Part B CONTRACT NO.

00000

MANPOWER LOADING CHART

Management and Engineering Consultancy Services for Design review and Site supervisions for reinforcement of
interconnection project between Egypt and Jordan by second circuit
Design Review / Site supervisions and Monitoring of Stations and 400KV Submarine & Land Cables
MONTH N O.
NO. OF
SL
CATEGORY MAN REMARKS
NO. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 MONTHS

CONSULTANT OFFICE - CAIRO, ARAB REPUBLIC OF EGYPT

1 Project Director 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24 Up to FAC

Design Project
Manager
2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24 Up to FAC
(S/S, OHTL &
Submarine Cable)
Senior Electrical
Engineer (S/S,
3 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
OHTL & Submarine
Cable)
Electrical Engineer
4 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
(S/S)

Electrical Engineer
5 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
(Submarine Cable)

Senior
Civil/Structural
6 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
Engineer (S/S &
submarine cable)
Civil/Structural
7 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
Engineer (S/S)
Civil/Structural
8 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
Engineer (OHTL)
Senior Building
9 Services Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
(S/S)
Building Services
10 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
Engineer (S/S)

Senior Protection
11 1 1 1 1 1 1 1 1 1 1 1 1 1 1 14
Engineer

12 Protection Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 14

Senior
13 Communication 1 1 1 1 1 1 1 1 1 1 1 1 1 1 14
Engineer
Communication
14 1 1 1 1 1 1 1 1 1 1 1 1 1 1 14
Engineer

Senior Geotechnical
15 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 21
Engineer

16 Quantity Surveyor 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 19

Planning &
17 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 22
Scheduling Engineer

19 CAD Operator 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24 Up to FAC

Secretary/
20 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24 Up to FAC
Engineering Aide

TOTAL 5 6 6 7 7 15 15 15 19 19 19 19 19 19 19 19 19 19 19 19 19 19 4 4 350

Page 1 of 2
Part B CONTRACT NO.00000

MANPOWER LOADING CHART

Management and Engineering Consultancy Services for Design review and Site supervisions for reinforcement of
interconnection project between Egypt and Jordan by second circuit
Design Review / Site supervisions and Monitoring of Stations and 400KV Submarine & Land Cables
MONTH N O.
NO. OF
SL
CATEGORY MAN REMARKS
NO. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 MONTHS

CONSULTANT OFFICE - CAIRO, ARAB REPUBLIC OF EGYPT


CONSULTANT OFFICE - OMAN, THE HASHEMITE KINGDOM OF JORDAN

Project Manager
21 (S/S, OHTL & 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24 Up to FAC
Submarine Cable)

Electrical Engineer
22 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
(S/S)

Electrical Engineer
23 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
( Submarine Cable)

Civil/Structural
24 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
Engineer (S/S)

Mechanical
26 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17
Engineer (S/S)

Senior Protection
1 1 1 1 1 1 1 1 1 1 1 1 1 1 14
Engineer

27 Protection Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 14

Senior
Communication 1 1 1 1 1 1 1 1 1 1 1 1 1 1 14
Engineer
Communication
28 1 1 1 1 1 1 1 1 1 1 1 1 1 1 14
Engineer

Quantity Surveyor 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 19

31 CAD Operator 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24 Up to FAC

Secretary/
32 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24 Up to FAC
Engineering Aide

TOTAL 3 3 3 4 4 8 8 8 12 12 12 12 12 12 12 12 12 12 12 12 12 12 3 3 215

565

Note: 1. Manpower loading chart for CONSULTANT Main Office in CAIRO, ARAB REPUBLIC OF
EGYPT and Secondary Office in OMAN, THE HASHEMITE KINGDOM OF JORDAN.
2. Manpower with high degree of specialization in Transition Stations, HVDC/HVAC
Submarine and Land Cables, QA/QC, Safety
Environment and Risk Assessment shall performed their responsibilities at
CONSULTANT Home Office except for technical meetings to be held at
STEERING COMMITTEE Head Offices or at Project Site under CONSULTANT CONTRACT
in consultation with STEERING COMMITTEE.

3. The Number of Manpower are estimated based on PROJECTS requirements and this
might increase at any stage of the PROJECTS duration.

Part "B"

Page 2 of 2