04how To Reduce Rod Pump Failures by 40 in 2 Years The X Field Story

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

IPA18-581-E

PROCEEDINGS INDONESIAN PETROLEUM ASSOCIATION


Forty-Second Annual Convention & Exhibition, May 2018

HOW TO REDUCE ROD PUMP FAILURES BY 40% IN 2 YEARS – THE X FIELD STORY

Japet Dongoran*

ABSTRACT pump with production range from 50 – 1500 BFPD


  and reservoir depth range from 400 to 600 ft TVD.
X field is one of the largest steam flood fields in the Steam operation in this field was started in 1985.
world, with over 6200 producers and 680 active Several challenges faced by artificial lift operation in
steam injectors. Historically there have been this field are:
challenges with rod pump run life in X field due to
high temperatures, scaling and sanding. In 2015 there  Massive sand problem. Combination of
were over 2700 rod pump failures. unconsolidated shallow reservoir and steam
flood operation (high temperature) cause sand
In early 2016 the Integrated Optimization and problem. Sand control devices used in this field
Decision Support Center – Well Reliability and is wire wrapped screen liner with gravel packed
Optimization (IODSC-WRO) organization was sand. Most of the sand control are aging.
formed as part of the implementation of a decision
support center (DSC), and this team commenced  Very hot temperature. As consequence of steam
implementing several initiatives to reduce the rod flood operation, the temperature of reservoir in
pump failure in X field: this field is very high especially reservoir which
already got steam breakthrough. The
1. Failure database improvement. temperature is range from 200 – 350 deg F. This
high temperature is one of the challenge in
2. Pump installation SOP improvements. artificial lit operation
3. Rigorous review and approval process for
 Scaling. Exposure of high temperature to
repeated and premature failures.
reservoir cause solubility of calcium carbonate
4. Installation of unique tail screens as secondary drops significantly which at the end cause
sand control. calcium carbonate precipitation. Scaling
precipitation in pump is one of problem in this
5. Pump speed reduction for low pump fillage field
wells.
 Very low rate. X field is very old field and
6. Proactively identify and replace failing pumps. already exploited more than 50 years. There is a
lot of wells with very limited rate
With the efforts above, failure rate in X field has
reduced by 40% since 2015. This equates to a All the challenges above contribute to pump failure
reduction of more than 1000 rod pump failures per in this field. In 2015, there are 2700 pull out job done
year. This has translated into very significant rig by rig to replace fail pump. Figure 1 - Failure History
OPEX avoidance and significant contributor to a and Mean Time Between Failure (MTBF) in X Field
2000 BOPD reduction in LPO. showing the trend of failure frequency increase over
the time. This failures impact to increasing of
Keywords: Rod pump, reliability, improvement, operating expenditure needed to replace the failed
failure reduction, sand control. pump and higher loss production opportunity (LPO)
due to well shut down because of pump failure.
BACKGROUND
  Improvement Strategy
X field is a mature steam flood field with over 6200  
producer wells and 680 active steam injectors. Most To respond the challenges, strategies were developed
of artificial lift in this field (99.7%) are sucker rod to reduce the pump failure. Before developing the

* Chevron Pacific Indonesia


strategy, several studies were conducted to Standard pump space was determined based on
understand the best solution to reduce the pump engineering calculation which is combined with field
failure. The studies focus on several aspects like observation/experience. When pump operated the
process, system, equipment and organizational rod will elongate. The length of the elongation
capability. Benchmarking also conducted to see best depends on the rod load, rod length, rod elasticity and
practice from other business unit with typical field temperature. Pump space for X field was made
and operating environment. typical considering range of depth is not wide (400 –
600 TVD). That standard pump space was written in
Figure 2 - Improvement Strategy showing shaping pump installation standard operating procedure
plan to reduce failure in X field. (SOP) and then socialized to field personnel. To
sustain the consistency of the pump space setting, rig
1. Failure database Improvement crew is required to report the pump space in tour
  report. And all that data is uploaded into database. In
Good failure database is very critical in doing several cases verification and validation using rigless
robust failure analysis. To understand more equipment done to make sure the pump space was set
comprehensive about root cause of failure, several properly. Beside the pump space, another
improvements were made including failure data improvement also made to standardize tightening of
system of record, failure reporting, field finding sucker rod connection. Statistical data showing that
reporting. Dismantle, inspection and failure 20% of not pumping failure due to unscrew cases. To
analysis (DIFA) process was revitalized with solve the unscrew problem, investigation was done
several improvements on finding record. All to understand the mechanism of the unscrew. Most
findings from DIFA were uploaded into database of the unscrew due to fluid pounding and rod
which then combined with other data like pull out buckling while downstroke. The rod buckling is
report, pull out history, pump history, well testing suspected due to high friction between plunger and
data and other surveillance. In DIFA and pull out barrel. High friction of plunger and barrel is common
report, pictures of all findings also recorded and problem at sandy wells. Improper tightening also
attached to the DIFA digital record to enable suspected as one of the contributor to the unscrew
engineers and analyst to see the real condition of failure in X field. Standard operating procedure for
the findings. Figure 3 - Pump condition pictures tightening the rod was modified to make sure the
taken during DIFA are example of pictures tightening done properly.
showing in DIFA report. Team also developed one
single review tool which allow to combine all data, 3. Rigorous review and approval process for
finding and failure root cause which enable team repeated and premature failure
to conduct comprehensive and detail review of  
failure analysis. The failure will be categorized as premature if the
run life of the failed pump is less than 30 days and if
Part by part failure analysis also conducted during the failure happens three times or more in last one
DIFA and all that data uploaded into database for year, it will be categorized as repetitive failure.
statistically analysis purposes. The robust analysis Premature failure and repetitive pump failure
has enable team to accurately mapping failure root contributed significant loss production opportunity
cause and failure mode in X field. Figure 4 - in X field. Most of the repetitive failure are caused
Example of failure mode analysis which is done for by massive sand problem. To reduce the premature
every main part in DIFA activity. and repetitive failure, special review was applied to
make sure there is appropriate mitigation to solve the
2. Pump installation Procedure Improvement failure root cause. This review is very detail and
comprehensive to understand bad actors of the
Based on failure mapping finding, pump space is one failure. Most of the repetitive and premature failure
of root cause which contribute to not pumping review involve cross functional team with multi
failure. Pump space in sucker rod pump is distance discipline expertise like reservoir engineer, operation
between travelling valve and standing valve while staff, production engineer, completion engineer and
pump in fully downstroke as described by Figure 5 - artificial lift experts. This review includes pump
Pump Space. Too high pump space will cause gas design and selection of special pump and equipment
lock on the other hand to narrow pump space will that will be used to mitigate failure cause. For
cause traveling valve hit standing valve while extremely sandy wells, utilization of unique pump
downstroke. This condition can cause pump to design was used like special clearance and other
become not pumping or stuck. unique pump design which is designed to mitigate

 
extreme sanded wells. Beside that it is also decided engineers, pump shop analyst and artificial lift
if needed to utilize additional unique sand control experts. Mesh size of the screen designed based on
which is installed at tail of the pump. This screen is sieve analysis from sand study which have been
designed as secondary sand control and installed conducted before. Figure 9 - Tail screen
before intake of the pump. For sucker rod pump configuration showing schematic of tail screen
which is placed in horizontal wells with high installed at Tubing and Insert Pump.
inclination (more than 85 deg inclination), special
valve design was used. Spring loaded valve and This screen is much cheaper compare to replace the
special valve cage was used to overcome failure due old sand control. This tail screen is 35 times cheaper
to very high inclination pump placement. The level than replacing the old sand control. This screen is
of review and approval for premature and repetitive also re-usable. Every time the pump is pulled out, the
failure recommendation is until manager level to get screen is cleaned out then re-attached to the pump
more attention and make sure appropriate mitigation intake. This tail screen is very easy to install and
is available. almost there is no risk for fail to pull out like the old
liner. Tail screen installed at wells with experienced
Very detail and comprehensive review involving repeated or premature failure. Utilization of this tail
cross functional discipline combined with high level screen is proven in improving run life of the pump.
review and approval has significantly reduce failure More than 150 installations have been done and
repetitive and premature failure in X field as statistically showing significant improvement. In
described in Figure 6 - Repetitive and Premature statistic, the run life improved more than three times
failure reduction. compared to previous condition before installing tail
liner as described by Figure 10 - Run Life
4. Utilization of unique pump intake tail screen comparison before and after Tail screen installation.
  The improvement will continue grow since most of
Most of failure in X field related to sand problem. the pump are still running.
Several studies have been conducted to see the most
optimum sand control design to overcome the sand Production after installation of tail screen also
issue at the same time not harm the production. Too evaluated to see impact of additional sand control to
aggressive sand control can create excessive the fluid production. Fluid rate three (3) months
additional skin at wellbore, on the other hand poor before and after installation is compared and
sand control will create high failure rate. Several showing relatively same performance of fluid rate
challenges in designing sand control in this field are before and after installation of the tail screen as
the wide range of particle size distribution as shown shown at Figure 11 - Fluid production before and
in Figure 7 - Example of particle size distribution in after the Tail screen installation.Figure 11 - Fluid
X field, existence of very fine sand and existence of production before and after the Tail screen
high temperature steam while breakthrough and installation
mature period which impact sand cementation.
5. Pump speed reduction for low pump fillage
Typical completion and sand control used in X field
is open hole gravel pack with liner as described by X field is mature field, most of the pump were
Figure 8 - Typical completion and sand control. designed when the fluid rate is still high. X field is
not water drive reservoir. As reservoir depleted,
Because this field is very mature field, the downhole amount of fluid flow into wellbore also depleted.
equipment include sand control are old. Some of the This situation cause lots of wells produce very low
sand control are in poor condition. This cause rate with very low pump fillage.
excessive sand production into wellbore which can
create failure to the pump. Replacing the old sand In 2015, 2400 wells operate with pump fillage less
control is costly and risky in this field. In some cases, than 30%. This situation cause more failure to the
the liner cannot be pulled out and some are cut off pump. The pump which operate with low rate but
during revise liner operation. Several wells end up high-speed cause severe fluid pounding and faster
with plug and abandon due to failure in pulling out worn out rate. The lubrication of moving part of the
the liner. To reduce the failure due to sand problem, pump is the fluid produced by the pump itself. If the
secondary unique screen was trialed. This screen was rate is low means that the pump has poor lubrication.
installed at tail of pump intake and inside the old The fluid or gas pounding as effect of low pump
liner. Several modifications were made to the pump fillage is harmful to the pumping operation since it
intake and screen connection involving completion can cause rod bucking. The reason for the pump

 
running in high speed (8 stroke per minute and
above) because the pumping unit cannot be slowed CONCLUSION
down due to there is no standard pulley available in  
market to allow less slow SPM for the unit. To allow  Good failure database, collaboration work
slower running, pulley modification was done after between cross functional team and creative
conducting comprehensive engineering review. The thinking is the key to reduce the failure
modified pulley can run until 5 strokes per minute.
Installation of the modified pulley significantly  Utilization of unique tail screen are proven in
improve pump efficiency as described by Figure 12 - reducing the failure due to pump stuck and
Pump fillage before and after installation of small efficiently reducing cost for improving old liner
pulley. Failure rate also improved 50% after slowing replacement
down the speed of pumping at low pump filalge
wells. From energy consumption perspective, the  Comprehensive analysis and collaboration has
power consumption of pump reduced 25% compared significantly reduce failure and loss production
to previous condition before installing the modified opportunity
pulley. No production reduction observed after
installation of modified small pulley. ACKNOWLEDGEMENT
6. Proactively identify and replace weak or fail Appreciation to the project team who involve
pump reducing pump failure in X field and help to prepare
  this paper. Thanks to Kynan Scarr, Rosyadi, Ahmad
To reduce the failure, aggressive identification of Riadi Hasibuan and Megah Ginting.
failure symptom is done. Corrective action is taken
to pumps with symptom of failure. The action REFERENCES
includes to replace the weak pump.
M. Ghareeb (Lufkin Industries, Inc.), B. Frost
RESULT (Odessa Separator, Inc) and C. Tarr (Harbison-
  Fischer) and Nael N. Sadek (Lufkin Automation),
After implementing improvement strategy above, 2014, Application of Beam Pumping System for
40% of failure reduced since 2015 as shown in High Gas/Oil Ratio Wells: Middle East Artificial
Figure 13 - MTBF and number of failure history. The Forum
improvement equals to reducing more than 1000
pump failure per year, means that reducing 1000 rig A.A.Hardy, 1952, Sucker-Rod Joint Failures:
pull out job to replace the failed pump. This American Petroleum Insitute
improvement contributes very significant business
impact to the corporation. Feilong Liu and Anilkumar Patel, 2013, Well Failure
Detection for Rod Pump Artificial Lift System
This improvement also contributes very significant through Pattern Recognition, International
(2000 BOPD) reduction of loss production Petroleum Technology Conference
opportunity (LPO) in X field as described in Figure
14 - Historical LPO due to pump failure.

 
Figure 1 - Failure History and Mean Time Between Failure (MTBF) in X Field
 

Figure 2 - Improvement Strategy


 

 
Figure 3 - Pump condition pictures taken during DIFA
 

PLUNGER CONDITION
2500
HEAVY SCRATCHED
2051 LIGHT SCRATCHED
2000
GOOD
WORN OUT
1500
1251 UNDER SIZE
NOT RECEIVED
1000
PITTED
477 ABRASION
500
202 CRACKED
124115
41 27 16 13 7 2 1 1 1 1 1 1 GALLED
0

Figure 4 - Example of failure mode analysis


 

 
Figure 5 - Pump Space
 

Figure 6 - Repetitive and Premature failure reduction

 
Figure 7 - Example of particle size distribution in X field
 

Figure 8 - Typical completion and sand control


 

 
 
Figure 9 - Tail screen configuration
 

Run Life Improvement
Data until Jul‐17
600

500

400

Q1
300 Min
Median
Max
200 188 Q3

100
53

Before (Avg) After
Figure 10 - Run Life comparison before and after Tail screen installation
 
 
Figure 11 - Fluid production before and after the Tail screen installation
 

Normalized Pump FIllage
50
45
40
35
30
% PF

25
20
15
10
5
0
‐120 ‐90 ‐60 ‐30 0 30 60 90 120

PUMP FILLAGE

Figure 12 - Pump fillage before and after installation of small pulley


 

 
Figure 13 - MTBF and number of failure history
 

SUBSURFACE REREACTIVE LPO
5000
4000
3000
2000
1000
0
1‐Jan‐2014

1‐Jan‐2015

1‐Jan‐2016

1‐Jan‐2017
1‐Oct‐2014

1‐Oct‐2015

1‐Oct‐2016
1‐Apr‐2014
1‐Jul‐2014

1‐Apr‐2015
1‐Jul‐2015

1‐Apr‐2016
1‐Jul‐2016

1‐Apr‐2017

Figure 14 - Historical LPO due to pump failure


 

You might also like