Professional Documents
Culture Documents
Specs - Geotechnical Investigations
Specs - Geotechnical Investigations
To
Shri. B. Yesubabu
Executive Engineer
PIPLMC Division
Maharanipet
Vishakapattnam
Dear Sir,
The undersigned, Dr. B. Janaki Ramaiah, Dept. of Civil & Environmental Engineering, IIT
Tirupati was approached by your office vide your letter cited above to conduct the stability
analysis of the foundation soil and for any need of ground improvement to withstand the loads
due to the self weight of the earthen dam/dykes. Dr. B. Janaki Ramaiah, hearafter referred to
as Consultant, has made site visit to understand the project details and ground conditions. The
site visit was made on 17th June, 2021 During the site visit, three Deputy Executive Engineers
viz Mrs. Supirya, Mrs. Sheshamani and Mr. Pavan Kumar from Water Resources Dept., and
Mr. Swaminanda from contractor agency M/S HES Infra accompanied the Consultant.
The project details and avaiable geotechnical investigations were explained to the
Consultant. It was understood that the proposed reservior for the storage capacity of 3.142
TMC will be formed by two existing natural hills, one on the North side and the other on the
South side. The remaining sides ie., on the East and West sides, the dykes namely Dyke-1
and Dyke-3 will be constructed. Dyke-2 will be constructed to cover the gap between two hils
on the North side. The length of the three dykes is: Dyke-1 = 2100 m, Dyke-2 = 491 m, and
Dyke-3 = 1690 m.
Page 1/2
It was noted that, as of date, the subsoil information was explored through a very limited
geotechnical investations namely three boreholes along Dyke-1, one borehole along Dyke-2
and two boreholes along Dyke-3. In comparison with the proposed heights and lengths of the
three Dykes, it was felt that the available geotechnical investigation is very limited. Baed on
this data, the stabiltiy of foundation ground can not be reliably evalauted. Therefore, the
Consultant recommeded for additional Geotechnical Investigations for collecting comprehesive
subsoil and rock information to reliably evaluate the stability of foundation and to assess the
need for any ground improvement for the safety of the proposed three Dykes.
In view of the above requirements, an online meeting was convened by the Consultant
on 30th June 2021 with the Officals of Water Resources Department and the Contractor
Agency M/s HES Infra. The meeting was to discuss the number of boreholes and their spacing
along each Dyke.
The Technical Specifications for the additonal geotehnical investigations upto the intact
rock and a layout showing the locations of additional-cum-existing boreholes along each Dyke
are enclosed for your information and subsequent action from your side. Please note that the
specifications and number of borehoiles specificed are bare minimum required and may be
increased as per the requirements based on the updated geotechnical investigation data. The
total number of additional boreholes are 36 including: 18 boreholes along Dyke-1, 4 boreholes
along Dyke-2, and 14 boreholes along Dyke-3.
Encl:
(1) Technical specifications for geotechnical investigations in soil & rock
(2) Layout showing the locations of boreholes along each Dyke
Page 2/2
Specifications of Geotechnical Investigations
1. Scope of Work
Main purpose of these studies is to obtain the relevant geotechnical design data including sub-
surface profile, classification, behavior and engineering properties of soil / rock, analysis of field
and laboratory test results and to provide the precise and feasible recommendations of
engineering properties of subsoil and its stability analysis for the earth dam.
This document covers the work required for geotechnical investigation and preparation of report.
The work includes mobilization of necessary equipment, providing necessary engineering
supervisors and technical personnel, skilled and unskilled labor and such other services as
required, to carry out field investigations and tests, laboratory tests and analysis and
interpretation of data and results.
2. Scope of Investigation:
The scope of Geotechnical Investigation for the project includes the following:
a. Conducting boring at the location specified in Annexure-A.
b. Conducting field tests such as standard penetration tests and collecting disturbed and
undisturbed samples from boreholes.
c. Conducting field permeability tests in soils and rocks.
Page 1/6
Specifications of Geotechnical Investigations
IS 11315-1987 : Method for the qualitative description of discontinuities in rock mass (All
Parts)
IS 11594-1985 : Mild Steel thin-walled sampling tubes and sampler heads
IS 13030-1991 : Method of test for laboratory determination of water-content, porosity,
density and related properties of rock material
IS 13063-1991 : Code of practice for structural safety of buildings on shallow foundations on
rocks
IS:13365-2010 : Quantitative Classification system of rock mass-guidelines (All Parts)
5. Field Work
5.1 Boreholes
5.1.1 Sequence of operation for field investigation:
The sequence of operation for the field investigation shall be as under:
a. The location of borehole shall be identified on ground with respect to existing structure,
chainage and GPS coordinates.
b. Drilling, sampling and field testing shall be carried out as per the guidelines given in following
paragraphs.
c. The findings of investigation, including field tests, sampling, visual description of strata
encountered etc., shall be recorded in field borehole log.
d. The SPT samples packed in polythene bags and rock cores, duly labeled shall be preserved in
wooden core boxes.
e. The UDS samples shall be sealed, labeled and preserved as per guidelines given in following
paras.
f. Boreholes shall be terminated as per specifications of this plan. Concurrence of geotechnical
engineer shall be sought before terminating the borehole not satisfying the requirements of
termination as outlined in technical specification.
g. Photographic evidence of machine positioned at particular location shall be collected.
h. Ground water table shall be recorded in each borehole after 24 hrs after completion of
borehole.
i. On termination of borehole, the scanned copy of the field borehole log shall be submitted to
the design team.
j. On weekly basis the samples shall be selected for testing at the laboratory and the information
about the selection of samples for testing shall be submitted to the design team.
k. Selected samples shall be carefully packed and shipped to laboratory for testing.
Page 2/6
Specifications of Geotechnical Investigations
l. On completion of borehole and recoding of observation of the ground water table, the
borehole shall be backfilled.
Page 3/6
Specifications of Geotechnical Investigations
The cutting edge of the sampler shall be tapered at an angle 150 ± 30 degrees. The sample tube / edge
shall be free from rust, pitting, burring or any other defect. The use of oil inside the sampler shall be
limited to the minimum practicable.
Page 4/6
Specifications of Geotechnical Investigations
6. Laboratory works
All laboratory tests shall be performed by qualified and experienced personnel, familiar with and
having access to equipment and facilities for the accurate determination of data necessary.
The tests to be conducted at various locations for properties of soil, etc., are different for cohesive and
cohesion less soils. These are enumerated below and shall be carried out, wherever practicable,
according to soil type.
Laboratory tests shall be carried out in accordance with the procedures described in the relevant BIS
codes of practiced.
a) On Soil Samples:
b) On Rock Samples:
Page 5/6
Specifications of Geotechnical Investigations
7. Reports
7.1 Borehole logs
The borehole log for each hole drilled shall be prepared and shall include the detailed information as
thickness of each stratum; RL of the Ground level at the bore location; Symbolic legend of strata in
accordance with IS 1892 or equivalent incorporating a suitable scale; ground water table; SPT results
for every 15 cm penetration for total 45 cm penetration; sample marking wherever UDS or DS
collected; sample slipped to be reported; a systematic description and classification of all cores by a
geotechnical engineer/engineering geologist in accordance with the Specification, an engineering
geologist's assessment of core recovery, and Rock Quality Designation.
The exploratory hole records shall include all the information, such information having been modified
as necessary in light of laboratory testing and of further examination of samples. Where appropriate, in
situ test results shall be given in the exploratory hole records or otherwise presented in tabular or
graphical form. The detailed records of the laboratory test results shall be presented after the
exploratory hole records or, if appropriate, in a separate volume.
Page 6/6
LEGEND :-
ENT
NM
LIG
E-2 A BH 2 S.NO. DESCRIPTION SIGN.
DYK
ED
POS
PRO
1. NEW DYKE ALIGNMENT
BH 1 2. ORIGINAL DYKE ALIGNMENT
BH 3
BH 1
BH 4 3. M.D.D.L
BH 2
4. F.R.L
BH 3
5. M.W.L
BH 5
6. T.B.L
BH 4 7. SURPLUS WEIR
PREVIOUSLY DONE BORE HOLE
OT SLUICE OF HLC CANAL
8. LEFT, RIGHT & DIST ALIGNMETS
BH 6
DELIVERY CISTERN &
9. PRESSURE MAIN ALIGNMENT
BH 7 CATCHMENT AREA
9.
BH 10
BH 8
102
2 BH 9
900
1 BH 16 BH 11
HYDRAULIC PARTICULARS
800
1
BH 15 BH 12 PEDAPUDI RESERVOIR
700
BH 14 1 BH 13
3.142
600
BH 13 1 PREVIOUSLY DONE BORE HOLE Reservoir Capacity T.M.C
500 BH 14
1
400 +127.00M
1 BH 12 F.R.L
300
PR
M.W.L +128.00M
OP
1 BH 10 BH 11
OS
BH 9
200
ED
1
T.B.L +132.00M
DY
K
100
E-1 1 5.00M
ALI PREVIOUSLY DONE BORE HOLE
Free board
GN
ME
000
1
+103.00M
NT
900 BH 8
M.D.D.L
0
TOP WIDTH OF BANK 6.00M
800 BH 7
0
CATCHMENT AREA 5.180 SQ KM
700 PREVIOUSLY DONE BORE HOLE
0 BH 6
BH 5
600
0
BH 4
500
0
400 BH 3
0
300 BH 2
0
200
0 BH 1
100
0
)
( 2 031M
MEN T 000
LIGN 0
MA INS A
RE
DELIVERY CISTERN
SU
ES
PR
PHASE-1 OF BJRUSS
AL
F.R.L.+127m
T.B.L.+132m
PREPARED & SUBMITTED BY CHECKED BY CHECKED BY
PUMP POUSE-STAGE2
3MOTORS
CHECKED BY APPROVED BY
1DELIVERY MAIN(3M
DIA) SCALE:-H:1:8000 DRG. NO.