CHARGING SYSTEM – Precautions, On–Vehicle Inspection
PRECAUTIONS
1. Check that the battery cables are connected to the cor–
rect terminals.
2. Disconnect the battery cables when the battery is given
a quick charge.
3. Do not perform tests with a high voltage insulation
resistance tester.
4. Never disconnect the battery while the engine is running.
ON–VEHICLE INSPECTION
1. INSPECT BATTERY SPECIFIC GRAVITY AND
ELECTROLYTE LEVEL
(a) Check the specific gravity of each cell.
Standard specific gravity
When fully charged at 20C (68F):
22R–E 1.25 – 1.27
3VZ–E 55D 23R 1.25 – 1.27
80D 26R 1.27 – 1.29
If not within specifications, charge the battery.
(b) Check the electrolyte quantity of each cell.
If insufficient, refill with distilled (or purified) water.
2. CHECK BATTERY TERMINALS AND FUSIBLE LINKS
(a) Check that the battery terminals are not loose or cor–
roded.
(b) Check the fusible links for continuity.
PRECAUTIONS
1. Check that the battery cables are connected to the cor–
rect terminals.
2. Disconnect the battery cables when the battery is given
a quick charge.
3. Do not perform tests with a high voltage insulation
resistance tester.
4. Never disconnect the battery while the engine is running.
ON–VEHICLE INSPECTION
1. INSPECT BATTERY SPECIFIC GRAVITY AND
ELECTROLYTE LEVEL
(a) Check the specific gravity of each cell.
Standard specific gravity
When fully charged at 20C (68F):
22R–E 1.25 – 1.27
3VZ–E 55D 23R 1.25 – 1.27
80D 26R 1.27 – 1.29
If not within specifications, charge the battery.
(b) Check the electrolyte quantity of each cell.
If insufficient, refill with distilled (or purified) water.
2. CHECK BATTERY TERMINALS AND FUSIBLE LINKS
(a) Check that the battery terminals are not loose or cor–
roded.
(b) Check the fusible links for continuity.
GENERATOR
COMPONENTS
CH–6
CHARGING SYSTEM – Generator
4. (w/ PS)
REMOVE WATER INLET HOSE
(a) Remove the engine under cover.
(b) Remove the water inlet hose.
(c) (with A/C)
Remove the No. 2 fan shroud.
6. REMOVE GENERATOR
(a) Hold the generator and remove the pivot.
(b) Remove the generator.
CH–7
CHARGING SYSTEM – Generator
DISASSEMBLY OF GENERATOR
(See page CH–5)
1. REMOVE REAR END COVER
(a) Remove the nut and terminal insulator.
(b) Remove the three nuts and end cover.
3. REMOVE IC REGULATOR
Remove the three screws and IC regulator.
5. REMOVE PULLEY
(a) Hold SST A with a torque wrench, and tighten SST
B clockwise to the specified torque.
SST 09820–63010
Torque: 39 N – m(400 kgf – cm, 29 ft – Ibf )
(b) Check that SST A is secured to the rotor shaft.
CH–9
CHARGING SYSTEM – Generator
Stator
1. INSPECT STATOR FOR OPEN CIRCUIT
Using an ohmmeter, check that there is continuity between
the coil leads.
If there is no continuity, replace the drive end frame as–
sembly.
Brushes
1. INSPECT EXPOSED BRUSH LENGTH
Using a scale, measure the exposed brush length.
Standard exposed length: 10.5 mm (0.413 in.)
Minimum exposed length: 1.5 mm l0.059 in.)
If the exposed length is less than minimum, replace the
brushes.
(c) Solder the brush wire to the brush holder at the ex–
posed length.
Exposed length: 10.5 mm (0.413 in.)
(d) Check that the brush moves smoothly in the brush
holder.
(e) Cut off the excess wire.
(f) Apply insulation paint to the soldered point.
Rectifier
1. INSPECT POSITIVE SIDE RECTIFIER
(a) Using an ohmmeter, connect one tester probe to the
positive stud and the other to each rectifier terminal.
Bearings
1. INSPECT FRONT BEARING
Check that the bearing is not rough or worn.
(b) Using a press and socket wrench, press out the front
bearing.
CH–13
CHARGING SYSTEM – Generator
(c) Using SST and a press, press the front bearing into
the drive end frame.
SST 09608–20012 (09608–00030)
(d) Install the bearing retainer with the four screws.
ASSEMBLY OF GENERATOR
(See page CH–5)
1. INSTALL ROTOR TO DRIVE END FRAME
2. INSTALL REAR END FRAME
(a) Using a plastic–faced hammer, lightly tap in the rear
end frame.
(b) Install the four nuts.
3. INSTALL PULLEY
(a) Install the pulley to the rotor shaft by tightening the
pulley nut by hand.
(b) Hold SST A with a torque wrench, and tighten SST
B clockwise to the specified torque.
SST 09820–63010
Torque: 39 N–m (400 kgf –cm, 29 ft–Ibf)
(c) Check that SST A is secured to the pulley shaft.