CHATTOGRAM
SHIP REPAIR DEPARTMENT
Electric shore supply to be arranged 24 hrs a day till undocking with 440v, 50Hz,
AC supply of 3 phase characteristics.
SERIAL REMARKS
NO. DESCRIPTION OF REPAIRS BY HEAD
OFFICE
Following valves to be overhauled, inspected, and fitted back after survey with
required packing, paints, and joints etc.
E/R STBD SEA CHEST VALVES:
a) Main sea suc. v/v before filter (B’fly) - 250 mm - 01 no.
b) Main sea suc v/v after filter (B’fly) - 250 mm - 01 no.
Port Sea Chest Valves
Both propellers shafts to be withdrawn/ fitted back. Aft and fwd simplex compact
stern tube seals to be checked, liner and stuffing boxes condition to be specially
examined, if require to be renewed by owner supply spares. Stern tube bearings
wear down to be measured.
Following repairs to be carried out under the guidance of expert with both
rudders:
a) Necessary clearences to be measured.
b) Bushes, links, bolt of link system to be checked and renewed. Slide
piece and link bolt alignment to be checked and repaired.
c) Tail fin supporting bushes (top, middle and bottom) and supports to be
checked and renewed.
d) Rudder hinge bushes to be checked and renewed.
e) Both the rudder to be gauged repaired and pressure tested in presence
of surveyor and ship staff.
f) Balancing of port rudder to be checked & necessary repair to be
carried out as per Class requirement.