Professional Documents
Culture Documents
Fdocuments - in I 15 Reconstruction Project Innovative Foundation and Bartlettgeofoampresentation
Fdocuments - in I 15 Reconstruction Project Innovative Foundation and Bartlettgeofoampresentation
Fdocuments - in I 15 Reconstruction Project Innovative Foundation and Bartlettgeofoampresentation
Embankment Construction
• Large
g Primary
y Consolidation Settlement ((1 to 1.5 m))
• Time Rate of Consolidation (2 years to end of primary)
• Creep Settlement (Bump at Bridge)
• Foundation Stability (Large Embankments on Soft Soils)
• Schedule Constraints (two 2-year projects)
• Maintenance of Traffic (Had to be maintained)
•New Technologies and Development of Specifications
Selected Topics
Surcharging
PV Drains
Alluvium
5
10 Bonneville Clay
h (m)
15
Primary Settlement
Pleistocene Alluvium
Depth
20
25
Cutler Clay
y
30
35 Secondary Settlement
40
Settlement of Soft Clays in Salt Lake Valley
Primary Settlement
Secondary Settlement
15
D e p th (m )
15
20
Depth (m)
20 25
30
25
35
30
40
35
40
Typical I-15 Embankment Construction
Existing
embankment
Alluvium
Pleistocene
Sands and Gravels
Prefabricated Vertical Drains
Installed drain
Cost:
Remove Surcharge
SV Rate of Secondary
Settlement w/ Surcharge
C
C’
Amount of Surcharge
Surcharging Summary
Geotextile p
placement on sloped,
p ,
pre-existing embankment
Horizontal 3 8 - 7.6
3.8 76 7 6 - 25.0
7.6 25 0 > 25.0
25 0
Displacement
Rate (mm/day)
Displacement
p 0.2 - 0.3 0.3 – 0.4 > 0.4
Ratio (DR)
70
DR = horz.
horz Displacement
/ vert. settlement 60
Vertical inclinometers 40
Settlement plates
1
20
10 DR
Survey Points
Embankment Fill
Horizontal Inclinometers
Reference Bench Mark
Magnet-Reed
g Extensiometer
Vertical Inclinometers
Objectives of MSE Wall Arrays
1. Monitor Stress and Strains
within Wall and Foundation
2. Determine Settlement
Distribution Away from
W ll
Wall
4. Deformation Modeling
Strain Gauges on Welded-Wire Reinforcing
Reading of Sondex
IInclinometer
li t and
d Sondex
S d Extensometer
Locations
3500 S. MSE Wall Deformations
MSE Wall Summary
1. Large primary consolidation settlement req’d use of
two stage MSE wall with flexible wire face.
2. Flexible faces can deform during construction and
post-construction.
3. Increasing the horizontal reinforcement in the bottom
half of the wall can reduce the deformation, but not
completely
p y eliminate it ((horzizontal buldge
g reduce by
ya
factor of 2.)
4. Material type, compaction and construction
procedures can also help in reducing face deformation.
5. Specifications should be written to control allowable
face deformation.
6. Zone of settlement influence is 1.5 times wall height.
Geofoam Embankment For Settlement
Reduction
Buried
Utilities
35 cm Concrete Pavement
60 cm Base Material
Tilt-up 15 cm Reinforced Concrete
Concrete Load Distribution Slab
Fascia
Panel Wall
Geofoam Block
Wall
Footing
Bedding Sand (20 cm min.)
Geofoam Properties
* I-15 used 1.25 pcf density exclusively (i.e., type VIII geofoam)
Geofoam Embankment
Geofoam cut
and placed
around piling
at bridge
abutment
Reinforced Concrete
Load Distribution Slab
atop Geofoam
Geofoam (Finished Cross Section)
Geofoam for Rapid Construction
C
Comparison
i off Construction
C t ti Times Ti
35
Consstruction Time (Weeeks)
Conventional
30
Geofoam
25
20
15
10
0
Preparation Construction Settlement Finish Work Total
Geofoam Wall Costs
Geofoam wall system (total cost) is about 2 ¼ times more expensive than
conventional 2-Stage MSE wall with PV drains
3300 South Geofoam Array
ROW OF SURVEY POINTS AT FACE OF WALL
25 MM - PVC STAND PIPE
ROW OF SURVEY POINTS ALONG INSIDE EDGE OF MOMENT SLAB
ROW OF SURVEY POINTS ALONG OUTSIDE EDGE OF EMERGENCY LAN
CONCRETE PAVEMENT
ROAD BASE
LOAD DISTRIBUTION SLAB
6.5 TO 7.3 m
GEOFOAM BLOCKS
LEVEL 2
GRANULAR BACKFILL
LEVEL 0
Pressure Cell Cast in Bridge Abutment First Method of Placing Pressure Cell
Improved Method of Placing Pressure Cell
03/21/99
05/20/99
07/19/99
09/17/99
11/16/99
01/15/00
03/15/00
05/14/00
07/13/00
09/11/00
11/10/00
01/09/01
03/10/01
05/09/01
07/08/01
09/06/01
0
10
20
ement (mm)
30
40 LEVEL 6
50
LEVEL 4
Settle
60
LEVEL 2
70
LEVEL 0
80
90
100
Construction Completed (7/28/99) 1% Construction Strain
Level 0
Level 2
Level 4
Level 6
Level 8
Level 9
Load Distribution Slab placed
Load Distribution Slab Curb placed
Granular Borrow
Open Graded Base
100 South Magnet Extensometer Data
Post-Construction Settlement
1% construction strain
2% total in 50 yrs
yrs.
3300 South Geofoam Array
Damage
g to Connections Duringg Construction
Loading
Damaged Connection
• Approximately 1%
loading strain can be
expected.
• Strain due to seating
g of
untrimmed block and
elastic compression.
• Damaged connection
was later repaired by
dowels.
• Rigid
Ri id connectt should
h ld bbe
avoided.
Geofoam Transition Zones
Post-Construction Settlement
Transition slope
3.5 H : 1 V
face of wall
Transition zone 5/30/00
face of wall
ent
25.0 3/18/01
me
Post-Constrruction Settlem
inside edge of
20.0 moment slab
5/30/00
15.0 inside edge of
(mm)
moment slab
3/18/01
10 0
10.0 outside edge
of emergency
lane 5/30/00
5.0 outside edge
of emergency
0.0 lane 3/18/01
340
350
360
370
380
390
400
410
420
430
440
450
460
470
480
490
2534
2535
2536
2537
2538
2539
2540
2542
2543
2544
2545
2546
2547
2548
2549
254
baseline survey
Mainline Stationing (m) completed on 11/10/99.
Geofoam Pressure Cell Measurements
Pressure Versus Time
3300 South Street Geofoam Array
50.0 LEVEL 6
40.0 LEVEL 4
30 0
30.0
LEVEL 2
20.0
LEVEL 0
10.0
00
0.0
1/20/99
3/21/99
5/20/99
7/19/99
9/17/99
11/16/99
1/15/00
3/15/00
5/14/00
7/13/00
9/11/00
11/10/00
1/9/01
3/10/01
5/9/01
7/8/01
9/6/01
11/5/01
Date
Geofoam Conclusions
6. Creep strain will be relatively small for dead loads that are less
than 50 percent of the compressive strength.
7. Creep strain in a 10 year post-construction period is expected to be
0.25 to 0.3 percent (18 to 21 mm).
8. Transition zones with the MSE wall need to be designed carefully
to minimize differential settlement in the transition zone
Lime Cement Stabilized Soil
Lime Cement Column Rig 125 kg/m3 15% lime 85% cement
M = 30 Mpa (design); Su 300 to 400 kPa
Lime Cement Treatment Area
Lime Cement Column Installation Pattern
Lime Cement Column Installation X-Section
1-Stage MSE Wall Construction
14
12
10 Fill 2
8
6
4
2 Fill 1
0
PC1 (off
200 column)
300
PC2 (on
400 column)
500
600
Inclinometer Measurements at LCC Array
Meters into Embankment (Inc 302)
Date
0 5 10 15 20 25 30 35 40 10/10/98
0 10/22/98
10 11/16/98
20 11/23/98
30 12/1/98
12/8/98
40
12/16/98
50
12/30/98
60 1/22/99
70
S ettlem ent (m m )
2/25/99
80 3/26/99
90 5/3/99
100 5/27/99
110 7/8/99
120 8/16/99
9/15/99
130
11/2/99
140
12/29/99
150 2/3/00
160 6/1/00
170 6/8/2000
180 10/3/00
190 3/22/01
Wall face
Ground Settlements at LCC Array
(July 98 to November 01)
Ftg 1
0
Ftg 2
20 Inc 1
40 Inc 2
mm)
60 LC1
Settlement (m
80 LC2
100 LC3
120 LC4
LC5
140
LC6
160
LC7
180 Wall LC8
200
face
-10
10 LC9
LC10
0 LC11
LC12
mm)
10 LC13
Settlement (m
LC14
20 LC15
LC16
30
LC17
LC18
40
LC19
S b
S. building
ildi LC20
50
LC21
60
Magnetic Extensometer Measurement
Max. = 4 cm
LCC Construction Performance
1. Primary Consolidation Settlement was reduced from about 1.0m
to 0.2 m at LCC array.
2. Construction Settlement of about 18 cm occurred at MSE wall
face.
3
3. Construction Settlement of about 3 to 4 cm occurred at nearby
bldg.
4. Lateral Displacement of about 4 cm occurred at wall face.
5. Column is carrying about 10 times the stress as the adjacent
untreated ground.
6
6. IInstallation
t ll ti rates
t and d costt became
b an iissue with
ith Wasatch
W t h
Constructors and this technology was only used at one location.
Long-Term Array Locations
Location Type
I 80 @ 300 W
I-80 W. MSE WWall
ll on Lime
Li Cement
C t Columns
C l
I-15 @ 3300 S. Geofoam Wall (Creep & Load)
I-15 @ 3500 S. MSE Wall (Deformation & Settlement)
I 15 @ 200 S
I-15 S. MSE WWall
ll (S
(Settlement)
ttl t)
I-15 @ S. Univ. Embankment (Settlement)
I-80 @ W. Temple MSE Wall (Lt. Weight Backfill)
I-15 @ 800 S. Geofoam (Lateral Earth Pressure)
I-15 @ 100 S. Geofoam (Differential Icing)
I-15 @ 2100 S. Embankment (Settlement)
I-15 @ 400 S. Embankment (Settlement)
Questions
Bartlett@civil.utah.edu