Download as pdf or txt
Download as pdf or txt
You are on page 1of 16

PT.AFB_PT.

BORT
WEEKLY REPORT #44
30 Oktober – 5 November 2021

SUMMARY WEEKLY REPORT Week 44


MINE EXPLORATION_AFB_BORT

SAFETY
No. Description Current Week Year to Date
1 Fatality 0 0
Disabling
2 Injury 0 0
3 Medical Aid 0 0
4 Nearmiss 0 0
5 First Aid 0 0

Total Incident/Accident : 0
Total Safety Talk : 1
Total SLA/Inspection : 0
Total Toolbox meeting : 5

Kind of _
Accident/Incident :

Safety Talk Topic : Kerjasama team dan komunikasi dalam bekerja

SLA Topic :

PRODUCTION
Current Week
No Description
Plan Actual
Meter
1 Production 100 195.00
Hole
2 Production 10 12
3 Core Recovery
5 Rig Utilization 66 74.44%

Remark
:

Q-TEAM Page 1
PT.AFB_PT.BORT
WEEKLY REPORT #44
30 Oktober – 5 November 2021

RESOURCES
Current Week
No Description
Plan Actual
1 Manpower 8 6
2 Manhours 470 360
3 LV 1 1

Remark
:

Reported By;

Name/BN : Frans Tandungan


Position :

Q-TEAM Page 2
PT.AFB_PT.BORT
WEEKLY REPORT #44
30 Oktober – 5 November 2021

PRODUCTION METER AFB_BT


W#44

Week 44 BT 02 Cum/day Average


Saturday, October 30, 2021 34.00 34.00 34.00
Sunday, October 31, 2021 0.00 0.00 0.00
Monday, November 1, 2021 40.00 40.00 40.00
Tuesday, November 2, 2021 33.00 33.00 33.00
Wednesday, November 3, 2021 34.00 34.00 34.00
Thursday, November 4, 2021 31.00 31.00 31.00
Friday, November 5, 2021 23.00 23.00 23.00
Total 195.00 32.20 27.86

Drill Rig Per Day 16

Week 44 BT 02 Total
Actual 195.00 195.00
Plan 112.00 112.00
Average/day 27.86 27.86

Daily Production Total Production


50 800.00
700.00
40
Production (m)

600.00
30
Production (m)

500.00
400.00
20
300.00
10 200.00
0 100.00 195.00 195.00
0.00
BT 02
Rig BT 02 Total
Saturday, October 30, 2021
Sunday, October 31, 2021
Monday, November 1, 2021 Actual Rig Plan

Q-TEAM Page 3
PT.AFB_PT.BORT
WEEKLY REPORT #44
30 Oktober – 5 November 2021

SUMMARY Rig Activity


W#44

30-Oct-21 31-Oct-21 1-Nov-21 2-Nov-21 3-Nov-21 4-Nov-21 5-Nov-21


BT 02 Sat Sunday Monday Tue Wed Thur Friday Total %
Transportation 15 15 15 15 15 30 105 2.92
Safety Talk/Meeting 5 30 0 5 5 5 50 1.39
Accesibility 0 0 0 0 0 0 0 0.00
Engine Check 5 15 15 10 10 10 65 1.81
Fueling 0 0 0 0 0 0 0 0.00
Drilling 365 400 420 405 405 285 2280 63.33
Water problem 0 0 0 0 0 0 0 0.00
Waiting Corebox 0 0 0 0 0 0 0 0.00
Pull out rod 30 15 30 45 30 30 180 5.00
Waiting Dozer 30 30 0 0 0 150 210 5.83
Moving 45 35 30 30 35 15 190 5.28
Setting 45 60 30 30 40 15 220 6.11
Resting/Lunch 60 0 60 60 60 60 300 8.33
Technical Problem 0 0 0 0 0 0 0 0.00
Mechanical Problem 0 0 0 0 0 0 0 0.00
Accessories & Mat 0 0 0 0 0 0 0 0.00
Wait pad 0 0 0 0 0 0 0 0.00
Permit & other 0 0 0 0 0 0 0 0.00
Weather Cond. 0 0 0 0 0 0 0 0.00
Wait Crew 0 0 0 0 0 0 0 0.00
Total 600 0 600 600 600 600 600 3600 100.00
Rig Utilization 74.44

Q-TEAM Page 4
PT.AFB_PT.BORT
WEEKLY REPORT #44
30 Oktober – 5 November 2021

Activity Total Percentage


Transportation 105.00 2.92%
Safety Talk/Meeting 50.00 1.39%
Accesibility 0.00 0.00%
Engine Check 65.00 1.81%
Fueling 0.00 0.00%
Drilling 2280.00 63.33%
Water problem 0.00 0.00%
Waiting Corebox 0.00 0.00%
Pull out rod 180.00 5.00%
Waiting Dozer 210.00 5.83%
Moving 190.00 5.28%
Setting 220.00 6.11%
Resting/Lunch 300.00 8.33%
Technical Problem 0.00 0.00%
Mechanical Problem 0.00 0.00%
Accessories & Mat 0.00 0.00%
Wait pad 0.00 0.00%
Permit & other 0.00 0.00%
Weather Cond. 0.00 0.00%
Wait Crew 0.00 0.00%

Rig Activity
Transportation
2.92%
Accessories & Mat Safety Talk/Meeting
0% 3.41%
Technical Problem Mechanical Problem
0.00% 0.00%

Resting/Lunch Accesibility
9,03% 0.00%
Setting
6.11% Engine Check
1.81%
Moving Fueling
5.28% 0.00%

Drilling
63.33%
Pull out rod Water problem
5.00% 0.00%

Q-TEAM Page 5
PT.AFB_PT.BORT
WEEKLY REPORT #44
30 Oktober – 5 November 2021

MANPOWER REPORT W#44

Tanggal
No. B/N Name Position Total
30-Oct 31-Oct 1-Nov 2-Nov 3-Nov 4-Nov 5-Nov
1 Rudy M SUPERVISOR 0 0
2 Petrus DRILLER 10 0 10 10 10 10 10 60
3 Suryo MEKANIK RIG 10 0 10 10 10 10 10 60
4 Daud As s . Dri l l er P 0 P P P P P 0
5 Andarias Masora Dri ver 10 0 10 10 10 10 10 60
6 Andarias Sakti Crew 10 0 10 10 10 10 10 60
7 Simon Salempa Crew 10 0 10 10 10 10 10 60
8 Heizkel Crew 10 0 10 10 10 10 10 60
0
TOTAL MAN HOURS 360
TOTAL MAN POWER 8

Report By

Remark
S : Sick
A : Absent
P : Permission Frans Tandungan / 2014
L : Leave
T : Training
R : Resign

Q-TEAM Page 6
PT.AFB_PT.BORT
WEEKLY REPORT #44
30 Oktober – 5 November 2021

EQUIPMENT REPORT W# 44

RIG
Rig Activity
No. Unit Operator Mechanical Water Rig Remark
Drilling
Problem Problem Utilization
1 BT 02 Petrus 0.00 0.00 63.33 74.44

DOZER

LV
Condition
No. Unit Driver Type Remark
Good Broken
1 DN 8466 RA Andarias Sora Ford SC.2.2 √

WATER PUMP MACHINE


Condition
No. Unit Operator Type Remark
Good Broken
2 HPW 02 YANMAR TF 5.5 √
3 HWP 03 YANMAR TF 85 √

Q-TEAM Page 7
PT.AFB_PT.BORT
WEEKLY REPORT #44
30 Oktober – 5 November 2021

LAMPIRAN WEEK 44

SAFETY TALK (30 Oktober 2021)

Q-TEAM Page 8
PT.AFB_PT.BORT
WEEKLY REPORT #44
30 Oktober – 5 November 2021
TOOLBOX MEETING ( 01 November 2021)

Q-TEAM Page 9
PT.AFB_PT.BORT
WEEKLY REPORT #44
30 Oktober – 5 November 2021
TOOLBOX MEETING ( 02 November 2021)

Q-TEAM Page 10
PT.AFB_PT.BORT
WEEKLY REPORT #44
30 Oktober – 5 November 2021
TOOLBOX MEETING ( 03 November 2021)

Q-TEAM Page 11
PT.AFB_PT.BORT
WEEKLY REPORT #44
30 Oktober – 5 November 2021
TOOLBOX MEETING ( 04 November 2021)

Q-TEAM Page 12
PT.AFB_PT.BORT
WEEKLY REPORT #44
30 Oktober – 5 November 2021
TOOLBOX MEETING ( 05 November 2021)

Q-TEAM Page 13
PT.AFB_PT.BORT
WEEKLY REPORT #44
30 Oktober – 5 November 2021
DHM 69 DHM 55

DHM 28 DHM 29

Q-TEAM Page 14
PT.AFB_PT.BORT
WEEKLY REPORT #44
30 Oktober – 5 November 2021
DHM 67 DHM 41

DHM 68 DHM 40

Q-TEAM Page 15
PT.AFB_PT.BORT
WEEKLY REPORT #44
30 Oktober – 5 November 2021
DHM 39 DHM 38

DHM 27 DHM 26

Q-TEAM Page 16