Professional Documents
Culture Documents
Geotechnical Factual Report On Deatiled Design For Mombasa Special Economic Zone Development Project
Geotechnical Factual Report On Deatiled Design For Mombasa Special Economic Zone Development Project
FOR
Prepared for:
Prepared by:
SOUTHERN ENGINEERING CO. LTD
CONTENTS
1|Page
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
LIST OF FIGURES 3
2|Page
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
LIST OF TABLES 4
3|Page
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
1.0 INTRODUCTION 1
4|Page
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
5|Page
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
6|Page
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
7|Page
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
8|Page
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
9|Page
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
APPENDICES 33
10 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
LIST OF FIGURES
Figure 1 Borehole location plan showing road boreholes and CBR points...................................2
Figure 2 Location plan showing onshore and offshore borehole points........................................3
Figure 3 Disturbed SPTs and bulk soil samples...........................................................................10
Figure 4 Rock Core Box samples.................................................................................................10
Figure 5 Surface preparation........................................................................................................13
Figure 6 Sample extraction..........................................................................................................14
Figure 7 Sample storage...............................................................................................................15
Figure 8 AB Section A-A.............................................................................................................22
Figure 9 QW Section A-A............................................................................................................22
Figure 10 QW Section B-B..........................................................................................................23
Figure 11 QW Section C-C..........................................................................................................23
Figure 12 QW Section D-D..........................................................................................................24
Figure 13 QW Section E-E...........................................................................................................24
Figure 14QW Section F-F............................................................................................................25
Figure 15 QW Section G-G..........................................................................................................25
Figure 16 QW Section H-H..........................................................................................................26
Figure 17 QW Section I-I.............................................................................................................26
Figure 18 Y Section A-A.............................................................................................................27
Figure 19 Y Section B-B..............................................................................................................27
Figure 20 Y Section C-C..............................................................................................................28
Figure 21 Y Section D-D.............................................................................................................28
Figure 22 Y Section E-E..............................................................................................................29
Figure 23 Y Section F-F...............................................................................................................29
Figure 24 Y Section G-G.............................................................................................................30
Figure 25 Y Section H-H.............................................................................................................30
11 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
LIST OF TABLES
12 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
1.0 INTRODUCTION
Following the detailed design and prior to commencement of construction of Shimoni Port
Jetty, Southern Engineering Co. Ltd was commissioned to perform geotechnical investigations
at the proposed Mombasa Special Economic Zone so as to ascertain the sub surface conditions
and close the gap in knowledge of the geologic condition of the area which will allow for
confidence in the detailed design analysis and development of the project including pavement,
foundation design and other auxiliary structures.
This report represents the desktop study of the area together with the factual geological and
geotechnical ground characterization that was made possible by borehole investigation, field
tests and sampling at site.
Whilst every attempt was made to record full details of the strata encountered in the
borehole, techniques of holes formation and sampling inevitably lead to disturbance, mixing or
loss of materials in some soils. The investigation was carried out in accordance with BS10175
Investigation of potentially Contaminated Sites: Code of Practice (2001).
The laboratory testing will be carried out in accordance with recommendations of British
Standards (BS 1377-7) and the American Society for Testing Materials (ASTM) designated D
2938-79.
All information given in this report is based on the ground conditions encountered during the
field work. This report therefore presents a best estimate of the likely ground conditions at
foundations for the structures.
The scope of services included geotechnical investigation through borehole drilling at forty six
(46) borehole locations as shown in the drawing presented in figure 1 and Appendix 1 below
for Geotechnical Investigation to a maximum 46m depths below the existing ground level/sea
1|Page
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
bed level. Figure 1 shows the onshore and offshore borehole location plans across the site.
The scope of work for the Geotechnical Investigation is as summarized as follows:
Boring and sampling of 18No. Boreholes – Offshore
Boring and Sampling of 24No. Boreholes - Near shore/onshore.
Boring and sampling of 4No. Boreholes – Onland/Road
Conduct CBR tests – 7No CBR tests
Laboratory testing of the various different materials of soils and rock collected during
the sampling campaign
Analyses of the in-situ and laboratory tests results to determine the physical and
mechanical properties of soil samples recovered from field boring.
Preparing geotechnical report with recommendation of suitable foundation solutions
to the desired structures to be erected
Figure 1 Borehole location plan showing road boreholes and CBR points
2|Page
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
The field works were executed generally in accordance with the British Standards BS 5930-
1999 “Code of Practice for Site Investigations", B522475-2 "Geotechnical Investigations
and testing", BS1377-2, "Methods of Testing Soils for Engineering Purposes", AASHTO Guide
for Design of Pavement Structures (1993, 2002)
Dongo Kundu Bypass starts in the neighbourhood called Miritini, on the Nairobi–
Mombasa Highway, approximately 11 kilometres (7 mi), and northwest of the
central business district of Mombasa. From there it loops around the western
edge of Mombasa International Airport and ends at a neighbourhood called
Mwache at the water's edge, west of the airport. From Mwache, several bridges
carry the highway across the Port Reitz Bay to Dongo Kundu on the south-side of
the bay. From Dongo Kundu the highway continues in a south easterly direction
3|Page
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
2.1.2.1 Geology
The Geology of Kenyan Coast is dominated by rifting and breakup of the Paleozoic Gondwana
continent and the development of the Indian Ocean. The Proterozoic gneisses of the
Mozambique belt from the basement of intracratonic basin, filled with continental permo-
Triassic classics.
The Geology of the project area mainly comprises:
i. The flat coastal plain which includes; The Island division;
ii. The broken severely dissected and eroded belt that consists of the Jurassic Shale
overlain in places by residual clayey and sandy plateau;
iii. The undulating plateau of sandstone and corals divided from the Jurassic belts by a
scarp fault to the south.
2.1.2.2 Soils
The soils are varied both physically and chemically depending on their geographical location.
The soils found around the project area include:
i. Soils developed on higher level lagoon (Kilindini sands, these are light soils with
very low fertility; they are excessively drained and very deep). Dominant soil in the
project area
ii. Soils in the mangrove swamps, they are poorly drained, very deep and excessively
saline with medium to heavy texture.
iii. Soils (clay soils) developed in shale, they are well to imperfectly drained, shallow to
moderately deep
4|Page
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
To obtain the geotechnical data needed for pavement, foundation and other geotechnical
parameters necessary for the detailed foundation design, different activities not limited to
borehole drilling, visual observations, in-situ tests and sampling were carried out in the field
between 13th December, 2020 and 28th March, 2021.
The field work involved two major phases:
1. Rotary drilling of 46 boreholes with hydraulic feed rig to a minimum depth of
6m and a maximum of 46m and carrying out maximum recovery of drilled
soil/cores
2. Performance in-situ tests comprising of Standard Penetration Test and every
1m up to 20m and 1.5m below 20m depth.
Borehole drilling was undertaken on forty six (46) positions as identified in the layout plan and
marked by the client in the scope of works (see Table 1 and 2 below).
Borehole drilling was conducted up to a minimum depth of 6m and a maximum of 46m depth,
the borehole was drilled by means of GY-150T, XY200 and GY250 Rotary drilling rig with water
flush, then observations and recording phases conducted, following disturbed samples (if
required) was collected. Visual assessment was implemented for all the boreholes. The
samples from the entire borehole were subjected to testing in Third Party laboratory.
Table 1 Showing borehole drilling locations
6|Page
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
7|Page
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
YBH - 23 20.00
YBH - 24 6.00
After drilling and sampling, visual description was performed along with a tape measure
to identify geological profile, colors, geological structure, weathering condition etc., and
recorded in logs as presented in Appendix 2.
The recovered soil/rock cores after coring were examined during preliminary logging after
which the core boxes were clearly labeled and kept in a secured location for further
examination and transportation to the materials laboratory for further testing. The following
parameters were included in the final geological logs as presented in Appendix 2:
i) Rock Quality Designation (RQD)
ii) Solid Core Recovery (SCR)
iii) Fracture Spacing Index (FSI)
iv) Jointing
8|Page
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
HW 113mm, HW 110mm and 127mm casings were also used in all the borehole areas with
incompetent formations.
Sampling details were specified by the engineering geologist on site as per the scope of work.
Geotechnical samples were taken and returned to the laboratory for classification and
Laboratory testing. The samples recovered from drilling were properly identified and stored in
sample bags and core boxes. Geological log description and photographs were carried out
before any sampling for laboratory testing was done.
9|Page
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
During Standard Penetration Test in soil formation at every specific interval, split-spoon
sampler was applied. The basis of the test consisted of dropping with a free fall a standard SPT
hammer of a mass 63.5 kg on to a drive head from a height of 760 mm. The number of blows
(N) necessary to achieve a penetration of the split-barrel sampler of 300 mm was recorded as
the penetration resistance (N).
Then if hard rock surface of which SPT N-value usually more than 50 blow counts with very less
or without any penetration was encountered, the rock coring with diamond bit-core barrel
and/or dry coring sampler was performed at specified range in order to obtain the rock sample
for rock type identification and also for further laboratory testing.
10 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
The locations of the trial pits for CBR tests were identified by the client see table 3 below for
summary of the locations. A total of two trial pits had been fully excavated to 3 metres on the
first day, while the remaining six were excavated on the second and final day. As soon the
sampling was completed all the trial pits were backfilled properly and to satisfaction.
Coordinates
The following gives a brief summary of the soil encountered in each of the trial pit.
11 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
Trial pit No. 4 comprises of yellowish Silty Sand at the sampling depth of 2.0m
Trial pit No. 5
Trial pit No. 5 comprises of brownish to light grey clay at the sampling depth of 2.0m
Trial pit No. 6
Trial pit No. 6 comprises of yellowish brown to light grey fragmented shale particles at the
sampling depth of 2.0m
Trial pit No. 7
Trial pit No. 7 comprises of grey to dark grey fragmented shale particles at the sampling depth
of 3.0m
Trial pit No. 8
Trial pit No. 8 comprises of dark grey fragmented shale particles at the sampling depth of 3.0m
12 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
2. Flatness or
monitoring
the level
Spirit level was
then placed on
the ground to
check for the
flatness to
ensure the
sampler
penetrates perpendicularly into the soil surface.
3. Hammering
The sampler assembly was placed with the cutting edge on the ground, collar and the lid at
the top. Hammering was done carefully until after the sampling mould and collar had fully
penetrated into the ground.
4. Mould assembly and sample extraction
Once the perfect depth was achieved, the process of removing the sampler with the sample
inside started. This was done quite tactfully by excavating around the sampler using a chisel
until the full depth of penetration was reached and finally the sampler inside with the
specimen was removed
13 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
5. Sample Storage
The recovered samples were wrapped using aluminum foil to protect it from in situ moisture
loss and later placed in an airtight bucket then transported to the laboratory for testing.
14 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
15 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
16 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
For the each of the fourteen boreholes drilled, the following parameters have been calculated
as shown in the borehole logs presented in Appendix 2. The descriptions adopted for the
borehole logging were those outlined in BS5930: 1999 Site Investigations.
17 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
For reference relating to descriptions given in the borehole logs tables 6 and 7 below
respectively gives comparable compressive strength and weathering categories descriptions
used in describing the rock strengths in the borehole logs. Where descriptions have been given
in terms of hardness/strengths in the borehole logs, table 6 provides the comparison with BS
5930:1999 rock strengths.
Table 6 Rock strength classification
UNCONFINED
TERM COMPRESSIVE FIELD DESCRIPTION
STRENGTH MN/m²
VERY WEAK <1.25 Gravel size lumps can be crushed between finger and thumb
WEAK 1.25 – 5.00 Grain size lumps can be broken in half by heavy hand pressure
MODERATELY Only thin slabs, corners or edges can be broken off with heavy hand
5.00 – 12.50
WEAK pressure
MODERATELY
12.50 – 50.00 When held in the hand, rock can be broken by hammer blows
STRONG
EXTREMELY
>200.00 Rock rings on hammer blows. Only broken by sledgehammer
STRONG
Where the rocks descriptions have been classified in terms of weathering categories as
presented in the borehole logs, table 7 below provides the comparison provided in BS
5930:1999 weathering categories. The determined grade and weathering category at various
depths is described and indicated in the borehole logs.
18 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
FRESH I Parent rock showing no signs of discoloration, strength loss or any other
weathering effect
SLIGHTLY II Rock may be slightly discolored particularly adjacent to discontinuities which may
WEATHERED be open and have discolored surfaces.
MODERATELY III Rock is discolored, discontinuities may be open and will have discolored surfaces
WEATHERED
HIGHLY IV Rock is discolored, discontinuities may be open and have discolored surfaces with
WEATHERED alteration starting to penetrate inwards, intact rock is noticeably weaker, as
determined in the field, than fresh rock
COMPLETELY V Rock is discolored and changed to a soil but the original fabric is mainly preserved.
WEATHERED There are occasional small core stones. The properties of the soil depend in part on
the nature of the parent rock
RESIDUAL VI Soil derived by in-situ weathering, but retaining none of the original texture or
fabric
For reference the following tables 8 give soil description of the cohesive and granular soils
based on Standard Penetration Tests that were referenced for the soil descriptions in the
borehole logs. The SPTs values obtained in the boreholes at various depths are shown in the
borehole logs.
Table 8 Soil description based on SPT
19 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
- - > 30 Hard
The following tables 9 give strength estimates to the description of the cohesive soils as used
for the cohesive soils descriptions in the borehole logs.
Table 9 Soil shear strength classification
20 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
A total of 46 cored boreholes together with in-situ SPT and laboratory testing have been
carried out to determine the ground conditions for the proposed construction Mombasa
Special Economic Zone.
The findings from the geotechnical investigation show that below a relatively shallow sea
water level, ranging from 0m to 5m in depth over most of the area where the offshore
boreholes are located are very soft compressible marine clay sediments. All the sediments
within the lagoon are very soft silty clays and very low in strength. Sandy and gravel layers are
present but these are thin and intermittent. An organic content to the clay is present together
with thin layers of peat or coal, probably lignite. There is a general increase in the firmness of
the consistency of the soils with depth as they strengthen from the effects of consolidation
and overburden pressures.
Borehole cross sections detailing water depths, SPT results and depths to the top of residual
bedrock together with depths to a presumed sound bearing stratum are included below in
figures 4 to 6.
All depths in the sections refer to m.s.l
21 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
22 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
23 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
24 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
25 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
26 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
27 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
28 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
29 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
30 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
Underlying the lagoon sediments is bedrock comprising horizontally bedded Kipevu Shale with
subordinate sandstone layers. The bedrock tends to be residual for a few meters, but the
transition to more competent and slightly weathered bedrock is rapid and usually occurs
within 4m from the upper Shale/clay overburden contact. There is little variation at the depth
below m.s.l at which defines the contact between the overburden and the underlying Shale
bedrock. To summarize the findings on the profiles:
- Normally consolidated marine sediments comprising very soft silty clays (with
subordinate sandy and gravelly bands) are present, generally starting between 3.0m to
5.0m below m.s.l. Laboratory results describe the samples in the range of sandy Silt,
sandy Clay to fat Clay of intermediate to high plasticity.
- The marine clays have a thickness ranging from 30 to 35m with 30m being an average.
- Standard Penetration Test results are very low until the lower part of the marine
sediments, usually 5 to 6m above bedrock. There are some exceptions in onshore YBH
boreholes where N values start to gradually increases much as 20m above bedrock.
- Underlying the marine Clays is a layer of residual, completely to highly weathered,
extremely weak to very weak, fissile, shale bedrock. It is likely that the strength of this
rock is well below 3MPa. The thickness of the highly to completely weathered shale
beneath the residual layer is usually between 3m to 4m.
- Underlying highly weathered shale is weak to moderately weak and moderately
weathered Shale (British Standard BS5930, UCS equivalent of 5MPa to 15MPa).
Competent end bearing strata, should piles be the option for the foundations, will fit
the description of hard rock or moderately weathered rock. This stratum is met at
depths ranging from 33m to 38m below the sea floor with an average bearing stratum
depth of 35m.
31 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
Typical soil samples recovered during the field work will be subjected to laboratory testing.
These tests will be carried out on collected samples and quantities of the tests determined
depending on the ground conditions.
Geotechnical laboratory testing will be generally carried out in accordance with the
recommendations of BS1377: 1990. Methods of Test for Soils for Civil Engineering Purposes,
Parts 1 to 8. Laboratory testing will be carried out at Geoff Griffiths & Associates Engineering
Laboratory, an accredited Independent Material testing and Inspection Centre.
Laboratory tests not limited to the following tests will be conducted on samples in accordance
with schedules of testing issued by the Engineering Geologist and approved by the Client.
Where required, the following test will be carried out on collected samples and tested in
accordance with the listed standards. Detailed laboratory results will be presented in Appendix
5.
The following sets of tests will be performed for alignment soils (disturbed specimens from the
boreholes), based on the observations from the field work:
33 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
34 | P a g e
Geotechnical Factual Report on Detailed Design for construction of Mombasa
Special Economic Zone Development Project
APPENDICES
35 | P a g e