8 Story Residential Buidling Classic Schedule Layout 27-Jun-22 22:30

Activity ID Activity Name Duration Start Finish 2021 2022 2023


A S Oct N D J F M Apr M J Jul A S Oct N D Jan F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct N D
8 Story Resident
Residential Buidling 611 01-Jun-22 01-Feb-24

Procurement Sc
Schedule 105 01-Jun-22 13-Sep-22 13-Sep-22, Procurement Schedule

Construction 510 01-Jun-22 01-Feb-24

Recovery Schedule 0 01-Jun-22 01-Jun-22 01-Jun-22, Recovery Schedule


A1000 Project Start 0 01-Jun-22 Project Start
PHASE - 03 (Roof - Level
L 7) 161 01-Jun-22 05-Dec-22 05-Dec-22, PHASE - 03 (Roof - Level 7)
Roof 161 01-Jun-22 05-Dec-22 05-Dec-22, Roof
Civil Works 161 01-Jun-22 05-Dec-22 05-Dec-22, Civil Works
FINISH - L9 - 1 Block Masonry 20 01-Jun-22 23-Jun-22 Block Masonry
FINISH - L9 - 2 Plaster Works 20 01-Jun-22 23-Jun-22 Plaster Works
FINISH - L9 - 3 Bathroom Water Proofing 20 01-Jun-22 23-Jun-22 Bathroom Water Proofing
FINISH - L9 - 4 Bathroom Wall Tile 20 18-Jul-22 09-Aug-22 Bathroom Wall Tile
FINISH - L9 - 5 Bathroom Floor Tile 20 21-Jul-22 12-Aug-22 Bathroom Floor Tile
FINISH - L9 - 6 Dry Area Floor Tiles 20 10-Aug-22 01-Sep-22 Dry Area Floor Tiles
FINISH - L9 - 7 False Ceiling Suspensions 20 13-Aug-22 05-Sep-22 False Ceiling Suspensions
FINISH - L9 - 8 Wooden Door Installation 20 16-Aug-22 07-Sep-22 Wooden Door Installation
FINISH - L9 - 9 False Ceiling Sheet Fixing 20 06-Sep-22 28-Sep-22 False Ceiling Sheet Fixing
FINISH - L9 - 10 Lobby Floor Tiling 20 11-Oct-22 02-Nov-22 Lobby Floor Tiling
FINISH - L9 - 13 Balcony Tiles 20 03-Nov-22 25-Nov-22 Balcony Tiles
FINISH - L9 - 11 Lobby Ceiling 20 09-Nov-22 01-Dec-22 Lobby Ceiling
FINISH - L9 - 12 Paint Work Final Coat 20 11-Nov-22 03-Dec-22 Paint Work Final Coat
FINISH - L9 - 14 Installation of Mirrors 20 12-Nov-22 05-Dec-22 Installation of Mirrors
Electrical Works 156 03-Jun-22 01-Dec-22 01-Dec-22, Electrical Works
1st Fix 20 03-Jun-22 25-Jun-22 25-Jun-22, 1st Fix
ELECT - L9 - 1 Installation of Electrical Conduits and Back Boxes 20 03-Jun-22 25-Jun-22 Installation of Electrical Conduits and Back Boxes
2nd Fix 133 07-Jun-22 08-Nov-22 08-Nov-22, 2nd Fix
ELECT - L9 - 2 Wiring of Circuits and Point Wiring 20 07-Jun-22 29-Jun-22 Wiring of Circuits and Point Wiring
ELECT - L9 - 5 Installation of Power Cables 20 10-Jun-22 02-Jul-22 Installation of Power Cables
ELECT - L9 - 3 Fire Alarm Cabling 20 14-Sep-22 06-Oct-22 Fire Alarm Cabling
ELECT - L9 - 7 CCTV System Cabling 20 07-Oct-22 29-Oct-22 CCTV System Cabling
ELECT - L9 - 8 CATV Cabling 20 12-Oct-22 03-Nov-22 CATV Cabling
ELECT - L9 - 9 Video Intercom System Cabling 20 17-Oct-22 08-Nov-22 Video Intercom System Cabling
3rd Fix 150 10-Jun-22 01-Dec-22 01-Dec-22, 3rd Fix
ELECT - L9 - 4 Installation of Switches, Sockets 20 10-Jun-22 02-Jul-22 Installation of Switches, Sockets
ELECT - L9 - 6 Distribution Board & UPS Installation & Termination 20 24-Jun-22 16-Jul-22 Distribution Board & UPS Installation & Termination
ELECT - L9 - 10 Installation of Ceiling Mounted Lights Fixtures 20 09-Nov-22 01-Dec-22 Installation of Ceiling Mounted Lights Fixtures
Plumbing Works 85 24-Jun-22 30-Sep-22 30-Sep-22, Plumbing Works
1st Fix 20 24-Jun-22 16-Jul-22 16-Jul-22, 1st Fix
PLUMB - L9 - 1 Water Supply Piping 20 24-Jun-22 16-Jul-22 Water Supply Piping
PLUMB - L9 - 2 Testing of Pipe 20 24-Jun-22 16-Jul-22 Testing of Pipe
2nd Fix 20 08-Sep-22 30-Sep-22 30-Sep-22, 2nd Fix
PLUMB - L9 - 3 Installation of Fixtures 20 08-Sep-22 30-Sep-22 Installation of Fixtures
HVAC Works 87 28-Jun-22 06-Oct-22 06-Oct-22, HVAC Works
1st Fix 20 28-Jun-22 20-Jul-22 20-Jul-22, 1st Fix
HVAC - L9 - 1 Marking & Fixing of Supports 20 28-Jun-22 20-Jul-22 Marking & Fixing of Supports
2nd Fix 20 14-Sep-22 06-Oct-22 06-Oct-22, 2nd Fix
HVAC - L9 - 2 Installation of Split AC 20 14-Sep-22 06-Oct-22 Installation of Split AC
HVAC - L9 - 3 Installation of Outdoor Units 20 14-Sep-22 06-Oct-22 Installation of Outdoor Units
Fire Works 53 10-Aug-22 10-Oct-22 10-Oct-22, Fire Works
1st Fix 40 10-Aug-22 24-Sep-22 24-Sep-22, 1st Fix

Actual Work Critical Remaining Work Summary Page 1 of 9 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
8 Story Residential Buidling Classic Schedule Layout 27-Jun-22 22:30
Activity ID Activity Name Duration Start Finish 2021 2022 2023
A S Oct N D J F M Apr M J Jul A S Oct N D Jan F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct N D
FIRE - L9 - 1 Marking & Fixing of Supports 20 10-Aug-22 01-Sep-22 Marking & Fixing of Supports
FIRE - L9 - 2 Installation of MS Pipes 20 02-Sep-22 24-Sep-22 Installation of MS Pipes
2nd Fix 23 14-Sep-22 10-Oct-22 10-Oct-22, 2nd Fix
FIRE - L9 - 3 Installation of Fire Hose Cabinets 20 14-Sep-22 06-Oct-22 Installation of Fire Hose Cabinets
FIRE - L9 - 4 Installation of Sprinklers 20 17-Sep-22 10-Oct-22 Installation of Sprinklers
Natural Gas Works 80 06-Jul-22 06-Oct-22 06-Oct-22, Natural Gas Works
1st Fix 50 06-Jul-22 01-Sep-22 01-Sep-22, 1st Fix
N.GAS - L9 - 1 Marking of Supports & Hangers 20 06-Jul-22 28-Jul-22 Marking of Supports & Hangers
N.GAS - L9 - 2 G.I Pipe Installation 20 10-Aug-22 01-Sep-22 G.I Pipe Installation
2nd Fix 20 14-Sep-22 06-Oct-22 06-Oct-22, 2nd Fix
N.GAS - L9 - 3 Gas Leak Detectors 20 14-Sep-22 06-Oct-22 Gas Leak Detectors
Level 8 141 24-Jun-22 05-Dec-22 05-Dec-22, Level 8
Civil Works 141 24-Jun-22 05-Dec-22 05-Dec-22, Civil Works
FINISH - L8 - 1 Block Masonry 20 24-Jun-22 16-Jul-22 Block Masonry
FINISH - L8 - 2 Plaster Works 20 24-Jun-22 16-Jul-22 Plaster Works
FINISH - L8 - 3 Bathroom Water Proofing 20 24-Jun-22 16-Jul-22 Bathroom Water Proofing
FINISH - L8 - 4 Bathroom Wall Tile 20 18-Jul-22 09-Aug-22 Bathroom Wall Tile
FINISH - L8 - 5 Bathroom Floor Tile 20 21-Jul-22 12-Aug-22 Bathroom Floor Tile
FINISH - L8 - 6 Dry Area Floor Tiles 20 10-Aug-22 01-Sep-22 Dry Area Floor Tiles
FINISH - L8 - 7 False Ceiling Suspensions 20 13-Aug-22 05-Sep-22 False Ceiling Suspensions
FINISH - L8 - 8 Wooden Door Installation 20 16-Aug-22 07-Sep-22 Wooden Door Installation
FINISH - L8 - 9 False Ceiling Sheet Fixing 20 06-Sep-22 28-Sep-22 False Ceiling Sheet Fixing
FINISH - L8 - 10 Lobby Floor Tiling 20 11-Oct-22 02-Nov-22 Lobby Floor Tiling
FINISH - L8 - 13 Balcony Tiles 20 03-Nov-22 25-Nov-22 Balcony Tiles
FINISH - L8 - 11 Lobby Ceiling 20 09-Nov-22 01-Dec-22 Lobby Ceiling
FINISH - L8 - 12 Paint Work Final Coat 20 11-Nov-22 03-Dec-22 Paint Work Final Coat
FINISH - L8 - 14 Installation of Mirrors 20 12-Nov-22 05-Dec-22 Installation of Mirrors
Electrical Works 136 27-Jun-22 01-Dec-22 01-Dec-22, Electrical Works
1st Fix 20 27-Jun-22 19-Jul-22 19-Jul-22, 1st Fix
ELECT - L8 - 1 Installation of Electrical Conduits and Back Boxes 20 27-Jun-22 19-Jul-22 Installation of Electrical Conduits and Back Boxes
2nd Fix 113 30-Jun-22 08-Nov-22 08-Nov-22, 2nd Fix
ELECT - L8 - 2 Wiring of Circuits and Point Wiring 20 30-Jun-22 22-Jul-22 Wiring of Circuits and Point Wiring
ELECT - L8 - 5 Installation of Power Cables 20 04-Jul-22 26-Jul-22 Installation of Power Cables
ELECT - L8 - 3 Fire Alarm Cabling 20 14-Sep-22 06-Oct-22 Fire Alarm Cabling
ELECT - L8 - 7 CCTV System Cabling 20 07-Oct-22 29-Oct-22 CCTV System Cabling
ELECT - L8 - 8 CATV Cabling 20 12-Oct-22 03-Nov-22 CATV Cabling
ELECT - L8 - 9 Video Intercom System Cabling 20 17-Oct-22 08-Nov-22 Video Intercom System Cabling
3rd Fix 130 04-Jul-22 01-Dec-22 01-Dec-22, 3rd Fix
ELECT - L8 - 4 Installation of Switches, Sockets 20 04-Jul-22 26-Jul-22 Installation of Switches, Sockets
ELECT - L8 - 6 Distribution Board & UPS Installation & Termination 20 18-Jul-22 09-Aug-22 Distribution Board & UPS Installation & Termination
ELECT - L8 - 10 Installation of Ceiling Mounted Lights Fixtures 20 09-Nov-22 01-Dec-22 Installation of Ceiling Mounted Lights Fixtures
Plumbing Works 65 18-Jul-22 30-Sep-22 30-Sep-22, Plumbing Works
1st Fix 20 18-Jul-22 09-Aug-22 09-Aug-22, 1st Fix
PLUMB - L8 - 1 Water Supply Piping 20 18-Jul-22 09-Aug-22 Water Supply Piping
PLUMB - L8 - 2 Testing of Pipe 20 18-Jul-22 09-Aug-22 Testing of Pipe
2nd Fix 20 08-Sep-22 30-Sep-22 30-Sep-22, 2nd Fix
PLUMB - L8 - 3 Installation of Fixtures 20 08-Sep-22 30-Sep-22 Installation of Fixtures
HVAC Works 67 21-Jul-22 06-Oct-22 06-Oct-22, HVAC Works
1st Fix 20 21-Jul-22 12-Aug-22 12-Aug-22, 1st Fix
HVAC - L8 - 1 Marking & Fixing of Supports 20 21-Jul-22 12-Aug-22 Marking & Fixing of Supports
2nd Fix 20 14-Sep-22 06-Oct-22 06-Oct-22, 2nd Fix

Actual Work Critical Remaining Work Summary Page 2 of 9 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
8 Story Residential Buidling Classic Schedule Layout 27-Jun-22 22:30
Activity ID Activity Name Duration Start Finish 2021 2022 2023
A S Oct N D J F M Apr M J Jul A S Oct N D Jan F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct N D
HVAC - L8 - 2 Installation of Split AC 20 14-Sep-22 06-Oct-22 Installation of Split AC
HVAC - L8 - 3 Installation of Outdoor Units 20 14-Sep-22 06-Oct-22 Installation of Outdoor Units
Fire Works 53 10-Aug-22 10-Oct-22 10-Oct-22, Fire Works
1st Fix 40 10-Aug-22 24-Sep-22 24-Sep-22, 1st Fix
FIRE - L8 - 1 Marking & Fixing of Supports 20 10-Aug-22 01-Sep-22 Marking & Fixing of Supports
FIRE - L8 - 2 Installation of MS Pipes 20 02-Sep-22 24-Sep-22 Installation of MS Pipes
2nd Fix 23 14-Sep-22 10-Oct-22 10-Oct-22, 2nd Fix
FIRE - L8 - 3 Installation of Fire Hose Cabinets 20 14-Sep-22 06-Oct-22 Installation of Fire Hose Cabinets
FIRE - L8 - 4 Installation of Sprinklers 20 17-Sep-22 10-Oct-22 Installation of Sprinklers
Natural Gas Works 67 21-Jul-22 06-Oct-22 06-Oct-22, Natural Gas Works
1st Fix 37 21-Jul-22 01-Sep-22 01-Sep-22, 1st Fix
N.GAS - L8 - 1 Marking of Supports & Hangers 20 21-Jul-22 12-Aug-22 Marking of Supports & Hangers
N.GAS - L8 - 2 G.I Pipe Installation 20 10-Aug-22 01-Sep-22 G.I Pipe Installation
2nd Fix 20 14-Sep-22 06-Oct-22 06-Oct-22, 2nd Fix
N.GAS - L8 - 3 Gas Leak Detectors 20 14-Sep-22 06-Oct-22 Gas Leak Detectors
Level 7 161 01-Jun-22 05-Dec-22 05-Dec-22, Level 7
Civil Works 161 01-Jun-22 05-Dec-22 05-Dec-22, Civil Works
FINISH - L7 - 1 Block Masonry 20 01-Jun-22 23-Jun-22 Block Masonry
FINISH - L7 - 2 Plaster Works 20 01-Jun-22 23-Jun-22 Plaster Works
FINISH - L7 - 3 Bathroom Water Proofing 20 01-Jun-22 23-Jun-22 Bathroom Water Proofing
FINISH - L7 - 4 Bathroom Wall Tile 20 18-Jul-22 09-Aug-22 Bathroom Wall Tile
FINISH - L7 - 5 Bathroom Floor Tile 20 21-Jul-22 12-Aug-22 Bathroom Floor Tile
FINISH - L7 - 6 Dry Area Floor Tiles 20 10-Aug-22 01-Sep-22 Dry Area Floor Tiles
FINISH - L7 - 7 False Ceiling Suspensions 20 13-Aug-22 05-Sep-22 False Ceiling Suspensions
FINISH - L7 - 8 Wooden Door Installation 20 16-Aug-22 07-Sep-22 Wooden Door Installation
FINISH - L7 - 9 False Ceiling Sheet Fixing 20 06-Sep-22 28-Sep-22 False Ceiling Sheet Fixing
FINISH - L7 - 10 Lobby Floor Tiling 20 11-Oct-22 02-Nov-22 Lobby Floor Tiling
FINISH - L7 - 13 Balcony Tiles 20 03-Nov-22 25-Nov-22 Balcony Tiles
FINISH - L7 - 11 Lobby Ceiling 20 09-Nov-22 01-Dec-22 Lobby Ceiling
FINISH - L7 - 12 Paint Work Final Coat 20 11-Nov-22 03-Dec-22 Paint Work Final Coat
FINISH - L7 - 14 Installation of Mirrors 20 12-Nov-22 05-Dec-22 Installation of Mirrors
Electrical Works 156 03-Jun-22 01-Dec-22 01-Dec-22, Electrical Works
1st Fix 20 03-Jun-22 25-Jun-22 25-Jun-22, 1st Fix
ELECT - L7 - 1 Installation of Electrical Conduits and Back Boxes 20 03-Jun-22 25-Jun-22 Installation of Electrical Conduits and Back Boxes
2nd Fix 133 07-Jun-22 08-Nov-22 08-Nov-22, 2nd Fix
ELECT - L7 - 2 Wiring of Circuits and Point Wiring 20 07-Jun-22 29-Jun-22 Wiring of Circuits and Point Wiring
ELECT - L7 - 5 Installation of Power Cables 20 10-Jun-22 02-Jul-22 Installation of Power Cables
ELECT - L7 - 3 Fire Alarm Cabling 20 14-Sep-22 06-Oct-22 Fire Alarm Cabling
ELECT - L7 - 7 CCTV System Cabling 20 07-Oct-22 29-Oct-22 CCTV System Cabling
ELECT - L7 - 8 CATV Cabling 20 12-Oct-22 03-Nov-22 CATV Cabling
ELECT - L7 - 9 Video Intercom System Cabling 20 17-Oct-22 08-Nov-22 Video Intercom System Cabling
3rd Fix 150 10-Jun-22 01-Dec-22 01-Dec-22, 3rd Fix
ELECT - L7 - 4 Installation of Switches, Sockets 20 10-Jun-22 02-Jul-22 Installation of Switches, Sockets
ELECT - L7 - 6 Distribution Board & UPS Installation & Termination 20 24-Jun-22 16-Jul-22 Distribution Board & UPS Installation & Termination
ELECT - L7 - 10 Installation of Ceiling Mounted Lights Fixtures 20 09-Nov-22 01-Dec-22 Installation of Ceiling Mounted Lights Fixtures
Plumbing Works 85 24-Jun-22 30-Sep-22 30-Sep-22, Plumbing Works
1st Fix 20 24-Jun-22 16-Jul-22 16-Jul-22, 1st Fix
PLUMB - L7 - 1 Water Supply Piping 20 24-Jun-22 16-Jul-22 Water Supply Piping
PLUMB - L7 - 2 Testing of Pipe 20 24-Jun-22 16-Jul-22 Testing of Pipe
2nd Fix 20 08-Sep-22 30-Sep-22 30-Sep-22, 2nd Fix
PLUMB - L7 - 3 Installation of Fixtures 20 08-Sep-22 30-Sep-22 Installation of Fixtures

Actual Work Critical Remaining Work Summary Page 3 of 9 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
8 Story Residential Buidling Classic Schedule Layout 27-Jun-22 22:30
Activity ID Activity Name Duration Start Finish 2021 2022 2023
A S Oct N D J F M Apr M J Jul A S Oct N D Jan F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct N D
HVAC Works 87 28-Jun-22 06-Oct-22 06-Oct-22, HVAC Works
1st Fix 20 28-Jun-22 20-Jul-22 20-Jul-22, 1st Fix
HVAC - L7 - 1 Marking & Fixing of Supports 20 28-Jun-22 20-Jul-22 Marking & Fixing of Supports
2nd Fix 20 14-Sep-22 06-Oct-22 06-Oct-22, 2nd Fix
HVAC - L7 - 2 Installation of Split AC 20 14-Sep-22 06-Oct-22 Installation of Split AC
HVAC - L7 - 3 Installation of Outdoor Units 20 14-Sep-22 06-Oct-22 Installation of Outdoor Units
Fire Works 53 10-Aug-22 10-Oct-22 10-Oct-22, Fire Works
1st Fix 40 10-Aug-22 24-Sep-22 24-Sep-22, 1st Fix
FIRE - L7 - 1 Marking & Fixing of Supports 20 10-Aug-22 01-Sep-22 Marking & Fixing of Supports
FIRE - L7 - 2 Installation of MS Pipes 20 02-Sep-22 24-Sep-22 Installation of MS Pipes
2nd Fix 23 14-Sep-22 10-Oct-22 10-Oct-22, 2nd Fix
FIRE - L7 - 3 Installation of Fire Hose Cabinets 20 14-Sep-22 06-Oct-22 Installation of Fire Hose Cabinets
FIRE - L7 - 4 Installation of Sprinklers 20 17-Sep-22 10-Oct-22 Installation of Sprinklers
Natural Gas Works 80 06-Jul-22 06-Oct-22 06-Oct-22, Natural Gas Works
1st Fix 50 06-Jul-22 01-Sep-22 01-Sep-22, 1st Fix
N.GAS - L7 - 1 Marking of Supports & Hangers 20 06-Jul-22 28-Jul-22 Marking of Supports & Hangers
N.GAS - L7 - 2 G.I Pipe Installation 20 10-Aug-22 01-Sep-22 G.I Pipe Installation
2nd Fix 20 14-Sep-22 06-Oct-22 06-Oct-22, 2nd Fix
N.GAS - L7 - 3 Gas Leak Detectors 20 14-Sep-22 06-Oct-22 Gas Leak Detectors
PHASE - 04 (Level 6 - Level 4) 161 24-Jun-22 28-Dec-22 28-Dec-22, PHASE - 04 (Level 6 - Level 4)
Level 6 161 24-Jun-22 28-Dec-22 28-Dec-22, Level 6
Level 5 141 18-Jul-22 28-Dec-22 28-Dec-22, Level 5
Civil Works 141 18-Jul-22 28-Dec-22 28-Dec-22, Civil Works
FINISH - L5 - 1 Block Masonry 20 18-Jul-22 09-Aug-22 Block Masonry
FINISH - L5 - 2 Plaster Works 20 18-Jul-22 09-Aug-22 Plaster Works
FINISH - L5 - 3 Bathroom Water Proofing 20 18-Jul-22 09-Aug-22 Bathroom Water Proofing
FINISH - L5 - 4 Bathroom Wall Tile 20 10-Aug-22 01-Sep-22 Bathroom Wall Tile
FINISH - L5 - 5 Bathroom Floor Tile 20 13-Aug-22 05-Sep-22 Bathroom Floor Tile
FINISH - L5 - 6 Dry Area Floor Tiles 20 02-Sep-22 24-Sep-22 Dry Area Floor Tiles
FINISH - L5 - 7 False Ceiling Suspensions 20 06-Sep-22 28-Sep-22 False Ceiling Suspensions
FINISH - L5 - 8 Wooden Door Installation 20 08-Sep-22 30-Sep-22 Wooden Door Installation
FINISH - L5 - 9 False Ceiling Sheet Fixing 20 29-Sep-22 21-Oct-22 False Ceiling Sheet Fixing
FINISH - L5 - 10 Lobby Floor Tiling 20 03-Nov-22 25-Nov-22 Lobby Floor Tiling
FINISH - L5 - 13 Balcony Tiles 20 26-Nov-22 19-Dec-22 Balcony Tiles
FINISH - L5 - 11 Lobby Ceiling 20 02-Dec-22 24-Dec-22 Lobby Ceiling
FINISH - L5 - 12 Paint Work Final Coat 20 05-Dec-22 27-Dec-22 Paint Work Final Coat
FINISH - L5 - 14 Installation of Mirrors 20 06-Dec-22 28-Dec-22 Installation of Mirrors
Electrical Works 136 20-Jul-22 24-Dec-22 24-Dec-22, Electrical Works
1st Fix 20 20-Jul-22 11-Aug-22 11-Aug-22, 1st Fix
ELECT - L5 - 1 Installation of Electrical Conduits and Back Boxes 20 20-Jul-22 11-Aug-22 Installation of Electrical Conduits and Back Boxes
2nd Fix 113 23-Jul-22 01-Dec-22 01-Dec-22, 2nd Fix
ELECT - L5 - 2 Wiring of Circuits and Point Wiring 20 23-Jul-22 15-Aug-22 Wiring of Circuits and Point Wiring
ELECT - L5 - 5 Installation of Power Cables 20 27-Jul-22 18-Aug-22 Installation of Power Cables
ELECT - L5 - 3 Fire Alarm Cabling 20 07-Oct-22 29-Oct-22 Fire Alarm Cabling
ELECT - L5 - 7 CCTV System Cabling 20 31-Oct-22 22-Nov-22 CCTV System Cabling
ELECT - L5 - 8 CATV Cabling 20 04-Nov-22 26-Nov-22 CATV Cabling
ELECT - L5 - 9 Video Intercom System Cabling 20 09-Nov-22 01-Dec-22 Video Intercom System Cabling
3rd Fix 130 27-Jul-22 24-Dec-22 24-Dec-22, 3rd Fix
ELECT - L5 - 4 Installation of Switches, Sockets 20 27-Jul-22 18-Aug-22 Installation of Switches, Sockets
ELECT - L5 - 6 Distribution Board & UPS Installation & Termination 20 10-Aug-22 01-Sep-22 Distribution Board & UPS Installation & Termination
ELECT - L5 - 10 Installation of Ceiling Mounted Lights Fixtures 20 02-Dec-22 24-Dec-22 Installation of Ceiling Mounted Lights Fixtures

Actual Work Critical Remaining Work Summary Page 4 of 9 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
8 Story Residential Buidling Classic Schedule Layout 27-Jun-22 22:30
Activity ID Activity Name Duration Start Finish 2021 2022 2023
A S Oct N D J F M Apr M J Jul A S Oct N D Jan F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct N D
Plumbing Works 65 10-Aug-22 24-Oct-22 24-Oct-22, Plumbing Works
1st Fix 20 10-Aug-22 01-Sep-22 01-Sep-22, 1st Fix
PLUMB - L5 - 1 Water Supply Piping 20 10-Aug-22 01-Sep-22 Water Supply Piping
PLUMB - L5 - 2 Testing of Pipe 20 10-Aug-22 01-Sep-22 Testing of Pipe
2nd Fix 20 01-Oct-22 24-Oct-22 24-Oct-22, 2nd Fix
PLUMB - L5 - 3 Installation of Fixtures 20 01-Oct-22 24-Oct-22 Installation of Fixtures
HVAC Works 67 13-Aug-22 29-Oct-22 29-Oct-22, HVAC Works
1st Fix 20 13-Aug-22 05-Sep-22 05-Sep-22, 1st Fix
HVAC - L5 - 1 Marking & Fixing of Supports 20 13-Aug-22 05-Sep-22 Marking & Fixing of Supports
2nd Fix 20 07-Oct-22 29-Oct-22 29-Oct-22, 2nd Fix
HVAC - L5 - 2 Installation of Split AC 20 07-Oct-22 29-Oct-22 Installation of Split AC
HVAC - L5 - 3 Installation of Outdoor Units 20 07-Oct-22 29-Oct-22 Installation of Outdoor Units
Fire Works 53 02-Sep-22 02-Nov-22 02-Nov-22, Fire Works
1st Fix 40 02-Sep-22 18-Oct-22 18-Oct-22, 1st Fix
FIRE - L5 - 1 Marking & Fixing of Supports 20 02-Sep-22 24-Sep-22 Marking & Fixing of Supports
FIRE - L5 - 2 Installation of MS Pipes 20 26-Sep-22 18-Oct-22 Installation of MS Pipes
2nd Fix 23 07-Oct-22 02-Nov-22 02-Nov-22, 2nd Fix
FIRE - L5 - 3 Installation of Fire Hose Cabinets 20 07-Oct-22 29-Oct-22 Installation of Fire Hose Cabinets
FIRE - L5 - 4 Installation of Sprinklers 20 11-Oct-22 02-Nov-22 Installation of Sprinklers
Natural Gas Works 67 13-Aug-22 29-Oct-22 29-Oct-22, Natural Gas Works
1st Fix 37 13-Aug-22 24-Sep-22 24-Sep-22, 1st Fix
N.GAS - L5 - 1 Marking of Supports & Hangers 20 13-Aug-22 05-Sep-22 Marking of Supports & Hangers
N.GAS - L5 - 2 G.I Pipe Installation 20 02-Sep-22 24-Sep-22 G.I Pipe Installation
2nd Fix 20 07-Oct-22 29-Oct-22 29-Oct-22, 2nd Fix
N.GAS - L5 - 3 Gas Leak Detectors 20 07-Oct-22 29-Oct-22 Gas Leak Detectors
Level 4 161 24-Jun-22 28-Dec-22 28-Dec-22, Level 4
Civil Works 161 24-Jun-22 28-Dec-22 28-Dec-22, Civil Works
FINISH - L4 - 1 Block Masonry 20 24-Jun-22 16-Jul-22 Block Masonry
FINISH - L4 - 2 Plaster Works 20 24-Jun-22 16-Jul-22 Plaster Works
FINISH - L4 - 3 Bathroom Water Proofing 20 24-Jun-22 16-Jul-22 Bathroom Water Proofing
FINISH - L4 - 4 Bathroom Wall Tile 20 10-Aug-22 01-Sep-22 Bathroom Wall Tile
FINISH - L4 - 5 Bathroom Floor Tile 20 13-Aug-22 05-Sep-22 Bathroom Floor Tile
FINISH - L4 - 6 Dry Area Floor Tiles 20 02-Sep-22 24-Sep-22 Dry Area Floor Tiles
FINISH - L4 - 7 False Ceiling Suspensions 20 06-Sep-22 28-Sep-22 False Ceiling Suspensions
FINISH - L4 - 8 Wooden Door Installation 20 08-Sep-22 30-Sep-22 Wooden Door Installation
FINISH - L4 - 9 False Ceiling Sheet Fixing 20 29-Sep-22 21-Oct-22 False Ceiling Sheet Fixing
FINISH - L4 - 10 Lobby Floor Tiling 20 03-Nov-22 25-Nov-22 Lobby Floor Tiling
FINISH - L4 - 13 Balcony Tiles 20 26-Nov-22 19-Dec-22 Balcony Tiles
FINISH - L4 - 11 Lobby Ceiling 20 02-Dec-22 24-Dec-22 Lobby Ceiling
FINISH - L4 - 12 Paint Work Final Coat 20 05-Dec-22 27-Dec-22 Paint Work Final Coat
FINISH - L4 - 14 Installation of Mirrors 20 06-Dec-22 28-Dec-22 Installation of Mirrors
Electrical Works 156 27-Jun-22 24-Dec-22 24-Dec-22, Electrical Works
1st Fix 20 27-Jun-22 19-Jul-22 19-Jul-22, 1st Fix
ELECT - L4 - 1 Installation of Electrical Conduits and Back Boxes 20 27-Jun-22 19-Jul-22 Installation of Electrical Conduits and Back Boxes
2nd Fix 133 30-Jun-22 01-Dec-22 01-Dec-22, 2nd Fix
ELECT - L4 - 2 Wiring of Circuits and Point Wiring 20 30-Jun-22 22-Jul-22 Wiring of Circuits and Point Wiring
ELECT - L4 - 5 Installation of Power Cables 20 04-Jul-22 26-Jul-22 Installation of Power Cables
ELECT - L4 - 3 Fire Alarm Cabling 20 07-Oct-22 29-Oct-22 Fire Alarm Cabling
ELECT - L4 - 7 CCTV System Cabling 20 31-Oct-22 22-Nov-22 CCTV System Cabling
ELECT - L4 - 8 CATV Cabling 20 04-Nov-22 26-Nov-22 CATV Cabling
ELECT - L4 - 9 Video Intercom System Cabling 20 09-Nov-22 01-Dec-22 Video Intercom System Cabling

Actual Work Critical Remaining Work Summary Page 5 of 9 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
8 Story Residential Buidling Classic Schedule Layout 27-Jun-22 22:30
Activity ID Activity Name Duration Start Finish 2021 2022 2023
A S Oct N D J F M Apr M J Jul A S Oct N D Jan F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct N D
3rd Fix 150 04-Jul-22 24-Dec-22 24-Dec-22, 3rd Fix
ELECT - L4 - 4 Installation of Switches, Sockets 20 04-Jul-22 26-Jul-22 Installation of Switches, Sockets
ELECT - L4 - 6 Distribution Board & UPS Installation & Termination 20 18-Jul-22 09-Aug-22 Distribution Board & UPS Installation & Termination
ELECT - L4 - 10 Installation of Ceiling Mounted Lights Fixtures 20 02-Dec-22 24-Dec-22 Installation of Ceiling Mounted Lights Fixtures
Plumbing Works 85 18-Jul-22 24-Oct-22 24-Oct-22, Plumbing Works
1st Fix 20 18-Jul-22 09-Aug-22 09-Aug-22, 1st Fix
PLUMB - L4 - 1 Water Supply Piping 20 18-Jul-22 09-Aug-22 Water Supply Piping
PLUMB - L4 - 2 Testing of Pipe 20 18-Jul-22 09-Aug-22 Testing of Pipe
2nd Fix 20 01-Oct-22 24-Oct-22 24-Oct-22, 2nd Fix
PLUMB - L4 - 3 Installation of Fixtures 20 01-Oct-22 24-Oct-22 Installation of Fixtures
HVAC Works 87 21-Jul-22 29-Oct-22 29-Oct-22, HVAC Works
1st Fix 20 21-Jul-22 12-Aug-22 12-Aug-22, 1st Fix
HVAC - L4 - 1 Marking & Fixing of Supports 20 21-Jul-22 12-Aug-22 Marking & Fixing of Supports
2nd Fix 20 07-Oct-22 29-Oct-22 29-Oct-22, 2nd Fix
HVAC - L4 - 2 Installation of Split AC 20 07-Oct-22 29-Oct-22 Installation of Split AC
HVAC - L4 - 3 Installation of Outdoor Units 20 07-Oct-22 29-Oct-22 Installation of Outdoor Units
Fire Works 53 02-Sep-22 02-Nov-22 02-Nov-22, Fire Works
1st Fix 40 02-Sep-22 18-Oct-22 18-Oct-22, 1st Fix
FIRE - L4 - 1 Marking & Fixing of Supports 20 02-Sep-22 24-Sep-22 Marking & Fixing of Supports
FIRE - L4 - 2 Installation of MS Pipes 20 26-Sep-22 18-Oct-22 Installation of MS Pipes
2nd Fix 23 07-Oct-22 02-Nov-22 02-Nov-22, 2nd Fix
FIRE - L4 - 3 Installation of Fire Hose Cabinets 20 07-Oct-22 29-Oct-22 Installation of Fire Hose Cabinets
FIRE - L4 - 4 Installation of Sprinklers 20 11-Oct-22 02-Nov-22 Installation of Sprinklers
Natural Gas Works 80 29-Jul-22 29-Oct-22 29-Oct-22, Natural Gas Works
1st Fix 50 29-Jul-22 24-Sep-22 24-Sep-22, 1st Fix
N.GAS - L4 - 1 Marking of Supports & Hangers 20 29-Jul-22 20-Aug-22 Marking of Supports & Hangers
N.GAS - L4 - 2 G.I Pipe Installation 20 02-Sep-22 24-Sep-22 G.I Pipe Installation
2nd Fix 20 07-Oct-22 29-Oct-22 29-Oct-22, 2nd Fix
N.GAS - L4 - 3 Gas Leak Detectors 20 07-Oct-22 29-Oct-22 Gas Leak Detectors
PHASE - 05 (Level 3 - Level 2) 161 18-Jul-22 20-Jan-23 20-Jan-23, PHASE - 05 (Level 3 - Level 2)
Level 3 161 18-Jul-22 20-Jan-23 20-Jan-23, Level 3
Civil Works 161 18-Jul-22 20-Jan-23 20-Jan-23, Civil Works
FINISH - L3 - 1 Block Masonry 20 18-Jul-22 09-Aug-22 Block Masonry
FINISH - L3 - 2 Plaster Works 20 18-Jul-22 09-Aug-22 Plaster Works
FINISH - L3 - 3 Bathroom Water Proofing 20 18-Jul-22 09-Aug-22 Bathroom Water Proofing
FINISH - L3 - 4 Bathroom Wall Tile 20 02-Sep-22 24-Sep-22 Bathroom Wall Tile
FINISH - L3 - 5 Bathroom Floor Tile 20 06-Sep-22 28-Sep-22 Bathroom Floor Tile
FINISH - L3 - 6 Dry Area Floor Tiles 20 26-Sep-22 18-Oct-22 Dry Area Floor Tiles
FINISH - L3 - 7 False Ceiling Suspensions 20 29-Sep-22 21-Oct-22 False Ceiling Suspensions
FINISH - L3 - 8 Wooden Door Installation 20 01-Oct-22 24-Oct-22 Wooden Door Installation
FINISH - L3 - 9 False Ceiling Sheet Fixing 20 22-Oct-22 14-Nov-22 False Ceiling Sheet Fixing
FINISH - L3 - 10 Lobby Floor Tiling 20 26-Nov-22 19-Dec-22 Lobby Floor Tiling
FINISH - L3 - 13 Balcony Tiles 20 20-Dec-22 11-Jan-23 Balcony Tiles
FINISH - L3 - 11 Lobby Ceiling 20 26-Dec-22 17-Jan-23 Lobby Ceiling
FINISH - L3 - 12 Paint Work Final Coat 20 28-Dec-22 19-Jan-23 Paint Work Final Coat
FINISH - L3 - 14 Installation of Mirrors 20 29-Dec-22 20-Jan-23 Installation of Mirrors
Electrical Works 156 20-Jul-22 17-Jan-23 17-Jan-23, Electrical Works
1st Fix 20 20-Jul-22 11-Aug-22 11-Aug-22, 1st Fix
ELECT - L3 - 1 Installation of Electrical Conduits and Back Boxes 20 20-Jul-22 11-Aug-22 Installation of Electrical Conduits and Back Boxes
2nd Fix 133 23-Jul-22 24-Dec-22 24-Dec-22, 2nd Fix
ELECT - L3 - 2 Wiring of Circuits and Point Wiring 20 23-Jul-22 15-Aug-22 Wiring of Circuits and Point Wiring

Actual Work Critical Remaining Work Summary Page 6 of 9 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
8 Story Residential Buidling Classic Schedule Layout 27-Jun-22 22:30
Activity ID Activity Name Duration Start Finish 2021 2022 2023
A S Oct N D J F M Apr M J Jul A S Oct N D Jan F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct N D
ELECT - L3 - 5 Installation of Power Cables 20 27-Jul-22 18-Aug-22 Installation of Power Cables
ELECT - L3 - 3 Fire Alarm Cabling 20 31-Oct-22 22-Nov-22 Fire Alarm Cabling
ELECT - L3 - 7 CCTV System Cabling 20 23-Nov-22 15-Dec-22 CCTV System Cabling
ELECT - L3 - 8 CATV Cabling 20 28-Nov-22 20-Dec-22 CATV Cabling
ELECT - L3 - 9 Video Intercom System Cabling 20 02-Dec-22 24-Dec-22 Video Intercom System Cabling
3rd Fix 150 27-Jul-22 17-Jan-23 17-Jan-23, 3rd Fix
ELECT - L3 - 4 Installation of Switches, Sockets 20 27-Jul-22 18-Aug-22 Installation of Switches, Sockets
ELECT - L3 - 6 Distribution Board & UPS Installation & Termination 20 10-Aug-22 01-Sep-22 Distribution Board & UPS Installation & Termination
ELECT - L3 - 10 Installation of Ceiling Mounted Lights Fixtures 20 26-Dec-22 17-Jan-23 Installation of Ceiling Mounted Lights Fixtures
Plumbing Works 85 10-Aug-22 16-Nov-22 16-Nov-22, Plumbing Works
1st Fix 20 10-Aug-22 01-Sep-22 01-Sep-22, 1st Fix
PLUMB - L3 - 1 Water Supply Piping 20 10-Aug-22 01-Sep-22 Water Supply Piping
PLUMB - L3 - 2 Testing of Pipe 20 10-Aug-22 01-Sep-22 Testing of Pipe
2nd Fix 20 25-Oct-22 16-Nov-22 16-Nov-22, 2nd Fix
PLUMB - L3 - 3 Installation of Fixtures 20 25-Oct-22 16-Nov-22 Installation of Fixtures
HVAC Works 87 13-Aug-22 22-Nov-22 22-Nov-22, HVAC Works
1st Fix 20 13-Aug-22 05-Sep-22 05-Sep-22, 1st Fix
HVAC - L3 - 1 Marking & Fixing of Supports 20 13-Aug-22 05-Sep-22 Marking & Fixing of Supports
2nd Fix 20 31-Oct-22 22-Nov-22 22-Nov-22, 2nd Fix
HVAC - L3 - 2 Installation of Split AC 20 31-Oct-22 22-Nov-22 Installation of Split AC
HVAC - L3 - 3 Installation of Outdoor Units 20 31-Oct-22 22-Nov-22 Installation of Outdoor Units
Fire Works 53 26-Sep-22 25-Nov-22 25-Nov-22, Fire Works
1st Fix 40 26-Sep-22 10-Nov-22 10-Nov-22, 1st Fix
FIRE - L3 - 1 Marking & Fixing of Supports 20 26-Sep-22 18-Oct-22 Marking & Fixing of Supports
FIRE - L3 - 2 Installation of MS Pipes 20 19-Oct-22 10-Nov-22 Installation of MS Pipes
2nd Fix 23 31-Oct-22 25-Nov-22 25-Nov-22, 2nd Fix
FIRE - L3 - 3 Installation of Fire Hose Cabinets 20 31-Oct-22 22-Nov-22 Installation of Fire Hose Cabinets
FIRE - L3 - 4 Installation of Sprinklers 20 03-Nov-22 25-Nov-22 Installation of Sprinklers
Natural Gas Works 80 22-Aug-22 22-Nov-22 22-Nov-22, Natural Gas Works
1st Fix 50 22-Aug-22 18-Oct-22 18-Oct-22, 1st Fix
N.GAS - L3 - 1 Marking of Supports & Hangers 20 22-Aug-22 13-Sep-22 Marking of Supports & Hangers
N.GAS - L3 - 2 G.I Pipe Installation 20 26-Sep-22 18-Oct-22 G.I Pipe Installation
2nd Fix 20 31-Oct-22 22-Nov-22 22-Nov-22, 2nd Fix
N.GAS - L3 - 3 Gas Leak Detectors 20 31-Oct-22 22-Nov-22 Gas Leak Detectors
Level 2 141 10-Aug-22 20-Jan-23 20-Jan-23, Level 2
Civil Works 141 10-Aug-22 20-Jan-23 20-Jan-23, Civil Works
FINISH - L2 - 1 Block Masonry 20 10-Aug-22 01-Sep-22 Block Masonry
FINISH - L2 - 2 Plaster Works 20 10-Aug-22 01-Sep-22 Plaster Works
FINISH - L2 - 3 Bathroom Water Proofing 20 10-Aug-22 01-Sep-22 Bathroom Water Proofing
FINISH - L2 - 4 Bathroom Wall Tile 20 02-Sep-22 24-Sep-22 Bathroom Wall Tile
FINISH - L2 - 5 Bathroom Floor Tile 20 06-Sep-22 28-Sep-22 Bathroom Floor Tile
FINISH - L2 - 6 Dry Area Floor Tiles 20 26-Sep-22 18-Oct-22 Dry Area Floor Tiles
FINISH - L2 - 7 False Ceiling Suspensions 20 29-Sep-22 21-Oct-22 False Ceiling Suspensions
FINISH - L2 - 8 Wooden Door Installation 20 01-Oct-22 24-Oct-22 Wooden Door Installation
FINISH - L2 - 9 False Ceiling Sheet Fixing 20 22-Oct-22 14-Nov-22 False Ceiling Sheet Fixing
FINISH - L2 - 10 Lobby Floor Tiling 20 26-Nov-22 19-Dec-22 Lobby Floor Tiling
FINISH - L2 - 13 Balcony Tiles 20 20-Dec-22 11-Jan-23 Balcony Tiles
FINISH - L2 - 11 Lobby Ceiling 20 26-Dec-22 17-Jan-23 Lobby Ceiling
FINISH - L2 - 12 Paint Work Final Coat 20 28-Dec-22 19-Jan-23 Paint Work Final Coat
FINISH - L2 - 14 Installation of Mirrors 20 29-Dec-22 20-Jan-23 Installation of Mirrors
Electrical Works 136 12-Aug-22 17-Jan-23 17-Jan-23, Electrical Works

Actual Work Critical Remaining Work Summary Page 7 of 9 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
8 Story Residential Buidling Classic Schedule Layout 27-Jun-22 22:30
Activity ID Activity Name Duration Start Finish 2021 2022 2023
A S Oct N D J F M Apr M J Jul A S Oct N D Jan F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct N D
1st Fix 20 12-Aug-22 03-Sep-22 03-Sep-22, 1st Fix
ELECT - L2 - 1 Installation of Electrical Conduits and Back Boxes 20 12-Aug-22 03-Sep-22 Installation of Electrical Conduits and Back Boxes
2nd Fix 113 16-Aug-22 24-Dec-22 24-Dec-22, 2nd Fix
ELECT - L2 - 2 Wiring of Circuits and Point Wiring 20 16-Aug-22 07-Sep-22 Wiring of Circuits and Point Wiring
ELECT - L2 - 5 Installation of Power Cables 20 19-Aug-22 10-Sep-22 Installation of Power Cables
ELECT - L2 - 3 Fire Alarm Cabling 20 31-Oct-22 22-Nov-22 Fire Alarm Cabling
ELECT - L2 - 7 CCTV System Cabling 20 23-Nov-22 15-Dec-22 CCTV System Cabling
ELECT - L2 - 8 CATV Cabling 20 28-Nov-22 20-Dec-22 CATV Cabling
ELECT - L2 - 9 Video Intercom System Cabling 20 02-Dec-22 24-Dec-22 Video Intercom System Cabling
3rd Fix 130 19-Aug-22 17-Jan-23 17-Jan-23, 3rd Fix
ELECT - L2 - 4 Installation of Switches, Sockets 20 19-Aug-22 10-Sep-22 Installation of Switches, Sockets
ELECT - L2 - 6 Distribution Board & UPS Installation & Termination 20 02-Sep-22 24-Sep-22 Distribution Board & UPS Installation & Termination
ELECT - L2 - 10 Installation of Ceiling Mounted Lights Fixtures 20 26-Dec-22 17-Jan-23 Installation of Ceiling Mounted Lights Fixtures
Plumbing Works 65 02-Sep-22 16-Nov-22 16-Nov-22, Plumbing Works
1st Fix 20 02-Sep-22 24-Sep-22 24-Sep-22, 1st Fix
PLUMB - L2 - 1 Water Supply Piping 20 02-Sep-22 24-Sep-22 Water Supply Piping
PLUMB - L2 - 2 Testing of Pipe 20 02-Sep-22 24-Sep-22 Testing of Pipe
2nd Fix 20 25-Oct-22 16-Nov-22 16-Nov-22, 2nd Fix
PLUMB - L2 - 3 Installation of Fixtures 20 25-Oct-22 16-Nov-22 Installation of Fixtures
HVAC Works 67 06-Sep-22 22-Nov-22 22-Nov-22, HVAC Works
1st Fix 20 06-Sep-22 28-Sep-22 28-Sep-22, 1st Fix
HVAC - L2 - 1 Marking & Fixing of Supports 20 06-Sep-22 28-Sep-22 Marking & Fixing of Supports
2nd Fix 20 31-Oct-22 22-Nov-22 22-Nov-22, 2nd Fix
HVAC - L2 - 2 Installation of Split AC 20 31-Oct-22 22-Nov-22 Installation of Split AC
HVAC - L2 - 3 Installation of Outdoor Units 20 31-Oct-22 22-Nov-22 Installation of Outdoor Units
Fire Works 53 26-Sep-22 25-Nov-22 25-Nov-22, Fire Works
1st Fix 40 26-Sep-22 10-Nov-22 10-Nov-22, 1st Fix
FIRE - L2 - 1 Marking & Fixing of Supports 20 26-Sep-22 18-Oct-22 Marking & Fixing of Supports
FIRE - L2 - 2 Installation of MS Pipes 20 19-Oct-22 10-Nov-22 Installation of MS Pipes
2nd Fix 23 31-Oct-22 25-Nov-22 25-Nov-22, 2nd Fix
FIRE - L2 - 3 Installation of Fire Hose Cabinets 20 31-Oct-22 22-Nov-22 Installation of Fire Hose Cabinets
FIRE - L2 - 4 Installation of Sprinklers 20 03-Nov-22 25-Nov-22 Installation of Sprinklers
Natural Gas Works 67 06-Sep-22 22-Nov-22 22-Nov-22, Natural Gas Works
1st Fix 37 06-Sep-22 18-Oct-22 18-Oct-22, 1st Fix
N.GAS - L2 - 1 Marking of Supports & Hangers 20 06-Sep-22 28-Sep-22 Marking of Supports & Hangers
N.GAS - L2 - 2 G.I Pipe Installation 20 26-Sep-22 18-Oct-22 G.I Pipe Installation
2nd Fix 20 31-Oct-22 22-Nov-22 22-Nov-22, 2nd Fix
N.GAS - L2 - 3 Gas Leak Detectors 20 31-Oct-22 22-Nov-22 Gas Leak Detectors
PHASE - 06 (Level 1 - Basement) 181 18-Jul-22 13-Feb-23 13-Feb-23, PHASE - 06 (Level 1 - Basement)
Level 1 161 18-Jul-22 20-Jan-23 20-Jan-23, Level 1
Basement 161 10-Aug-22 13-Feb-23 13-Feb-23, Basement
Facade Works - Curtain
Curta Wall 450 10-Aug-22 01-Feb-24
FACADE - L8 Aluminium Facade Work with Glazing - L8 90 10-Aug-22 22-Nov-22 Aluminium Facade Work with Glazing - L8
FACADE - L9 Aluminium Facade Work with Glazing - L9 90 10-Aug-22 22-Nov-22 Aluminium Facade Work with Glazing - L9
FACADE - L6 Aluminium Facade Work with Glazing - L6 90 23-Nov-22 07-Mar-23 Aluminium Facade Work with Glazing - L6
FACADE - L7 Aluminium Facade Work with Glazing - L7 90 23-Nov-22 07-Mar-23 Aluminium Facade Work with Glazing - L7
FACADE - L4 Aluminium Facade Work with Glazing - L4 90 08-Mar-23 26-Jun-23 Aluminium Facade Work w
FACADE - L5 Aluminium Facade Work with Glazing - L5 90 08-Mar-23 26-Jun-23 Aluminium Facade Work w
FACADE - L2 Aluminium Facade Work with Glazing - L2 90 27-Jun-23 18-Oct-23 Aluminium
FACADE - L3 Aluminium Facade Work with Glazing - L3 90 27-Jun-23 18-Oct-23 Aluminium
FACADE - L16 Aluminium Facade Work with Glazing - L1 90 19-Oct-23 01-Feb-24

Actual Work Critical Remaining Work Summary Page 8 of 9 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
8 Story Residential Buidling Classic Schedule Layout 27-Jun-22 22:30
Activity ID Activity Name Duration Start Finish 2021 2022 2023
A S Oct N D J F M Apr M J Jul A S Oct N D Jan F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct N D
FACADE - L17 Aluminium Facade Work with Glazing - GF 90 19-Oct-23 01-Feb-24
Project Closure & Hand Over 381 29-Oct-22 01-Feb-24

GEN-0004 Project Testing & Commissioning 90 29-Oct-22 11-Feb-23 Project Testing & Commissioning
GEN-0006 Snagging And Cleaning 60 23-Nov-23 01-Feb-24
GEN-0013 Project Completion 0 01-Feb-24
GEN-0007 Completion of Tower A 0 01-Feb-24

Actual Work Critical Remaining Work Summary Page 9 of 9 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation