Professional Documents
Culture Documents
04how To Reduce Rod Pump Failures by 40 in 2 Years The X Field Story
04how To Reduce Rod Pump Failures by 40 in 2 Years The X Field Story
04how To Reduce Rod Pump Failures by 40 in 2 Years The X Field Story
HOW TO REDUCE ROD PUMP FAILURES BY 40% IN 2 YEARS – THE X FIELD STORY
Japet Dongoran*
extreme sanded wells. Beside that it is also decided engineers, pump shop analyst and artificial lift
if needed to utilize additional unique sand control experts. Mesh size of the screen designed based on
which is installed at tail of the pump. This screen is sieve analysis from sand study which have been
designed as secondary sand control and installed conducted before. Figure 9 - Tail screen
before intake of the pump. For sucker rod pump configuration showing schematic of tail screen
which is placed in horizontal wells with high installed at Tubing and Insert Pump.
inclination (more than 85 deg inclination), special
valve design was used. Spring loaded valve and This screen is much cheaper compare to replace the
special valve cage was used to overcome failure due old sand control. This tail screen is 35 times cheaper
to very high inclination pump placement. The level than replacing the old sand control. This screen is
of review and approval for premature and repetitive also re-usable. Every time the pump is pulled out, the
failure recommendation is until manager level to get screen is cleaned out then re-attached to the pump
more attention and make sure appropriate mitigation intake. This tail screen is very easy to install and
is available. almost there is no risk for fail to pull out like the old
liner. Tail screen installed at wells with experienced
Very detail and comprehensive review involving repeated or premature failure. Utilization of this tail
cross functional discipline combined with high level screen is proven in improving run life of the pump.
review and approval has significantly reduce failure More than 150 installations have been done and
repetitive and premature failure in X field as statistically showing significant improvement. In
described in Figure 6 - Repetitive and Premature statistic, the run life improved more than three times
failure reduction. compared to previous condition before installing tail
liner as described by Figure 10 - Run Life
4. Utilization of unique pump intake tail screen comparison before and after Tail screen installation.
The improvement will continue grow since most of
Most of failure in X field related to sand problem. the pump are still running.
Several studies have been conducted to see the most
optimum sand control design to overcome the sand Production after installation of tail screen also
issue at the same time not harm the production. Too evaluated to see impact of additional sand control to
aggressive sand control can create excessive the fluid production. Fluid rate three (3) months
additional skin at wellbore, on the other hand poor before and after installation is compared and
sand control will create high failure rate. Several showing relatively same performance of fluid rate
challenges in designing sand control in this field are before and after installation of the tail screen as
the wide range of particle size distribution as shown shown at Figure 11 - Fluid production before and
in Figure 7 - Example of particle size distribution in after the Tail screen installation.Figure 11 - Fluid
X field, existence of very fine sand and existence of production before and after the Tail screen
high temperature steam while breakthrough and installation
mature period which impact sand cementation.
5. Pump speed reduction for low pump fillage
Typical completion and sand control used in X field
is open hole gravel pack with liner as described by X field is mature field, most of the pump were
Figure 8 - Typical completion and sand control. designed when the fluid rate is still high. X field is
not water drive reservoir. As reservoir depleted,
Because this field is very mature field, the downhole amount of fluid flow into wellbore also depleted.
equipment include sand control are old. Some of the This situation cause lots of wells produce very low
sand control are in poor condition. This cause rate with very low pump fillage.
excessive sand production into wellbore which can
create failure to the pump. Replacing the old sand In 2015, 2400 wells operate with pump fillage less
control is costly and risky in this field. In some cases, than 30%. This situation cause more failure to the
the liner cannot be pulled out and some are cut off pump. The pump which operate with low rate but
during revise liner operation. Several wells end up high-speed cause severe fluid pounding and faster
with plug and abandon due to failure in pulling out worn out rate. The lubrication of moving part of the
the liner. To reduce the failure due to sand problem, pump is the fluid produced by the pump itself. If the
secondary unique screen was trialed. This screen was rate is low means that the pump has poor lubrication.
installed at tail of pump intake and inside the old The fluid or gas pounding as effect of low pump
liner. Several modifications were made to the pump fillage is harmful to the pumping operation since it
intake and screen connection involving completion can cause rod bucking. The reason for the pump
running in high speed (8 stroke per minute and
above) because the pumping unit cannot be slowed CONCLUSION
down due to there is no standard pulley available in
market to allow less slow SPM for the unit. To allow Good failure database, collaboration work
slower running, pulley modification was done after between cross functional team and creative
conducting comprehensive engineering review. The thinking is the key to reduce the failure
modified pulley can run until 5 strokes per minute.
Installation of the modified pulley significantly Utilization of unique tail screen are proven in
improve pump efficiency as described by Figure 12 - reducing the failure due to pump stuck and
Pump fillage before and after installation of small efficiently reducing cost for improving old liner
pulley. Failure rate also improved 50% after slowing replacement
down the speed of pumping at low pump filalge
wells. From energy consumption perspective, the Comprehensive analysis and collaboration has
power consumption of pump reduced 25% compared significantly reduce failure and loss production
to previous condition before installing the modified opportunity
pulley. No production reduction observed after
installation of modified small pulley. ACKNOWLEDGEMENT
6. Proactively identify and replace weak or fail Appreciation to the project team who involve
pump reducing pump failure in X field and help to prepare
this paper. Thanks to Kynan Scarr, Rosyadi, Ahmad
To reduce the failure, aggressive identification of Riadi Hasibuan and Megah Ginting.
failure symptom is done. Corrective action is taken
to pumps with symptom of failure. The action REFERENCES
includes to replace the weak pump.
M. Ghareeb (Lufkin Industries, Inc.), B. Frost
RESULT (Odessa Separator, Inc) and C. Tarr (Harbison-
Fischer) and Nael N. Sadek (Lufkin Automation),
After implementing improvement strategy above, 2014, Application of Beam Pumping System for
40% of failure reduced since 2015 as shown in High Gas/Oil Ratio Wells: Middle East Artificial
Figure 13 - MTBF and number of failure history. The Forum
improvement equals to reducing more than 1000
pump failure per year, means that reducing 1000 rig A.A.Hardy, 1952, Sucker-Rod Joint Failures:
pull out job to replace the failed pump. This American Petroleum Insitute
improvement contributes very significant business
impact to the corporation. Feilong Liu and Anilkumar Patel, 2013, Well Failure
Detection for Rod Pump Artificial Lift System
This improvement also contributes very significant through Pattern Recognition, International
(2000 BOPD) reduction of loss production Petroleum Technology Conference
opportunity (LPO) in X field as described in Figure
14 - Historical LPO due to pump failure.
Figure 1 - Failure History and Mean Time Between Failure (MTBF) in X Field
Figure 3 - Pump condition pictures taken during DIFA
PLUNGER CONDITION
2500
HEAVY SCRATCHED
2051 LIGHT SCRATCHED
2000
GOOD
WORN OUT
1500
1251 UNDER SIZE
NOT RECEIVED
1000
PITTED
477 ABRASION
500
202 CRACKED
124115
41 27 16 13 7 2 1 1 1 1 1 1 GALLED
0
Figure 5 - Pump Space
Figure 7 - Example of particle size distribution in X field
Figure 9 - Tail screen configuration
Run Life Improvement
Data until Jul‐17
600
500
400
Q1
300 Min
Median
Max
200 188 Q3
100
53
Before (Avg) After
Figure 10 - Run Life comparison before and after Tail screen installation
Figure 11 - Fluid production before and after the Tail screen installation
Normalized Pump FIllage
50
45
40
35
30
% PF
25
20
15
10
5
0
‐120 ‐90 ‐60 ‐30 0 30 60 90 120
PUMP FILLAGE
Figure 13 - MTBF and number of failure history
SUBSURFACE REREACTIVE LPO
5000
4000
3000
2000
1000
0
1‐Jan‐2014
1‐Jan‐2015
1‐Jan‐2016
1‐Jan‐2017
1‐Oct‐2014
1‐Oct‐2015
1‐Oct‐2016
1‐Apr‐2014
1‐Jul‐2014
1‐Apr‐2015
1‐Jul‐2015
1‐Apr‐2016
1‐Jul‐2016
1‐Apr‐2017