. (K3) Pemasangan 1 m3 batu kosong (anstamping)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7800 112,500.00 87,750.00
Tukang batu L.03 OH 0.3900 127,500.00 49,725.00
Kepala tukang L.14 OH 0.0390 147,500.00 5,752.50
Mandor L.17 OH 0.0390 150,000.00 5,850.00
JUMLAH TENAGA KERJA 149,077.50
B BAHAN
Batu belah m3 1.2000 -
Pasir urug m3 0.4320 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 149,077.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 149,077.50

C.I.10. Pemasangan 1 m3 pondasi siklop, 60% beton campuran 1SP : 2PB : 3KR dan 40% batu belah
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.4000 112,500.00 382,500.00
Tukang batu L.03 OH 0.8500 127,500.00 108,375.00
Kepala tukang L.14 OH 0.0850 147,500.00 12,537.50
Mandor L.17 OH 0.1700 150,000.00 25,500.00
JUMLAH TENAGA KERJA 528,912.50
B BAHAN
Batu belah m3 0.4800 -
Semen portland Kg 194.0000 -
Pasir beton m3 0.3120 -
Kerikil m3 0.4680 -
Besi beton Kg 126.0000 -
Kawat beton Kg 1.8000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 528,912.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 528,912.50

C.I.11. Pemasangan 1 m3 pondasi sumuran, diameter 100 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.4000 112,500.00 270,000.00
Tukang batu L.03 OH 0.8000 127,500.00 102,000.00
Kepala tukang L.14 OH 0.0800 147,500.00 11,800.00
Mandor L.17 OH 0.1190 150,000.00 17,850.00
JUMLAH TENAGA KERJA 401,650.00
B BAHAN
Batu belah m3 0.4500 -
Semen portland Kg 194.0000 -
Pasir beton m3 0.3120 -
Kerikil Kg 0.4680 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 401,650.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 401,650.00

II (SNI 03-2836-2002)
C.II.1. Pemasangan 1 m3 pondasi batu kali 1SP : 1PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 112,500.00 168,750.00
Tukang batu L.03 OH 0.6000 127,500.00 76,500.00
Kepala tukang L.14 OH 0.0600 147,500.00 8,850.00
Mandor L.17 OH 0.0750 150,000.00 11,250.00
JUMLAH TENAGA KERJA 265,350.00
B BAHAN
Batu belah m3 1.2000 -
Semen portland Kg 392.0000 -
Pasir pasang m3 0.3140 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 265,350.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 265,350.00

C.II.2. Pemasangan 1 m3 pondasi batu kali 1SP : 2PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 112,500.00 168,750.00
Tukang batu L.03 OH 0.6000 127,500.00 76,500.00
Kepala tukang L.14 OH 0.0600 147,500.00 8,850.00
Mandor L.17 OH 0.0750 150,000.00 11,250.00
JUMLAH TENAGA KERJA 265,350.00
B BAHAN
Batu belah m3 1.1000 -
Semen portland Kg 267.0000 -
Pasir pasang m3 0.4270 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 265,350.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 265,350.00

C.II.3. Pemasangan 1 m3 pondasi batu kali 1SP : 2,5PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 112,500.00 168,750.00
Tukang batu L.03 OH 0.6000 127,500.00 76,500.00
Kepala tukang L.14 OH 0.0600 147,500.00 8,850.00
Mandor L.17 OH 0.0750 150,000.00 11,250.00
JUMLAH TENAGA KERJA 265,350.00
B BAHAN
Batu belah m3 1.1300 -
Semen portland Kg 392.0000 -
Pasir pasang m3 0.3140 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 265,350.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 265,350.00

C.II.4. Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 1/4 KP : 4PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 112,500.00 168,750.00
Tukang batu L.03 OH 0.6000 127,500.00 76,500.00
Kepala tukang L.14 OH 0.0600 147,500.00 8,850.00
Mandor L.17 OH 0.0750 150,000.00 11,250.00
JUMLAH TENAGA KERJA 265,350.00
B BAHAN
Batu belah m3 1.1000 -
Semen portland Kg 156.0000 -
Kapur m3 0.0320 -
Pasir pasang m3 0.5840 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 265,350.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 265,350.00

C.II.5. Pembuatan 1 m3 tiang pancang 40 x 40 cm beton bertulang


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang batu L.03 OH 0.6700 127,500.00 85,425.00
Kepala tukang L.14 OH 0.0670 147,500.00 9,882.50
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 215,307.50
B BAHAN
Pasir urug m3 0.0190 -
Pasir beton m3 0.0194 -
Kerikil m3 0.1500 -
Semen portland Kg 60.5000 -
Besi beton Kg 45.0000 -
Kawat beton Kg 0.9000 -
Kayu 5/7 m3 0.0320 -
Paku biasa Kg 0.1200 -
Minyak bekisting Liter 0.0900 -
Plamir Kg 0.2400 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 215,307.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 215,307.50

C.II.6. Pembuatan 1 m3 tiang pancang 35 x 35 cm beton bertulang


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8000 112,500.00 90,000.00
Tukang batu L.03 OH 0.5000 127,500.00 63,750.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0400 150,000.00 6,000.00
JUMLAH TENAGA KERJA 167,125.00
B BAHAN
Pasir urug m3 0.0160 -
Pasir beton m3 0.0800 -
Kerikil m3 0.1250 -
Semen portland Kg 49.0000 -
Besi beton Kg 34.5000 -
Kawat beton Kg 0.7000 -
Kayu 5/7 m3 0.0270 -
Paku biasa Kg 0.1200 -
Minyak bekisting Liter 0.0900 -
Plamir Kg 0.2000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 167,125.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 167,125.00

III ANALISA SENDIRI


C.III.1. Pengeboran 1 m1 pondasi bored pile diameter 30 cm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Tukang gali L.02 OH 0.1600 120,000.00 19,200.00
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 20,400.00
B BAHAN
Oli Liter 0.0500 -
Solar Liter 1.0000 -
Alat bantu % 1.0000 - -
JUMLAH HARGA BAHAN -
C PERALATAN
Crawler crane Jam 0.1300 -
Mesin bor Jam 0.1300 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 20,400.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 20,400.00
D HARGA SATUAN PEKERJAAN BETON
I (PERMEN NOMOR 28/PRT/M/2016)
D.I.1. Membuat 1 m3 beton mutu f’c = 7,4 Mpa, (K.100), slump (12 ± 2) cm, w/c = 0,87
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6500 112,500.00 185,625.00
Tukang batu L.03 OH 0.2750 127,500.00 35,062.50
Kepala tukang L.14 OH 0.0280 147,500.00 4,130.00
Mandor L.17 OH 0.0830 150,000.00 12,450.00
JUMLAH TENAGA KERJA 237,267.50
B BAHAN
Semen portland Kg 247.0000 -
Pasir beton Kg 869.0000 -
Kerikil (maks 30 mm) Kg 999.0000 -
Air Liter 215.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 237,267.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 237,267.50

D.I.2. Membuat 1 m3 beton mutu f’c = 9,8 Mpa, (K.125), slump (12 ± 2) cm, w/c = 0,78
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6500 112,500.00 185,625.00
Tukang batu L.03 OH 0.2750 127,500.00 35,062.50
Kepala tukang L.14 OH 0.0280 147,500.00 4,130.00
Mandor L.17 OH 0.0830 150,000.00 12,450.00
JUMLAH TENAGA KERJA 237,267.50
B BAHAN
Semen portland Kg 276.0000 -
Pasir beton Kg 828.0000 -
Kerikil (maks 30 mm) Kg 1,012.0000 -
Air Liter 215.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 237,267.50
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 237,267.50

D.I.3. Membuat 1 m3 beton mutu f’c = 12,2 Mpa, (K.150), slump (12 ± 2) cm, w/c = 0,72
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6500 112,500.00 185,625.00
Tukang batu L.03 OH 0.2750 127,500.00 35,062.50
Kepala tukang L.14 OH 0.0280 147,500.00 4,130.00
Mandor L.17 OH 0.0830 150,000.00 12,450.00
JUMLAH TENAGA KERJA 237,267.50
B BAHAN
Semen portland Kg 299.0000 -
Pasir beton Kg 799.0000 -
Kerikil (maks 30 mm) Kg 1,017.0000 -
Air Liter 215.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 237,267.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 237,267.50

CATATAN :
Bobot isi pasir = 1.400 Kg/m3, Bobot isi kerikil = 1.350 Kg/m3, Buckling factor pasir = 20 %

D.I.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 Mpa, (K.100), slump (3 - 6) cm, w/c = 0,87
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.2000 112,500.00 135,000.00
Tukang batu L.03 OH 0.2000 127,500.00 25,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0600 150,000.00 9,000.00
JUMLAH TENAGA KERJA 172,450.00
B BAHAN
Semen portland Kg 230.0000 -
Pasir beton Kg 893.0000 -
Kerikil (maks 30 mm) Kg 1,027.0000 -
Air Liter 200.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 172,450.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 172,450.00

D.I.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa, (K.175), slump (12 ± 2) cm, w/c = 0,66
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6500 112,500.00 185,625.00
Tukang batu L.03 OH 0.2750 127,500.00 35,062.50
Kepala tukang L.14 OH 0.0275 147,500.00 4,056.25
Mandor L.17 OH 0.0830 150,000.00 12,450.00
JUMLAH TENAGA KERJA 237,193.75
B BAHAN
Semen portland Kg 326.000 -
Pasir beton Kg 760.000 -
Kerikil (maks 30 mm) Kg 1,029.000 -
Air Liter 215.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 237,193.75


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 237,193.75

D.I.6. Membuat 1 m3 beton mutu f’c = 16,9 Mpa, (K.200), slump (12 ± 2) cm, w/c = 0,61
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6500 112,500.00 185,625.00
Tukang batu L.03 OH 0.2750 127,500.00 35,062.50
Kepala tukang L.14 OH 0.0275 147,500.00 4,056.25
Mandor L.17 OH 0.0830 150,000.00 12,450.00
JUMLAH TENAGA KERJA 237,193.75
B BAHAN
Semen portland Kg 352.000 -
Pasir beton Kg 731.000 -
Kerikil (maks 30 mm) Kg 1,031.000 -
Air Liter 215.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 237,193.75


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 237,193.75

D.I.7. Membuat 1 m3 beton mutu f’c = 19,3 Mpa, (K225), slump (12 ± 2) cm, w/c = 0,58
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6500 112,500.00 185,625.00
Tukang batu L.03 OH 0.2750 127,500.00 35,062.50
Kepala tukang L.14 OH 0.0275 147,500.00 4,056.25
Mandor L.17 OH 0.0830 150,000.00 12,450.00
JUMLAH TENAGA KERJA 237,193.75
B BAHAN
Semen portland Kg 371.0000 -
Pasir beton Kg 698.0000 -
Kerikil (maks 30 mm) Kg 1,047.0000 -
Air Liter 215.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 237,193.75


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 237,193.75

D.I.8. Membuat 1 m3 beton mutu f’c = 21,7 Mpa, (K.250), slump (12 ± 2) cm, w/c = 0,56
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6500 112,500.00 185,625.00
Tukang batu L.03 OH 0.2750 127,500.00 35,062.50
Kepala tukang L.14 OH 0.0275 147,500.00 4,056.25
Mandor L.17 OH 0.0830 150,000.00 12,450.00
JUMLAH TENAGA KERJA 237,193.75
B BAHAN
Semen portland Kg 384.0000 1,325.00 508,800.00
Pasir beton Kg 692.0000 142.86 98,857.14
Kerikil (maks 30 mm) Kg 1,039.0000 218.52 227,040.74
Air Liter 215.0000 55.00 11,825.00
JUMLAH HARGA BAHAN 846,522.88
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,083,716.63


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,083,716.63

D.I.9. Membuat 1 m3 beton mutu f’c = 24,0 Mpa, (K.275), slump (12 ± 2) cm, w/c = 0,53
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6500 112,500.00 185,625.00
Tukang batu L.03 OH 0.2750 127,500.00 35,062.50
Kepala tukang L.14 OH 0.0275 147,500.00 4,056.25
Mandor L.17 OH 0.0830 150,000.00 12,450.00
JUMLAH TENAGA KERJA 237,193.75
B BAHAN
Semen portland Kg 406.0000 -
Pasir beton Kg 684.0000 -
Kerikil (maks 30 mm) Kg 1,026.0000 -
Air Liter 215.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 237,193.75


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 237,193.75

D.I.10. Membuat 1 m3 beton mutu f’c = 26,4 Mpa, (K.300), slump (12 ± 2) cm, w/c = 0,52
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6500 112,500.00 185,625.00
Tukang batu L.03 OH 0.2750 127,500.00 35,062.50
Kepala tukang L.14 OH 0.0275 147,500.00 4,056.25
Mandor L.17 OH 0.0830 150,000.00 12,450.00
JUMLAH TENAGA KERJA 237,193.75
B BAHAN
Semen portland Kg 413.0000 -
Pasir beton Kg 681.0000 -
Kerikil (maks 30 mm) Kg 1,021.0000 -
Air Liter 215.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 237,193.75


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 237,193.75

D.I.11. Membuat 1 m3 beton mutu f’c = 28,8 Mpa, (K.325), slump (12 ± 2) cm, w/c = 0,49
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.1000 112,500.00 236,250.000
Tukang batu L.03 OH 0.3500 127,500.00 44,625.000
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.500
Mandor L.17 OH 0.1050 150,000.00 15,750.000
JUMLAH TENAGA KERJA 301,787.500
B BAHAN
Semen portland Kg 439.0000 -
Pasir beton Kg 670.0000 -
Kerikil (maks 30 mm) Kg 1,006.0000 -
Air Liter 215.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 301,787.500


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 301,787.50

D.I.12. Membuat 1 m3 beton mutu f’c = 31,2 MPa, (K.350), slump (12 ± 2) cm, w/c = 0,48
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.1000 112,500.00 236,250.00
Tukang batu L.03 OH 0.3500 127,500.00 44,625.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.1050 150,000.00 15,750.00
JUMLAH TENAGA KERJA 301,787.50
B BAHAN
Semen portland Kg 448.0000 -
Pasir beton Kg 667.0000 -
Kerikil (maks 30 mm) Kg 1,000.0000 -
Air Liter 215.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 301,787.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 301,787.50

Untuk pekerjaan beton pracetak yang bisa diangkat 24 jam diperlukan


penambahan bahan tambahan sesuai Tabel berikut:
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.100
Tukang Batu L.02 OH 0.350
Kepala Tukang L.03 OH 0.035
Mandor L.04 OH 0.105
JUMLAH TENAGA KERJA
B BAHAN
Semen Portland Kg 448.000
Pasir Beton Kg 667.000
Kerikil (Maks 30 mm) Kg 1,000.000
Bahan Tambahan Kimia Liter 4.500
Air Liter 200.000
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit 0%
F Harga Satuan Pekerjaan (D+E)
CATATAN: Bobot isi pasir = 1400 Kg/m3, Bobot isi kerikil = 1350 Kg/m3, Buckling factor pasir = 20%

D.I.13. Membuat 1 m3 beton kedap air dengan strorox - 100


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.1000 112,500.00 236,250.00
Tukang batu L.03 OH 0.3500 127,500.00 44,625.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.1050 150,000.00 15,750.00
JUMLAH TENAGA KERJA 301,787.50
B BAHAN
Semen portland Kg 400.0000 -
Pasir beton m3 0.4800 -
Kerikil (2cm/3cm) m3 0.8000 -
Storox - 100 Kg 1.2000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 301,787.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 301,787.50

D.I.14. Pemasangan 1 m1 PVC waterstop lebar 150 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0600 112,500.00 6,750.00
Tukang batu L.03 OH 0.0300 127,500.00 3,825.00
Kepala tukang L.14 OH 0.0030 147,500.00 442.50
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 11,467.50
B BAHAN
Waterstop lebar 150 mm m1 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 11,467.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 11,467.50

D.I.15. Pemasangan 1 m1 PVC waterstop lebar 200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0700 112,500.00 7,875.00
Tukang batu L.03 OH 0.0350 127,500.00 4,462.50
Kepala tukang L.14 OH 0.0040 147,500.00 590.00
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 13,977.50
B BAHAN
Waterstop lebar 200 mm m1 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 13,977.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 13,977.50

D.I.16. Pemasangan 1 m1 PVC waterstop lebar 230 mm - 320 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0800 112,500.00 9,000.00
Tukang batu L.03 OH 0.0400 127,500.00 5,100.00
Kepala tukang L.14 OH 0.0040 147,500.00 590.00
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 15,290.00
B BAHAN
Waterstop lebar 230 mm -
m1 1.0500 -
320 mm
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 15,290.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 15,290.00

D.I.17. Pembesian 10 kg dengan besi polos atau besi ulir


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0700 112,500.00 7,875.00
Tukang besi L.05 OH 0.0700 127,500.00 8,925.00
Kepala tukang L.14 OH 0.0070 147,500.00 1,032.50
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 18,432.50
B BAHAN
Besi beton (polos/ulir) Kg 10.5000 12,500.00 131,250.00
Kawat beton Kg 0.1500 17,500.00 2,625.00
JUMLAH HARGA BAHAN 133,875.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 152,307.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 152,307.50
D.I.17a. Pembesian 1 kg dengan besi polos atau besi ulur Rp 15,230.75

D.I.18. Pembesian 10 kg kabel presstressed polos/strands


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0500 112,500.00 5,625.00
Tukang besi L.05 OH 0.0500 127,500.00 6,375.00
Kepala tukang L.14 OH 0.0050 147,500.00 737.50
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 13,187.50
B BAHAN
Kabel presstressed
Kg 10.5000 -
(polos/strands)
Kawat beton Kg 0.1500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 13,187.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 13,187.50
D.I.18a. Pembesian 1 kg kabel presstressed polos/strands Rp 1,318.75

D.I.19. Pemasangan 10 kg jaring kawat baja (wiremesh)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0250 112,500.00 2,812.50
Tukang besi L.05 OH 0.0250 127,500.00 3,187.50
Kepala tukang L.14 OH 0.0250 147,500.00 3,687.50
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 9,837.50
B BAHAN
Jaring kawat baja dilas Kg 10.2000 12,008.42 122,485.84
Kawat beton Kg 0.0500 17,500.00 875.00
JUMLAH HARGA BAHAN 123,360.84
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 133,198.34


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 133,198.34
D.I.19a. Pembesian 1 kg jaring kawat baja (wiremesh) Rp 13,319.83

D.I.20. (K3) Pemasangan 1 m2 bekisting untuk pondasi


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5200 112,500.00 58,500.00
Tukang kayu L.04 OH 0.2600 132,500.00 34,450.00
Kepala tukang L.14 OH 0.0260 147,500.00 3,835.00
Mandor L.17 OH 0.0260 150,000.00 3,900.00
JUMLAH TENAGA KERJA 100,685.00
B BAHAN
Kayu kelas III m3 0.0400 5,300,000.00 212,000.00
Paku 5 - 10 cm Kg 0.3000 20,666.67 6,200.00
Minyak bekisting Liter 0.1000 17,500.00 1,750.00
JUMLAH HARGA BAHAN 219,950.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 320,635.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 320,635.00
D.I.20a. (K3) Pemasangan 1m2 bekisting untuk pondasi 2x pakai Rp 160,317.50

D.I.21. (K3) Pemasangan 1 m2 bekisting untuk sloof


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5200 112,500.00 58,500.00
Tukang kayu L.04 OH 0.2600 132,500.00 34,450.00
Kepala tukang L.14 OH 0.0260 147,500.00 3,835.00
Mandor L.17 OH 0.0260 150,000.00 3,900.00
JUMLAH TENAGA KERJA 100,685.00
B BAHAN
Kayu kelas III m3 0.0450 -
Paku 5 - 10 cm Kg 0.3000 -
Minyak bekisting Liter 0.1000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,685.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,685.00
D.I.21a. (K3) Pemasangan 1m2 bekisting untuk sloof 2x pakai Rp 50,342.50

D.I.22. (K3) Pemasangan 1 m2 bekisting untuk kolom


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6600 112,500.00 74,250.00
Tukang kayu L.04 OH 0.3300 132,500.00 43,725.00
Kepala tukang L.14 OH 0.0330 147,500.00 4,867.50
Mandor L.17 OH 0.0330 150,000.00 4,950.00
JUMLAH TENAGA KERJA 127,792.50
B BAHAN
Kayu kelas III m3 0.0400 5,300,000.00 212,000.00
Paku 5 cm - 12 cm Kg 0.4000 22,000.00 8,800.00
Minyak bekisting Liter 0.2000 17,500.00 3,500.00
Balok kayu kelas II m3 0.0150 7,366,666.67 110,500.00
Plywood tebal 9 mm Lembar 0.3500 225,000.00 78,750.00
Dolken kayu Ø 8-10 cm
Batang 2.0000 28,000.00 56,000.00
panjang 4 m
JUMLAH HARGA BAHAN 469,550.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 597,342.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 597,342.50
D.I.22a. (K3) Pemasangan 1m2 bekisting untuk kolom 2x pakai Rp 298,671.25

D.I.23. (K3) Pemasangan 1 m2 bekisting untuk balok


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6600 112,500.00 74,250.00
Tukang kayu L.04 OH 0.3300 132,500.00 43,725.00
Kepala tukang L.14 OH 0.0330 147,500.00 4,867.50
Mandor L.17 OH 0.0330 150,000.00 4,950.00
JUMLAH TENAGA KERJA 127,792.50
B BAHAN
Kayu kelas III m3 0.0400 5,300,000.00 212,000.00
Paku 5 cm - 12 cm Kg 0.4000 22,000.00 8,800.00
Minyak bekisting Liter 0.2000 17,500.00 3,500.00
Balok kayu kelas II m3 0.0180 7,366,666.67 132,600.00
Plywood tebal 9 mm Lembar 0.3500 225,000.00 78,750.00
Dolken kayu Ø 8-10 cm
Batang 2.0000 28,000.00 56,000.00
panjang 4 m
JUMLAH HARGA BAHAN 491,650.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 619,442.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 619,442.50
D.I.23a. (K3) Pemasangan 1m2 bekisting untuk balok 2x pakai Rp 309,721.25

D.I.24. (K3) Pemasangan 1 m2 bekisting untuk lantai


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6600 112,500.00 74,250.00
Tukang kayu L.04 OH 0.3300 132,500.00 43,725.00
Kepala tukang L.14 OH 0.0330 147,500.00 4,867.50
Mandor L.17 OH 0.0330 150,000.00 4,950.00
JUMLAH TENAGA KERJA 127,792.50
B BAHAN
Kayu kelas III m3 0.0400 5,300,000.00 212,000.00
Paku 5 cm - 12 cm Kg 0.4000 22,000.00 8,800.00
Minyak bekisting Liter 0.2000 17,500.00 3,500.00
Balok kayu kelas II m3 0.0150 7,366,666.67 110,500.00
Plywood tebal 9 mm Lembar 0.3500 225,000.00 78,750.00
Dolken kayu Ø 8-10 cm
Batang 6.0000 28,000.00 168,000.00
panjang 4 m
JUMLAH HARGA BAHAN 581,550.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 709,342.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 709,342.50
D.I.24a. (K3) Pemasangan 1m2 bekisting untuk lantai 2x pakai Rp 354,671.25

D.I.25. (K3) Pemasangan 1 m2 bekisting untuk dinding


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6600 112,500.00 74,250.00
Tukang kayu L.04 OH 0.3300 132,500.00 43,725.00
Kepala tukang L.14 OH 0.0330 147,500.00 4,867.50
Mandor L.17 OH 0.0330 150,000.00 4,950.00
JUMLAH TENAGA KERJA 127,792.50
B BAHAN
Kayu kelas III m3 0.0300 -
Paku 5 cm - 12 cm Kg 0.4000 -
Minyak bekisting Liter 0.2000 -
Balok kayu kelas II m3 0.0200 -
Plywood tebal 9 mm Lembar 0.3500 -
Dolken kayu Ø 8-10 cm
Batang 3.0000 -
panjang 4 m
Penjaga jarak
Buah 4.0000 -
bekisting/spacer
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 127,792.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 127,792.50
D.I.25a. (K3) Pemasangan 1m2 bekisting untuk dinding 2x pakai Rp 63,896.25

D.I.26. Pemasangan 1 m2 bekisting untuk tangga


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6600 112,500.00 74,250.00
Tukang kayu L.04 OH 0.3300 132,500.00 43,725.00
Kepala tukang L.14 OH 0.0330 147,500.00 4,867.50
Mandor L.17 OH 0.0330 150,000.00 4,950.00
JUMLAH TENAGA KERJA 127,792.50
B BAHAN
Kayu kelas III m3 0.0300 5,300,000.00 159,000.00
Paku 5 cm - 12 cm Kg 0.4000 22,000.00 8,800.00
Minyak bekisting Liter 0.1500 17,500.00 2,625.00
Balok kayu kelas II m3 0.0150 7,366,666.67 110,500.00
Plywood tebal 9 mm Lembar 0.3500 225,000.00 78,750.00
Dolken kayu Ø 8-10 cm
Batang 2.0000 28,000.00 56,000.00
panjang 4 m
JUMLAH HARGA BAHAN 415,675.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 543,467.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 543,467.50
D.I.26a. Pemasangan 1m2 bekisting untuk tangga 2x pakai Rp 271,733.75

D.I.27. Pemasangan 1 m2 jembatan untuk pengecoran beton


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang kayu L.04 OH 0.0500 132,500.00 6,625.00
Kepala tukang L.14 OH 0.0050 147,500.00 737.50
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 25,437.50
B BAHAN
Kayu kelas III (papan) m3 0.0264 -
Paku 5 cm - 12 cm Kg 0.6000 -
Dolken kayu Ø 8-10 cm
Batang 0.5000 -
panjang 4 m
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 25,437.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 25,437.50
D.I.28. Membuat 1 m1 kolom praktis beton bertulang (11 x 11) cm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1800 112,500.00 20,250.00
Tukang batu L.03 OH 0.0200 127,500.00 2,550.00
Tukang kayu L.04 OH 0.0200 132,500.00 2,650.00
Tukang besi L.05 OH 0.0200 127,500.00 2,550.00
Kepala tukang L.14 OH 0.0060 147,500.00 885.00
Mandor L.17 OH 0.0090 150,000.00 1,350.00
JUMLAH TENAGA KERJA 30,235.00
B BAHAN
Kayu kelas III m3 0.0020 -
Paku 5 cm - 12 cm Kg 0.0100 -
Minyak bekisting Liter - -
Besi beton polos Kg 3.0000 -
Kawat beton Kg 0.4500 -
Semen portland Kg 4.0000 -
Pasir beton m3 0.0060 -
Kerikil m3 0.0090 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 30,235.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 30,235.00

D.I.29. Membuat 1 m1 ring balok beton bertulang (10 x 15) cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.29700 112,500.00 33,412.50
Tukang batu L.03 OH 0.03300 127,500.00 4,207.50
Tukang kayu L.04 OH 0.03300 132,500.00 4,372.50
Tukang besi L.05 OH 0.03300 127,500.00 4,207.50
Kepala tukang L.14 OH 0.01000 147,500.00 1,475.00
Mandor L.17 OH 0.01500 150,000.00 2,250.00
JUMLAH TENAGA KERJA 49,925.00
B BAHAN
Kayu kelas III m3 0.00300 -
Paku 5 cm - 12 cm Kg 0.02000 -
Minyak bekisting Liter - -
Besi beton polos Kg 3.60000 -
Kawat beton Kg 0.05000 -
Semen portland Kg 5.50000 -
Pasir beton m3 0.00900 -
Kerikil m3 0.01500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 49,925.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 49,925.00

II (PERMEN NO.11/PRT/M/2013)
D.II.1. Membuat 1 m3 pondasi beton bertulang (150 Kg besi + bekisting)
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 5.3000 112,500.00 596,250.00
Tukang batu L.03 OH 0.2750 127,500.00 35,062.50
Tukang kayu L.04 OH 1.3000 132,500.00 172,250.00
Tukang besi L.05 OH 1.0500 127,500.00 133,875.00
Kepala tukang L.14 OH 0.2620 147,500.00 38,645.00
Mandor L.17 OH 0.2650 150,000.00 39,750.00
JUMLAH TENAGA KERJA 1,015,832.50
B BAHAN
Kayu kelas III m3 0.2000 -
Paku 5 cm - 12 cm Kg 1.5000 -
Minyak bekisting Liter 0.4000 -
Besi beton polos Kg 157.5000 -
Kawat beton Kg 2.2500 -
Semen portland Kg 336.0000 -
Pasir beton m3 0.5400 -
Kerikil m3 0.8100 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,015,832.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,015,832.50
D.II.2. Membuat 1 m3 sloof beton bertulang (200 Kg besi + bekisting)
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 5.6500 112,500.00 635,625.00
Tukang batu L.03 OH 0.2750 127,500.00 35,062.50
Tukang kayu L.04 OH 1.5600 132,500.00 206,700.00
Tukang besi L.05 OH 1.4000 127,500.00 178,500.00
Kepala tukang L.14 OH 0.3230 147,500.00 47,642.50
Mandor L.17 OH 0.2830 150,000.00 42,450.00
JUMLAH TENAGA KERJA 1,145,980.00
B BAHAN
Kayu kelas III m3 0.2700 -
Paku 5 cm - 12 cm Kg 2.0000 -
Minyak bekisting Liter 0.6000 -
Besi beton polos Kg 210.0000 -
Kawat beton Kg 3.0000 -
Semen portland Kg 336.0000 -
Pasir beton m3 0.5400 -
Kerikil m3 0.8100 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,145,980.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,145,980.00

D.II.3. Membuat 1 m3 kolom beton bertulang (300 Kg besi + bekisting)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 7.0500 112,500.00 793,125.00
Tukang batu L.03 OH 0.2750 127,500.00 35,062.50
Tukang kayu L.04 OH 1.6500 132,500.00 218,625.00
Tukang besi L.05 OH 2.1000 127,500.00 267,750.00
Kepala tukang L.14 OH 0.4030 147,500.00 59,442.50
Mandor L.17 OH 0.3530 150,000.00 52,950.00
JUMLAH TENAGA KERJA 1,426,955.00
B BAHAN
Kayu kelas III m3 0.4000 -
Paku 5 cm - 12 cm Kg 4.0000 -
Minyak bekisting Liter 2.0000 -
Besi beton polos Kg 315.0000 -
Kawat beton Kg 4.5000 -
Semen portland Kg 336.0000 -
Pasir beton m3 0.5400 -
Kerikil m3 0.8100 -
Kayu kelas II balok m3 0.1500 -
Plywood 9 mm Lembar 3.5000 -
Dolken kayu Ø 8-10 cm
Batang 20.0000 -
panjang 4 m
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,426,955.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,426,955.00

D.II.4. Membuat 1 m3 balok beton bertulang (200 Kg besi + bekisting)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 6.3500 112,500.00 714,375.00
Tukang batu L.03 OH 0.2750 127,500.00 35,062.50
Tukang kayu L.04 OH 1.6500 132,500.00 218,625.00
Tukang besi L.05 OH 1.4000 127,500.00 178,500.00
Kepala tukang L.14 OH 0.3330 147,500.00 49,117.50
Mandor L.17 OH 0.3180 150,000.00 47,700.00
JUMLAH TENAGA KERJA 1,243,380.00
B BAHAN
Kayu kelas III m3 0.3200 -
Paku 5 cm - 12 cm Kg 3.2000 -
Minyak bekisting Liter 1.6000 -
Besi beton polos Kg 210.0000 -
Kawat beton Kg 3.0000 -
Semen portland Kg 336.0000 -
Pasir beton m3 0.5400 -
Kerikil m3 0.8100 -
Kayu kelas II balok m3 0.1400 -
Plywood 9 mm Lembar 2.8000 -
Dolken kayu Ø 8-10 cm
Batang 16.0000 -
panjang 4 m
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,243,380.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,243,380.00

D.II.5. Membuat 1 m3 kolom beton bertulang (150 Kg besi + bekisting)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 5.3000 112,500.00 596,250.00
Tukang batu L.03 OH 0.2750 127,500.00 35,062.50
Tukang kayu L.04 OH 1.3000 132,500.00 172,250.00
Tukang besi L.05 OH 1.0500 127,500.00 133,875.00
Kepala tukang L.14 OH 0.2650 147,500.00 39,087.50
Mandor L.17 OH 0.2650 150,000.00 39,750.00
JUMLAH TENAGA KERJA 1,016,275.00
B BAHAN
Kayu kelas III m3 0.3200 -
Paku 5 cm - 12 cm Kg 3.2000 -
Minyak bekisting Liter 1.6000 -
Besi beton polos Kg 157.5000 -
Kawat beton Kg 2.2500 -
Semen portland Kg 336.0000 -
Pasir beton m3 0.5400 -
Kerikil m3 0.8100 -
Kayu kelas II balok m3 0.1200 -
Plywood 9 mm Lembar 2.8000 -
Dolken kayu Ø 8-10 cm
Batang 32.0000 -
panjang 4 m
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,016,275.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,016,275.00

D.II.6. Membuat 1 m3 dinding beton bertulang (150 Kg besi + bekisting)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 5.3000 112,500.00 596,250.00
Tukang batu L.03 OH 0.2750 127,500.00 35,062.50
Tukang kayu L.04 OH 1.3000 132,500.00 172,250.00
Tukang besi L.05 OH 1.0500 127,500.00 133,875.00
Kepala tukang L.14 OH 0.2620 147,500.00 38,645.00
Mandor L.17 OH 0.2650 150,000.00 39,750.00
JUMLAH TENAGA KERJA 1,015,832.50
B BAHAN
Kayu kelas III m3 0.2400 -
Paku 5 cm - 12 cm Kg 3.2000 -
Minyak bekisting Liter 1.6000 -
Besi beton polos Kg 157.5000 -
Kawat beton Kg 2.2500 -
Semen portland Kg 336.0000 -
Pasir beton m3 0.5400 -
Kerikil m3 0.8100 -
Kayu kelas II balok m3 0.1600 -
Plywood 9 mm Lembar 2.8000 -
Dolken kayu Ø 8-10 cm
Batang 24.0000 -
panjang 4 m
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,015,832.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,015,832.50

D.II.7. Membuat 1 m3 dinding beton bertulang (200 Kg besi + bekisting)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 5.6500 112,500.00 635,625.00
Tukang batu L.03 OH 0.2750 127,500.00 35,062.50
Tukang kayu L.04 OH 1.5600 132,500.00 206,700.00
Tukang besi L.05 OH 1.4000 127,500.00 178,500.00
Kepala tukang L.14 OH 0.3230 147,500.00 47,642.50
Mandor L.17 OH 0.2830 150,000.00 42,450.00
JUMLAH TENAGA KERJA 1,145,980.00
B BAHAN
Kayu kelas III m3 0.2500 -
Paku 5 cm - 12 cm Kg 3.0000 -
Minyak bekisting Liter 1.2000 -
Besi beton polos Kg 210.0000 -
Kawat beton Kg 3.0000 -
Semen portland Kg 336.0000 -
Pasir beton m3 0.5400 -
Kerikil m3 0.8100 -
Kayu kelas II balok m3 0.1050 -
Plywood 9 mm Lembar 2.5000 -
Dolken kayu Ø 8-10 cm
Batang 14.0000 -
panjang 4 m
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,145,980.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,145,980.00

III ANALISA SENDIRI


D.III.1. Pemasangan 1 m2 floor deck
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0500 112,500.00 5,625.00
Tukang kayu L.04 OH 0.5000 132,500.00 66,250.00
Kepala tukang L.14 OH 0.0250 147,500.00 3,687.50
Mandor L.17 OH 0.0250 150,000.00 3,750.00
JUMLAH TENAGA KERJA 79,312.50
B BAHAN
Floor deck 0,75 mm m2 1.1000 -
Kayu kelas III m3 0.0054 -
Paku 5 cm - 12 cm Kg 0.1000 -
Kayu kelas II balok m3 0.0150 -
Dolken kayu Ø 8-10 cm
Batang 4.0000 -
panjang 4 m
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 79,312.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 79,312.50

D.III.2. Pemasangan 1 m1 endstop floor deck (side closer)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0100 112,500.00 1,125.00
Tukang kayu L.04 OH 0.0100 132,500.00 1,325.00
Kepala tukang L.14 OH 0.0050 147,500.00 737.50
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 3,337.50
B BAHAN
Endstop floordeck m1 1.1000 -
Sekrup Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,337.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,337.50

D.III.3. Pemasangan 1 m2 plastik cor


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0130 112,500.00 1,462.50
Tukang kayu L.04 OH 0.0040 132,500.00 530.00
Kepala tukang L.14 OH 0.0040 147,500.00 590.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 2,882.50
B BAHAN
Plastik cor m2 1.1000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 2,882.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 2,882.50
E A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK
I (PERMEN NOMOR 28/PRT/M/2016)
Untuk produksi pracetak bisa dilakukan dipabrik (cor di plant) atau di lapangan (cast in
place). Indeks yang ada dalam pedoman ini hanya untuk pekerjaan produksi yang
dilakukan di lapangan, terutama untuk analisa cetakan (bekisting) pracetak baik untuk
komponen kolom, balok dan pelat.
E.I.1. (K3) Pembuatan 1 m2 lahan produksi tebal 8 cm beton f’c 14,5 MPa, (K.175), slump (120 ± 20) mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1320 112,500.00 14,850.00
Tukang batu L.03 OH 0.0220 127,500.00 2,805.00
Kepala tukang L.14 OH 0.0022 147,500.00 324.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 19,029.50
B BAHAN
Semen portland Kg 26.0800 -
Pasir beton Kg 60.8000 -
Kerikil (maks 30 mm) Kg 82.3200 -
Air Liter 17.2000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 19,029.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 19,029.50

E.I.2. (K3) Pembuatan 1 m2 lahan produksi tebal 10 cm beton f’c 14,5 MPa, (K.175), slump (120 ± 20) mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1650 112,500.00 18,562.50
Tukang batu L.03 OH 0.0280 127,500.00 3,570.00
Kepala tukang L.14 OH 0.0028 147,500.00 413.00
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 23,745.50
B BAHAN
Semen portland Kg 32.6000 -
Pasir beton Kg 76.0000 -
Kerikil (maks 30 mm) Kg 102.9000 -
Air Liter 21.5000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,745.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,745.50

E.I.3. (K3) Pembuatan 1 m2 lahan produksi tebal 12 cm beton f’c 14,5 MPa, (K.175), slump (120 ± 20) mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1980 112,500.00 22,275.00
Tukang batu L.03 OH 0.0330 127,500.00 4,207.50
Kepala tukang L.14 OH 0.0033 147,500.00 486.75
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 28,469.25
B BAHAN
Semen portland Kg 39.1200 -
Pasir beton Kg 91.2000 -
Kerikil (maks 30 mm) Kg 123.4800 -
Air Liter 25.8000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 28,469.25


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 28,469.25

E.I.4. (K3) Pembuatan 1 m2 lahan produksi tebal 15 cm beton f’c 14,5 MPa, (K.175), slump (120 ± 20) mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2480 112,500.00 27,900.00
Tukang batu L.03 OH 0.0410 127,500.00 5,227.50
Kepala tukang L.14 OH 0.0040 147,500.00 590.00
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 35,667.50
B BAHAN
Semen portland Kg 48.9000 -
Pasir beton Kg 114.0000 -
Kerikil (maks 30 mm) Kg 154.3500 -
Air Liter 32.2500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 35,667.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 35,667.50
E.I.5. Pembuatan 1 m2 bekisting untuk pelat beton pracetak (5 kali pakai)
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0070 112,500.00 787.50
Tukang kayu L.04 OH 0.0760 132,500.00 10,070.00
Kepala tukang L.14 OH 0.0076 147,500.00 1,121.00
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 12,128.50
B BAHAN
Lantai kerja t = 10 cm m3 0.0800 -
Besi hollow (50 x 50 x 3)
Kg 9.3940 -
mm
Kayu kaso 5/7 (lebar 5 cm,
m3 0.0050 -
tinggi 7 cm)
Phenol film 12 mm Lembar 0.0800 -
Minyak cetakan (bekisting) Liter 0.2000 -
Dinabolt Ø 12mm (10 s.d.
Buah 3.8820 -
15 cm)
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 12,128.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 12,128.50

E.I.6. Pembuatan 1 m2 bekisting untuk balok beton pracetak (10-12 kali pakai)
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0040 112,500.00 450.00
Tukang kayu L.04 OH 0.0380 132,500.00 5,035.00
Kepala tukang L.14 OH 0.0040 147,500.00 590.00
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 6,225.00
B BAHAN
Kayu kaso 5/7 (lebar 5 cm,
m3 0.0050 -
tinggi 7 cm)
Phenol film 12 mm Lembar 0.0430 -
Minyak cetakan (bekisting) Liter 0.2000 -
Paku (5 s.d. 7) cm Kg 0.0460 -
Dinabolt Ø 12mm (10 s.d.
Buah 0.6930 -
15 cm)
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 6,225.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 6,225.00

E.I.7. Pembuatan 1 m2 bekisting untuk kolom beton pracetak (10-12 kali pakai)
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0040 112,500.00 450.00
Tukang kayu L.04 OH 0.0380 132,500.00 5,035.00
Kepala tukang L.14 OH 0.0040 147,500.00 590.00
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 6,225.00
B BAHAN
Kayu kaso 5/7 (lebar 5 cm,
m3 0.0040 -
tinggi 7 cm)
Phenol film 12 mm Lembar 0.0480 -
Minyak cetakan (bekisting) Liter 0.2000 -
Paku (5 s.d. 7) cm Kg 0.0460 -
Dinabolt Ø 12mm (10 s.d.
Buah 0.6930 -
15 cm)
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 6,225.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 6,225.00

E.I.8. Pemasangan dan membuka bekisting 1 buah komponen pelat beton pracetak
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0530 112,500.00 5,962.50
Tukang kayu L.04 OH 0.0180 132,500.00 2,385.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 9,097.50
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 9,097.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 9,097.50

E.I.9. Pemasangan dan membuka bekisting 1 buah komponen balok beton pracetak
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0890 112,500.00 10,012.50
Tukang kayu L.04 OH 0.0300 132,500.00 3,975.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 14,737.50
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 14,737.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 14,737.50

E.I.10. Pemasangan dan membuka bekisting 1 buah komponen kolom beton pracetak
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0710 112,500.00 7,987.50
Tukang kayu L.04 OH 0.0240 132,500.00 3,180.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 11,917.50
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 11,917.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 11,917.50

E.I.11. Penuangan/menebar beton 1 m3 komponen untuk pelat pracetak


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0640 112,500.00 7,200.00
Tukang batu L.03 OH 0.2440 127,500.00 31,110.00
Tukang vibrator L.11 OH 0.1280 - -
Kepala tukang L.14 OH 0.0340 147,500.00 5,015.00
Mandor L.17 OH 0.0730 150,000.00 10,950.00
JUMLAH TENAGA KERJA 54,275.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 54,275.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 54,275.00

E.I.12. Penuangan/menebar beton 1 m3 komponen untuk balok pracetak


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0690 112,500.00 7,762.50
Tukang batu L.03 OH 0.2420 127,500.00 30,855.00
Tukang vibrator L.11 OH 0.1380 - -
Kepala tukang L.14 OH 0.0370 147,500.00 5,457.50
Mandor L.17 OH 0.0730 150,000.00 10,950.00
JUMLAH TENAGA KERJA 55,025.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 55,025.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 55,025.00

E.I.13. Penuangan/menebar beton 1 m3 komponen untuk kolom pracetak


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0610 112,500.00 6,862.50
Tukang batu L.03 OH 0.2130 127,500.00 27,157.50
Tukang vibrator L.11 OH 0.1220 - -
Kepala tukang L.14 OH 0.0330 147,500.00 4,867.50
Mandor L.17 OH 0.0730 150,000.00 10,950.00
JUMLAH TENAGA KERJA 49,837.50
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 49,837.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 49,837.50

E.I.14. Ereksi dan mendirikan 1 buah komponen untuk pelat pracetak


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Operator crane L.21b OH 0.0670 - -
Pembantu operator crane L.22b OH 0.0670 - -
Pekerja L.01 OH 0.0670 112,500.00 7,537.50
Tukang batu L.03 OH 0.0670 127,500.00 8,542.50
Tukang ereksi L.13 OH 0.1340 - -
Kepala tukang L.14 OH 0.0670 147,500.00 9,882.50
Mandor L.17 OH 0.0670 150,000.00 10,050.00
JUMLAH TENAGA KERJA 36,012.50
B BAHAN
Solar Liter 6.6760 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa crane (mobile) UH 0.0670 -
Sewa pipe suport UH 1.1000 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 36,012.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 36,012.50

Indeks kenaikan lantai ereksi komponen untuk pelat pracetak

E.I.15. Ereksi dan mendirikan 1 buah komponen untuk balok pracetak


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Operator crane L.21b OH 0.0610 - -
Pembantu operator crane L.22b OH 0.0610 - -
Pekerja L.01 OH 0.0610 112,500.00 6,862.50
Tukang batu L.03 OH 0.0610 127,500.00 7,777.50
Tukang ereksi L.13 OH 0.1220 - -
Kepala tukang L.14 OH 0.0610 147,500.00 8,997.50
Mandor L.17 OH 0.0610 150,000.00 9,150.00
JUMLAH TENAGA KERJA 32,787.50
B BAHAN
Solar Liter 6.1100 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa crane UH 0.0610 -
Sewa scaffolding UH 1.1000 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 32,787.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 32,787.50

Indeks kenaikan lantai ereksi komponen untuk balok pracetak

E.I.16. Ereksi dan mendirikan 1 buah komponen untuk kolom pracetak


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Operator crane L.21b OH 0.0830 - -
Pembantu operator crane L.22b OH 0.0830 - -
Pekerja L.01 OH 0.0830 112,500.00 9,337.50
Tukang batu L.03 OH 0.0830 127,500.00 10,582.50
Tukang ereksi L.13 OH 0.1660 - -
Kepala tukang L.14 OH 0.0830 147,500.00 12,242.50
Mandor L.17 OH 0.0830 150,000.00 12,450.00
JUMLAH TENAGA KERJA 44,612.50
B BAHAN
Solar Liter 8.2770 - -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa crane UH 0.0830 - -
Sewa scaffolding UH 2.2000 - -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 44,612.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 44,612.50

Indeks kenaikan lantai ereksi komponen untuk kolom pracetak


E.I.17. Langsir 1 buah komponen untuk pelat pracetak (± 20 m)
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Operator crane L.21b OH 0.0190 - -
Pembantu operator crane L.22b OH 0.0190 - -
Pekerja L.01 OH 0.0190 112,500.00 2,137.50
Tukang batu L.03 OH 0.0380 127,500.00 4,845.00
JUMLAH TENAGA KERJA 6,982.50
B BAHAN
Solar Liter 1.8970 - -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa crane UH 0.0190 - -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 6,982.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 6,982.50

E.I.18. Langsir 1 buah komponen untuk balok pracetak (± 20 m)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Operator crane L.21b OH 0.0190 - -
Pembantu operator crane L.22b OH 0.0190 - -
Pekerja L.01 OH 0.0190 112,500.00 2,137.50
Tukang batu L.03 OH 0.0380 127,500.00 4,845.00
JUMLAH TENAGA KERJA 6,982.50
B BAHAN
Solar Liter 1.8970 - -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa crane UH 0.0190 - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 6,982.50
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 6,982.50

E.I.19. Langsir 1 buah komponen untuk kolom pracetak (± 20 m)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Operator crane L.21b OH 0.0190 - -
Pembantu operator crane L.22b OH 0.0190 - -
Pekerja L.01 OH 0.0190 112,500.00 2,137.50
Tukang batu L.03 OH 0.0380 127,500.00 4,845.00
JUMLAH TENAGA KERJA 6,982.50
B BAHAN
Solar Liter 1.8970 - -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa crane UH 0.0190 - -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 6,982.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 6,982.50

E.I.20. Bahan 1 m3 grout campuran


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
JUMLAH TENAGA KERJA -
B BAHAN
Semen grout Kg 1,200.0000 -
Screening Kg 650.0000 -
Air Liter 350.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp -

E.I.21. Bahan 1 m3 grout (tidak campuran)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
JUMLAH TENAGA KERJA -
B BAHAN
Semen grout Kg 1,850.000 -
Air Liter 400.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp -

E.I.22. Upah melakukan 1 titik grouting pada join pracetak


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Tukang batu L.03 OH 0.3670 127,500.00 46,792.50
Kepala tukang L.14 OH 0.0740 147,500.00 10,915.00
Mandor L.17 OH 0.0370 150,000.00 5,550.00
JUMLAH TENAGA KERJA 63,257.50
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 63,257.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 63,257.50

E.I.23. Pemasangan 1 titik bekisting join pracetak


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1470 112,500.00 16,537.50
Tukang kayu L.04 OH 0.1470 132,500.00 19,477.50
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 38,977.50
B BAHAN
Kayu kaso 5/7 (lebar 5 cm,
m3 0.0120 -
tinggi 7 cm)
Papan cor m3 0.0040 -
Paku (5 s.d. 7) cm Kg 0.2640 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 38,977.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 38,977.50

E.I.24. Upah 1 titik join dengan sling


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2200 112,500.00 24,750.00
Tukang kayu L.04 OH 0.0220 132,500.00 2,915.00
Tukang besi L.05 OH 0.2200 127,500.00 28,050.00
Mandor L.17 OH 0.0110 150,000.00 1,650.00
JUMLAH TENAGA KERJA 57,365.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,365.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 57,365.00
F HARGA SATUAN PEKERJAAN BESI DAN ALUMINIUM
I (PERMEN NOMOR 28/PRT/M/2016)
F.I.1. Pemasangan 1 kg besi profil
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0600 112,500.00 6,750.00
Tukang las konstruksi L.10b OH 0.0600 130,000.00 7,800.00
Kepala tukang L.14 OH 0.0060 147,500.00 885.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 15,885.00
B BAHAN
Baja profil Kg 1.1500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 15,885.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 15,885.00

F.I.2. Pemasangan 1 kg rangka kuda-kuda baja IWF


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0600 112,500.00 6,750.00
Tukang las konstruksi L.10b OH 0.0600 130,000.00 7,800.00
Kepala tukang L.14 OH 0.0060 147,500.00 885.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 15,885.00
B BAHAN
Besi baja IWF Kg 1.1500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 15,885.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 15,885.00

F.I.3. Pengerjaan 100 kg pekerjaan perakitan


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang besi L.05 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0010 147,500.00 147.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 24,897.50
B BAHAN
Solar Liter 1.0000 -
Minyak pelumas Liter 0.1000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa alat Jam 0.8000 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 24,897.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 24,897.50
F.I.3a Pengerjaan 1 kg pekerjaan perakitan Rp 248.98

F.I.4. Pembuatan 1 m2 pintu besi pelat baja tebal 2 mm rangkap, rangka baja siku
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0500 112,500.00 118,125.00
Tukang las L.10a OH 1.0500 130,000.00 136,500.00
Kepala tukang L.14 OH 0.1050 147,500.00 15,487.50
Mandor L.17 OH 0.0520 150,000.00 7,800.00
JUMLAH TENAGA KERJA 277,912.50
B BAHAN
Besi siku L 30.30.3 Kg 15.0000 -
Besi pelat baja Kg 32.8000 -
Kawat las Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 277,912.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 277,912.50

F.I.5. Pengerjaan 10 cm pengelasan dengan las listrik


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0400 112,500.00 4,500.00
Tukang besi L.05 OH 0.0200 127,500.00 2,550.00
Kepala tukang L.14 OH 0.0020 147,500.00 295.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 7,645.00
B BAHAN
Kawat las Kg 0.4000 -
Solar Liter 0.3000 -
Minyak pelumas Liter 0.0400 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa alat Jam 0.1700 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 7,645.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 7,645.00
F.I.5a Pengerjaan 1 cm pengelasan dengan las listrik Rp 764.50

F.I.6. Pembuatan 1 m2 rangka jendela besi scuare tube


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6500 112,500.00 73,125.00
Tukang las L.10a OH 0.6500 130,000.00 84,500.00
Kepala tukang L.14 OH 0.0650 147,500.00 9,587.50
Mandor L.17 OH 0.0320 150,000.00 4,800.00
JUMLAH TENAGA KERJA 172,012.50
B BAHAN
Besi scuare Tube m 4.7600 -
Besi lis kaca (1x1) cm m 4.5220 -
Pengelasan cm 20.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 172,012.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 172,012.50

F.I.7. Pemasangan 1 m2 pintu rolling door besi


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.2000 112,500.00 135,000.00
Tukang las L.10a OH 1.2000 130,000.00 156,000.00
Kepala tukang L.14 OH 0.1200 147,500.00 17,700.00
Mandor L.17 OH 0.0060 150,000.00 900.00
JUMLAH TENAGA KERJA 309,600.00
B BAHAN
Pintu gulung besi m2 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 309,600.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 309,600.00

F.I.8. Pemasangan 1 m2 pintu lipat (folding door) bahan plastik/PVC


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4400 112,500.00 49,500.00
Tukang besi L.05 OH 0.4400 127,500.00 56,100.00
Kepala tukang L.14 OH 0.0440 147,500.00 6,490.00
Mandor L.17 OH 0.0220 150,000.00 3,300.00
JUMLAH TENAGA KERJA 115,390.00
B BAHAN
Pintu lipat m2 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 115,390.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 115,390.00

F.I.9. Pemasangan 1 m2 sunscreen aluminium


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0800 112,500.00 9,000.00
Tukang aluminium L.12 OH 0.8000 130,000.00 104,000.00
Kepala tukang L.14 OH 0.0800 147,500.00 11,800.00
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 125,400.00
B BAHAN
Sunscreen aluminium m2 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 125,400.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 125,400.00

F.I.10. Pemasangan 1 m2 rolling door aluminium


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.000 112,500.00 112,500.00
Tukang aluminium L.12 OH 1.000 130,000.00 130,000.00
Kepala tukang L.14 OH 0.100 147,500.00 14,750.00
Mandor L.17 OH 0.050 150,000.00 7,500.00
JUMLAH TENAGA KERJA 264,750.00
B BAHAN
Rolling door aluminium m2 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 264,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 264,750.00

F.I.11. Pemasangan 1 m kusen pintu aluminium


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0430 112,500.00 4,837.50
Tukang aluminium L.12 OH 0.0430 130,000.00 5,590.00
Kepala tukang L.14 OH 0.0043 147,500.00 634.25
Mandor L.17 OH 0.0021 150,000.00 315.00
JUMLAH TENAGA KERJA 11,376.75
B BAHAN
Profil aluminium m1 1.1000 -
Skrup fixer Buah 2.0000 -
Sealant Tube 0.0600 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 11,376.75


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 11,376.75

F.I.12. Pemasangan 1 m2 pintu aluminium strip lebar 8 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0850 112,500.00 9,562.50
Tukang aluminium L.12 OH 0.0850 130,000.00 11,050.00
Kepala tukang L.14 OH 0.0085 147,500.00 1,253.75
Mandor L.17 OH 0.0042 150,000.00 630.00
JUMLAH TENAGA KERJA 22,496.25
B BAHAN
Profil aluminium m1 4.4000 -
Allumunium strip m1 14.6000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 22,496.25


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 22,496.25

F.I.13. Pemasangan 1 m2 pintu kaca rangka aluminium


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0850 112,500.00 9,562.50
Tukang aluminium L.12 OH 0.0850 130,000.00 11,050.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 22,690.00
B BAHAN
Profil aluminium m1 4.4000 -
Profil kaca m1 4.5000 -
Sealant Tube 0.2700 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 22,690.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 22,690.00
F.I.14. Pemasangan 1 m2 venetions blinds dan vertical blinds
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3500 112,500.00 39,375.00
Tukang aluminium L.12 OH 0.3500 130,000.00 45,500.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0180 150,000.00 2,700.00
JUMLAH TENAGA KERJA 92,737.50
B BAHAN
Venetions blinds dan vertical
m2 1.0000 -
binds (tirai)
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 92,737.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 92,737.50

F.I.15. Pemasangan 1 m2 terali besi strip (2 x 3) mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6700 112,500.00 187,875.00
Tukang las L.10a OH 1.6700 130,000.00 217,100.00
Kepala tukang L.14 OH 0.1670 147,500.00 24,632.50
Mandor L.17 OH 0.0830 150,000.00 12,450.00
JUMLAH TENAGA KERJA 442,057.50
B BAHAN
Besi strip Kg 6.1770 -
Pengelasan cm 27.0800 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 442,057.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 442,057.50

F.I.16. Pemasangan 1 m2 kawat nyamuk


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang las L.10a OH 0.1000 130,000.00 13,000.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 26,475.00
B BAHAN
Kawat nyamuk m2 1.1000 -
Pengelasan cm 11.1100 -
Baja strip (0,2 x 2) cm Kg 1.7160 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 26,475.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 26,475.00

F.I.17. Pemasangan 1 m2 jendela nako & tralis


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang aluminium L.12 OH 0.2000 130,000.00 26,000.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 51,600.00
B BAHAN
Jendela nako (rangka + kaca
m2 1.1000 -
5 mm)
Paku skrup 1 cm - 2,5 cm Buah 10.0000 -
Baja strip m 7.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 51,600.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 51,600.00

F.I.18. Pemasangan 1 m1 talang datar/jurai seng bjls 28 lebar 90 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang aluminium L.12 OH 0.2000 130,000.00 26,000.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 51,600.00
B BAHAN
Seng pelat m1 1.0500 -
Paku skrup 1 cm - 2,5 cm Kg 0.0150 -
Papan kayu kelas II atau III m3 0.0190 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 51,600.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 51,600.00
F.I.19. Pemasangan 1 m talang 1/2 lingkaran D-15 cm, seng pelat bjls 30 lebar 45 cm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang aluminium L.12 OH 0.3000 130,000.00 39,000.00
Kepala tukang L.14 OH 0.0300 147,500.00 4,425.00
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 61,500.00
B BAHAN
Seng pelat m1 1.0500 -
Paku skrup 1 cm - 2,5 cm Kg 0.0100 -
Besi strip Kg 0.5000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 61,500.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 61,500.00

F.I.20. Pemasangan 1 m2 rangka besi hollow 1 x 40.40.2 mm, modul 60 x 120 cm, untuk dinding partisi
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Tukang besi L.05 OH 0.2500 127,500.00 31,875.00
Kepala tukang L.14 OH 0.0250 147,500.00 3,687.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 65,637.50
B BAHAN
Rangka metal hollow 40.40.2
m1 3.5000 -
mm

Assesoris (perkuatan, las dll) % 1.0000 - -

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 65,637.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 65,637.50

F.I.21. Pemasangan 1 m2 rangka besi hollow 1 x 40.40.2 mm, modul 60 x 60 cm, untuk plafon
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3500 112,500.00 39,375.00
Tukang besi L.05 OH 0.3500 127,500.00 44,625.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0180 150,000.00 2,700.00
JUMLAH TENAGA KERJA 91,862.50
B BAHAN
Rangka metal hollow 40.40.2
m1 4.0000 -
mm

Assesoris (perkuatan, las dll) % 1.0000 - -

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 91,862.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 91,862.50

F.I.22. (K3) Pemasangan 1 m2 atap pelana rangka atap baja canai dingin profil C75
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7340 112,500.00 82,575.00
Tukang besi L.05 OH 0.7340 127,500.00 93,585.00
Kepala tukang L.14 OH 0.0730 147,500.00 10,767.50
Mandor L.17 OH 0.0370 150,000.00 5,550.00
JUMLAH TENAGA KERJA 192,477.50
B BAHAN

Baja ringan canai dingin C75 Kg 3.0650 -

JUMLAH HARGA BAHAN -


C PERALATAN
Peralatan % 0.1000 - -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 192,477.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 192,477.50

F.I.23. (K3) Pemasangan 1 m2 atap jurai rangka atap baja canai dingin profil C75
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7604 112,500.00 85,545.00
Tukang besi L.05 OH 0.7604 127,500.00 96,951.00
Kepala tukang L.14 OH 0.0760 147,500.00 11,210.00
Mandor L.17 OH 0.0380 150,000.00 5,700.00
JUMLAH TENAGA KERJA 199,406.00
B BAHAN

Baja ringan canai dingin C75 M360 Kg 4.0500 -

JUMLAH HARGA BAHAN -


C PERALATAN
Peralatan % 0.1000 - -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 199,406.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 199,406.00

II ANALISA SENDIRI
F.II.1. Pemasangan 1 m2 rangka atap baja ringan UK - galvalume
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2470 112,500.00 27,787.50
Tukang besi L.05 OH 0.1760 127,500.00 22,440.00
Kepala tukang L.14 OH 0.1170 147,500.00 17,257.50
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 74,985.00
B BAHAN
Main truss UK-75-75 m1 2.1820 -
Main truss UK-75-55 m1 1.9090 -
Main truss UK-65-55 m1 1.6910 -
Reng AA 0,45 m1 7.7730 -
Skrup SDS 8 x 16 Buah 12.7270 -
Skrup SDS 12 x 20 Buah 27.2730 -
Skrup SDS 10 x 16 Buah 13.6360 -
Dynabolt 10 x 65 Buah 0.5460 -
Diafrakma (PLD) Buah 8.8640 -
Sepatu UK (PK) Buah 0.2730 -
JUMLAH HARGA BAHAN -
C PERALATAN
Alat bantu % 0.2000 - -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 74,985.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 74,985.00

F.II.2. Pemasangan 1 m2 reng baja ringan


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0860 112,500.00 9,675.00
Tukang besi L.05 OH 0.1940 127,500.00 24,735.00
Kepala tukang L.14 OH 0.0040 147,500.00 590.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 35,300.00
B BAHAN
Reng baja ringan m1 5.4000 -
Skrup Buah 35.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Alat bantu % 0.1000 - -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 35,300.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 35,300.00

F.II.3. Pemasangan 1 m1 railing hollow galvanis


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6000 112,500.00 67,500.00
Tukang besi L.05 OH 1.0000 127,500.00 127,500.00
Kepala tukang L.14 OH 0.2000 147,500.00 29,500.00
Mandor L.17 OH 0.0200 150,000.00 3,000.00
JUMLAH TENAGA KERJA 227,500.00
B BAHAN
Plat dudukan tiang railing Kg 0.5000 -
Dynabolt type 6222 ukuran
Buah 2.0000 -
10 x 105 mm
Hollow Steel 40 x 40 x 2,7
Batang 0.2500 -
mm 6 meter
Hollow Steel 40 x 40 x 2,7
Batang 0.1500 -
mm 6 meter
Hollow Steel 40 x 40 x 2,7
Batang 0.1500 -
mm 6 meter
Hollow Steel 40 x 40 x 2,7
Batang 0.1500 -
mm 6 meter
Hollow Steel 40 x 20 x 1,7
Batang 1.2000 -
mm 6 meter
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 227,500.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 227,500.00

F.II.4. Pemasangan 1 m1 handrail


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang besi L.05 OH 0.5000 127,500.00 63,750.00
Kepala tukang L.14 OH 0.1000 147,500.00 14,750.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 113,750.00
B BAHAN
Pipa stainless m1 1.1000 -
Dudukan railing Buah 2.0000 -
Dynabolt type 6222 ukuran
Buah 6.0000 -
10 x 105 mm
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 113,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 113,750.00

F.II.5. Pemasangan 1 m1 railing


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang besi L.05 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0200 150,000.00 3,000.00
JUMLAH TENAGA KERJA 50,975.00
B BAHAN
Pipa stainless m1 8.0000 -
Dynabolt type 6222 ukuran
Buah 18.0000 -
10 x 105 mm
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,975.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 50,975.00
G A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
I (PERMEN NOMOR 28/PRT/M/2016)
G.I.1. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 2PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6000 112,500.00 67,500.00
Tukang batu L.03 OH 0.2000 127,500.00 25,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0300 150,000.00 4,500.00
JUMLAH TENAGA KERJA 100,450.00
B BAHAN
Bata merah Buah 140.0000 -
Semen portland Kg 43.5000 -
Pasir pasang m3 0.0800 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,450.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,450.00

G.I.2. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6000 112,500.00 67,500.00
Tukang batu L.03 OH 0.2000 127,500.00 25,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0300 150,000.00 4,500.00
JUMLAH TENAGA KERJA 100,450.00
B BAHAN
Bata merah Buah 140.0000 -
Semen portland Kg 32.9500 -
Pasir pasang m3 0.0910 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,450.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,450.00

G.I.3. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 4PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6000 112,500.00 67,500.00
Tukang batu L.03 OH 0.2000 127,500.00 25,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0300 150,000.00 4,500.00
JUMLAH TENAGA KERJA 100,450.00
B BAHAN
Bata merah Buah 140.0000 -
Semen portland Kg 26.5500 -
Pasir pasang m3 0.0930 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,450.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,450.00

G.I.4. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 5PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6000 112,500.00 67,500.00
Tukang batu L.03 OH 0.2000 127,500.00 25,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0300 150,000.00 4,500.00
JUMLAH TENAGA KERJA 100,450.00
B BAHAN
Bata merah Buah 140.0000 -
Semen portland Kg 22.2000 -
Pasir pasang m3 0.1020 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,450.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,450.00

G.I.5. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 6PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6000 112,500.00 67,500.00
Tukang batu L.03 OH 0.2000 127,500.00 25,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0300 150,000.00 4,500.00
JUMLAH TENAGA KERJA 100,450.00
B BAHAN
Bata merah Buah 140.0000 -
Semen portland Kg 18.5000 -
Pasir pasang m3 0.1220 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,450.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,450.00

G.I.6. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3KP : 10PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6000 112,500.00 67,500.00
Tukang batu L.03 OH 0.2000 127,500.00 25,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0300 150,000.00 4,500.00
JUMLAH TENAGA KERJA 100,450.00
B BAHAN
Bata merah Buah 140.0000 -
Semen portland Kg 10.0800 -
Kapur padam m3 0.0275 -
Pasir pasang m3 0.0925 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,450.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,450.00

G.I.7. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 2PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 50,225.00
B BAHAN
Bata merah Buah 70.0000 -
Semen portland Kg 18.9500 -
Pasir pasang m3 0.0380 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,225.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 50,225.00

G.I.8. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 3PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 50,225.00
B BAHAN
Bata merah Buah 70.0000 -
Semen portland Kg 14.3700 -
Pasir pasang m3 0.0400 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 50,225.00
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 50,225.00

G.I.9. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 4PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 50,225.00
B BAHAN
Bata merah Buah 70.0000 -
Semen portland Kg 11.5000 -
Pasir pasang m3 0.0430 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,225.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 50,225.00

G.I.10. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 5PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 50,225.00
B BAHAN
Bata merah Buah 70.0000 -
Semen portland Kg 9.6800 -
Pasir pasang m3 0.0450 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,225.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 50,225.00

G.I.11. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 6PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 50,225.00
B BAHAN
Bata merah Buah 70.0000 -
Semen portland Kg 8.3200 -
Pasir pasang m3 0.0490 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,225.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 50,225.00

G.I.12. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 8PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 50,225.00
B BAHAN
Bata merah Buah 70.0000 -
Semen portland Kg 6.5000 -
Pasir pasang m3 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,225.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 50,225.00

G.I.13. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 3KP : 10PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 50,225.00
B BAHAN
Bata merah Buah 70.0000 -
Semen portland Kg 4.5000 -
Kapur padam m3 0.0150 -
Pasir pasang m3 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,225.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 50,225.00

G.I.14. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SM : 1KP : 1PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 50,225.00
B BAHAN
Bata merah Buah 70.0000 -
Semen portland Kg 0.0180 -
Kapur padam m3 0.0180 -
Pasir pasang m3 0.0180 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,225.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 50,225.00

G.I.15. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SM : 1KP : 2PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 50,225.00
B BAHAN
Bata merah Buah 70.0000 -
Semen portland Kg 0.0140 -
Kapur padam m3 0.0140 -
Pasir pasang m3 0.0280 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,225.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 50,225.00

G.I.16. Pemasangan 1 m2 dinding conblock HB20 campuran 1SP : 3PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3500 112,500.00 39,375.00
Tukang batu L.03 OH 0.1500 127,500.00 19,125.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0180 150,000.00 2,700.00
JUMLAH TENAGA KERJA 63,412.50
B BAHAN
HB-20 Buah 12.5000 -
Semen portland Kg 30.3200 -
Pasir pasang m3 0.7280 -
Besi angker diameter 8 Kg 0.2800 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 63,412.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 63,412.50

G.I.17. Pemasangan 1 m2 dinding conblock HB20 campuran 1SP : 4PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3500 112,500.00 39,375.00
Tukang batu L.03 OH 0.1500 127,500.00 19,125.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0180 150,000.00 2,700.00
JUMLAH TENAGA KERJA 63,412.50
B BAHAN
HB-20 Buah 12.5000 -
Semen portland Kg 24.2600 -
Pasir pasang m3 0.7720 -
Besi angker diameter 8 Kg 0.2800 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 63,412.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 63,412.50

G.I.18. Pemasangan 1 m2 dinding conblock HB15 campuran 1SP : 3PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3200 112,500.00 36,000.00
Tukang batu L.03 OH 0.1200 127,500.00 15,300.00
Kepala tukang L.14 OH 0.0120 147,500.00 1,770.00
Mandor L.17 OH 0.0160 150,000.00 2,400.00
JUMLAH TENAGA KERJA 55,470.00
B BAHAN
HB-15 Buah 12.5000 -
Semen portland Kg 22.7400 -
Pasir pasang m3 0.5500 -
Besi angker diameter 8 Kg 0.2800 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 55,470.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 55,470.00

G.I.19. Pemasangan 1 m2 dinding conblock HB15 campuran 1SP : 4PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3200 112,500.00 36,000.00
Tukang batu L.03 OH 0.1200 127,500.00 15,300.00
Kepala tukang L.14 OH 0.0120 147,500.00 1,770.00
Mandor L.17 OH 0.0160 150,000.00 2,400.00
JUMLAH TENAGA KERJA 55,470.00
B BAHAN
HB-15 Buah 12.5000 -
Semen portland Kg 18.2000 -
Pasir pasang m3 0.5820 -
Besi angker diameter 8 Kg 0.2800 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 55,470.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 55,470.00

G.I.20. Pemasangan 1 m2 dinding conblock HB10 campuran 1SP : 3PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 50,225.00
B BAHAN
HB-10 Buah 12.5000 -
Semen portland Kg 15.1600 -
Pasir pasang m3 0.3640 -
Besi angker diameter 8 Kg 0.2800 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,225.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 50,225.00
Hb10 : Hollow Block tebal 10 cm

G.I.21. Pemasangan 1 m2 dinding conblock HB10 campuran 1SP : 4PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.000
Tukang batu L.03 OH 0.1000 127,500.00 12,750.000
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.000
Mandor L.17 OH 0.0150 150,000.00 2,250.000
JUMLAH TENAGA KERJA 50,225.000
B BAHAN
HB-10 Buah 12.5000 2,400.000 30,000.000
Semen portland Kg 12.1300 1,325.000 16,072.250
Pasir pasang m3 0.3880 240,000.000 93,120.000
Besi angker diameter 8 Kg 0.2800 11,708.861 3,278.481
JUMLAH HARGA BAHAN 142,470.731
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 192,695.731


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 192,695.73
HB10 : Hollow Block tebal 10cm

G.I.22. Pemasangan 1 m2 dinding terawang (rooster) 12x11x24 campuran 1SP : 3PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 50,225.00
B BAHAN
Bata rooster Buah 30.0000 -
Semen portland Kg 11.0000 -
Pasir pasang m3 0.0350 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,225.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 50,225.00

G.I.23. Pemasangan 1 m2 dinding terawang (rooster) 12x11x24 campuran 1SP : 4PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 50,225.00
B BAHAN
Bata rooster Buah 30.0000 -
Semen portland Kg 11.0000 -
Pasir pasang m3 0.0350 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,225.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 50,225.00

G.I.24. Pemasangan 1 m2 dinding bata berongga ekspose 12x11x24 campuran 1SP : 3PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1500 127,500.00 19,125.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 57,337.50
B BAHAN
Bata rooster Buah 70.0000 -
Semen portland Kg 14.0000 -
Pasir pasang m3 0.0320 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,337.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 57,337.50

G.I.25. Pemasangan 1 m2 dinding bata ringan tebal 7,5 cm dengan mortar siap pakai
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6700 112,500.00 75,375.00
Tukang batu L.03 OH 1.3000 127,500.00 165,750.00
Kepala tukang L.14 OH 0.1300 147,500.00 19,175.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 260,750.00
B BAHAN
Bata ringan tebal 7.5 cm Buah 8.4000 -
Mortar siap pakai Kg 0.4730 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan % 0.1000 - -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 260,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 260,750.00

G.I.26. Pemasangan 1 m2 dinding bata ringan tebal 10 cm dengan mortar siap pakai
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6710 112,500.00 75,487.50
Tukang batu L.03 OH 1.3000 127,500.00 165,750.00
Kepala tukang L.14 OH 0.1300 147,500.00 19,175.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 260,862.50
B BAHAN
Bata ringan tebal 10 cm Buah 8.4000 -
Mortar siap pakai Kg 0.0630 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan % 0.1000 - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 260,862.50
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 260,862.50

II (SNI-03-6897-2002)
G.II.1. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 1PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6500 112,500.00 73,125.00
Tukang batu L.03 OH 0.2000 127,500.00 25,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0300 150,000.00 4,500.00
JUMLAH TENAGA KERJA 106,075.00
B BAHAN
Bata merah Buah 140.0000 -
Semen portland Kg 64.0300 -
Pasir pasang m3 0.0590 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 106,075.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 106,075.00

G.II.2. Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 1PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3200 112,500.00 36,000.00
Tukang batu L.03 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 52,475.00
B BAHAN
Bata merah Buah 70.0000 -
Semen portland Kg 27.8000 -
Pasir pasang m3 0.0280 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 52,475.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 52,475.00

G.II.3. Pemasangan 1 m2 dinding conblock CB20


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3700 112,500.00 41,625.00
Tukang batu L.03 OH 0.1570 127,500.00 20,017.50
Tukang besi L.05 OH 0.0070 127,500.00 892.50
Kepala tukang L.14 OH 0.0164 147,500.00 2,419.00
Mandor L.17 OH 0.0185 150,000.00 2,775.00
JUMLAH TENAGA KERJA 67,729.00
B BAHAN
Concrete block CB20 Buah 12.5000 -
Semen portland Kg 14.0500 -
Pasir beton m3 0.0040 -
Pasir pasang m3 0.0420 -
Besi beton polos Kg 3.8700 -
Paku biasa 2" - 5" Kg 0.0060 -
Kayu terentang Kg 0.0010 -
Kawat beton Kg 0.0300 -
Koral beton Kg 0.0050 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 67,729.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 67,729.00

G.II.4. Pemasangan 1 m2 dinding conblock CB15


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3400 112,500.00 38,250.00
Tukang batu L.03 OH 0.1300 127,500.00 16,575.00
Tukang besi L.05 OH 0.0070 127,500.00 892.50
Kepala tukang L.14 OH 0.0137 147,500.00 2,020.75
Mandor L.17 OH 0.0170 150,000.00 2,550.00
JUMLAH TENAGA KERJA 60,288.25
B BAHAN
Concrete block CB15 Buah 12.5000 -
Semen portland Kg 10.4600 -
Pasir beton m3 0.0030 -
Pasir pasang m3 0.0320 -
Besi beton polos Kg 0.8700 -
Paku biasa 2" - 5" Kg 0.0040 -
Kayu terentang Kg 0.0010 -
Kawat beton Kg 0.0200 -
Koral beton Kg 0.0040 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 60,288.25


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 60,288.25

G.II.5. Pemasangan 1 m2 dinding conblock CB10


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3400 112,500.00 38,250.00
Tukang batu L.03 OH 0.1070 127,500.00 13,642.50
Tukang besi L.05 OH 0.0070 127,500.00 892.50
Kepala tukang L.14 OH 0.0114 147,500.00 1,681.50
Mandor L.17 OH 0.0170 150,000.00 2,550.00
JUMLAH TENAGA KERJA 57,016.50
B BAHAN
Concrete block CB10 Buah 12.5000 -
Semen portland Kg 7.2000 -
Pasir beton m3 0.0020 -
Pasir pasang m3 0.0210 -
Besi beton polos Kg 2.5400 -
Paku biasa 2" - 5" Kg 0.0030 -
Kayu terentang Kg 0.0010 -
Kawat beton Kg 0.0150 -
Koral beton Kg 0.0030 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,016.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 57,016.50

G.II.6. Pemasangan 1 m2 dinding lantai


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang batu L.03 OH 0.0300 127,500.00 3,825.00
Tukang besi L.05 OH 0.0300 127,500.00 3,825.00
Kepala tukang L.14 OH 0.0060 147,500.00 885.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 20,535.00
B BAHAN
Bondbea, 40x20x20 cm Buah 2.5000 -
Semen portland Kg 5.1000 -
Pasir beton m3 0.0800 -
Besi beton polos Kg 1.5000 -
Koral beton m3 0.1500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 20,535.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 20,535.00

G.II.7. Pemasangan 1 m2 dinding anyaman bambu, rangka kayu


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.0500 132,500.00 6,625.00
Kepala tukang L.14 OH 0.0050 147,500.00 737.50
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 18,912.50
B BAHAN
Bilik bambu 0.1500 -
Kayu 5/7 m3 0.0140 -
Paku kg 0.0120
List kayu 2/4 m3 0.0030 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 18,912.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 18,912.50

III (SNI-6897-2008)
G.III.1. Pemasangan 1 m2 dinding bata berongga ekspose 5x11x24 campuran 1SP : 3PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1500 127,500.00 19,125.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 57,337.50
B BAHAN
Bata berongga Buah 70.0000 -
Semen portland Kg 14.0000 -
Pasir pasang m3 32.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,337.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 57,337.50

IV ANALISA SENDIRI
G.IV.1. Pemasangan 1 buah loster ukir paras 30 x 30 cm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang batu L.03 OH 0.0500 127,500.00 6,375.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 21,350.00
B BAHAN
Loster ukir paras Buah 1.0000 -
Semen portland Kg 5.2500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 21,350.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 21,350.00
H HARGA SATUAN PEKERJAAN PLESTERAN
I (PERMEN NOMOR 28/PRT/M/2016)
H.I.1. Pemasangan 1 m2 plesteran 1SP : 1PP tebal 15 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1500 127,500.00 19,125.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 57,337.50
B BAHAN
Semen portland Kg 15.5040 -
Pasir pasang m3 0.0160 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,337.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 57,337.50

H.I.2. Pemasangan 1 m2 plesteran 1SP : 2PP tebal 15 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1500 127,500.00 19,125.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 57,337.50
B BAHAN
Semen portland Kg 10.2240 -
Pasir pasang m3 0.0200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,337.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 57,337.50

H.I.3. Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1500 127,500.00 19,125.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 57,337.50
B BAHAN
Semen portland Kg 7.7760 -
Pasir pasang m3 0.0230 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,337.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 57,337.50

H.I.4. Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1500 127,500.00 19,125.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 57,337.50
B BAHAN
Semen portland Kg 6.2400 -
Pasir pasang m3 0.0240 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,337.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 57,337.50

H.I.5. Pemasangan 1 m2 plesteran 1SP : 5PP tebal 15 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1500 127,500.00 19,125.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 57,337.50
B BAHAN
Semen portland Kg 5.1840 -
Pasir pasang m3 0.0260 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,337.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 57,337.50

H.I.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1500 127,500.00 19,125.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 57,337.50
B BAHAN
Semen portland Kg 4.4160 -
Pasir pasang m3 0.0270 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,337.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 57,337.50

H.I.7. Pemasangan 1 m2 plesteran 1SP : 7PP tebal 15 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1500 127,500.00 19,125.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 57,337.50
B BAHAN
Semen portland Kg 3.9360 -
Pasir pasang m3 0.0280 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,337.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 57,337.50

H.I.8. Pemasangan 1 m2 plesteran 1SP : 8PP tebal 15 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1500 127,500.00 19,125.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 57,337.50
B BAHAN
Semen portland Kg 3.4560 -
Pasir pasang m3 0.0290 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,337.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 57,337.50

H.I.9. Pemasangan 1 m2 plesteran 1SP : 1/2KP : 3PP tebal 15 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3600 112,500.00 40,500.00
Tukang batu L.03 OH 0.1200 127,500.00 15,300.00
Kepala tukang L.14 OH 0.0120 147,500.00 1,770.00
Mandor L.17 OH 0.0180 150,000.00 2,700.00
JUMLAH TENAGA KERJA 60,270.00
B BAHAN
Semen portland Kg 5.7600 -
Kapur padam m3 0.0030 -
Pasir pasang m3 0.0130 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 60,270.00
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 60,270.00

H.I.10. Pemasangan 1 m2 plesteran 1SP : 2KP : 8PP tebal 15 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3600 112,500.00 40,500.00
Tukang batu L.03 OH 0.1200 127,500.00 15,300.00
Kepala tukang L.14 OH 0.0120 147,500.00 1,770.00
Mandor L.17 OH 0.0180 150,000.00 2,700.00
JUMLAH TENAGA KERJA 60,270.00
B BAHAN
Semen portland Kg 3.0000 -
Kapur padam m3 0.0050 -
Pasir pasang m3 0.0200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 60,270.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 60,270.00

H.I.11. Pemasangan 1 m2 plesteran 1SP : 1KP : 1PP tebal 15 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3600 112,500.00 40,500.00
Tukang batu L.03 OH 0.1200 127,500.00 15,300.00
Kepala tukang L.14 OH 0.0120 147,500.00 1,770.00
Mandor L.17 OH 0.0180 150,000.00 2,700.00
JUMLAH TENAGA KERJA 60,270.00
B BAHAN
Semen portland m3 0.0090 -
Kapur padam m3 0.0090 -
Pasir pasang m3 0.0090 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 60,270.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 60,270.00
H.I.12. Pemasangan 1 m2 plesteran 1SP : 1KP : 2PP tebal 15 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3600 112,500.00 40,500.00
Tukang batu L.03 OH 0.1200 127,500.00 15,300.00
Kepala tukang L.14 OH 0.0120 147,500.00 1,770.00
Mandor L.17 OH 0.0180 150,000.00 2,700.00
JUMLAH TENAGA KERJA 60,270.00
B BAHAN
Semen portland m3 0.0070 -
Kapur padam m3 0.0070 -
Pasir pasang m3 0.0150 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 60,270.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 60,270.00

H.I.13. Pemasangan 1 m2 plesteran 1SP : 1PP tebal 20 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4000 112,500.00 45,000.00
Tukang batu L.03 OH 0.2000 127,500.00 25,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0220 150,000.00 3,300.00
JUMLAH TENAGA KERJA 76,750.00
B BAHAN
Semen portland Kg 13.6320 1,325.00 18,062.40
Pasir pasang m3 0.0270 240,000.00 6,480.00
JUMLAH HARGA BAHAN 24,542.40
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 101,292.40


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 101,292.40

H.I.14. Pemasangan 1 m2 plesteran 1SP : 3PP tebal 20 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2600 112,500.00 29,250.00
Tukang batu L.03 OH 0.2000 127,500.00 25,500.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 58,175.00
B BAHAN
Semen portland Kg 10.3680 -
Pasir pasang m3 0.0310 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 58,175.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 58,175.00

H.I.15. Pemasangan 1 m2 plesteran 1SP : 4PP tebal 20 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4000 112,500.00 45,000.00
Tukang batu L.03 OH 0.2000 127,500.00 25,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0220 150,000.00 3,300.00
JUMLAH TENAGA KERJA 76,750.00
B BAHAN
Semen portland Kg 8.3200 -
Pasir pasang m3 0.0320 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 76,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 76,750.00

H.I.16. Pemasangan 1 m2 plesteran 1SP : 5PP tebal 20 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4000 112,500.00 45,000.00
Tukang batu L.03 OH 0.2000 127,500.00 25,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0220 150,000.00 3,300.00
JUMLAH TENAGA KERJA 76,750.00
B BAHAN
Semen portland Kg 6.9120 -
Pasir pasang m3 0.0350 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 76,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 76,750.00

H.I.17. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 20 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4000 112,500.00 45,000.00
Tukang batu L.03 OH 0.2000 127,500.00 25,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0220 150,000.00 3,300.00
JUMLAH TENAGA KERJA 76,750.00
B BAHAN
Semen portland Kg 5.8880 -
Pasir pasang m3 0.0360 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 76,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 76,750.00

H.I.18. Pemasangan 1 m2 plesteran 1SP : 1KP : 2PP tebal 20 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4400 112,500.00 49,500.00
Tukang batu L.03 OH 0.2000 127,500.00 25,500.00
Kepala tukang L.14 OH 0.0220 147,500.00 3,245.00
Mandor L.17 OH 0.0220 150,000.00 3,300.00
JUMLAH TENAGA KERJA 81,545.00
B BAHAN
Semen portland m3 0.0090 -
Kapur padam m3 0.0090 -
Pasir pasang m3 0.0180 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 81,545.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 81,545.00

H.I.19. Pemasangan 1 m2 berapen 1SP : 5PP tebal 15 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang batu L.03 OH 0.0750 127,500.00 9,562.50
Kepala tukang L.14 OH 0.0080 147,500.00 1,180.00
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 28,817.50
B BAHAN
Semen portland Kg 5.1840 -
Pasir pasang m3 0.0260 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 28,817.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 28,817.50

H.I.20. Pemasangan 1 m1 plesteran skoning 1SP : 3PP 10 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0800 112,500.00 9,000.00
Tukang batu L.03 OH 0.4000 127,500.00 51,000.00
Kepala tukang L.14 OH 0.0400 147,500.00 5,900.00
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 66,500.00
B BAHAN
Semen portland Kg 0.5000 -
Pasir pasang m3 0.0130 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 66,500.00
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 66,500.00

H.I.21. Pemasangan 1 m2 plesteran granit 1SP : 2 granit tebal 1 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4500 112,500.00 50,625.00
Tukang batu L.03 OH 0.2250 127,500.00 28,687.50
Kepala tukang L.14 OH 0.0230 147,500.00 3,392.50
Mandor L.17 OH 0.0230 150,000.00 3,450.00
JUMLAH TENAGA KERJA 86,155.00
B BAHAN
Semen portland Kg 10.0000 -
Batu granit Kg 15.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 86,155.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 86,155.00

H.I.22. Pemasangan 1 m2 plesteran traso 1SP : 2 traso tebal 1 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4500 112,500.00 50,625.00
Tukang batu L.03 OH 0.2250 127,500.00 28,687.50
Kepala tukang L.14 OH 0.0230 147,500.00 3,392.50
Mandor L.17 OH 0.0230 150,000.00 3,450.00
JUMLAH TENAGA KERJA 86,155.00
B BAHAN
Semen portland Kg 10.0000 -
Batu traso Kg 15.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 86,155.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 86,155.00

H.I.23. Pemasangan 1 m2 plesteran ciprat 1SP : 2PP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 50,225.00
B BAHAN
Semen portland Kg 4.3200 1,325.00 5,724.00
Pasir pasang m3 0.0060 240,000.00 1,440.00
JUMLAH HARGA BAHAN 7,164.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,389.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 57,389.00

H.I.24. Pemasangan 1 m2 finishing siar pasangan bata merah


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang batu L.03 OH 0.0750 127,500.00 9,562.50
Kepala tukang L.14 OH 0.0080 147,500.00 1,180.00
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 28,817.50
B BAHAN
Semen portland Kg 3.1080 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 28,817.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 28,817.50

H.I.25. Pemasangan 1 m2 finishing siar pasangan conblock ekspose


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0700 112,500.00 7,875.00
Tukang batu L.03 OH 0.0350 127,500.00 4,462.50
Kepala tukang L.14 OH 0.0040 147,500.00 590.00
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 13,527.50
B BAHAN
Semen portland Kg 1.6000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 13,527.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 13,527.50

H.I.26. Pemasangan 1 m2 finishing siar pasangan batu kali, campuran 1SP : 2PP
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.1500 127,500.00 19,125.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 57,337.50
B BAHAN
Semen portland Kg 6.3400 -
Pasir pasang m3 0.0120 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,337.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 57,337.50

H.I.27. Pemasangan 1 m2 acian


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang batu L.03 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 38,225.00
B BAHAN
Semen portland Kg 3.2500 1,325.00 4,306.25
JUMLAH HARGA BAHAN 4,306.25
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 42,531.25


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 42,531.25

H.I.28. Pemasangan 1 m2 plesteran dengan mortar siap pakai (MSP)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 112,500.00 -
Tukang batu L.03 OH 127,500.00 -
Kepala tukang L.14 OH 147,500.00 -
Mandor L.17 OH 150,000.00 -
JUMLAH TENAGA KERJA -
B BAHAN
MSP Kg -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp -

H.I.29. Pemasangan 1 m2 plesteran acian mortar siap pakai (MSP)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 112,500.00 -
Tukang batu L.03 OH 127,500.00 -
Kepala tukang L.14 OH 147,500.00 -
Mandor L.17 OH 150,000.00 -
JUMLAH TENAGA KERJA -
B BAHAN
MSP Kg -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) -
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp -
I HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
I (PERMEN NOMOR 28/PRT/M/2016)
I.I.1. Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 40 cm x 40 cm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Tukang batu L.03 OH 0.1250 127,500.00 15,937.50
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 47,930.00
B BAHAN
Ubin abu-abu 40x40 Buah 6.6300 -
Semen portland Kg 9.8000 -
Pasir pasang m3 0.0450 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 47,930.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 47,930.00

I.I.2. Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 30 cm x 30 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Tukang batu L.03 OH 0.1250 127,500.00 15,937.50
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 47,930.00
B BAHAN
Ubin abu-abu 40x40 Buah 11.8700 -
Semen portland Kg 10.0000 -
Pasir pasang m3 0.0450 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 47,930.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 47,930.00

I.I.3. Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 20 cm x 20 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2700 112,500.00 30,375.00
Tukang batu L.03 OH 0.1350 127,500.00 17,212.50
Kepala tukang L.14 OH 0.0140 147,500.00 2,065.00
Mandor L.17 OH 0.0140 150,000.00 2,100.00
JUMLAH TENAGA KERJA 51,752.50
B BAHAN
Ubin abu-abu 40x40 Buah 26.5000 -
Semen portland Kg 10.4000 -
Pasir pasang m3 0.0450 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 51,752.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 51,752.50

I.I.4. Pemasangan 1 m2 lantai ubin warna ukuran 40 cm x 40 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Tukang batu L.03 OH 0.1250 127,500.00 15,937.50
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 47,930.00
B BAHAN
Ubin warna Buah 6.6300 -
Semen portland Kg 9.8000 -
Semen warna Kg 0.6000 -
Pasir pasang m3 0.0450 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 47,930.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 47,930.00

I.I.5. Pemasangan 1 m2 lantai ubin warna ukuran 30 cm x 30 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2600 112,500.00 29,250.00
Tukang batu L.03 OH 0.1300 127,500.00 16,575.00
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 49,692.50
B BAHAN
Ubin warna Buah 11.8700 -
Semen portland Kg 10.0000 -
Semen warna Kg 0.6000 -
Pasir pasang m3 0.0450 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 49,692.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 49,692.50

I.I.6. Pemasangan 1 m2 lantai ubin warna ukuran 20 cm x 20 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2700 112,500.00 30,375.00
Tukang batu L.03 OH 0.1350 127,500.00 17,212.50
Kepala tukang L.14 OH 0.0140 147,500.00 2,065.00
Mandor L.17 OH 0.0140 150,000.00 2,100.00
JUMLAH TENAGA KERJA 51,752.50
B BAHAN
Ubin warna Buah 26.5000 -
Semen portland Kg 10.4000 -
Semen warna Kg 1.6200 -
Pasir pasang m3 0.0450 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 51,752.50
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 51,752.50

I.I.7. Pemasangan 1 m2 lantai ubin teraso ukuran 40 cm x 40 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Tukang batu L.03 OH 0.1250 127,500.00 15,937.50
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 47,930.00
B BAHAN
Ubin teraso Buah 6.6300 -
Semen portland Kg 9.8000 -
Semen warna Kg 1.3000 -
Pasir pasang m3 0.0450 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 47,930.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 47,930.00

I.I.8. Pemasangan 1 m2 lantai ubin teraso ukuran 30 cm x 30 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2600 112,500.00 29,250.00
Tukang batu L.03 OH 0.1300 127,500.00 16,575.00
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 49,692.50
B BAHAN
Ubin teraso Buah 11.8700 -
Semen portland Kg 10.0000 -
Semen warna Kg 1.5000 -
Pasir pasang m3 0.0450 -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 49,692.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 49,692.50

I.I.9. Pemasangan 1 m2 lantai ubin granit ukuran 40 cm x 40 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Tukang batu L.03 OH 0.1250 127,500.00 15,937.50
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 47,930.00
B BAHAN
Ubin granit Buah 6.6300 -
Semen portland Kg 9.8000 -
Semen warna Kg 1.3000 -
Pasir pasang m3 0.0450 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 47,930.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 47,930.00

I.I.10. Pemasangan 1 m2 lantai ubin granit ukuran 30 cm x 30 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2600 112,500.00 29,250.00
Tukang batu L.03 OH 0.1300 127,500.00 16,575.00
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 49,692.50
B BAHAN
Ubin granit Buah 11.8700 -
Semen portland Kg 10.0000 -
Semen warna Kg 1.5000 -
Pasir pasang m3 0.0450 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 49,692.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 49,692.50

I.I.11. Pemasangan 1 m2 lantai ubin teralux ukuran 40 cm x 40 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Tukang batu L.03 OH 0.1250 127,500.00 15,937.50
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 47,930.00
B BAHAN
Ubin teralux Buah 6.6300 -
Semen portland Kg 9.8000 -
Semen warna Kg 1.3000 -
Pasir pasang m3 0.0450 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 47,930.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 47,930.00

I.I.12. Pemasangan 1 m2 lantai ubin teralux ukuran 30 cm x 30 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2600 112,500.00 29,250.00
Tukang batu L.03 OH 0.1300 127,500.00 16,575.00
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 49,692.50
B BAHAN
Ubin teralux Buah 11.8700 -
Semen portland Kg 10.0000 -
Semen warna Kg 1.5000 -
Pasir pasang m3 0.0450 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 49,692.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 49,692.50

I.I.13. Pemasangan 1 m2 lantai ubin teralux marmer ukuran 60 cm x 60 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2400 112,500.00 27,000.00
Tukang batu L.03 OH 0.1200 127,500.00 15,300.00
Kepala tukang L.14 OH 0.0120 147,500.00 1,770.00
Mandor L.17 OH 0.0120 150,000.00 1,800.00
JUMLAH TENAGA KERJA 45,870.00
B BAHAN
Ubin teralux marmer Buah 3.1000 -
Semen portland Kg 9.6000 -
Semen warna Kg 1.5000 -
Pasir pasang m3 0.0450 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 45,870.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 45,870.00

I.I.14. Pemasangan 1 m2 lantai ubin teralux marmer ukuran 40 cm x 40 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Tukang batu L.03 OH 0.1250 127,500.00 15,937.50
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 47,930.00
B BAHAN
Ubin teralux marmer Buah 6.6300 -
Semen portland Kg 9.8000 -
Semen warna Kg 1.3000 -
Pasir pasang m3 0.0450 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 47,930.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 47,930.00

I.I.15. Pemasangan 1 m2 lantai ubin teralux marmer ukuran 30 cm x 30 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2600 112,500.00 29,250.00
Tukang batu L.03 OH 0.1300 127,500.00 16,575.00
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 49,692.50
B BAHAN
Ubin teralux marmer Buah 11.8700 -
Semen portland Kg 10.0000 -
Semen warna Kg 1.5000 -
Pasir pasang m3 0.0450 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 49,692.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 49,692.50

I.I.16. Pemasangan 1 m1 plint ubin PC abu-abu ukuran 15 cm x 20 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 23,677.50
B BAHAN
Plint ubin PC Buah 5.3000 -
Semen portland Kg 1.6500 -
Pasir pasang m3 0.0040 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,677.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,677.50

I.I.17. Pemasangan 1 m1 plint ubin PC abu-abu ukuran 10 cm x 30 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 23,677.50
B BAHAN
Plint ubin PC Buah 3.5300 -
Semen portland Kg 1.2400 -
Pasir pasang m3 0.0030 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,677.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,677.50

I.I.18. Pemasangan 1 m1 plint ubin PC abu-abu ukuran 10 cm x 40 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 23,677.50
B BAHAN
Plint ubin PC Buah 2.6500 -
Semen portland Kg 1.2400 -
Pasir pasang m3 0.0030 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,677.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,677.50

I.I.19. Pemasangan 1 m1 plint ubin warna ukuran 10 cm x 20 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 23,677.50
B BAHAN
Plint ubin warna Buah 2.6500 -
Semen portland Kg 1.1400 -
Semen warna Kg 0.1500 -
Pasir pasang m3 0.0030 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,677.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,677.50

I.I.20. Pemasangan 1 m1 plint ubin warna ukuran 10 cm x 30 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 23,677.50
B BAHAN
Plint ubin warna Buah 3.5300 -
Semen portland Kg 1.1400 -
Semen warna Kg 0.1000 -
Pasir pasang m3 0.0030 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,677.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,677.50

I.I.21. Pemasangan 1 m1 plint ubin warna ukuran 10 cm x 40 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 23,677.50
B BAHAN
Plint ubin warna Buah 2.6500 -
Semen portland Kg 1.1400 -
Semen warna Kg 0.1000 -
Pasir pasang m3 0.0030 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,677.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,677.50

I.I.22. Pemasangan 1 m1 plint ubin teraso ukuran 10 cm x 30 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 23,677.50
B BAHAN
Plint ubin teraso Buah 3.5300 -
Semen portland Kg 1.1400 -
Semen warna Kg 0.1000 -
Pasir pasang m3 0.0030 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,677.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,677.50

I.I.23. Pemasangan 1 m1 plint ubin teraso ukuran 10 cm x 40 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 23,677.50
B BAHAN
Plint ubin teraso Buah 2.6500 -
Semen portland Kg 1.1400 -
Semen warna Kg 0.1000 -
Pasir pasang m3 0.0030 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,677.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,677.50

I.I.24. Pemasangan 1 m1 plint ubin granit ukuran 10 cm x 40 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 23,677.50
B BAHAN
Plint ubin granit Buah 2.6500 -
Semen portland Kg 1.1400 -
Semen warna Kg 0.1000 -
Pasir pasang m3 0.0030 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,677.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,677.50

I.I.25. Pemasangan 1 m1 plint ubin granit ukuran 10 cm x 30 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 23,677.50
B BAHAN
Plint ubin granit Buah 3.5300 -
Semen portland Kg 1.1400 -
Semen warna Kg 0.1000 -
Pasir pasang m3 0.0030 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,677.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,677.50

I.I.26. Pemasangan 1 m1 plint ubin teralux kerang ukuran 10 cm x 40 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 23,677.50
B BAHAN
Plint teralux kerang Buah 2.6300 -
Semen portland Kg 1.1400 -
Semen warna Kg 0.1000 -
Pasir pasang m3 0.0030 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,677.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,677.50

I.I.27. Pemasangan 1 m1 plint ubin teralux kerang ukuran 10 cm x 30 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 23,677.50
B BAHAN
Plint teralux kerang Buah 3.5300 -
Semen portland Kg 1.1400 -
Semen warna Kg 0.1000 -
Pasir pasang m3 0.0030 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,677.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,677.50
I.I.28. Pemasangan 1 m1 plint ubin teralux marmer ukuran 10 cm x 60 cm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 23,677.50
B BAHAN
Plint teralux marmer Buah 1.7000 -
Semen portland Kg 1.1400 -
Semen warna Kg 0.1000 -
Pasir pasang m3 0.0030 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,677.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,677.50

I.I.29. Pemasangan 1 m1 plint ubin teralux marmer ukuran 10 cm x 40 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 23,677.50
B BAHAN
Plint teralux marmer Buah 2.6500 -
Semen portland Kg 1.1400 -
Semen warna Kg 0.1000 -
Pasir pasang m3 0.0030 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,677.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,677.50

I.I.30. Pemasangan 1 m1 plint ubin teralux marmer ukuran 10 cm x 30 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 23,677.50
B BAHAN
Plint teralux marmer Buah 3.5300 -
Semen portland Kg 1.1400 -
Semen warna Kg 0.1000 -
Pasir pasang m3 0.0030 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,677.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,677.50

I.I.31. Pemasangan 1 m2 lantai teraso cor di tempat, tebal 3 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3600 112,500.00 40,500.00
Tukang batu L.03 OH 0.1800 127,500.00 22,950.00
Kepala tukang L.14 OH 0.0180 147,500.00 2,655.00
Mandor L.17 OH 0.0180 150,000.00 2,700.00
JUMLAH TENAGA KERJA 68,805.00
B BAHAN
Teraso cor m3 0.0360 -
Semen warna Kg 0.1000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 68,805.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 68,805.00

I.I.32. Pemasangan 1 m2 lantai keramik artistik 10 cm x 20 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7000 112,500.00 78,750.00
Tukang batu L.03 OH 0.3500 127,500.00 44,625.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 133,787.50
B BAHAN
Ubin keramik Buah 53.0000 -
Semen portland Kg 8.1900 -
Pasir pasang m3 0.0450 -
Semen warna Kg 2.7500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 133,787.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 133,787.50

I.I.33. Pemasangan 1 m2 lantai keramik artistik 10 cm x 10 cm atau 5 cm x 20 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7000 112,500.00 78,750.00
Tukang batu L.03 OH 0.3500 127,500.00 44,625.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 133,787.50
B BAHAN
Ubin keramik Buah 106.0000 -
Semen portland Kg 8.1900 -
Pasir pasang m3 0.0450 -
Semen warna Kg 3.2000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 133,787.50
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 133,787.50

I.I.34. Pemasangan 1 m2 lantai keramik ukuran 33 cm x 33 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7000 112,500.00 78,750.00
Tukang batu L.03 OH 0.3500 127,500.00 44,625.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 133,787.50
B BAHAN
Ubin keramik Doos 1.0500 -
Semen portland Kg 8.1900 -
Pasir pasang m3 0.0450 -
Semen warna Kg 0.5000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 133,787.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 133,787.50

I.I.35. Pemasangan 1 m2 lantai keramik ukuran 30 cm x 30 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7000 112,500.00 78,750.00
Tukang batu L.03 OH 0.3500 127,500.00 44,625.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 133,787.50
B BAHAN
Ubin keramik Doos 1.0500 -
Semen portland Kg 10.0000 -
Pasir pasang m3 0.0450 -
Semen warna Kg 0.5000 -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 133,787.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 133,787.50

I.I.36. Pemasangan 1 m2 lantai keramik ukuran 20 cm x 20 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.700 112,500.00 78,750.00
Tukang batu L.03 OH 0.350 127,500.00 44,625.00
Kepala tukang L.14 OH 0.035 147,500.00 5,162.50
Mandor L.17 OH 0.035 150,000.00 5,250.00
JUMLAH TENAGA KERJA 133,787.50
B BAHAN
Ubin keramik Doos 1.050 -
Semen portland Kg 10.400 -
Pasir pasang m3 0.045 -
Semen warna Kg 0.500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 133,787.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 133,787.50

I.I.37. Pemasangan 1 m2 lantai keramik ukuran 10 cm x 33 cm untuk variasi/border


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0500 112,500.00 118,125.00
Tukang batu L.03 OH 0.5250 127,500.00 66,937.50
Kepala tukang L.14 OH 0.0530 147,500.00 7,817.50
Mandor L.17 OH 0.0530 150,000.00 7,950.00
JUMLAH TENAGA KERJA 200,830.00
B BAHAN
Ubin keramik Buah 33.0000 -
Semen portland Kg 9.8000 -
Pasir pasang m3 0.0450 -
Semen warna Kg 4.3700 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 200,830.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 200,830.00

I.I.38. Pemasangan 1 m2 lantai keramik mozaik ukuran 30 cm x 30 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7000 112,500.00 78,750.00
Tukang batu L.03 OH 0.3500 127,500.00 44,625.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 133,787.50
B BAHAN
Ubin keramik Buah 11.8700 -
Semen portland Kg 14.1500 -
Pasir pasang m3 0.0390 -
Semen warna Kg 2.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 133,787.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 133,787.50

I.I.39. Pemasangan 1 m1 plint keramik ukuran 10 cm x 20 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 27,512.50
B BAHAN
Plint keramik Buah 5.3000 -
Semen portland Kg 1.1400 -
Pasir pasang m3 0.0030 -
Semen warna Kg 0.0250 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,512.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,512.50

I.I.40. Pemasangan 1 m1 plint keramik ukuran 10 cm x 10 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 27,512.50
B BAHAN
Plint keramik Buah 10.6000 -
Semen portland Kg 1.1400 -
Pasir pasang m3 0.0030 -
Semen warna Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,512.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,512.50

I.I.41. Pemasangan 1 m1 plint keramik ukuran 5 cm x 20 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 27,512.50
B BAHAN
Plint keramik Buah 5.3000 -
Semen portland Kg 0.5700 -
Pasir pasang m3 0.0015 -
Semen warna Kg 0.0130 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,512.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,512.50

I.I.42. Pemasangan 1 m1 plint internal cove artistik 5 cm x 5 cm x 20 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7500 112,500.00 84,375.00
Tukang batu L.03 OH 0.7500 127,500.00 95,625.00
Kepala tukang L.14 OH 0.0750 147,500.00 11,062.50
Mandor L.17 OH 0.0380 150,000.00 5,700.00
JUMLAH TENAGA KERJA 196,762.50
B BAHAN
Internal cove Buah 5.3000 -
Semen portland Kg 1.1400 -
Pasir pasang m3 0.0030 -
Semen warna Kg 0.1000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 196,762.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 196,762.50

I.I.43. Pemasangan 1 m2 lantai marmer ukuran 100 cm x 100 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7000 112,500.00 78,750.00
Tukang batu L.03 OH 0.3500 127,500.00 44,625.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 133,787.50
B BAHAN
Marmer Buah 1.0600 -
Semen portland Kg 8.1900 -
Pasir pasang m3 0.0450 -
Semen warna Kg 0.1340 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 133,787.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 133,787.50

I.I.44. Pemasangan 1 m2 lantai karpet


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1700 112,500.00 19,125.00
Tukang kayu L.04 OH 0.1700 132,500.00 22,525.00
Kepala tukang L.14 OH 0.0170 147,500.00 2,507.50
Mandor L.17 OH 0.0090 150,000.00 1,350.00
JUMLAH TENAGA KERJA 45,507.50
B BAHAN
Karpet m2 1.0500 -
Lem Kg 0.3500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 45,507.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 45,507.50

I.I.45. Pemasangan 1 m2 underlayer (pelapis bawah karpet)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1200 112,500.00 13,500.00
Tukang kayu L.04 OH 0.1200 132,500.00 15,900.00
Kepala tukang L.14 OH 0.0120 147,500.00 1,770.00
Mandor L.17 OH 0.0060 150,000.00 900.00
JUMLAH TENAGA KERJA 32,070.00
B BAHAN
Underlayer m2 1.0500 -
Lem Kg 0.3500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 32,070.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 32,070.00

I.I.46. Pemasangan 1 m2 lantai parquet kayu


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7000 112,500.00 78,750.00
Tukang kayu L.04 OH 0.3500 132,500.00 46,375.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 135,537.50
B BAHAN
Parquet m2 1.0500 -
Lem Kg 0.6000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 135,537.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 135,537.50

I.I.47. Pemasangan 1 m2 lantai kayu gymfloor


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7000 112,500.00 78,750.00
Tukang kayu L.04 OH 0.3500 132,500.00 46,375.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 135,537.50
B BAHAN
Parquet m2 1.0500 -
Lem Kg 0.6000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 135,537.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 135,537.50

I.I.48. Pemasangan 1 m2 dinding porselen 11 cm x 11 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang batu L.03 OH 0.5000 127,500.00 63,750.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 191,125.00
B BAHAN
Dinding porselen 11x11 Doos 1.0500 -
Semen portland Kg 9.3000 -
Pasir pasang m3 0.0180 -
Semen warna Kg 0.5000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 191,125.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 191,125.00

I.I.49. Pemasangan 1 m2 dinding porselen 10 cm x 20 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9000 112,500.00 101,250.00
Tukang batu L.03 OH 0.4500 127,500.00 57,375.00
Kepala tukang L.14 OH 0.0450 147,500.00 6,637.50
Mandor L.17 OH 0.0450 150,000.00 6,750.00
JUMLAH TENAGA KERJA 172,012.50
B BAHAN
Porslen Buah 53.0000 -
Semen portland Kg 9.3000 -
Pasir pasang m3 0.0180 -
Semen warna Kg 2.7500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 172,012.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 172,012.50

I.I.50. Pemasangan 1 m2 dinding porselen 20 cm x 20 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9000 112,500.00 101,250.00
Tukang batu L.03 OH 0.4500 127,500.00 57,375.00
Kepala tukang L.14 OH 0.0450 147,500.00 6,637.50
Mandor L.17 OH 0.0450 150,000.00 6,750.00
JUMLAH TENAGA KERJA 172,012.50
B BAHAN
Porslen Buah 26.0000 -
Semen portland Kg 9.3000 -
Pasir pasang m3 0.0180 -
Semen warna Kg 1.9400 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 172,012.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 172,012.50

I.I.51. Pemasangan 1 m2 dinding keramik artistik 10 cm x 20 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9000 112,500.00 101,250.00
Tukang batu L.03 OH 0.4500 127,500.00 57,375.00
Kepala tukang L.14 OH 0.0450 147,500.00 6,637.50
Mandor L.17 OH 0.0450 150,000.00 6,750.00
JUMLAH TENAGA KERJA 172,012.50
B BAHAN
Keramik artistik Buah 53.0000 -
Semen portland Kg 9.3000 -
Pasir pasang m3 0.0180 -
Semen warna Kg 2.7500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 172,012.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 172,012.50

I.I.52. Pemasangan 1 m2 dinding keramik artistik 5 cm x 20 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9000 112,500.00 101,250.00
Tukang batu L.03 OH 0.4500 127,500.00 57,375.00
Kepala tukang L.14 OH 0.0450 147,500.00 6,637.50
Mandor L.17 OH 0.0450 150,000.00 6,750.00
JUMLAH TENAGA KERJA 172,012.50
B BAHAN
Keramik artistik Buah 106.0000 -
Semen portland Kg 9.3000 -
Pasir pasang m3 0.0180 -
Semen warna Kg 2.9000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 172,012.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 172,012.50

I.I.53. Pemasangan 1 m2 dinding keramik 10 cm x 20 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9000 112,500.00 101,250.00
Tukang batu L.03 OH 0.4500 127,500.00 57,375.00
Kepala tukang L.14 OH 0.0450 147,500.00 6,637.50
Mandor L.17 OH 0.0450 150,000.00 6,750.00
JUMLAH TENAGA KERJA 172,012.50
B BAHAN
Keramik artistik Buah 53.0000 -
Semen portland Kg 9.3000 -
Pasir pasang m3 0.0180 -
Semen warna Kg 2.7500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 172,012.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 172,012.50

I.I.54. Pemasangan 1 m2 dinding keramik 20 cm x 20 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9000 112,500.00 101,250.00
Tukang batu L.03 OH 0.4500 127,500.00 57,375.00
Kepala tukang L.14 OH 0.0450 147,500.00 6,637.50
Mandor L.17 OH 0.0450 150,000.00 6,750.00
JUMLAH TENAGA KERJA 172,012.50
B BAHAN
Keramik artistik Buah 26.5000 -
Semen portland Kg 9.3000 -
Pasir pasang m3 0.0180 -
Semen warna Kg 1.9400 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 172,012.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 172,012.50

I.I.55. Pemasangan 1 m2 dinding marmer 100 cm x 100 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.3000 112,500.00 146,250.00
Tukang batu L.03 OH 0.6500 127,500.00 82,875.00
Kepala tukang L.14 OH 0.0650 147,500.00 9,587.50
Mandor L.17 OH 0.0650 150,000.00 9,750.00
JUMLAH TENAGA KERJA 248,462.50
B BAHAN
Marmer Buah 1.0600 -
Semen portland Kg 12.4400 -
Pasir pasang m3 0.0250 -
Semen warna Kg 0.6500 -
Paku 12 cm Buah 3.0300 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 248,462.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 248,462.50

I.I.56. Pemasangan 1 m2 dinding bata pelapis 3 cm x 7 cm x 24 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang batu L.03 OH 0.5000 127,500.00 63,750.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 191,125.00
B BAHAN
Bata pelapis Buah 63.0000 -
Semen portland Kg 12.4400 -
Pasir pasang m3 0.0250 -
Semen warna Kg 2.7500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 191,125.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 191,125.00

I.I.57. Pemasangan 1 m2 dinding batu paras


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7000 112,500.00 78,750.00
Tukang batu L.03 OH 0.3500 127,500.00 44,625.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 133,787.50
B BAHAN
Batu paras m2 1.1000 -
Semen portland Kg 11.7500 -
Pasir pasang m3 0.0350 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 133,787.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 133,787.50

I.I.58. Pemasangan 1 m2 dinding batu tempel hitam


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7000 112,500.00 78,750.00
Tukang batu L.03 OH 0.3500 127,500.00 44,625.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 133,787.50
B BAHAN
Batu tempel hitam m2 1.1000 -
Semen portland Kg 11.7500 -
Pasir pasang m3 0.0350 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 133,787.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 133,787.50

I.I.59. Pemasangan 1 m2 lantai vinyl ukuran 30 cm x 30 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang batu L.03 OH 0.1500 127,500.00 19,125.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 39,412.50
B BAHAN
Vinyl Buah 11.8700 -
Lem Kg 0.3500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 39,412.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 39,412.50

I.I.60. Pemasangan 1 m2 wallpaper lebar 50 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3500 112,500.00 39,375.00
Tukang batu L.03 OH 0.1750 127,500.00 22,312.50
Kepala tukang L.14 OH 0.0170 147,500.00 2,507.50
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 64,495.00
B BAHAN
Wallpaper m1 2.2000 -
Lem Kg 0.2500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 64,495.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 64,495.00

I.I.61. Pemasangan 1 m2 floor harderner


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1200 112,500.00 13,500.00
Tukang batu L.03 OH 0.1200 127,500.00 15,300.00
Kepala tukang L.14 OH 0.0120 147,500.00 1,770.00
Mandor L.17 OH 0.0060 150,000.00 900.00
JUMLAH TENAGA KERJA 31,470.00
B BAHAN
Floor hardener Kg 5.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 31,470.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 31,470.00

I.I.62. Pemasangan 1 m1 plint vinyl 15 cm x 30 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0800 112,500.00 9,000.00
Tukang batu L.03 OH 0.0800 127,500.00 10,200.00
Kepala tukang L.14 OH 0.0080 147,500.00 1,180.00
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 20,980.00
B BAHAN
Vynil Buah 1.7600 -
Lem Kg 0.0800 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 20,980.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 20,980.00

I.I.63. Pemasangan 1 m1 plint kayu tebal 2 cm lebar 10 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1200 112,500.00 13,500.00
Tukang batu L.03 OH 0.1200 127,500.00 15,300.00
Kepala tukang L.14 OH 0.0120 147,500.00 1,770.00
Mandor L.17 OH 0.0060 150,000.00 900.00
JUMLAH TENAGA KERJA 31,470.00
B BAHAN
Papan kayu kelas 1 m3 0.0030 -
Paku/skrup 5 cm Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 31,470.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 31,470.00

I.I.64. Pemasangan 1 m2 paving block natural 6 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Tukang batu L.03 OH 0.5000 127,500.00 63,750.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0013 150,000.00 195.00
JUMLAH TENAGA KERJA 99,445.00
B BAHAN
Paving block 6 cm m2 1.0100 -
Pasir beton m3 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN
Perlatan % 0.1000 - -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 99,445.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 99,445.00

I.I.65. Pemasangan 1 m2 paving block natural 8 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang batu L.03 OH 0.5000 127,500.00 63,750.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0013 150,000.00 195.00
JUMLAH TENAGA KERJA 127,570.00
B BAHAN
Paving block 8 cm natural m2 1.0100 -
Pasir beton m3 2.0700 -
JUMLAH HARGA BAHAN -
C PERALATAN
Perlatan % 0.1000 - -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 127,570.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 127,570.00

I.I.66. Pemasangan 1 m2 paving block berwarna tebal 6 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Tukang batu L.03 OH 0.5000 127,500.00 63,750.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0013 150,000.00 195.00
JUMLAH TENAGA KERJA 99,445.00
B BAHAN

Paving block 6 cm berwarna m2 1.0100 -

Pasir beton m3 0.0500 -


JUMLAH HARGA BAHAN -
C PERALATAN
Perlatan % 0.1000 - -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 99,445.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 99,445.00

I.I.67. Pemasangan 1 m2 paving block berwarna tebal 8 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang batu L.03 OH 0.5000 127,500.00 63,750.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0013 150,000.00 195.00
JUMLAH TENAGA KERJA 127,570.00
B BAHAN
Paving block 8 cm berwarna m2 1.0100 -

Pasir beton m3 2.0700 -


JUMLAH HARGA BAHAN -
C PERALATAN
Perlatan % 0.1000 - -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 127,570.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 127,570.00

II ANALISA SENDIRI
I.II.1. Pemasangan 1 m2 koral sikat
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang batu L.03 OH 0.5000 127,500.00 63,750.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 191,125.00
B BAHAN
Koral sikat Zak 0.8000 -
Semen portland Kg 14.1600 -
Pasir pasang m3 0.0230 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 191,125.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 191,125.00

I.II.2. Pemasangan 1 m1 kanstein jumbo (P:50, L:15, T:30, K225)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9500 112,500.00 106,875.00
Tukang batu L.03 OH 0.3500 127,500.00 44,625.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0950 150,000.00 14,250.00
JUMLAH TENAGA KERJA 170,912.50
B BAHAN
Kanstein jumbo m1 2.0000 -
Semen portland Kg 22.5000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 170,912.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 170,912.50

I.II.3. Pemasangan 1 m1 kanstein kursi (P:50, L:10, T:40, K225)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9500 112,500.00 106,875.00
Tukang batu L.03 OH 0.3500 127,500.00 44,625.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0950 150,000.00 14,250.00
JUMLAH TENAGA KERJA 170,912.50
B BAHAN
Kanstein kursi m1 2.0000 -
Semen portland Kg 22.5000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 170,912.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 170,912.50

I.II.4. Pemasangan 1 m2 lantai granit tile ukuran 60 x 60 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 32,012.50
B BAHAN
Granit tile Dus 1.0500 -
Semen portland Kg 9.6000 -
Semen warna Kg 0.0450 -
Pasir pasang m3 1.5000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 32,012.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 32,012.50

I.II.5. Pemasangan 1 m1 plint granit tile ukuran 10 x 60 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 32,012.50
B BAHAN
Granit tile Buah 1.7000 -
Semen portland Kg 1.1400 -
Semen warna Kg 0.0030 -
Pasir pasang m3 0.1000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 32,012.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 32,012.50

I.II.6. Pemasangan 1 m2 dinding keramik ukuran 20 x 40 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7000 112,500.00 78,750.00
Tukang batu L.03 OH 0.3500 127,500.00 44,625.00
Kepala tukang L.14 OH 0.0350 147,500.00 5,162.50
Mandor L.17 OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 133,787.50
B BAHAN
Keramik Buah 12.5000 4,960.00 62,000.00
Semen portland Kg 9.3000 1,325.00 12,322.50
Semen warna Kg 0.0180 15,000.00 270.00
Pasir pasang m3 0.9700 240,000.00 232,800.00
JUMLAH HARGA BAHAN 307,392.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 441,180.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 441,180.00

I.II.7. Pemasangan 1 m2 dinding keramik ukuran 25 x 40 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9000 112,500.00 101,250.00
Tukang batu L.03 OH 0.4500 127,500.00 57,375.00
Kepala tukang L.14 OH 0.0450 147,500.00 6,637.50
Mandor L.17 OH 0.0450 150,000.00 6,750.00
JUMLAH TENAGA KERJA 172,012.50
B BAHAN
Keramik Buah 10.0000 -
Semen portland Kg 9.3000 -
Semen warna Kg 0.0180 -
Pasir pasang m3 1.9400 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 172,012.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 172,012.50
J SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)
I (PERMEN NOMOR 28/PRT/M/2016)
J.I.1. Pemasangan 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Tukang kayu L.04 OH 0.0700 132,500.00 9,275.00
Kepala tukang L.14 OH 0.0070 147,500.00 1,032.50
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 14,282.50
B BAHAN
Asbes semen m2 1.1000 -
Paku tripleks Kg 0.0100 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 14,282.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 14,282.50

J.I.2. Pemasangan 1 m2 langit-langit akustik ukuran 30 x 30 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1200 112,500.00 13,500.00
Tukang kayu L.04 OH 0.1200 132,500.00 15,900.00
Kepala tukang L.14 OH 0.0120 147,500.00 1,770.00
Mandor L.17 OH 0.0060 150,000.00 900.00
JUMLAH TENAGA KERJA 32,070.00
B BAHAN
Akustik Lembar 12.0000 -
Paku tripleks Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 32,070.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 32,070.00

J.I.3. Pemasangan 1 m2 langit-langit akustik ukuran 30 x 60 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1200 112,500.00 13,500.00
Tukang kayu L.04 OH 0.1200 132,500.00 15,900.00
Kepala tukang L.14 OH 0.0120 147,500.00 1,770.00
Mandor L.17 OH 0.0060 150,000.00 900.00
JUMLAH TENAGA KERJA 32,070.00
B BAHAN
Akustik Lembar 5.8000 -
Paku tripleks Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 32,070.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 32,070.00

J.I.4. Pemasangan 1 m2 langit-langit akustik ukuran 60 x 120 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.1000 132,500.00 13,250.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 26,725.00
B BAHAN
Akustik Lembar 1.5000 -
Paku tripleks Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 26,725.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 26,725.00

J.I.5. Pemasangan 1 m2 langit-langit tripleks ukuran 120 x 240 cm, tebal 3 mm, 4 mm & 6 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.1000 132,500.00 13,250.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 26,725.00
B BAHAN
Tripleks Lembar 0.3750 -
Paku tripleks Kg 0.0300 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 26,725.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 26,725.00

J.I.6. Pemasangan 1 m2 langit-langit lambersering kayu, tebal 9 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8000 112,500.00 90,000.00
Tukang kayu L.04 OH 0.8000 132,500.00 106,000.00
Kepala tukang L.14 OH 0.0800 147,500.00 11,800.00
Mandor L.17 OH 0.0400 150,000.00 6,000.00
JUMLAH TENAGA KERJA 213,800.00
B BAHAN
Kayu papan m3 0.0150 8,362,500.00 125,437.50
Paku tripleks Kg 0.0100 20,666.67 206.67
JUMLAH HARGA BAHAN 125,644.17
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 339,444.17


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 339,444.17

J.I.7. Pemasangan 1 m2 langit-langit gypsum board ukuran 120 x 240 x 9 mm, tebal 9 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.0500 132,500.00 6,625.00
Kepala tukang L.14 OH 0.0050 147,500.00 737.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 19,362.50
B BAHAN
Gypsum board Lembar 0.3640 -
Paku skrup Kg 0.1100 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 19,362.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 19,362.50

J.I.8. Pemasangan 1 m2 langit-langit akustik ukuran 60 x 120 cm berikut rangka alluminium


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang besi L.05 OH 0.5000 127,500.00 63,750.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0250 150,000.00 3,750.00
JUMLAH TENAGA KERJA 131,125.00
B BAHAN
Profil Alluminium "T" m1 3.6000 -
Kawat dia. 4 mm Kg 0.1500 -
Ramset Bh 1.0500 -
Akustik 60 x 120 Lembar 1.5000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 131,125.00
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 131,125.00

J.I.9. Pemasangan 1 m1 list langit-langit kayu profil


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0500 112,500.00 5,625.00
Tukang kayu L.04 OH 0.0500 132,500.00 6,625.00
Kepala tukang L.14 OH 0.0050 147,500.00 737.50
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 13,437.50
B BAHAN
List kayu profil m1 1.0500 -
Paku Kg 0.0100 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 13,437.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 13,437.50

J.I.10. Pemasangan 1 m2 rangka langit-langit besi hollow 40 x 40


Lihat pada kelompok Pekerjaan Besi dan Alumunium (A.9.21)

II (SNI 2839:2008)
J.II.1. Pemasangan 1 m1 list plafond gypsum profil
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0600 112,500.00 6,750.00
Tukang kayu L.04 OH 0.0600 132,500.00 7,950.00
Kepala tukang L.14 OH 0.0060 147,500.00 885.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 16,035.00
B BAHAN
List gypsum profil m1 1.0500 -
Tepung gypsum Kg 0.1500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 16,035.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 16,035.00

III ANALISA SENDIRI


J.III.1. Pemasangan 1 m2 plafond kalsiboard
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang kayu L.04 OH 0.1000 132,500.00 13,250.00
Kepala tukang L.14 OH 0.0300 147,500.00 4,425.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 42,425.00
B BAHAN
Kalsiboard Lembar 0.3600 -
Paku skrup Buah 23.0000 -
Cotton plaster Buah 0.0700 -
Compound Kg 0.1300 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 42,425.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 42,425.00

J.III.2. Pemasangan 1 m2 plafond PVC


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4000 112,500.00 45,000.00
Tukang kayu L.04 OH 0.3000 132,500.00 39,750.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0300 150,000.00 4,500.00
JUMLAH TENAGA KERJA 96,625.00
B BAHAN
Plafon PVC Lembar 1.3750 -
Paku skrup Buah 6.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 96,625.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 96,625.00

J.III.3. Pemasangan 1 m1 list plafond PVC


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.0500 132,500.00 6,625.00
Kepala tukang L.14 OH 0.0050 147,500.00 737.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 19,362.50
B BAHAN
List plafon PVC m1 1.0500 -
Paku skrup Buah 6.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 19,362.50
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 19,362.50
K HARGA SATUAN PEKERJAAN PENUTUP ATAP
I (PERMEN NOMOR 28/PRT/M/2016)
K.I.1. Pemasangan 1 m2 atap genteng palentong kecil
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang kayu L.04 OH 0.0750 132,500.00 9,937.50
Kepala tukang L.14 OH 0.0075 147,500.00 1,106.25
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 29,118.75
B BAHAN
Genteng palentong Buah 25.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 29,118.75


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 29,118.75

K.I.2. Pemasangan 1 m2 atap genteng kodok glazur


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang kayu L.04 OH 0.0750 132,500.00 9,937.50
Kepala tukang L.14 OH 0.0080 147,500.00 1,180.00
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 29,192.50
B BAHAN
Genteng kodok Buah 25.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 29,192.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 29,192.50

K.I.3. Pemasangan 1 m2 atap genteng plentong besar/super


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang kayu L.04 OH 0.0750 132,500.00 9,937.50
Kepala tukang L.14 OH 0.0080 147,500.00 1,180.00
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 29,192.50
B BAHAN
Genteng kodok Buah 12.0000 4,500.00 54,000.00
JUMLAH HARGA BAHAN 54,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 83,192.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 83,192.50

K.I.4. Pemasangan 1 m1 bubung genteng plentong


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4000 112,500.00 45,000.00
Tukang kayu L.04 OH 0.2000 132,500.00 26,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 74,750.00
B BAHAN
Genteng bubung Buah 5.0000 -
Semen portland Kg 8.0000 -
Pasir pasang m3 0.0320 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 74,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 74,750.00

K.I.5. Pemasangan 1 m1 bubung genteng kodok glazuur


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4000 112,500.00 45,000.00
Tukang kayu L.04 OH 0.2000 132,500.00 26,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 74,750.00
B BAHAN
Genteng bubung Buah 5.0000 -
Semen portland Kg 8.0000 -
Pasir pasang m3 0.0320 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 74,750.00
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 74,750.00

K.I.6. Pemasangan 1 m1 bubung genteng plentong besar


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4000 112,500.00 45,000.00
Tukang kayu L.04 OH 0.2000 132,500.00 26,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 74,750.00
B BAHAN
Genteng bubung Buah 4.0000 6,000.00 24,000.00
Semen portland Kg 8.0000 1,325.00 10,600.00
Pasir pasang m3 0.0320 240,000.00 7,680.00
JUMLAH HARGA BAHAN 42,280.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 117,030.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 117,030.00

K.I.7. Pemasangan 1 m2 roof light fibreglass 90 x 180


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1400 112,500.00 15,750.00
Tukang kayu L.04 OH 0.0670 132,500.00 8,877.50
Kepala tukang L.14 OH 0.0070 147,500.00 1,032.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 26,710.00
B BAHAN
Rooflight 90 x 180 Lembar 0.6000 -
Paku boasa 1/2" - 1" Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 26,710.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 26,710.00

K.I.8. Pemasangan 1 m2 asbes gelombang 0,92 m x 2,50 m x 5 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1400 112,500.00 15,750.00
Tukang kayu L.04 OH 0.0750 132,500.00 9,937.50
Kepala tukang L.14 OH 0.0080 147,500.00 1,180.00
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 28,067.50
B BAHAN
Asbes gel 0.92 x 2.50 x 5 Lembar 0.5000 -
Paku pancing 6x23 Kg 0.1200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 28,067.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 28,067.50

K.I.9. Pemasangan 1 m2 asbes gelombang 0,92 m x 2,25 m x 5 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1400 112,500.00 15,750.00
Tukang kayu L.04 OH 0.0750 132,500.00 9,937.50
Kepala tukang L.14 OH 0.0080 147,500.00 1,180.00
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 28,067.50
B BAHAN
Asbes gel 0,92 x 2,25 x 5 Lembar 0.6000 -
Paku pancing 6x23 Kg 0.1200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 28,067.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 28,067.50

K.I.10. Pemasangan 1 m2 asbes gelombang 0,92 m x 2,00 m x 5 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1400 112,500.00 15,750.00
Tukang kayu L.04 OH 0.0700 132,500.00 9,275.00
Kepala tukang L.14 OH 0.0070 147,500.00 1,032.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 27,107.50
B BAHAN
Asbes gel 0,92 x 2,00 x 5 Lembar 0.6000 -
Paku pancing 6x23 Kg 0.1200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,107.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,107.50

K.I.11. Pemasangan 1 m2 asbes gelombang 0,92 m x 1,80 m x 5 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1400 112,500.00 15,750.00
Tukang kayu L.04 OH 0.0700 132,500.00 9,275.00
Kepala tukang L.14 OH 0.0070 147,500.00 1,032.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 27,107.50
B BAHAN
Asbes gel 0,92 x 1,80 x 5 Lembar 0.7500 -
Paku pancing 6x23 Kg 0.1200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,107.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,107.50

K.I.12. Pemasangan 1 m2 asbes gelombang 1,05 m x 3,00 m x 4 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1400 112,500.00 15,750.00
Tukang kayu L.04 OH 0.0700 132,500.00 9,275.00
Kepala tukang L.14 OH 0.0070 147,500.00 1,032.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 27,107.50
B BAHAN
Asbes gel 1,05 x 3,00 x 4 Lembar 0.3500 -
Paku pancing 6x23 Kg 0.1200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,107.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,107.50

K.I.13. Pemasangan 1 m2 asbes gelombang 1,05 m x 2,70 m x 4 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1400 112,500.00 15,750.00
Tukang kayu L.04 OH 0.0700 132,500.00 9,275.00
Kepala tukang L.14 OH 0.0070 147,500.00 1,032.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 27,107.50
B BAHAN
Asbes gel 1,05 x 2,70 x 4 Lembar 0.4200 -
Paku pancing 6x23 Kg 0.1200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,107.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,107.50

K.I.14. Pemasangan 1 m2 asbes gelombang 1,05 m x 2,40 m x 4 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1400 112,500.00 15,750.00
Tukang kayu L.04 OH 0.0700 132,500.00 9,275.00
Kepala tukang L.14 OH 0.0070 147,500.00 1,032.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 27,107.50
B BAHAN
Asbes gel 1,05 x 2,40 x 4 Lembar 0.4400 -
Paku pancing 6x23 Kg 0.1200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,107.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,107.50

K.I.15. Pemasangan 1 m2 asbes gelombang 1,05 m x 2,10 m x 4 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1400 112,500.00 15,750.00
Tukang kayu L.04 OH 0.0700 132,500.00 9,275.00
Kepala tukang L.14 OH 0.0070 147,500.00 1,032.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 27,107.50
B BAHAN
Asbes gel 1,05 x 2,10 x 4 Lembar 0.5100 -
Paku pancing 6x23 Kg 0.1200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,107.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,107.50

K.I.16. Pemasangan 1 m2 asbes gelombang 1,05 m x 1.50 m x 4 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1400 112,500.00 15,750.00
Tukang kayu L.04 OH 0.0700 132,500.00 9,275.00
Kepala tukang L.14 OH 0.0070 147,500.00 1,032.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 27,107.50
B BAHAN
Asbes gel 1,05 x 1,50 x 4 Lembar 0.8000 -
Paku pancing 6x23 Kg 0.1200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,107.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,107.50

K.I.17. Pemasangan 1 m2 asbes gelombang 1,08 m x 3.00 m x 6 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1400 112,500.00 15,750.00
Tukang kayu L.04 OH 0.0700 132,500.00 9,275.00
Kepala tukang L.14 OH 0.0070 147,500.00 1,032.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 27,107.50
B BAHAN
Asbes gel 1,08 x 3,00 x 6 Lembar 0.3700 -
Paku pancing 6x23 Kg 0.1200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,107.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,107.50

K.I.18. Pemasangan 1 m2 asbes gelombang 1,08 m x 2.70 m x 6 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1400 112,500.00 15,750.00
Tukang kayu L.04 OH 0.0700 132,500.00 9,275.00
Kepala tukang L.14 OH 0.0070 147,500.00 1,032.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 27,107.50
B BAHAN
Asbes gel 1,08 x 2,70 x 6 Lembar 0.3800 -
Paku pancing 6x23 Kg 0.1200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,107.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,107.50

K.I.19. Pemasangan 1 m2 asbes gelombang 1,08 m x 2.40 m x 6 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1400 112,500.00 15,750.00
Tukang kayu L.04 OH 0.0700 132,500.00 9,275.00
Kepala tukang L.14 OH 0.0070 147,500.00 1,032.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 27,107.50
B BAHAN
Asbes gel 1,08 x 2,40 x 6 Lembar 0.4600 -
Paku pancing 6x23 Kg 0.1200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,107.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,107.50

K.I.20. Pemasangan 1 m2 asbes gelombang 1,08 m x 2.10 m x 6 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1400 112,500.00 15,750.00
Tukang kayu L.04 OH 0.0700 132,500.00 9,275.00
Kepala tukang L.14 OH 0.0070 147,500.00 1,032.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 27,107.50
B BAHAN
Asbes gel 1,08 x 2,10 x 6 Lembar 0.4900 -
Paku pancing 6x23 Kg 0.1200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,107.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,107.50

K.I.21. Pemasangan 1 m2 asbes gelombang 1,08 m x 1,80 m x 6 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1400 112,500.00 15,750.00
Tukang kayu L.04 OH 0.0700 132,500.00 9,275.00
Kepala tukang L.14 OH 0.0070 147,500.00 1,032.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 27,107.50
B BAHAN
Asbes gel 1,08 x 1,80 x 6 Lembar 0.5700 -
Paku pancing 6x23 Kg 0.1200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,107.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,107.50

K.I.22. Pemasangan 1 m1 bubung stel gelombang 0,92 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0840 112,500.00 9,450.00
Tukang kayu L.04 OH 0.1250 132,500.00 16,562.50
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 28,530.00
B BAHAN
Bubung stel gel. 0,92 Lembar 2.4000 -
Paku skrup 3,5" Buah 6.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 28,530.00
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 28,530.00

K.I.23. Pemasangan 1 m1 bubung stel gelombang 1,05 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0840 112,500.00 9,450.00
Tukang kayu L.04 OH 0.1250 132,500.00 16,562.50
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 28,530.00
B BAHAN
Bubung stel gel. 1,05 Lembar 2.1000 -
Paku skrup 3,5" Buah 6.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 28,530.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 28,530.00

K.I.24. Pemasangan 1 m1 bubung stel gelombang 1,08 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0840 112,500.00 9,450.00
Tukang kayu L.04 OH 0.1250 132,500.00 16,562.50
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 28,530.00
B BAHAN
Bubung stel gel. 1,08 Lembar 2.0500 -
Paku skrup 3,5" Buah 6.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 28,530.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 28,530.00

K.I.25. Pemasangan 1 m1 nok paten 0,92 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0840 112,500.00 9,450.00
Tukang kayu L.04 OH 0.1250 132,500.00 16,562.50
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 28,530.00
B BAHAN
Nok paten 0,92 Lembar 1.2000 -
Paku skrup 3,5" Buah 6.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 28,530.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 28,530.00

K.I.26. Pemasangan 1 m1 nok paten 1,05 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0840 112,500.00 9,450.00
Tukang kayu L.04 OH 0.1250 132,500.00 16,562.50
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 28,530.00
B BAHAN
Nok paten 1,05 Lembar 1.2000 -
Paku skrup 3,5" Buah 6.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 28,530.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 28,530.00

K.I.27. Pemasangan 1 m1 nok paten 1,08 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0840 112,500.00 9,450.00
Tukang kayu L.04 OH 0.1250 132,500.00 16,562.50
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 28,530.00
B BAHAN
Nok paten 1,08 Lembar 1.2000 -
Paku skrup 3,5" Buah 6.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 28,530.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 28,530.00

K.I.28. Pemasangan 1 m1 nok stel rata 0,92 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.1500 132,500.00 19,875.00
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 33,642.50
B BAHAN
Nok stel rata 0,92 Lembar 1.1000 -
Paku skrup 3,5" Buah 6.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 33,642.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 33,642.50

K.I.29. Pemasangan 1 m1 nok stel rata 1,05 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0840 112,500.00 9,450.00
Tukang kayu L.04 OH 0.1250 132,500.00 16,562.50
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 28,530.00
B BAHAN
Nok stel rata 1,05 Lembar 1.1000 -
Paku skrup 3,5" Buah 6.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 28,530.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 28,530.00

K.I.30. Pemasangan 1 m2 genteng beton


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang kayu L.04 OH 0.1000 132,500.00 13,250.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 38,725.00
B BAHAN
Genteng beton Buah 11.0000 -
Paku biasa 2" - 5" Kg 0.0300 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 38,725.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 38,725.00

K.I.31. Pemasangan 1 m2 genteng aspal


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang kayu L.04 OH 0.3000 132,500.00 39,750.00
Kepala tukang L.14 OH 0.0030 147,500.00 442.50
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 64,192.50
B BAHAN
Genteng aspal Buah 6.9000 -
Plywood 6 mm Lembar 0.3500 -
Paku biasa 1/2" - 1" Kg 0.0300 -
Plastik aerator Buah 0.5000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 64,192.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 64,192.50

K.I.32. Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap pelana


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang kayu L.04 OH 0.1000 132,500.00 13,250.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 37,375.00
B BAHAN
Genteng metal Buah 1.3000 -
Paku biasa 1/2" - 1" Kg 0.2000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 37,375.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 37,375.00

K.I.33. Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap jurai


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang kayu L.04 OH 0.1000 132,500.00 13,250.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 37,375.00
B BAHAN
Genteng metal Buah 2.0000 -
Paku biasa 1/2" - 1" Kg 0.2000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 37,375.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 37,375.00

K.I.34. Pemasangan 1 m2 atap sirap kayu


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1660 112,500.00 18,675.00
Tukang kayu L.04 OH 0.2500 132,500.00 33,125.00
Kepala tukang L.14 OH 0.0250 147,500.00 3,687.50
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 56,687.50
B BAHAN
Sirap kayu Buah 30.0000 -
Paku biasa 1/2" - 1" Kg 0.2000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 56,687.50
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 56,687.50

K.I.35. Pemasangan 1 m1 nok genteng beton


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4000 112,500.00 45,000.00
Tukang kayu L.04 OH 0.2000 132,500.00 26,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0200 150,000.00 3,000.00
JUMLAH TENAGA KERJA 77,450.00
B BAHAN
Nok genteng beton Buah 3.5000 -
Paku biasa 1/2" - 1" Kg 0.0500 -
Semen portland Kg 10.8000 -
Pasir pasang m3 0.0320 -
Semen warna Kg 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 77,450.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 77,450.00

K.I.36. Pemasangan 1 m1 nok genteng aspal


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1250 112,500.00 14,062.50
Tukang kayu L.04 OH 0.2500 132,500.00 33,125.00
Kepala tukang L.14 OH 0.0250 147,500.00 3,687.50
Mandor L.17 OH 0.0060 150,000.00 900.00
JUMLAH TENAGA KERJA 51,775.00
B BAHAN
Nok genteng aspal Buah 2.0000 -
Paku biasa 1/2" - 1" Kg 0.0500 -
Kayu balok borneo m3 0.0035 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 51,775.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 51,775.00

K.I.37. Pemasangan 1 m1 nok genteng metal


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Tukang kayu L.04 OH 0.1500 132,500.00 19,875.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 52,162.50
B BAHAN
Nok genteng metal Buah 1.1000 -
Paku biasa 1/2" - 1" Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 52,162.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 52,162.50

K.I.38. Pemasangan 1 m1 nok sirap


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1250 112,500.00 14,062.50
Tukang kayu L.04 OH 0.2500 132,500.00 33,125.00
Kepala tukang L.14 OH 0.0250 147,500.00 3,687.50
Mandor L.17 OH 0.0060 150,000.00 900.00
JUMLAH TENAGA KERJA 51,775.00
B BAHAN
Seng plat 3 x 6" Lembar 0.4000 -
Paku biasa 1/2" - 1" Kg 0.0500 -
Paku biasa 2" - 5" Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 51,775.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 51,775.00

K.I.39. Pemasangan 1 m2 atap seng gelombang


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1200 112,500.00 13,500.00
Tukang kayu L.04 OH 0.0600 132,500.00 7,950.00
Kepala tukang L.14 OH 0.0060 147,500.00 885.00
Mandor L.17 OH 0.0060 150,000.00 900.00
JUMLAH TENAGA KERJA 23,235.00
B BAHAN
Seng gel. 3 x 6" Lembar 0.7000 -
Paku biasa 1/2" - 1" Kg 0.0200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,235.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,235.00

K.I.40. Pemasangan 1 m1 nok atap seng


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang kayu L.04 OH 0.0700 132,500.00 9,275.00
Kepala tukang L.14 OH 0.0070 147,500.00 1,032.50
Mandor L.17 OH 0.0060 150,000.00 900.00
JUMLAH TENAGA KERJA 28,082.50
B BAHAN
Seng plat 3 x 6" bjls 28 Lembar 0.3000 -
Paku biasa 1/2" - 1" Kg 0.0400 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 28,082.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 28,082.50

K.I.41. Pemasangan 1 m2 atap aluminium


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang kayu L.04 OH 0.7500 132,500.00 99,375.00
Kepala tukang L.14 OH 0.0800 147,500.00 11,800.00
Mandor L.17 OH 0.0060 150,000.00 900.00
JUMLAH TENAGA KERJA 128,950.00
B BAHAN
Almn gel. tbl 0,55 Lembar 1.0500 -
Paku hak panjang 15 cm Kg 0.0200 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 128,950.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 128,950.00

K.I.42. Pemasangan 1 m1 nok aluminium


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 1.0000 132,500.00 132,500.00
Kepala tukang L.14 OH 0.1000 147,500.00 14,750.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 166,000.00
B BAHAN
Nok standar 40x18 Buah 1.2000 -
Paku hak panjang 15 cm Kg 0.0400 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 166,000.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 166,000.00

K.I.43. Pemasangan 1 m2 aluminium foil/sisalation


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang kayu L.04 OH 0.0500 132,500.00 6,625.00
Kepala tukang L.14 OH 0.0050 147,500.00 737.50
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 25,437.50
B BAHAN
Aluminium foil m2 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 25,437.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 25,437.50

II ANALISA SENDIRI
K.II.1. Pemasangan 1 buah murda paras
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3500 112,500.00 39,375.00
Tukang kayu L.04 OH 0.0500 132,500.00 6,625.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 49,725.00
B BAHAN
Murda paras m2 1.0000 -
Semen portland Kg 5.2500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 49,725.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 49,725.00

K.II.2. Pemasangan 1 buah ikut celedu paras


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3500 112,500.00 39,375.00
Tukang kayu L.04 OH 0.0500 132,500.00 6,625.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 49,725.00
B BAHAN
Ikut celedu paras m2 1.0000 90,000.00 90,000.00
Semen portland Kg 5.2500 1,325.00 6,956.25
JUMLAH HARGA BAHAN 96,956.25
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 139,725.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 139,725.00

K.II.3. Pemasangan 1 buah bentala paras


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3500 112,500.00 39,375.00
Tukang kayu L.04 OH 0.0500 132,500.00 6,625.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 49,725.00
B BAHAN
Bentala paras m2 1.0000 150,000.00 150,000.00
Semen portland Kg 5.2500 1,325.00 6,956.25
JUMLAH HARGA BAHAN 156,956.25
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 199,725.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 199,725.00
L HARGA SATUAN PEKERJAAN KAYU
I (PERMEN NOMOR 28/PRT/M/2016)
L.I.1. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 7.0000 112,500.00 787,500.00
Tukang kayu L.04 OH 21.0000 132,500.00 2,782,500.00
Kepala tukang L.14 OH 2.1000 147,500.00 309,750.00
Mandor L.17 OH 0.3500 150,000.00 52,500.00
JUMLAH TENAGA KERJA 3,932,250.00
B BAHAN
Balok kayu m3 1.1000 -
Paku 10 cm Kg 1.2500 -
Lem kayu Kg 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,932,250.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,932,250.00

L.I.2. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 6.0000 112,500.00 675,000.00
Tukang kayu L.04 OH 18.0000 132,500.00 2,385,000.00
Kepala tukang L.14 OH 1.8000 147,500.00 265,500.00
Mandor L.17 OH 0.3000 150,000.00 45,000.00
JUMLAH TENAGA KERJA 3,370,500.00
B BAHAN
Balok kayu m3 1.2000 -
Paku 10 cm Kg 1.2500 -
Lem kayu Kg 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,370,500.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,370,500.00

L.I.3. Pembuatan dan pemasangan 1 m2 pintu klamp standar, kayu kelas II


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3500 112,500.00 39,375.00
Tukang kayu L.04 OH 1.0500 132,500.00 139,125.00
Kepala tukang L.14 OH 0.1050 147,500.00 15,487.50
Mandor L.17 OH 0.0180 150,000.00 2,700.00
JUMLAH TENAGA KERJA 196,687.50
B BAHAN
Papan kayu m3 0.0400 -
Paku 5 - 7 cm Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 196,687.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 196,687.50

L.I.4. Pembuatan dan pemasangan 1 m2 pintu klamp sederhana, kayu kelas III
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3500 112,500.00 39,375.00
Tukang kayu L.04 OH 1.0500 132,500.00 139,125.00
Kepala tukang L.14 OH 0.1050 147,500.00 15,487.50
Mandor L.17 OH 0.0180 150,000.00 2,700.00
JUMLAH TENAGA KERJA 196,687.50
B BAHAN
Papan kayu m3 0.0400 -
Paku 5 - 7 cm Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 196,687.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 196,687.50

L.I.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau II
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang kayu L.04 OH 3.0000 132,500.00 397,500.00
Kepala tukang L.14 OH 0.3000 147,500.00 44,250.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 561,750.00
B BAHAN
Papan kayu m3 0.0400 -
Lem kayu Kg 0.5000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 561,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 561,750.00

L.I.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau II
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8000 112,500.00 90,000.00
Tukang kayu L.04 OH 2.4000 132,500.00 318,000.00
Kepala tukang L.14 OH 0.2400 147,500.00 35,400.00
Mandor L.17 OH 0.0400 150,000.00 6,000.00
JUMLAH TENAGA KERJA 449,400.00
B BAHAN
Papan kayu m3 0.0240 -
Lem kayu Kg 0.3000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 449,400.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 449,400.00

L.I.7. Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi kayu kelas I atau II
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang kayu L.04 OH 3.0000 132,500.00 397,500.00
Kepala tukang L.14 OH 0.3000 147,500.00 44,250.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 561,750.00
B BAHAN
Papan kayu m3 0.0640 -
Lem kayu Kg 0.5000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 561,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 561,750.00

L.I.8. Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90 cm)
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7000 112,500.00 78,750.00
Tukang kayu L.04 OH 2.1000 132,500.00 278,250.00
Kepala tukang L.14 OH 0.2100 147,500.00 30,975.00
Mandor L.17 OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 393,225.00
B BAHAN
Papan kayu m3 0.0250 -
Paku 1 cm - 2,5 cm Kg 0.0300 -
Lem kayu Kg 0.5000 -
Plywood tebal 4 mm ukuran
Lembar 1.0000 -
(90 x 220) cm
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 393,225.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 393,225.00

L.I.9. Pembuatan 1 m2 pintu plywood rangkap, rangka expose kayu kelas I atau II
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8000 112,500.00 90,000.00
Tukang kayu L.04 OH 2.4000 132,500.00 318,000.00
Kepala tukang L.14 OH 0.2400 147,500.00 35,400.00
Mandor L.17 OH 0.0400 150,000.00 6,000.00
JUMLAH TENAGA KERJA 449,400.00
B BAHAN
Papan kayu m3 0.0256 -
Paku 1 cm - 2,5 cm Kg 0.0300 -
Lem kayu Kg 0.5000 -
Plywood tebal 4 mm (90 x
Lembar 1.0000 -
220) cm
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 449,400.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 449,400.00

L.I.10. Pemasangan 1 m2 jalusi kusen, kayu kelas I atau II


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6700 112,500.00 75,375.00
Tukang kayu L.04 OH 2.0000 132,500.00 265,000.00
Kepala tukang L.14 OH 0.2000 147,500.00 29,500.00
Mandor L.17 OH 0.3350 150,000.00 50,250.00
JUMLAH TENAGA KERJA 420,125.00
B BAHAN
Papan kayu m3 0.0600 -
Paku 1 cm - 2,5 cm Kg 0.1500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 420,125.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 420,125.00

L.I.11. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8000 112,500.00 90,000.00
Tukang kayu L.04 OH 2.4000 132,500.00 318,000.00
Kepala tukang L.14 OH 0.2400 147,500.00 35,400.00
Mandor L.17 OH 0.0400 150,000.00 6,000.00
JUMLAH TENAGA KERJA 449,400.00
B BAHAN
Papan kayu m3 0.0250 -
Paku 1 - 2,5 cm Kg 0.0300 -
Lem kayu Kg 0.3000 -
Teakwood 4 mm 90 x 220
Lembar 1.0000 -
cm
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 449,400.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 449,400.00

L.I.12. Pemasangan 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas II
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8500 112,500.00 95,625.00
Tukang kayu L.04 OH 2.5500 132,500.00 337,875.00
Kepala tukang L.14 OH 0.2550 147,500.00 37,612.50
Mandor L.17 OH 0.0430 150,000.00 6,450.00
JUMLAH TENAGA KERJA 477,562.50
B BAHAN
Papan kayu m3 0.0250 -
Paku 1 - 2,5 cm Kg 0.0300 -
Lem kayu Kg 0.8000 -
Teakwood 4 mm 90 x 220
Lembar 1.0000 -
cm
Formika Lembar 0.5000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 477,562.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 477,562.50

L.I.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 4.0000 112,500.00 450,000.00
Tukang kayu L.04 OH 12.0000 132,500.00 1,590,000.00
Kepala tukang L.14 OH 1.2000 147,500.00 177,000.00
Mandor L.17 OH 0.2000 150,000.00 30,000.00
JUMLAH TENAGA KERJA 2,247,000.00
B BAHAN
Balok kayu m3 1.1000 -
Besi strip tebal 5 mm Kg 15.0000 -
Paku 12 cm Kg 5.6000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 2,247,000.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 2,247,000.00

L.I.14. Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas I


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 6.7000 112,500.00 753,750.00
Tukang kayu L.04 OH 20.1000 132,500.00 2,663,250.00
Kepala tukang L.14 OH 2.0100 147,500.00 296,475.00
Mandor L.17 OH 0.3350 150,000.00 50,250.00
JUMLAH TENAGA KERJA 3,763,725.00
B BAHAN
Balok kayu m3 1.2000 -
Besi strip tebal 5 mm Kg 15.0000 -
Paku 12 cm Kg 5.6000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,763,725.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,763,725.00

L.I.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 6.7000 112,500.00 753,750.00
Tukang kayu L.04 OH 20.1000 132,500.00 2,663,250.00
Kepala tukang L.14 OH 2.0100 147,500.00 296,475.00
Mandor L.17 OH 0.3350 150,000.00 50,250.00
JUMLAH TENAGA KERJA 3,763,725.00
B BAHAN
Balok kayu m3 1.1000 -
Besi strip tebal 5 mm Kg 15.0000 -
Paku 12 cm Kg 3.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,763,725.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,763,725.00

L.I.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.1000 132,500.00 13,250.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 26,725.00
B BAHAN
Kaso-kaso 5 x 7 cm m3 0.0140 -
Reng 2 x 3 cm m3 0.0360 -
Paku 5 dan 10 cm Kg 0.2500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 26,725.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 26,725.00

L.I.17. Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.1000 132,500.00 13,250.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 26,725.00
B BAHAN
Kaso-kaso 5 x 7 cm m3 0.0140 -
Reng 3 x 4 cm m3 0.0570 -
Paku 5 dan 10 cm Kg 0.2500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 26,725.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 26,725.00

L.I.18. Pemasangan 1 m2 rangka atap sirap, kayu kelas II


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1200 112,500.00 13,500.00
Tukang kayu L.04 OH 0.1200 132,500.00 15,900.00
Kepala tukang L.14 OH 0.0120 147,500.00 1,770.00
Mandor L.17 OH 0.0060 150,000.00 900.00
JUMLAH TENAGA KERJA 32,070.00
B BAHAN
Kayu kelas II m3 0.0140 -
Paku 5 - 10 cm Kg 0.0570 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 32,070.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 32,070.00

L.I.19. Pemasangan 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas II atau III
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang kayu L.04 OH 0.3000 132,500.00 39,750.00
Kepala tukang L.14 OH 0.0300 147,500.00 4,425.00
Mandor L.17 OH 0.0750 150,000.00 11,250.00
JUMLAH TENAGA KERJA 72,300.00
B BAHAN
Kaso-kaso 5 x 7 cm m3 0.0154 -
Paku 7 cm - 10 cm Kg 0.2000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 72,300.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 72,300.00

L.I.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang kayu L.04 OH 0.3000 132,500.00 39,750.00
Kepala tukang L.14 OH 0.0300 147,500.00 4,425.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 68,175.00
B BAHAN
Kaso-kaso 5 x 7 cm m3 0.0163 -
Paku 7 cm - 10 cm Kg 0.2500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 68,175.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 68,175.00

L.I.21. Pemasangan 1 m1 lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.2000 132,500.00 26,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 41,450.00
B BAHAN
Papan kayu m3 0.0108 -
Paku 5 dan 7 cm Kg 0.1000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 41,450.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 41,450.00

L.I.22. Pemasangan 1 m1 lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.2000 132,500.00 26,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 41,450.00
B BAHAN
Papan kayu m3 0.0110 8,362,500.00 91,987.50
Paku 5 dan 7 cm Kg 0.0500 20,666.67 1,033.33
JUMLAH HARGA BAHAN 93,020.83
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 134,470.83


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 134,470.83

L.I.23. Pemasangan 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas I


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang kayu L.04 OH 0.4500 132,500.00 59,625.00
Kepala tukang L.14 OH 0.0450 147,500.00 6,637.50
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 84,337.50
B BAHAN
Balok kayu m3 0.0280 -
Paku 5 dan 7 cm Kg 0.1500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 84,337.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 84,337.50

II (PERMEN NO.11/PRT/M/2013)
L.II.1. Pemasangan 1 m2 dinding pemisah teakwood rangkap, rangka kayu kelas II
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang kayu L.04 OH 0.4500 132,500.00 59,625.00
Kepala tukang L.14 OH 0.0450 147,500.00 6,637.50
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 84,337.50
B BAHAN
Balok kayu 6 x 12 m3 0.0280 -
Paku 5 dan 10 Kg 0.1500 -

Teakwood 4 mm, 120 x 240 Lembar 0.8600 -

Lem kayu Kg 0.5600 -


JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 84,337.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 84,337.50

III (SNI-3434-2008)
L.III.1. Pemasangan 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang kayu L.04 OH 0.6000 132,500.00 79,500.00
Kepala tukang L.14 OH 0.0600 147,500.00 8,850.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 112,350.00
B BAHAN
Balok kayu, ukuran (6 x 12)
m3 0.0280 -
cm
Paku 5 cm dan 10 cm Kg 0.1500 -
Teakwood tebal 4 mm,
Lembar 0.8600 -
ukuran 120 cm x 240 cm
Lem kayu Kg 0.5600 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 112,350.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 112,350.00

L.III.2. Pemasangan 1 m2 dinding lambersering dari papan kayu kelas I


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6000 112,500.00 67,500.00
Tukang kayu L.04 OH 1.8000 132,500.00 238,500.00
Kepala tukang L.14 OH 0.1800 147,500.00 26,550.00
Mandor L.17 OH 0.0300 150,000.00 4,500.00
JUMLAH TENAGA KERJA 337,050.00
B BAHAN
Papan kayu m3 0.0070 -
Paku 5 cm dan 10 cm Kg 0.1000 -
Paku skrup 10 cm Kg 0.1500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 337,050.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 337,050.00

L.III.3. Pemasangan 1 m2 dinding lambersering dari plywood ukuran (120 x 240) cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0250 112,500.00 2,812.50
Tukang kayu L.04 OH 0.0750 132,500.00 9,937.50
Kepala tukang L.14 OH 0.0800 147,500.00 11,800.00
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 24,700.00
B BAHAN
Plywood tebal 4 mm Lembar 0.4000 -
Paku 1 cm dan 2,5 cm Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 24,700.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 24,700.00

L.III.4. Pemasangan 1 m2 dinding bilik, rangka kayu kelas III atau IV


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.0500 132,500.00 6,625.00
Kepala tukang L.14 OH 0.0050 147,500.00 737.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 19,362.50
B BAHAN
Bilik bambu m2 1.5000 -
Kaso-kaso (5 x 7) cm m3 0.0140 -
Paku Kg 0.0120 -
List kayu 2/4 m3 0.0030 -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 19,362.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 19,362.50

IV ANALISA SENDIRI
L.IV.1. Pekerjaan 1 m2 anti rayap (wood treatment)
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Mandor L.17 OH 0.0210 150,000.00 3,150.00
JUMLAH TENAGA KERJA 20,025.00
B BAHAN
Larutan termisida m2 1.5000 -
Air m3 0.0140 -
JUMLAH HARGA BAHAN -
C PERALATAN
Alat bantu % 1.0000 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 20,025.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 20,025.00

L.IV.2. Pemasangan 1 m2 HPL


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0250 112,500.00 2,812.50
Tukang kayu L.04 OH 0.0750 132,500.00 9,937.50
Kepala tukang L.14 OH 0.0080 147,500.00 1,180.00
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 14,080.00
B BAHAN
HPL Lembar 0.3695 -
Lem Kayu Kg 0.1833 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 14,080.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 14,080.00

L.IV.3. Pemasangan 1 m3 balok kayu


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 6.7000 112,500.00 753,750.00
Tukang kayu L.04 OH 20.1000 132,500.00 2,663,250.00
Kepala tukang L.14 OH 2.0100 147,500.00 296,475.00
Mandor L.17 OH 0.3350 150,000.00 50,250.00
JUMLAH TENAGA KERJA 3,763,725.00
B BAHAN
Balok kayu m3 1.1000 7,366,666.67 8,103,333.33
Besi strip tebal 5 mm Kg 15.0000 13,500.00 202,500.00
Paku 12 cm Kg 3.0000 22,000.00 66,000.00
JUMLAH HARGA BAHAN 8,371,833.33
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 12,135,558.33


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 12,135,558.33

L.IV.4. Pemasangan 1 m2 usuk kuda-kuda expose


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.2000 132,500.00 26,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 40,850.00
B BAHAN
Kaso-kaso 5 x 7 cm m3 0.0070 7,100,000.00 49,700.00
Paku 7 cm - 10 cm Kg 0.2500 20,666.67 5,166.67
JUMLAH HARGA BAHAN 54,866.67
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 95,716.67


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 95,716.67

L.IV.5. Pemasangan 1 m2 reng kuda-kuda expose


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.2000 132,500.00 26,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 42,200.00
B BAHAN
Reng 2 x 4 cm m3 0.0032 7,100,000.00 22,720.00
Paku 7 cm - 10 cm Kg 0.1500 20,666.67 3,100.00
JUMLAH HARGA BAHAN 25,820.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 68,020.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 68,020.00

L.IV.6. Pemasangan 1 m1 lisplank ukuran (2 x 20) cm, kayu kelas I atau kelas II
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.2000 132,500.00 26,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 41,450.00
B BAHAN
Papan kayu m3 0.0040 8,362,500.00 33,450.00
Paku 5 dan 7 cm Kg 0.0500 20,666.67 1,033.33
JUMLAH HARGA BAHAN 34,483.33
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 75,933.33


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 75,933.33

L.IV.7. Pemasangan 1 m1 lisplank ukuran (2 x 15) cm, kayu kelas I atau kelas II
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.2000 132,500.00 26,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 41,450.00
B BAHAN
Papan kayu m3 0.0030 8,362,500.00 25,087.50
Paku 5 dan 7 cm Kg 0.0500 20,666.67 1,033.33
JUMLAH HARGA BAHAN 26,120.83
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 67,570.83


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 67,570.83

L.IV.8. Pemasangan 1 m1 tatab ukuran (3 x 10) cm, kayu kelas I atau kelas II
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.2000 132,500.00 26,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 41,450.00
B BAHAN
Papan kayu m3 0.0030 8,362,500.00 25,087.50
Paku 5 dan 7 cm Kg 0.0500 20,666.67 1,033.33
JUMLAH HARGA BAHAN 26,120.83
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 67,570.83


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 67,570.83
M HARGA SATUAN PEKERJAAN KUNCI DAN KACA
I (PERMEN NOMOR 28/PRT/M/2016)
M.I.1. Pemasangan 1 buah kunci tanam antik
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0600 112,500.00 6,750.00
Tukang kayu L.04 OH 0.6000 132,500.00 79,500.00
Kepala tukang L.14 OH 0.0600 147,500.00 8,850.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 95,550.00
B BAHAN
Kunci tanam antik Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 95,550.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 95,550.00

M.I.2. Pemasangan 1 buah kunci tanam biasa


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0100 112,500.00 1,125.00
Tukang kayu L.04 OH 0.5000 132,500.00 66,250.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 75,500.00
B BAHAN
Kunci tanam biasa Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 75,500.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 75,500.00

M.I.3. Pemasangan 1 buah kunci kamar mandi


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0050 112,500.00 562.50
Tukang kayu L.04 OH 0.5000 132,500.00 66,250.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 74,637.50
B BAHAN
Kunci tanam KM Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 74,637.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 74,637.50

M.I.4. Pemasangan 1 buah kunci silinder


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0050 112,500.00 562.50
Tukang kayu L.04 OH 0.5000 132,500.00 66,250.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 74,637.50
B BAHAN
Kunci silinder Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 74,637.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 74,637.50

M.I.5. Pemasangan 1 buah engsel pintu


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0150 112,500.00 1,687.50
Tukang kayu L.04 OH 0.1500 132,500.00 19,875.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0008 150,000.00 120.00
JUMLAH TENAGA KERJA 23,895.00
B BAHAN
Engsel pintu Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,895.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,895.00

M.I.6. Pemasangan 1 buah engsel jendela kupu-kupu


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0100 112,500.00 1,125.00
Tukang kayu L.04 OH 0.1000 132,500.00 13,250.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0005 150,000.00 75.00
JUMLAH TENAGA KERJA 15,925.00
B BAHAN
Engsel jendela Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 15,925.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 15,925.00

M.I.7. Pemasangan 1 buah engsel angin


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang kayu L.04 OH 0.2000 132,500.00 26,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0005 150,000.00 75.00
JUMLAH TENAGA KERJA 40,775.00
B BAHAN
Engsel angin Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 40,775.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 40,775.00

M.I.8. Pemasangan 1 buah spring knip


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0150 112,500.00 1,687.50
Tukang kayu L.04 OH 0.1500 132,500.00 19,875.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 24,975.00
B BAHAN
Spring knip Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 24,975.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 24,975.00

M.I.9. Pemasangan 1 buah kait angin


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0150 112,500.00 1,687.50
Tukang kayu L.04 OH 0.1500 132,500.00 19,875.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 24,975.00
B BAHAN
Kait angin Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 24,975.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 24,975.00

M.I.10. Pemasangan 1 buah door closer


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0500 112,500.00 5,625.00
Tukang kayu L.04 OH 0.5000 132,500.00 66,250.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 79,700.00
B BAHAN
Door closer Set 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 79,700.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 79,700.00

M.I.11. Pemasangan 1 buah kunci slot


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Tukang kayu L.04 OH 0.2000 132,500.00 26,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 31,850.00
B BAHAN
Kunci slot Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 31,850.00
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 31,850.00

M.I.12. Pemasangan 1 buah door holder


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0500 112,500.00 5,625.00
Tukang kayu L.04 OH 0.5000 132,500.00 66,250.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 79,700.00
B BAHAN
Door holder Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 79,700.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 79,700.00

M.I.13. Pemasangan 1 buah door stop


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.010 112,500.00 1,125.00
Tukang kayu L.04 OH 0.100 132,500.00 13,250.00
Kepala tukang L.14 OH 0.010 147,500.00 1,475.00
Mandor L.17 OH 0.005 150,000.00 750.00
JUMLAH TENAGA KERJA 16,600.00
B BAHAN
Door stop Buah 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 16,600.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 16,600.00

M.I.14. Pemasangan 1 buah rel pintu sorong


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0600 112,500.00 6,750.00
Tukang kayu L.04 OH 0.6000 132,500.00 79,500.00
Kepala tukang L.14 OH 0.0600 147,500.00 8,850.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 95,550.00
B BAHAN
Rel pintu sorong Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 95,550.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 95,550.00

M.I.15. Pemasangan 1 buah kunci lemari


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0250 112,500.00 2,812.50
Tukang kayu L.04 OH 0.2500 132,500.00 33,125.00
Kepala tukang L.14 OH 0.0250 147,500.00 3,687.50
Mandor L.17 OH 0.0013 150,000.00 195.00
JUMLAH TENAGA KERJA 39,820.00
B BAHAN
Kunci lemari Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 39,820.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 39,820.00

M.I.16. Pemasangan 1 m2 kaca tebal 3 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0150 112,500.00 1,687.50
Tukang kayu L.04 OH 0.1500 132,500.00 19,875.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0008 150,000.00 120.00
JUMLAH TENAGA KERJA 23,895.00
B BAHAN
Kaca bening 3 mm m2 1.1000 -
Sealant Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,895.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,895.00

M.I.17. Pemasangan 1 m2 kaca tebal 5 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0150 112,500.00 1,687.50
Tukang kayu L.04 OH 0.1500 132,500.00 19,875.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0008 150,000.00 120.00
JUMLAH TENAGA KERJA 23,895.00
B BAHAN
Kaca bening 5 mm m2 1.1000 -
Sealant Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,895.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,895.00

M.I.18. Pemasangan 1 m2 kaca tebal 8 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0170 112,500.00 1,912.50
Tukang kayu L.04 OH 0.1700 132,500.00 22,525.00
Kepala tukang L.14 OH 0.0170 147,500.00 2,507.50
Mandor L.17 OH 0.0009 150,000.00 135.00
JUMLAH TENAGA KERJA 27,080.00
B BAHAN
Kaca bening 8 mm m2 1.1000 -
Sealant Kg 0.0700 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,080.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,080.00

M.I.19. Pemasangan 1 m2 kaca buram tebal 12 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0250 112,500.00 2,812.50
Tukang kayu L.04 OH 0.2500 132,500.00 33,125.00
Kepala tukang L.14 OH 0.0250 147,500.00 3,687.50
Mandor L.17 OH 0.0013 150,000.00 195.00
JUMLAH TENAGA KERJA 39,820.00
B BAHAN
Kaca buram 12 mm m2 1.1000 -
Sealant Kg 0.0700 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 39,820.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 39,820.00

M.I.20. Pemasangan 1 m2 kaca cermin tebal 5 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0150 112,500.00 1,687.50
Tukang kayu L.04 OH 0.1500 132,500.00 19,875.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 24,975.00
B BAHAN
Kaca cermin 5 mm m2 1.1000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 24,975.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 24,975.00

M.I.21. Pemasangan 1 m2 kaca cermin tebal 8 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0170 112,500.00 1,912.50
Tukang kayu L.04 OH 0.1700 132,500.00 22,525.00
Kepala tukang L.14 OH 0.0170 147,500.00 2,507.50
Mandor L.17 OH 0.0090 150,000.00 1,350.00
JUMLAH TENAGA KERJA 28,295.00
B BAHAN
Kaca cermin 8 mm m2 1.1000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 28,295.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 28,295.00

M.I.22. Pemasangan 1 m2 kaca wireglassed tebal 5 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0150 112,500.00 1,687.50
Tukang kayu L.04 OH 0.1500 132,500.00 19,875.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 24,975.00
B BAHAN
Kaca wireglassed 5 mm m2 1.1000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 24,975.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 24,975.00

M.I.23. Pemasangan 1 m2 kaca patri tebal 5 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0750 112,500.00 8,437.50
Tukang kayu L.04 OH 0.1500 132,500.00 19,875.00
Kepala tukang L.14 OH 0.0150 147,500.00 2,212.50
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 31,125.00
B BAHAN
Kaca patri 5 mm m2 1.1000 -
Sealant Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 31,125.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 31,125.00

II PT-T-30-2000-C
M.II.1. Pemasangan 1 m2 kaca tebal 3 mm dengan kisi-kisi
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Tukang kayu L.04 OH 0.2500 132,500.00 33,125.00
Kepala tukang L.14 OH 0.0250 147,500.00 3,687.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 66,887.50
B BAHAN
Kaca tebal 3 mm m2 1.2000 -
Sealant Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 66,887.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 66,887.50

M.II.2. Pemasangan 1 m2 kaca raiben tebal 5 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1600 112,500.00 18,000.00
Tukang kayu L.04 OH 0.1600 132,500.00 21,200.00
Kepala tukang L.14 OH 0.0160 147,500.00 2,360.00
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 42,760.00
B BAHAN
Kaca raiben 5 mm m2 1.1000 -
Sealant Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 42,760.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 42,760.00

M.II.3. Pemasangan 1 m2 kaca raiben tebal 10 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Tukang kayu L.04 OH 0.1250 132,500.00 16,562.50
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 48,555.00
B BAHAN
Kaca raiben 10 mm m2 1.1000 -
Sealant Kg 0.0700 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 48,555.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 48,555.00

M.II.4. Pemasangan 1 m2 kaca raiben tebal 12 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Tukang kayu L.04 OH 0.1250 132,500.00 16,562.50
Kepala tukang L.14 OH 0.0130 147,500.00 1,917.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 48,555.00
B BAHAN
Kaca raiben tebal 12 mm m2 1.1000 -
Sealant Kg 0.0700 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 48,555.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 48,555.00

M.II.5. Pemasangan 1 m2 kaca buram tebal 3 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1600 112,500.00 18,000.00
Tukang kayu L.04 OH 0.1600 132,500.00 21,200.00
Kepala tukang L.14 OH 0.0160 147,500.00 2,360.00
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 42,760.00
B BAHAN
Kaca buram tebal 3 mm m2 1.1000 -
Sealant Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 42,760.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 42,760.00

M.II.6. Pemasangan 1 m2 kaca buram tebal 5 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1600 112,500.00 18,000.00
Tukang kayu L.04 OH 0.1600 132,500.00 21,200.00
Kepala tukang L.14 OH 0.0160 147,500.00 2,360.00
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 42,760.00
B BAHAN
Kaca buram tebal 5 mm m2 1.1000 -
Sealant Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 42,760.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 42,760.00

M.II.7. Pemasangan 1 m2 kaca buram tebal 3 mm (motif) Jumlah


Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1600 112,500.00 18,000.00
Tukang kayu L.04 OH 0.1600 132,500.00 21,200.00
Kepala tukang L.14 OH 0.0160 147,500.00 2,360.00
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 42,760.00
B BAHAN
Kaca buram tebal 3 mm
m2 1.1000 -
(motif)
Sealant Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 42,760.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 42,760.00

M.II.8. Pemasangan 1 m2 kaca buram tebal 5 mm (motif)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1600 112,500.00 18,000.00
Tukang kayu L.04 OH 0.1600 132,500.00 21,200.00
Kepala tukang L.14 OH 0.0160 147,500.00 2,360.00
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 42,760.00
B BAHAN
Kaca buram tebal 5 mm
m2 1.1000 -
(motif)
Sealant Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 42,760.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 42,760.00

III ANALISA SENDIRI


M.III.1. Pemasangan 1 buah handel pintu
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0500 112,500.00 5,625.00
Tukang kayu L.04 OH 0.5000 132,500.00 66,250.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 79,700.00
B BAHAN
Handel pintu Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 79,700.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 79,700.00
N HARGA SATUAN PEKERJAAN PENGECATAN
I (PERMEN NOMOR 28/PRT/M/2016)
N.I.1. Pengikisan/pengerokan 1 m2 permukaan cat lama
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 17,325.00
B BAHAN
Soda api Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 17,325.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 17,325.00

N.I.2. Pencucian 1 m2 bidang permukaan tembok yang pernah dicat


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 17,325.00
B BAHAN
Sabun Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 17,325.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 17,325.00

N.I.3. Pengerokan 1 m2 karat pada permukaan baja cara manual


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 18,075.00
B BAHAN
Sabun Kg 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 18,075.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 18,075.00

N.I.4. Pengecatan 1 m2 bidang kayu baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0700 112,500.00 7,875.00
Tukang cat L.06 OH 0.0090 127,500.00 1,147.50
Kepala tukang L.14 OH 0.0060 147,500.00 885.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 10,357.50
B BAHAN
Cat menie Kg 0.2000 -
Plamir Kg 0.1500 -
Cat dasar Kg 0.1700 -
Cat penutup Kg 0.2600 -
Kuas Buah 0.0100 -
Pengencer Kg 0.0300 -
Ampelas Lembar 0.2000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 10,357.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 10,357.50

N.I.5. Pengecatan 1 m2 bidang kayu baru (1 lapis plamur, 1 lapis cat dasar, 3 lapis cat penutup)
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0700 112,500.00 7,875.00
Tukang cat L.06 OH 0.1050 127,500.00 13,387.50
Kepala tukang L.14 OH 0.0040 147,500.00 590.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 22,302.50
B BAHAN
Cat menie Kg 0.2000 -
Plamir Kg 0.1500 -
Cat dasar Kg 0.1700 -
Cat penutup Kg 0.3500 -
Kuas Buah 0.0100 -
Pengencer Kg 0.0300 -
Ampelas Lembar 0.2000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 22,302.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 22,302.50

N.I.6. Pelaburan 1 m2 bidang kayu dengan teak oil


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0400 112,500.00 4,500.00
Tukang cat L.06 OH 0.0630 127,500.00 8,032.50
Kepala tukang L.14 OH 0.0630 147,500.00 9,292.50
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 22,275.00
B BAHAN
Teak oil Liter 0.3600 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 22,275.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 22,275.00
N.I.7. Pelaburan 1 m2 bidang kayu dengan politur
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0400 112,500.00 4,500.00
Tukang cat L.06 OH 0.0600 127,500.00 7,650.00
Kepala tukang L.14 OH 0.0160 147,500.00 2,360.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 14,960.00
B BAHAN
Politur Liter 0.1500 107,333.33 16,100.00
Politur jadi Liter 0.3720 107,500.00 39,990.00
Ampelas Lembar 2.0000 5,333.33 10,666.67
JUMLAH HARGA BAHAN 66,756.67
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 81,716.67


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 81,716.67

N.I.8. Pelaburan 1 m2 bidang kayu dengan cat residu dan ter


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Mandor L.17 OH 0.0060 150,000.00 900.00
JUMLAH TENAGA KERJA 12,150.00
B BAHAN
Residu atau ter Liter 0.3500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 12,150.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 12,150.00

N.I.9. Pelaburan 1 m2 bidang kayu dengan vernis


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1600 112,500.00 18,000.00
Tukang cat L.06 OH 0.1600 127,500.00 20,400.00
Kepala tukang L.14 OH 0.0160 147,500.00 2,360.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 41,210.00
B BAHAN
Movilex Liter 0.1500 -
Dempul Kg 0.0500 -
Ampelas Lembar 0.1000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 41,210.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 41,210.00

N.I.10. Pengecatan 1 m2 tembok baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Tukang cat L.06 OH 0.0630 127,500.00 8,032.50
Kepala tukang L.14 OH 0.0063 147,500.00 929.25
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 11,661.75
B BAHAN
Plamir Kg 0.1000 -
Cat dasar Kg 0.1000 -
Cat penutup Kg 0.2600 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 11,661.75


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 11,661.75
N.I.11. Pengecatan 1 m2 tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0280 112,500.00 3,150.00
Tukang cat L.06 OH 0.0420 127,500.00 5,355.00
Kepala tukang L.14 OH 0.0042 147,500.00 619.50
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 9,574.50
B BAHAN
Cat dasar Kg 0.1200 -
Cat penutup Kg 0.1800 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 9,574.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 9,574.50

N.I.12. Pelaburan 1 m2 tembok dengan kalkarium


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0280 112,500.00 3,150.00
Tukang cat L.06 OH 0.0420 127,500.00 5,355.00
Kepala tukang L.14 OH 0.0042 147,500.00 619.50
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 9,574.50
B BAHAN
Kalkarium Kg 0.1000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 9,574.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 9,574.50

N.I.13. Pelaburan 1 m2 tembok dengan kapur sirih


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang cat L.06 OH 0.0010 127,500.00 127.50
Kepala tukang L.14 OH 0.0001 147,500.00 14.75
Mandor L.17 OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 17,392.25
B BAHAN
Kapur sirih Kg 0.1500 -
Ampelas Lembar 0.1000 -
Alang-alang Ikat 0.2500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 17,392.25


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 17,392.25

N.I.14. Pelaburan 1 m2 tembok lama dengan kapur sirih (pemeliharaan)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0400 112,500.00 4,500.00
Tukang cat L.06 OH 0.0050 127,500.00 637.50
Kepala tukang L.14 OH 0.0005 147,500.00 73.75
Mandor L.17 OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 5,586.25
B BAHAN
Kapur sirih Kg 0.3000 -
Ampelas Lembar 0.2000 -
Alang-alang Ikat 0.2500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 5,586.25


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 5,586.25
N.I.15. Pemasangan 1 m2 wallpaper
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Tukang cat L.06 OH 0.2000 127,500.00 25,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 31,075.00
B BAHAN
Wallpaper m2 1.2000 -
Lem Kg 0.2000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 31,075.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 31,075.00

N.I.16. Pengecatan 1 m2 permukaan baja dengan menie besi


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Tukang cat L.06 OH 0.2000 127,500.00 25,500.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 31,075.00
B BAHAN
Menie besi Kg 0.1000 -
Kuas Buah 0.0100 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 31,075.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 31,075.00

N.I.17. Pengecatan 1 m2 permukaan baja dengan menie besi dengan perancah


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Tukang cat L.06 OH 0.2250 127,500.00 28,687.50
Kepala tukang L.14 OH 0.0225 147,500.00 3,318.75
Mandor L.17 OH 0.0075 150,000.00 1,125.00
JUMLAH TENAGA KERJA 61,256.25
B BAHAN
Menie besi Kg 0.1000 -
Pengencer Liter 0.0100 -
Kuas Buah 0.0100 -
Perancah kayu Buah 0.0020 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 61,256.25


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 61,256.25

N.I.18. Pengecatan 1 m2 permukaan baja galvanis secara manual 4 lapis


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2500 112,500.00 28,125.00
Tukang cat L.06 OH 0.2500 127,500.00 31,875.00
Kepala tukang L.14 OH 0.0250 147,500.00 3,687.50
Mandor L.17 OH 0.0013 150,000.00 195.00
JUMLAH TENAGA KERJA 63,882.50
B BAHAN
Menie A Kg 0.1000 -
Menie B Kg 0.1000 -
Cat Kg 0.0800 -
Kuas Buah 0.0100 -
Pengencer Liter 0.0100 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 63,882.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 63,882.50

N.I.19. Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 1 lapis cat mutakhir
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0600 112,500.00 6,750.00
Tukang cat L.06 OH 0.0600 127,500.00 7,650.00
Kepala tukang L.14 OH 0.0120 147,500.00 1,770.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 16,620.00
B BAHAN
Cat Kg 0.3000 -
Kuas Buah 0.0100 -
Pengencer Liter 0.0100 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 16,620.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 16,620.00

N.I.20. Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 3 lapis


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4000 112,500.00 45,000.00
Tukang cat L.06 OH 0.8000 127,500.00 102,000.00
Kepala tukang L.14 OH 0.0800 147,500.00 11,800.00
Mandor L.17 OH 0.0200 150,000.00 3,000.00
JUMLAH TENAGA KERJA 161,800.00
B BAHAN
Cat dasar Kg 0.1100 -
Cat antara Kg 0.1700 -
Cat Kg 0.0800 -
Kuas Buah 0.0100 -
Pengencer Liter 0.0100 -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 161,800.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 161,800.00

N.I.21. Pengecatan 1 m2 permukaan baja galvanis secara semprot sistem 3 lapis cat mutakhir
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4000 112,500.00 45,000.00
Tukang cat L.06 OH 0.7000 127,500.00 89,250.00
Kepala tukang L.14 OH 0.0700 147,500.00 10,325.00
Mandor L.17 OH 0.0200 150,000.00 3,000.00
JUMLAH TENAGA KERJA 147,575.00
B BAHAN
Cat dasar Kg 0.3000 -
Pengencer Liter 0.0100 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 147,575.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 147,575.00

N.I.22. Pengecatan 10 m2 dengan plitur melamic


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.0000 112,500.00 225,000.00
Tukang cat L.06 OH 12.0000 127,500.00 1,530,000.00
Kepala tukang L.14 OH 1.2000 147,500.00 177,000.00
Mandor L.17 OH 0.1000 150,000.00 15,000.00
JUMLAH TENAGA KERJA 1,947,000.00
B BAHAN
Wood filler Kg 1.5000 -
Woodstain Kg 1.5000 -
Sanding Kg 1.5000 -
Melamic Kg 2.4000 -
Thinner Liter 2.0000 -
Amplas Lembar 6.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,947,000.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,947,000.00
N.I.22a. Pengecatan 1 m2 dengan plitur melamic Rp 194,700.00

II PT-T-38-2000-C
N.II.1. Pengecatan 1 m2 lapis plamir
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Tukang cat L.06 OH 0.0300 127,500.00 3,825.00
Kepala tukang L.14 OH 0.0030 147,500.00 442.50
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 6,667.50
B BAHAN
Plamir Kg 0.1000 -
Amplas Lembar 0.5000 -
Kapi Buah 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 6,667.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 6,667.50

N.II.2. Pengecatan 1 m2 langit-langit 2 lapis dengan cat tembok, menggunakan kuas termasuk plamur
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0800 112,500.00 9,000.00
Tukang cat L.06 OH 0.0600 127,500.00 7,650.00
Kepala tukang L.14 OH 0.0060 147,500.00 885.00
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 18,135.00
B BAHAN
Plamir Kg 0.1000 -
Cat penutup Kg 0.2400 -
Amplas Lembar 0.5000 -
Kuas Buah 0.0150 -
Kapi Buah 0.0150 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 18,135.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 18,135.00

N.II.3. Pengecatan 1 m2 plafond 2 lapis dengan cat tembok menggunakan roll


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0600 112,500.00 6,750.00
Tukang cat L.06 OH 0.0400 127,500.00 5,100.00
Kepala tukang L.14 OH 0.0040 147,500.00 590.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 12,890.00
B BAHAN
Plamir Kg 0.1000 -
Cat penutup Kg 0.4700 -
Amplas Lembar 0.5000 -
Roll Buah 0.0100 -
Kapi Buah 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 12,890.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 12,890.00

III ANALISA SENDIRI


N.III.1. Pengecatan 1 m2 tembok interior
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Tukang cat L.06 OH 0.0630 127,500.00 8,032.50
Kepala tukang L.14 OH 0.0060 147,500.00 885.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 11,617.50
B BAHAN
Plamir Kg 0.1000 -
Cat dasar interior Kg 0.1000 -
Cat penutup interior Kg 0.2600 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 11,617.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 11,617.50

N.III.2. Pengecatan 1 m2 tembok eksterior


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang cat L.06 OH 0.0630 127,500.00 8,032.50
Kepala tukang L.14 OH 0.0060 147,500.00 885.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 20,617.50
B BAHAN
Alkali Kg 0.1120 -
Plamir Kg 0.1000 -
Cat dasar exterior Kg 0.1000 -
Cat penutup exterior Kg 0.2600 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 20,617.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 20,617.50

N.III.3. Pekerjaan 1 m2 waterproofing


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Tukang cat L.06 OH 0.0630 127,500.00 8,032.50
Kepala tukang L.14 OH 0.0600 147,500.00 8,850.00
Mandor L.17 OH 0.0300 150,000.00 4,500.00
JUMLAH TENAGA KERJA 23,632.50
B BAHAN
Sikabon Kg 0.2500 -
Sikacoat Kg 0.3500 -
Kuas Buah 0.1000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,632.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,632.50

N.III.4. Pekerjaan 1 m2 coating batu alam


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Tukang cat L.06 OH 0.0630 127,500.00 8,032.50
Kepala tukang L.14 OH 0.0600 147,500.00 8,850.00
Mandor L.17 OH 0.0300 150,000.00 4,500.00
JUMLAH TENAGA KERJA 23,632.50
B BAHAN
Coating Kg 0.3500 -
Kuas Buah 0.1000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,632.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,632.50

N.III.5. Pekerjaan 1 m2 cat lantai epoxy


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Tukang cat L.06 OH 0.0630 127,500.00 8,032.50
Kepala tukang L.14 OH 0.0600 147,500.00 8,850.00
Mandor L.17 OH 0.0300 150,000.00 4,500.00
JUMLAH TENAGA KERJA 23,632.50
B BAHAN
Cat epoxy Kg 0.4500 -
Kuas Buah 0.1000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,632.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,632.50
O HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
I (PERMEN NOMOR 28/PRT/M/2016)
O.I.1. Pemasangan 1 buah closet duduk/monoblock
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.3000 112,500.00 371,250.00
Tukang batu L.03 OH 1.1000 127,500.00 140,250.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.1600 150,000.00 24,000.00
JUMLAH TENAGA KERJA 536,975.00
B BAHAN
Closet duduk Unit 1.0000 1,325,000.00 1,325,000.00
Perlengkapan % 0.0600 1,325,000.00 79,500.00
JUMLAH HARGA BAHAN 1,404,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,941,475.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,941,475.00

O.I.2. Pemasangan 1 buah closet jongkok porselen


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang batu L.03 OH 1.5000 127,500.00 191,250.00
Kepala tukang L.14 OH 0.1500 147,500.00 22,125.00
Mandor L.17 OH 0.1600 150,000.00 24,000.00
JUMLAH TENAGA KERJA 349,875.00
B BAHAN
Closet jongkok Unit 1.0000 -
Semen portland Kg 6.0000 -
Pasir pasang m3 0.0100 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 349,875.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 349,875.00

O.I.3. Pemasangan 1 buah closet jongkok teraso


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang batu L.03 OH 1.5000 127,500.00 191,250.00
Kepala tukang L.14 OH 0.1500 147,500.00 22,125.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 333,375.00
B BAHAN
Closet jongkok Unit 1.0000 -
Semen portland Kg 6.0000 -
Pasir pasang m3 0.0100 -
Bata merah Buah 7.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 333,375.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 333,375.00

O.I.4. (K3) Pemasangan 1 buah urinoir


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang batu L.03 OH 1.0000 127,500.00 127,500.00
Kepala tukang L.14 OH 0.1000 147,500.00 14,750.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 262,250.00
B BAHAN
Urinoir Unit 1.0000 969,000.00 969,000.00
Semen portland Kg 6.0000 1,325.00 7,950.00
Pasir pasang m3 0.0100 240,000.00 2,400.00
Perlengkapan % 0.3000 979,350.00 293,805.00
JUMLAH HARGA BAHAN 1,273,155.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,535,405.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,535,405.00

O.I.5. (K3) Pemasangan 1 buah wastafel


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.2000 112,500.00 135,000.00
Tukang batu L.03 OH 1.4500 127,500.00 184,875.00
Kepala tukang L.14 OH 0.1500 147,500.00 22,125.00
Mandor L.17 OH 0.0600 150,000.00 9,000.00
JUMLAH TENAGA KERJA 351,000.00
B BAHAN
Wastafel Unit 1.2000 535,500.00 642,600.00
Semen portland Kg 6.0000 1,325.00 7,950.00
Pasir pasang m3 0.0100 240,000.00 2,400.00
Perlengkapan % 0.1200 652,950.00 78,354.00
JUMLAH HARGA BAHAN 731,304.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,082,304.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,082,304.00

O.I.6. (K3) Pemasangan 1 buah bathcuip porselen


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0750 112,500.00 8,437.50
Tukang batu L.03 OH 0.7500 127,500.00 95,625.00
Kepala tukang L.14 OH 0.0750 147,500.00 11,062.50
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 115,575.00
B BAHAN
Bathcuip Unit 1.0000 -
Perlengkapan % 0.2000 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 115,575.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 115,575.00

O.I.7. (K3) Pemasangan 1 buah bak fibreglass vol 1 m3


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.0000 112,500.00 337,500.00
Tukang batu L.03 OH 4.5000 127,500.00 573,750.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.9000 150,000.00 135,000.00
JUMLAH TENAGA KERJA 1,053,625.00
B BAHAN
Bak fibreglass Unit 1.0000 -
Perlengkapan % 0.1200 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,053,625.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,053,625.00

O.I.8. (K3) Pemasangan 1 buah bak mandi batu bata vol 0.30 m3
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 6.0000 112,500.00 675,000.00
Tukang batu L.03 OH 3.0000 127,500.00 382,500.00
Kepala tukang L.14 OH 0.3000 147,500.00 44,250.00
Mandor L.17 OH 0.0300 150,000.00 4,500.00
JUMLAH TENAGA KERJA 1,106,250.00
B BAHAN
Bata merah Buah 150.0000 -
Semen portland Kg 120.0000 -
Pasir pasang m3 0.3000 -
Porselen 11x11 Buah 360.0000 -
Semen warna Kg 6.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,106,250.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,106,250.00

O.I.9. Pemasangan 1 buah bak mandi teraso vol 0.30 m3


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.0000 112,500.00 337,500.00
Tukang batu L.03 OH 4.5000 127,500.00 573,750.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.9000 150,000.00 135,000.00
JUMLAH TENAGA KERJA 1,053,625.00
B BAHAN
Bak fibreglass Unit 1.0000 -
Perlengkapan % 0.1200 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,053,625.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,053,625.00

O.I.10. Pemasangan 1 buah bak air fibreglass vol 1 m3


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang batu L.03 OH 0.4500 127,500.00 57,375.00
Kepala tukang L.14 OH 0.0450 147,500.00 6,637.50
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 100,012.50
B BAHAN
Bak air fibreglass Unit 1.0000 -
Perlengkapan % 0.1200 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,012.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,012.50

O.I.11. (K3) Pemasangan 1 buah bak beton volume 1 m3


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.5000 112,500.00 393,750.00
Tukang batu L.03 OH 4.5000 127,500.00 573,750.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0180 150,000.00 2,700.00
JUMLAH TENAGA KERJA 977,575.00
B BAHAN
Beton 1:2:3 m3 0.9000 -
Baja tulangan Kg 180.0000 -
Kayu bekisting m2 8.0000 -
Ubin porselen Buah 500.0000 -
Perlengkapan % 0.1000 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 977,575.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 977,575.00

O.I.12. Pemasangan 1 buah bak cuci piring stainlessteel


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Tukang batu L.03 OH 0.3000 127,500.00 38,250.00
Kepala tukang L.14 OH 0.0300 147,500.00 4,425.00
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 48,300.00
B BAHAN
Bak cuci piring Unit 1.0000 -
Waterdrain Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 48,300.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 48,300.00

O.I.13. Pemasangan 1 buah bak cuci piring teraso


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0500 112,500.00 5,625.00
Tukang batu L.03 OH 0.5000 127,500.00 63,750.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0250 150,000.00 3,750.00
JUMLAH TENAGA KERJA 80,500.00
B BAHAN
Bak cuci piring Unit 1.0000 -
Waterdrain Buah 1.0000 -
Semen portland Kg 20.0000 -
Pasir pasang m3 0.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 80,500.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 80,500.00

O.I.14. Pemasangan 1 buah floor drain


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0100 112,500.00 1,125.00
Tukang batu L.03 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 16,100.00
B BAHAN
Floor drain Unit 1.0000 32,500.00 32,500.00
JUMLAH HARGA BAHAN 32,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 48,600.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 48,600.00

O.I.15. Pemasangan 1 buah bak kontrol pasangan bata 30 cm x 30 cm tinggi 35 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.1600 112,500.00 243,000.00
Tukang batu L.03 OH 0.7200 127,500.00 91,800.00
Kepala tukang L.14 OH 0.0720 147,500.00 10,620.00
Mandor L.17 OH 0.0110 150,000.00 1,650.00
JUMLAH TENAGA KERJA 347,070.00
B BAHAN
Bata merah Buah 40.0000 -
Semen portland Kg 44.0000 -
Pasir pasang m3 0.0700 -
Pasir beton m3 0.0600 -
Koral beton m3 0.0700 -
Baja tulangan Kg 1.6000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 347,070.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 347,070.00

O.I.16. Pemasangan 1 buah bak kontrol pasangan bata 45 cm x 45 cm tinggi 50 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.2000 112,500.00 360,000.00
Tukang batu L.03 OH 1.1500 127,500.00 146,625.00
Kepala tukang L.14 OH 0.0110 147,500.00 1,622.50
Mandor L.17 OH 0.0160 150,000.00 2,400.00
JUMLAH TENAGA KERJA 510,647.50
B BAHAN
Bata merah Buah 70.0000 -
Semen portland Kg 77.0000 -
Pasir pasang m3 0.1300 -
Pasir beton m3 0.0900 -
Koral beton m3 0.0200 -
Baja tulangan Kg 2.6000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 510,647.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 510,647.50

O.I.17. Pemasangan 1 buah bak kontrol pasangan bata 60 cm x 60 cm tinggi 65 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.2000 112,500.00 360,000.00
Tukang batu L.03 OH 1.1500 127,500.00 146,625.00
Kepala tukang L.14 OH 0.0110 147,500.00 1,622.50
Mandor L.17 OH 0.0160 150,000.00 2,400.00
JUMLAH TENAGA KERJA 510,647.50
B BAHAN
Bata merah Buah 123.0000 -
Semen portland Kg 114.0000 -
Pasir pasang m3 0.1840 -
Pasir beton m3 0.1200 -
Koral beton m3 0.0330 -
Baja tulangan Kg 4.8500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 510,647.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 510,647.50

O.I.18. Pemasangan 1 m1 pipa galvanis diameter 1/2"


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0540 112,500.00 6,075.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0270 150,000.00 4,050.00
JUMLAH TENAGA KERJA 22,927.50
B BAHAN
Pipa galvanis 1/2" m1 1.2000 -
Perlengkapan % 0.3500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 22,927.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 22,927.50

O.I.19. Pemasangan 1 buah kran diameter 1/2" atau 3/4"


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0100 112,500.00 1,125.00
Tukang batu L.03 OH 0.4000 127,500.00 51,000.00
Kepala tukang L.14 OH 0.0400 147,500.00 5,900.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 58,775.00
B BAHAN
Kran air Buah 1.0000 28,750.00 28,750.00
Sealtape Buah 0.0250 5,000.00 125.00
JUMLAH HARGA BAHAN 28,875.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 87,650.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 87,650.00

O.I.20. Pemasangan 1 m1 pipa galvanis diameter 3/4"


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0540 112,500.00 6,075.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0270 150,000.00 4,050.00
JUMLAH TENAGA KERJA 22,927.50
B BAHAN
Pipa galvanis 3/4" m1 1.2000 -
Perlengkapan % 0.3500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 22,927.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 22,927.50

O.I.21. Pemasangan 1 m1 pipa galvanis diameter 1"


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0540 112,500.00 6,075.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0270 150,000.00 4,050.00
JUMLAH TENAGA KERJA 22,927.50
B BAHAN
Pipa galvanis 1" m1 1.2000 -
Perlengkapan % 0.3500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 22,927.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 22,927.50

O.I.22. Pemasangan 1 m1 pipa galvanis diameter 1 1/2"


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1080 112,500.00 12,150.00
Tukang batu L.03 OH 0.1800 127,500.00 22,950.00
Kepala tukang L.14 OH 0.0180 147,500.00 2,655.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 38,505.00
B BAHAN
Pipa galvanis 1 1/2" m1 1.2000 -
Perlengkapan % 0.3500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 38,505.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 38,505.00

O.I.23. Pemasangan 1 m1 pipa galvanis diameter 3"


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1350 112,500.00 15,187.50
Tukang batu L.03 OH 0.2250 127,500.00 28,687.50
Kepala tukang L.14 OH 0.0230 147,500.00 3,392.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 48,317.50
B BAHAN
Pipa galvanis 3" m1 1.2000 -
Perlengkapan % 0.3500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 48,317.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 48,317.50

O.I.24. Pemasangan 1 m1 pipa galvanis diameter 4"


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1350 112,500.00 15,187.50
Tukang batu L.03 OH 0.2250 127,500.00 28,687.50
Kepala tukang L.14 OH 0.0230 147,500.00 3,392.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 48,317.50
B BAHAN
Pipa galvanis 4" m1 1.2000 -
Perlengkapan % 0.3500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 48,317.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 48,317.50

O.I.25. Pemasangan 1 m1 pipa PVC tipe AW diameter 1/2"


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0360 112,500.00 4,050.00
Tukang batu L.03 OH 0.0600 127,500.00 7,650.00
Kepala tukang L.14 OH 0.0060 147,500.00 885.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 12,885.00
B BAHAN
Pipa PVC 1/2" m1 1.2000 -
Perlengkapan % 0.3500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 12,885.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 12,885.00

O.I.26. Pemasangan 1 m1 pipa PVC tipe AW diameter 3/4"


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0360 112,500.00 4,050.00
Tukang batu L.03 OH 0.0600 127,500.00 7,650.00
Kepala tukang L.14 OH 0.0060 147,500.00 885.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 12,885.00
B BAHAN
Pipa PVC 3/4" m1 1.2000 10,750.00 12,900.00
Perlengkapan % 0.3500 12,900.00 4,515.00
JUMLAH HARGA BAHAN 17,415.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 30,300.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 30,300.00

O.I.27. Pemasangan 1 m1 pipa PVC tipe AW diameter 1"


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0360 112,500.00 4,050.00
Tukang batu L.03 OH 0.0600 127,500.00 7,650.00
Kepala tukang L.14 OH 0.0060 147,500.00 885.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 12,885.00
B BAHAN
Pipa PVC 1" m1 1.2000 -
Perlengkapan % 0.3500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 12,885.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 12,885.00

O.I.28. Pemasangan 1 m1 pipa PVC tipe AW diameter 1 1/2"


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0540 112,500.00 6,075.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 19,327.50
B BAHAN
Pipa PVC 1 1/2" m1 1.2000 -
Perlengkapan % 0.3500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 19,327.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 19,327.50

O.I.29. Pemasangan 1 m1 pipa PVC tipe AW diameter 2"


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0540 112,500.00 6,075.00
Tukang batu L.03 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 19,327.50
B BAHAN
Pipa PVC 2" m1 1.2000 36,500.00 43,800.00
Perlengkapan % 0.3500 43,800.00 15,330.00
JUMLAH HARGA BAHAN 59,130.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 78,457.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 78,457.50

O.I.30. Pemasangan 1 m1 pipa PVC tipe AW diameter 2 1/2"


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0810 112,500.00 9,112.50
Tukang batu L.03 OH 0.1350 127,500.00 17,212.50
Kepala tukang L.14 OH 0.0135 147,500.00 1,991.25
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 28,916.25
B BAHAN
Pipa PVC 2 1/2" m1 1.2000 -
Perlengkapan % 0.3500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 28,916.25


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 28,916.25

O.I.31. Pemasangan 1 m1 pipa PVC tipe AW diameter 3"


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0810 112,500.00 9,112.50
Tukang batu L.03 OH 0.1350 127,500.00 17,212.50
Kepala tukang L.14 OH 0.0135 147,500.00 1,991.25
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 28,916.25
B BAHAN
Pipa PVC 3" m1 1.2000 67,000.00 80,400.00
Perlengkapan % 0.3500 80,400.00 28,140.00
JUMLAH HARGA BAHAN 108,540.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 137,456.25


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 137,456.25

O.I.32. Pemasangan 1 m1 pipa PVC tipe AW diameter 4"


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0810 112,500.00 9,112.50
Tukang batu L.03 OH 0.1350 127,500.00 17,212.50
Kepala tukang L.14 OH 0.0135 147,500.00 1,991.25
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 28,916.25
B BAHAN
Pipa PVC 4" m1 1.2000 -
Perlengkapan % 0.3500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 28,916.25


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 28,916.25

O.I.33. Pemasangan 1 m1 pipa air limbah jenis pipa tanah diameter 20 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 0.0800 112,500.00 9,000.00
Tukang batu L.03 OH 0.0400 127,500.00 5,100.00
Kepala tukang L.14 OH 0.0040 147,500.00 590.00
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH BIAYA PASANG 15,290.00
B BAHAN
Pipa tanah Buah 1.6000 -
Semen portland Kg 35.0000 -
Pasir pasang m3 0.0140 -
Pasir urug m3 0.0140 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 15,290.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 15,290.00

O.I.34. Pemasangan 1 m1 pipa air limbah jenis pipa tanah diameter 15 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 0.0600 112,500.00 6,750.00
Tukang batu L.03 OH 0.0300 127,500.00 3,825.00
Kepala tukang L.14 OH 0.0030 147,500.00 442.50
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH BIAYA PASANG 11,467.50
B BAHAN
Pipa tanah dia. 15 Buah 1.6000 -
Semen portland Kg 0.6800 -
Pasir pasang m3 0.0130 -
Pasir urug m3 0.0110 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 11,467.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 11,467.50
O.I.35. Pemasangan 1 m1 pipa beton diameter 15 - 20 cm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 0.1400 112,500.00 15,750.00
Tukang batu L.03 OH 0.0700 127,500.00 8,925.00
Kepala tukang L.14 OH 0.0070 147,500.00 1,032.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH BIAYA PASANG 26,757.50
B BAHAN
Pipa tanah dia 15 Buah 1.1000 -
Bata merah m3 0.0270 -
Semen portland Kg 3.9200 -
Pasir pasang m3 0.0560 -
Pasir urug m3 0.0240 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 26,757.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 26,757.50

O.I.36. Pemasangan 1 m1 pipa beton diameter 30 - 100 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 0.3800 112,500.00 42,750.00
Tukang batu L.03 OH 0.1900 127,500.00 24,225.00
Kepala tukang L.14 OH 0.0190 147,500.00 2,802.50
Mandor L.17 OH 0.0190 150,000.00 2,850.00
JUMLAH BIAYA PASANG 72,627.50
B BAHAN
Pipa tanah dia 15 Buah 1.1000 -
Bata merah m3 0.5500 -
Semen portland Kg 10.3000 -
Pasir pasang m3 0.0610 -
Pasir urug m3 0.0690 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 72,627.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 72,627.50

II ANALISA SENDIRI
O.II.1. Pemasangan 1 buah shower spray
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 0.0100 112,500.00 1,125.00
Tukang batu L.03 OH 0.4000 127,500.00 51,000.00
Kepala tukang L.14 OH 0.0400 147,500.00 5,900.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH BIAYA PASANG 58,775.00
B BAHAN
Shower head spray m1 1.0000 -
Sealtape Buah 0.0250 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 58,775.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 58,775.00

O.II.2. Pemasangan 1 buah kran wastafel


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 0.0100 112,500.00 1,125.00
Tukang batu L.03 OH 0.4000 127,500.00 51,000.00
Kepala tukang L.14 OH 0.0400 147,500.00 5,900.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH BIAYA PASANG 58,775.00
B BAHAN
Kran wastafel Buah 1.0000 375,000.00 375,000.00
Sealtape Buah 0.0250 5,000.00 125.00
JUMLAH HARGA BAHAN 375,125.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 433,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 433,900.00

O.II.3. Pemasangan 1 unit biotank


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 3.0000 112,500.00 337,500.00
Tukang batu L.03 OH 1.5000 127,500.00 191,250.00
Kepala tukang L.14 OH 0.7500 147,500.00 110,625.00
Mandor L.17 OH 0.3000 150,000.00 45,000.00
JUMLAH BIAYA PASANG 684,375.00
B BAHAN
Galian tanah m3 4.7250 88,125.00 416,390.63
Pas. Batako m2 12.0000 55,470.00 665,640.00
Plesteran dinding m2 10.4000 57,337.50 596,310.00
Urugan pasir m3 0.1130 362,522.73 40,965.07
Rabatan beton K.100 m3 0.1130 237,267.50 26,811.23
Plat beton K.250 m3 0.1200 1,083,716.63 130,046.00
Tutup plat beton K.250 m3 0.0250 1,083,716.63 27,092.92
Bekisting plat beton m2 4.0000 354,671.25 1,418,685.00
Pembesian wiremesh M7 Kg 16.0000 13,319.83 213,117.34
Bio tank Unit 1.0000 -
JUMLAH HARGA BAHAN 3,535,058.18
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 4,219,433.18


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 4,219,433.18

O.II.4. Pemasangan 1 unit ground tank


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 3.0000 112,500.00 337,500.00
Tukang batu L.03 OH 1.5000 127,500.00 191,250.00
Kepala tukang L.14 OH 0.7500 147,500.00 110,625.00
Mandor L.17 OH 0.3000 150,000.00 45,000.00
JUMLAH BIAYA PASANG 684,375.00
B BAHAN
Galian tanah m3 4.7250 88,125.00 416,390.63
Pas. Batako m2 12.0000 55,470.00 665,640.00
Plesteran dinding m2 10.4000 57,337.50 596,310.00
Urugan pasir m3 0.1130 362,522.73 40,965.07
Rabatan beton K.100 m3 0.1130 237,267.50 26,811.23
Plat beton K.250 m3 0.1200 1,083,716.63 130,046.00
Tutup plat beton K.250 m3 0.0250 1,083,716.63 27,092.92
Pembesian wiremesh M7 Kg 21.7500 13,319.83 289,706.39
Tangki air 1000 liter Unit 1.0000 -
JUMLAH HARGA BAHAN 2,192,962.22
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 2,877,337.22


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 2,877,337.22

O.II.5. Pemasangan 1 unit peresapan


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 2.0000 112,500.00 225,000.00
Tukang batu L.03 OH 0.7500 127,500.00 95,625.00
Kepala tukang L.14 OH 0.5000 147,500.00 73,750.00
Mandor L.17 OH 0.1000 150,000.00 15,000.00
JUMLAH BIAYA PASANG 409,375.00
B BAHAN
Galian tanah m3 1.1550 88,125.00 101,784.38
Buis beton Buah 3.0000 -
Material pengisi batu apung m2 1.0000 -

Material pengisi ijuk m2 1.0000 -

Pas. Bata merah tebal 1 bata m2 0.6070 100,450.00 60,973.15

Plat beton K.250 m3 0.0660 1,083,716.63 71,525.30


Pembesian wiremesh M7 Kg 9.0000 13,319.83 119,878.51
Pipa PVC 4" m1 3.0000 -
Pipa PVC 1" m1 1.5000 -
JUMLAH HARGA BAHAN 354,161.33
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 763,536.33


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 763,536.33

O.II.6. Pemasangan 1 unit biopori


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang batu L.03 OH 0.6000 127,500.00 76,500.00
Kepala tukang L.14 OH 0.4000 147,500.00 59,000.00
Mandor L.17 OH 0.1000 150,000.00 15,000.00
JUMLAH BIAYA PASANG 263,000.00
B BAHAN
Galian tanah m3 1.1550 88,125.00 101,784.38
Buis beton Buah 3.0000 -

Material pengisi batu apung m2 1.0000 -

Material pengisi ijuk m2 1.0000 -

Pas. Bata merah tebal 1 bata m2 0.6070 100,450.00 60,973.15

Plat beton K.250 m3 0.0660 1,083,716.63 71,525.30


Pembesian wiremesh M7 Kg 9.0000 13,319.83 119,878.51
JUMLAH HARGA BAHAN 354,161.33
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 617,161.33


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 617,161.33

O.II.7. Pemasangan 1 buah tempat sabun


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 0.0100 112,500.00 1,125.00
Tukang batu L.03 OH 0.1000 127,500.00 12,750.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH BIAYA PASANG 16,100.00
B BAHAN
Tempat sabun Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 16,100.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 16,100.00

O.II.8. Pemasangan 1 unit tangki air stainless kapasitas 1000 liter


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 3.0000 112,500.00 337,500.00
Tukang pipa L.07 OH 3.0000 127,500.00 382,500.00
Kepala tukang L.14 OH 0.2000 147,500.00 29,500.00
Mandor L.17 OH 0.0200 150,000.00 3,000.00
JUMLAH BIAYA PASANG 752,500.00
B BAHAN
Tangki air stainless 1000
Unit 1.0000 -
liter
Aksesoris pipa % 0.3500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 752,500.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 752,500.00

O.II.9. Pemasangan 1 unit pompa pendorong


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang pipa L.07 OH 1.0000 127,500.00 127,500.00
Kepala tukang L.14 OH 0.1000 147,500.00 14,750.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH BIAYA PASANG 256,250.00
B BAHAN
Pompa jet pump Unit 1.0000 -
Aksesoris pipa % 0.3500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 256,250.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 256,250.00

O.II.10. Pemasangan 1 unit pompa submersible


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang pipa L.07 OH 1.0000 127,500.00 127,500.00
Kepala tukang L.14 OH 0.1000 147,500.00 14,750.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH BIAYA PASANG 256,250.00
B BAHAN
Pompa submersible Unit 1.0000 -
Pipa dia 1 1/4" m1 80.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 256,250.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 256,250.00

O.II.11. Pemasangan 1 unit pompa transfer


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 2.8000 112,500.00 315,000.00
Tukang pipa L.07 OH 2.1000 127,500.00 267,750.00
Kepala tukang L.14 OH 0.6200 147,500.00 91,450.00
Mandor L.17 OH 0.1000 150,000.00 15,000.00
JUMLAH BIAYA PASANG 689,200.00
B BAHAN
Pompa transfer Unit 1.0000 -
Material bantu % 0.0500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 689,200.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 689,200.00

O.II.12. Pemasangan 1 m1 pipa PPR dia. 20 mm (1/2") PN-10


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 0.0500 112,500.00 5,625.00
Tukang pipa L.07 OH 0.0300 127,500.00 3,825.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH BIAYA PASANG 13,900.00
B BAHAN
Pipa PPR m1 1.2000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Alat bantu % 0.3500 - -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 13,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 13,900.00

O.II.13. Pemasangan 1 m1 pipa PPR dia. 25 mm (3/4") PN-10


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 0.0500 112,500.00 5,625.00
Tukang pipa L.07 OH 0.0300 127,500.00 3,825.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH BIAYA PASANG 13,900.00
B BAHAN
Pipa PPR m1 1.2000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Alat bantu % 0.3500 - -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 13,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 13,900.00

O.II.14. Pemasangan 1 m1 pipa PPR dia. 40 mm (1 1/4") PN-10


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A BIAYA PASANG
Pekerja L.01 OH 0.0540 112,500.00 6,075.00
Tukang pipa L.07 OH 0.0900 127,500.00 11,475.00
Kepala tukang L.14 OH 0.0090 147,500.00 1,327.50
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH BIAYA PASANG 19,327.50
B BAHAN
Pipa PPR m1 1.2000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Alat bantu % 0.3500 - -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 19,327.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 19,327.50
P HARGA SATUAN PEKERJAAN PEMASANGAN PIPA DI LUAR GEDUNG
I (PERMEN NOMOR 28/PRT/M/2016)
P.I.1. (K3) Pemasangan 1 m pipa PVC Ø 63 mm
Jumlah
Harga Satuan
\ Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0810 112,500.00 9,112.50
Tukang pipa L.07 OH 0.0410 127,500.00 5,227.50
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 15,540.00
B BAHAN
Pipa PVC Ø 63 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0060 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 15,540.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 15,540.00

Catatan:
Koefisien peralatan yang digunakan pada A.4.8.4.1 ini adalah seperti yang tercantum pada tabel.
Apabila ada tambahan perlatan yang digunakan, harus disesuaikan dengan spesifikasi dan
gambar kerja.

P.I.2. (K3) Pemasangan 1 m pipa PVC Ø 90 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0940 112,500.00 10,575.00
Tukang pipa L.07 OH 0.0470 127,500.00 5,992.50
Mandor L.17 OH 0.0090 150,000.00 1,350.00
JUMLAH TENAGA KERJA 17,917.50
B BAHAN
Pipa PVC Ø 90 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0080 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 17,917.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 17,917.50

P.I.3. (K3) Pemasangan 1 m pipa PVC Ø 110 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1050 112,500.00 11,812.50
Tukang pipa L.07 OH 0.0530 127,500.00 6,757.50
Mandor L.17 OH 0.0110 150,000.00 1,650.00
JUMLAH TENAGA KERJA 20,220.00
B BAHAN
Pipa PVC Ø 110 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.010 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 20,220.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 20,220.00

P.I.4. (K3) Pemasangan 1 m pipa PVC Ø 150 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1180 112,500.00 13,275.00
Tukang pipa L.07 OH 0.0590 127,500.00 7,522.50
Mandor L.17 OH 0.0120 150,000.00 1,800.00
JUMLAH TENAGA KERJA 22,597.50
B BAHAN
Pipa PVC Ø 150 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0120 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 22,597.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 22,597.50

P.I.5. (K3) Pemasangan 1 m pipa PVC Ø 200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1890 112,500.00 21,262.50
Tukang pipa L.07 OH 0.0950 127,500.00 12,112.50
Mandor L.17 OH 0.0190 150,000.00 2,850.00
JUMLAH TENAGA KERJA 36,225.00
B BAHAN
Pipa PVC Ø 200 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0240 -
crane 2 T
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 36,225.00
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 36,225.00

P.I.6. (K3) Pemasangan 1 m pipa PVC Ø 250 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2560 112,500.00 28,800.00
Tukang pipa L.07 OH 0.1280 127,500.00 16,320.00
Mandor L.17 OH 0.0260 150,000.00 3,900.00
JUMLAH TENAGA KERJA 49,020.00
B BAHAN
Pipa PVC Ø 250 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0340 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 49,020.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 49,020.00

P.I.7. (K3) Pemasangan 1 m pipa PVC Ø 300 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2940 112,500.00 33,075.00
Tukang pipa L.07 OH 0.1470 127,500.00 18,742.50
Mandor L.17 OH 0.0290 150,000.00 4,350.00
JUMLAH TENAGA KERJA 56,167.50
B BAHAN
Pipa PVC Ø 300 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0400 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 56,167.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 56,167.50

P.I.8. (K3) Pemasangan 1 m pipa PVC Ø 400 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5440 112,500.00 61,200.00
Tukang pipa L.07 OH 0.2720 127,500.00 34,680.00
Mandor L.17 OH 0.0540 150,000.00 8,100.00
JUMLAH TENAGA KERJA 103,980.00
B BAHAN
Pipa PVC Ø 400 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0800 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 103,980.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 103,980.00

P.I.9. (K3) Pemasangan 1 m pipa PVC Ø 450 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.669 112,500.00 75,262.50
Tukang pipa L.07 OH 0.335 127,500.00 42,712.50
Mandor L.17 OH 0.067 150,000.00 10,050.00
JUMLAH TENAGA KERJA 128,025.00
B BAHAN
Pipa PVC Ø 450 mm m1 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.100 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 128,025.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 128,025.00

P.I.10. (K3) Pemasangan 1 m pipa PVC Ø 500 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8090 112,500.00 91,012.50
Tukang pipa L.07 OH 0.4050 127,500.00 51,637.50
Mandor L.17 OH 0.0810 150,000.00 12,150.00
JUMLAH TENAGA KERJA 154,800.00
B BAHAN
Pipa PVC Ø 500 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.1220 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 154,800.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 154,800.00

P.I.11. (K3) Pemasangan 1 m pipa PVC Ø 600 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9570 112,500.00 107,662.50
Tukang pipa L.07 OH 0.4790 127,500.00 61,072.50
Mandor L.17 OH 0.0960 150,000.00 14,400.00
JUMLAH TENAGA KERJA 183,135.00
B BAHAN
Pipa PVC Ø 600 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.1450 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 183,135.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 183,135.00

P.I.12. (K3) Pemasangan 1 m pipa PVC Ø 800 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6180 112,500.00 182,025.00
Tukang pipa L.07 OH 0.8090 127,500.00 103,147.50
Mandor L.17 OH 0.1620 150,000.00 24,300.00
JUMLAH TENAGA KERJA 309,472.50
B BAHAN
Pipa PVC Ø 800 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.2500 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 309,472.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 309,472.50

P.I.13. (K3) Pemasangan 1 m pipa PVC Ø 900 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6910 112,500.00 190,237.50
Tukang pipa L.07 OH 0.8460 127,500.00 107,865.00
Mandor L.17 OH 0.1690 150,000.00 25,350.00
JUMLAH TENAGA KERJA 323,452.50
B BAHAN
Pipa PVC Ø 900 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.2620 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 323,452.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 323,452.50

P.I.14. (K3) Pemasangan 1 m pipa PVC Ø 1000 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.8950 112,500.00 213,187.50
Tukang pipa L.07 OH 0.9480 127,500.00 120,870.00
Mandor L.17 OH 0.1900 150,000.00 28,500.00
JUMLAH TENAGA KERJA 362,557.50
B BAHAN
Pipa PVC Ø 1000 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.2940 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 362,557.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 362,557.50

P.I.15. (K3) Pemasangan 1 m pipa PVC Ø 1100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.0990 112,500.00 236,137.50
Tukang pipa L.07 OH 1.0500 127,500.00 133,875.00
Mandor L.17 OH 0.2100 150,000.00 31,500.00
JUMLAH TENAGA KERJA 401,512.50
B BAHAN
Pipa PVC Ø 1100 mm m1 1.000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.327 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 401,512.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 401,512.50
P.I.16. (K3) Pemasangan 1 m pipa PVC Ø 1200 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.3030 112,500.00 259,087.50
Tukang pipa L.07 OH 1.1520 127,500.00 146,880.00
Mandor L.17 OH 0.2300 150,000.00 34,500.00
JUMLAH TENAGA KERJA 440,467.50
B BAHAN
Pipa PVC Ø 1200 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.3590 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 440,467.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 440,467.50

P.I.17. (K3) Pemasangan 1 m pipa HDPE Ø 63 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0350 112,500.00 3,937.50
Tukang pipa L.07 OH 0.0170 127,500.00 2,167.50
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 6,555.00
B BAHAN
Pipa HDPE Ø 63 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0190 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 6,555.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 6,555.00

P.I.18. (K3) Pemasangan 1 m pipa HDPE Ø 100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0400 112,500.00 4,500.00
Tukang pipa L.07 OH 0.0200 127,500.00 2,550.00
Mandor L.17 OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 7,650.00
B BAHAN
Pipa HDPE Ø 100 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0190 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 7,650.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 7,650.00

P.I.19. (K3) Pemasangan 1 m pipa HDPE Ø 125 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0450 112,500.00 5,062.50
Tukang pipa L.07 OH 0.0230 127,500.00 2,932.50
Mandor L.17 OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 8,745.00
B BAHAN
Pipa HDPE Ø 125 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0190 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 8,745.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 8,745.00

P.I.20. (K3) Pemasangan 1 m pipa HDPE Ø 150 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0620 112,500.00 6,975.00
Tukang pipa L.07 OH 0.0310 127,500.00 3,952.50
Mandor L.17 OH 0.0060 150,000.00 900.00
JUMLAH TENAGA KERJA 11,827.50
B BAHAN
Pipa HDPE Ø 150 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0190 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 11,827.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 11,827.50

P.I.21. (K3) Pemasangan 1 m pipa HDPE Ø 200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1020 112,500.00 11,475.00
Tukang pipa L.07 OH 0.0510 127,500.00 6,502.50
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 19,477.50
B BAHAN
Pipa HDPE Ø 200 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0190 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 19,477.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 19,477.50

P.I.22. (K3) Pemasangan 1 m pipa HDPE Ø 250 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1330 112,500.00 14,962.50
Tukang pipa L.07 OH 0.0670 127,500.00 8,542.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 25,455.00
B BAHAN
Pipa HDPE Ø 250 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0420 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 25,455.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 25,455.00

P.I.23. (K3) Pemasangan 1 m pipa HDPE Ø 300 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1700 112,500.00 19,125.00
Tukang pipa L.07 OH 0.0850 127,500.00 10,837.50
Mandor L.17 OH 0.0170 150,000.00 2,550.00
JUMLAH TENAGA KERJA 32,512.50
B BAHAN
Pipa HDPE Ø 300 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0650 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 32,512.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 32,512.50

P.I.24. (K3) Pemasangan 1 m pipa HDPE Ø 400 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2900 112,500.00 32,625.00
Tukang pipa L.07 OH 0.1450 127,500.00 18,487.50
Mandor L.17 OH 0.0290 150,000.00 4,350.00
JUMLAH TENAGA KERJA 55,462.50
B BAHAN
Pipa HDPE Ø 400 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.1520 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 55,462.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 55,462.50

P.I.25. (K3) Pemasangan 1 m pipa HDPE Ø 450 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3590 112,500.00 40,387.50
Tukang pipa L.07 OH 0.1800 127,500.00 22,950.00
Mandor L.17 OH 0.0360 150,000.00 5,400.00
JUMLAH TENAGA KERJA 68,737.50
B BAHAN
Pipa HDPE Ø 450 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.2000 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 68,737.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 68,737.50

P.I.26. (K3) Pemasangan 1 m pipa HDPE Ø 500 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4330 112,500.00 48,712.50
Tukang pipa L.07 OH 0.2160 127,500.00 27,540.00
Mandor L.17 OH 0.0430 150,000.00 6,450.00
JUMLAH TENAGA KERJA 82,702.50
B BAHAN
Pipa HDPE Ø 500 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.2510 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 82,702.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 82,702.50

P.I.27. (K3) Pemasangan 1 m pipa HDPE Ø 600 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5120 112,500.00 57,600.00
Tukang pipa L.07 OH 0.2560 127,500.00 32,640.00
Mandor L.17 OH 0.0510 150,000.00 7,650.00
JUMLAH TENAGA KERJA 97,890.00
B BAHAN
Pipa HDPE Ø 600 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.3070 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 97,890.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 97,890.00

P.I.28. (K3) Pemasangan 1 m pipa HDPE Ø 800 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8930 112,500.00 100,462.50
Tukang pipa L.07 OH 0.4460 127,500.00 56,865.00
Mandor L.17 OH 0.0890 150,000.00 13,350.00
JUMLAH TENAGA KERJA 170,677.50
B BAHAN
Pipa HDPE Ø 800 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.5730 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 170,677.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 170,677.50

P.I.29. (K3) Pemasangan 1 m pipa HDPE Ø 900 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.3530 112,500.00 152,212.50
Tukang pipa L.07 OH 0.6770 127,500.00 86,317.50
Mandor L.17 OH 0.1350 150,000.00 20,250.00
JUMLAH TENAGA KERJA 258,780.00
B BAHAN
Pipa HDPE Ø 900 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.8830 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 258,780.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 258,780.00

P.I.30. (K3) Pemasangan 1 m pipa HDPE Ø 1000 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6590 112,500.00 186,637.50
Tukang pipa L.07 OH 0.8300 127,500.00 105,825.00
Mandor L.17 OH 0.1660 150,000.00 24,900.00
JUMLAH TENAGA KERJA 317,362.50
B BAHAN
Pipa HDPE Ø 1000 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 1.0930 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 317,362.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 317,362.50

P.I.31. (K3) Pemasangan 1 m pipa HDPE Ø 1100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.8180 112,500.00 204,525.00
Tukang pipa L.07 OH 0.9090 127,500.00 115,897.50
Mandor L.17 OH 0.1820 150,000.00 27,300.00
JUMLAH TENAGA KERJA 347,722.50
B BAHAN
Pipa HDPE Ø 1100 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 1.2050 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 347,722.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 347,722.50

P.I.32. (K3) Pemasangan 1 m pipa HDPE Ø 1200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.3700 112,500.00 266,625.00
Tukang pipa L.07 OH 1.1850 127,500.00 151,087.50
Mandor L.17 OH 0.2370 150,000.00 35,550.00
JUMLAH TENAGA KERJA 453,262.50
B BAHAN
Pipa HDPE Ø 1200 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 1.5840 - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 453,262.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 453,262.50

P.I.33. (K3) Pemasangan 1 m pipa GIP Ø 63 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3450 112,500.00 38,812.50
Tukang pipa L.07 OH 0.1720 127,500.00 21,930.00
Mandor L.17 OH 0.0340 150,000.00 5,100.00
JUMLAH TENAGA KERJA 65,842.50
B BAHAN
Pipa GIP Ø 63 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari - -
crane 2 T
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 65,842.50
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 65,842.50

P.I.34. (K3) Pemasangan 1 m pipa GIP Ø 100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4000 112,500.00 45,000.00
Tukang pipa L.07 OH 0.2000 127,500.00 25,500.00
Mandor L.17 OH 0.0400 150,000.00 6,000.00
JUMLAH TENAGA KERJA 76,500.00
B BAHAN
Pipa GIP Ø 100 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 76,500.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 76,500.00

P.I.35. (K3) Pemasangan 1 m pipa GIP Ø 125 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4480 112,500.00 50,400.00
Tukang pipa L.07 OH 0.2240 127,500.00 28,560.00
Mandor L.17 OH 0.0450 150,000.00 6,750.00
JUMLAH TENAGA KERJA 85,710.00
B BAHAN
Pipa GIP Ø 125 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 85,710.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 85,710.00

P.I.36. (K3) Pemasangan 1 m pipa GIP Ø 150 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5060 112,500.00 56,925.00
Tukang pipa L.07 OH 0.2530 127,500.00 32,257.50
Mandor L.17 OH 0.0510 150,000.00 7,650.00
JUMLAH TENAGA KERJA 96,832.50
B BAHAN
Pipa GIP Ø 150 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari - - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 96,832.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 96,832.50

P.I.37. (K3) Pemasangan 1 m pipa GIP Ø 200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7960 112,500.00 89,550.00
Tukang pipa L.07 OH 0.3980 127,500.00 50,745.00
Mandor L.17 OH 0.0800 150,000.00 12,000.00
JUMLAH TENAGA KERJA 152,295.00
B BAHAN
Pipa GIP Ø 200 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari - - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 152,295.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 152,295.00

P.I.38. (K3) Pemasangan 1 m pipa GIP Ø 250 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9490 112,500.00 106,762.50
Tukang pipa L.07 OH 0.4750 127,500.00 60,562.50
Mandor L.17 OH 0.0950 150,000.00 14,250.00
JUMLAH TENAGA KERJA 181,575.00
B BAHAN
Pipa GIP Ø 250 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 181,575.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 181,575.00

P.I.39. (K3) Pemasangan 1 m pipa GIP Ø 300 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9580 112,500.00 107,775.00
Tukang pipa L.07 OH 0.4790 127,500.00 61,072.50
Mandor L.17 OH 0.0960 150,000.00 14,400.00
JUMLAH TENAGA KERJA 183,247.50
B BAHAN
Pipa GIP Ø 300 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari - - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 183,247.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 183,247.50

P.I.40. (K3) Pemasangan 1 m pipa GIP Ø 400 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.2120 112,500.00 136,350.00
Tukang pipa L.07 OH 0.6060 127,500.00 77,265.00
Mandor L.17 OH 0.1210 150,000.00 18,150.00
JUMLAH TENAGA KERJA 231,765.00
B BAHAN
Pipa GIP Ø 400 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 231,765.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 231,765.00

P.I.41. (K3) Pemasangan 1 m pipa GIP Ø 450 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.3530 112,500.00 152,212.50
Tukang pipa L.07 OH 0.6760 127,500.00 86,190.00
Mandor L.17 OH 0.1350 150,000.00 20,250.00
JUMLAH TENAGA KERJA 258,652.50
B BAHAN
Pipa GIP Ø 450 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari - - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 258,652.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 258,652.50

P.I.42. (K3) Pemasangan 1 m pipa GIP Ø 500 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.4690 112,500.00 165,262.50
Tukang pipa L.07 OH 0.7350 127,500.00 93,712.50
Mandor L.17 OH 0.1470 150,000.00 22,050.00
JUMLAH TENAGA KERJA 281,025.00
B BAHAN
Pipa GIP Ø 500 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 281,025.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 281,025.00

P.I.43. (K3) Pemasangan 1 m pipa GIP Ø 600 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.3270 112,500.00 149,287.50
Tukang pipa L.07 OH 0.6640 127,500.00 84,660.00
Mandor L.17 OH 0.1330 150,000.00 19,950.00
JUMLAH TENAGA KERJA 253,897.50
B BAHAN
Pipa GIP Ø 600 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari - - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 253,897.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 253,897.50
P.I.44. (K3) Pemasangan 1 m pipa GIP Ø 800 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.3270 112,500.00 261,787.50
Tukang pipa L.07 OH 1.1630 127,500.00 148,282.50
Mandor L.17 OH 0.2330 150,000.00 34,950.00
JUMLAH TENAGA KERJA 445,020.00
B BAHAN
Pipa GIP Ø 800 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 445,020.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 445,020.00

P.I.45. (K3) Pemasangan 1 m pipa GIP Ø 900 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.6230 112,500.00 295,087.50
Tukang pipa L.07 OH 1.3120 127,500.00 167,280.00
Mandor L.17 OH 0.2620 150,000.00 39,300.00
JUMLAH TENAGA KERJA 501,667.50
B BAHAN
Pipa GIP Ø 900 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 501,667.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 501,667.50

P.I.46. (K3) Pemasangan 1 m pipa GIP Ø 1000 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.9110 112,500.00 327,487.50
Tukang pipa L.07 OH 1.4560 127,500.00 185,640.00
Mandor L.17 OH 0.2910 150,000.00 43,650.00
JUMLAH TENAGA KERJA 556,777.50
B BAHAN
Pipa GIP Ø 1000 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 556,777.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 556,777.50

P.I.47. (K3) Pemasangan 1 m pipa GIP Ø 1100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.2000 112,500.00 360,000.00
Tukang pipa L.07 OH 1.6000 127,500.00 204,000.00
Mandor L.17 OH 0.3200 150,000.00 48,000.00
JUMLAH TENAGA KERJA 612,000.00
B BAHAN
Pipa GIP Ø 1100 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 612,000.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 612,000.00

P.I.48. (K3) Pemasangan 1 m pipa GIP Ø 1200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.4880 112,500.00 392,400.00
Tukang pipa L.07 OH 1.7440 127,500.00 222,360.00
Mandor L.17 OH 0.3490 150,000.00 52,350.00
JUMLAH TENAGA KERJA 667,110.00
B BAHAN
Pipa GIP Ø 1200 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 667,110.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 667,110.00

P.I.49. (K3) Pemasangan 1 m pipa DCI Ø 100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4890 112,500.00 55,012.50
Tukang pipa L.07 OH 0.0980 127,500.00 12,495.00
Mandor L.17 OH 0.0490 150,000.00 7,350.00
JUMLAH TENAGA KERJA 74,857.50
B BAHAN
Pipa DCI Ø 100 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.3800 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 74,857.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 74,857.50

P.I.50. (K3) Pemasangan 1 m pipa DCI Ø 125 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5470 112,500.00 61,537.50
Tukang pipa L.07 OH 0.1090 127,500.00 13,897.50
Mandor L.17 OH 0.0550 150,000.00 8,250.00
JUMLAH TENAGA KERJA 83,685.00
B BAHAN
Pipa DCI Ø 125 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.3800 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 83,685.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 83,685.00

P.I.51. (K3) Pemasangan 1 m pipa DCI Ø 150 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6130 112,500.00 68,962.50
Tukang pipa L.07 OH 0.1230 127,500.00 15,682.50
Mandor L.17 OH 0.0610 150,000.00 9,150.00
JUMLAH TENAGA KERJA 93,795.00
B BAHAN
Pipa DCI Ø 150 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.3800 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 93,795.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 93,795.00

P.I.52. (K3) Pemasangan 1 m pipa DCI Ø 200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8550 112,500.00 96,187.50
Tukang pipa L.07 OH 0.1710 127,500.00 21,802.50
Mandor L.17 OH 0.0850 150,000.00 12,750.00
JUMLAH TENAGA KERJA 130,740.00
B BAHAN
Pipa DCI Ø 200 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.3800 - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 130,740.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 130,740.00

P.I.53. (K3) Pemasangan 1 m pipa DCI Ø 250 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9510 112,500.00 106,987.50
Tukang pipa L.07 OH 0.1900 127,500.00 24,225.00
Mandor L.17 OH 0.0950 150,000.00 14,250.00
JUMLAH TENAGA KERJA 145,462.50
B BAHAN
Pipa DCI Ø 250 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0500 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 145,462.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 145,462.50

P.I.54. (K3) Pemasangan 1 m pipa DCI Ø 300 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9730 112,500.00 109,462.50
Tukang pipa L.07 OH 0.1950 127,500.00 24,862.50
Mandor L.17 OH 0.0970 150,000.00 14,550.00
JUMLAH TENAGA KERJA 148,875.00
B BAHAN
Pipa DCI Ø 300 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0710 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 148,875.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 148,875.00

P.I.55. (K3) Pemasangan 1 m pipa DCI Ø 400 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5450 112,500.00 173,812.50
Tukang pipa L.07 OH 0.3090 127,500.00 39,397.50
Operator alat berat L.21a OH 0.0930 175,000.00 16,275.00
Mandor L.17 OH 0.1540 150,000.00 23,100.00
JUMLAH TENAGA KERJA 252,585.00
B BAHAN
Pipa DCI Ø 400 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.0230 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.0310 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 252,585.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 252,585.00

P.I.56. (K3) Pemasangan 1 m pipa DCI Ø 450 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.8130 112,500.00 203,962.50
Tukang pipa L.07 OH 0.3630 127,500.00 46,282.50
Operator alat berat L.21a OH 0.1430 175,000.00 25,025.00
Mandor L.17 OH 0.1810 150,000.00 27,150.00
JUMLAH TENAGA KERJA 302,420.00
B BAHAN
Pipa DCI Ø 450 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.0290 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.0390 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 302,420.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 302,420.00

P.I.57. (K3) Pemasangan 1 m pipa DCI Ø 500 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.0470 112,500.00 230,287.50
Tukang pipa L.07 OH 0.4090 127,500.00 52,147.50
Operator alat berat L.21a OH 0.1930 175,000.00 33,775.00
Mandor L.17 OH 0.2050 150,000.00 30,750.00
JUMLAH TENAGA KERJA 346,960.00
B BAHAN
Pipa DCI Ø 450 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.0340 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.0450 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 346,960.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 346,960.00

P.I.58. (K3) Pemasangan 1 m pipa DCI Ø 600 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.0110 112,500.00 226,237.50
Tukang pipa L.07 OH 0.4020 127,500.00 51,255.00
Operator alat berat L.21a OH 0.2930 175,000.00 51,275.00
Mandor L.17 OH 0.2010 150,000.00 30,150.00
JUMLAH TENAGA KERJA 358,917.50
B BAHAN
Pipa DCI Ø 600 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.0580 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.0770 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 358,917.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 358,917.50

P.I.59. (K3) Pemasangan 1 m pipa DCI Ø 800 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.8590 112,500.00 434,137.50
Tukang pipa L.07 OH 0.7720 127,500.00 98,430.00
Operator alat berat L.21a OH 0.4930 175,000.00 86,275.00
Mandor L.17 OH 0.3860 150,000.00 57,900.00
JUMLAH TENAGA KERJA 676,742.50
B BAHAN
Pipa DCI Ø 800 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.0840 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.2250 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 676,742.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 676,742.50

P.I.60. (K3) Pemasangan 1 m pipa DCI Ø 900 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 4.9950 112,500.00 561,937.50
Tukang pipa L.07 OH 0.9990 127,500.00 127,372.50
Operator alat berat L.21a OH 0.5930 175,000.00 103,775.00
Mandor L.17 OH 0.4990 150,000.00 74,850.00
JUMLAH TENAGA KERJA 867,935.00
B BAHAN
Pipa DCI Ø 900 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.0930 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.2480 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 867,935.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 867,935.00
P.I.61. (K3) Pemasangan 1 m pipa DCI Ø 1000 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 5.9310 112,500.00 667,237.50
Tukang pipa L.07 OH 1.1860 127,500.00 151,215.00
Operator alat berat L.21a OH 0.7930 175,000.00 138,775.00
Mandor L.17 OH 0.6930 150,000.00 103,950.00
JUMLAH TENAGA KERJA 1,061,177.50
B BAHAN
Pipa DCI Ø 1000 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.1120 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.2980 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,061,177.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,061,177.50

P.I.62. (K3) Pemasangan 1 m pipa DCI Ø 1100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 6.9490 112,500.00 781,762.50
Tukang pipa L.07 OH 1.3900 127,500.00 177,225.00
Operator alat berat L.21a OH 0.7930 175,000.00 138,775.00
Mandor L.17 OH 0.6950 150,000.00 104,250.00
JUMLAH TENAGA KERJA 1,202,012.50
B BAHAN
Pipa DCI Ø 1100 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.1520 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.3040 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,202,012.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,202,012.50

P.I.63. (K3) Pemasangan 1 m pipa DCI Ø 1200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 8.0560 112,500.00 906,300.00
Tukang pipa L.07 OH 1.6110 127,500.00 205,402.50
Operator alat berat L.21a OH 0.8930 175,000.00 156,275.00
Mandor L.17 OH 0.8060 150,000.00 120,900.00
JUMLAH TENAGA KERJA 1,388,877.50
B BAHAN
Pipa DCI Ø 1200 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.1800 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.3600 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,388,877.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,388,877.50

P.I.64. (K3) Pemasangan 1 m pipa baja Ø 63 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4990 112,500.00 56,137.50
Tukang pipa L.07 OH 0.1000 127,500.00 12,750.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 76,387.50
B BAHAN
Pipa baja Ø 63 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0040 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 76,387.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 76,387.50

P.I.65. (K3) Pemasangan 1 m pipa baja Ø 100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5790 112,500.00 65,137.50
Tukang pipa L.07 OH 0.1160 127,500.00 14,790.00
Mandor L.17 OH 0.0580 150,000.00 8,700.00
JUMLAH TENAGA KERJA 88,627.50
B BAHAN
Pipa baja Ø 100 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0040 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 88,627.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 88,627.50

P.I.66. (K3) Pemasangan 1 m pipa baja Ø 125 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6480 112,500.00 72,900.00
Tukang pipa L.07 OH 0.1300 127,500.00 16,575.00
Mandor L.17 OH 0.0650 150,000.00 9,750.00
JUMLAH TENAGA KERJA 99,225.00
B BAHAN
Pipa baja Ø 125 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0040 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 99,225.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 99,225.00

P.I.67. (K3) Pemasangan 1 m pipa baja Ø 150 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7080 112,500.00 79,650.00
Tukang pipa L.07 OH 0.1420 127,500.00 18,105.00
Mandor L.17 OH 0.0710 150,000.00 10,650.00
JUMLAH TENAGA KERJA 108,405.00
B BAHAN
Pipa baja Ø 150 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0040 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 108,405.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 108,405.00

P.I.68. (K3) Pemasangan 1 m pipa baja Ø 200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.1130 112,500.00 125,212.50
Tukang pipa L.07 OH 0.2230 127,500.00 28,432.50
Mandor L.17 OH 0.1110 150,000.00 16,650.00
JUMLAH TENAGA KERJA 170,295.00
B BAHAN
Pipa baja Ø 200 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0040 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 170,295.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 170,295.00

P.I.69. (K3) Pemasangan 1 m pipa baja Ø 250 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.3250 112,500.00 149,062.50
Tukang pipa L.07 OH 0.2650 127,500.00 33,787.50
Mandor L.17 OH 0.1330 150,000.00 19,950.00
JUMLAH TENAGA KERJA 202,800.00
B BAHAN
Pipa baja Ø 250 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0040 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 202,800.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 202,800.00

P.I.70. (K3) Pemasangan 1 m pipa baja Ø 300 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.4150 112,500.00 159,187.50
Tukang pipa L.07 OH 0.2830 127,500.00 36,082.50
Mandor L.17 OH 0.1410 150,000.00 21,150.00
JUMLAH TENAGA KERJA 216,420.00
B BAHAN
Pipa baja Ø 300 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0040 - -
crane 2 T
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 216,420.00
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 216,420.00

P.I.71. (K3) Pemasangan 1 m pipa baja Ø 400 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.3660 112,500.00 266,175.00
Tukang pipa L.07 OH 0.4730 127,500.00 60,307.50
Mandor L.17 OH 0.2370 150,000.00 35,550.00
JUMLAH TENAGA KERJA 362,032.50
B BAHAN
Pipa baja Ø 400 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.0270 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.0390 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 362,032.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 362,032.50

P.I.72. (K3) Pemasangan 1 m pipa baja Ø 450 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.2310 112,500.00 250,987.50
Tukang pipa L.07 OH 0.4460 127,500.00 56,865.00
Mandor L.17 OH 0.2230 150,000.00 33,450.00
JUMLAH TENAGA KERJA 341,302.50
B BAHAN
Pipa baja Ø 450 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.0260 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.0370 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 341,302.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 341,302.50

P.I.73. (K3) Pemasangan 1 m pipa baja Ø 500 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.4320 112,500.00 273,600.00
Tukang pipa L.07 OH 0.4860 127,500.00 61,965.00
Mandor L.17 OH 0.2430 150,000.00 36,450.00
JUMLAH TENAGA KERJA 372,015.00
B BAHAN
Pipa baja Ø 500 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.0290 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.0450 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 372,015.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 372,015.00

P.I.74. (K3) Pemasangan 1 m pipa baja Ø 600 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.2080 112,500.00 248,400.00
Tukang pipa L.07 OH 0.4420 127,500.00 56,355.00
Mandor L.17 OH 0.2210 150,000.00 33,150.00
JUMLAH TENAGA KERJA 337,905.00
B BAHAN
Pipa baja Ø 600 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.0270 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.0390 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 337,905.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 337,905.00

P.I.75. (K3) Pemasangan 1 m pipa baja Ø 800 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.8970 112,500.00 438,412.50
Tukang pipa L.07 OH 0.7790 127,500.00 99,322.50
Mandor L.17 OH 0.3900 150,000.00 58,500.00
JUMLAH TENAGA KERJA 596,235.00
B BAHAN
Pipa baja Ø 800 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.0460 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.0980 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 596,235.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 596,235.00

P.I.76. (K3) Pemasangan 1 m pipa baja Ø 900 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 4.4030 112,500.00 495,337.50
Tukang pipa L.07 OH 0.0810 127,500.00 10,327.50
Mandor L.17 OH 0.4400 150,000.00 66,000.00
JUMLAH TENAGA KERJA 571,665.00
B BAHAN
Pipa baja Ø 900 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.0520 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.1150 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 571,665.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 571,665.00

P.I.77. (K3) Pemasangan 1 m pipa baja Ø 1000 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 4.8950 112,500.00 550,687.50
Tukang pipa L.07 OH 0.9790 127,500.00 124,822.50
Mandor L.17 OH 0.4890 150,000.00 73,350.00
JUMLAH TENAGA KERJA 748,860.00
B BAHAN
Pipa baja Ø 1000 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.0580 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.1330 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 748,860.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 748,860.00

P.I.78. (K3) Pemasangan 1 m pipa baja Ø 1100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 5.3870 112,500.00 606,037.50
Tukang pipa L.07 OH 1.0770 127,500.00 137,317.50
Mandor L.17 OH 0.5390 150,000.00 80,850.00
JUMLAH TENAGA KERJA 824,205.00
B BAHAN
Pipa baja Ø 1100 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.0640 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.1500 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 824,205.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 824,205.00

P.I.79. (K3) Pemasangan 1 m pipa baja Ø 1200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 5.8970 112,500.00 663,412.50
Tukang pipa L.07 OH 1.1760 127,500.00 149,940.00
Mandor L.17 OH 0.5880 150,000.00 88,200.00
JUMLAH TENAGA KERJA 901,552.50
B BAHAN
Pipa baja Ø 1200 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa excavator type 225
Hari 0.0700 -
kapasitas 0,5 - 1,0 m3
Sewa Tripot/Tackel & handle
Hari 0.1670 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 901,552.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 901,552.50
Q HARGA SATUAN PEKERJAAN PEMOTONGAN PIPA
I (PERMEN NOMOR 28/PRT/M/2016)
Q.I.1. (K3) Pemotongan 1 buah pipa PVC Ø 63 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0050 112,500.00 562.50
Tukang pipa L.07 OH 0.0020 127,500.00 255.00
Mandor L.17 OH 0.0005 150,000.00 75.00
JUMLAH TENAGA KERJA 892.50
B BAHAN
Pipa PVC Ø 63 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0030 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 892.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 892.50

Q.I.2. (K3) Pemotongan 1 m pipa PVC Ø 90 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0140 112,500.00 1,575.00
Tukang pipa L.07 OH 0.0070 127,500.00 892.50
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 2,617.50
B BAHAN
Pipa PVC Ø 90 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0030 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 2,617.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 2,617.50

Q.I.3. (K3) Pemotongan 1 buah pipa PVC Ø 110 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0220 112,500.00 2,475.00
Tukang pipa L.07 OH 0.0110 127,500.00 1,402.50
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 4,177.50
B BAHAN
Pipa PVC Ø 110 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0030 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 4,177.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 4,177.50

Q.I.4. (K3) Pemotongan 1 buah pipa PVC Ø 150 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0310 112,500.00 3,487.50
Tukang pipa L.07 OH 0.0150 127,500.00 1,912.50
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 5,850.00
B BAHAN
Pipa PVC Ø 150 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0030 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 5,850.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 5,850.00

Q.I.5. (K3) Pemotongan 1 buah pipa PVC Ø 200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0810 112,500.00 9,112.50
Tukang pipa L.07 OH 0.0400 127,500.00 5,100.00
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 15,412.50
B BAHAN
Pipa PVC Ø 200 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0170 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 15,412.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 15,412.50

Q.I.6. (K3) Pemotongan 1 buah pipa PVC Ø 250 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1280 112,500.00 14,400.00
Tukang pipa L.07 OH 0.0640 127,500.00 8,160.00
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 24,510.00
B BAHAN
Pipa PVC Ø 250 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0300 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 24,510.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 24,510.00

Q.I.7. (K3) Pemotongan 1 buah pipa PVC Ø 300 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1550 112,500.00 17,437.50
Tukang pipa L.07 OH 0.0770 127,500.00 9,817.50
Mandor L.17 OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 29,505.00
B BAHAN
Pipa PVC Ø 300 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0370 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 29,505.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 29,505.00

Q.I.8. (K3) Pemotongan 1 buah pipa PVC Ø 400 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3310 112,500.00 37,237.50
Tukang pipa L.07 OH 0.1660 127,500.00 21,165.00
Mandor L.17 OH 0.0330 150,000.00 4,950.00
JUMLAH TENAGA KERJA 63,352.50
B BAHAN
Pipa PVC Ø 400 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0860 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 63,352.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 63,352.50

Q.I.9. (K3) Pemotongan 1 buah pipa PVC Ø 450 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4200 112,500.00 47,250.00
Tukang pipa L.07 OH 0.2100 127,500.00 26,775.00
Mandor L.17 OH 0.0420 150,000.00 6,300.00
JUMLAH TENAGA KERJA 80,325.00
B BAHAN
Pipa PVC Ø 450 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0540 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 80,325.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 80,325.00

Q.I.10. (K3) Pemotongan 1 buah pipa PVC Ø 500 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5180 112,500.00 58,275.00
Tukang pipa L.07 OH 0.2590 127,500.00 33,022.50
Mandor L.17 OH 0.0520 150,000.00 7,800.00
JUMLAH TENAGA KERJA 99,097.50
B BAHAN
Pipa PVC Ø 500 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0690 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 99,097.50
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 99,097.50

Q.I.11. (K3) Pemotongan 1 buah pipa PVC Ø 600 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6230 112,500.00 70,087.50
Tukang pipa L.07 OH 0.3110 127,500.00 39,652.50
Mandor L.17 OH 0.0620 150,000.00 9,300.00
JUMLAH TENAGA KERJA 119,040.00
B BAHAN
Pipa PVC Ø 600 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0860 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 119,040.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 119,040.00

Q.I.12. (K3) Pemotongan 1 buah pipa PVC Ø 800 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0890 112,500.00 122,512.50
Tukang pipa L.07 OH 0.5450 127,500.00 69,487.50
Mandor L.17 OH 0.1090 150,000.00 16,350.00
JUMLAH TENAGA KERJA 208,350.00
B BAHAN
Pipa PVC Ø 800 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.1600 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 208,350.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 208,350.00

Q.I.13. (K3) Pemotongan 1 buah pipa PVC Ø 900 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.1410 112,500.00 128,362.50
Tukang pipa L.07 OH 0.5710 127,500.00 72,802.50
Mandor L.17 OH 0.1140 150,000.00 17,100.00
JUMLAH TENAGA KERJA 218,265.00
B BAHAN
Pipa PVC Ø 900 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.1680 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 218,265.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 218,265.00

Q.I.14. (K3) Pemotongan 1 buah pipa PVC Ø 1000 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.2850 112,500.00 144,562.50
Tukang pipa L.07 OH 0.6430 127,500.00 81,982.50
Mandor L.17 OH 0.1290 150,000.00 19,350.00
JUMLAH TENAGA KERJA 245,895.00
B BAHAN
Pipa PVC Ø 1000 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.1910 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 245,895.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 245,895.00

Q.I.15. (K3) Pemotongan 1 buah pipa PVC Ø 1100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.4290 112,500.00 160,762.50
Tukang pipa L.07 OH 0.7150 127,500.00 91,162.50
Mandor L.17 OH 0.1430 150,000.00 21,450.00
JUMLAH TENAGA KERJA 273,375.00
B BAHAN
Pipa PVC Ø 1100 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.2130 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 273,375.00
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 273,375.00

Q.I.16. (K3) Pemotongan 1 buah pipa PVC Ø 1200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5730 112,500.00 176,962.50
Tukang pipa L.07 OH 0.7870 127,500.00 100,342.50
Mandor L.17 OH 0.1570 150,000.00 23,550.00
JUMLAH TENAGA KERJA 300,855.00
B BAHAN
Pipa PVC Ø 1200 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.2360 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 300,855.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 300,855.00

Q.I.17. (K3) Pemotongan 1 buah pipa HDPE Ø 63 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0020 112,500.00 225.00
Tukang pipa L.07 OH 0.0010 127,500.00 127.50
Mandor L.17 OH 0.0002 150,000.00 30.00
Operator alat berat L.21a OH 0.0340 175,000.00 5,950.00
JUMLAH TENAGA KERJA 6,332.50
B BAHAN
Pipa HDPE Ø 63 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0040 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 6,332.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 6,332.50

Q.I.18. (K3) Pemotongan 1 buah pipa HDPE Ø 100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0060 112,500.00 675.00
Tukang pipa L.07 OH 0.0030 127,500.00 382.50
Mandor L.17 OH 0.0010 150,000.00 150.00
Operator alat berat L.21a OH 0.0710 175,000.00 12,425.00
JUMLAH TENAGA KERJA 13,632.50
B BAHAN
Pipa HDPE Ø 100 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0050 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 13,632.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 13,632.50

Q.I.19. (K3) Pemotongan 1 buah pipa HDPE Ø 125 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0090 112,500.00 1,012.50
Tukang pipa L.07 OH 0.0050 127,500.00 637.50
Mandor L.17 OH 0.0010 150,000.00 150.00
Operator alat berat L.21a OH 0.0960 175,000.00 16,800.00
JUMLAH TENAGA KERJA 18,600.00
B BAHAN
Pipa HDPE Ø 125 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0060 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 18,600.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 18,600.00

Q.I.20. (K3) Pemotongan 1 buah pipa HDPE Ø 150 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0160 112,500.00 1,800.00
Tukang pipa L.07 OH 0.0080 127,500.00 1,020.00
Mandor L.17 OH 0.0020 150,000.00 300.00
Operator alat berat L.21a OH 0.1210 175,000.00 21,175.00
JUMLAH TENAGA KERJA 24,295.00
B BAHAN
Pipa HDPE Ø 150 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0090 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 24,295.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 24,295.00

Q.I.21. (K3) Pemotongan 1 buah pipa HDPE Ø 200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0440 112,500.00 4,950.00
Tukang pipa L.07 OH 0.0220 127,500.00 2,805.00
Mandor L.17 OH 0.0040 150,000.00 600.00
Operator alat berat L.21a OH 0.1710 175,000.00 29,925.00
JUMLAH TENAGA KERJA 38,280.00
B BAHAN
Pipa HDPE Ø 200 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0170 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 38,280.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 38,280.00

Q.I.22. (K3) Pemotongan 1 buah pipa HDPE Ø 250 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0670 112,500.00 7,537.50
Tukang pipa L.07 OH 0.0330 127,500.00 4,207.50
Mandor L.17 OH 0.0070 150,000.00 1,050.00
Operator alat berat L.21a OH 0.2210 175,000.00 38,675.00
JUMLAH TENAGA KERJA 51,470.00
B BAHAN
Pipa HDPE Ø 250 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0230 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 51,470.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 51,470.00

Q.I.23. (K3) Pemotongan 1 buah pipa HDPE Ø 300 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0900 112,500.00 10,125.00
Tukang pipa L.07 OH 0.0450 127,500.00 5,737.50
Mandor L.17 OH 0.0090 150,000.00 1,350.00
Operator alat berat L.21a OH 0.2710 175,000.00 47,425.00
JUMLAH TENAGA KERJA 64,637.50
B BAHAN
Pipa HDPE Ø 300 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0300 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 64,637.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 64,637.50

Q.I.24. (K3) Pemotongan 1 buah pipa HDPE Ø 400 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1770 112,500.00 19,912.50
Tukang pipa L.07 OH 0.0880 127,500.00 11,220.00
Mandor L.17 OH 0.0180 150,000.00 2,700.00
Operator alat berat L.21a OH 0.3710 175,000.00 64,925.00
JUMLAH TENAGA KERJA 98,757.50
B BAHAN
Pipa HDPE Ø 400 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0550 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 98,757.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 98,757.50

Q.I.25. (K3) Pemotongan 1 buah pipa HDPE Ø 450 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2550 112,500.00 28,687.50
Tukang pipa L.07 OH 0.1130 127,500.00 14,407.50
Mandor L.17 OH 0.0230 150,000.00 3,450.00
Operator alat berat L.21a OH 0.4210 175,000.00 73,675.00
JUMLAH TENAGA KERJA 120,220.00
B BAHAN
Pipa HDPE Ø 450 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0700 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 120,220.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 120,220.00

Q.I.26. (K3) Pemotongan 1 buah pipa HDPE Ø 500 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2770 112,500.00 31,162.50
Tukang pipa L.07 OH 0.1390 127,500.00 17,722.50
Mandor L.17 OH 0.0280 150,000.00 4,200.00
Operator alat berat L.21a OH 0.4710 175,000.00 82,425.00
JUMLAH TENAGA KERJA 135,510.00
B BAHAN
Pipa HDPE Ø 500 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.0850 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 135,510.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 135,510.00

Q.I.27. (K3) Pemotongan 1 buah pipa HDPE Ø 600 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3330 112,500.00 37,462.50
Tukang pipa L.07 OH 0.1670 127,500.00 21,292.50
Mandor L.17 OH 0.0330 150,000.00 4,950.00
Operator alat berat L.21a OH 0.5710 175,000.00 99,925.00
JUMLAH TENAGA KERJA 163,630.00
B BAHAN
Pipa HDPE Ø 600 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.1010 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 163,630.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 163,630.00

Q.I.28. (K3) Pemotongan 1 buah pipa HDPE Ø 800 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6010 112,500.00 67,612.50
Tukang pipa L.07 OH 0.3010 127,500.00 38,377.50
Mandor L.17 OH 0.0600 150,000.00 9,000.00
Operator alat berat L.21a OH 0.7710 175,000.00 134,925.00
JUMLAH TENAGA KERJA 249,915.00
B BAHAN
Pipa HDPE Ø 800 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.1790 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 249,915.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 249,915.00

Q.I.29. (K3) Pemotongan 1 buah pipa HDPE Ø 900 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9130 112,500.00 102,712.50
Tukang pipa L.07 OH 0.4560 127,500.00 58,140.00
Mandor L.17 OH 0.0910 150,000.00 13,650.00
Operator alat berat L.21a OH 0.8710 175,000.00 152,425.00
JUMLAH TENAGA KERJA 326,927.50
B BAHAN
Pipa HDPE Ø 900 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.2700 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 326,927.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 326,927.50
Q.I.30. (K3) Pemotongan 1 buah pipa HDPE Ø 1000 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.1250 112,500.00 126,562.50
Tukang pipa L.07 OH 0.5620 127,500.00 71,655.00
Mandor L.17 OH 0.1120 150,000.00 16,800.00
Operator alat berat L.21a OH 0.9710 175,000.00 169,925.00
JUMLAH TENAGA KERJA 384,942.50
B BAHAN
Pipa HDPE Ø 1000 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.3320 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 384,942.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 384,942.50

Q.I.31. (K3) Pemotongan 1 buah pipa HDPE Ø 1100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.2380 112,500.00 139,275.00
Tukang pipa L.07 OH 0.6190 127,500.00 78,922.50
Mandor L.17 OH 0.1240 150,000.00 18,600.00
Operator alat berat L.21a OH 1.0710 175,000.00 187,425.00
JUMLAH TENAGA KERJA 424,222.50
B BAHAN
Pipa HDPE Ø 1100 mm buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.3650 -
T1/manual (gergaji) /saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 424,222.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 424,222.50

Q.I.32. (K3) Pemotongan 1 buah pipa HDPE Ø 1200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6190 112,500.00 182,137.50
Tukang pipa L.07 OH 0.8090 127,500.00 103,147.50
Mandor L.17 OH 0.1620 150,000.00 24,300.00
Operator alat berat L.21a OH 1.1710 175,000.00 204,925.00
JUMLAH TENAGA KERJA 514,510.00
B BAHAN
Pipa HDPE Ø 1200 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.4770 -
T2/mekanik / cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 514,510.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 514,510.00

Q.I.33. (K3) Pemotongan 1 buah pipa GIP Ø 63 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0190 112,500.00 2,137.50
Tukang pipa L.07 OH 0.0100 127,500.00 1,275.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,712.50
B BAHAN
Pipa GIP Ø 63 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari - -
T2/mekanik / cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,712.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,712.50

Q.I.34. (K3) Pemotongan 1 buah pipa GIP Ø 100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0580 112,500.00 6,525.00
Tukang pipa L.07 OH 0.0290 127,500.00 3,697.50
Mandor L.17 OH 0.0060 150,000.00 900.00
JUMLAH TENAGA KERJA 11,122.50
B BAHAN
Pipa GIP Ø 100 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari - -
T2/mekanik / cilinder saw
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 11,122.50
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 11,122.50

Q.I.35. (K3) Pemotongan 1 buah pipa GIP Ø 125 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0920 112,500.00 10,350.00
Tukang pipa L.07 OH 0.0460 127,500.00 5,865.00
Mandor L.17 OH 0.0090 150,000.00 1,350.00
JUMLAH TENAGA KERJA 17,565.00
B BAHAN
Pipa GIP Ø 125 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari - -
T2/mekanik / cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 17,565.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 17,565.00

Q.I.36. (K3) Pemotongan 1 buah pipa GIP Ø 150 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1310 112,500.00 14,737.50
Tukang pipa L.07 OH 0.0660 127,500.00 8,415.00
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 25,102.50
B BAHAN
Pipa GIP Ø 150 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari - -
T2/mekanik / cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 25,102.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 25,102.50

Q.I.37. (K3) Pemotongan 1 buah pipa GIP Ø 200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3400 112,500.00 38,250.00
Tukang pipa L.07 OH 0.1700 127,500.00 21,675.00
Mandor L.17 OH 0.0340 150,000.00 5,100.00
JUMLAH TENAGA KERJA 65,025.00
B BAHAN
Pipa GIP Ø 200 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari - -
T2/mekanik / cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 65,025.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 65,025.00

Q.I.38. (K3) Pemotongan 1 buah pipa GIP Ø 250 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4750 112,500.00 53,437.50
Tukang pipa L.07 OH 0.2370 127,500.00 30,217.50
Mandor L.17 OH 0.0470 150,000.00 7,050.00
JUMLAH TENAGA KERJA 90,705.00
B BAHAN
Pipa GIP Ø 250 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari - -
T2/mekanik / cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 90,705.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 90,705.00

Q.I.39. (K3) Pemotongan 1 buah pipa GIP Ø 300 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5040 112,500.00 56,700.00
Tukang pipa L.07 OH 0.2520 127,500.00 32,130.00
Mandor L.17 OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 96,330.00
B BAHAN
Pipa GIP Ø 300 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari - -
T2/mekanik / cilinder saw
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 96,330.00
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 96,330.00

Q.I.40. (K3) Pemotongan 1 buah pipa GIP Ø 400 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7380 112,500.00 83,025.00
Tukang pipa L.07 OH 0.3690 127,500.00 47,047.50
Mandor L.17 OH 0.0740 150,000.00 11,100.00
JUMLAH TENAGA KERJA 141,172.50
B BAHAN
Pipa GIP Ø 400 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari - -
T2/mekanik / cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 141,172.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 141,172.50

Q.I.41. (K3) Pemotongan 1 buah pipa GIP Ø 450 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8480 112,500.00 95,400.00
Tukang pipa L.07 OH 0.4240 127,500.00 54,060.00
Mandor L.17 OH 0.0850 150,000.00 12,750.00
JUMLAH TENAGA KERJA 162,210.00
B BAHAN
Pipa GIP Ø 450 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari - -
T2/mekanik / cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 162,210.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 162,210.00

Q.I.42. (K3) Pemotongan 1 buah pipa GIP Ø 500 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9410 112,500.00 105,862.50
Tukang pipa L.07 OH 0.4710 127,500.00 60,052.50
Mandor L.17 OH 0.0940 150,000.00 14,100.00
JUMLAH TENAGA KERJA 180,015.00
B BAHAN
Pipa GIP Ø 500 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari - -
T2/mekanik / cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 180,015.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 180,015.00

Q.I.43. (K3) Pemotongan 1 buah pipa GIP Ø 600 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8640 112,500.00 97,200.00
Tukang pipa L.07 OH 0.4320 127,500.00 55,080.00
Mandor L.17 OH 0.0860 150,000.00 12,900.00
JUMLAH TENAGA KERJA 165,180.00
B BAHAN
Pipa GIP Ø 600 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari - -
T2/mekanik / cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 165,180.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 165,180.00

Q.I.44. (K3) Pemotongan 1 buah pipa GIP Ø 800 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5670 112,500.00 176,287.50
Tukang pipa L.07 OH 0.7830 127,500.00 99,832.50
Mandor L.17 OH 0.1570 150,000.00 23,550.00
JUMLAH TENAGA KERJA 299,670.00
B BAHAN
Pipa GIP Ø 800 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari - -
T2/mekanik / cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 299,670.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 299,670.00

Q.I.45. (K3) Pemotongan 1 buah pipa GIP Ø 900 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.7700 112,500.00 199,125.00
Tukang pipa L.07 OH 0.8850 127,500.00 112,837.50
Mandor L.17 OH 0.1770 150,000.00 26,550.00
JUMLAH TENAGA KERJA 338,512.50
B BAHAN
Pipa GIP Ø 900 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari - -
T2/mekanik / cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 338,512.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 338,512.50

Q.I.46. (K3) Pemotongan 1 buah pipa GIP Ø 1000 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.9740 112,500.00 222,075.00
Tukang pipa L.07 OH 0.9870 127,500.00 125,842.50
Mandor L.17 OH 0.1970 150,000.00 29,550.00
JUMLAH TENAGA KERJA 377,467.50
B BAHAN
Pipa GIP Ø 1000 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari - -
T2/mekanik / cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 377,467.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 377,467.50

Q.I.47. (K3) Pemotongan 1 buah pipa GIP Ø 1100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.1780 112,500.00 245,025.00
Tukang pipa L.07 OH 1.0890 127,500.00 138,847.50
Mandor L.17 OH 0.2180 150,000.00 32,700.00
JUMLAH TENAGA KERJA 416,572.50
B BAHAN
Pipa GIP Ø 1100 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari - -
T2/mekanik / cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 416,572.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 416,572.50

Q.I.48. (K3) Pemotongan 1 buah pipa GIP Ø 1200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.3820 112,500.00 267,975.00
Tukang pipa L.07 OH 1.1910 127,500.00 151,852.50
Mandor L.17 OH 0.2380 150,000.00 35,700.00
JUMLAH TENAGA KERJA 455,527.50
B BAHAN
Pipa GIP Ø 1200 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari - -
T2/mekanik / cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 455,527.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 455,527.50

Q.I.49. (K3) Pemotongan 1 buah pipa DCI Ø 100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0710 112,500.00 7,987.50
Tukang pipa L.07 OH 0.0140 127,500.00 1,785.00
Mandor L.17 OH 0.0070 150,000.00 1,050.00
JUMLAH TENAGA KERJA 10,822.50
B BAHAN
Pipa GIP Ø 1200 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0030 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 10,822.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 10,822.50

Q.I.50. (K3) Pemotongan 1 buah pipa DCI Ø 125 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1120 112,500.00 12,600.00
Tukang pipa L.07 OH 0.0220 127,500.00 2,805.00
Mandor L.17 OH 0.0110 150,000.00 1,650.00
JUMLAH TENAGA KERJA 17,055.00
B BAHAN
Pipa GIP Ø 125 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0100 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 17,055.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 17,055.00

Q.I.51. (K3) Pemotongan 1 buah pipa DCI Ø 150 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1590 112,500.00 17,887.50
Tukang pipa L.07 OH 0.0320 127,500.00 4,080.00
Mandor L.17 OH 0.0160 150,000.00 2,400.00
JUMLAH TENAGA KERJA 24,367.50
B BAHAN
Pipa DCI Ø 150 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0180 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 24,367.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 24,367.50

Q.I.52. (K3) Pemotongan 1 buah pipa DCI Ø 200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3660 112,500.00 41,175.00
Tukang pipa L.07 OH 0.0730 127,500.00 9,307.50
Mandor L.17 OH 0.0370 150,000.00 5,550.00
JUMLAH TENAGA KERJA 56,032.50
B BAHAN
Pipa DCI Ø 200 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0540 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 56,032.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 56,032.50

Q.I.53. (K3) Pemotongan 1 buah pipa DCI Ø 250 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4760 112,500.00 53,550.00
Tukang pipa L.07 OH 0.0950 127,500.00 12,112.50
Mandor L.17 OH 0.0480 150,000.00 7,200.00
JUMLAH TENAGA KERJA 72,862.50
B BAHAN
Pipa DCI Ø 250 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0730 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 72,862.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 72,862.50

Q.I.54. (K3) Pemotongan 1 buah pipa DCI Ø 300 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5120 112,500.00 57,600.00
Tukang pipa L.07 OH 0.1020 127,500.00 13,005.00
Mandor L.17 OH 0.0510 150,000.00 7,650.00
JUMLAH TENAGA KERJA 78,255.00
B BAHAN
Pipa DCI Ø 300 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0790 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 78,255.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 78,255.00

Q.I.55. (K3) Pemotongan 1 buah pipa DCI Ø 400 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9410 112,500.00 105,862.50
Tukang pipa L.07 OH 0.1880 127,500.00 23,970.00
Mandor L.17 OH 0.0940 150,000.00 14,100.00
JUMLAH TENAGA KERJA 143,932.50
B BAHAN
Pipa DCI Ø 400 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.1580 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 143,932.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 143,932.50

Q.I.56. (K3) Pemotongan 1 buah pipa DCI Ø 450 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.1370 112,500.00 127,912.50
Tukang pipa L.07 OH 0.2270 127,500.00 28,942.50
Mandor L.17 OH 0.1140 150,000.00 17,100.00
JUMLAH TENAGA KERJA 173,955.00
B BAHAN
Pipa DCI Ø 450 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.1760 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 173,955.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 173,955.00
Q.I.57. (K3) Pemotongan 1 buah pipa DCI Ø 500 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.3120 112,500.00 147,600.00
Tukang pipa L.07 OH 0.2620 127,500.00 33,405.00
Mandor L.17 OH 0.1310 150,000.00 19,650.00
JUMLAH TENAGA KERJA 200,655.00
B BAHAN
Pipa DCI Ø 500 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.1920 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 200,655.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 200,655.00

Q.I.58. (K3) Pemotongan 1 buah pipa DCI Ø 600 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.3090 112,500.00 147,262.50
Tukang pipa L.07 OH 0.2620 127,500.00 33,405.00
Mandor L.17 OH 0.1310 150,000.00 19,650.00
JUMLAH TENAGA KERJA 200,317.50
B BAHAN
Pipa DCI Ø 600 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.1920 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 200,317.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 200,317.50

Q.I.59. (K3) Pemotongan 1 buah pipa DCI Ø 800 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.5980 112,500.00 292,275.00
Tukang pipa L.07 OH 0.5200 127,500.00 66,300.00
Mandor L.17 OH 0.2600 150,000.00 39,000.00
JUMLAH TENAGA KERJA 397,575.00
B BAHAN
Pipa DCI Ø 800 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.3100 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 397,575.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 397,575.00

Q.I.60. (K3) Pemotongan 1 buah pipa DCI Ø 900 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.3700 112,500.00 379,125.00
Tukang pipa L.07 OH 0.6740 127,500.00 85,935.00
Mandor L.17 OH 0.3370 150,000.00 50,550.00
JUMLAH TENAGA KERJA 515,610.00
B BAHAN
Pipa DCI Ø 900 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.3810 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 515,610.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 515,610.00

Q.I.61. (K3) Pemotongan 1 buah pipa DCI Ø 1000 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 4.0210 112,500.00 452,362.50
Tukang pipa L.07 OH 0.8040 127,500.00 102,510.00
Mandor L.17 OH 0.4020 150,000.00 60,300.00
JUMLAH TENAGA KERJA 615,172.50
B BAHAN
Pipa DCI Ø 1000 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.4410 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 615,172.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 615,172.50
Q.I.62. (K3) Pemotongan 1 buah pipa DCI Ø 1100 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 4.7310 112,500.00 532,237.50
Tukang pipa L.07 OH 0.9460 127,500.00 120,615.00
Mandor L.17 OH 0.4730 150,000.00 70,950.00
JUMLAH TENAGA KERJA 723,802.50
B BAHAN
Pipa DCI Ø 1100 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.5060 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 723,802.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 723,802.50

Q.I.63 (K3) Pemotongan 1 buah pipa DCI Ø 1200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 5.5020 112,500.00 618,975.00
Tukang pipa L.07 OH 1.1000 127,500.00 140,250.00
Mandor L.17 OH 0.5500 150,000.00 82,500.00
JUMLAH TENAGA KERJA 841,725.00
B BAHAN
Pipa DCI Ø 1200 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.5760 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 841,725.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 841,725.00

Q.I.64. (K3) Pemotongan 1 buah pipa baja Ø 63 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0280 112,500.00 3,150.00
Tukang pipa L.07 OH 0.0060 127,500.00 765.00
Mandor L.17 OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 4,365.00
B BAHAN
Pipa baja Ø 63 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0370 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 4,365.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 4,365.00

Q.I.65. (K3) Pemotongan 1 buah pipa baja Ø 100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0850 112,500.00 9,562.50
Tukang pipa L.07 OH 0.0170 127,500.00 2,167.50
Mandor L.17 OH 0.0080 150,000.00 1,200.00
JUMLAH TENAGA KERJA 12,930.00
B BAHAN
Pipa baja Ø 100 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0400 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 12,930.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 12,930.00

Q.I.66. (K3) Pemotongan 1 buah pipa baja Ø 125 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1330 112,500.00 14,962.50
Tukang pipa L.07 OH 0.0270 127,500.00 3,442.50
Mandor L.17 OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 20,355.00
B BAHAN
Pipa baja Ø 125 mm buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0420 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 20,355.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 20,355.00

Q.I.67. (K3) Pemotongan 1 buah pipa baja Ø 150 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1840 112,500.00 20,700.00
Tukang pipa L.07 OH 0.0370 127,500.00 4,717.50
Mandor L.17 OH 0.0180 150,000.00 2,700.00
JUMLAH TENAGA KERJA 28,117.50
B BAHAN
Pipa baja Ø 150 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0450 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 28,117.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 28,117.50

Q.I.68. (K3) Pemotongan 1 buah pipa baja Ø 200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4760 112,500.00 53,550.00
Tukang pipa L.07 OH 0.0950 127,500.00 12,112.50
Mandor L.17 OH 0.0480 150,000.00 7,200.00
JUMLAH TENAGA KERJA 72,862.50
B BAHAN
Pipa baja Ø 200 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0600 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 72,862.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 72,862.50

Q.I.69. (K3) Pemotongan 1 buah pipa baja Ø 250 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6630 112,500.00 74,587.50
Tukang pipa L.07 OH 0.1330 127,500.00 16,957.50
Mandor L.17 OH 0.0660 150,000.00 9,900.00
JUMLAH TENAGA KERJA 101,445.00
B BAHAN
Pipa baja Ø 250 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0680 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 101,445.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 101,445.00

Q.I.70. (K3) Pemotongan 1 buah pipa baja Ø 300 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7450 112,500.00 83,812.50
Tukang pipa L.07 OH 0.1490 127,500.00 18,997.50
Mandor L.17 OH 0.0740 150,000.00 11,100.00
JUMLAH TENAGA KERJA 113,910.00
B BAHAN
Pipa baja Ø 300 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0720 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 113,910.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 113,910.00

Q.I.71. (K3) Pemotongan 1 buah pipa baja Ø 400 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.4400 112,500.00 162,000.00
Tukang pipa L.07 OH 0.2880 127,500.00 36,720.00
Mandor L.17 OH 0.1440 150,000.00 21,600.00
JUMLAH TENAGA KERJA 220,320.00
B BAHAN
Pipa baja Ø 400 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.1050 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 220,320.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 220,320.00

Q.I.72. (K3) Pemotongan 1 buah pipa baja Ø 450 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.3990 112,500.00 157,387.50
Tukang pipa L.07 OH 0.2800 127,500.00 35,700.00
Mandor L.17 OH 0.1400 150,000.00 21,000.00
JUMLAH TENAGA KERJA 214,087.50
B BAHAN
Pipa baja Ø 450 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.1070 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 214,087.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 214,087.50

Q.I.73. (K3) Pemotongan 1 buah pipa baja Ø 500 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5580 112,500.00 175,275.00
Tukang pipa L.07 OH 0.3120 127,500.00 39,780.00
Mandor L.17 OH 0.1560 150,000.00 23,400.00
JUMLAH TENAGA KERJA 238,455.00
B BAHAN
Pipa baja Ø 500 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.1070 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 238,455.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 238,455.00

Q.I.74. (K3) Pemotongan 1 buah pipa baja Ø 600 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.4370 112,500.00 161,662.50
Tukang pipa L.07 OH 0.2870 127,500.00 36,592.50
Mandor L.17 OH 0.1440 150,000.00 21,600.00
JUMLAH TENAGA KERJA 219,855.00
B BAHAN
Pipa baja Ø 600 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.1130 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 219,855.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 219,855.00

Q.I.75. (K3) Pemotongan 1 buah pipa baja Ø 800 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.6240 112,500.00 295,200.00
Tukang pipa L.07 OH 0.5250 127,500.00 66,937.50
Mandor L.17 OH 0.2620 150,000.00 39,300.00
JUMLAH TENAGA KERJA 401,437.50
B BAHAN
Pipa baja Ø 800 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.1660 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 401,437.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 401,437.50

Q.I.76. (K3) Pemotongan 1 buah pipa baja Ø 900 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.9710 112,500.00 334,237.50
Tukang pipa L.07 OH 0.5940 127,500.00 75,735.00
Mandor L.17 OH 0.2970 150,000.00 44,550.00
JUMLAH TENAGA KERJA 454,522.50
B BAHAN
Pipa baja Ø 900 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.1830 -
crane 2 T
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 454,522.50
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 454,522.50

Q.I.77. (K3) Pemotongan 1 buah pipa baja Ø 1000 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.3190 112,500.00 373,387.50
Tukang pipa L.07 OH 0.6640 127,500.00 84,660.00
Mandor L.17 OH 0.3320 150,000.00 49,800.00
JUMLAH TENAGA KERJA 507,847.50
B BAHAN
Pipa baja Ø 1000 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.2010 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 507,847.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 507,847.50

Q.I.78. (K3) Pemotongan 1 buah pipa baja Ø 1100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.6670 112,500.00 412,537.50
Tukang pipa L.07 OH 0.7330 127,500.00 93,457.50
Mandor L.17 OH 0.3670 150,000.00 55,050.00
JUMLAH TENAGA KERJA 561,045.00
B BAHAN
Pipa baja Ø 1100 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.2180 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 561,045.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 561,045.00

Q.I.79. (K3) Pemotongan 1 buah pipa baja Ø 1200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 4.0150 112,500.00 451,687.50
Tukang pipa L.07 OH 0.8030 127,500.00 102,382.50
Mandor L.17 OH 0.4020 150,000.00 60,300.00
JUMLAH TENAGA KERJA 614,370.00
B BAHAN
Pipa baja Ø 1100 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.2360 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 614,370.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 614,370.00
R HARGA SATUAN PEKERJAAN PEMASANGAN AKSESORIS PIPA
I (PERMEN NOMOR 28/PRT/M/2016)
R.I.1. (K3) Pemasangan 1 buah valve Ø 150 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.4290 112,500.00 160,762.50
Tukang pipa L.07 OH 0.7150 127,500.00 91,162.50
Mandor L.17 OH 0.1430 150,000.00 21,450.00
JUMLAH TENAGA KERJA 273,375.00
B BAHAN
Valve Ø 150 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.1000 - -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 273,375.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 273,375.00

R.I.2. (K3) Pemasangan 1 buah valve Ø 200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.7140 112,500.00 192,825.00
Tukang pipa L.07 OH 0.8570 127,500.00 109,267.50
Mandor L.17 OH 0.1710 150,000.00 25,650.00
JUMLAH TENAGA KERJA 327,742.50
B BAHAN
Valve Ø 200 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.3000 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 327,742.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 327,742.50

R.I.3. (K3) Pemasangan 1 buah valve Ø 250 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.7140 112,500.00 192,825.00
Tukang pipa L.07 OH 0.8570 127,500.00 109,267.50
Mandor L.17 OH 0.1710 150,000.00 25,650.00
JUMLAH TENAGA KERJA 327,742.50
B BAHAN
Valve Ø 250 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.4000 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 327,742.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 327,742.50

R.I.4. (K3) Pemasangan 1 buah valve Ø 300 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.0000 112,500.00 225,000.00
Tukang pipa L.07 OH 1.0000 127,500.00 127,500.00
Mandor L.17 OH 0.2000 150,000.00 30,000.00
JUMLAH TENAGA KERJA 382,500.00
B BAHAN
Valve Ø 300 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.5000 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 382,500.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 382,500.00

R.I.5. (K3) Pemasangan 1 buah valve Ø 400 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.4290 112,500.00 385,762.50
Tukang pipa L.07 OH 1.7150 127,500.00 218,662.50
Mandor L.17 OH 0.3430 150,000.00 51,450.00
JUMLAH TENAGA KERJA 655,875.00
B BAHAN
Valve Ø 400 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 1.0000 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 655,875.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 655,875.00
R.I.6. (K3) Pemasangan 1 buah valve Ø 450 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.4290 112,500.00 385,762.50
Tukang pipa L.07 OH 1.7150 127,500.00 218,662.50
Mandor L.17 OH 0.3430 150,000.00 51,450.00
JUMLAH TENAGA KERJA 655,875.00
B BAHAN
Valve Ø 450 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 1.0000 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 655,875.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 655,875.00

R.I.7. (K3) Pemasangan 1 buah valve Ø 500 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 4.0000 112,500.00 450,000.00
Tukang pipa L.07 OH 2.0000 127,500.00 255,000.00
Mandor L.17 OH 0.4000 150,000.00 60,000.00
JUMLAH TENAGA KERJA 765,000.00
B BAHAN
Valve Ø 500 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 1.0000 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 765,000.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 765,000.00

R.I.8. (K3) Pemasangan 1 buah valve Ø 600 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.4210 112,500.00 159,862.50
Tukang pipa L.07 OH 0.7110 127,500.00 90,652.50
Mandor L.17 OH 0.1420 150,000.00 21,300.00
JUMLAH TENAGA KERJA 271,815.00
B BAHAN
Valve Ø 600 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.6000 -
crane 2 T
Mobile crane ≤ 3 ton Hari 0.3000 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 271,815.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 271,815.00

R.I.9. (K3) Pemasangan 1 buah valve Ø 700 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.4290 112,500.00 160,762.50
Tukang pipa L.07 OH 0.7150 127,500.00 91,162.50
Mandor L.17 OH 0.1430 150,000.00 21,450.00
JUMLAH TENAGA KERJA 273,375.00
B BAHAN
Valve Ø 700 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.5000 -
crane 2 T
Mobile crane ≤ 3 ton Hari 0.5000 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 273,375.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 273,375.00

R.I.10. (K3) Pemasangan 1 buah valve Ø 800 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.7860 112,500.00 200,925.00
Tukang pipa L.07 OH 0.8930 127,500.00 113,857.50
Mandor L.17 OH 0.1790 150,000.00 26,850.00
JUMLAH TENAGA KERJA 341,632.50
B BAHAN
Valve Ø 800 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.5000 -
crane 2 T
Mobile crane ≤ 3 ton Hari 0.5000 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 341,632.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 341,632.50

R.I.11. (K3) Pemasangan 1 buah valve Ø 900 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.7140 112,500.00 192,825.00
Tukang pipa L.07 OH 0.8570 127,500.00 109,267.50
Mandor L.17 OH 0.1710 150,000.00 25,650.00
JUMLAH TENAGA KERJA 327,742.50
B BAHAN
Valve Ø 900 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.7500 -
crane 2 T
Mobile crane ≤ 3 ton Hari 0.7500 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 327,742.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 327,742.50

R.I.12. (K3) Pemasangan 1 buah valve Ø 1000 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.5710 112,500.00 289,237.50
Tukang pipa L.07 OH 1.2860 127,500.00 163,965.00
Mandor L.17 OH 0.2570 150,000.00 38,550.00
JUMLAH TENAGA KERJA 491,752.50
B BAHAN
Valve Ø 1000 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 1.0000 -
crane 2 T
Mobile crane ≤ 3 ton Hari 1.0000 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 491,752.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 491,752.50

R.I.13. (K3) Pemasangan 1 buah valve Ø 1100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.0000 112,500.00 337,500.00
Tukang pipa L.07 OH 1.5000 127,500.00 191,250.00
Mandor L.17 OH 0.3000 150,000.00 45,000.00
JUMLAH TENAGA KERJA 573,750.00
B BAHAN
Valve Ø 1100 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 1.0000 -
crane 2 T
Mobile crane ≤ 3 ton Hari 1.0000 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 573,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 573,750.00

R.I.14. (K3) Pemasangan 1 buah valve Ø 1200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.0000 112,500.00 337,500.00
Tukang pipa L.07 OH 1.5000 127,500.00 191,250.00
Mandor L.17 OH 0.3000 150,000.00 45,000.00
JUMLAH TENAGA KERJA 573,750.00
B BAHAN
Valve Ø 1200 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 1.0000 -
crane 2 T
Mobile crane ≤ 3 ton Hari 1.0000 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 573,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 573,750.00

R.I.15. (K3) Pemasangan 1 buah tee Ø 150 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1060 112,500.00 11,925.00
Tukang pipa L.07 OH 0.0530 127,500.00 6,757.50
Mandor L.17 OH 0.0110 150,000.00 1,650.00
JUMLAH TENAGA KERJA 20,332.50
B BAHAN
Tee Ø 150 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0280 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 20,332.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 20,332.50

R.I.16. (K3) Pemasangan 1 buah tee Ø 200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2160 112,500.00 24,300.00
Tukang pipa L.07 OH 0.1080 127,500.00 13,770.00
Mandor L.17 OH 0.0220 150,000.00 3,300.00
JUMLAH TENAGA KERJA 41,370.00
B BAHAN
Tee Ø 200 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0290 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 41,370.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 41,370.00

R.I.17. (K3) Pemasangan 1 buah tee Ø 250 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3260 112,500.00 36,675.00
Tukang pipa L.07 OH 0.1630 127,500.00 20,782.50
Mandor L.17 OH 0.0330 150,000.00 4,950.00
JUMLAH TENAGA KERJA 62,407.50
B BAHAN
Tee Ø 200 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.0390 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 62,407.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 62,407.50

R.I.18. (K3) Pemasangan 1 buah tee Ø 300 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4360 112,500.00 49,050.00
Tukang pipa L.07 OH 0.2180 127,500.00 27,795.00
Mandor L.17 OH 0.0440 150,000.00 6,600.00
JUMLAH TENAGA KERJA 83,445.00
B BAHAN
Tee Ø 300 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.5000 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 83,445.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 83,445.00

R.I.19. (K3) Pemasangan 1 buah tee Ø 400 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6560 112,500.00 73,800.00
Tukang pipa L.07 OH 0.3280 127,500.00 41,820.00
Mandor L.17 OH 0.0660 150,000.00 9,900.00
JUMLAH TENAGA KERJA 125,520.00
B BAHAN
Tee Ø 400 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.5000 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 125,520.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 125,520.00

R.I.20. (K3) Pemasangan 1 buah tee Ø 450 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7660 112,500.00 86,175.00
Tukang pipa L.07 OH 0.3830 127,500.00 48,832.50
Mandor L.17 OH 0.0770 150,000.00 11,550.00
JUMLAH TENAGA KERJA 146,557.50
B BAHAN
Tee Ø 450 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.5000 -
crane 2 T
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 146,557.50
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 146,557.50

R.I.21. (K3) Pemasangan 1 buah tee Ø 500 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8760 112,500.00 98,550.00
Tukang pipa L.07 OH 0.4380 127,500.00 55,845.00
Mandor L.17 OH 0.0880 150,000.00 13,200.00
JUMLAH TENAGA KERJA 167,595.00
B BAHAN
Tee Ø 500 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.6000 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 167,595.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 167,595.00

R.I.22. (K3) Pemasangan 1 buah tee Ø 600 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0960 112,500.00 123,300.00
Tukang pipa L.07 OH 0.5480 127,500.00 69,870.00
Mandor L.17 OH 0.1100 150,000.00 16,500.00
JUMLAH TENAGA KERJA 209,670.00
B BAHAN
Tee Ø 600 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.1930 -
crane 2 T
Mobile crane ≤ 3 ton Hari 0.0960 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 209,670.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 209,670.00

R.I.23. (K3) Pemasangan 1 buah tee Ø 700 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.3160 112,500.00 148,050.00
Tukang pipa L.07 OH 0.6580 127,500.00 83,895.00
Mandor L.17 OH 0.1320 150,000.00 19,800.00
JUMLAH TENAGA KERJA 251,745.00
B BAHAN
Tee Ø 700 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.2250 -
crane 2 T
Mobile crane ≤ 3 ton Hari 0.1130 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 251,745.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 251,745.00

R.I.24. (K3) Pemasangan 1 buah tee Ø 800 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5360 112,500.00 172,800.00
Tukang pipa L.07 OH 0.7680 127,500.00 97,920.00
Mandor L.17 OH 0.1540 150,000.00 23,100.00
JUMLAH TENAGA KERJA 293,820.00
B BAHAN
Tee Ø 800 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.2570 -
crane 2 T
Mobile crane ≤ 3 ton Hari 0.1290 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 293,820.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 293,820.00

R.I.25. (K3) Pemasangan 1 buah tee Ø 900 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.7560 112,500.00 197,550.00
Tukang pipa L.07 OH 0.8780 127,500.00 111,945.00
Mandor L.17 OH 0.1760 150,000.00 26,400.00
JUMLAH TENAGA KERJA 335,895.00
B BAHAN
Tee Ø 900 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.3210 -
crane 2 T
Mobile crane ≤ 3 ton Hari 0.1610 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 335,895.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 335,895.00

R.I.26. (K3) Pemasangan 1 buah tee Ø 1000 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.9760 112,500.00 222,300.00
Tukang pipa L.07 OH 0.9880 127,500.00 125,970.00
Mandor L.17 OH 0.1980 150,000.00 29,700.00
JUMLAH TENAGA KERJA 377,970.00
B BAHAN
Tee Ø 1000 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.3660 -
crane 2 T
Mobile crane ≤ 3 ton Hari 0.1830 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 377,970.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 377,970.00

R.I.27. (K3) Pemasangan 1 buah tee Ø 1100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.1960 112,500.00 247,050.00
Tukang pipa L.07 OH 1.0980 127,500.00 139,995.00
Mandor L.17 OH 0.2200 150,000.00 33,000.00
JUMLAH TENAGA KERJA 420,045.00
B BAHAN
Tee Ø 1100 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.3860 -
crane 2 T
Mobile crane ≤ 3 ton Hari 0.1930 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 420,045.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 420,045.00
R.I.28. (K3) Pemasangan 1 buah tee Ø 1200 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.4160 112,500.00 271,800.00
Tukang pipa L.07 OH 1.2080 127,500.00 154,020.00
Mandor L.17 OH 0.2420 150,000.00 36,300.00
JUMLAH TENAGA KERJA 462,120.00
B BAHAN
Tee Ø 1200 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel & handle
Hari 0.4500 -
crane 2 T
Mobile crane ≤ 3 ton Hari 0.2250 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 462,120.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 462,120.00

II ANALISA SENDIRI
R.II.1. Pemasangan 1 buah floating valve 1"
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang pipa L.07 OH 0.0800 127,500.00 10,200.00
Kepala tukang L.14 OH 0.0790 147,500.00 11,652.50
Mandor L.17 OH 0.0400 150,000.00 6,000.00
JUMLAH TENAGA KERJA 61,602.50
B BAHAN
Floating valve 1" Buah 1.0000 -
Seal tape Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 61,602.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 61,602.50
S HARGA SATUAN PEKERJAAN PENYAMBUNGAN PIPA BARU KE PIPA LAMA
I (PERMEN NOMOR 28/PRT/M/2016)
S.I.1. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 80 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.4660 112,500.00 164,925.00
Tukang pipa L.07 OH 0.7330 127,500.00 93,457.50
Mandor L.17 OH 0.1470 150,000.00 22,050.00
JUMLAH TENAGA KERJA 280,432.50
B BAHAN
Pipa Ø 80 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.6060 -
T2/mekanik / cilinder saw
Sewa Genset 1500 watt Hari 0.0750 -
Sewa Pompa Submersible 3
Hari 0.9680 -
m3/h
Sewa Tripot/Tackel & handle
Hari 0.8650 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 280,432.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 280,432.50

S.I.2. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 100 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6460 112,500.00 185,175.00
Tukang pipa L.07 OH 0.8230 127,500.00 104,932.50
Mandor L.17 OH 0.1650 150,000.00 24,750.00
JUMLAH TENAGA KERJA 314,857.50
B BAHAN
Pipa Ø 100 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.6500 -
T2/mekanik / cilinder saw
Sewa Genset 1500 watt Hari 0.1590 -
Sewa Pompa Submersible 3
Hari 1.0780 -
m3/h
Sewa Tripot/Tackel & handle
Hari 0.9110 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 314,857.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 314,857.50
S.I.3. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 150 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.0960 112,500.00 235,800.00
Tukang pipa L.07 OH 1.0480 127,500.00 133,620.00
Mandor L.17 OH 0.2100 150,000.00 31,500.00
JUMLAH TENAGA KERJA 400,920.00
B BAHAN
Pipa Ø 150 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.7600 -
T2/mekanik / cilinder saw
Sewa Genset 1500 watt Hari 0.3690 -
Sewa Pompa Submersible 3
Hari 1.3530 -
m3/h
Sewa Tripot/Tackel & handle
Hari 1.0260 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 400,920.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 400,920.00

S.I.4. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 200 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.5460 112,500.00 286,425.00
Tukang pipa L.07 OH 1.2730 127,500.00 162,307.50
Mandor L.17 OH 0.2550 150,000.00 38,250.00
JUMLAH TENAGA KERJA 486,982.50
B BAHAN
Pipa Ø 200 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.8700 -
T2/mekanik / cilinder saw
Sewa Genset 1500 watt Hari 0.5790 -
Sewa Pompa Submersible 3
Hari 1.6280 -
m3/h
Sewa Tripot/Tackel & handle
Hari 1.1410 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 486,982.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 486,982.50
S.I.5. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 250 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.9960 112,500.00 337,050.00
Tukang pipa L.07 OH 1.4980 127,500.00 190,995.00
Mandor L.17 OH 0.3000 150,000.00 45,000.00
JUMLAH TENAGA KERJA 573,045.00
B BAHAN
Pipa Ø 250 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 0.9800 -
T2/mekanik / cilinder saw
Sewa Genset 1500 watt Hari 0.7890 -
Sewa Pompa Submersible 3
Hari 1.9030 -
m3/h
Sewa Tripot/Tackel & handle
Hari 1.2560 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 573,045.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 573,045.00

S.I.6. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 300 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.4460 112,500.00 387,675.00
Tukang pipa L.07 OH 1.7230 127,500.00 219,682.50
Mandor L.17 OH 0.3450 150,000.00 51,750.00
JUMLAH TENAGA KERJA 659,107.50
B BAHAN
Pipa Ø 300 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 1.0900 -
T2/mekanik / cilinder saw
Sewa Genset 1500 watt Hari 0.9990 -
Sewa Pompa Submersible 3
Hari 2.1780 -
m3/h
Sewa Tripot/Tackel & handle
Hari 1.3710 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 659,107.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 659,107.50

S.I.7. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 400 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 4.3460 112,500.00 488,925.00
Tukang pipa L.07 OH 2.1730 127,500.00 277,057.50
Mandor L.17 OH 0.4350 150,000.00 65,250.00
JUMLAH TENAGA KERJA 831,232.50
B BAHAN
Pipa Ø 400 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 1.3100 -
T2/mekanik / cilinder saw
Sewa Genset 1500 watt Hari 1.4190 -
Sewa Pompa Submersible 3
Hari 2.7280 -
m3/h
Sewa Tripot/Tackel & handle
Hari 1.6010 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 831,232.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 831,232.50

S.I.8. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 450 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 4.7960 112,500.00 539,550.00
Tukang pipa L.07 OH 2.3980 127,500.00 305,745.00
Mandor L.17 OH 0.4800 150,000.00 72,000.00
JUMLAH TENAGA KERJA 917,295.00
B BAHAN
Pipa Ø 450 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 1.4200 -
T2/mekanik / cilinder saw
Sewa Genset 1500 watt Hari 1.6290 -
Sewa Pompa Submersible 3
Hari 3.0030 -
m3/h
Sewa Tripot/Tackel & handle
Hari 1.7160 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 917,295.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 917,295.00

S.I.9. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 500 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 5.2460 112,500.00 590,175.00
Tukang pipa L.07 OH 2.6230 127,500.00 334,432.50
Mandor L.17 OH 0.5250 150,000.00 78,750.00
JUMLAH TENAGA KERJA 1,003,357.50
B BAHAN
Pipa Ø 500 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 1.5300 -
T2/mekanik / cilinder saw
Sewa Genset 1500 watt Hari 1.8390 -
Sewa Pompa Submersible 3
Hari 3.2780 -
m3/h
Sewa Tripot/Tackel & handle
Hari 1.8310 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,003,357.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,003,357.50

S.I.10. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 600 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 6.1460 112,500.00 691,425.00
Tukang pipa L.07 OH 3.0730 127,500.00 391,807.50
Mandor L.17 OH 0.6150 150,000.00 92,250.00
JUMLAH TENAGA KERJA 1,175,482.50
B BAHAN
Pipa Ø 600 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 1.7500 -
T2/mekanik / cilinder saw
Sewa Genset 1500 watt Hari 2.2590 -
Sewa Pompa Submersible 3
Hari 3.8280 -
m3/h
Sewa Tripot/Tackel & handle
Hari 2.0610 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,175,482.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,175,482.50

S.I.11. (K3) Penyambungan 1 buah pipa baru ke pipa yang ada Ø 700 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 7.0460 112,500.00 792,675.00
Tukang pipa L.07 OH 3.5230 127,500.00 449,182.50
Mandor L.17 OH 0.7050 150,000.00 105,750.00
JUMLAH TENAGA KERJA 1,347,607.50
B BAHAN
Pipa Ø 700 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 1.9700 -
T2/mekanik / cilinder saw
Sewa Genset 1500 watt Hari 2.6790 -
Sewa Pompa Submersible 3
Hari 4.3780 -
m3/h
Sewa Tripot/Tackel & handle
Hari 2.2910 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,347,607.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,347,607.50

S.I.12. (K3) Penyambungan 1 buah 1 buah pipa baru ke pipa yang ada Ø 800 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 7.9460 112,500.00 893,925.00
Tukang pipa L.07 OH 3.9730 127,500.00 506,557.50
Mandor L.17 OH 0.7950 150,000.00 119,250.00
JUMLAH TENAGA KERJA 1,519,732.50
B BAHAN
Pipa Ø 800 mm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
Peralatan potong pipa
Hari 2.1900 -
T2/mekanik / cilinder saw
Sewa Genset 1500 watt Hari 3.0990 -
Sewa Pompa Submersible 3
Hari 4.9280 -
m3/h
Sewa Tripot/Tackel & handle
Hari 2.5210 -
crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,519,732.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,519,732.50
T HARGA SATUAN PEKERJAAN PENGETESAN PIPA
I (PERMEN NOMOR 28/PRT/M/2016)
T.I.1. (K3) Pengetesan 1 m pipa Ø 50 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0080 112,500.00 900.00
Mandor L.17 OH 0.0008 150,000.00 120.00
JUMLAH TENAGA KERJA 1,020.00
B BAHAN
Air test (air bersih) m3 0.0020 -
Bahan bakar Liter 0.0600 -
Oli Liter 0.0020 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,020.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,020.00

T.I.2. (K3) Pengetesan 1 m pipa Ø 75 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0080 112,500.00 900.00
Mandor L.17 OH 0.0008 150,000.00 120.00
JUMLAH TENAGA KERJA 1,020.00
B BAHAN
Air test (air bersih) m3 0.0040 -
Bahan bakar Liter 0.0600 -
Oli Liter 0.0020 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,020.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,020.00

T.I.3. (K3) Pengetesan 1 m pipa Ø 100 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0080 112,500.00 900.00
Mandor L.17 OH 0.0008 150,000.00 120.00
JUMLAH TENAGA KERJA 1,020.00
B BAHAN
Air test (air bersih) m3 0.0080 -
Bahan bakar Liter 0.0600 -
Oli Liter 0.0020 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,020.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,020.00

T.I.4. (K3) Pengetesan 1 m pipa Ø 150 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0080 112,500.00 900.00
Mandor L.17 OH 0.0008 150,000.00 120.00
JUMLAH TENAGA KERJA 1,020.00
B BAHAN
Air test (air bersih) m3 0.0180 -
Bahan bakar Liter 0.0600 -
Oli Liter 0.0020 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,020.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,020.00

T.I.5. (K3) Pengetesan 1 m pipa Ø 200 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0080 112,500.00 900.00
Mandor L.17 OH 0.0008 150,000.00 120.00
JUMLAH TENAGA KERJA 1,020.00
B BAHAN
Air test (air bersih) m3 0.0310 -
Bahan bakar Liter 0.0600 -
Oli Liter 0.0020 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,020.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,020.00

T.I.6. (K3) Pengetesan 1 m pipa Ø 250 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0080 112,500.00 900.00
Mandor L.17 OH 0.0008 150,000.00 120.00
JUMLAH TENAGA KERJA 1,020.00
B BAHAN
Air test (air bersih) m3 0.0490 -
Bahan bakar Liter 0.0600 -
Oli Liter 0.0020 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,020.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,020.00

T.I.7. (K3) Pengetesan 1 m pipa Ø 300 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0080 112,500.00 900.00
Mandor L.17 OH 0.0008 150,000.00 120.00
JUMLAH TENAGA KERJA 1,020.00
B BAHAN
Air test (air bersih) m3 0.0710 -
Bahan bakar Liter 0.0600 -
Oli Liter 0.0020 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,020.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,020.00

T.I.8. (K3) Pengetesan 1 m pipa Ø 400 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0080 112,500.00 900.00
Mandor L.17 OH 0.0008 150,000.00 120.00
JUMLAH TENAGA KERJA 1,020.00
B BAHAN
Air test (air bersih) m3 0.1260 -
Bahan bakar Liter 0.0600 -
Oli Liter 0.0020 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,020.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,020.00

T.I.9. (K3) Pengetesan 1 m pipa Ø 500 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0080 112,500.00 900.00
Mandor L.17 OH 0.0008 150,000.00 120.00
JUMLAH TENAGA KERJA 1,020.00
B BAHAN
Air test (air bersih) m3 0.1580 -
Bahan bakar Liter 0.0600 -
Oli Liter 0.0020 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,020.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,020.00

T.I.10. (K3) Pengetesan 1 m pipa Ø 600 mm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0080 112,500.00 900.00
Mandor L.17 OH 0.0008 150,000.00 120.00
JUMLAH TENAGA KERJA 1,020.00
B BAHAN
Air test (air bersih) m3 0.2830 -
Bahan bakar Liter 0.0600 -
Oli Liter 0.0020 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,020.00
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,020.00
U HARGA SATUAN PEKERJAAN MEKANIKAL / ELEKTRIKAL
I ANALISA SENDIRI
U.I.1. Pemasangan 1 titik instalasi lampu
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang listrik L.09 OH 0.1500 130,000.00 19,500.00
Kepala tukang L.14 OH 0.0140 147,500.00 2,065.00
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 55,465.00
B BAHAN
Kabel NYM 3cx2.5 mm2 m1 8.0000 17,850.00 142,800.00
PVC HI conduct Ø20 mm m1 8.0000 4,250.00 34,000.00
Inbowduss Buah 1.0000 9,333.33 9,333.33
Klem Ø20 mm Buah 10.0000 1,150.00 11,500.00
Sock Ø20 mm Buah 3.0000 5,333.33 16,000.00
Tee dos/JB Buah 1.0000 8,833.33 8,833.33
JUMLAH HARGA BAHAN 222,466.67
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 277,931.67


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 277,931.67

U.I.2. Pemasangan 1 titik instalasi stop kontak


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 69,400.00
B BAHAN
Kabel NYM 3cx2.5 mm2 m1 19.0000 17,850.00 339,150.00
PVC HI conduct Ø20 mm m1 19.0000 4,250.00 80,750.00
Inbowduss Buah 1.0000 9,333.33 9,333.33
Klem Ø20 mm Buah 15.8300 1,150.00 18,204.50
Sock Ø20 mm Buah 7.9200 5,333.33 42,240.00
Tee dos/JB Buah 1.0000 8,833.33 8,833.33
JUMLAH HARGA BAHAN 498,511.17
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 567,911.17


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 567,911.17

U.I.3. Pemasangan 1 titik instalasi power AC


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2700 112,500.00 30,375.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 66,025.00
B BAHAN
Kabel NYM/NYA 3cx2.5
m1 30.0000 -
mm2
PVC HI conduct Ø20 mm m1 30.0000 -
Inbowduss Buah 1.0000 -
Klem Ø20 mm Buah 23.0000 -
Sock Ø20 mm Buah 17.0000 -
Tee dos/JB Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 66,025.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 66,025.00

U.I.4. Pemasangan 1 titik instalasi exhaust fan di toilet


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 91,900.00
B BAHAN
Kabel NYM/NYA 3cx2.5
m1 30.0000 -
mm2
PVC HI conduct Ø20 mm m1 30.0000 -
Klem Ø20 mm Buah 20.6900 -
Sock Ø20 mm Buah 10.3400 -
Tee dos/JB Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 91,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 91,900.00

U.I.5. Pemasangan 1 titik instalasi saklar


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 58,150.00
B BAHAN
Kabel NYM/NYA 3cx2.5
m1 15.0000 -
mm2
PVC HI conduct Ø20 mm m1 15.0000 -
MK zeng Buah 1.0000 -
Klem Ø20 mm Buah 12.5000 -
Sock Ø20 mm Buah 6.2500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 58,150.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 58,150.00

U.I.6. Pemasangan 1 titik instalasi kabel data


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 91,900.00
B BAHAN
Kabel cat 5E m1 25.0000 -
PVC HI conduct Ø20 mm m1 25.0000 -
Inbowduss Buah 1.0000 -
Klem Ø20 mm Buah 35.7140 -
Sock Ø20 mm Buah 8.6210 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 91,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 91,900.00

U.I.7. Pemasangan 1 titik instalasi sound system


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 58,150.00
B BAHAN
Kabel multi core 2x80 m1 14.0000 -
PVC HI conduct Ø20 mm m1 14.0000 -
Inbowduss Buah 1.0000 -
Klem Ø20 mm Buah 17.5000 -
Sock Ø20 mm Buah 6.0000 -
Tee dos/JB Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 58,150.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 58,150.00

U.I.8. Pemasangan 1 titik instalasi volume kontrol


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang listrik L.09 OH 0.1500 130,000.00 19,500.00
Kepala tukang L.14 OH 0.0340 147,500.00 5,015.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 48,515.00
B BAHAN
Kabenl NYM 2cx1,5 mm2 m1 10.5000 -
PVC HI conduct Ø20 mm m1 10.5000 -
Inbowduss Buah 1.0000 -
Klem Ø20 mm Buah 1.3130 -
Sock Ø20 mm Buah 3.7500 -
Tee dos/JB Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 48,515.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 48,515.00

U.I.9. Pemasangan 1 titik instalasi detector fire alarm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 58,150.00
B BAHAN
Kabenl NYM 2cx1,5 mm2 m1 16.0000 -
PVC HI conduct Ø20 mm m1 11.0400 -
Inbowduss Buah 3.0000 -
Klem Ø20 mm Buah 14.0000 -
Sock Ø20 mm Buah 6.0000 -
Tee dos/JB Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 58,150.00
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 58,150.00

U.I.10. Pemasangan 1 titik instalasi indicator lamp, alarm bell dan manual push button
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang listrik L.09 OH 0.1500 130,000.00 19,500.00
Kepala tukang L.14 OH 0.0340 147,500.00 5,015.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 48,515.00
B BAHAN
Kabenl NYM 2cx1,5 mm2 m1 76.0000 -
PVC HI conduct Ø20 mm m1 76.0000 -
Inbowduss Buah 1.0000 -
Klem Ø20 mm Buah 9.5000 -
Sock Ø20 mm Buah 27.1430 -
Tee dos/JB Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 48,515.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 48,515.00

U.I.11. Pemasangan 1 titik instalasi CCTV


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 58,150.00
B BAHAN
Coadsial 7C m1 20.0000 -
PVC HI conduct Ø20 mm m1 20.0000 -
Inbowduss Buah 1.0000 -
Klem Ø20 mm Buah 60.7100 -
Sock Ø20 mm Buah 30.3600 -
Tee dos/JB Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 58,150.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 58,150.00

U.I.12. Pemasangan 1 titik instalasi antena TV


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0500 112,500.00 5,625.00
Tukang listrik L.09 OH 0.0200 130,000.00 2,600.00
Kepala tukang L.14 OH 0.1000 147,500.00 14,750.00
Mandor L.17 OH 0.1000 150,000.00 15,000.00
JUMLAH TENAGA KERJA 37,975.00
B BAHAN
Kabel antena m1 10.0000 -
Stop kontak tanam Pasang 1.0000 -
Isolasi Buah 0.5000 -
Klem Ø20 mm Buah 3.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 37,975.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 37,975.00

U.I.13. Pemasangan 1 titik instalasi telephone


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0500 112,500.00 5,625.00
Tukang listrik L.09 OH 0.0200 130,000.00 2,600.00
Kepala tukang L.14 OH 0.1000 147,500.00 14,750.00
Mandor L.17 OH 0.1000 150,000.00 15,000.00
JUMLAH TENAGA KERJA 37,975.00
B BAHAN
Kabel telephone 4x0,5 mm m1 10.0000 -
Isolasi Buah 0.5000 -
Klem Ø20 mm Buah 3.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 37,975.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 37,975.00

U.I.14. Pemasangan 1 m1 kabel NYY 4x16 mm2


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Tukang listrik L.09 OH 0.1400 130,000.00 18,200.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 23,425.00
B BAHAN
Kabel NYY 4cx16 mm2 m1 1.0000 -
Termination material % 0.0500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,425.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,425.00

U.I.15. Pemasangan 1 m1 kabel NYY 4x25 mm2


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Tukang listrik L.09 OH 0.1400 130,000.00 18,200.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 23,425.00
B BAHAN
Kabel NYY 4cx25 mm2 m1 1.0000 -
Termination material % 0.0500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 23,425.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 23,425.00

U.I.16. Pemasangan 1 m1 kabel feeder 2x UTP cat 6


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang listrik L.09 OH 0.0500 130,000.00 6,500.00
Kepala tukang L.14 OH 0.0060 147,500.00 885.00
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 24,410.00
B BAHAN
Kabel feeder UTP cat 6 m1 1.0000 -
Termination material % 0.0500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 24,410.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 24,410.00

U.I.17. Pemasangan 1 buah saklar tunggal


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0400 112,500.00 4,500.00
Tukang listrik L.09 OH 0.1400 130,000.00 18,200.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 25,675.00
B BAHAN
Saklar single Buah 1.0000 24,500.00 24,500.00
JUMLAH HARGA BAHAN 24,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,175.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 50,175.00

U.I.18. Pemasangan 1 buah saklar ganda


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0400 112,500.00 4,500.00
Tukang listrik L.09 OH 0.1400 130,000.00 18,200.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 25,675.00
B BAHAN
Saklar double Buah 1.0000 37,000.00 37,000.00
JUMLAH HARGA BAHAN 37,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 62,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 62,675.00

U.I.19. Pemasangan 1 buah saklar tukar


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0400 112,500.00 4,500.00
Tukang listrik L.09 OH 0.1400 130,000.00 18,200.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 25,675.00
B BAHAN
Saklar tukar Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 25,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 25,675.00
U.I.20. Pemasangan 1 buah stop kontak
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0400 112,500.00 4,500.00
Tukang listrik L.09 OH 0.1400 130,000.00 18,200.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 25,675.00
B BAHAN
Stop kontak Buah 1.0000 29,500.00 29,500.00
JUMLAH HARGA BAHAN 29,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 55,175.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 55,175.00

U.I.21. Pemasangan 1 buah stop kontak AC


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0700 112,500.00 7,875.00
Tukang listrik L.09 OH 0.1000 130,000.00 13,000.00
Kepala tukang L.14 OH 0.0020 147,500.00 295.00
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 21,320.00
B BAHAN
Stop kontak AC Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 21,320.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 21,320.00

U.I.22. Pemasangan 1 buah outlet kabel data


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0700 112,500.00 7,875.00
Tukang listrik L.09 OH 0.0100 130,000.00 1,300.00
Kepala tukang L.14 OH 0.0020 147,500.00 295.00
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 9,620.00
B BAHAN
Outlet kabel data Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 9,620.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 9,620.00

U.I.23. Pemasangan 1 buah outlet TV


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang listrik L.09 OH 0.1000 130,000.00 13,000.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0250 150,000.00 3,750.00
JUMLAH TENAGA KERJA 35,375.00
B BAHAN
Outlet TV Buah 1.0000 -
Mangkok listrik Buah 1.0000 -
Isolasi Buah 0.2500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 35,375.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 35,375.00

U.I.24. Pemasangan 1 buah telephone


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang listrik L.09 OH 0.1000 130,000.00 13,000.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0250 150,000.00 3,750.00
JUMLAH TENAGA KERJA 35,375.00
B BAHAN
Outlet telephone Buah 1.0000 -
Mangkok listrik Buah 1.0000 -
Isolasi Buah 0.2500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 35,375.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 35,375.00

U.I.25. Pemasangan 1 unit lampu LED 9 watt


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0400 112,500.00 4,500.00
Tukang listrik L.09 OH 0.1400 130,000.00 18,200.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 25,675.00
B BAHAN
Fitting Buah 1.0000 11,500.00 11,500.00
Lampu LED 9 watt Buah 1.0000 93,000.00 93,000.00
JUMLAH HARGA BAHAN 104,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 130,175.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 130,175.00

U.I.26. Pemasangan 1 buah kap lampu RMI 2x18 watt cover akrilik
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0400 112,500.00 4,500.00
Tukang listrik L.09 OH 0.1400 130,000.00 18,200.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 25,675.00
B BAHAN
Kap lampu RMI 2x18 watt
Buah 1.0000 -
cover akrilik
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 25,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 25,675.00

U.I.27. Pemasangan 1 buah lampu TL 18 watt


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0400 112,500.00 4,500.00
Tukang listrik L.09 OH 0.1400 130,000.00 18,200.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 25,675.00
B BAHAN
Lampu TL 18 watt Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 25,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 25,675.00
U.I.28. Pemasangan 1 buah lampu baret LED 7 watt
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0400 112,500.00 4,500.00
Tukang listrik L.09 OH 0.1400 130,000.00 18,200.00
Kepala tukang L.14 OH 0.0100 147,500.00 1,475.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 25,675.00
B BAHAN
Lampu baret LED 7 watt Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 25,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 25,675.00

U.I.29. Pemasangan 1 buah lampu periksa


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0700 112,500.00 7,875.00
Tukang listrik L.09 OH 0.0100 130,000.00 1,300.00
Kepala tukang L.14 OH 0.0080 147,500.00 1,180.00
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 10,505.00
B BAHAN
Lampu periksa Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 10,505.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 10,505.00

U.I.30. Pemasangan 1 m1 lampu LED strips 7.2 watt


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang listrik L.09 OH 0.1000 130,000.00 13,000.00
Kepala tukang L.14 OH 0.0500 147,500.00 7,375.00
Mandor L.17 OH 0.0250 150,000.00 3,750.00
JUMLAH TENAGA KERJA 35,375.00
B BAHAN
Lampu periksa m1 1.0000 -
Isolasi Buah 0.2500 -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 35,375.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 35,375.00

U.I.31. Pemasangan 1 unit AC wall mounted


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang listrik L.09 OH 0.7500 130,000.00 97,500.00
Kepala tukang L.14 OH 0.0630 147,500.00 9,292.50
Mandor L.17 OH 0.0380 150,000.00 5,700.00
JUMLAH TENAGA KERJA 224,992.50
B BAHAN
Lampu periksa m1 1.0000 -
Perlengkapan % 0.1500 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 224,992.50


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 224,992.50

U.I.32. Pemasangan 1 buah exhaust fan type ceiling


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang listrik L.09 OH 0.1000 130,000.00 13,000.00
Kepala tukang L.14 OH 0.0060 147,500.00 885.00
Mandor L.17 OH 0.0010 150,000.00 150.00
JUMLAH TENAGA KERJA 30,910.00
B BAHAN
Exhaust fan type ceiling Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 30,910.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 30,910.00

U.I.33. Pemasangan 1 unit panel MDP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 5.0000 112,500.00 562,500.00
Tukang listrik L.09 OH 3.0000 130,000.00 390,000.00
Kepala tukang L.14 OH 2.0000 147,500.00 295,000.00
Mandor L.17 OH 1.2000 150,000.00 180,000.00
JUMLAH TENAGA KERJA 1,427,500.00
B BAHAN
Box panel metal ukuran
Unit 1.0000 -
80x140x40 cm
Panel aksesoris % 0.4500 - -
COS (change over suite) Buah 1.0000 -
MCB induk 50 A Buah 1.0000 -
MCB induk 20 A Buah 2.0000 -
MCB beban 1 PH Buah 31.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,427,500.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,427,500.00

U.I.34. Pemasangan 1 unit panel SDP


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0400 112,500.00 4,500.00
Tukang listrik L.09 OH 0.1400 130,000.00 18,200.00
Kepala tukang L.14 OH 0.1000 147,500.00 14,750.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 38,950.00
B BAHAN
Box panel metal ukuran
Unit 1.0000 -
80x140x40 cm
Panel aksesoris % 0.4500 - -
MCB induk 50 A Buah 1.0000 -
MCB beban 1 PH Buah 30.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 38,950.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 38,950.00

U.I.35. Pemasangan 1 buah dvr 16 channel


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.4000 130,000.00 52,000.00
Kepala tukang L.14 OH 0.0360 147,500.00 5,310.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 124,060.00
B BAHAN
Dvr 16 ch Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 124,060.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 124,060.00

U.I.36. Pemasangan 1 buah monitor CCTV


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.4000 130,000.00 52,000.00
Kepala tukang L.14 OH 0.0360 147,500.00 5,310.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 124,060.00
B BAHAN
Monitor 29 inch Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 124,060.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 124,060.00

U.I.37. Pemasangan dan instalasi 1 unit komputer storage 2 TB


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.4000 130,000.00 52,000.00
Kepala tukang L.14 OH 0.0360 147,500.00 5,310.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 124,060.00
B BAHAN
Monitor 24 inch Buah 1.0000 -
CPU full set Unit 1.0000 -
Mouse Buah 1.0000 -
Keyboard Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 124,060.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 124,060.00

U.I.38. Pemasangan 1 buah CCTV


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.4000 130,000.00 52,000.00
Kepala tukang L.14 OH 0.0360 147,500.00 5,310.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 124,060.00
B BAHAN
Colour camera (fixed) Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 124,060.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 124,060.00

U.I.39. Pemasangan 1 buah amplifier 240 watt


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 100,900.00
B BAHAN
Amplifier 240 watt Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,900.00

U.I.40. Pemasangan 1 buah mixer 12 channel


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.4000 130,000.00 52,000.00
Kepala tukang L.14 OH 0.0360 147,500.00 5,310.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 124,060.00
B BAHAN
Mixer 12 channel Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 124,060.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 124,060.00

U.I.41. Pemasangan 1 buah tuner radio dan CD mp3


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 100,900.00
B BAHAN
Tuner radio dan CD mp3 Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,900.00

U.I.42. Pemasangan 1 buah DVD player


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.4000 130,000.00 52,000.00
Kepala tukang L.14 OH 0.0360 147,500.00 5,310.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 124,060.00
B BAHAN
DVD player Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 124,060.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 124,060.00

U.I.43. Pemasangan 1 buah speaker selector 10 channel


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.4000 130,000.00 52,000.00
Kepala tukang L.14 OH 0.0360 147,500.00 5,310.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 124,060.00
B BAHAN
Speaker selector 10 channel Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 124,060.00
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 124,060.00

U.I.44. Pemasangan 1 unit cabinet rack sound system dengan power


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 100,900.00
B BAHAN
Cabinet rack sound system
Unit 1.0000 -
dengan power
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,900.00

U.I.45. Pemasangan 1 buah ceiling speaker


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 58,150.00
B BAHAN
Ceiling speaker Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 58,150.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 58,150.00

U.I.46. Pemasangan 1 buah volume control


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 58,150.00
B BAHAN
Volume control Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 58,150.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 58,150.00

U.I.47. Pemasangan 1 unit DP sound system


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 112,500.00 22,500.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 58,150.00
B BAHAN
Box panel metal ukuran
Unit 1.0000 -
30x40x20 cm
Panel aksesoris % 0.1500 - -
Conector ls 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 58,150.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 58,150.00

U.I.48. Pemasangan 1 unit master control FA


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.4000 130,000.00 52,000.00
Kepala tukang L.14 OH 0.0360 147,500.00 5,310.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 124,060.00
B BAHAN
Box panel metal ukuran
Unit 1.0000 -
30x40x20 cm
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 124,060.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 124,060.00

U.I.49. Pemasangan 1 unit panel MDF


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.4000 130,000.00 52,000.00
Kepala tukang L.14 OH 0.0360 147,500.00 5,310.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 124,060.00
B BAHAN
Panel MDF Unit 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 124,060.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 124,060.00

U.I.50. Pemasangan 1 buah ROR heat detector


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 100,900.00
B BAHAN
ROR heat detector Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,900.00

U.I.51. Pemasangan 1 buah smoke detector


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.4000 130,000.00 52,000.00
Kepala tukang L.14 OH 0.0360 147,500.00 5,310.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 124,060.00
B BAHAN
Smoke detector Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 124,060.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 124,060.00
U.I.52. Pemasangan 1 buah indicator lamp
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 100,900.00
B BAHAN
Indicator lamp Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,900.00

U.I.53. Pemasangan 1 buah alarm bell


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 100,900.00
B BAHAN
Alarm bell Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,900.00

U.I.54. Pemasangan 1 buah manual push button


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 100,900.00
B BAHAN
Manual push button Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,900.00

U.I.55. Pemasangan 1 buah terminal box fire alarm 24 pair


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 100,900.00
B BAHAN
Terminal box fire alarm 24
Buah 1.0000 -
pair
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,900.00

U.I.56. Pemasangan dan instalasi 1 unit komputer ruang server


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 100,900.00
B BAHAN
Monitor 24 inch Buah 1.0000 -
Komputer full set Unit 1.0000 -
Mouse Buah 1.0000 -
Keyboard Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,900.00

U.I.57. Pemasangan 1 buah router ceiling wifi


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.4000 130,000.00 52,000.00
Kepala tukang L.14 OH 0.0360 147,500.00 5,310.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 124,060.00
B BAHAN
Router ceiling wifi Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 124,060.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 124,060.00

U.I.58. Pemasangan 1 buah switch hub 24 port


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 100,900.00
B BAHAN
Switch hub 24 port Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,900.00

U.I.59. Pemasangan 1 buah wall mounted rack 8 U


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5800 112,500.00 65,250.00
Tukang listrik L.09 OH 0.2400 130,000.00 31,200.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 100,900.00
B BAHAN
Wall mounted rack 8 U Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 100,900.00

U.I.60. Pemasangan 1 buah box panel MCB


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0500 112,500.00 5,625.00
Tukang listrik L.09 OH 1.0000 130,000.00 130,000.00
Kepala tukang L.14 OH 1.0000 147,500.00 147,500.00
JUMLAH TENAGA KERJA 283,125.00
B BAHAN
Box panel isi 4 MCB Buah 1.0000 -
MCB 6 A Buah 2.0000 -
MCB 4 A Buah 2.0000 -
Kabel NYM 3x2,5 mm2 m1 6.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 283,125.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 283,125.00

U.I.61. Pemasangan 1 set air protection 50 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8000 112,500.00 90,000.00
Tukang listrik L.09 OH 0.2100 130,000.00 27,300.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 121,750.00
B BAHAN
Air protection 50 m Set 1.0000 -
Material bantu % 1.0000 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 121,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 121,750.00

U.I.62. Pemasangan 1 m1 BC 70 mm
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang listrik L.09 OH 0.0800 130,000.00 10,400.00
Kepala tukang L.14 OH 0.0320 147,500.00 4,720.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 27,870.00
B BAHAN
BC 70 mm m1 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,870.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,870.00

U.I.63. Pemasangan 1 unit kontrol box


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang listrik L.09 OH 0.0800 130,000.00 10,400.00
Kepala tukang L.14 OH 0.0320 147,500.00 4,720.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 27,870.00
B BAHAN
Kontrol box Unit 1.0000 -
Material bantu % 1.0000 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,870.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 27,870.00

U.I.64. Pemasangan 1 unit ground rout


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8000 112,500.00 90,000.00
Tukang listrik L.09 OH 0.2100 130,000.00 27,300.00
Kepala tukang L.14 OH 0.0200 147,500.00 2,950.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 121,750.00
B BAHAN
Ground electrode Unit 1.0000 -
Material bantu % 1.0000 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 121,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 121,750.00

U.I.65. Pemasangan 1 m1 tiang galvanis


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 112,500.00 16,875.00
Tukang listrik L.09 OH 0.0800 130,000.00 10,400.00
Kepala tukang L.14 OH 0.0400 147,500.00 5,900.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 34,675.00
B BAHAN
Tiang galvanis m1 1.0000 -
Material bantu % 1.0000 - -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 34,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 34,675.00
V HARGA SATUAN PEKERJAAN SOFTSCAPE
I ANALISA SENDIRI
V.I.1. Pengurugan 1 m3 tanah subur
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3500 112,500.00 39,375.00
Mandor L.17 OH 0.0230 150,000.00 3,450.00
JUMLAH TENAGA KERJA 42,825.00
B BAHAN
Tanah subur m3 1.1000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 42,825.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 42,825.00

V.I.2. Pengurugan 1 m3 pupuk kompos


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3500 112,500.00 39,375.00
Mandor L.17 OH 0.0230 150,000.00 3,450.00
JUMLAH TENAGA KERJA 42,825.00
B BAHAN
Pupuk kompos m3 1.1000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 42,825.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 42,825.00

V.I.3. Penanaman 1 m2 rumput jepang


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,675.00
B BAHAN
Rumput jepang m2 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,675.00
V.I.4. Penanaman 1 buah tanaman pandan merah
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,675.00
B BAHAN
Tanaman pandan merah Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,675.00

V.I.5. Penanaman 1 buah tanaman jaburan hijau


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,675.00
B BAHAN
Tanaman jaburan hijau Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,675.00

V.I.6. Penanaman 1 buah tanaman jaburan putih


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,675.00
B BAHAN
Tanaman jaburan putih Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,675.00

V.I.7. Penanaman 1 buah tanaman leli


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,675.00
B BAHAN
Tanaman leli Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,675.00

V.I.8. Penanaman 1 buah tanaman sirih belanda


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,675.00
B BAHAN
Tanaman sirih belanda Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,675.00

V.I.9. Penanaman 1 buah tanaman rosalia


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,675.00
B BAHAN
Tanaman rosalia Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,675.00

V.I.10. Penanaman 1 buah tanaman pandan afrika


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,675.00
B BAHAN
Tanaman pandan afrika Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,675.00

V.I.11. Penanaman 1 buah tanaman pasok 1,5 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,675.00
B BAHAN
Tanaman pasok 1,5 m Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,675.00

V.I.12. Penanaman 1 buah tanaman andong 1 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,675.00
B BAHAN
Tanaman andong 1m Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,675.00

V.I.13. Penanaman 1 buah tanaman kembang sepatu 1,5 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,675.00
B BAHAN
Tanaman kembang sepatu
Buah 1.0500 -
1,5 m
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,675.00

V.I.14. Penanaman 1 buah tanaman puring 0,9 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,675.00
B BAHAN
Tanaman puring 0,9 m Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,675.00

V.I.15. Penanaman 1 buah tanaman onje 1,2 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,675.00
B BAHAN
Tanaman onje 1,2 m Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,675.00

V.I.16. Penanaman 1 buah tanaman soka 1 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,675.00
B BAHAN
Tanaman soka 1 m Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,675.00

V.I.17. Penanaman 1 buah tanaman bunga portulaca


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,675.00
B BAHAN
Tanaman bunga portulaca Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,675.00

V.I.18. Penanaman 1 buah tanaman jepun / kamboja 3,5 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 112,500.00 168,750.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 169,050.00
B BAHAN
Tanaman jepun/kamboja 3,5
Buah 1.0500 -
m
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 169,050.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 169,050.00

V.I.19. Penanaman 1 buah tanaman jepun fosil diameter 15 - 25


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 112,500.00 168,750.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 169,050.00
B BAHAN
Tanaman jepun fosil dia. 15-
Buah 1.0500 -
25
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 169,050.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 169,050.00

V.I.20. Penanaman 1 buah tanaman ketapang kencana 4 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,675.00
B BAHAN
Tanaman ketapang kencana
Buah 1.0500 -
4m
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,675.00

V.I.21. Penanaman 1 buah tanaman pule diameter 75 - 90 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.5000 112,500.00 281,250.00
Mandor L.17 OH 0.1600 150,000.00 24,000.00
JUMLAH TENAGA KERJA 305,250.00
B BAHAN
Tanaman pule dia. 75 - 90
Buah 1.0000 -
cm
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 305,250.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 305,250.00

V.I.22. Penanaman 1 buah tanaman pule diameter 60 -75 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 2.5000 112,500.00 281,250.00
Mandor L.17 OH 0.1600 150,000.00 24,000.00
JUMLAH TENAGA KERJA 305,250.00
B BAHAN
Tanaman pule dia. 60 - 75
Buah 1.0000 -
cm
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 305,250.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 305,250.00

V.I.23. Penanaman 1 buah tanaman maja


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5600 112,500.00 63,000.00
Mandor L.17 OH 0.1600 150,000.00 24,000.00
JUMLAH TENAGA KERJA 87,000.00
B BAHAN
Tanaman maja Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 87,000.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 87,000.00

V.I.24. Penanaman 1 buah tanaman kamboja merah diameter 40 - 60 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5600 112,500.00 63,000.00
Mandor L.17 OH 0.1600 150,000.00 24,000.00
JUMLAH TENAGA KERJA 87,000.00
B BAHAN
Tanaman kamboja merah
Buah 1.0000 -
dia. 40 - 60 cm
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 87,000.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 87,000.00

V.I.25. Penanaman 1 buah tanaman pisang karibia


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0800 112,500.00 9,000.00
Mandor L.17 OH 0.0160 150,000.00 2,400.00
JUMLAH TENAGA KERJA 11,400.00
B BAHAN
Tanaman pisang karibia Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 11,400.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 11,400.00

V.I.26. Penanaman 1 buah tanaman cotadera selloana


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0100 112,500.00 1,125.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 2,625.00
B BAHAN
Tanaman cotadera solloana Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 2,625.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 2,625.00

V.I.27. Penanaman 1 buah tanaman bambusa vulgaris (bambu kuning)


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Mandor L.17 OH 0.0160 150,000.00 2,400.00
JUMLAH TENAGA KERJA 4,650.00
B BAHAN
Tanaman bambusa vulgaris
Buah 1.0000 -
(bambu kuning)
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 4,650.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 4,650.00

V.I.28. Penanaman 1 buah tanaman calathea lutea


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0160 112,500.00 1,800.00
Mandor L.17 OH 0.0140 150,000.00 2,100.00
JUMLAH TENAGA KERJA 3,900.00
B BAHAN
Tanaman calathea lutea Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,900.00

V.I.29. Penanaman 1 buah tanaman ruellia brittoniana


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0100 112,500.00 1,125.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 2,625.00
B BAHAN

Tanaman ruellia brottoniana Buah 1.0000 -

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 2,625.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 2,625.00

V.I.30. Penanaman 1 buah tanaman lantana camara


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0100 112,500.00 1,125.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 2,625.00
B BAHAN
Tanaman lantana camara Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 2,625.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 2,625.00

V.I.31. Penanaman 1 buah tanaman pucuk merah tinggi 1 m


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2400 112,500.00 27,000.00
Mandor L.17 OH 0.0160 150,000.00 2,400.00
JUMLAH TENAGA KERJA 29,400.00
B BAHAN
Pucuk merah tinggi 1 m Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 29,400.00
E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 29,400.00

V.I.32. Penanaman 1 m1 tanaman lee kuan yu


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 3,750.00
B BAHAN
Lee kuan yu m1 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,750.00

V.I.33. Penanaman 1 buah pohon dolar


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.2400 112,500.00 139,500.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 141,000.00
B BAHAN
Pohon dolar Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 141,000.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 141,000.00

V.I.34. Penanaman 1 m2 pohon kaki laba-laba


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 3,750.00
B BAHAN
Pohon kaki laba-laba m2 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,750.00

V.I.35. Penanaman 1 m2 pohon corrymbousa mini


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 3,750.00
B BAHAN
Pohon corrymbousa mini m2 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,750.00

V.I.36. Penanaman 1 m2 pohon pangkas kuning


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 3,750.00
B BAHAN
Pohon pangkas kuning m2 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,750.00

V.I.37. Penanaman 1 m2 tanaman kacang-kacangan


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 3,750.00
B BAHAN
Tanaman kacang-kacangan m2 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,750.00
V.I.38. Penanaman 1 rumpun pohon bambu jakarta
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 3,750.00
B BAHAN
Pohon bambu jakarta Rumpun 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,750.00

V.I.39. Penanaman 1 buah pohon puring kirana


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 3,750.00
B BAHAN
Pohon puring kirana Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,750.00

V.I.40. Penanaman 1 buah pohon puring nuri


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 3,750.00
B BAHAN
Pohon puring nuri Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,750.00

V.I.41. Penanaman 1 buah pohon puring bor merah


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 3,750.00
B BAHAN
Pohon puring bor merah Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,750.00

V.I.42. Penanaman 1 buah pohon puring bor kuning


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 3,750.00
B BAHAN
Pohon puring bor kuning Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,750.00

V.I.43. Penanaman 1 buah pohon soka india


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 3,750.00
B BAHAN
Pohon soka india Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,750.00

V.I.44. Penanaman 1 buah pohon walisongo


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 3,750.00
B BAHAN
Pohon walisongo Buah 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,750.00

V.I.45. Penanaman 1 buah pohon bougenville variegata


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 2,250.00
Mandor L.17 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 3,750.00
B BAHAN

Pohon bougenville variegata Buah 1.0500 -

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,750.00

V.I.46. Penanaman 1 m2 pohon bunga pukul sembilan


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 112,500.00 1,900.00
Mandor L.17 OH 0.0100 150,000.00 1,300.00
JUMLAH TENAGA KERJA 3,200.00
B BAHAN
Pohon bunga pukul
Buah 114.0000 -
sembilan
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,200.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,200.00

V.I.47. Penanaman 1 buah pohon kamboja diameter 10 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Mandor L.17 OH 0.0200 150,000.00 3,000.00
JUMLAH TENAGA KERJA 36,750.00
B BAHAN
Pohon kamboja diameter 10
Buah 1.0000 -
cm
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 36,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 36,750.00

V.I.48. Penanaman 1 buah pohon kamboja diameter 15 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Mandor L.17 OH 0.0200 150,000.00 3,000.00
JUMLAH TENAGA KERJA 36,750.00
B BAHAN
Pohon kamboja dia. 15 cm Buah 1.0000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 36,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 36,750.00

V.I.49. Penanaman 1 buah pohon dadap merah diameter 10 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Mandor L.17 OH 0.0200 150,000.00 3,000.00
JUMLAH TENAGA KERJA 36,750.00
B BAHAN
Pohon dadap merah dia. 10
Buah 1.0000 -
cm
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 36,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 36,750.00

V.I.50. Penanaman 1 buah pohon dadap merah diameter 15 cm


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 112,500.00 33,750.00
Mandor L.17 OH 0.0200 150,000.00 3,000.00
JUMLAH TENAGA KERJA 36,750.00
B BAHAN
Pohon dadap merah dia. 15
Buah 1.0000 -
cm
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 36,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 36,750.00

V.I.51. Penanaman 1 m2 rumput mutiara


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 112,500.00 3,375.00
Mandor L.17 OH 0.0020 150,000.00 300.00
JUMLAH TENAGA KERJA 3,675.00
B BAHAN
Rumput mutiara m2 1.0500 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,675.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,675.00
W HARGA SATUAN PEKERJAAN STYLE BALI
I ANALISA SENDIRI
W.I.1. Pemasangan 1 m2 bata gosok 2 muka
Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 112,500.00 112,500.00
Tukang style Bali L.08 OH 2.0000 157,000.00 314,000.00
Kepala tukang style bali L.15 OH 0.1000 175,000.00 17,500.00
Mandor style bali L.16 OH 0.0100 190,000.00 1,900.00
JUMLAH TENAGA KERJA 445,900.00
B BAHAN
Bata gosok Buah 110.0000 -
Semen portland Kg 8.4000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 445,900.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 445,900.00

W.I.2. Pemasangan 1 m2 batu candi 1 muka


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang style Bali L.08 OH 1.5000 157,000.00 235,500.00
Kepala tukang style bali L.15 OH 0.5000 175,000.00 87,500.00
Mandor style bali L.16 OH 0.0500 190,000.00 9,500.00
JUMLAH TENAGA KERJA 388,750.00
B BAHAN
Batu candi hitam m2 1.2000 -
Semen portland Kg 8.4000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 388,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 388,750.00

W.I.3. Pemasangan 1 m2 bata press 1 muka


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang style Bali L.08 OH 1.5000 157,000.00 235,500.00
Kepala tukang style bali L.15 OH 0.5000 175,000.00 87,500.00
Mandor style bali L.16 OH 0.0500 190,000.00 9,500.00
JUMLAH TENAGA KERJA 388,750.00
B BAHAN
Bata press Buah 65.0000 -
Semen portland Kg 8.4000 -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 388,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 388,750.00

W.I.4. Pemasangan 1 m2 batu paras jogya 1 muka


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang style Bali L.08 OH 1.5000 157,000.00 235,500.00
Kepala tukang style bali L.15 OH 0.5000 175,000.00 87,500.00
Mandor style bali L.16 OH 0.0500 190,000.00 9,500.00
JUMLAH TENAGA KERJA 388,750.00
B BAHAN
Paras jogya putih Buah 16.7500 -
Semen portland Kg 8.4000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 388,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 388,750.00

W.I.5. Pemasangan 1 m2 bata gosok 1 muka


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang style Bali L.08 OH 1.5000 157,000.00 235,500.00
Kepala tukang style bali L.15 OH 0.5000 175,000.00 87,500.00
Mandor style bali L.16 OH 0.0500 190,000.00 9,500.00
JUMLAH TENAGA KERJA 388,750.00
B BAHAN
Bata gosok Buah 65.0000 -
Semen portland Kg 8.4000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 388,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 388,750.00

W.I.6. Pemasangan 1 m2 paras dan bata gosok 1 muka


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang style Bali L.08 OH 1.5000 157,000.00 235,500.00
Kepala tukang style bali L.15 OH 0.5000 175,000.00 87,500.00
Mandor style bali L.16 OH 0.0500 190,000.00 9,500.00
JUMLAH TENAGA KERJA 388,750.00
B BAHAN
Paras jogya putih Buah 16.7500 -
Bata gosok Buah 55.0000 -
Semen portland Kg 8.4000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 388,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 388,750.00

W.I.7. Pemasangan 1 m2 batu jogya diukir 1 muka


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang style Bali L.08 OH 1.5000 157,000.00 235,500.00
Kepala tukang style bali L.15 OH 0.5000 175,000.00 87,500.00
Mandor style bali L.16 OH 0.0500 190,000.00 9,500.00
JUMLAH TENAGA KERJA 388,750.00
B BAHAN
Paras jogya putih Buah 16.7500 -
Semen portland Kg 8.4000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 388,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 388,750.00

W.I.8. Pemasangan 1 m2 batu tulung agung 1 muka


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang style Bali L.08 OH 1.5000 157,000.00 235,500.00
Kepala tukang style bali L.15 OH 0.5000 175,000.00 87,500.00
Mandor style bali L.16 OH 0.0500 190,000.00 9,500.00
JUMLAH TENAGA KERJA 388,750.00
B BAHAN
Paras Tulung Agung 2.5 cm Buah 16.0000 -
Semen portland Kg 8.4000 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 388,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 388,750.00

W.I.9. Pemasangan 1 m2 batu karangasem 1 muka


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.500 112,500.00 56,250.00
Tukang style Bali L.08 OH 1.500 157,000.00 235,500.00
Kepala tukang style bali L.15 OH 0.500 175,000.00 87,500.00
Mandor style bali L.16 OH 0.050 190,000.00 9,500.00
JUMLAH TENAGA KERJA 388,750.00
B BAHAN
Batu karangasem Buah 20.000 -
Semen portland Kg 8.400 -
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 388,750.00


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 388,750.00

W.I.10. Pembuatan 1 unit aling-aling batu tulung agung


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang style Bali L.08 OH 1.5000 157,000.00 235,500.00
Tukang batu L.03 OH 0.8500 127,500.00 108,375.00
Kepala tukang style bali L.15 OH 0.5000 175,000.00 87,500.00
Mandor style bali L.16 OH 0.0500 190,000.00 9,500.00
JUMLAH TENAGA KERJA 497,125.00
B BAHAN
Galian tanah m3 1.2250 88,125.00 107,953.13
Pasir urug m3 0.1225 362,522.73 44,409.03
Batu kosong m3 0.4900 149,077.50 73,047.98
Batu kali m3 1.4963 286,687.50 428,956.17
Beton pengeresek K175 m3 0.5250 237,193.75 124,526.72
Batu tulung agung Buah 207.0000 -
Kolom praktis m1 4.0000 30,235.00 120,940.00
Ring praktis m1 3.5000 49,925.00 174,737.50
Sloof praktis m1 3.5000 49,925.00 174,737.50
Semen portland Kg 8.4000 -
Karang simbar Buah 16.0000 -
Karang tapel Buah 16.0000 -
Murda Buah 2.0000 -
JUMLAH HARGA BAHAN 1,249,308.02
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,746,433.02


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 1,746,433.02

W.I.11. Pemasangan 1 m1 tembok penyengker batu tulung agung


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang style Bali L.08 OH 1.0000 157,000.00 157,000.00
Kepala tukang style bali L.15 OH 0.1000 175,000.00 17,500.00
Mandor style bali L.16 OH 0.0150 190,000.00 2,850.00
JUMLAH TENAGA KERJA 188,600.00
B BAHAN
Beton Pengresek K175 m3 0.1800 237,193.75 42,694.88
Batu Tulung Agung m1 1.0000 -
Semen portland Kg 8.4000 -
JUMLAH HARGA BAHAN 42,694.88
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 231,294.88


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 231,294.88

W.I.12. Pemasangan 1 unit pilar paduraksa batu tulung agung


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang style Bali L.08 OH 1.0000 157,000.00 157,000.00
Kepala tukang style bali L.15 OH 0.1000 175,000.00 17,500.00
Mandor style bali L.16 OH 0.0150 190,000.00 2,850.00
JUMLAH TENAGA KERJA 188,600.00
B BAHAN
Beton Pengresek K175 m3 0.1800 237,193.75 42,694.88
Batu Tulung Agung Buah 1.0000 -
Semen portland Kg 8.4000 -
JUMLAH HARGA BAHAN 42,694.88
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 231,294.88


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 231,294.88

W.I.13. Pemasangan 1 Unit Padmasari Batu Karangasem


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang style Bali L.08 OH 1.5000 157,000.00 235,500.00
Tukang batu L.03 OH 0.8500 127,500.00 108,375.00
Kepala tukang style bali L.15 OH 0.5000 175,000.00 87,500.00
Mandor style bali L.16 OH 0.0500 190,000.00 9,500.00
JUMLAH TENAGA KERJA 497,125.00
B BAHAN
Galian tanah m3 0.8450 88,125.00 74,465.63
Pasir urug m3 0.0845 362,522.73 30,633.17
Batu kosong m3 0.3380 149,077.50 50,388.20
Pasangan batu kali m3 1.2350 286,687.50 354,059.06
Beton pengresek K175 m3 2.5000 237,193.75 592,984.38
Urugan tanah kembali m3 0.2535 63,750.00 16,160.63
Tempelan batu gunung ex
m2 9.9000 388,750.00 3,848,625.00
karangasem
Karang gajah Buah 4.0000 -
Karang simbar Buah 16.0000 -
Karang tapel Buah 4.0000 -
Ulon Buah 1.0000 -
Tabing ulon motif naga Buah 2.0000 -
Karang garuda Buah 1.0000 -
karang wisnu Buah 1.0000 -
Karang angsa Buah 1.0000 -
Pek. pembesian kolom Kg 17.8200 15,230.75 271,411.97
Beton kolom K225 m3 0.1400 237,193.75 33,207.13
Semen portland Kg 22.5000 -
JUMLAH HARGA BAHAN 5,271,935.14
C PERALATAN
Alat bantu % 0.0500 5,271,935.14 263,596.76
JUMLAH HARGA ALAT 263,596.76

D Jumlah (A+B+C) 6,032,656.90


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 6,032,656.90

W.I.14. Pemasangan 1 Unit Penunggu Karang Batu Karangasem


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang style Bali L.08 OH 1.5000 157,000.00 235,500.00
Tukang batu L.03 OH 0.8500 127,500.00 108,375.00
Kepala tukang style bali L.15 OH 0.5000 175,000.00 87,500.00
Mandor style bali L.16 OH 0.0500 190,000.00 9,500.00
JUMLAH TENAGA KERJA 497,125.00
B BAHAN
Galian tanah m3 0.5000 88,125.00 44,062.50
Pasir urug m3 0.0500 362,522.73 18,126.14
Batu kosong m3 0.2000 149,077.50 29,815.50
Pasangan batu kali m3 0.9500 286,687.50 272,353.13
Beton pengresek K175 m3 1.2800 237,193.75 303,608.00
Urugan tanah kembali m3 0.1500 63,750.00 9,562.50
Tempelan batu gunung ex
m2 8.9000 388,750.00 3,459,875.00
karangasem
Karang gajah Buah 4.0000 -
Karang simbar Buah 16.0000 -
Karang tapel Buah 4.0000 -
Ikut celedu Buah 4.0000 -
Pek. pembesian kolom Kg 17.8200 15,230.75 271,411.97
Beton kolom K225 m3 0.1400 237,193.75 33,207.13
Semen portland Kg 22.5000 -
JUMLAH HARGA BAHAN 4,442,021.85
C PERALATAN
Alat bantu % 0.0500 4,442,021.85 222,101.09
JUMLAH HARGA ALAT 222,101.09

D Jumlah (A+B+C) 5,161,247.94


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 5,161,247.94

W.I.15. Pemasangan 1 unit candi bentar t = 4.25 m batu karangasem


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang style Bali L.08 OH 1.5000 157,000.00 235,500.00
Tukang batu L.03 OH 0.8500 127,500.00 108,375.00
Kepala tukang style bali L.15 OH 0.5000 175,000.00 87,500.00
Mandor style bali L.16 OH 0.0500 190,000.00 9,500.00
JUMLAH TENAGA KERJA 497,125.00
B BAHAN
Galian tanah m3 1.5000 88,125.00 132,187.50
Pasir urug m3 0.1500 362,522.73 54,378.41
Batu kosong m3 0.4800 149,077.50 71,557.20
Pasangan batu kali m3 2.8500 286,687.50 817,059.38
Beton pengresek K175 m3 4.0000 237,193.75 948,775.00
Urugan tanah kembali m3 0.4500 63,750.00 28,687.50
Candi bentar Unit 1.0000 -
Pek. pembesian kolom Kg 68.5328 15,230.75 1,043,805.18
Beton kolom K.225 m3 0.5738 237,193.75 136,089.91
Semen portland Kg 42.5000 -
JUMLAH HARGA BAHAN 3,232,540.08
C PERALATAN
Alat bantu % 0.0500 3,232,540.08 161,627.00
JUMLAH HARGA ALAT 161,627.00

D Jumlah (A+B+C) 3,891,292.08


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,891,292.08

W.I.16. Pemasangan 1 unit candi bentar t = 2.50 m batu karangasem


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang style Bali L.08 OH 1.5000 157,000.00 235,500.00
Tukang batu L.03 OH 0.8500 127,500.00 108,375.00
Kepala tukang style bali L.15 OH 0.5000 175,000.00 87,500.00
Mandor style bali L.16 OH 0.0500 190,000.00 9,500.00
JUMLAH TENAGA KERJA 497,125.00
B BAHAN
Galian tanah m3 0.8000 88,125.00 70,500.00
Pasir urug m3 0.0800 362,522.73 29,001.82
Batu kosong m3 0.3200 149,077.50 47,704.80
Pasangan batu kali m3 2.0520 286,687.50 588,282.75
Beton pengresek K175 m3 2.0000 237,193.75 474,387.50
Urugan tanah kembali m3 0.2400 63,750.00 15,300.00
Candi bentar Unit 1.0000 -
Pek. pembesian kolom Kg 16.0875 15,230.75 245,024.69
Beton kolom K.225 m3 0.2250 237,193.75 53,368.59
Semen portland kg 42.5000 -
JUMLAH HARGA BAHAN 1,523,570.15
C PERALATAN
Alat bantu % 0.0500 1,523,570.15 76,178.51
JUMLAH HARGA ALAT 76,178.51

D Jumlah (A+B+C) 2,096,873.66


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 2,096,873.66

W.I.17. Pemasangan 1 m1 tembok penyengker batu karangasem


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang style Bali L.08 OH 1.0000 157,000.00 157,000.00
Kepala tukang style bali L.15 OH 0.1000 175,000.00 17,500.00
Mandor style bali L.16 OH 0.0150 190,000.00 2,850.00
JUMLAH TENAGA KERJA 188,600.00
B BAHAN
Beton pengresek K175 m3 0.3600 237,193.75 85,389.75
Batu karangasem m1 1.0000 -
Semen portland Kg 8.4000 -
JUMLAH HARGA BAHAN 85,389.75
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 273,989.75


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 273,989.75

W.I.18. Pemasangan 1 unit pilar paduraksa batu karangasem


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 112,500.00 11,250.00
Tukang style Bali L.08 OH 1.0000 157,000.00 157,000.00
Kepala tukang style bali L.15 OH 0.1000 175,000.00 17,500.00
Mandor style bali L.16 OH 0.0150 190,000.00 2,850.00
JUMLAH TENAGA KERJA 188,600.00
B BAHAN
Beton pengresek K175 m3 0.1800 237,193.75 42,694.88
Batu karangasem Unit 1.0000 -
Semen portland Kg 8.4000 -
JUMLAH HARGA BAHAN 42,694.88
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 231,294.88


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 231,294.88

W.I.19. Pemasangan 1 unit candi bentar t = 4.25 m batu tulung agung


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang style Bali L.08 OH 1.5000 157,000.00 235,500.00
Tukang batu L.03 OH 0.8500 127,500.00 108,375.00
Kepala tukang style bali L.15 OH 0.5000 175,000.00 87,500.00
Mandor style bali L.16 OH 0.0500 190,000.00 9,500.00
JUMLAH TENAGA KERJA 497,125.00
B BAHAN
Galian tanah m3 1.5000 88,125.00 132,187.50
Pasir urug m3 0.1500 362,522.73 54,378.41
Batu kosong m3 0.4800 149,077.50 71,557.20
Pasangan batu kali m3 2.8500 286,687.50 817,059.38
Beton pengresek K175 m3 4.0000 237,193.75 948,775.00
Urugan tanah kembali m3 0.4500 63,750.00 28,687.50
Tempelan batu tulung
Unit 1.0000 -
agung
Pek. pembesian kolom Kg 68.5328 15,230.75 1,043,805.18
Beton kolom K225 m3 0.5738 237,193.75 136,089.91
Semen portland Kg 42.5000 -
JUMLAH HARGA BAHAN 3,232,540.08
C PERALATAN
Alat bantu % 0.0500 3,232,540.08 161,627.00
JUMLAH HARGA ALAT 161,627.00

D Jumlah (A+B+C) 3,891,292.08


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 3,891,292.08

W.I.20. Pemasangan 1 unit candi bentar t = 2.50 m batu tulung agung


Jumlah
Harga Satuan
No Uraian Kode Satuan Koefisien Harga
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 112,500.00 56,250.00
Tukang style Bali L.08 OH 1.5000 157,000.00 235,500.00
Tukang batu L.03 OH 0.8500 127,500.00 108,375.00
Kepala tukang style bali L.15 OH 0.5000 175,000.00 87,500.00
Mandor style bali L.16 OH 0.0500 190,000.00 9,500.00
JUMLAH TENAGA KERJA 497,125.00
B BAHAN
Galian tanah m3 0.8000 88,125.00 70,500.00
Pasir urug m3 0.0800 362,522.73 29,001.82
Batu kosong m3 0.3200 149,077.50 47,704.80
Pasangan batu kali m3 2.0520 286,687.50 588,282.75
Beton pengresek K175 m3 2.0000 237,193.75 474,387.50
Urugan tanah kembali m3 0.2400 63,750.00 15,300.00
Tempelan batu tulung
Unit 1.0000 -
agung
Pek. pembesian kolom Kg 16.0875 15,230.75 245,024.69
Beton kolom K.225 m3 0.2250 237,193.75 53,368.59
Semen portland Kg 42.5000 -
JUMLAH HARGA BAHAN 1,523,570.15
C PERALATAN
Alat bantu % 0.0500 1,523,570.15 76,178.51
JUMLAH HARGA ALAT 76,178.51

D Jumlah (A+B+C) 2,096,873.66


E Overhead & Profit 0% -
F Harga Satuan Pekerjaan (D+E) Rp 2,096,873.66
NAMA PROYEK
Pembangunan Gedung Laboratorium