Draft Minutes of 3rd Monthly Meeting of May 2022 OPRC Pkg-12
Draft Minutes of 3rd Monthly Meeting of May 2022 OPRC Pkg-12
Draft Minutes of 3rd Monthly Meeting of May 2022 OPRC Pkg-12
1. Introduction/Attendance
2. Approval of Previous Meeting Minutes
3. Matters arising from the previous Meeting
4. Status on CE’s pre-construction documents submissions for Phase-I assignment
C-ESMP document
EPB for Camp Site & Borrow Pits
Initial Contract Condition Report
Updated Work Programme
Quality Assurance Plan
MC’s Camp construction Layout drawings
Detailed Design of the 1st section of Road that CE want to undertake
Any other pre-construction documents submission as per MC’s letter dated 11 March 2022 not
covered above
5. Submission of Contractor’s Monthly Progress Reports along with:
Contractor’s ESMP Report
Contractor’s HSMP Report
Contractor’s HIV/AIDS Prevention Report
6. Finalize date for joint site visit for verification of Initial Condition Report within 1 st week of June
2022 as per the decision taken during the meeting chaired by RDA on 17 May 2022.
7. Provide temporary facilities for MC at site after 90 days from the Start Date of the Project till CE
provide permanent facilities as per the provision of Contract.
8. Any Other Business (AOB)
9. Date of Next Meeting
10. Closure of Meeting
Page 1 of 9
S/N Name Position Organization
Team Leader(TL)
1 Mr. Narapati Katel LASA/ILISO
(Highway Engineer/Resident Engineer)
2 Mr. Soumik Sarkar Manager (Operations) LASA/ILISO
3 Mr. Francis Regedzai Hydrologist/Drainage Engineer ILISO
4 Mr. Glory Nthara Surveyor/Geometric Engineer ILISO
5 Mr. Misheck Musonda Material Technician ILISO
6 Mr. William Kunda Inspector of Works ILISO
7 Md Abdus Sattar Contract Manager M & N Merchants Ltd
8 Mr. Trasizio Banda Civil Engineer Bari Zambia Ltd
Page 2 of 9
SL.NO KEY DISCUSSION AND ACTION POINTS ACTIONS
meeting mentioned in 2nd Draft Minutes of Meeting under Sl. No. 11 (Page
no. 2 of 10) and needs to be corrected as “M & N Merchants Ltd.” and
accordingly made correction in the Final 2 nd Minutes of Monthly Progress
Meeting.
The Final 2nd Minutes of Monthly Progress Review Meeting after necessary
corrections has been signed by the representatives of RDA, MC & CE and
hence adopted.
The Contract Manager, M & N Merchants Ltd pointed out that there are no
any matters arising from the previous meeting. Further, the TL replied that
issues which need attention are covered in the Agenda for the meeting and
hence there were no any issues to be discussed further.
Page 3 of 9
SL.NO KEY DISCUSSION AND ACTION POINTS ACTIONS
incorporation in final document. Also, Zambia Environmental
Management Authority (ZEMA) reviewed EPB for Campsite and
issued comments on 7 April 2022 to CE and enquired on the status
on final submission of EBP for Campsite. The Contract Manager of
CE responded that the submission on EPB for Camp site is almost
completed and shall be submitted to MC within one or two days.
Further regarding the status on EPB for Borrow Pits, the Contract
Manager of CE said that it will be submitted to MC together with
with 1st link of design drawings tentatively by 3 June 2022.
CE
Initial Condition Report:
The TL informed that CE incorporated all the comments of
MC and re-submitted softcopy of updated Initial Condition
Report on 24 May 2022 via email and requested to follow
procedures to submit by letter as agreed in the Introductory
Meeting conducted between MC & CE during 21 March 2022.
Further, the TL mentioned that a joint site visit is proposed to
be conducted by the representatives of RDA, MC & CE before
submitting the final Initial Condition Report to RDA as pert
the provision of contract. As per the decision taken during
the online meeting chaired by RDA on 17 May 2022, it was
agreed to conduct a joint site visit during the first week of
June 2022 which shall be discussed separately in this monthly Info
progress meeting under Agenda point No. 6.
Page 4 of 9
SL.NO KEY DISCUSSION AND ACTION POINTS ACTIONS
but CE has not submitted final updated QAP after
incorporating the comments of MC even after a lapse of
about 45 days and enquired on the status of submission with
CE. The Contract Manager of CE responded that CE is working CE
to complete on priority but not given any specified time of
submission of final QAP.
Page 5 of 9
SL.NO KEY DISCUSSION AND ACTION POINTS ACTIONS
MC’s letter dated 11 March 2022 not covered above:
The TL reminded CE to submit all the other documents not
covered above as per MC’s letter Ref. No:
LASA/M&N/OPRC/PACKAGE-12/2022-23/001 dated 11 March
2022. Some of the important documents not covered above, but
not limited to, are as follows:
(i) All technical documents listed in the Specifications.
(ii) Handing over of the entire Road Reserve as per Sub-Clause
14.2
(iii) Site Regulations for Employer’s approval as required within 2
months of Start Date as per Sub-Clause A 3.4
(iv) Details of mobilization of Plants & Machineries along with the
Date of mobilization.
(v) Health & Safety Management Plan
5. SUBMISSION OF CONTRACTOR’S MONTHLY PROGRESS REPORT:
The TL said as per GC Sub-Clause 17.3.1 of the contract provision it is CE
stipulated that “The Contractor shall monitor progress of works and
other activities specified in the program referred in GC Sub-Clause 17.2
and submit a Monthly Progress Report to the Project Manager every
month together with his monthly Statement unless otherwise stated in
the Specifications, each progress report shall include the
Environmental and Social (ES) matrices set out in Appendix B”. Futher,
TL pointed out that the Employer has issued Possession of Site
Certificate as per GC 14.2 for the vide letter Ref. No.
RDAHQ/101/12/280 effective from 25 March 2022 which is also the
Start Date of the Project. However, CE has not submitted any Monthly
Reports for the months of March & April 2022 as per the provision of
contract and started making claims without any proof of any activities
performed in the Monthly Reports and instructed CE to submit CE’s
Monthly Reports as per GC Sub-Clause 17.3.1 by end of every months
without fail along with ESMP, HSMP, HIV Report, Quality Report,
Contractor’s Monthly Statement of any activities performed as per
standard formats otherwise MC will assume that no any activities have
been performed at site and claims made on that particular month
cannot be entertained. The Contract Manager responded that CE will
start submitting Monthly Progress Reports in standard formats from
Page 6 of 9
SL.NO KEY DISCUSSION AND ACTION POINTS ACTIONS
May 2022 onwards regularly as per the provision of the Contract.
6. FINALIZE DATE OF JOINT SITE VISIT FOR VERIFICATION OF
CONTRACTOR”S INITIAL CONDITION REPORT:
RDA/MC/
The TL informed that during the online meeting conducted by CE
RDA on 17 May 2022, it was decided to conduct a joint site visit
for the verification of Contractor’s Initial Condition Report in field
by the representatives of RDA, MC & CE tentatively during the
first week of June 2022 as per the provision of the contract and
requested to finalize a suitable date during the meeting for
proposed site visit. Accordingly, the meeting decided to conduct
joint site visit from 6 June 2022 for verification of Initial
Condition Report.
7. TEMPORARY FACILITIES FOR MC AT SITE AFTER 90 DAYS FROM
THE START DATE OF THE PROJECT TILL CE PROVIDE PERMANENT
FACILITIES AS PER THE PROVISION OF CONTRACT: CE
The TL informed that the accommodation should be ready for
occupation not later than 90 days from the Start Date of the Project.
The TL pointed out that CE should provide the facilities for the use of
MC’s Staffs as per the provision of Contract not later than 90 days from
the Start Date of the Project and enquired on the status of the
following:
(i) Consultant’s Office, Office Eqipment and Supplies
(ii) Consultant’s Residential accommodation
(iii) Procurement & supply of Vehicles
Page 7 of 9
SL.NO KEY DISCUSSION AND ACTION POINTS ACTIONS
points/issues which is not covered in the meeting and requested all
particitants to raise any concerns under AOB. The representatives of CE
said all the issues were well covered in the Agenda as such there were
no any additional issues for discussions and CE & MC should work in a
group for the successful completion the project. Info
Page 8 of 9
RDA Representative MC Representative CE Representative
Page 9 of 9