Professional Documents
Culture Documents
Unblanced Bid
Unblanced Bid
Unbalanced Bidding
Engineering contract
Contents
Contents ................................................................................................... 1
Introduction ............................................................................................. 2
Unbalanced bids....................................................................................... 4
Changes .............................................................................................. 14
References ............................................................................................. 23
1
The Effects of Unbalanced Bidding
Introduction
An owner and contractor may agree to structure the contract on
specified unit prices for the estimated quantities of the work; Unit
price contracts are somewhat more
common on public works,
engineering, and road building
projects.
The unit prices for a particular item of work will vary from job
to job.
2
The Effects of Unbalanced Bidding
3
The Effects of Unbalanced Bidding
Unbalanced bids
It is usually advantageous for a contractor to use unbalanced
bidding strategies in order to benefit from the uneven distribution
of markup among the project’s component items. The contractor
has to decide on the unit prices of all the project’s activities so
that the summation of the project’s
component items equals to the tender
price. This strategy leads contractor to
price some items with a high markup
and others with a low one in order to
compensate.
Tendering relatively high unit prices
on items scheduled for early completion and proportionately
lower prices for other items is a type of unbalanced bidding. Well-
managed unbalanced bidding can help to obtain monies earlier for
financing the later stages to improve cash flow of the project.
4
The Effects of Unbalanced Bidding
Models
Theoretical Empirical
Theoretical models
There is a lack of exact definition of unbalanced bidding.
Models are one way of making concepts more concrete. Two
types of models have been developed regarding unbalanced
bidding. A first type focuses on assisting practitioners to detect
possibilities for unbalanced bidding in the tendering stage and
how to exploit these. The detection models supports clients’
interests and exploitations models assist contractors in optimizing
the skew.
5
The Effects of Unbalanced Bidding
6
The Effects of Unbalanced Bidding
The model predicts that the most inefficient types i.e. the
slowest contractor, will win the bidding process.
Ewerhart and Fieseler express this as the slow types are being
subsidized. In the extended version of the model, it is shown that
the subsidy to inefficient contractors will force the efficient ones
to bid more aggressively, having a positive effect on client cost.
7
The Effects of Unbalanced Bidding
reverse order from the above model, the buyers will mark up the
price on overestimated timber types and compensate through
bidding a lower price on the underestimated type in order to
secure a high bid ex ante and pay less ex post. Payment is made
by the actual amount of timber and the ex-ante prices.
Empirical studies
The empirical work on unbalanced bidding has focused on
capturing the correlation between differences in prices and
quantities respectively.
Athey and Levin (2001) have data from both oral (N=697) and
sealed (N=63) timber auctions. The study has data on the sellers
estimated volume and proportion of timber type, ex ante bids and
ex post (actual) volume and proportion of timber type.
8
The Effects of Unbalanced Bidding
9
The Effects of Unbalanced Bidding
The actual ex post quantities and “Blue book” prices are also
available.
This data makes it possible to regress quantity overrun on the
dependent variable percentage difference between the winning
and the blue book price. In accordance to what the theory predicts
the correlation is positive, indicating that on average a 10
percentage overrun on quantities will result in a mark-up of
approximately 0.27 per cent.
10
The Effects of Unbalanced Bidding
11
The Effects of Unbalanced Bidding
documents and once the project has been bid, the pressure to start
work may obscure a need to identify and eliminate an unbalanced
bid.
Not only are unbalanced bids difficult to detect in a lump sum
bid, but it can be argued that if the entire project is constructed,
an imbalance will have no effect by the end of the project.
Unfortunately, somewhere along the way the owner may add or
delete work and if it affects the unbalanced work, the change
order process is adversely impacted.
Mathematically Unbalanced Bid
A mathematically unbalanced bid is one in which each bid item
(or breakdown of scheduled values in a lump-sum contract) fails
to carry its proportionate share of the overhead and profit in
addition to the necessary costs for the item. The results are
understated prices for some items and enhanced or overstated
prices for others.
A common example is Front End loading, wherein activities
scheduled to be performed early in the project (such as demolition
or site work) have values encumbered with an excessive
proportion of planned overhead costs and anticipated profit. As
innocuous as it may seem, this “advance payment” characteristic
is objectionable. If excess funds are paid at an early stage of the
contract, the potential exists for an inadequate amount to properly
complete the project and protect the owner’s interests. Another
12
The Effects of Unbalanced Bidding
Costs for other parts of the work were shifted to the unit prices
for the drilling and grouting. When the drilling and grouting work
was eliminated from the contract, the contractor complained that
it had not been fairly compensated for the understated line items
of work that it had performed. In its decision, the Board of
Contract Appeals held the contractor responsible for the
unbalanced nature of the bid.
13
The Effects of Unbalanced Bidding
While this court did not view the unbalanced bid as objectionable
as others have, the costs of the resulting dispute between the
government and the contractor could have been avoided had the
imbalance been detected prior to the award.
14
The Effects of Unbalanced Bidding
15
The Effects of Unbalanced Bidding
Therefore, if the contractor’s costs are the same for the base
contract units and the overrun units, no adjustment is warranted.
In this example, the owners could have benefited from
identification of the imbalance and would not have been obligated
to pay inflated prices for the overrun units. The issues would not
exist if the quantity estimate were accurate.
16
The Effects of Unbalanced Bidding
17
The Effects of Unbalanced Bidding
18
The Effects of Unbalanced Bidding
19
The Effects of Unbalanced Bidding
20
The Effects of Unbalanced Bidding
21
The Effects of Unbalanced Bidding
22
The Effects of Unbalanced Bidding
References
Management and Innovation for a Sustainable Built
Environment ISBN: 9789052693958 20 – 23 June 2011,
Amsterdam, the Netherlands.
Improving the Procurement Process – Unbalanced Bids Jeff
Griffiths, Auditor Jan 07.
A fuzzy-based model for unbalanced bidding in
construction, Abbas Afshar, Iran University of Science and
Technology, Tehran, Iran.
A bid-unbalancing method for lowering a contractor’s
financial risk, SYMEON E. CHRISTODOULOU,
Department of Civil and Environmental Engineering,
University of Cyprus.
The highs and lows of unbalanced bidding models, David
Cattell Bond University.
The Impact of an Unbalanced Bid on the Change Order
Process, Frank A. Manzo.
Course book (engineering contracts)
23