Professional Documents
Culture Documents
Method Statement For For Cable Tray and Conduit Installation With Risk Assesment
Method Statement For For Cable Tray and Conduit Installation With Risk Assesment
TABLE OF CONTENT
1.0. PURPOSE
2.0. SCOPE
3.0. TOOLS & EQUIPMENT
4.0. MATERIALS
5.0. PRE-INSTALLATION REQUIREMENTS
6.0. WORK METHODOLOGY
7.0. RISK/HAZARD ANALYSIS
8.0. PERSONAL PROTECTIVE EQUIPMENT 9PPE)
9.0. MANPOWER
1.0 PURPOSE
The purpose of generating this Method Statement is to establish a general guideline, monitor and
control all activities of the Electrical and ELV cable tray and conduit installation works; which shall
include the main cable tray, branch cable tray, conduits, junction and pull boxes; and all associated
supports; through the guidelines contained herein so as to ensure that the job execution complies with
the requirements and serves the intended function to a satisfactory level.
2.0 SCOPE
This Method Statement gives details of how the work will be carried out, the health and safety issues
and controls that are involved and also reflecting findings of the relevant risk assessments.
This method statement only includes the activity of Cable Tray and Conduit installation works as listed
below:
Cable tray and conduit material handling
Fabrication and installation of support for cable tray and/or conduit
Fabrication and assembly of cable tray and/or conduit accessories.
Installation of cable tray and conduit.
Cutting tools
Portable Drill machine
Welding machine
Hacksaw Frame and Blade
Spirit Level
Sand Paper and File
Measuring Tape
Barricade tape
Set of Screwdrivers
Working platforms: scaffolding as required within the specified work area
Portable Ladder
Pipe Wrench
Socket Wrench Set
Combination Spanner Set
Hammer
Full PPE as per risk assessment and site survey plan and procedures: Safety goggles and glasses,
glove, safety harness etc.
4.0 MATERIALS
All materials shall be in line with the approved material submittal and approved shop drawings
On receipt of materials at site, necessary precaution shall be taken for unloading, shifting and storage as
follows:
5.1 All materials received at site shall be inspected and ensured that the materials are as per
approved material submittal.
5.2 Any discrepancies, damage etc., found will be notified and reported for further action
5.3 Material not found suitable for site use will be removed from site immediately
5.4 Material shall be stored in covered/dry designated area and placed off the ground at all times
5.5 Ensure that the work area is tidy and safe to carry out the work
5.6 Prior to start the installation, refer to the approved shop drawings related to the area of
installation and ensure that the required materials are available at site as per approved
material submittals.
5.7 Ensure the materials are stored properly and there is no mark of damage or deformity of any
kind before issuing the materials from site store. All materials and accessories should also be
free of dust, scale or oil.
5.8 Ensure that the issued materials are of approved specifications/submittals and as per
requirement of the area shop drawings. (i.e. Make, size, Model/Type etc.)
5.9 Quantity of support required to be counted from the drawing and fabricated at site work
shop
5.10 Before work commencement, pre-inspection of all materials, tools and access for installation
to be carried out.
6.1 Ensure the Cable Tray Installation is carried out in accordance with manufacturer’s
installation recommendations, requirement of applicable standards and in accordance with
recognized industry practices and as per the project specifications to ensure that installation
complies with requirements
6.2 Installation will be carried out by skilled and suitably experienced electricians under
supervision of highly competent site supervisor and engineer to ensure correctness and
quality of installation.
6.3 Installation will be coordinated to other services to avoid clashes and conflicts
6.4 After cutting and drilling works, all sharp edges shall be smoothed
6.5 Supports for cable trays should provide strength and working load capabilities sufficient to
meet the load requirement of the cable tray wiring system.
6.6 Cable tray and conduit supports will be fastened to building structure.
6.7 Cable trays will be installed directly on designated supports and using other services’
supports will not be allowed
6.8 Cable tray will be installed with enough space to permit access for installing cables.
6.9 There will be no site fabrication for all fittings that will be used. All fittings will be from
approved manufacturer
6.10 Welding support by qualified and certified welders and make sure all supports are welded as
per specifications, after finish then remove the debris from welding points
6.11 The supports will be touched up, painted wherever it has been cut, drilled & filed.
Upon Completion of alignment of support installation, the cable tray will be placed on the
supports and fastened on the supports by means of tray holding clamps as per the
manufacturer recommendation.
The tray segments will be joined to each of its length by manufactures supplied splice plates
using bolts, nuts & Washers. Splice plates shall not be located over supports
All the cut locations of the cable tray will be filed properly for smooth edges and shall be
painted with approved galvanization. Where necessary to cut the cable trays, the cutting line of
the cable trays shall be through continuous metal parts and not through the perforation.
There are no sharp edges throughout the run, which could cause damage to the cable and
clamping bolts present smooth heads inside the trays and not the nut end of the bolt.
The electrical continuity of cable trays will be maintained by using earth bonding jumper at
joints and between the cable trays & the fittings used at change of direction to connect each
other. Metal cable trays must be grounded and electrically continuous system.
Cable tray installation will be completed and will be inspected by QC inspector as per project
procedures before the commencement of cable installation.
Cable trays’ covers shall be provided after the cabling activities are completed, wherever it is
installed outdoors.
The main cable tray routing should be installed in accordance with the newest IFC layout
drawing.
The following PPE among others which have been identified to be appropriate for the installation shall
be provided to our personnel before work commencement:
Hard hat with chin strap
Steel-toed safety boots
Heavy-duty work gloves and rubber (latex) gloves
Ear plug
Safety Vest etc.
Safety goggle
Safety harness with 2 fall arrest lanyards
9.0 MANPOWER