Professional Documents
Culture Documents
Concrete Works Management Procedure Final
Concrete Works Management Procedure Final
Concrete Works Management Procedure Final
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
September, 2016
Page 0
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Table of Contents
Page
Preamble 2
Acronyms 3
List of Tables 4
List of Figures 5
1 Introduction 6
1.1 TACON Overview 6
1.2 The Purpose of this Procedure 7
1.3 The Scope of this Procedure 7
2 Concrete Works 10
2.1 Definition 10
2.2 General Requirements 11
2.3 Deliver, Storage, Handling & Placing Requirements 18
2.4 Concrete Works: High Level Process Map 20
3 Concrete Works: Detail Implementation Guide 23
3.1 Preparatory Works or Services 23
3.2 Form & False Works 31
3.3 Reinforcement Works 36
3.4 Preliminary Installation Works (MEP) 41
3.5 Concreting, Vibrating & Curing 44
3.6 Form & False Works Removal 47
3.7 Monitoring & Evaluation Indicators, Baselines & Measurement 47
Methods
3.8 Monitoring & Evaluation Services 47
4 Roles and Responsibilities 48
5 Adjustment, Revision & Amendment 50
5.1 Adjustment 50
5.2 Revision 50
5.3 Effective Date 50
Page 1
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
6 Annexes 51
Page 2
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Preamble
Whereas, TACON identifies three Key Performance Indicators (KPIs) while monitoring
and evaluating its quarterly reports; namely: Productivity, Cost Overrun & Cash
Flow, that ensure successful completion of its projects;
Whereas, TACON envisions to look after the management of these identified three
KPIs to enhance its efficiency, viz: Increasing Productivity, Minimizing Cost Overrun
and Cash Flow problems;
Whereas, Concrete Works (including its components; namely: Preparatory, Form &
False, Reinforcement, Preliminary Installation and Concreting Works) covers 20 to
40% of the total project cost and the sole trade of works the company engages in
without subcontracting which is identified as “Game Changer”;
Page 3
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Acronyms
BC Building Contractor
CEO Chief Executive Officer
SHE &F Safety, Health, Environment & Fire
EWLAP Eight Weeks Look Ahead Plan
FW Formwork
GC General Contractor
ICT Information & Communications Technology
KPI Key Performance Indicators
MD Managing Director
OPC Ordinary Portland Cement
PCD Project coordination departments
PPC Pozzolanic Portland Cement
PVC Polyvinyl Chloride
QA Quality Assurance
SHE Safety, Health and Environment
SWLAP Six Weeks Look Ahead Plan
TACON Tekleberhane Ambaye Construction Plc
TAF CG Tekleberhane Ambaye Fanta Corporate Group
RW Reinforcement Works
Page 4
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Tables
Table 1-1 Identified Performance Gaps
Table 1-2 Desired Outcomes/Intended Transformation
Table 2-1 Minimum cement content per m3 of concrete
Table 2-2 Standard Mix Recommended for Ordinary Structural
Concrete per 50kg of Cement
Table 2-3 Concrete Works Materials Required per 50kg Bag of Cement
Table 2-4 Compressive Strength of Concrete without Admixtures
Table 3-1 Concrete Works Methods
Table 3-2 Concrete Works Crews
Table 3-3 Concrete Works QA Checklist
Table 3-4 Concrete Works EHS & F Requirement Checklist
Table 3-5 Concrete Works M&E Indicators, Baselines & Measurement
Methods
Table 3-6 Form & False Works Prescribed Re-Use Times
Table 3-7 Form & False Works M&E Indicators, Baselines &
Measurement Methods
Table 3-8 Reinforcement Bars Cross Sections Area in cm2/m
Table 3-9 Reinforcement Cross Section Area in cm2
Table 3-10 Maximum No of Bars in One Row
Table 3-11 Bending Schedule Format
Table 3-12 Form & False Works M&E Indicators, Baselines &
Measurement Methods
Table 3-13 Preliminary Installation Works M&E Indicators, Baselines &
Measurement Methods
Table 3-14 Form & False Works M&E Indicators, Baselines &
Measurement Methods
Page 5
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Figures
Figure 2.1 Concrete Mix
Figure 2.2 Box Size for Concrete Mix Properties
Figure 2.3 Concrete Works High Level Process Map
Figure 3.1 Formwork Detail Process Map
Figure 3.2 Formwork installation guide
Figure 3.3 Reinforcement detail process map
Figure 3.4 Preparatory works detail process map
Page 6
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
1. Introduction
1.1. TACON Overview
1.1.1. Tekleberhan Ambaye Construction (TACON) P.L.C. is a privately
owned GC-1 construction company that has been in business since
1993. Established as a category 6 Building Contractor (BC), success
allowed TACON to be shortly ranked among the top local Grade 1
construction companies in the nation. TACON’s remarkable
achievement in construction and engineering areas has also resulted
in gaining international and nationwide recognitions.
1.1.2. In order to maintain the above achievements and increase TACON’s
competitiveness and operational excellence, TACON has initiated the
preparation and implementation of Company Overhauling Project
whose objectives are to increase customer satisfaction, service and
products quality, operational speed or reduce process time, cost
reduction, enhance innovation, productivity, etc.
1.1.3. The Engineering and Construction sector is one among the focus
areas of the company overhauling project. In this sector game
changers identified to introduce major shift through Context Analysis
and determination of Desired Outcomes & Recommended Intervention
study in relation to the following major operational areas/processes:
Concrete Works (Including Form, Reinforcement, Preliminary
Installation and Concreting works);
Metal (Aluminum) Works Mainly Doors, Windows, curtain wall and
cladding
Finishing Works (Including Wall & Floor Finishing Works);
Sanitary Works mainly Sanitary pipes and Fixtures;
Electrical Works mainly Electrical conduits, boards, fixtures and
Appliances
Subcontract Management, and
Construction Programming.
1.1.4. This Procedure is prepared in order to develop standardized
operational systems and implement one of the identified game
changers/improvement area; namely Concrete Works, efficiently and
effectively.
Page 7
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 8
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Optimization Poor Utilization / Cost Traditional Approach / Bar ICT Based Optimization
Overrun/wastage Bender Led
Preparing & Lifting Rework / Low Productivity Sub Contractor’s Quality Assurance & Inspection
Responsibility only
Placing Rejections / Reworks/ Lack of Competency & Due Engineer Led / Quality Assurance &
Missing Top & Secondary Care Inspection
Reinforcements
Inspection Non Existent / Bar Bender Assumed Consultant Guide Line Preparation / TACON’s
Concrete Works
Optimization, if Poor Utilization / Cost Traditional Approach / Lack Quality Assurance / Inspections
necessary Overrun of Cost Consciousness
Positioning Outlets Reworks Sub Contractor’s Appropriate Positioning / Inspection /
Works
NB: Preliminary Works / Services has not been a practice as a recognized & distinct process for each Game Changers in TACON.
Page 9
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Conformance Error
Cost due to unjustified Reliability & Applicability
No Unjustified delay
Concreting
No Cueing / Idleness
Mixing reworks & / or rejections TACON
Site
Page 10
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
2. Concrete Works
2.1. Definition
2.1.1. Concrete is the most common construction material with strong
compressive strength that can be cast in any desired shapes using
forms and false works, which does not rust, decay, rot and resistant
to wind, rodents, water, fire for longer life with relatively low
maintenance requirements.
2.1.2. Concrete can either be Mass or Reinforced Concrete such that its
strength can be augmented to withstand tensile forces.
a. Mass Concrete can be used in retaining walls and in some
instances as structural members in stepped footings with
minimum reinforcements when placed on loose soils.
b. Reinforced Concrete is a composite structure of Concrete and
Reinforcement bars in order to strengthen Concrete load bearing
characteristics and enable to withstand all kind of forces;
compressive as well as tensile forces exhibited either in the form
of direct actions, and / or moments, and / or torsions, and / or
shear forces under static and / or dynamic states and dead and
/ or live and / or accidental loads.
2.1.3. Concrete can be with different strength such as C5, C10, C15, C20,
C25, C30, C40, etc.
a. C5 Concrete (Lean Concrete) is a mix where the amount of
cement is lower than the amount of liquid present and is ideal as
a base layer where other kinds of concrete are placed on top of it.
It is good for providing a flat bottom in uneven or dirt terrain as
well; hence mostly used below Foundation Structures and under
Masonry Walls or Ground Slabs constructed on compacted earth.
b. C10 & C15 Concrete: Usually they are used with minimum
reinforcement criteria for ground slabs resting directly on hard
cores and steel mesh floor structures with construction joints
that separate from the main structures.
c. C25 & C30 Concrete: Usually they are used for structural
members of Midrise Buildings and Bridges with smaller spans.
d. C40 & Above Concrete: Usually they are used for structural
members of High Rise Buildings and Bridges with bigger spans.
2.1.4. Concrete can either be cast in situ / place, or pre-manufactured.
a. Cast in situ / place concrete is also either premixed concrete at
a batching plant and transported to the work site using transit
mixer and pumped to be placed, or concrete whose ingredients
are transported to the site and mixed just before casting in place.
b. Pre-Manufactured Concrete can either be normal / standard
Mass or Reinforced Concrete, or Pre-Stressed (pre-tensioned or
Page 11
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 12
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 13
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Table 1.1: Minimum Cement Content per m3 of Concrete to Ensure Durability under Specified Conditions of Exposure
Reinforced Concrete Plain / Mass Concrete
Nominal Maximum Max. w/c Nominal Maximum Max. w/c
Exposure Size of Aggregate Ratio Size of Aggregate Ratio
40 30 20 10 40 30 20 10
Mild: e.g. Completely protected against weather, or aggressive
conditions, except for a brief period of exposure to normal
weather conditions during construction 230 260 280 300 0.65 220 230 260 280 0.70
Moderate: e.g. Sheltered from sever rain. Buried concrete and
concrete continuous under water 270 300 330 350 0.55 230 260 290 310 0.60
Sever: e.g. Exposed to sea water, driving main alternate wetting
and drying. Subject to heavy condensation or corrosive fumes. 330 370 400 420 0.45 280 320 340 370 0.50
2.2.3. Concrete Works can be produced using either Designed or Prescribed
mixes. In both cases, standard mixes recommended for the different
grades of Concrete per 50 kg Bag of Cement are given in Table 1.2
below.
Table 1.2: Standard Mixes Recommended for Ordinary Structural Concrete per 50Kg of Cement
Nominal max. size of Aggregate (mm) 40 20 14 10
Concrete
Workability Medium High Medium High Medium High Medium High
Grade
Limits of slump that may be expected (mm) 30 to 60 60 to 120 20 to 50 50 to 100 10 to 30 30 to 60 10 to 25 25 to 50
Total aggregate(kg) 640 550 540 480
C5 Fine aggregate (%) 30-45 30-45 35-50 35-50 - - - -
Vol. of Finished Concrete (m3) 0.312 0.275 0.277 0.252
Total aggregate(kg) 370 330 320 280 - - - -
C15 Fine aggregate (%) 30-45 30-45 35-50 35-50 - - -- -
Vol. of finished Concrete(m3) 0.2 0.183 0.178 0.16 - - -- -
Total aggregate(kg) 305 270 280 250 255 220 240 200
C20 Fine aggregate (%) 30-35 30-40 30-40 35-45 35-45 40-50 40-50 45-55
Vol. of finished Concrete(m3) 0.165 0.155 0.156 0.143 0.146 0.13 0.137 0.121
Total aggregate(kg) 265 240 240 215 220 195 210 175
C25 Fine aggregate (%) 30-35 30-40 30-40 35-45 35-45 40-50 40-50 45-55
Vol. of finished Concrete(m3) 0.147 0.137 0.137 0.127 0.13 0.118 0.124 0.11
Total aggregate(kg) 235 215 210 190 195 170 180 150
C30 Fine aggregate (%) 30-35 30-40 30-40 35-45 35-45 40-50 40-50 45-55
Vol. of finished Concrete(m3) 0.134 0.127 0.124 0.115 0.115 0.106 0.109 0.097
Page 14
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 15
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
f. False works are temporary structures which are meant for supporting
formworks or provide access to build structures. Both formworks and
false works need to be designed to carry loads subjected on it.
Specialist literature need to be visited to design form and false works.
g. Form and False works shall be designed and supervised during
erection by suitably trained professional and erected by qualified
occupational.
h. Form and False works shall be removed slowly and the greater of
either of when 50 % of compressive strength is proved gained or twice
the stress it will be subjected is achieved provided that such earlier
removal will not result unacceptable deflections due to mainly creep
and shrinkages.
i. Form and False works are recommended to be removed within the
following recommended times in normal situations (without using
admixtures:
1. Vertical formworks of beams, columns and walls 18 hours
2. Soffit formworks to slabs 7 days
3. Soffit to beams 14 days
4. Props to slabs 14 days
5. Props to beams 21 days
2.2.11. Concrete is often strengthened with reinforcements forming strong
Concrete - Reinforcement Bond to augment its weak tensile strength
as Reinforcement Bars have high tensile strength.
a. Reinforcements or Re-Bars shall be stored in a clean location, lifted off
the ground, placed on a flat surface with sufficient supports preventing
buckling, sags or bending, different sizes separately and away from mud
and oil so as to be free from factors except minor rust coating that can
be cleaned easily affecting good bonding with concrete.
b. Concrete – Reinforcement Bond is meant for maintaining the
composite action required to transfer load between concrete and
reinforcement along the steel – concrete interface to act as a monolithic
Reinforced Concrete structure.
2.2.12. Reinforcement works shall be understood as the supply, cutting,
bending, preparing and placing of top, bottom and secondary
reinforcement bars, including ties and chairs.
2.2.13. Reinforcement bars used for reinforced concrete structures shall not
have notches of dents or damaged, surface deposits decreasing
bonding properties with concrete, reduced sizes throughout their
lengths and corrosions.
2.2.14. Reinforcement bars can be plain and deformed with sizes varying
from diameter 06mm to 32mm whose weights are 0.222 (ø6), 0.395
(ø8), 0.617 (ø10), 0.888 (ø12), 1.210 (ø14), 1.518 (ø16), 2.00 (ø18), 2.47
(ø20), 2.98 (ø22), 3.55 (ø24), 4.17 (ø26), 4.83 (ø28), 5.55 (ø30) and 6.31
(ø32) kgs/m length.
Page 16
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 17
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
2.2.21. Curing of Concrete is the hydration process that occurs after placing
of concrete with water as damp concrete sets better than dry concrete
to allow concrete to achieve optimal strength, hardness, lower
permeability (enhance water tightness), prevent premature drying and
avoid shrinkage cracking.
a. Curing is the maintenance of a satisfactory moisture content
and temperature in concrete for a period of time immediately
following placing and finishing so that the desired properties will
develop; or,
b. Curing is the process of controlling the rate and extent of
moisture loss from concrete during cement hydration.
c. Improper Curing does also cause scaling, reduced strength,
poor abrasion resistance and cracking; hence the following care
shall be taken:
Maintain the concrete at controlled temperature (> 10 0c) and humidity
(internally > 80 %) within the first seven days.
Hydration and Hardening of the first three days is too critical.
Too much water is counterproductive and too little is deleterious.
Care need to be more for Slabs as they are more affected by improper
curing as compared to other structures.
Surfaces of concrete require curing as they are more susceptible to
insufficient hydration because they dry first.
Special care is required for curing in (a) low water cement ratio concrete
(< 0.4), (b) hot and (c) cold climates.
Curing for a minimum of seven days is recommended as non-cured
concrete can achieve only 40 % of its strength as compared to fully cured
concrete for 180 days.
Concrete cured for seven and twenty-eight days even acquire 72 and 95
% of their strengths as compared to those fully cured for 180 days; hence
keeping concrete moist and curing more than seven days is therefore the
most effective way to increase strength and is advantageous.
2.2.22. Concrete starts to set or hardens within a couple of hours in which
it enters a setting stages and its compressive strength increases over
time (Table 2.1). Admixtures can be used to fasten or retard such
compressive strengths.
Page 18
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 19
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 20
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 21
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 22
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 23
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
the desired shape, lines, levels, and dimensions, and sufficiently brace them both
horizontally and vertically
Make sure proper provisions shall be made for openings, offsets, sinking, keyways,
1 recesses, moldings, chamfers, blockings, screeds bullheads, anchorages, inserts
and other features as required
Form & False works generally involves the following operations during installations
or erections; (a) propping and centering, (b) shuttering, (c) provision of camber, (d)
cleaning and surface treatments with appropriate releasing agents, and (e)
stripping
Ensure joints of formworks shall be tightly sealed against leakage of cement
Ensure false and form works components shall be light in weight, shall not warp
or get distorted when exposed to different situations, shall be free from loose knots
and shall easily be workable with connectors without splitting or any damages
Removal of form and false works shall follow first sides of vertical faces, second
soffit of slabs, and finally soffits of beams, girders or other heavily loaded structures
Removal of form and false works shall be gradually, evenly and carefully made in
order to prevent loads being suddenly transferred to the concrete structure
Form and False works shall not under no circumstances be allowed to be removed
until all the concrete reaches strength of at least twice the stresses to which it may
be subjected at the time of removal of form and false works
Avoid protruding of form and false works connectors into the concrete
Page 24
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Check and review Contract Documents, Site Situations and Availability of designed
sizes requiring changes for existence of Contract Discrepancies that affect delivery
orders or progress of works
Quantify and optimize for preparation purposes based on the fabrication lengths
(12m except for ∅6) using Bending Schedule to minimize wastages
Timely order & deliver; properly handle during transport and storage; supply based
on each structures requirements; and properly clean to ensure effective utilization
or minimize wastages
Prepare reinforcement works as per optimized sizes in bending schedules such as
cutting, bending and tying before placing in the case for footings, beams, columns,
Reinforcement Works
etc
Bending of Bars shall be done only in cold conditions, no heating is permitted and
shall not be straightened
Make sure form and false works are ready and safe to place reinforcement bars
2 Reinforcement bars must be cleaned with dry gunny bags if they are coated lightly
with rust or other impurities before being bound and placing
Accurately place main (Bottom & Top), secondary, tying such as stirrups and other
accessory such as spacers reinforcement works on the form works
Reinforcement works generally involves the following operations; (a) cutting &
bending to optimized sizes, (b) fabricating or tying to designed meshes when
necessary, (c) hauling and / or hoisting, (d) placing, and (e) finishing fabrications
with secondary, tying and accessory reinforcement works
Ensure top and secondary reinforcements are properly and accurately placed
Ensure staggering of laps and anchorages to minimize loss of bonding between the
concrete and the reinforcements
Ensure the right types, numbers, locations, sizes, lengths (including la or
anchorage lengths, curtailments, directions in cases for slabs, walls, etc, welding,
and strengths of reinforcement bars are used and placed
Ensure adequate numbers of chairs, spacers and cover blocks are used and placed
Check and review Contract Documents and Site Situations requiring changes for
existence of Contract Discrepancies that affect delivery orders or progress of works
Prepare Shop Drawings to locate appliance and fixture positions in the concrete
structures
Quantify and optimize for preparation purposes based on the shop drawing
fabrication lengths of pipes and conduits to be placed to minimize wastages
Timely order & deliver; properly handle during transport and storage; supply based
on each structures requirements; and properly clean to ensure effective utilization
Preliminary Installation Works
or minimize wastages
Prepare preliminary installation works as per optimized sizes in shop drawings
before placing
Conduits and Pipes shall be joined and bend with proper connectors, additives and
fibers, and if necessary by heating in case PVC is used
Make sure form and false, and reinforcement works are ready and safe to place
3 preliminary installation works
Accurately place preliminary installation works and tie them on the reinforcement
bars to prevent movement during concreting relocate positions
Properly seal all possible openings and connections in order to prevent entrance of
concrete and blockage thereof
Ensure locations of fixtures and appliances are properly and accurately located
and preliminary installation outlets placed
Fix Scat olla firmly so that shifting of positions of appliances and fixtures is
prevented
Preliminary Installation works generally involves the following operations; (a)
cutting & bending to optimized sizes, (b) hauling and / or hoisting, (c) placing,
joining and tying and (d) finishing with properly fixing and sealing preliminary
installation works
Ensure the right types, locations and sizes preliminary installation works are used
and placed
Page 25
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Check and review Contract Documents and Site Situations requiring changes for
existence of Contract Discrepancies that affect delivery orders or progress of works
Prepare mix proportions and install batching plants
Quantify both concrete and inputs for preparation purposes based on the mix
proportions, production capacity of batching plants and construction program in
order to minimize wastages
Timely order & deliver inputs or concrete; properly handle during transport and /
Concreting Works
or storage; and supply based on each scheduled works and structure requirements
to ensure effective utilization or minimize wastages
Make sure form and false, reinforcement and preliminary installation works are
4
ready and safe to place concreting works
Make sure the batching plant, transit mixer, concrete pump and vibrators are
available and properly operating
Make sure inputs or concrete itself supplied are to the required specification and
appropriately tested and approved for use
Properly mix the concrete as per the Batching Plant type and requirement including
the use of admixtures and transport with transit mixer
Make sure Cube Test samples are taken, slump test checked, and place, level and
vibrate the concrete properly
Make sure appropriate curing is made
3.1.5. Concrete Works Crews are described for the four Detail Process Maps
below (Table 3.2).
Table 3.2: Concrete Works Crews
Items Detail
Crews
Processes
1 Form & False Manpower: FW Forman, Carpenter, Ast. Carpenter and Daily Laborer
Works Machineries: Circular Saw & FW Tools
2 Reinforcement Manpower: Rebar Forman, Bar Bender& Daily Laborer
Works Machineries: Bar Cutting & Bending Machine, Rebar Tools
3 Preliminary Manpower: FW Forman, Carpenter, Ast. Carpenter and Daily Laborer
Installation Machineries: Bar Cutting & Bending Machine, Rebar Tools
Works
4 Concreting Manpower: Concrete Forman, Concrete Masson, Carpenter, Ast.
Works Concrete Mason & Daily Laborer
Machineries: Batching Plant, Transit Mixer, Concrete Pump, Vibrator,
Concreting Tools
3.1.6. Concrete Works Prior Works shall be determined from Head Office
Basic Plans using Project Offices EWLA & Head Office SWLA Plans
and all necessary efforts shall be arranged to ensure their readiness
to execute Concrete Works timely.
3.1.7. Concrete Works Inputs or Resources shall be determined from
Construction Resources Program using Project Offices EWLA & Head
Office SWLA Plans and all necessary efforts shall be arranged to
ensure their delivery or deployment within the Resources Buffers or
Delivery or Deployment Times.
Page 26
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Formwork subject, type, design, methodology & crews defined and accepted
Form & False works carrying capacity & stability checked
Works
1 Form & False works Monitoring & Evaluation baselines and indicators are set (Right
Methodology & Crew assignment, Right Quality & Quantity Delivery timely,
Productivity & Utilization) and gauged
Form & False works are set out and installed properly or as per the design
Form & False works appropriate oiling is applied for easy and safe removal
Preceding work(s) acceptance
Reinforcement works working place is ready
Reinforcement Works
Preliminary Installation works positions, types, sizes, length & accessories are
Preliminary
Page 27
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
2. Ensure proper design, erection and removal of form and false works to avoid
formwork collapse and consequential accidents
3. Avoid as much as possible falling from heights using falling protection equipment
and avoiding slips and trips
4. Avoid as much as possible falling objects and ensure using falling objects protection
equipment
5. Keep dusts produced within acceptable limits
6. Ensure availability of fire precautions requirements fulfillment
2 1. Create awareness regarding EHS&F precaution requirements and / or train crews
Reinforceme
1. Minimizing Hazards from Cement Dust and Wet Concrete such as eyes, noses, troths
and respiratory irritations, skin irritation and chemical burns
2. Guarding Concrete related Machines including log out / tag out during servicing to
minimize accident to Concrete Workers and others
Concreting Works
3. Protect from falling objects from higher places, blocked concrete equipment,
Conveyor belt system, if any to minimize workers’ accidents
4 4. Avoid improper lifting, awkward postures and repetitive motions to minimize
musculoskeletal disorder and strains
5. Beware of hazards associated with concrete works in confined spaces such as heat
stress from concrete mixers; use of entry, work and exit spaces; and avoid silica
exposure using appropriate protective equipment
6. Use Noise or Hearing Protection
7. Ensure Pollution Control to acceptable level if not better
Page 28
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Table 3.5: Concrete Works M&E Baselines, Indicators & Measurement Methods
Item Detail Processes Indicators Baselines Measurement Method
Zigba FW:
Productivity
Others:
Zigba FW:
Utilization Plywood FW:
Form & False
1 Steel FW:
Works
Quantification % Error:
Accuracy Cause:
SHE&F Accident:
Compliance Compliance Rate:
Productivity Preparation:
Placing & Finishing:
Utilization % waste:
Quality % Rework:
Reinforcement Compliance % Delay:
2
Works Cost Overrun:
Quantification % Error:
Accuracy Cause:
SHE&F Accident:
Compliance Compliance Rate:
Productivity Preparation:
Placing & Finishing:
Preliminary Utilization % waste:
3 Installation Quantification % Error:
Works Accuracy Cause:
SHE&F Accident:
Compliance Compliance Rate:
Productivity Mix to Pumping:
Placing & Finishing
Utilization % waste:
Quality % Rework:
Concreting Compliance % Delay:
4
Works Cost Overrun:
Quantification % Error:
Accuracy Cause:
SHE&F Accident:
Compliance Compliance Rate:
Page 29
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 30
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 31
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
3.2.9. Forms & False Works hauling and hoisting (Lifting) as part of TAF
& TACON FW implementation Strategy / Policy shall not be made
manually and using human labor except in some mandatory
situations.
Page 32
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
3.2.10. Forms & False Works shall be hauled and hoisted by Trucks and
Mechanical Pulleys. Necessary care shall be adhered to during hauling
and hoisting of Farm & False Works in order not to damage and
minimize wastes, hence cost overruns.
3.2.11. Forms & False Works shall be set out using surveyors, carpenters
and setting out tools and equipment not to cause chiseling of Concrete
Works.
3.2.12. Forms shall conform to the shape, lines, grade and dimensions
indicated on the drawings.
3.2.13. Forms shall be substantially and sufficiently tight to prevent leakage
of mortar and shall be supported by False Works not to deflect under
the weight of the wet concrete or construction loads.
3.2.14. Forms shall be properly braced or tied together with False Works so
as to maintain position and shape, and insure the safety of workmen
and passerby. Appropriate access shall be provided to facilitate
cleaning and inspection immediately before placing concrete /
concreting.
3.2.15. Forms & False Works shall not be disturbed until the concrete has
hardened adequately to carry its own weight and other loads that may
occur. When the inside forms are erected and reinforcements together
with preliminary installations are in place, the Engineer / Consultant
in charge shall be notified and the outside forms shall not be placed
until works before concreting has been approved.
3.2.16. Forms & False Works shall be assembled in such a manner as to
facilitate their removal without damage to the concrete and
themselves. All forms shall be cleaned and oiled each time they are
used.
3.2.17. Forms & False Works shall be removed carefully to avoid damage and
wastages, hence cost overruns.
Page 33
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
3.2.18. Forms & False works shall be cleaned as soon as they are removed
and stored in appropriate place to ensure re-use to its prescribed
times.
3.2.19. Form & False works need to be inspected before, during and after
concreting and approved before placing of concrete for Stability,
Opening and Setting Out.
3.2.20. Forms & False Works prescribed re-use or re-manufactured times
are as described in Table 3.5 below.
Table 3.5: Form & False Works Prescribed Re-Use Times
Item FW Types Prescribed Re-Use Times
1 Plywood based Form & False Works Up to 20 Times
2 Steel based Form & False Works Up to 30 Times
3.2.21. Form & False Works M&E Indicators, Baselines and Measurement
Methods are as described in Table 3.6 below.
Table3.6: Form & False Works M&E Indicators, Baselines & Measurement Methods
No Detail Process Indicators Baselines Measurement Methods
1 Preparatory Works Prep Reliability No. of Review:
2 Design, Reliability No. of Review:
Optimization & Utilization % Wastage:
Preparation Productivity Design & Opt:
Prep:
3 Hauling, Lifting, Productivity Hauling & Lifting:
Setting Out & SO & Erection:
Erection Rework Cost Overrun:
4 Removal& Re - Use Utilization No. of Re-use:
Wastage / Damage:
Cost Overrun
Page 34
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 35
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 36
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
1.1.7. Reinforcement bars used as stirrups shall be of size ø8 and ø10 for
main bars sizes between ø10 to ø20 and ø22 to ø32 respectively.
1.1.8. Reinforcement Works shall be prepared based on the bending
scheduled and optimization guide determined or shown in sections
3.3.4 & 3.3.8 above in order to minimize wastages, hence cost
overruns.
1.1.9. Reinforcement bars can be replaced by one another using equivalent
areas using Tables 3.8 (for slabs and shear walls) & 3.9 (for others)
below.
Page 37
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 38
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 39
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 40
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 41
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 42
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 43
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 44
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 45
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 46
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 47
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 48
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 49
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Cost
expense bar for 3- and productivity with in standards
Placing as per drawing and 4(three to Minimized rework and improved
Quality four) floors
properly efficiency
No damage to manpower columns,
Safety beams, slabs,
and resources Zero accident
stairs, shear
walls as per
Timely cash in flow drawing Collection of cash from executed
Cash flow
generated within one works
month
Page 50
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Sanitary pipes
Installation of pipes as per to four) floor
Quality No rework and improved efficiency
installation
drawing and standards slabs as per
Safety No damage to manpower drawing Zero accident
Timely cash in flow within one Collection of cash from executed
Cash flow month
generated works
Time No of unjustified delay To install No delay to schedule
Comparing productivity to electrical Wastage minimized, cost of resources
Cost
Electrical conduits
Quality minimized defect, accuracy beams, slabs, improved accuracy level for
level for subsequent works stairs, shear subsequent works
No damage to manpower walls as per
Safety Zero accident
and resources drawing
Timely cash in flow within (1) one Collection of cash from executed
Cash flow month
generated works
Page 51
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 52
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 53
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
B. Formwork
1. Material delivery, storage and handover
Different types of formworks Temporary structure
and accessories shall be department
delivered as per the requirement
of the work.
Formwork and accessories shall Project store
be stored properly and kept
protected from rain and sun to
avoid any damage from
occurring.
Formwork and accessories shall Site Forman and
be kept clean when stored. project store
Formwork and accessories shall Project store and site
be formally handed over to the Forman/subcontractor
person in charge of the work or
subcontractor who execute the
work.
2. Formwork usage, construction and removal
Formwork and accessories shall Project store and site
be transported and used safely to Forman/subcontractor
avoid any damage.
Any cutting of permanent Forman/subcontractor
formwork element shall not be
allowed.
Removal of formwork and Forman/subcontractor
accessories shall be safe and free
from any damage.
C. Reinforcement
General Reinforcement should comply to Office engineer Refer
requirement the requirement of standards standards
Delivery and Reinforcements shall be Procurement
storage delivered from accepted
suppliers and shall meet the
requirements.
Reinforcement shall be stored Project
above the ground and under
shade
Preparation and Placing
Preparation of reinforcement Office engineer
shall be done as per the bar
schedule of the work.
Preparation shall be made with Optimization
optimization to minimize engineer/subcontractor
wastages.
Reinforcement shall be done as Site
per the drawing. engineer/subcontractor
Page 54
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
The following checklists are defined to measure our performance targets during concrete
casting.
Page 55
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Cement
Water
Protected from contamination
Availability & sufficiency of water
Admixture
Type of admixture
Preserved & identified with labels
Stored according to manufacturer’s instruction;
Mix
Availability of batching plant
Required duration to mix the cement & aggregate
thoroughly
/check manufacturer’s instruction of the batching plant
Page 56
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Type of Vibrator
The following checklists are defined to measure our performance targets during works of
formwork erection.
Page 57
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 58
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
The following checklists are defined to measure our performance targets during formwork
removal.
Item Description of parameter for performance Conform Not Not
no measurement ed conforme applicable
d
1 The day concrete casting registered
2 Formwork removal date defined according to the
type of concrete activity(work)
3 No of days required for formwork removal
4 Dismantled formwork cleaned and handled properly
The following checklists are defined to measure our performance targets during works of
reinforcement preparation and placing.
Item Description of parameters for Conformed Not Not
no performance measurement conformed applicable
Identify type of reinforcement bar from
construction program
Fulfillment of quality test
Checked for the right dimension, level &
straightness of formwork.
Method used to keep the formwork in
position /clamp, bolt or anchors/
Well braced and strong enough formwork to
carry the load
Rigidity, wrapping & opening of formwork
joints due to shrinkage of timber.
Coated with release agent for the inside
surface of formwork;
Nature & type of release agent;
Avoiding contact between release agent and
reinforcement / care not to be
visible on the finished work/
Page 59
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 60
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Approximate length of
embedded pipe
Method of crossing in
structural frames
Cover to embedded pipes
Page 61
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Purpose:
To establish minimum safety-related requirements for concrete work, formwork, pre stressed
concrete, precast concrete and reinforcement works.
Concrete Construction
General Requirement
I. Personnel working at heights more than 1.8 m shall be provided with proper work
platforms with a complete guardrail system. Otherwise, a full body harness and shock-
absorbing lanyard shall be worn and securely attached to a lifeline or substantial
anchorage.
II. No construction loads shall be placed on a concrete or masonry structure or a portion
thereof unless the contractor determines that the structure or portion of the structure is
capable of supporting the loads. Structural capabilities shall be verified by structural
engineer.
III. Bulk storage bins, containers or silos shall have conical or tapered bottoms with
mechanical or pneumatic means of initiating the flow of material.
IV. Personnel shall not be permitted to perform maintenance or repair activities on equipment
used for concrete and masonry construction activities (such as compressors, mixers,
screens or pumps), unless all potentially hazardous energy sources have been properly
isolated.
V. All concrete construction activities covered by this manual shall be supervised by a
construction engineer who is knowledgeable and experienced in the type of work to be
performed, including potential hazards of that work and associated hazard control
measures.
Page 62
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 63
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
construction work. Personnel shall not be allowed under or near formwork during
concrete pour operations.
XII. Personnel not engaged in concrete pour operations shall stay clear of the pour area.
XIII. Stripped forms and formwork shall be stockpiled promptly after stripping. Protruding
nails, wire ties, etc., shall be bent over, pulled, cut or other means taken to eliminate the
hazard.
XIV. Placement of concrete or construction materials on partially completed formwork shall
not be permitted.
XV. Tube-and-Coupler Formwork Shoring (see Figure 3.1 )
a. Couplers (clamps) shall not be used if they are deformed, broken, have defective
or missing threads on bolts, or other defects.
b. All tubing used for formwork shall be “embossed.”
c. Connection of tubular members and tightness of couplers shall be checked prior
to placement of concrete.
d. Base plates, shore heads, extension devices and screw jacks shall be in firm contact
with the footing sill and form materials.
Page 64
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Page 65
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
h. Timber and adjusting devices to be used for adjustable timber single post shores shall
be inspected y a form work engineer before erection.
i. Nails used to secure bracing or adjustable timber single post shores shall be driven fully.
The protruding point of any nails shall be bent over, if possible.
j. Single post shores shall not be stacked vertically.
Concrete placement:
I. Loading skips with a capacity of 0.75 m3or larger shall be equipped with a mechanical
device to clear the skips of concrete.
II. Mixers of 0.75 m3capacity or greater shall be equipped with a mechanical device to clear
the skip of materials and protective guardrails installed on each side of the skip.
III. Bull float handles, where they may contact energized electrical conductors, shall be
constructed of nonconductive material or be insulated with a nonconductive protection
sheath.
IV. Manually guided, powered and rotating-type concrete toweling machines shall be
equipped with an automatic control switch (“dead man” switch) that will automatically
shut off the power whenever the operator removes his hands from the equipment handles.
The rotating blades shall be guarded at the top and outer perimeter.
V. Handles of concrete buggies shall not extend beyond the wheels on either side of the
buggy. Knuckle guards are to be installed on buggy handles to protect the worker’s hands.
VI. Pump Crete Systems
a.Pump Crete or similar systems using discharge pipes shall be provided with pipe
supports designed for at least 100% overload (safety factor of at least
two).
b.Hoses in pump Crete or similar systems shall be provided with joint
connectors with a positive locking mechanism and safety chain/pin to
prevent separation of the sections.
c.Pump Crete outriggers shall be in place and outrigger pads used. Outrigger
pads shall be at least three times larger in area than the outrigger float.
d.Pump Crete machines shall maintain minimum clearance distances from
overhead power lines.
Page 66
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Reinforcement work:
General Requirement:
TACON should follow the following procedures to ensure safety while handling reinforcement
work
Work must be done in compliance with the work jurisdictions of the Federal
Democratic Republic of Ethiopia, Ministry of Labor and Social Affairs, occupational
Safety and Health Directive
TACON shall hire professional rebar subcontractors to carry out extensive rebar work
on project sites.
For smaller operations, rebar tying and cutting operations may be assumed by qualified
TACON crew members under experienced Supervision.
Always have a designated storage/staging area for rebar.
Ensure when it is delivered to site that it is inspected for good condition and
appropriate for its application (i.e. the correct length, diameter, strength, etc.)
There is a high risk of sprains, strains and other MSIs for workers who do rebar
regularly. Follow the MSI program’s prevention strategies ( read below)
Always ensure the engineering drawings for rebar placement are readily available
onsite.
Always enforce the usage of appropriate PPE when working with rebar.
Page 67
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
Personnel working with reinforcement shall follow the following safety procedures
Page 68
Document No:
Tekleberhan Ambaye Construction PLC TWR/EC/002
Title: Game Changer procedure for Concrete Issue No: A1 Page No:
works management Issue Date: Sept, 2016
General Requirement:
TACON should follow the following procedures to ensure safety while handling preliminary
sanitary and electrical works
Work must be done in compliance with the work jurisdictions of the Federal
Democratic Republic of Ethiopia, Ministry of Labor and Social Affairs, occupational
Safety and Health Directive
TACON shall hire professional sanitary and electrical subcontractors to carry out the
work on project sites.
For smaller operations In-house staffs may be assumed by qualified TACON crew
members under experienced Supervision.
Always have a designated storage area for sanitary pipes and electrical conduits.
Ensure when it is delivered to site that it is inspected for good condition and
appropriate for its application (i.e. the correct length, diameter, strength, and free of
damage etc.)
Always ensure the engineering drawings for sanitary pipes and electrical conduits
placement are readily available onsite.
Always enforce the usage of appropriate PPE when working with pipes, conduits and
rebar.
Use clear communication when working in teams
Page 69