Professional Documents
Culture Documents
Lec - SCM300 Process Order
Lec - SCM300 Process Order
Page: 100
Order is released, control recipes with parameters for the process control
level can be generated
Material
Resources
Production Version
Master Recipes (BOM)
o BOMs are created through Recipes
Batch management is used in all areas of logistics.
A batch can be traced across the whole supply chain, from the receipt of the
raw material to processing in production and the creation of the final product,
all the way to sales and delivery to the customer.
The procedure involved in process order management can be divided into the
following steps:
Process planning
Process order execution / process management
Order Completion
A control key must be entered for both the phases and the secondary resources.
The control key is used to determine how an operation or phase is to be treated in
Confirmations are entered for phases and secondary resources (however, not for
operations).
You can also define formulas for calculating phase quantities in material quantity
calculation.
120: FIG.
*** Order Release Function (Important)
The process order must have status Released so that the business transactions for process order execution
and process management can be executed.
For this type of staging, you can create transfer requirements manually or
automatically at order release.
RATE ROUTING
Production Line / Assembly Line as Work Center
173
To allow the material to be used in repetitive manufacturing, you set the
Repetitive Mfg Indicator in the material master (in the MRP view).
173:
When you backflush components in repetitive manufacturing, you can define
the issue storage location from which components are to be backflushed
in the status/long text of the BOM item (Production storage location field).
Routing
In repetitive manufacturing, the routing defines the production rate
(quantity per time unit) used to produce materials on production lines.
The production quantities and their capacity requirements are scheduled and
calculated respectively according to the production rate.
The routing therefore provides the basis for lead time scheduling.
It defines how many materials per time unit can be produced on this
production line. In the single operation, you enter the production line as the
work center.
Rate routings are specially designed for the needs of repetitive
manufacturers
Less: Functions and Process Steps in Repetitive Manufacturing
188: FIG.
IMP
PLAN LINE LOADING >> Dispatching Planned orders on the Production Line
Scenario: You have a long production line with a long lead time.
However, the goods issues for the first components at work centers 1-1 and
1-2 are to be posted on-time and not by backflushing with final confirmation
at the end of the production line.
All components used along the production line are usually backflushed during
final confirmation.
If there are long lead times, the goods issues for the components may be
posted much later in the system than when they are actually physically
withdrawn.
In this case, it makes sense to use the reporting point backflush to post
the withdrawal of components (and production activities) at an earlier stage
after operations already completed.
The above example contains the three reporting points that are linked to
operations 10 (work center 1-1), 20 (work center 1-2), and 40 (work center
1-4).
This means that material staging does not need to be planned. Instead,
material that is consumed is replenished immediately using KANBAN.
The supply area is a data object used to organize material flow for
KANBAN.
o It is not an inventory management object.
Therefore, storage locations must be assigned to the
supply areas.
o Inventory management (which is relevant, for example, for
posting goods receipts) takes place at the storage location to
which the supply area is assigned.
Unloading point:
o In external procurement, the supplier often delivers the material
directly to a certain unloading point rather than to the supply
area in production.
o The KANBANS are then transported from this unloading point to
the supply area.
o The unloading point defines where the supplier has to deliver the
material (for example, gate 1).
o It is printed on the KANBAN card or is transferred to the
summarized JIT call.
If the demand source sets the status to empty, the system creates a
replenishment element, instructing the material supply source to deliver.