Professional Documents
Culture Documents
Method Statement Concrete Pouring
Method Statement Concrete Pouring
Method Statement Concrete Pouring
1. Scope
This method statement describes the method and procedures involved in the TT-4 Raft and
BC-03 Raft Mass Concrete Work. The technical specification and other relevant information on Machinery and
Equipment used in this works are included.
For Execution Quantity
TT-4 Raft =179 Cum
Bc-03- = 28 Cum
Total Quantity = 207 Cum
2. Reference
Drawing no: CME-BC3-CA-001-c and CME-TT4-CA-001-b
3. Equipment’s & Tools 4.Manpower
Batching Plant -60 cum/hrs. Capacity 1.Civil Engineer/supervisor -3 no’s
Transit Mixer -03 no’s – 8.0 cum capacity 2.Driver&Operator -04 Nos
Concrete Vibrator -3 Nos -60 mm needle 3.Helper- 10 Nos
Concrete Chute-4 no’s -6 m long 4.Vibrating Helper- 5 Nos
Surveying Instrument 5.Concrete Mason- 3 Nos
Lighting Arrangement 6.Surveyor&Safety- 2 no’s
Page 1 of 4
NAME OF THE WORK : CONCRETE METHOD STATEMENT FOR RAFT
NAME OF THE PROJECT : TRANSFER TOWER-4 AND BC-03
NAME OF THE CLIENT : CIMASSO LINE-2
CONTRACTOR : AYOKI FABRICON PVT LTD
CONSULTANT : INTERCEM ENGINEERING
Page 2 of 4
NAME OF THE WORK : CONCRETE METHOD STATEMENT FOR RAFT
NAME OF THE PROJECT : TRANSFER TOWER-4 AND BC-03
NAME OF THE CLIENT : CIMASSO LINE-2
CONTRACTOR : AYOKI FABRICON PVT LTD
CONSULTANT : INTERCEM ENGINEERING
Page 3 of 4
NAME OF THE WORK : CONCRETE METHOD STATEMENT FOR RAFT
NAME OF THE PROJECT : TRANSFER TOWER-4 AND BC-03
NAME OF THE CLIENT : CIMASSO LINE-2
CONTRACTOR : AYOKI FABRICON PVT LTD
CONSULTANT : INTERCEM ENGINEERING
Page 4 of 4