(BOQ AND SPECIFICATIONS FOR MED UNITED -TATIPAKA)

Project : INTERIORS OF PHARMACY& LAB

SR. NO. ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT

1 Dismantling
a Dismantling of Brick wall and dumping of debris outside store Sft 300.00 30.00 9000.00
b Removal of debris from site ( store front ) to dump yard Each 2.00 1000.00 2000.00
c Site Maintenance & Cleaning & handover L.S 1.00 10000.00 10000.00

2 Civil works
a Construction of 150mm brick work 150mm x 200mm x600mm ACC blocks with 2'' CC bed with 2nos of 8mm Sft 350.00 180.00 63000.00
b Construction of 100mm brick work 100mm x 200mm x600mm ACC blocks with 2'' CC bed with 2nos of 8mm Sft 120.00 170.00 20400.00
c Plastering on existing walls and column with cement motor to spong finish. Sft 800.00 45.00 36000.00
Providing & laying brick batting / cinder filling upto 6'' - 9'' with Cinder or light weight bricks and screeding the
Sft 65.00 100.00 6500.00
d top surface with water proof chemical and plain cement motor.

3 Tiling Works
Providing and laying of Vitrified tiles flooring of size 600 x 600mm in paper joint laid with latictere / cement
a Sft 640.00 100.00 64000.00
motor upto 2'' ( Inside store )
Flooring on steps & entrance with anti skid rough tiles ( store front)
Sft 175.00 130.00 22750.00
b
c Skirting for the above with 75mm Vitrified tile Rft 110.00 50.00 5500.00
d providing and laying of flooring in wash rooms with 12'' x 12'' anti skid Vitrified tiles with cement motor ( basic Sft 30.00 90.00 2700.00
e Wall cladding in wash rooms with 24''x 12'' vitrified tiles with grouting the joints to matching colour grout. Sft 110.00 90.00 9900.00
f Granite on lab platform including concrete Sft 25.00 450.00 11250.00

4 Gypsum Works
a Ceiling - Providing & fixing Gypsum board false ceiling with Gypsteel MR Ultra frame work for hangers, main Sft 550.00 65.00 35750.00
b Side verticals-Providing and fixing of 2'' to 9'' verticals in gyp board with frame work for steps, coves etc.. Rft 150.00 45.00 6750.00
Providing opaque gypsum partitions with Gypsteel frame work with vertical studs @ 600mm CC, Cladding with
d Sft 162.00 120.00 19440.00
12.5mm gyp board on either side and joints finished with paper tape and joint compound. the partition to

5 Glass Partitions & Doors


a Fully Glazed partitions with Aluminium profiles of size 10mm toughened glass with rubber beading. Rate Sft 245.00 400.00 98000.00
b Providing and fixing of patch fitted 12mm toughened glass doors with complete Dorma hardware like floor Nos 2.00 32000.00 64000.00
c Supply and fixing of WPC door with out vision panel, with architrive and complete hardware. Size:900 x Nos 2.00 18000.00 36000.00
d Supply and fixing of PVC door with door frame with out vision panel, architrive and complete hardware. Nos 1.00 6000.00 6000.00

6 Plumbing & Sanitary


Providing & fixing of floor mount EWC with cistern and with all accessories ( seat cover, angle
a Nos 1.00 7500.00 7500.00
valve, PVC connection etc. parryware make
b Providing & fixing of health faucet with 2 in 1 bib cock - Parryware make Nos 1.00 1500.00 1500.00
c Providing of pedestal basin with all necessary accessories ( angle valve, bottle trap, PVC connections, Nos 1.00 5000.00 5000.00
d Providing and fixing steel sink with long body bib cock bottle trap and other accessories Nos 1.00 5000.00 5000.00
e 200 litres water tank sintex Nos 1.00 6000.00 6000.00
f Concealed pipelines for wash room L.S 1.00 6000.00 6000.00
g External pipelines,septic tank connection & water inlet to decied at later stage L.S 1.00 15000.00 15000.00

7 Painting
a Painting up of the ceiling with three coats of plastic emulsion paint for interiors including 2 coats of JK wall Sft 1800.00 25.00 45000.00

8 Lighting & electrical


a 15W LED Luminaries with Translucence Diffuser & all the required accessories as required. Nos 12.00 1200.00 14400.00
b 22w led tube lights Nos 8.00 500.00 4000.00
b 9" dia Exhaust fan with all the mounting accessories like connecting wires, nuts & bolts, 3 core cable, Nos 2.00 2500.00 5000.00
c Supply & Fixing of 1200mm Ceiling Fan of Crompton Make Nos 3.00 2800.00 8400.00
d Strip lights in cove Rft 100.00 65.00 6500.00
e Wiring for Ceiling lights, sockets swithes, fans, AC & Misc as required L.S 1.00 50000.00 50000.00

9 Air conditioners
a 1.5 ton hi wall ac in pharmacy - voltas make Nos 1.00 34000.00 34000.00
b 1.0 ton hi wall ac in opd room - voltas make Nos 1.00 31000.00 31000.00
c Core cutting in brick walls Nos 2.00 600.00 1200.00
d Extra copper & drain piping Rmt 10.00 900.00 9000.00

10 ACP cladding in Elevation


a Straight, Fixing of Aluminum Composite panel (Make :4MANN 4mm x 0.25 x 0.25 work using. Complete work Nos 320.00 275.00 88000.00
b Straight, Fixing of Aluminium framing for acp support Kgs 450.00 75.00 33750.00

11 Furniture
a Pharmacy counters in metal & glass Nos 1.00 45000.00 45000.00
b Pharmacy racks in Slotted angle M.S Racks and glass shelves. Sft 420.00 450.00 1,89,000.00
c Doctor cabin front and side table (4'x2' & 3'x1'3") Nos 1.00 22000.00 22000.00
d Reception table in m.s framing powder coating paint Nos 1.00 26000.00 26000.00
e Metal examination bed 6'-0"x 2'-0" with metal storage underneath Nos 0.00 38000.00 0.00

12 Networking & cctv cabling


a Cat-6 Cable Box supply & installation Box 1.00 7800.00 7800.00
b Cat-6 Information Outlet for Voice/data Nos 6 275.00 1650.00
c Cat-6 Patch Cord 3ft for Voice/data Nos 6 225.00 1350.00
d Face Plate 4 IO, Duplex or single Nos 6 100.00 600.00
e Cat-6 24 port 1U jack panel (loded) for Voice Nos 1 5500.00 5500.00
f Cat-6 24 port 1U jack panel (loded) for Data Nos 1 5500.00 5500.00
g 14U Closed Rack with Front Glass Nos 1 20000.00 20000.00
h Door,Shelf,Fans
CCTV Cabling with Hard ware
Cat-6 Cable Box Box 1 7800.00 7800.00

13 Pest control treatment L.S 1.00 8000.00 8000.00

1245390.00

Total A ( MS. Slotted angle rack shelves) 1245390.00

GST 18 % extra

Terms & Conditions


1 cctv camera, chairs not considered, All sanitary ware are of parryware make basic range

Terms of payment: 40% of the basic work order value as Advance along with work order, 30% against
2 Civil & Gypsum works and frame works, 20 % against supply of furniture and air conditioners,10% on
virtual completion of job.
3 The Quotation is valid for 30 days only.
4 Delivery time line is 45 days from the date of P.O Released along with advance amount.