MATERIAL SPECIFICATION AND QUANTITY OF A PORTION OF WORKING

DRAWING PROJECT OF CLASSROOM

GROUND FLOOR
Sl.No. Description Unit Quantity Rate Amount
1 Excavation of foundation in all kinds of soil NOxLxBxH
within 1.50m. depth, dressing, levelling the bed
and sides and depositing the excavated earth
clear from working area within 50 m.
lead as directed.
Ground Floor Cum 7x1.584= 370.91 4100.59
11.08
2 Filling foundation and plinth with coarse river
sand, well watered and rammed with cost of
conveyance royality taxes labour T&P required.

Ground Floor Cum 5.54 432.50 2396.05


3 Cement concrete (1:4:8) with 40 mm down grade
size crusher broken hard granite metal including
lowering laying in position in layers not
exceeding 150 mm in depth, ramming,
compacting to required thickness, and curing for
seven days with cost of conveyance royality taxes
of all materials labour T&P
required.
Ground Floor Cum 0.35 2400.00 840
4 Reinforced cement concrete (1:1 ½:3) with 19mm
size crusher broken H.G. chips including hoisting
laying in position compacting to required
thickness including rigid smooth centring and
shuttering and dismantling the same and clearing
from the sites as directed excluding cost of MS
bars, watering curing for twenty one days with
cost of conveyance reality taxes of all
materials
labour T&P required.
i) foundation Cum 5.65 4400.00 24,860
ii) Plinth Beam Cum 5.55 4400.00 24,420
5 1st class KB brick masonry in cement mortar
(1:6) in full brick wall in superstructure
immersing the brick in water not less than six
hours before use, watering curing for seven days
with cost of conveyance royality taxes of all
materials labour T&P required for the work.

Ground Floor Cum 134.43 3900.00 524277


6 1st class KB brick masonry in cement mortar
(1:6) in superstructure of 1/2 brick wall including
immersing the brick in water for not less than six
hours before use, watering curing for seven days
with cost of conveyance royality taxes of all
materials
labour T&P required for the work.
Ground Floor Sq m 85.51 3900.00 333489
7 Reinforced cement concrete (1:1 ½:3) with
19 mm size crusher broken H.G. chips including
hoisting laying in position compacting to required
thickness incluiding rigid smooth centring &
shuttering and dismantling the same and clearing
from the sites as directed excluding cost of MS
bars, watering curing for twenty one days with
cost of conveyance royality taxes of all materials
labour T&P required.

i) RCC Lintel
Ground Floor Cum 1.5 4400.00 6600

ii) RCC Column


Ground Floor Cum 4.43 4400.00 19,492
iii) RCC Beam
Ground Floor Cum 8.44 4400.00 37,136
iv) RCC Slab
Ground Floor Cum 20.56 4400.00 90,464
8 Cutting, bending, laying, straightening, cranking
and hooking the MS bars or Torsteel including
hoisting and placing in position and binding at
each cross-section point with 20BWG binding
wires including cost of MS bar/Torsteel and
binding wires with royality taxes of all materials
labour T&P required.

Ground Floor Qtl. 15.65 5600.00 87640


9 12 mm thick cement plaster (1:6) over brick
masonry including racking out joints, finished
with proper plumb and line, watering curing for
seven days with cost of conveyance royality taxes
of all materials labour T&P
required for total Inside surfaces.
Ground Floor Sqm. 134.56 95.00 12,783.2
10
16 mm thick cement plaster (1:6) over brick
masonry including racking out joints, finished
with proper plumb and line, watering curing for
seven days with cost of conveyance royality taxes
of all materials labour T&P required for total
outside surfaces including head rooms and
parapets.

Ground Floor Sqm. 85.51 105.00 8,978.55


11 6mm thk. cement plaster (1:4) as ceiling plaster &
over R.C.C surfaces including cost, conveyance
etc. in all respects as directed by the engineer.

Ground Floor Sqm. 56 95.00 5320