Hamdard Laboratories (India)

Project Number: NDD22977.02 MINUTES OF MEETING

Project Title Extraction Plant / Spray Dryer MOM No. NDD22977.02-MOM-GEN-019

Meeting Location Interarch Office at NOIDA Meeting Date 06th September 2022

Subject Thick Paste / Extraction Block Meeting Time 09:00 to 18:00

List of Attendees
S.No Initials Attendee Name Company Name
1 SA Mr. Shamshad Ali Sb. Hamdard Laboratories (India)
2 AK Asghar Khan Hamdard Laboratories (India)
3 MT Mohd. Tauseef Hamdard Laboratories (India)
4 MA Mohd. Arif Hamdard Laboratories (India)
5 AC A K Chopra Shefa Engineers
6 PY Prashant Yadav Drying Systems
7 SK Souma Kanti SSP
8 RS Rajpal Singh Process Consultant
9 NP Narendra Prasad IPS International
10 SJ Sachin Jaggi IPS International
11 PG Pratik Ghate IPS International

ACTION
ITEM DESCRIPTION STATUS DUE
BY

Thick Paste / Extraction Block

A Site meeting was held with the all the participants as


mentioned in the above Participants List. The concerns
and discussions are briefed here below :
• A site visit was made and the site conditioned were
reviewed. It was observed that the PEB installation
work is moving reasonably fast and an immediate
requirement for deputation of team for installation of
Need to
IPSI / HLI
Process Equipment. It is discussed and agreed to To be taken
Expedite / SSP /
evaluate the possibilities for deputation of up with
immediately Drying
1. Supervisory Teams and start of Equipment immediate
Systems /
Installation from coming Tuesday (13th Sept. 2022) action
Dr. Rajpal
onwards.
• All the team members discussed and agreed that
the Layout, Design, Equipment Placement,
Orientation is okay and executable at site. However,
there is no sufficient space for expansion.
• The requirement of Openings in the Slab to be left
for lifting and placement of Process Equipment was
discussed, Agreed, and marked on the Drawings.

Format No.: IPSI-SOP-PRM-001-F02.1 IPS International


Page 1 of 3
Hamdard Laboratories (India)
Project Number: NDD22977.02 MINUTES OF MEETING

ACTION
ITEM DESCRIPTION STATUS DUE
BY

• There is a difference in Floor Heights, of building as


compared to the Elevation Drawing available with
SSP. SSP needs to check the same with their
design team and check for the possible solutions for
placement of equipment. Also, SSP is requested to
check with their design / fabrication team if the
difference in height has already been captured
earlier and incorporated in the drawing or not (as
per the earlier drawings submitted by IPS).
Accordingly, a feasible solution would be worked
out together.
• All the Process Equipment Suppliers were
requested for the followings :
✓ To submit detailed P&IDs.
✓ To submit the requirement of various Utilities –
i.e., the Quality, Specifications, and the Volumes.
✓ Confirm the availability of Site Engineer for IPSI / HLI
Supervision of equipment installation activities To be taken / SSP /
Need to
and their reporting date at site. Drying
up with Expedite
immediate immediately
Systems /
• Shefa Engineers was shown all the designs and the Dr. Rajpal
requirements and was requested to plan for action
Process Equipment and Utility Piping installation.
(Process Piping is in the scope of respective
equipment suppliers).
• Following details were discussed with Drying
Systems :
✓ They were requested to propose supply of
Product Down-Chute for transfer of powder
material from First Floor to Ground Floor for
Powder Processing and Packing (@E107). The
same can be in 3 pieces of 1.5 m. each and to be
interconnected by means of Gasket and Tri-
clover Flange Joint with Clamp.
✓ As the System will be handling and transfer
Powder, please check and provide proper Static
Current Dissipation System.
✓ As there are possibilities for escape of some
powder with the exhaust system, it is requested
for providing a Scrubber System (as additional
item), to be placed at Terrace Level and connect
the same with the exhaust pipe.
✓ It was discussed that the Heated Air
Temperature needs to reach around 180 deg.C.

Format No.: IPSI-SOP-PRM-001-F02.1 IPS International


Page 2 of 3
Hamdard Laboratories (India)
Project Number: NDD22977.02 MINUTES OF MEETING

ACTION
ITEM DESCRIPTION STATUS DUE
BY

As the available Steam is only at 6 kg.Bar.


pressure, the expected temperature would be
only 120 deg.C. Hence, Drying System was
requested to provide suitable Electric Air Heating IPSI / HLI
System to take the Air temperature to 180 deg.C. To be taken Need to / SSP /
up with Expedite Drying
• It was discussed to provide a new CIP System for immediate immediately Systems /
the cleaning of Tanks and Spray Dryer. Shefa will action Dr. Rajpal
work on the same and shall offer a suitable
proposal.
• IPSI to provide the drawing for laying Torr Steel and
Concrete over the Deck-Sheet.

Safi / Cinkara / N G Syrup Block

• It was discussed to not to use the existing CIP


System, as the same has been already installed for To be IPS / HLI /
2. Expedited
Immediate
a different use. Hence the CIP System to be Shefa
procured to be new system
NOTE: If anyone notes any errors, omissions, or needed clarifications to these Minutes, please notify this within two working days,
otherwise these Minutes shall stand as written.

For Integrated Project Services International Pvt. Ltd.

Prepared By : Narendra Prasad


Signed :
Date : 06th September 2022.