Bid Form - Davao Medical School Road
Bid Form - Davao Medical School Road
Contract ID : 22LB0406
Contract Name : Rehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. -
Jct. Circumferential Road), Davao City
Location of the Contract : Davao City
Duly authorized to signed the Bid for and on behalf of NEN Builders and Development Services Corp.
Department of Public Works and Highways (DPWH)
Contract ID : 22LB0406
Contract Name : Rehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. - Jct.
Circumferential Road), Davao City
Location of the Contract : Davao City
BILL OF QUANTITIES
Part No. _____________ Part Description : _______________________
Part Item Description Unit Quantity Quantity Bid Price
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
PART B OTHER GENERAL REQUIREMENTS
B.5 each 3.00 In Words In Words
Project Billboard / Signboard
Six Thousand One Hundred Sixty Eight Eighteen Thousand Five Hubdred Six Pesos
(2- 4'x8' DPWH Billboard & 1-
Pesos and 87/100. and 60/100.
8'x8' COA Billboard)
In Figures 6,168.87 In Figures 18,506.60
B.7(2) Occupational Safety and lumpsum 1.00 In Words In Words
Health Program One Hundred Forty Eight Thousand Two One Hundred Forty Eight Thousand Two
Hundred Pesos and 53/100. Hundred Pesos and 53/100.
In Figures 148,200.53 In Figures 148,200.53
B.8(2) Traffic Management lumpsum 1.00 In Words In Words
Seven Six Thousand Four Hundred Twelve Seven Six Thousand Four Hundred Twelve
Pesos and 70/100. Pesos and 70/100.
In Figures 76,412.70 In Figures 76,412.70
B.9 Mobilization/Demobilization LS 1.00 In Words In Words
Two Hundred Thirty Six Thousand Eight Two Hundred Thirty Six Thousand Eight
Hundred Sixteen Pesos and 96/100. Hundred Sixteen Pesos and 96/100.
In Figures 236,816.96 In Figures 236,816.96
In Words
Sub-Total for this Page: Four Hundred Seventy Nine Thousand Nine
Hundred Thirty Six Pesos and 79/100.
In Figures 479,936.79
Submitted by:
Contract ID : 22LB0406
Contract Name : Rehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. - Jct.
Circumferential Road), Davao City
Location of the Contract : Davao City
BILL OF QUANTITIES
Part No. _____________ Part Description : _______________________
Part Item Description Unit Quantity Quantity Bid Price
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
PART C EARTHWORKS
101(3)b5 sq.m 788.40 In Words In Words
Removal of Actual
Two Thousand Seven Hundred Twenty Two Million One Hundred Forty Seven
Structures/Obstruction, 0.28m
Three Pesos and 91/100. Thousand Five Hundred Thirty Four Pesos.
THK PCCP Unreinforced
In Figures 2,723.91 In Figures 2,147,534.00
102(2) Surplus Common Excavation cu.m. 378.43 In Words In Words
Four Hundred Forty Seven Pesos. One Hundred Sixty Three Thousand One
Hundred Fifty Seven Pesos and 10/100.
In Figures 447.00 In Figures 169,157.10
105(1)a Subgrade Preparation sq.m. 788.40 In Words In Words
(Common Material) Forty One Pesos and 95/100. Thirty Three Thousand Seventy Pesos
and 25/100.
In Figures 41.95 In Figures 33,070.25
PART D SUBBASE AND BASE COURSE
200(1) Aggregate Subbase Course cu.m. 157.68 In Words In Words
One Thousand Two Hundred Seventy Two Hundred One Thousand Four Hundred
Seven Pesos and 44/100. Twenty Six Pesos and 1/100.
In Figures 1,277.44 In Figures 201,426.01
In Words
Sub-Total for this Page: Two Million Five Hundred Fifty One
Thousand One Hundred Eighty Seven
Pesos and 36/100.
In Figures 2,551,187.36
Submitted by:
Contract ID : 22LB0406
Contract Name : Rehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. - Jct.
Circumferential Road), Davao City
Location of the Contract : Davao City
BILL OF QUANTITIES
Part No. _____________ Part Description : _______________________
Part Item Description Unit Quantity Quantity Bid Price
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
PART E SURFACE COURSES
302(2) Emulsified Asphalt Sq.m. 8,510.00 In Words In Words
Three Hundred Twenty Seven Pesos and Two Million Seven Hundred Eighty Six
47/100. Thousand Seven Hundred Fifty Four Pesos
and 77/100.
In Figures 327.47 In Figures 2,786,754.77
310(12)a Bituminous Concrete Surface, sq.m. 4,114.00 In Words In Words
(With Anti-Rutting Additive) One Thousand Two Hundred Twenty Two Five Million Twenty Seven Thousand Nine
Hot-Laid, 30mm thk Pesos and 16/100. Hundred Sixty Pesos and 3/100.
In Figures 1,222.16 In Figures 5,027,960.03
310(12)c Bituminous Concrete Surface, sq.m. 4,114.00 In Words In Words
(With Anti-Rutting Additive) One Thousand Three Hundred Twenty Five Five Million Four Hundred Fifty Two
Hot-Laid, 50mm thk Pesos and 34/100. Thousand Four Hundred Sixty Seven Pesos
and 47/100.
In Figures 1,325.34 In Figures 5,452,467.47
311(1)e3 Portland Cement Concrete sq.m. 788.40 In Words In Words
Pavement (Unreinforced) (0.28 One Thousand Two Hundred Fifty Nine Nine Hundred Ninety Two Thousand Eight
m thick, 3 days) Pesos and 34/100. Hundred Sixty Three Pesos and 98/100.
In Figures 1,259.34 In Figures 992,863.98
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
502(7) Adjusting Manholes each 2.00 In Words In Words
Sixty One Thousand Nine Hundred Fifty One hundred Twenty Three Thousand
Pesos. Nine Hundred Pesos.
In Figures 61,950.00 In Figures 123,900.00
In Words
Sub-Total for this Page: Fourteen Million Three Hundred Eighty
Three Thousand Nine Hundred Forty Six
Pesos and 25/100.
In Figures 14,383,946.25
Submitted by:
Contract ID : 22LB0406
Contract Name : Rehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. - Jct.
Circumferential Road), Davao City
Location of the Contract : Davao City
BILL OF QUANTITIES
Part No. C, F &G Part Description : _______________________
Part Item Description Unit Quantity Quantity Bid Price
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
PART H MISCELLANEOUS STRUCTURES
612(1) Reflectorized Thermoplastic Sq.m. 176.20 In Words In Words
Pavement Marking White One Thousand Five Hundred Fifty Five Two Hundred Seventy Four Thousand One
Pesos and 94/100. Hundred Fifty Six Pesos and 87/100.
In Figures 1,555.94 In Figures 274,156.87
612(4) Reflectorized Thermoplastic Sq.m. 41.11 In Words In Words
Pavement Markings Green One Thousand Seven Hundred Forty Pesos Seventy One Thousand Five Hundred
and 80/100. Sixty Four Pesos and 36/100.
In Figures 1,740.80 In Figures 71,564.36
PART I MATERIALS DETAILS
702(1) Bituminous Materials mt. 3.80 In Words In Words
Three Hundred Sixty One Thousand Eight One Million Three Hundred Seventy Eight
Hundred Eight Pesos and 14/100. Thousand Eight Hundred Seventy Pesos
and 93/100.
In Figures 354,265.36 In Figures 1,346,208.36
In Words
Sub-Total for this Page: One Million Six Hundred Ninety One
Thousand Nine Hundred Twenty Nine
Pesos and 59/100.
In Figures 1,691,929.59
In Words
TOTAL Nineteen Million One Hundred Seven
Thousand Pesos.
In Figures 19,107,000.00
Submitted by:
Contract ID : 22LB0406
Contract Name : Rehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. - Jct.
Circumferential Road), Davao City
Location of the Contract : Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 2,525.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 2,525.00
Contract ID : 22LB0406
Contract Name : Rehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. - Jct.
Circumferential Road), Davao City
Location of the Contract : Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 36,754.15
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 36,754.15
Contract ID : 22LB0406
Contract Name : Rehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. - Jct.
Circumferential Road), Davao City
Location of the Contract : Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 16,050.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 16,050.00
Contract ID : 22LB0406
Contract Name : Rehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. - Jct.
Circumferential Road), Davao City
Location of the Contract : Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL -
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P -
Contract ID : 22LB0406
Contract Name : Rehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. - Jct.
Circumferential Road), Davao City
Location of the Contract : Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 112,050.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 112,050.00
Contract ID : 22LB0406
Contract Name : Rehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. -
Jct. Circumferential Road), Davao City
Location of the Contract : Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 1,700.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 1,700.00
Contract ID : 22LB0406
Contract Name : Rehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. - Jct.
Circumferential Road), Davao City
Location of the Contract : Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 1,700.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 1,700.00
Contract ID : 22LB0406
Contract Name : Rehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. - Jct.
Circumferential Road), Davao City
Location of the Contract : Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 4,288.90
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 4,288.90
Contract ID : 22LB0406
Contract Name : Rehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. - Jct.
Circumferential Road), Davao City
Location of the Contract : Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
Output = 8,510.00 sq.m../1200 sq.m./day = 9.46 say 10.0
SUB-TOTAL 17,000.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 17,000.00
Contract ID : 22LB0406
Contract Name : Rehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. - Jct.
Circumferential Road), Davao City
Location of the Contract : Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
Output = 4,114.00 sq.m./342.60 sq.m./day 12.01 say 13.00 day/s
SUB-TOTAL 69,550.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 69,550.00
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
Output = 4,114.00 sq.m./342.60 sq.m./day 12.01 say 13.00 day/s
Material:
12.01 m.t. Bituminous Concrete Surface Course 313,855.51 3,768,831.24
thickness = 50mm (w/ 5% wastage)
SUB-TOTAL 69,550.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 69,550.00
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)
26.00 kg. Reinforcing Steel Bar 44.00 1,144.00
18.00 lit. Curing Compound 95.00 1,710.00
8.00 lit. Asphalt Sealant 44.00 352.00
28.00 m. Steel Forms (Rental) 61.00 1,708.00
8.00 cu.m. Sand 556.00 4,448.00
14.00 cu.m. Gravel 676.00 9,464.00
132.00 bag Cement 260.00 34,320.00
1.00 pc Concrete Saw 8,000.00 8,000.00
1.00 m. Pipe Sleeve, 2"Ø 97.00 97.00
1.00 lit. Grease/Tar 300.00 300.00
TOTAL Materials Cost P 61,543.00
SUB-TOTAL 67,500.00
Plus % Fringe Benefits
TOTAL Direct Labor Cost P 67,500.00
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL -
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P -
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)
58.00 bag Thermoplastic Paint (White) 1,585.00 91,930.00
6.00 bag Glass Beads 2,310.00 13,860.00
22.00 L Primer 125.00 2,750.00
0.70 cyl LPG (50 kg) 4,500.00 3,171.60
0.35 cyl LPG (12 kg) 1,080.00 380.59
23.00 kg Calsumine 3.50 80.50
TOTAL Materials P 112,172.69
SUB-TOTAL 8,800.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 8,800.00
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)
14.00 bag Thermoplastic Paint (White) 1,585.00 22,190.00
2.00 bag Glass Beads 2,310.00 4,620.00
5.00 L Primer 125.00 625.00
0.16 cyl LPG (50 kg) 4,500.00 739.98
0.08 cyl LPG (12 kg) 1,080.00 88.80
6.00 kg Calsumine 3.50 21.00
TOTAL Materials P 28,284.78
SUB-TOTAL 4,400.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 4,400.00
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 2,300.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 2,300.00
No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 11.82 trips/day
Total DT travel time 38.07
say 11.00 trips/day
=
No. of days to complete hauling = #REF! cu.m. #REF! days
Loader Requirement:
No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 11.82 trips/day
Total DT travel time 38.07
say 11.00 trips/day
=
No. of days to complete hauling = #REF! cu.m. #REF! days
Loader Requirement:
No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 11.82 trips/day
Total DT travel time 38.07
say 11.00 trips/day
=
No. of days to complete hauling = #REF! cu.m. #REF! days
Loader Requirement:
No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 5.21 trips/day
Total DT travel time 86.29
say 5.00 trips/day
=
No. of days to complete hauling = #REF! cu.m. #REF! days
Loader Requirement:
Equipments Required:
GRADER: for spreading 1 unit
Capacity: 60 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 60 x 7 = 420.00 sq.m/day
No.of days required: #REF! / 420.00 = #REF! days say #REF! days
COMPACTOR: 1 unit
Capacity: 30 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 30 x 7 = 210.00 cu.m/day
No. of days required: #REF! / 210.00 = #REF! days say #REF! days
Equipments Required:
GRADER: for spreading 1 unit
Capacity: 60 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 60 x 7 = 420.00 sq.m/day
No.of days required: #REF! / 420.00 = #REF! days say #REF! days
COMPACTOR: 1 unit
Capacity: 30 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 30 x 7 = 210.00 cu.m/day
No. of days required: #REF! / 210.00 = #REF! days say #REF! days
BACK-UP COMPUTATION
5b/8
Equipments Required :
GRADER: for spreading 1 unit
Capacity: 60 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 60 x 7 = 420.00 cu.m/day
No. of days required: #REF! / 420 = #REF! days say #REF! days
COMPACTOR: 1 unit
Capacity: 30 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 30 x 7 = 210.00 cu.m/day
No. of days required: #REF! / 210.00 = #REF! days say #REF! days
BACK - UP COMPUTATION
Quantity:
Volume Multiplier
Cement = #REF! x 3.5 = #REF! bags say #REF! bags
Sand = #REF! x 0.625 = #REF! say #REF! cu.m.
Boulders = #REF! x 0.95 = #REF! say #REF! cu.m.
Quantity:
Volume Multiplier
Cement = #REF! x 4.25 = #REF! bags say #REF! bags
Sand = #REF! x 0.625 = #REF! say #REF! cu.m.
Boulders = #REF! x 0.95 = #REF! say #REF! cu.m.
Department of Public Works and Highways (DPWH)
Contract ID :22LB0406
Contract Name : Rehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. -
Jct. Circumferential Road), Davao City
Location of the Contract Davao City
MANPOWER
Project Engineer 1,000.00 / day
C & M Foreman / Eng'ng Assistant 650.00 / day
Laborer / T&C Helper 350.00 / day
Mason/ Steelman/ Carpenter/ Painter 475.00 / day
Welder/Eletrician 420.00 / day
H.E.O. (Bulldozer/Excavator/Loader/Grader/Crane/Prime Mover) 550.00 / day
Driver (Dumptruck/Water Truck) 475.00 / day
L.E.O. (Compactor, Vibrator, Mixer) 425.00 / day
Submitted by:
Contract ID :22LB0406
Contract NamRehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. - Jct.
Circumferential Road), Davao City
Location of the Contract Davao City
Submitted by:
Contract ID : 22LB0406
Contract Name : Rehabilitation of Road, Davao Medical School Drive, (Jct. Daang Maharlika Rd. - Jct. Circumferential Road), Davao City
Location of the Contract : Davao City
ABC : 19,300,000.00
YEAR
PARTICULAR TOTAL
FIRST QUARTER SECOND QUARTER THIRD QUARTER FOURTH QUARTER
Percentage Accomplishment 100.00% 24.54% 26.18% 28.30% 20.99%
AMOUNT 4,688,032.35 5,001,262.02 5,407,236.08 4,010,469.55
Cumulative Percentage Accomplishment 100.00% 24.54% 50.71% 79.01% 100.00%
AMOUNT 4,688,032.35 9,689,294.37 15,096,530.45 19,107,000.00
Submitted by: