Professional Documents
Culture Documents
BG-DWG-2017-0171-R0 AL TATWIR CONTRACTING 10-18-2017-Layout1
BG-DWG-2017-0171-R0 AL TATWIR CONTRACTING 10-18-2017-Layout1
BG-DWG-2017-0171-R0 AL TATWIR CONTRACTING 10-18-2017-Layout1
ACCESS ONLY MAX This drawing is confidential and is the property of Brogan Group. The drawing is supplied subject to the Company's standard
Conditions as applicable. No unauthorised use, copy or disclosure is to be made without written permission.
TRANSOM SPACING
BS 1139* Metal scaffolding
BS EN 12811-1:2003 Temporary works equipment: Scaffolds - Performance requirements and general design
WORKING PLATFORMS: 5 NOS. BS EN 13374:2004 Temporary Edge Protection Systems - Product Specification, test methods
BS 5975: 2008 Code of practice for temporary works procedures and the permissible stress design of falsework.
TG20:08
Table 9 Erection tolerances
Feature
Bay length and width ± 200mm on designated lengths Levl to within ± 20mm in 2m
(subject to max. deviation of 50mm) (1)
W1
Self Weight of Formwork ............0.50 kN/m²
1.30m 1.30m 1.80m
Live load......................................1.50 kN/m²
* For Shores: Maximum Allowable leg load = 30kN/ Leg
Foundations / Supports
The Client must ensure that the foundations provided are adequate and that they are capable of taking the imposed scaffold loads.
Where Brogan Group equipment is supported, anchored, suspended or tied to an existing structure or the ground, the Client must
1.30m 1.30m 1.80m ensure that the structure is adequate to safely support the additional imposed loads.
Maximum Calculated Leg Load . . . . . . . . . . . . . . . . . . . . . . . . . . . . kN
Maximum Lift Height . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . m
Tying
Ties on Plan, Elevation and Section are denoted thus . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
The Client is to ensure that no ties or braces are removed without the approval of Brogan Group.
C7
25
Assumptions
00
1.30m 1.30m 1.80m
.The
. . . following
. . . . . . . .assumptions
. . . . . . . . . . affecting
. . . . . . . .the
. . use
. . . of
. . equipment
. . . . . . . . . shown
. . . . . . on
. . .this
. . .drawing
. . . . . . .have
. . . .been
. . . . made.
............................ ...
Permanent Structure
Brogan Group cannot and will not pass comment on the building structure being scaffolded as this involves matters beyond our knowledge.
It is the clients responsibility to ensure that the existing structure can safely withstand all additional imposed loads from scaffold structure
1.30m 1.30m 1.80m
Sheeting/Fans
No wind protection, sheeting or fans etc. to are to be added to the scaffolding structure unless otherwise stated on this drawing or
agreed with Brogan Group.
Modifications
1.30m 1.30m 1.80m
No alterations to components, assembly, loading or any other aspect are to be made to the scaffold structure detailed on this
drawing except by Brogan Group employees authorised to do so.
Dimensions
Written dimensions shall take precedence over scaled dimensions.
The contractor should verify all site dimensions and notify Brogan Group of any discrepancies.
The contractor is responsible for accurate setting out dimensions of the position of the scaffold structure.
Drawing Status
Working Drawing - for construction purposes.
Preliminary Drawing - should not be used for construction
25
25
00
Permits
00
1.30m 1.30m 1.80m
The Client is responsible for obtaining all permits and permissions necessary prior to construction.
All ancillary work to scaffolds e.g. hoarding, lighting, baulk timber, plykentledge etc to be supplied by the Client.
Inspection: The scaffold must be inspected by the Client at 7No. day intervals (Statuatory Inspection) .
D3
CDM Regulations and Obligations
1.30m 1.30m 1.80m Brogan Group drawing constitutes Design Risk assessment in accordance with Regulation 11 of CDM Regulations 2007.
Refer to relevant Guides Codes and HSE publications for guidance of elimination of general risk in use of temporary works
and good practice. Wherever possible risk is designed out of this proposal
Erection
Scaffold erected in accordance with SG4:15
1.30m 1.30m 1.80m
D1
6.4 TEST PROCEDURES
Hilti M16 HKD
Table of proof test sample M16 Ringbolt
anchor
tie
Total ties number of
on the job proof test
Butt
D3
0 - 60 3
D1
tube
101 - 120
121 - 140
5
7
Tie tube
141 - 160 8 through ring
161 - 180 9
PERMANENT STRUCTURE
D2
50mm Min. 50mm Min.
1200mm 1200mm 1200mm
150mm Max. 150mm Max.
1.00m
1.00m
1.00m
1200 1200 1200
HKD-M16
Maximum
1.00m
2.40
UNIT BEAM
CR2 1.00m
HKD-M16
LACING & BRACING DETAIL
1.00m
1.00m 1.30m
1.00m 1.30m
WFD1
1.00m 1.30m
HKD-M16
WORKING
C1 1.30m
DRAWING
D3
1.30m
CW-5* D1
1.30m
SCAFFOLDING PLAN
REV. AMENDMENTS BY DATE
www.brogangroup.com
Title:
ACCESS SCAFFOLDING
USING CUPLOCK SYSTEM
SCAFFOLDING PLAN LAYOUT & CANTILEVER SECTION AREA
Customer: