Professional Documents
Culture Documents
Operations Assignment 7
Operations Assignment 7
1. The activities and time estimate for a particular project are as follows:
A - 7 8 15 9.00
B A 10 11 12 11.00
C A,B 5 7 9 7.00
D B, C 11 14 17 14.00
E D 5 7 9 7.00
F E 5 7 11 7.00
What is the critical path and expected project completion time? Critical Path = A-B-C-D-E-F
A 9.00 0 0 9 9 0 Yes
B 11.00 9 9 20 20 0 Yes
C 7.00 20 20 27 27 0 Yes
D 14.00 27 27 41 41 0 Yes
E 7.00 41 41 48 48 0 Yes
F 7.33 48 48 55 55 0 Yes
Normal
Activity time Crash time Cost/day
A 9.00 6 12,000
B 11.00 8 4,000
C 7.00 4 7,000
D 14.00 11 2,000
E 7.00 5 7,000
F 7.00 4
A 12,000 3 days
B 4,000 3 days
C 7,000 3 days
D 2,000 3 days
E 7,000 2 days
F 3,000 3 days
A-B-D-E-F 48 47 46 45 44 43
A-B-C-D-E-F 55 54 53 52 51 50
A-C-D-E-F 44 43 42 41 40 39
Activity Crashed D D D F F
Solutions:
A ( 7 + 4(8) + 15 ) / 6 = 9.00
B ( 10 + 4(11) + 12 ) / 6 = 11.00
C ( 5 + (4)7 + 9 ) / 6 = 7.00
D ( 11 + 4(14) + 17 ) / 6 = 14.00
E ( 5 + 4(7) + 9 ) / 6 = 7.00
F (5
Earliest Time 0
Forward
Earliest Finish 9+0=9
Slack 0 – 0 = 0 or 9 – 9 = 0
Critical Path Yes, since the slack is 0, Activity A is critical, and its
delay would delay the whole project.
ACTIVITY B
Latest Start 20 – 11 = 9
Backward
Latest Finish 20 (from the latest start of Activity C since it is lower)
Slack 9 – 9 = 0 or 20 – 20 = 0
ACTIVITY C
Latest Start 27 -7 = 20
Backward
Latest Finish 27 (from the latest start of Activity D)
Slack 20 – 20 = 0 or 27 – 27 = 0
Critical Path Yes, since the slack is 0, Activity C is critical, and its
delay would delay the whole project as well.
ACTIVITY D
Latest Start 41 – 14 = 27
Backward
Latest Finish 41 (from the latest start of Activity E)
Slack 27 – 27 = 0 or 41 – 41 = 0
Critical Path Yes, since the slack is 0, Activity D is critical, and its
delay would delay the whole project as well.
ACTIVITY E
Slack 41 – 41 = 0 or 48 – 48 = 0
ACTIVITY F(end)
Latest Start 55 – 7 = 48
Backward
Latest Finish 55 (Since it is the last Activity)
Slack 48 – 48 = 0 or 55 – 55 = 0
Critical Path
A 9.00 6 3 Days
B 11.00 8 3 Days
C 7.00 4 3 Days
D 14.00 11 3 Days
E 7.00 5 2 Days
F 7.00 4 3 Days
Proof: