Method Statement for installation of Control Panels and Revision: A Date: 30/12/2019
Marshalling Panels POI: IFA
Contractor PO No: BH 1048 Page 1 of 9
Attachments:
Method Statement for installation of Control Panels and Revision: A Date: 30/12/2019
Marshalling Panels POI: IFA
Contractor PO No: BH 1048 Page 2 of 9
Title Page No
1. Scope………………………………………… 3
2. Definitions and Abbreviations………………. 3
3. Reference Documents.………………………. 3
4. Responsibilities………………………………. 4
5. Procedure……………………………………... 5
5.1. Pre-installation check……………………. 5
5.2. Material withdrawn from warehouse……. 5
5.3. Support Pre-fabrication…………………. 6
5.4. Description of Indoor installation……… 6
5.5. Description of Outdoor installation……… 6
6. Tools and Equipment’s………………………. 7
7. Inspection and Testing……………………….. 7
7.1 QC Inspection…………………………….. 7
7.2 Red Line Markup (RLM)………………… 8
8. Safety…………………………………………. 8
9. Documentation………………………………... 9
10. JSA (Job Safety Plan)………………………… 9
Document number:
Al Dur II SWRO Project AD2-C2-WO-WZZ-YBB-JEL-34
Method Statement for installation of Control Panels and Revision: A Date: 30/12/2019
Marshalling Panels POI: IFA
1.SCOPE:
This Method statement covers Installation of Control Panels and Marshalling Boxes be carried out in
AL DUR PHASE 2.This method was prepared as guideline for the effective execution of the work,
Construction personnel have to determine the update applicability of this MS in the accordance with
approve construction drawing, actual site condition and specific project requirements.
3.REFERENCE DOCUMENTS:
Method Statement for installation of Control Panels and Revision: A Date: 30/12/2019
Marshalling Panels POI: IFA
4. RESPONSIBILITIES:
a) Site Manager
Overall responsibility for the safe execution of the project and also responsible for overall
co-ordination with other agencies.
b) Construction Manager
Construction manager will be responsible for safe execution of work at site, coordination
with client engineers & progress monitoring.
c) Site engineer
Site engineer will be responsible for the monitoring the work to execute as per approved
drawings and documents and to arrange the resources to the site team to execute the work as
planned smoothly.
d) Site supervisor
Site supervisor will be responsible to implement the installation of work at site as per
approved drawings and monitor the quality& safety aspects and guide the foremen
accordingly.
e) QA/QC
1) Monitoring the site work as per the specification and the related quality procedures.
2) Arranging & coordinating with the consultants for the Inspection of site works
installation as per ITP (if any) for the approval.
3) Maintaining the site inspection and test records for further reference.
4) Raising and closing internal NCR if any
5) Documentation in accordance to approved PQP / ITP
f) Safety Officer
1) The implementation of all the safety measures in accordance with the HSE
Plan and that whole work force is aware of its proper implementation.
Method Statement for installation of Control Panels and Revision: A Date: 30/12/2019
Marshalling Panels POI: IFA
6) Foreman
Foreman will allocate the manpower as required on site and arrange the tools and
tackles as required to execute the job smoothly.
5.PROCEDURE:
The work method to install the above-mentioned panels/Equipment shell be in the following sequence.
5.1 Pre-installation checks
1) Verification of equipment layout from relevant construction drawings.
2) Check drawing are of current revised status.
3) Site released for panel installation.
4) Confirm readiness of the area.
5) Location of the panels/Equipment shall be determined and covered false flouring shall be
removed to expose main structural steel. This will how ever be done in phases depending
on the panel that is going to be installed.
6) Review vendor drawings of the panels and familiarize the installation methods
recommended by the vendor.
7) Exposed floor areas shall be cordoned by means of hazard identity tape.
Document number:
Al Dur II SWRO Project AD2-C2-WO-WZZ-YBB-JEL-34
Method Statement for installation of Control Panels and Revision: A Date: 30/12/2019
Marshalling Panels POI: IFA
1) The supports required, if any, for the installation of marshalling boxes can be done
in the yard or JEL workshop. Support type should conform to approved construction
drawing and site condition.
2) Double channels support supplied by SIDEM shall be placed in position aligned and
installed.
3) Double channels installation will be carried out by ensuring by correct level has
been achieved.
1) Equipment packages shall be unpacked properly and wooden waste or carton waste
should be dump in solid waste.
2) Shortages or damages if any shall be brought to the attention of the
contractor/engineer immediately.
3) Marshalling boxes to be installed as per construction drawing (like double channel
support/structural beam).
4) Control panels/Marshalling Box shall be wall or chassis mounted, equipment with a
sunshade
5) All earthing wires be connected to general safety ground system of the plant.
6) All cables inside the marshalling box/control panel must be dressed properly and
tried-up inside trunk and wire distributed to every terminal as per approved
termination drawings.
7) Each and every loose item shall be properly identified before installation.
8) Inspection of the installation and punch list.
9) RLM markup drawings certified by contractor or engineer.
Document number:
Al Dur II SWRO Project AD2-C2-WO-WZZ-YBB-JEL-34
Method Statement for installation of Control Panels and Revision: A Date: 30/12/2019
Marshalling Panels POI: IFA
7.1 QC Inspection
1) Inspection for Cable Installation. RFI for cable termination activity shall be coordinated
by JEL QA/QC Inspector, who will implement the inspection program and notify all
parties involved in advance of the scheduled dates of inspection at least 24 hours to
enable them to participate and Inspection of the following:
2) Internal and preliminary inspection shall be done before submitting to contractor for
final inspection
3) RFI will be raised for inspection once work and internal inspection is completed and
inspection checklist to be used.
4) Review and inspection for assembly, arrangement, anchoring and grounding.
5) Relevant records shall be signed by all the required parties and originals kept by JEL
QA/QC Department.
6) Acceptance criteria for inspection will be within Project specification and standards.
Required actions will be taken place as per site work condition for remarks and punch
lists noted during inspection.
Document number:
Al Dur II SWRO Project AD2-C2-WO-WZZ-YBB-JEL-34
Method Statement for installation of Control Panels and Revision: A Date: 30/12/2019
Marshalling Panels POI: IFA
4) Ensure that work area is safe and clear from any danger. Identify any hazards and take
necessary preventive actions.
5) All personal should be site inducted by HSE department to prior start work.
6) Job should be monitored at all times.
7) To deploy trained person for electrical work or particular task.
Document number:
Al Dur II SWRO Project AD2-C2-WO-WZZ-YBB-JEL-34
Method Statement for installation of Control Panels and Revision: A Date: 30/12/2019
Marshalling Panels POI: IFA
9. DOCUMENTATION:
All reports issued for information related Glanding, Termination and Testing of control and
Instrumentation cables shall be submitted officially to SIDEM thru transmittal. Documents required as
per Inspection and Test Plan (ITP) shall be signed off with SIDEM Representative.