Professional Documents
Culture Documents
Construction Schedule Contracts Management
Construction Schedule Contracts Management
Management
Schedule Strategy
• Many Clients have ‘Schedule’ as the Paramount
value for them. Being ahead of Schedule delights
them
• Time is money ; Schedule drive pays back
• If you want to be focussed on Safety, Quality and
Productivity, you should not be all the time under
Client Pressure for Schedule. Take charge and lead
the client
• LD Penalties will sweep your Margin
First step in Schedule Management
• Just after front realease Client jump on us to start the work, the
very next moment and declare “Front Available; Work not
done”
• Let us establish minimum time required to start the work after
inputs are cleared from Client. To explain, for a foundation job
the following steps are involved after drawing release by Client
• Drawing study / Quantity survey / Material management / Job
Planning / material Procurement / Labour mobilisation /
Redirection.
• The above takes minimum 3 to 4 weeks time
• hence, calculate work fronts for the month applying minimum
time to start
Work front concepts……...
• “Work Front Available” is the quantum of work can be turned
over immediately with inputs - Drawings, materials, Structural
Foundation, Clearance etc. available on the date in complete
order / sequence with respect to time
• Work front that can be turned over during the most considering
minimum period for work start
Example
– minimum time for work start is 20 days
– work front on 05/09/98 is 300T
– work front on 10/09/98 is 400T
– work front on 15/09/98 is 500T
– work front for the month is 400T
Front Release recording
• Front release position becomes the deciding point
Contractual Schedule matters
• Finalise front for the month with Cut off date, say ‘A’.
Check ‘A’ within capacity
• Check last month look ahead work plan for the month,
say ‘B’.
• Check resources were mobilised for the look ahead
plan ‘B’
• If front availability ‘A’ is more than look ahead plan for
the month ‘B’, freeze month plan ‘B’; stretch 20% to
30% ‘B’ plan is meeting Client requirements.
If ‘A’ is less than ‘B’, freeze month plan as ‘A’ and
make a claim on Clients for under utilisation of
resources mobilised for ‘B’ plan
• Direct execution of final plan
Second month front study/Scheduling
• Finalise 1st month plan ‘A’
• Assess front availability and arrive work plan for 2nd month, say ‘B’.
Check the last month look ahead plan for 2nd month and resources
are budgeted
• Check ‘B’ plan with ‘A’ plan
a) B>A
Checkup 3rd month work plan C
B>C
Finalise 2nd month plan by balancing the work plan for sustained
resource deployment in 2 and 3rd month
Balance plan will be one B+C
2 Contd..
B<C
Finalise 2nd month plan as ‘B’
Second month front study/Scheduling
• b) B<A
Finalise 2nd month plan as ‘B’
• If final plan for the 2nd month is more than the the present
resources can make, commit additional resources for the final
second month plan
• If final plan of 2nd Month is less than the plan the present
resources can make, inform claim that resources are underutilised
and ask for additional front release.
• Team should focus on achieving progress and milestones together. All reviews
should follow this sacrosantly.
Example;
R8 - Rack completion (Milestone) 28.02.99
R8 - Rack Piping (Quantum) Jan 4000 ID, Feb 500 ID
S - Curve
• Represent Construction Quantum Schedule, Capacity,
Front release, Progress achieved in ‘S’ curve
45000
40000
35000
30000
25000
20000
15000
10000
5000
Inch dia
0
Nov- Dec- Jan- Feb- Mar- Apr- May- Jun- Jul- Aug- Sep- Oct- Nov- Dec-
97 97 98 98 98 98 98 98 98 98 98 98 98 98
Month
Origiunal fab. Prog. Actual Fab. Prgs. Avl. Net front (fab.)
Original Eren Prog. Actual Eren. Prgs. Avl. Net front (eren.)
• Like you have ‘S’ curve for quantum schedule, have a
golden frame for Milestone schedule
Delay Accountable
Sl. Original Revised Delay Dates
Milestones Client ECC
No. Date Date
Area Project Area Project Area Project
1
2
3
4
5
6
Sl
Major Inputs Quantum Cost Claim Ststus
No.
01. SFL Safety 9.7 Bill Passed, further Provision
Directly by Clients
02. Fab. Yard 54 Claim Sumbitted
Development
Accountability
Sl Major Reasons for O/R Days
ECC Client
01 Paint spec change 120 4
02 Sheeting spec. change / Design 30 4
changes / re design
03 Compaction Clearance 30 4
Thank U