Project Name : New Plant AHM Deltamas Cikarang Loca

September
Minggu 2 Minggu
NO DESCRIPTION
mon tue wed thu fri sat sun mon tue wed
12 13 14 15 16 17 18 19 20 21

1 BOBOK TIANG PANCANG AS 17-21/P1-Z

2 As P1 / 17-21

3 As J1 / 17-21

4 As Z / 17-21

5 As O1 / 17-21

6 As M1 / 17-21

7 As N1 / 17-21

8 As L1 / 17-21

9 As K1 / 17-21

10 As J1 / 17-21

11 As I1 / 17-21

12 As H1 / 17-21

13 As G1 / 17-21

14 As P1 / 17-21

15 As E1 / 17-21

16 As D1 / 17-21

17 As C1 / 17-21

18 As B1 / 17-21

19 As A1 / 17-21

20 COR LC 17-21 / P1-Z

21 PAS. BEKISTING PILECAP AS P1/17

22 PAS. BEKISTING PILECAP AS P1/18

23 PAS. BEKISTING PILECAP AS P1/19

24 PAS. BEKISTING PILECAP AS P1/20

25 PAS. BEKISTING PILECAP AS P1/21

26 PAS. BESI PILECAP, TIE BEAM AS P1/17

27 PAS. BESI PILECAP, TIE BEAM AS P1/18

28 PAS. BESI PILECAP, TIE BEAM AS P1/19


29 PAS. BESI PILECAP, TIE BEAM AS P1/20

30 PAS. BESI PILECAP, TIE BEAM AS P1/21

31 COR PILE CAP AS 17-21 / Z,P1,J1

32 PARIMETER UNTUK ERCTION BAJA(14 HR)


Location : Plant Assembling

September Oktober
Minggu 3 Minggu 4 Minggu 5 Min
thu fri sat sun mon tue wed thu fri mon tue wed thu fri sat sun mon tue wed thu fri
22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12
Oktober
Minggu 6
sat sun mon tue wed thu thu tue wed thu thu fri
13 14 15 16 17 18 19 20 21 22 23 12

E
R
E
C
T
I
O
N

B
A
J
A