Professional Documents
Culture Documents
ARC Flash KPI Compliance at A Large Oil and Gas Company
ARC Flash KPI Compliance at A Large Oil and Gas Company
ARC Flash KPI Compliance at A Large Oil and Gas Company
0093-9994 © 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission.
See http://www.ieee.org/publications standards/publications/rights/index.html for more information.
Authorized licensed use limited to: Institut Teknologi Sepuluh Nopember. Downloaded on December 09,2021 at 19:30:54 UTC from IEEE Xplore. Restrictions apply.
890 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 54, NO. 1, JANUARY/FEBRUARY 2018
Authorized licensed use limited to: Institut Teknologi Sepuluh Nopember. Downloaded on December 09,2021 at 19:30:54 UTC from IEEE Xplore. Restrictions apply.
PRAGALE et al.: ARC FLASH KPI COMPLIANCE AT A LARGE OIL AND GAS COMPANY 891
Authorized licensed use limited to: Institut Teknologi Sepuluh Nopember. Downloaded on December 09,2021 at 19:30:54 UTC from IEEE Xplore. Restrictions apply.
892 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 54, NO. 1, JANUARY/FEBRUARY 2018
B. Administrative Controls
1) Training and Certification—Includes But Is Not Limited
to Electrical Hazard Recognition (EHR): All ESOs and tech-
nicians are required to successfully complete the course. It is
required to perform any work on electrical equipment operated Fig. 8. Arc flash analysis KPI.
at more than 240 V.
a) Hazardous-duty potential testing (HDPT): Company power systems software, and arc flash analysis of the existing
technicians as well as those who receive or release work clear- power system. The second phase involved arc flash mitigation
ances, test for potentials, and/or apply/remove grounds on elec- of locations with incident energy greater than 40 calories/cm2 ,
trical equipment rated at or above 1000 V must successfully equipment labeling, and personnel training. All arc-flash hazard
complete the HDPT requirements. analyses was performed in association with or as a continua-
b) Corporate ESO certification/recertification (CESOR): tion of the short-circuit study and protective-device coordination
all ESOs are required to complete the course—pass a written study [4]. More than 40 arc flash studies have been conducted
exam and complete the field assessment requirements. A CE- so far for various company facilities. It was observed that a sig-
SOR certificate is required to perform hazardous-duty switch- nificant number of the dangerous locations are at the line side
ing, including circuit breaker insertion/removal, in all company of low voltage switchgear, i.e., main circuit breaker cubicle.
facilities. This is not surprising knowing that the arcing fault at this
For initial certification, the candidates attend instructor-led location will be cleared by the upstream protective relay at
courses that last anywhere from one day to several weeks. Per- the high side of distribution transformer. Currently, company
sonnel re-certification is required every three years and is typi- compliance is at 70.4% (refer to Fig. 8); however, several large
cally completed via online course. facilities are nearing arc flash analysis completion that will bring
2) Operation and Maintenance Delineation: The objective compliance to over 90%.
was to define clear and consistent roles and responsibilities be-
tween a facility’s maintenance and operation units and the com-
pany’s Power Systems Operations Department (e.g., equipment III. ARC FLASH COMPLIANCE ASSESSMENT PROGRAM
ownership, switching operations, maintenance responsibilities, The arc flash KPI compliance assessment program consists
etc.). The responsibility for power systems operation and main- of field-based internal assessments conducted by a team com-
tenance are outlined in a separate company GI. The company prised of safety professionals, field compliance and electrical
achieved 100% compliance as of 2012. power systems engineers—all under the Power Systems En-
3) Unified Procedures—Operation and Maintenance: The gineering Department. The compliance program consists of
objective was to unify the electrical operation and maintenance field-based assessments through a combination of on-site ob-
procedures to best in class practices at all company facilities. servations, interviews/discussions with facility engineers, ESOs
These procedures include electrical switching and isolation, en- and technicians, as well as reviewing existing documentation.
ergizing new equipment, minimum requirements for electrical The assessment team has highlighted positive aspects of exist-
equipment maintenance, etc. The new unified procedures re- ing arc flash KPI compliance, as well as identifying areas of
placed all existing fragmented operation and maintenance pro- opportunity for improvement.
cedures and were integrated into each facility’s operating in-
structions. The company achieved 100% compliance as of 2015.
A. Assessment Methodology
4) Arc Flash Analysis: The arc flash analysis is the foun-
dation of the arc flash mitigation program at every company The assessments are designed to validate the proponent’s
facility; a company best practice procedure was developed to stated compliance to the Arc Flash KPIs as well as to identify
guide engineers on how to perform or review arc flash hazard any high-level opportunities for improvement in application of
analysis using commercially available power system analysis arc flash mitigation efforts at every substation assessed.
and design software [3]. The assessors used a standardized assessment checklist (see
The facility arc flash studies were implemented in two phases. pre-assessment checklist in Table II). The checklist questions
The first phase was data gathering (field work), modeling in are weighted and scored. By using this standardized checklist,
Authorized licensed use limited to: Institut Teknologi Sepuluh Nopember. Downloaded on December 09,2021 at 19:30:54 UTC from IEEE Xplore. Restrictions apply.
PRAGALE et al.: ARC FLASH KPI COMPLIANCE AT A LARGE OIL AND GAS COMPANY 893
TABLE II TABLE IV
PREASSESSMENT TASKS CHECKLIST ARC FLASH ANALYSIS COMPLIANCE ASSESSMENT CHECKLIST
TABLE III
COMPLETED ASSESSMENTS
should consider revising the power system configuration
(e.g., tie-breaker close to tie-breaker open for double-
Date Facility Type No. of Substations
ended switchgear, use of current-limiting reactors, etc.) to
11-2014 Power Systems 26
03-2015 GOSP 6 reduce the available fault current. Company facilities also
04-2015 Refinery 24 need to determine an appropriate arc flash mitigation strat-
09-2015 Bulk Plant, Storage 4 egy for equipment locations that exceed 40 calories/cm2 .
10-2015 Gas Plant 23
11-2015 Community 12 The team highlights the following challenges.
Oil Processing 17 1) Transition of the arc flash electrical safe operations pro-
01-2016 Power Systems 2 gram from the task method to analysis method: This will
Refinery 51
02-2016 Gas Plant 23 be the most challenging in terms of ESO and technician
03-2016 Oil Processing 52 re-training requirements and program implementation
NGL Plant 10 2) Alignment of the arc flash analysis KPI to the assessment
04-2016 Refinery 24
Gas Plant 28 requirements (refer to checklist in Table IV): The assess-
Oil Terminal 10 ment requirements are more stringent than the arc flash
05-2016 NGL Plant 28 analysis KPIs. The assessment involves extensive review
Total 340 of the arc flash analysis results and requires each facility
to act on the analysis recommendations.
assessors are able to validate and measure arc flash KPI com-
IV. FUTURE WORK
pliance at all company substations in a consistent manner.
By first Quarter 2016, the team has assessed 250 substations.
B. Facilities Selected for Assessment By the end of 2016, the team plans to assess all company substa-
tions. The assessment team recommends phasing out several of
The arc flash compliance assessment team visited the follow- the arc flash KPI metrics (e.g., operation and maintenance delin-
ing facilities between late 2014 and early 2016: eation and unified operation and maintenance procedures) where
100% compliance (or near 100%) has been achieved. The objec-
C. Findings, Recommendations, and Program Challenges tive is continuous improvement; therefore, the company needs
The arc flash compliance assessment team reports that the to measure a different metric that can create positive value.
surveyed facility’s arc flash KPI compliances are generally in
line with the self-reported percentages. The team highlights the
V. CONCLUSION
following assessment findings and recommendations.
1) Technology Deployment: The corporate KPI compliance General findings from the completed assessments suggest
will continue to rise towards the 100% target as each there are generally positive measures taking place at assessed
facility ensure RRDs are utilized where possible. RRD locations to ensure arc flash mitigation; however, there are also
suppliers can assist in ensuring units are commissioned as many areas of opportunities for improvement. A major challenge
well as training on proper use of the RRDs. will be the transition away from the arc flash task (or table)
2) Training and Certification: New employees and attrition; method to the analysis method. Implementation of this new
training and mentorship program to transfer knowledge strategy will be facilitated as the company’s compliance to the
from experienced ESOs and technicians to new (younger) arc flash analysis KPI nears 100%.
employees.
3) Arc Flash Analysis: The short-circuit study, performed as
part of the arc flash analysis, has revealed several overdu- ACKNOWLEDGMENT
tied equipment (i.e., calculated available fault current ex- The authors express their gratitude to Mr. A. Al-Omair and
ceeds the equipment rating). Overdutied equipment must Mr. M. B. Al-Zuabi for their contributions in developing this
be replaced with properly rated equipment or each facility paper.
Authorized licensed use limited to: Institut Teknologi Sepuluh Nopember. Downloaded on December 09,2021 at 19:30:54 UTC from IEEE Xplore. Restrictions apply.
894 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 54, NO. 1, JANUARY/FEBRUARY 2018
Authorized licensed use limited to: Institut Teknologi Sepuluh Nopember. Downloaded on December 09,2021 at 19:30:54 UTC from IEEE Xplore. Restrictions apply.