PERT-CPM Activities

PROBLEM 1
A. PERT Network

12
E F
6

A B 4
START 1
G
1 FINISH
C

G–2 2
D
ML – 4
PT – 6

B. CRITICAL PATH
• A, B, E, F, G = 23 weeks

EXPECTED TIME
= 2 + (4 x 4) + 6/6
= 2 + 16 + 6/6
= 24/6 = 4 weeks (Expected Time)

C. SHORTEST WAY
• A, B, C, E, F, G
PROBLEM 2
A.

ACTIVITY To Tm Tp Te
S, A 2 4 6 4
SU 4 12 20 12
SI 4 8 11.5 8
AI 4.5 20 36 20
UI 4 12 16 12
IN 6 8 12 8.33
NG 8 10 12 10

B.

4 A
20

S I N G
START 8 8.33 10 FINISH

12
12
U

S, A, I, N, G = 42.33
SI, N, G = 26.33
S, U, I, N, G = 42.33
PROBLEM 3
A.
PATH PATH TIME PATH TIME IN WEEKS
A–D–F–G–H 3 + 4 + 4 + 1 +5 17
B–F–G–H 3+4+1+5 13
C–E–F–G–H 7+2+4+1+5 19

B.
A–D–F–G–H 19 – 17 = 2
B–F–G–H 19 – 13 = 6
C–E–F–G–H 19 – 19 = 0

• The slack time of the shortest path is 6.