COST CODE WORK PACKAGE DESCRIPTION RESPONSIBLE DURATION MAN HOURS REMARKS
ILISO CONSULTING
(Days) MM CR FJR GN BK CC LK ML WK LM Mish TBA TBA TBA
Director Director Snr Eng Snr Eng Snr Eng Snr Eng Eng Eng MT MT MT Jnr Tech Jnr Tech Jnr Tech
CHINGOLA TO KASUMBALESA ROAD - 40KM
1 0 0 Project Management/Admin MM
2 MATERIALS INVESTIGATIONS
2.1 0 0 Insitu Investigations & Material sources WK/BK
3 TOPOGRAPHICAL SURVEYS
3.1 0 0 Control Surveys GN
5 0 0 Traffic Analysis IC
5 1 0 Planning BK/MM 6 6
5 2 0 Review draft data received from AVIC BK/MM 16 16
5 5 0 Analyse traffic data BK/MM 16 16
8 0 0 DOCUMENTATION IC
CR Colin Raman Total Hours 392 92 692 560 520 352 608 516 516 356 356 360 360 360
MM Mususeni Mumba Max Allowed 1440 1440 1440 1440 1440 1440 1440 1440 1440 1440 1440 1440 1440 1440
BK Benjamin Kasonso Utilization 27% 6% 48% 39% 36% 24% 42% 36% 36% 25% 25% 25% 25% 25%
FJR Francis Regegzai TACE (USD) 85,885.31 85,885.31 43,880.63 45,049.68 30,906.66 30,906.66 15,780.26 30,993.75 10,367.90 8,023.01 10,920.21 6,875.00 6,875.00 6,875.00
GN Glory Nthara Hourly Rate (USD) 167.48 167.48 76.79 87.85 60.27 60.27 23.67 46.49 15.55 12.03 16.38 10.31 10.31 10.31
ML Mike Lungu
LM Likando Mubita Total Cost (USD) 65,650.73 15,407.83 53,139.44 49,194.26 31,339.35 21,214.33 14,391.60 23,989.16 8,024.75 4,284.29 5,831.39 3,712.50 3,712.50 3,712.50 303,604.62
Mish Misheck Musonda
WK Watson Kashimba
LK Lloyd Kababa
CC Chisha Chanda
PROJECT - CHINGOLA KASUMBALESA ROAD TO PDR
CONTRACT No. OPRC 12 - DIRECT COSTS
A Transport costs
A1 Reconnaisance Day 4 11.72 46.88
A2 Survey team Day 20 11.72 234.38
A3 Insitu investigations Day 20 11.72 234.38
A4 Material sources Day 10 11.72 117.19
A5 Transportation of materials to Lab Sum 1 78.13 78.13
A6 Hydrology/Hydraulics Team Day 4 11.72 46.88
A7 Project management Day 10 11.72 117.19
875.00
B Survey costs
B1 Equipment cost Day 1 253.91 253.91
Sundries/Materials - Danger Tapes,
B2 Picks/Shovels Sum 1 253.91 253.91
B3 Survey Assistants Day 80 31.25 2,500.00
B4 Casuals Day 80 18.75 1,500.00
Total 42,720.31
Su PROJECT - CHINGOLA KASUMBALESA ROAD TO PDR
Summary