SAUDI ARAMCO 9000-ENG (10/03) 726-400 (ID/PID)

SATIP No. APPROVED DATE DISCIPLINE:


SAUDI ARAMCO TYPICAL INSPECTION PLAN
SHOP FABRICATED STORAGE TANK INSTALLATION
SATIP-D-109-01 11-Apr-04 Mechanical
(UL-142 or API SPEC 12F & 12P)
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

CHECKLIST INSPECTION RESPONSIBILITY


ITEM and/or QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. TEST RECORD SAUDI
CNTRCTR
RECORD ARAMCO

1.0 DOCUMENT REVIEW

Tank Data Sheet & Safety Instruction


1.1
Sheet
SAIC-D-2014 RH1 RH1

2.0 MATERIAL RECEIVING

External Visual Inspection and


SAIC-D-2015
2.1 Verification of Tank and its external W1 W1
appurtenances

Internal Visual Inspection Tank and its SAIC-D-2016


2.1
internal appurtenances
W1 W1

Fabricated Piping Spool Inspection (if


2.2 Refer to SATIP-L-350-01
applicable) at nozzles.

2.3 Storage, Handling & Tank Preservation SAIC-D-2005 W1 S


Refer to the respective SATIPs for Electrical &
Verification & Visual inspection of vendor
2.4 Instrumentation: ( SATIP-P-113-01, P-515-01, J-100-01,
supplied electrical & instrumentation
J-200-01, J-300-01, J-902-03)

3.0 INSTALLATION

3.1 Concrete Placement Refer to SATIP-Q-001-02

Trench Preparation and backfilling for


3.2 Refer to SATIP-S-070-01 & SATIP-A-114-01
Buried Tanks

3.3 Grounding Refer to SATIP-P-111-01

3.4 Pre-Installation Inspection SAIC-D-2006 H1 W1


Cathodic Protection (if required for tank Refer to SATIP-X-600-01, SATIP X-600-02 or J-500-
3.5
bottom an/or internal shell) 01(Internal CP) as applicable

3.6 Inspection of buried tank installation SAIC-D-2017 H1 H1

Page 1 of 4
SAUDI ARAMCO 9000-ENG (10/03) 726-400 (ID/PID)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
SHOP FABRICATED STORAGE TANK INSTALLATION
SATIP-D-109-01 11-Apr-04 Mechanical
(UL-142 or API SPEC 12F & 12P)
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

CHECKLIST INSPECTION RESPONSIBILITY


ITEM and/or QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. TEST RECORD SAUDI
CNTRCTR
RECORD ARAMCO

Under-Tank Leak detection & Sub-grade


3.7
Protection (if required)
SAIC-D-2018 H1 H1
SAIC-D-2019
SATR-D-2001
3.8 Tank Erection (above ground)
OR
H1 W1
SATR-D-2002

3.9 Grouting (if required) Refer to SATIP-Q-010-01

Refer to the respective SATIPs for Electrical &


Hook-up of vendor supplied electrical &
3.10 Instrumentation: ( SATIP-P-113-01, P-515-01, J-100-01,
instrumentation
J-200-01, J-300-01, J-902-03)

3.11 Piping Installation Refer to SATIP-L350-01

3.12 Tank Trim installation SAIC-D-2020 H1 W1

Refer to the respective SATIPs for Electrical &


Verification & Visual inspection of vendor
3.13 Instrumentation: ( SATIP-P-113-01, P-515-01, J-100-01,
supplied electrical & instrumentation
J-200-01, J-300-01, J-400-01, J-902-03)

3.14 Block valves installation Refer to SATIP-L-008-01

Relief/Vacuum Valve installation


3.15 Refer to SATIP-J-600-01
inspection
See Note 1 of the General Notes and minimum of 10%,
3.16 Flange Joint Inspection SAIC-L-2014 W1 W2 thereafter.

3.17 Structural Attachments & Access Refer to SATIP-M-001-01

External Coating, Color coding &


3.18 Refer to SATIP-H-002-03 OR H-002-05 as applicable
Identification

4.0 PRE-COMMISSIONING

SAIC-D-2011
4.1 Tank Closure Inspection
SATR-D-2003
H1 H1
Instrumentation and electrical pre- Refer to the respective SATIPs for Electrical &
4.2
commissioning Instrumentation

Page 2 of 4
SAUDI ARAMCO 9000-ENG (10/03) 726-400 (ID/PID)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
SHOP FABRICATED STORAGE TANK INSTALLATION
SATIP-D-109-01 11-Apr-04 Mechanical
(UL-142 or API SPEC 12F & 12P)
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

CHECKLIST INSPECTION RESPONSIBILITY


ITEM and/or QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. TEST RECORD SAUDI
CNTRCTR
RECORD ARAMCO

Punch Listing/Final Inspection of Tank SAIC-D-2021


4.3
Installation SATR-A-2011
H1 S
SA-6133
4.4 MCC Punchlisting
(FEIL)
H1

4.5 Tightness test or Service test W1 W1 Refer to SATIP-A-004-05

Page 3 of 4
SAUDI ARAMCO 9000-ENG (10/03) 726-400 (ID/PID)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
SHOP FABRICATED STORAGE TANK INSTALLATION
SATIP-D-109-01 11-Apr-04 Mechanical
(UL-142 or API SPEC 12F & 12P)
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

CHECKLIST INSPECTION RESPONSIBILITY


ITEM and/or QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. TEST RECORD SAUDI
CNTRCTR
RECORD ARAMCO

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust
1
the levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3
representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4
attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
W1 100% Witness Inspection/Test H2 Sample Hold Point for QC Inspection or Test RH1 100% Review and Approval of Documents
W2 Sample Witness Inspection/Test R1 100% Review of Documents RH2 Sample Review and Approval of Documents
H1 100% Hold Point for QC Inspection or Test R2 sample Review of Documents S Surveillance