Professional Documents
Culture Documents
S - Ind-Me-08-Eng-Eng-12-001 Rev000 300 Hrs Maintenance Instruction
S - Ind-Me-08-Eng-Eng-12-001 Rev000 300 Hrs Maintenance Instruction
INSTRUCTION
E48, E53
(CS48)
Instruction Number : s_ind-me-08-eng-eng-12-001 Rev000
Compiled by- Central Technical Team
Released By- Central Technical Leads
Date of Release : 05.05.2012
The 300h maintenance is the first health check (maintenance) of WEC after commissioning. The purpose of
this maintenance is to conduct a thorough check of sitting of mechanical and electrical components after
300hr operation from grid commissioning of WEC.
*During this maintenance all the mentioned checks to be performed without any fail and the deviation report
with pictures to be published to OMS and TSS team.
Safety instructions:
Improper conduct in or around the wind turbine may result in material damage or personal injury. In order to
avoid this, take note of and comply with all safety instructions mentioned in this document. Depending on the
degree of risk, safety instructions are marked with the following symbols:
Bolt Connection:
Tighten all bolt/screw connections to the required torque as Per Torque Table.
Important: Use calibrated Torque wrench only.
Record any deviations, Torque wrench number and next due date of calibration under
‘Miscellaneous/Remarks with checking report in the Life time file.
Every bolt/ screw (M16 and above) after checking in 300hrs maintenance should
be marked with red marker as shown.
Take note of the documents applicable to the respective maintenance items as stated in the
latest document reference list!
Warning signs:
1
While carrying out maintenance, check that all warning signs (as per document s-me-02-ger-
eng-05-001) are present and clearly visible in the entire WEC.
2 a) Visually check the foundation as stated in the annual foundation inspection checking list (s-
m-01-eng-04-002/ Annexure-1).
b) In case of grouting chip out, measure the gap between flange and grouting.
Basic Settings:
Check turbine-specific settings in the “Basic settings” menu on the control cabinet I/O board and
3 compare to the turbine data sticker.
Check in IO Board of Control Cabinet and Nacelle Control Cabinet as per Basic Setting List
given in Annexure-4. Fill in measurement sheet s_ind-e-03-eng-eng-12-002 Rev000.
If the observed values are not as per Basic setting List, correct it and record as per Annexure-4
Grid Voltage:
a) Measure the grid voltage 230V (± 8V).
5
b) Compare the voltage with that indicated on the display.
c) If it is different, adjust the grid voltage in FACTS Power Control.
12 NZM Setting
Check the MCCB 006.Q01 (NZM) setting as per instruction (s_ind-e-02-eng-eng-10-004Rev000)
Tower
Bolt Connection Checking:
13
Check tightness of all bolt connections in Tower and Foundation as per Torque Table
16 Safety Ladder:
IMPORTANT
If the nacelle position and the north direction sticker differ, determine the cause and if
necessary, reset the cable twist limit switch.
Machine House
• While applying rotor lock ensure no body part come near rotating area
• While locking the rotor take care that the lock pin do not damage the rotor
• Enter into rotor only after confirming rotor lock completely set.
Non confirming above point may cause fatal injury/ accident
Bolt Connection Checking:
21
Check tightness of all bolt connections in machine house as per Torque Table
Note:- All earthing point should be metal to metal contact. Bi-metallic contact should be
protected with cold galvanized spray
Rotor lock:
Visually check the entire rotor lock and check whether it works properly. Refer Instruction(s_Ind-
24 me-01-eng-eng-06-001)
a) Check the rotor lock guide plate as per instruction.
b) Check the stopper bolt modification done
c) Check the pulser setting (Limit : 4mm pulsar setting = 2-3 mm gap) Record in checking
report after checking/adjusting
Hydraulic unit:
a) Functional check: ON/OFF the hydraulic motor and check the duration for activation of
brake (Limit :The hydraulic brake should apply within 10 seconds. If not ok then remove
the air entrapped in the lines or clear leakages if any)
25 b) Check for any leakages hydraulic unit
c) Check for any leakages all hydraulic hoses.
d) Check oil level is ok? The level should be at the central position of the inspection
window/Level shown on tank. {If found less then top up the oil upto the level (Renolin
PG46)}.
Record the findings in checking report under the column of ‘Miscellaneous / Remarks’
Fire extinguisher next due date: DD/MM/YYYY.
Assembly parts:
Install stabilizing angle plates as per instruction s_ind-m-02-eng-eng-10-002 Rev 001.
29 Visually check all assembly parts, such as:
a) Holder angle on casing
b) Nacelle platform
c) Nacelle Control cabinet
d) Cabinet brackets
Page 8 of 21 s_ind-me-08-eng-eng-12-001 Rev000
Lights / sockets / earth leakage circuit breaker:
Check the lighting system (illumination) of Entire WEC is in working condition. Such as:
a) Tower Lights
b) Nacelle lamps
c) Spinner lamps,
30 d) Emergency lamps, etc.
e) Check supply in CEE socket outside NCC for 1 phase and 3 phase supply
f) Check F08 for functionality by testing it with trip button
Nacelle Cooling fans:
31 Visually check all fans and their assembly parts.
Install the fan holders as per instruction (s_ind-m-01-eng-eng-07-002 Rev002).
Check fan rotational direction as per mark given on the fan body.
Cables:
a) Visually check all cables and wires in Nacelle Machine house
37 b) Check cables for edge protection at sharp edge and tightness of lug and hood
connecters in Control boxes
If edge protection is not there, provide it.
Main carrier, axle pin:
Visually check the following components for any damages, crack
and corrosion:
a) Main carrier
38 b) Axle pin
Mark identification line between axle pin-> stator Jib-> main carrier
with red color permanent marker as shown
Yaw control:
a) Check and set the 2mm Yaw pulsar gap setting of B01.1, B01.2, B01.3, B01.4, B01.5
and B01.6 between Motor shaft and pulsar in range of 0.7mm-1.0mm.
b) Check movement of nacelle in left and right direction from NCC Yaw control switch.
40 c) Check the Yaw Inverter Operational On/ Off from Yaw parameter in NCC IO-board-2.
d) Check the brake functioning on/off from K03 relay of special function of IO-board-2 NCC
e) Check for smooth yawing in Yaw Inverter mode for 1 turn in any one direction.
f) Check the motor current balance in both master and slave system in Yaw Inverter
Generator:
42
Rotor Head
Bolt Connection Checking:
44
Check tightness of all bolt connections in rotor head as per Torque Table
Note:-
• If leakages observed then inform immediately with photographs to Area Lead and
Central and record in Life Time File.
If GRP joints are not properly sealed, then seal it with pyrmaflex paste.
53
Lock the rotor so that blade A (B, C) stops at 12 o’clock.
Check the lightning protection system for burn marks and damage:
a) Lightning rods
b) Discharge color
c) Lightning protection ring
Check the settings of the lightning protection system:
• Use the “Blade A /B/ C (blade) buttons on the nacelle control cabinet to manually pitch
the blade forward.
Discharge Box
54 After opening the Discharge Box connection from adapter side measure the resistance of each
blade discharge box. It should come in range of 50kΩ + 5kΩ
Rotor blades:
• Visually check the rotor blades for damage with binocular.
56
• Check that the sealing brushes are correctly and securely positioned.
In case of deficiencies complete the rotor blades inspection report and cross off on the checking
report.( s-me-03-ger-eng-06-002)
Pitch control:
• Pitch blade A to the 95° limit switch.
• Check that the blade stops at a 95°± 1° angle.
• Reset the wind turbine control system.
• Pitch the blade in to approx. 1°.
• Listen for abnormal noises!
• The discharge rod does not come in contact with the discharge ring.
• Slowly pitch the blade to the -2° limit switch from pitch control box A.
• Check that the limit switch reacts at an angle of -2° ± 1° and that the blade pitches out to
58 an angle of 97° ± 1°.
• Reset the wind turbine control system.
• Pitch the blade in to approx. 70°.
• Actuate the mechanical overspeed switch:
• Check that the mechanism and the switch itself function smoothly.
• Check that the blade is pitched out in capacitor mode and stops at approx. 92°.
• Status 41:1 (blade B = 41:2; blade C = 41:3) is displayed in the pitch control box.
• Reset the switch.
• Reset the wind turbine control system.
• Repeat the tests for blades B and C.
After Maintenance
Painting and cleaning:
59 Use a vacuum cleaner to clean the stator windings.
- Check for damage and foreign objects.
Paint and clean.
Before taking the running test, clear all the tools, materials and tackles from the
rotating area and kepp it in a safer distance.
60 Turn the nacelle automatically into the wind.
Listen to the wind turbine in idle mode.
Use the quick start button on the nacelle control cabinet to initiate a quick start and listen to the
wind turbine in normal mode.
Press the quick start button again to stop the wind turbine.
WARNING
Before starting work in Tower mounted Transformer structure, ensure that WEC is stopped and
isolated from supply line from VCB. Use earth rod in all three phases and ground in earth pit.
Apply Cold Galvanized spray on unpainted joint part or bi-metallic part in earthing connection
Documentation
File a report copy in the wind turbine folder (LTF) after maintenance.
65 All checking reports .
Rotor Area
Torque (Lubricated
Bolt Connection Bolts
with MoS2)
M12 – 10.9 90 Nm
Supports rotor - spinner fastener And And
M16 – 8.8 160 Nm
Stator support star - stator support
M24 – 10.9 790 Nm
ring
Generator rotor - rotor hub M24 – 10.9 790 Nm
Rotor hub - blade flange bearing M24 – 10.9 790 Nm
Rotor blade - blade adapter M22 – 10.9 570 Nm
Pitch drives M16 – 10.9 230 Nm
Rotor hub - bearing cover M16 – 8.8 160 Nm
SRU fastening bolts M16 – 8.8 160 Nm
Transformer Structure
Concrete Tower to DP Frame M20 A2 281 Nm
OR OR OR
Steel Tower to DP Frame M24 – 8.8 540 Nm
M16 – 8.8 160 Nm
Transformer Frame to Platform
M12 – 8.8 120 Nm
Bolt/screw connections:
After the 300h maintenance use Loctite 290 to secure all bolt/screw connections between
different materials (e.g. metal – GRP) in the rotor area.
Settings in PCB Display
Mains Parameter
Nom. Voltage 230
Min. Voltage 190
Max. Voltage 270
Limitation Voltage 265
Nom. Freq. 50
Min. Freq. 46
Max. Freq. 54
Start Delay 00:00:00
Frequency Limitation parameter
Frequency Limitation Off
Mode Static
Ref. power P‐rated
Fre. Limitation 53Hz
Operation Adjust
Noise Optimisation Off
Settings in PCB IO Board C.C.
Basic Setting
Rated Power 800kW
Site Height above sealevel Location Height as per Micro‐siting
Rated reactive Power Q(rated) 0 kVAr
max. power (SCADA) 950kW
blade version E53/1
Generator version G53/8/G1
stat comp operation Off
fci‐reactive‐power‐control Off
SCADA farm control Off
dp/dt‐ control Off
storm control As per inst. s_ind‐me‐02‐eng‐eng‐08‐001 Rev002
min. start wind speed 2m/sec
max. start wind speed 6m/sec
storm wind (3min average) 28m/sec
storm wind (15sec average) 30m/sec
Pitch parameter
nominal speed (power opt) 29.8
nominal speed (noise opt) 29.5
ini. In nom. Speed 0.0rpm
over speed 35rpm
min. blade angle +1o
min. start blade angle +5o
max. blade angle +92o
adjust min blade angle 600kW
wind direction adj : Lambda 5
Corr. 30o
wind direction adj (blade angle) 0.6 °/ °