BG-DWG-2017-0171-R0 AL TATWIR CONTRACTING 10-18-2017-Layout1

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

GENERAL NOTES

ACCESS ONLY MAX This drawing is confidential and is the property of Brogan Group. The drawing is supplied subject to the Company's standard
Conditions as applicable. No unauthorised use, copy or disclosure is to be made without written permission.

LIVE LOAD = 0.75kN/m2


Design Basis
This drawing has been prepared from information supplied to us by, or on behalf of the Client, who should check that their
requirements have been correctly interpreted and that all loadings, dimensions, details, erection, and striking sequences etc. are as
required and practicable.
The following documents obtained on loan have been used to prepare this scheme
..........................................................................................................
This drawing has been prepared in accordance with the following:

TRANSOM SPACING
BS 1139* Metal scaffolding

BS 2482 Timber scaffold boards

BS 5950-1:1990* Structural Steelwork

1.20M C/C BS EN 1999-1-1-4:2005 + A1:2010

BS EN 12810-1:2003 Façade scaffolds made of prefabricated components - products specifications

BS EN 12811-1:2003 Temporary works equipment: Scaffolds - Performance requirements and general design

WORKING PLATFORMS: 5 NOS. BS EN 13374:2004 Temporary Edge Protection Systems - Product Specification, test methods

TG4:11 Anchoring systems for scaffolding

BS 5975: 2008 Code of practice for temporary works procedures and the permissible stress design of falsework.

TG20:08 NASC Technical Guidance on the use of BS EN 12811-1

TG20:08
Table 9 Erection tolerances

Feature

Standards Vertical to within ± 20mm in 2m (subject to max. deviation of 50mm)

Bay length and width ± 200mm on designated lengths Levl to within ± 20mm in 2m
(subject to max. deviation of 50mm) (1)

Lift height ± 100mm on designated height

Nodes <Generally 150mm between coupler centres,

Bracing <300mm from the node


(1) Foot ties may follow the general slope of the ground on which the scaffold is founded.
Note

1.30m 1.30m 1.80m


Design Loads
The structure detailed on this drawing has been designed to support the following imposed Loads only
* For Soffits:
Self Weight of Concrete ............ 25.0 kN/m³

W1
Self Weight of Formwork ............0.50 kN/m²
1.30m 1.30m 1.80m
Live load......................................1.50 kN/m²
* For Shores: Maximum Allowable leg load = 30kN/ Leg
Foundations / Supports
The Client must ensure that the foundations provided are adequate and that they are capable of taking the imposed scaffold loads.
Where Brogan Group equipment is supported, anchored, suspended or tied to an existing structure or the ground, the Client must
1.30m 1.30m 1.80m ensure that the structure is adequate to safely support the additional imposed loads.
Maximum Calculated Leg Load . . . . . . . . . . . . . . . . . . . . . . . . . . . . kN
Maximum Lift Height . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . m
Tying
Ties on Plan, Elevation and Section are denoted thus . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
The Client is to ensure that no ties or braces are removed without the approval of Brogan Group.

CP4 All ties to be fixed with load-bearing couplers.


Where proprietary anchors are specified they should be fixed and tested in accordance with the manufacturers recommendations.
Making good of tie locations by client
Maximum anchor load = . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.10 kN
00
25

C7

25
Assumptions

00
1.30m 1.30m 1.80m

.The
. . . following
. . . . . . . .assumptions
. . . . . . . . . . affecting
. . . . . . . .the
. . use
. . . of
. . equipment
. . . . . . . . . shown
. . . . . . on
. . .this
. . .drawing
. . . . . . .have
. . . .been
. . . . made.
............................ ...
Permanent Structure
Brogan Group cannot and will not pass comment on the building structure being scaffolded as this involves matters beyond our knowledge.
It is the clients responsibility to ensure that the existing structure can safely withstand all additional imposed loads from scaffold structure
1.30m 1.30m 1.80m
Sheeting/Fans
No wind protection, sheeting or fans etc. to are to be added to the scaffolding structure unless otherwise stated on this drawing or
agreed with Brogan Group.
Modifications
1.30m 1.30m 1.80m
No alterations to components, assembly, loading or any other aspect are to be made to the scaffold structure detailed on this
drawing except by Brogan Group employees authorised to do so.
Dimensions
Written dimensions shall take precedence over scaled dimensions.
The contractor should verify all site dimensions and notify Brogan Group of any discrepancies.
The contractor is responsible for accurate setting out dimensions of the position of the scaffold structure.

Drawing Status
Working Drawing - for construction purposes.
Preliminary Drawing - should not be used for construction
25

25
00
Permits

00
1.30m 1.30m 1.80m
The Client is responsible for obtaining all permits and permissions necessary prior to construction.
All ancillary work to scaffolds e.g. hoarding, lighting, baulk timber, plykentledge etc to be supplied by the Client.
Inspection: The scaffold must be inspected by the Client at 7No. day intervals (Statuatory Inspection) .

D3
CDM Regulations and Obligations
1.30m 1.30m 1.80m Brogan Group drawing constitutes Design Risk assessment in accordance with Regulation 11 of CDM Regulations 2007.
Refer to relevant Guides Codes and HSE publications for guidance of elimination of general risk in use of temporary works
and good practice. Wherever possible risk is designed out of this proposal
Erection
Scaffold erected in accordance with SG4:15
1.30m 1.30m 1.80m

Temporary Handrails have been omitted for clarity


Drawing to be read in conjunction with Method statement and Risk Assessment
TG4:11

D1
6.4 TEST PROCEDURES
Hilti M16 HKD
Table of proof test sample M16 Ringbolt
anchor
tie
Total ties number of
on the job proof test
Butt
D3
0 - 60 3

D1
tube

ELEVATION PLAN @ CANTILEVER AREA 61 - 100

101 - 120

121 - 140
5

7
Tie tube
141 - 160 8 through ring
161 - 180 9

181 - 200 10 TIE DETAIL


C13 200 - 220 11 PROOF TEST TO 7.60kN
221 - 240 12 PRELIMINARY TEST LOAD TO 12.20kN

PERMANENT STRUCTURE
D2
50mm Min. 50mm Min.
1200mm 1200mm 1200mm
150mm Max. 150mm Max.

1.00m

1.00m

1.00m
1200 1200 1200
HKD-M16

Maximum

1.00m

2.40
UNIT BEAM
CR2 1.00m

HKD-M16
LACING & BRACING DETAIL

1.00m

STANDARD 3.9m BOARD


TRANSOM SUPPORT DETAIL
+ 100mm Tollerance in accordance with TG20 Table 8

1.00m 1.30m

1.00m 1.30m

WFD1
1.00m 1.30m

HKD-M16

WORKING
C1 1.30m

DRAWING
D3
1.30m

CW-5* D1
1.30m

SCAFFOLDING PLAN
REV. AMENDMENTS BY DATE

SECTION C @ CANTILEVER AREA BRO G A N


GROUP
1303 GROSVENOR TOWER BUSINESS TOWER
TECOM DUBAI
UNITED ARAB EMIRATES

www.brogangroup.com

Title:

ACCESS SCAFFOLDING
USING CUPLOCK SYSTEM
SCAFFOLDING PLAN LAYOUT & CANTILEVER SECTION AREA

Customer:

Design Based Hazards actively eliminated where possible in


AL TATWEER CONTRACTING LLC
the Design Process. Where Hazards cannot be eliminated, this
symbol on the drawing with an attached note means: Depot: Scale:

1. Design Based Hazards Exists within this proposal NTS


2. Action is required by the person supervising the
work to manage the design Hazards during construction Prepd By: Date: Drg. No:
In accordance with Brogan Group Procedures the PERSON SUPERVISING DS 30-OCT-2017
the construction MUST CONTACT the Design Office, BEFORE
WORK COMMENCES, for CLARIFICATION of the Identified Hazards Approved By: Pages: BG-DWG-2017-0171-R1
--- 01 OF 02

You might also like