Name of Work Piling works for GDA flyover

Client GDA
Name of Agency M/s ITD Cementation India Limited

Title Pile Pour Card


Type of pile Bored Cast in Situ pile

A Details of pile
S.No. S.No.
1 Type of pile Bored cast in situ pile 8 Theoritical concrete qty.
2 Diameter of pile 9 Actual concrete quantity
3 Bore depth from EGL 10 Existing Ground Level
4 Bore depth from COL 11 Cut off level
5 Location 12 Casing Top level
6 Pile Ref. No. 13 Empty Bore
N: 14 Ref. Drawing No.
7 Coordinates
E: 15 Date of casting

B Boring Details
Time
S.No. Activity Date Remark
from to

1 Casing fixing

2 Boring

3 Cage Lowering

4 Tremmie Lowering

5 Concreting

C Reinforcement Details:-
Quantity in KG as per
S.No. Dia of Bar Extra quantity as per site ( Resting hook)
BBS
1 8mm
2 10mm
3 12mm
4 16mm
5 20mm
6 25mm
Total in KG

Signature : Signature :

Name : Name :

ITD Cementation India Limited GDA


Details of claim for Bored casting situ and precast driven pile

1. precast driven pile:

 Test Pile ( 5 different location)


1) B-34A - 3 nos.
2) B-45 - 5 nos.
3) Kasa Issle - 5 nos.
4) Boulevard - 3 nos.
5) Crescent - 3 nos.
Total - 19 nos.

 Routine Pile ( 5204 nos. completed) as on 19th Oct'11

1) B-34A - completed
2) B-45 - completed --- ( worked for only single shift from the beginning of the work)
3) Kasa - tower-01 complete
tower-02 - 52 piles are balance
tower-03 - 63 piles are balance
tower-04,05,06 ( approx. 885 piles are available)
( 3 RIGS ARE WORKING AND WILL GET FREE FROM 30TH NOV'11)

4) Boulevard - tower-01 complete


tower-02 - 2 piles are balance ( area is not clear)
tower-03 - 209 piles are balance ( work stopped by villager’s)
tower-04,05, 06,07 ( approx. 1269 piles are available) , urgent requirement of front.
( 3 RIGS ARE WORKING AND WILL GET FREE FROM 30TH NOV'11)

1. Bored cast in situ pile:

 Test Pile ( 3 different location)

1) Crescent Homes – 04 nos.


2) B-45 Towers ---02 nos.
3) Kube Towers --- 03 nos.
Total ====== 09 nos.

Claim: -
1) Our claim is for B-45 towers for one complete shift, which was idle due to the villager’s problem from the start to
2) Power supply at Old casting yard , where the supply of power is restricted upto 10 pm Only
3) driving depth which is certified as per the termination of 15 mtr. pile , Ave. driving depth paid @ 13.5 mtr./pile

Area of concern:-
1) Requirement of additional casting bed
2) we have deployed 6 driving rigs 3 at boulevard and 3 at kasa isles which will get free by the first week of Dec'11
Requirement of front for driving in advance for the deployment of above rig. from 20th of Nov'11 , Because
rigs will get free one by one.
3) Continously work is getting stopped by villegers at Boulevard which is affecting the driving progress.

Progress of work from 1st Oct'11 to 18th Oct'11


Casting = 502 nos.
Ave/day= 35/day

Driven = 640 nos.


Ave/day= 46/day

Shutters available = 62+28 = 90 complete sets