Ref no: Qtn\Q-29774

April 1, 2022

GENERAL MILLING CORP.


Lapu-Lapu City

Attention : Engr. Maria Claire Teffanie Mabugnon

Dear Ma'am:

We are pleased to offer you the following:

1) 1 lot Restoration of ERICO Lightning Protection in GMC Basketball P 70,175.00 / lot


Court mounted in a Lamp Post that includes replacement
of damaged 3m Lower Mast, mounting of FRP Mast and the
ERICO Dynasphere Lightning Arrester

2) 1 lot Restoration of ERICO Lightning Protection in GMC Power


House mounted above the rooftop that includes the following:
I. MATERIALS
1 pc - FRP Mast (Fiberglass Reenforced Plastic) 22,000.00 22,000.00
2 pcs - Upper Termination Kit 32,000.00 64,000.00
1 pc - Lower Termination Kit 4,000.00 4,000.00
1 pc - New Stainless Termination Box 7,600.00 7,600.00
1 lgth - 17m Lower Steel Mast
20 mtrs - ERICORE Downconductor 2,700.00 54,000.00
1 pc - Inline Couplling 15,000.00 15,000.00
Materials - Total P 166,600.00

II) LABOR for the restoration of Lightning Protection that includes: 275,000.00 / lot
- Pull out and replace damaged 17m Lower Pole Mast
- Pull out and replace damaged 2m FRP Mast
- Pull out and replace 20m damaged Ericore Downconductor.
- Terminate the new cable to the undamaged Erico Interceptor.
- Interconnect the new cable using stainless termination/busbar box
and upper/lower termination kits.

COMPLETION : One(1) week after receipt of P.O.

TERMS : Thirty (30) days

Very truly yours,

JUN S. TINAMISAN