This document summarizes comments from a review of a design report for the U4K project. It includes 3 comments: [1] The calculation of CBR from DCP tests should be consistent with TRL standards; test results should indicate refusal points and in-situ material. [2] The borrow pits did not meet specifications for rural road pavement and the sieve analysis did not conform to TRH 20 standards. Quantification and testing of in-situ material was also insufficient. [3] Precise names and chainages should be provided for water sample collection locations.
This document summarizes comments from a review of a design report for the U4K project. It includes 3 comments: [1] The calculation of CBR from DCP tests should be consistent with TRL standards; test results should indicate refusal points and in-situ material. [2] The borrow pits did not meet specifications for rural road pavement and the sieve analysis did not conform to TRH 20 standards. Quantification and testing of in-situ material was also insufficient. [3] Precise names and chainages should be provided for water sample collection locations.
This document summarizes comments from a review of a design report for the U4K project. It includes 3 comments: [1] The calculation of CBR from DCP tests should be consistent with TRL standards; test results should indicate refusal points and in-situ material. [2] The borrow pits did not meet specifications for rural road pavement and the sieve analysis did not conform to TRH 20 standards. Quantification and testing of in-situ material was also insufficient. [3] Precise names and chainages should be provided for water sample collection locations.
RESPONSE MATRIX ON THE U4K DESIGN REPORT REVIEW OPRC PACKAGE 12
S/N Comment Ref COMMENTS/CONCERN BY MC ACTION/RESPONSE BY CE
1 Clause 5.2.6 DCP –CBR Relationship is calculated refer to TRL (CBR)=2.48- 1.057Log(DCP Number) whereas, the CBR on all layer properties for dcp test were being calculated using (CBR)=2.632-1.28Log(DCP Number) On the attached results appendix B Therefore, calculation should be the same refer to TRL standard. Contractor should indicate the DCP Test Refusal on test pit points where 1meter DCP rod did not further penetrate due to some difficulties underground condition and also indicate points of in-situ material on test pits where material where not sampled respectively.
2 Clause 7.1 All seven (7) borrow pits which are
located on U4k has failed to meet some properties required for unpaved road pavement design in rural areas according to standard specified under TRH 20 document The sieve line up used based on satcc 3402/1 didn’t conform to TRH 20 sieve line up to calculate grading coefficient. (Check Percentage Passing 26.5mm sieve ‘TRH 20’)’’ Contractor can use soils sieve line up that can conform to recommended material specification for unpaved road in rural areas. RESPONSE MATRIX ON THE U4K DESIGN REPORT REVIEW OPRC PACKAGE 12 Borrow pit quantification where not done to determine the availability of material to use on road project except the location of borrow pit’s with one GPS coordinate for each borrow pit point. In-situ material for Test pit points of dcp are not fully reported for further analysis only three (3) points are attached on appendix E such as km 20+000, km25+000 and km36+000
3 Clause 7.2.4 Contractor should Specify the precisely
name of the streams/rivers where water samples were collected with chainages.